PROCUREMENT PLAN (Textual Part) Project information: Greater Accra Resilient Integrated Development (GARID) Project- [P-164330] Project Implementation agency: Ministry of Works and Housing Date of the Procurement Plan: March 28, 2018 Period covered by this Procurement Plan: January to December, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [Ghana Public Procurement Act 663, amended with Act 914 ], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. a. Open advertising of the procurement opportunity at the national level; b. The procurement is open to eligible firms from any country; c. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. Publication of contract award information; f. Rights for the Bank to review procurement documentation and activities; g. An effective complaints mechanism; and h. Maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. N/A Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables N/A Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables]; Works: is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. . PROCUREMENT Ghana : Greater Accra Resilient and Integrated Development Project PLAN General Information Country: Ghana Bank’s Approval Date of the Original Procurement Plan: 2018-04-10 2019-11-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164330 GPN Date: Project Name: Greater Accra Resilient and Integrated Development Project Loan / Credit No: IDA / V1450 Executing Agency(ies): Ministry of Works and Housing WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MWH-103675-CW-RFP / Component 1: Climate Under Request for Single Stage - One Rehabilitation of Project IDA / V1450 Resilient Drainage and Post Limited 0.00 Implementati 2019-03-30 2019-04-26 2019-05-26 Quotations Envelope Office (PCU). Flood Mitigation Measures on GH-MWH-96706-CW-RFQ / Component 4: Project Request for Single Stage - One Rehabilitation of Project IDA / V1450 Post Open - National 0.00 Canceled 2019-02-10 2019-04-07 2019-06-06 Management Quotations Envelope Office (PCU) GH-MWH-96642-CW-RFB / Construction of Detention Component 1: Climate Pending Single Stage - One ponds at Atomic East (Off- IDA / V1450 Resilient Drainage and Prior Request for Bids Open - National 0.00 Implementati 2020-11-25 2020-11-30 2020-12-30 2021-01-29 2021-03-05 2022-08-27 Envelope line) and Atomic West (in- Flood Mitigation Measures on line) GH-MWH-96703-CW-RFB / Component 1: Climate Pending Reconstruction of three(3) Single Stage - One IDA / V1450 Resilient Drainage and Prior Request for Bids Open - National 0.00 Implementati 2020-11-25 2020-11-30 2021-01-11 2021-02-10 2021-03-17 2022-11-07 Bridges, Demolishing of Envelope Flood Mitigation Measures on two(2) Foot Bridges GH-MWH-96639-CW-RFB / Construction of Detention Component 1: Climate Pending Open - Single Stage - Two Ponds, Sand Traps, and IDA / V1450 Resilient Drainage and Prior Request for Bids 0.00 Implementati 2020-11-25 2020-11-30 2021-01-11 2021-03-26 2021-04-30 2023-04-20 International Envelope Urgent Repairs Networks in Flood Mitigation Measures on Odaw Drainage Basin. GH-MWH-96698-CW-RFB / Component 1: Climate Pending Dredging of Odaw River Request for Open - IDA / V1450 Resilient Drainage and Prior Multi Stage 0.00 Implementati 2020-06-15 2020-08-31 2020-08-31 2020-06-20 2020-11-09 2021-02-21 2021-03-28 2025-03-07 Main Channel and Selected Proposals International Flood Mitigation Measures on Tributaries and Clearing Pending GH-MWH-145711-CW-RFQ / Component 4: Project Request for Single Stage - One IDA / V1450 Post Limited 0.00 Implementati 2019-12-05 2020-01-30 2020-07-28 Paving of PCU car park Management Quotations Envelope on GH-MWH-145710-CW-RFQ / Pending Component 4: Project Request for Single Stage - One Installation and Networking IDA / V1450 Post Limited 0.00 Implementati 2019-12-05 2020-01-30 2020-07-28 Management Quotations Envelope of PCU Offices on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 GH-MWH-56616-GO-RFQ / Procurement of 3No Component 1: Climate Request for Single Stage - One Executive L' shape Tables, IDA / V1450 Resilient Drainage and Prior Limited 0.00 Canceled 2018-04-12 2018-06-07 2018-12-04 Quotations Envelope 3No Office Desk, 5No Flood Mitigation Measures Executive Chairs. GH-MWH-56618-GO-RFB / Component 1: Climate Single Stage - One Procurement of 5No, Saloon IDA / V1450 Resilient Drainage and Prior Request for Bids Open - National 0.00 Canceled 2018-04-10 2018-04-15 2018-05-27 2018-06-26 2018-07-31 2019-01-27 Envelope Vehicles Flood Mitigation Measures GH-MWH-56619-GO-RFQ / Procurement of 3No Desktop Computers and Accessories, Component 1: Climate 20No Laptop Computers, Request for Single Stage - One IDA / V1450 Resilient Drainage and Prior Limited 0.00 Canceled 2018-04-14 2018-06-09 2018-12-06 5No Printers, 5No Scanners, Quotations Envelope Flood Mitigation Measures 1No Photocopiers, 5No Digital Cameras, 2No Projectors. GH-MWH-56620-GO-RFQ / Component 1: Climate Request for Single Stage - One Procurement Of Equipment IDA / V1450 Resilient Drainage and Prior Limited 0.00 Canceled 2018-04-18 2018-06-13 2018-12-10 Quotations Envelope For Improving Monitoring Flood Mitigation Measures GH-MWH-96537-GO-RFB / Procurement of Vehicles (6 Component 1: Climate Under Single Stage - One No,s Double Cabin Pick- up IDA / V1450 Resilient Drainage and Post Request for Bids Open - National 0.00 Implementati 2019-03-04 2019-03-09 2019-04-20 2019-05-20 2019-06-24 2019-12-21 Envelope , 1 No. Salon Car and 1 Flood Mitigation Measures on No. Motor Bike) GH-MWH-103671-GO-RFB / Procurement of Vehicles (6 Component 1: Climate Request for Single Stage - One Nos Double Cabin Pick-Up, IDA / V1450 Resilient Drainage and Post Limited 0.00 Canceled 2019-03-30 2019-04-26 2019-05-26 Quotations Envelope 1No. Saloon and 1No. Motto Flood Mitigation Measures Bike. GH-MWH-96524-GO-RFB / Component 1: Climate Procurement of light Single Stage - One IDA / V1450 Resilient Drainage and Post Request for Bids Open - National 0.00 Canceled 2019-09-02 2019-09-07 2019-10-19 2019-11-18 2019-12-23 2020-01-22 imaging, Detection and Envelope Flood Mitigation Measures Ranging ( LIDAR/DEM) GH-MWH-137038-GO-RFQ / Procurement of 1 No Double Pending Component 4: Project Request for Single Stage - One Cabin Pick- up and 4 No IDA / V1450 Post Limited 0.00 Implementati 2019-11-29 2020-01-24 2020-02-28 Management Quotations Envelope Medium Cross country on vehicles for PCU GH-MWH-137042-GO-RFQ / Procurement of Office Furniture for PCU comprising 9 No. Desks, 4 Pending No. Steel wide cabinets for Component 4: Project Request for Single Stage - One IDA / V1450 Post Limited 0.00 Implementati 2019-11-29 2020-01-24 2020-02-28 Arch Files, 8 No. Medium Management Quotations Envelope on Steel cabinets with drawers, 1 No. workstation, wooden bookshelves, 18No. Visitors chairs GH-MWH-137050-GO-RFQ / Procurement of Computers and Accessories comprising 6 No. Laptop Computers and Pending Component 4: Project Request for Single Stage - One accessories, 2No. Desktop IDA / V1450 Post Limited 0.00 Implementati 2019-11-25 2020-01-20 2020-02-28 Management Quotations Envelope computers, 2 No. on Photocopiers, 3 No. Scanners, 3 No printers, 1No. Project with screen Page 2 GH-MWH-137043-GO-RFQ / Procurement of Office equipment comprising 9 sets of Staple machines, Pending Component 4: Project Request for Single Stage - One Perforator, Filing trays, IDA / V1450 Post Limited 0.00 Implementati 2019-11-29 2020-01-24 2020-02-28 Management Quotations Envelope Filing trays, waste bins, 3No on paper shredders, 1No. Comb binding machine, 1No cash safe, 3No. Small size fridges. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MWH-122693-NC-RFB / Mapping of the Odaw Drainage Basin using Light Component 1: Climate Under Imaging Detection and Single Stage - One IDA / V1450 Resilient Drainage and Post Request for Bids Open - National 0.00 Implementati 2019-07-30 2019-08-04 2019-09-15 2019-10-15 2019-11-19 2020-07-16 Ranging (LiDAR/DEM) Envelope Flood Mitigation Measures on technology and production of digital colour orthophoto maps GH-MWH-124174-NC-RFP / Development, Implementation, operation and Hand-over of Flood Component 1: Climate Pending Request for Open - Single Stage - Two Early Warning Response IDA / V1450 Resilient Drainage and Prior 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-08-14 2020-09-18 2023-03-07 Proposals International Envelope System (FEWS) Accra, Flood Mitigation Measures on including procurement and installation of equipment and training. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MWH-56565-CS-CQS / Consultancy services for the Component 1: Climate Consultant study to identify sustainable IDA / V1450 Resilient Drainage and Prior Qualification Limited 0.00 Canceled 2018-04-20 2018-05-04 2018-06-03 2018-07-08 2019-01-04 option for disposing dredged Flood Mitigation Measures Selection materials GH-MWH-56568-CS-CQS / Consultancy Service for Component 2: Solid Waste Consultant Feasibility and Design IDA / V1450 Management Capacity Prior Qualification Open - National 0.00 Canceled 2018-04-17 2018-05-08 2018-06-21 2018-07-21 2018-08-25 2019-02-21 Studies for Designing Improvements Selection Integrated Solid Waste Management GH-MWH-56573-CS-CQS / Component 2: Solid Waste Consultant Consultancy Service for IDA / V1450 Management Capacity Prior Qualification Open - National 0.00 Canceled 2018-04-12 2018-05-03 2018-06-16 2018-07-16 2018-08-20 2019-02-16 detailed Engineering Design Improvements Selection of Transfer Stations. GH-MWH-66198-CS-CQS / Consultancy Services for Component 2: Solid Waste Consultant Under Environmental and Social IDA / V1450 Management Capacity Prior Qualification Limited 0.00 2018-06-11 2018-06-21 2018-07-15 2018-08-03 2018-11-01 Implementation Impact Assessment(ESIA) for Improvements Selection Capping Page 3 Component 3: Participatory GH-MWH-56589-CS-CQS / Upgrading of Targeted Flood Consultant Consultancy Services For IDA / V1450 Prone Low-income Prior Qualification Limited 0.00 Canceled 2018-04-16 2018-04-30 2018-05-30 2018-07-04 2018-12-31 Procurement on Community Communities and Local Selection Liaisons Government Support GH-MWH-80965-CS-CQS / Consultancy Services to Component 2: Solid Waste Consultant Under Improving Waste IDA / V1450 Management Capacity Post Qualification Open - National 0.00 2018-10-08 2018-10-29 2018-12-12 2018-12-19 2019-01-02 2019-07-01 Implementation Management in Low Income Improvements Selection Communities. GH-MWH-56593-CS-CQS / Consultancy Service for Consultant Preparation of ESIA, RAP, Component 4: Project IDA / V1450 Prior Qualification Open - National 0.00 Canceled 2018-04-13 2018-05-04 2018-06-17 2018-07-17 2018-08-21 2019-02-17 ESMF and RPF and Management Selection Socioeconomic Assessment and Survey GH-MWH-56611-CS-CQS / Consultant Consultancy Service for Component 4: Project Under IDA / V1450 Post Qualification Limited 0.00 2018-04-23 2018-05-07 2018-06-06 2018-07-11 2019-01-07 Project Implementation Management Implementation Selection Manual. GH-MWH-56561-CS-CQS / Consultancy Service for preparatory studies for Component 1: Climate Consultant improving flood, drain, IDA / V1450 Resilient Drainage and Post Qualification Limited 0.00 Canceled 2018-04-12 2018-04-26 2018-05-26 2018-06-30 2018-12-27 wetland and retention basins Flood Mitigation Measures Selection management, including land ownership, enforcement, operation and mantianance GH-MWH-56601-CS-CQS / Consultant Consultant Service to Component 4: Project IDA / V1450 Post Qualification Limited 0.00 Canceled 2018-04-10 2018-04-24 2018-05-24 2018-06-28 2018-12-25 Publish, Print and Management Selection Disseminate the report. GH-MWH-56622-CS-CQS / Consultancy Service to Consultant Component 4: Project Conduct a Sensitization and IDA / V1450 Post Qualification Limited 0.00 Canceled 2018-04-17 2018-05-01 2018-05-31 2018-07-05 2019-01-01 Management Readiness Assessment Study Selection within the Project Area GH-MWH-56595-CS-CQS / Consultant Consultancy Service for Component 4: Project IDA / V1450 Post Qualification Limited 0.00 Canceled 2018-04-25 2018-05-09 2018-06-08 2018-07-13 2019-01-09 finalization of the Management Selection Metropolitan Study Report GH-MWH-96509-CS-INDV / Consultancy Services for Component 1: Climate Consultant Environmental, Social Impact Under IDA / V1450 Resilient Drainage and Post Qualification Open - National 0.00 2019-09-02 2019-09-23 2019-11-06 2019-12-06 2020-01-10 2020-07-08 Assessment(ESIA) for Implementation Flood Mitigation Measures Selection Detention Ponds, Urgent Repairs and Bridges GH-MWH-103660-CS-CQS / Component 1: Climate Consultant Consultancy Services - IDA / V1450 Resilient Drainage and Post Qualification Open - National 0.00 Canceled 2019-05-08 2019-05-29 2019-07-12 2019-08-11 2019-09-15 2019-10-15 Supervision of FEWS- Accra. Flood Mitigation Measures Selection GH-MWH-56592-CS-CQS / Component 3: Participatory Consultancy Services For Upgrading of Targeted Flood Consultant Rapid Assessment on IDA / V1450 Prone Low-income Post Qualification Open - National 0.00 Canceled 2018-04-19 2018-05-10 2018-06-23 2018-07-23 2018-08-27 2019-02-23 Housing and Resettlement Communities and Local Selection Options Government Support Page 4 Component 3: Participatory GH-MWH-56579-CS-CQS / Upgrading of Targeted Flood Consultant Consultancy Service for Land IDA / V1450 Prone Low-income Post Qualification Open - National 0.00 Canceled 2018-10-26 2018-10-26 2018-10-26 2018-10-26 2018-10-26 2018-10-26 Ownership Mapping and Communities and Local Selection Access to Land Study Government Support Component 3: Participatory GH-MWH-56581-CS-CQS / Upgrading of Targeted Flood Consultant Consultancy Service for IDA / V1450 Prone Low-income Prior Qualification Open - National 0.00 Canceled 2018-04-26 2018-05-17 2018-06-30 2018-07-21 2018-08-18 2019-02-14 Community Profiling and Communities and Local Selection Enumeration Government Support GH-MWH-96501-CS-QCBS / Consultancy Services for Supervision of Works for Component 1: Climate Quality And Cost- Open - Pending Detention Ponds, Dredging IDA / V1450 Resilient Drainage and Prior 0.00 2020-12-15 2021-01-05 2021-02-18 2021-03-18 2021-04-17 2021-05-22 2021-06-26 2022-06-26 Based Selection International Implementation and urgent repairs of Flood Mitigation Measures drainage network and bridges. GH-MWH-123083-CS-QCBS / Design and Supervision of Flood Early Warning Component 1: Climate Quality And Cost- Open - Response System (FEWS) IDA / V1450 Resilient Drainage and Prior 0.00 Under Review 2019-07-30 2019-08-20 2019-10-03 2019-10-31 2019-11-30 2020-01-04 2020-02-08 2022-09-30 Based Selection International Accra, including the Flood Mitigation Measures development of CONOPS for HSD, GMet and NADMO GH-MWH-123092-CS-QCBS / Consulting Services for Preparation of Community Component 3: Participatory Facilitation, Planning, Upgrading of Targeted Flood Quality And Cost- Open - Preliminary and Detailed IDA / V1450 Prone Low-income Prior 0.00 Under Review 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-03-06 Based Selection International Engineering Design and Communities and Local Construction Supervision and Government Support Contract Management for 3 Communities GH-MWH-145641-CS-QCBS / Consultancy Service for Component 1: Climate Detailed Engineering Design Quality And Cost- Open - Pending IDA / V1450 Resilient Drainage and Prior 0.00 2019-11-20 2019-12-11 2020-01-24 2020-02-21 2020-03-22 2020-04-26 2020-05-31 2022-05-31 for Detention Ponds, Bridge Based Selection International Implementation Flood Mitigation Measures Reconstruction and Urgent Repairs. GH-MWH-145708-CS-QCBS / Consultancy Service for Component 2: Solid Waste Quality And Cost- Pending Design and construction IDA / V1450 Management Capacity Post Open - National 0.00 2019-11-20 2019-12-11 2020-01-24 2020-02-21 2020-03-22 2020-04-26 2020-05-31 2021-05-31 Based Selection Implementation supervision for Capping of Improvements Dumpsites. GH-MWH-145730-CS-LCS / Consulting Services for the Component 4: Project Least Cost Pending preparation of Online IDA / V1450 Post Open - National 0.00 2019-12-05 2019-12-26 2020-02-08 2020-03-07 2020-04-06 2020-05-11 2020-06-15 2020-12-12 Management Selection Implementation Grievances Redress Mechanism GH-MWH-145732-CS-LCS / Component 3: Participatory Consulting Services for the Upgrading of Targeted Flood Least Cost Pending Development of a Geospatial IDA / V1450 Prone Low-income Post Open - National 0.00 2019-11-30 2019-12-21 2020-02-03 2020-03-02 2020-04-01 2020-05-06 2020-06-10 2021-01-06 Selection Implementation Asset Management System Communities and Local for the MMDAs. Government Support GH-MWH-145703-CS-CQS / Consultant Component 4: Project Pending Development of Website and IDA / V1450 Post Qualification Open - National 0.00 2019-11-25 2019-12-16 2020-01-29 2020-02-28 2020-04-03 2020-09-30 Management Implementation hosting for GARID Project Selection Page 5 GH-MWH-56465-CS-QCBS / Consultancy Service for Component 1: Climate Detailed Engineering Design Quality And Cost- Open - IDA / V1450 Resilient Drainage and Prior 0.00 Canceled 2019-09-02 2019-09-23 2019-11-06 2019-12-04 2020-01-03 2020-02-07 2020-03-13 2021-03-13 for Detention Ponds, Bridge Based Selection International Flood Mitigation Measures Reconstruction and Urgent Repairs. GH-MWH-56586-CS-CQS / Component 3: Participatory Consultancy Service for Upgrading of Targeted Flood Consultant Strategy on Livelihoods IDA / V1450 Prone Low-income Post Qualification Open - National 0.00 Canceled 2020-04-15 2020-05-06 2020-06-19 2020-07-19 2020-08-23 2021-02-19 Restoration and Communities and Local Selection Enhancement Government Support INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MWH-56604-CS-INDV / Component 1: Climate Individual Under Procurement of Project IDA / V1450 Resilient Drainage and Prior Consultant Limited 0.00 2018-04-11 2018-04-16 2018-05-07 2018-06-11 2018-12-08 Implementation Coordinator. Flood Mitigation Measures Selection GH-MWH-59168-CS-INDV / Consultancy Service for Component 2: Solid Waste Individual environmental and social IDA / V1450 Management Capacity Prior Consultant Limited 0.00 Canceled 2018-04-16 2018-04-21 2018-04-27 2018-05-12 2018-11-08 impact assessment (ESIA) Improvements Selection for waste transfer station GH-MWH-60059-CS-CQS / Component 1: Climate Individual Procurement of an Under IDA / V1450 Resilient Drainage and Prior Consultant Open 0.00 2018-05-21 2018-07-09 2018-07-30 2018-08-27 2018-11-05 Environmentald Safeguard Implementation Flood Mitigation Measures Selection specialist GH-MWH-60064-CS-CQS / Component 1: Climate Individual Under Procurement of Financial IDA / V1450 Resilient Drainage and Prior Consultant Open 0.00 2018-05-21 2018-07-09 2018-07-30 2018-08-27 2018-11-05 Implementation Management Specialist Flood Mitigation Measures Selection GH-MWH-63174-CS-INDV / Component 1: Climate Individual Under Procurement of a Social IDA / V1450 Resilient Drainage and Prior Consultant Open 0.00 2018-05-21 2018-07-09 2018-07-30 2018-08-27 2018-11-05 Implementation Safeguard Specialist Flood Mitigation Measures Selection GH-MWH-65243-CS-INDV / Consultancy Services for the Component 2: Solid Waste Individual Under Environmental and Social IDA / V1450 Management Capacity Prior Consultant Limited 0.00 2018-06-08 2018-06-13 2018-06-19 2018-06-28 2018-09-06 Implementation Impact Assessment(ESIA) for Improvements Selection Waste Transfer Stations GH-MWH-60063-CS-CQS / Component 1: Climate Individual Under Procurement of a IDA / V1450 Resilient Drainage and Prior Consultant Open 0.00 2018-05-21 2018-07-09 2018-07-30 2018-08-27 2018-11-05 Implementation Procurement Specialist Flood Mitigation Measures Selection Component 3: Participatory GH-MWH-67597-CS-CQS / Upgrading of Targeted Flood Individual Under Consultancy Service for IDA / V1450 Prone Low-income Post Consultant Open 0.00 2018-07-09 2018-08-27 2018-09-03 2018-10-08 2019-04-06 Implementation Community Laison in Nima Communities and Local Selection Government Support Component 3: Participatory GH-MWH-67593-CS-CQS / Upgrading of Targeted Flood Individual Consultancy Services for Under IDA / V1450 Prone Low-income Post Consultant Open 0.00 2018-07-09 2018-08-27 2018-09-03 2018-10-08 2019-04-06 Community Laison Implementation Communities and Local Selection Alogboshie Government Support Page 6 Component 3: Participatory GH-MWH-67599-CS-CQS / Upgrading of Targeted Flood Individual Consultancy Services for Under IDA / V1450 Prone Low-income Post Consultant Open 0.00 2018-07-09 2018-08-27 2018-09-03 2018-10-08 2019-04-06 Community Laison for Implementation Communities and Local Selection Akweteman Government Support GH-MWH-72548-CS-INDV / Component 2: Solid Waste Individual Consultancy Service for IDA / V1450 Management Capacity Post Consultant Open 0.00 Canceled 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2019-05-14 Design and construction Improvements Selection supervision for Capping GH-MWH-80964-CS-INDV / Component 2: Solid Waste Individual Consultancy Services for Under IDA / V1450 Management Capacity Post Consultant Limited 0.00 2018-10-04 2018-10-09 2018-10-16 2018-10-30 2019-04-28 Environmental Audit of Implementation Improvements Selection Kpone Landfill Site GH-MWH-81175-CS-INDV / Consultancy service for the Component 1: Climate Individual preparation of an Under IDA / V1450 Resilient Drainage and Post Consultant Limited 0.00 2018-10-10 2018-10-15 2018-11-05 2018-12-10 2019-06-08 Environmental and Social Implementation Flood Mitigation Measures Selection Impact Assessment on Dredging. GH-MWH-82203-CS-INDV / Consultancy Service for the Component 2: Solid Waste Individual preparation of a Pending IDA / V1450 Management Capacity Post Consultant Open 0.00 2018-10-22 2018-12-10 2018-12-31 2019-02-04 2019-08-03 Resettlement Action Plan Implementation Improvements Selection for proposed Capping of Dumpsite. Component 3: Participatory GH-MWH-67598-CS-CQS / Upgrading of Targeted Flood Individual Consultancy Services for IDA / V1450 Prone Low-income Post Consultant Open 0.00 Canceled 2018-07-09 2018-08-27 2018-09-03 2018-10-08 2019-04-06 Community Laison for Alajo Communities and Local Selection Government Support GH-MWH-96520-CS-INDV / Consultancy services for Component 1: Climate Individual preparation of concept of IDA / V1450 Resilient Drainage and Post Consultant Open 0.00 Canceled 2019-03-20 2019-05-08 2019-05-29 2019-07-03 2019-12-30 operations (CONOPS) to Flood Mitigation Measures Selection support Hydrological services department(HSD) GH-MWH-103657-CS-INDV / Consultancy Services for Component 1: Climate Individual preparation of Operation IDA / V1450 Resilient Drainage and Post Consultant Open 0.00 Canceled 2019-03-29 2019-05-17 2019-06-07 2019-07-12 2019-08-11 (CONOPS) to support Flood Mitigation Measures Selection NADMO. GH-MWH-96514-CS-INDV / Consultancy service for Component 1: Climate Individual preparation of concept of IDA / V1450 Resilient Drainage and Post Consultant Open 0.00 Canceled 2019-03-20 2019-05-08 2019-05-29 2019-07-03 2019-12-30 operations (CONOPS) to Flood Mitigation Measures Selection support Ghana Meteorological Agency(G-Met) GH-MWH-145632-CS-INDV / Individual Component 4: Project Pending Procurement of a IDA / V1450 Post Consultant Open 0.00 2019-11-24 2020-01-12 2020-02-02 2020-03-08 2022-02-28 Management Implementation Communication Specialist Selection GH-MWH-56614-CS-INDV / Individual Component 4: Project Pending Procurement of a Monitoring IDA / V1450 Post Consultant Open 0.00 2019-11-24 2020-01-12 2020-02-02 2020-03-08 2022-02-28 Management Implementation and Evaluation Specialist Selection Page 7