Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: October 2016]: Revision 1 of Updated Procurement Plan, January 2017] 2. Date of General Procurement Notice: 15 July 2017 3. Period covered by this procurement plan: The procurement period of project covered from year January 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 780,000 All 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 476,000 First contract 5. Consultation of the suppliers Above US$ 20,000 First contract (Works) 6. (Non-Consultant Services) Above US$ 10,000 First contract 6. Individual consultants Above US$ 19,200 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project under preparation. 5. Any Other Special Procurement Arrangements: 5 ICB works packages will be financed under Project preparation advance. 6. Summary of the Procurement Packages planned during the first 18 months PADAP August 22, 2017 after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estimate Packages Dome Review Commen No. d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million (yes/n o) Summary of the ICB 0.00 0 No Prior (Works) Summary of the ICB 0.50 1 No Prior (Goods) Summary of the NCB 3.656 5 No Prior (Works) Summary of the NCB 0.78 1 No Prior (Goods) Summary of the ICB 0.00 0 No Prior (Non-Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) All 2. Single Source (Firms) All 3. Individual All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Assignment Estimated Packages Review Comments No. Cost by Bank US$ million (Prior / Post) PADAP August 22, 2017 Summary of number of 0.00 0 Prior contracts that will be let under QCBS Summary of number of 0.00 0 Prior contracts that will be let under other methods PADAP August 22, 2017 PROCUREMENT Madagascar : Sustainable Landscape Management Project PLAN General Information Country: Madagascar Bank’s Approval Date of the Original Procurement Plan: 2017-11-23 2020-11-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154698 GPN Date: Project Name: Sustainable Landscape Management Project Loan / Credit No: IDA / V0430, IDA / 59790, COFN / C1540 PADAP PROJECT UNIT MANAGEMENT Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned T 05-18/CN / Travaux de rénovation des locaux de Component 3: Project l'UGP (Unité de Gestion du Single Stage - One 2018-11- 2018-10- 2018-11- 2018-12- 2018-11- 2018-12- 2018-12- 2019-02- 2019-02- 2019-07- IDA / 59790 Management Coordination A posteriori Appel d'offres Open - National 50,000.00 69,010.77 Signé Projet) du PADAP à la Envelope 13 13 18 18 14 28 20 01 11 01 and M&E direction du Génie rural - MINAE à Nanisana Antananarivo. T 01-19/SAV / Travaux de réhabilitation de deux (02) bâtiments de la DRAEP : Lot 01 : sis à Sambava, Component 3: Project Single Stage - One 2019-03- 2019-04- 2019-03- 2019-04- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-08- Commune Sambava, District COFN / C1540 Management Coordination A posteriori Appel d'offres Open - National 65,000.00 55,651.97 Signé Envelope 15 11 26 25 13 05 17 09 28 18 Sambava and M&E Lot 02 : à Sahamazava Andapa, Commune Andapa, District Andapa T 03-19/SOF / Travaux de réhabilitations des bureaux Component 3: Project Single Stage - One 2019-05- 2019-08- 2019-05- 2019-06- 2019-09- 2019-07- 2019-10- 2019-08- 2019-11- 2020-01- de la DRAEP Sofia : COFN / C1540 Management Coordination A posteriori Appel d'offres Open - National 100,000.00 80,022.23 Signé Envelope 24 14 29 28 16 08 25 12 14 09 Lot 01 : Antsohihy and M&E Lot 02 : Bealanana T 01-19/ANJ / Travaux de réhabilitation des ouvrages Component 2: Investments Single Stage - One 2019-02- 2019-02- 2019-02- 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- 2019-04- 2019-08- sur canaux d'irrigation dans COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 427,520.00 239,627.26 Achevé Envelope 21 14 21 23 18 07 03 02 19 30 le périmètre de Sahavaviana- selected landscapes Iazafo. T 02-19/ANJ / Travaux de Component 2: Investments réhabilitation des barrages Single Stage - One 2019-02- 2019-02- 2019-02- 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- 2019-04- 2019-08- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 427,520.00 328,571.95 Signé de dérivation dans le Envelope 21 14 21 23 18 07 03 02 19 30 selected landscapes périmètre de Sahanofia- Iazafo. T 02-19/SOF / Travaux d'aménagement du périmètre de Bealanana I Lot 01 : La partie amont du Component 2: Investments Single Stage - One 2019-03- 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- 2019-04- 2019-06- 2019-05- 2019-11- PM 580 sur le canal principal COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 756,250.00 500,253.01 Signé Envelope 11 05 21 20 04 05 24 05 24 02 de la rive droite. selected landscapes Lot 02 : La partie aval du PM 580 sur le canal principal de la rive droite. T 01-19/SOF / Construction des ouvrages hydraulique et piste d'entretien dans le PI Mangindrano: Lot 1:BARRAGE ANTAFIANAMALONA Component 2: Investments Single Stage - One 2,188,071.8 1,599,522. 2019-03- 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- 2019-04- 2019-06- 2019-05- 2019-11- Lot 2:CANAL CPRD DU PM COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National Signé Envelope 7 67 11 05 21 20 04 05 24 05 24 02 2153 - BOUT DU RESEAU selected landscapes Lot 3:CANAL CPRG 1er TRONÇON DE 2921 ML Lot 4:CANAL CPRG 2ème TRONÇON DE 3261 ML Lot 5:PISTE-PONT T 01-20/SOF / Travaux Component 2: Investments d'aménagement du périmètre Single Stage - One 1,600,000.0 En attente 2020-07- 2020-07- 2020-08- 2020-08- 2020-09- 2021-06- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 irrigué de Beandrarezona Envelope 0 d'exécution 01 11 10 30 30 07 selected landscapes dans le Paysage de Bealanana. T 03-20/SOF / Travaux Component 2: Investments d'aménagement du périmètre Single Stage - One 2020-04- 2020-05- 2020-05- 2020-06- 2020-07- 2020-06- 2020-08- 2020-08- 2020-09- 2021-01- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 375,000.00 234,454.72 Signé d'Anjohibe-Ambatosia dans Envelope 30 15 10 09 06 29 17 04 11 01 selected landscapes le Paysage de Bealanana. T 04-20/SOF / Travaux de Component 2: Investments stabilisation des lavaka dans Single Stage - One En attente 2020-05- 2020-05- 2020-06- 2020-07- 2020-08- 2021-01- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 220,000.00 0.00 le sous-paysage Ambatoriha Envelope d'exécution 01 16 15 05 10 07 selected landscapes Est, Bealanana et Ambatosia. T 02-20/ANJ / Travaux de réhabilitation des Component 2: Investments Single Stage - One 2020-02- 2020-02- 2020-03- 2020-04- 2020-03- 2020-05- 2020-03- 2020-06- 2020-04- 2021-02- infrastructures COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 340,000.00 193,722.01 Signé Envelope 28 01 14 13 10 03 24 03 27 08 hydroagricoles dans le selected landscapes périmètre d'Iazafo- Mahatsara - Andapatsara T 05-19/ANJ / Travaux de réhabilitation des Component 2: Investments Single Stage - One 2019-09- 2019-10- 2019-10- 2019-11- 2019-11- 2019-12- 2020-01- 2020-01- 2020-06- infrastructures COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 340,000.00 0.00 Annulé Envelope 30 10 15 14 19 04 23 04 02 hydroagricoles dans le selected landscapes périmètre d'Iazafo- Mahatsara - Andapatsara T 04-19/SOF / Travaux de réhabilitation route non revêtue (RIP 117M) reliant Bealanana à Ambatoriha District Bealanana, Région Component 2: Investments Sofia repartis en trois (03): Single Stage - One 4,600,000.0 En cours 2020-05- 2020-06- 2020-06- 2020-07- 2020-08- 2020-07- 2020-09- 2021-03- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 Lot1:du PK 0+000-PK Envelope 0 d'exécution 29 20 08 08 04 28 01 30 selected landscapes 18+000. Lot2:du PK 18+000-PK 22+000. Lot3:du PK 22+000-PK 30+825 (barrière Ambatoriha). T 05-19/SAV / Travaux d'amélioration du réseau hydroagricole du périmètre Component 2: Investments Single Stage - One 2020-03- 2020-05- 2020-04- 2020-05- 2020-07- 2020-05- 2020-08- 2020-06- 2020-08- 2020-12- Ambalafary de 252 ha, IDA / 59790 and capacity building in the A posteriori Appel d'offres Open - National 324,800.00 359,580.46 Signé Envelope 20 23 02 02 07 22 06 26 20 23 Commune Rurale selected landscapes Ambodidivaina, District Andapa, Région SAVA T 03-19/SAV / Travaux de reconstruction du réseau hydroagricole de la grappe Component 2: Investments des périmètres Andalamena Single Stage - One 2020-03- 2020-05- 2020-03- 2020-04- 2020-07- 2020-05- 2020-08- 2020-06- 2020-08- 2020-12- IDA / 59790 and capacity building in the A posteriori Appel d'offres Open - National 313,500.00 248,719.71 Signé et Amboadiala de 191 ha , Envelope 16 23 28 27 07 17 07 21 20 18 selected landscapes Commune Rurale Andasibe Kobahina, District Andapa, Région SAVA. T 06-19/SAV / Travaux de rénovation du réseau Component 2: Investments hydroagricole du périmètre Single Stage - One 2020-03- 2020-05- 2020-04- 2020-05- 2020-07- 2020-05- 2020-08- 2020-06- 2020-08- 2020-12- IDA / 59790 and capacity building in the A posteriori Appel d'offres Open - National 598,500.00 494,317.43 Signé Tanandava sur 400 ha, Envelope 20 23 02 02 07 22 06 26 20 23 selected landscapes Commune Rurale Tanandava, District Andapa, Région SAVA. T 04-19/SAV / Travaux de remise en état du réseau hydroagricole de la grappe Component 2: Investments de Périmètre Antanimbaribe, Single Stage - One En cours 2020-03- 2020-05- 2020-03- 2020-04- 2020-07- 2020-05- 2020-06- 2020-12- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 412,500.00 0.00 Ambatoharanana et Envelope d'exécution 16 23 28 27 07 17 21 18 selected landscapes Andasimenalamba de 244 ha, CR Ambalamanasy II, District Andapa, Région SAVA. T 02-19/SAV / Travaux de renforcement du réseau hydroagricole du Périmètre Component 2: Investments Single Stage - One 2020-03- 2020-05- 2020-04- 2020-05- 2020-07- 2020-05- 2020-08- 2020-06- 2020-08- 2020-12- Ambodivitagnona de 370ha, IDA / 59790 and capacity building in the A posteriori Appel d'offres Open - National 465,000.00 351,675.26 Signé Envelope 20 23 01 01 07 21 10 25 20 22 Commune Rurale selected landscapes Ambalamanasy II, District Andapa, Région SAVA. T 01-20/BOE / Travaux de Component 2: Investments réhabilitation des réseaux de Single Stage - One En cours 2020-09- 2020-08- 2020-09- 2020-10- 2020-09- 2020-11- 2020-11- 2020-12- 2021-04- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 800,000.00 343,689.98 drainage des secteurs 04, 05 Envelope d'exécution 08 28 18 18 29 03 03 02 01 selected landscapes et 06 répartis en trois (3) lots. T 01-19/BOE / Travaux de Component 2: Investments Single Stage - One 31,045,438 En cours 2020-07- 2020-07- 2020-07- 2020-08- 2020-08- 2020-09- 2020-09- 2020-10- 2022-03- curage du drain de ceinture COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 431,250.00 Envelope .11 d'exécution 16 08 30 29 10 18 15 23 07 et du drain naturel Manompo selected landscapes T 02-20/SOF / Travaux Component 2: Investments d'aménagement du périmètre Single Stage - One En attente 2020-09- 2020-10- 2020-11- 2020-11- 2021-01- 2021-06- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 160,000.00 0.00 de Doany dans le paysage de Envelope d'exécution 30 10 09 29 03 02 selected landscapes Bealanana. T 02-19/BOE / Travaux de regabaritage des cours d’eau exutoire du drainage des PI Marovoay, répartis en 2 lots : Component 2: Investments Lot 01: dans le secteur 5 du Single Stage - One En cours 2020-07- 2020-07- 2020-08- 2020-09- 2020-08- 2020-10- 2020-09- 2020-11- 2022-04- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 458,000.00 299,370.00 PM 2903 (Ambohijaoka) au Envelope d'exécution 28 17 07 16 18 11 29 21 20 selected landscapes PM 4114 (Andranodaka). Lot 02: dans le secteur 4 du PM 4114 (Andranodaka) au PM 5865 (Ambolomoty). T 02-20/SAV / Travaux de remise en état du réseau hydroagricole de la grappe de Périmètre Antanimbaribe, Component 2: Investments Single Stage - One En cours 2020-10- 2020-09- 2020-10- 2020-11- 2020-10- 2020-12- 2021-01- 2021-05- Ambatoharanana et COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 412,500.00 0.00 Envelope d'exécution 13 24 18 17 26 07 11 11 Andasimenalamba de 244 selected landscapes ha, CR Ambalamanasy II, District Andapa, Région SAVA (RELANCE). Page 1 T 04-20/BOE / Travaux de trouaison et plantation de Component 2: Investments bandes anti-érosives : Single Stage - One En attente 2020-10- 2020-11- 2020-12- 2020-12- 2021-01- 2021-05- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 200,000.00 0.00 Lot 1: CR Ambolomoty Envelope d'exécution 30 09 09 29 27 27 selected landscapes Lot 2: CR Tsararano lot 3: CR Anosinalainolona T 06-20/SOF / Travaux d'aménagement de champs Component 2: Investments Single Stage - One En attente 2020-10- 2020-11- 2020-12- 2020-12- 2021-01- 2022-03- d'agroforesterie et plantation COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 522,710.00 0.00 Envelope d'exécution 30 04 04 24 28 29 d'arbres fruitiers dans le selected landscapes paysage de Bealanana. T 03-19/BOE / Travaux de Component 2: Investments Single Stage - One En attente 2020-11- 2020-12- 2021-01- 2021-01- 2021-02- 2021-06- stabilisation des grands COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 95,000.00 0.00 Envelope d'exécution 20 05 04 19 06 16 lavaka selected landscapes T 4-19/ANJ / Travaux de réhabilitation des canaux d'irrigation et ouvrages de franchissement dans le Component 2: Investments district de Soanierana Ivongo Single Stage - One 2,720,000.0 En attente 2019-12- 2019-12- 2020-01- 2020-02- 2020-03- 2020-08- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 : Lot 01 : périmètre de Envelope 0 d'exécution 21 31 30 19 21 18 selected landscapes Marovinanto Lot 02 : périmètre de Sahafary Lot 03 : périmètre de Vohijiny Lot 04 : périmètre d'Ampasimbola T 04-19/ANJ / Travaux de réhabilitation des canaux d'irrigation et des ouvrages de franchissement dans le district de Soanierana Ivongo Component 2: Investments Single Stage - One 2,720,000.0 2019-07- 2019-12- 2019-07- 2019-08- 2020-01- 2019-09- 2020-02- 2019-10- 2020-03- : COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 Annulé Envelope 0 11 21 21 20 21 09 26 04 02 Lot 01 : périmètre de selected landscapes Marovinanto Lot 02 : périmètre de Sahafary Lot 03 : périmètre de Vohijiny Lot 04 : périmètre d'Ampasimbola T 03-19/ANJ / Travaux de remise en état des ouvrages existant et curage des drains dans le PI d'Iazaf: Lot 1:zone Mahanoro- Mahatsara Component 2: Investments Single Stage - One 2,550,000.0 2019-04- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-08- 2019-07- 2019-12- Lot 2:zone Ambalabe II- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 Annulé Envelope 0 26 06 11 10 11 30 14 31 28 Antsiratenina selected landscapes Lot 3:zone B1-B6 Lot 4:zone Maromitety Lot 5:zone Sahafana- Ambatomirahalahy Lot 6:Mahatsara-Andapat T 3-19/ANJ. / Travaux de remise en état ouvrages et curage des drains dans le PI d'Iazaf: Lot 1:zone Mahanoro- Component 2: Investments Mahatsara Lot 2:zone Single Stage - One 2,550,000.0 En attente 2019-05- 2019-05- 2019-06- 2019-07- 2019-08- 2020-02- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 Ambalabe II-Antsiratenina Envelope 0 d'exécution 06 11 22 22 26 22 selected landscapes Lot 3:zone B1-B6 Lot 4:zone Maromitety Lot 5:zone Sahafana-Ambatomirahalahy Lot 6:Mahatsara- Andapatsara T 02-20/BOE / Travaux de stabilisation des zones Component 2: Investments Single Stage - One En attente 2020-10- 2020-10- 2020-11- 2020-12- 2021-01- 2021-05- d'érosion CPRD et CSPC COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 50,000.00 0.00 Envelope d'exécution 09 19 18 08 01 01 Ambolomoty composé d'un selected landscapes seul lot. T 05-20/BOE / Travaux de mise en place de dispositifs Component 2: Investments Single Stage - One En attente 2020-10- 2020-11- 2020-12- 2020-12- 2021-02- 2021-08- antiérosifs sur courbes de COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 468,000.00 0.00 Envelope d'exécution 30 09 09 29 02 01 niveau dans le paysage de selected landscapes Marovoay. T 05-20/SAV / Travaux de repiquage mécanisé dans les communes rurales Component 2: Investments Passation de d'Andasibe Kobahina, En cours 2020-10- 2020-09- 2020-11- 2020-10- 2020-12- 2021-01- COFN / C1540 and capacity building in the A posteriori marché de gré à Direct 450,000.00 0.00 Ankiakabe Nord, Bealampona d'exécution 23 28 07 09 22 21 selected landscapes gré et Ambodidivaina, district d'Andapa dans le cadre de la relance de la production post- Covid. T 06-20/BOE / Travaux de protection des bassins versants par la plantation d'acacia et eucalyptus répatis en 4 lots de 300 ha Lot 1: Commune d' Component 2: Investments Single Stage - One En attente 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- 2022-06- Anosinalainolona COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 480,000.00 0.00 Envelope d'exécution 30 09 09 08 12 07 Lot 2: Commune de selected landscapes Tsararano Ouest Lot 3: Commune de Tsararano Est lot 4: Commune d'Ambolomoty T 03-20/SAV / Travaux Component 2: Investments d'aménagement des zones à Single Stage - One En attente 2020-10- 2020-11- 2020-12- 2020-12- 2021-01- 2021-11- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 140,000.00 0.00 forte érosion au niveau du Envelope d'exécution 30 04 04 24 28 24 selected landscapes paysage d'Andapa. T 07-20/SOF / Travaux de protection biologique des Bassins Versants: Lot 1:Ambatosia Lot 2:Antsamaka, Beandrarezona Component 2: Investments Single Stage - One 2,766,000.0 En attente 2020-09- 2020-10- 2020-11- 2020-11- 2020-12- 2022-04- Lot 3:Ambodiampana, COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 Envelope 0 d'exécution 30 05 04 24 29 23 Bealanana selected landscapes Lot 4:Ambatoriha, Ambararatabe, Mangindrano Lot 5: , Marotolana, Analila, Anjozoromadosy, Ankazotokana,Ambovonomb y T 05-20/SOF / Travaux de Component 2: Investments Lutte Antiérosive et de Single Stage - One 2,367,000.0 En attente 2021-06- 2021-06- 2021-07- 2021-08- 2021-09- 2022-09- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 restauration des sols dans le Envelope 0 d'exécution 18 28 28 17 21 21 selected landscapes paysage de Bealanana. T 09-20/SOF / Reprise des travaux de réhabilitation du réseau hydroagricole du périmètre Andranomafana Component 2: Investments Passation de Mangindrano du paysage de En attente 2020-10- 2020-11- 2020-12- 2021-04- COFN / C1540 and capacity building in the A posteriori marché de gré à Direct 295,000.00 0.00 Bealanana, CR Mangindrano ; d'exécution 27 06 06 05 selected landscapes gré région SOFIA lot 01 : travaux sur le barrage d'Antafianamalona CPRD, partiteur, bâche et chute T 08-20/SOF / Reprise des travaux de réhabilitation des infrastructures hydroagricoles du périmètre Component 2: Investments Passation de Bealanana 1 du paysage de En attente 2020-10- 2020-11- 2020-12- 2021-04- COFN / C1540 and capacity building in the A posteriori marché de gré à Direct 180,000.00 0.00 Bealanana, CR Bealanana d'exécution 27 06 06 05 selected landscapes gré district Bealanana région SOFIA- lot 01 bis : la partie amont du pm 580 sur le canal principal de la rive droite T 01-20/ANJ / Travaux de réhabilitation d'un bâtiment à usage de Banque de Component 2: Investments semence communautaire: Single Stage - One En attente 2020-07- 2020-07- 2020-08- 2020-09- 2020-10- 2021-01- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 110,500.00 0.00 -Lot 01: Banque de semence Envelope d'exécution 23 28 27 10 15 13 selected landscapes à Iazafo - Lot 02: Banque desemence à Soanierana Ivongo T 01-21/ANJ / Travaux de protection des berges des rivières dans les Paysages d'Iazafo et de Soanierana Ivongo: -Lot 01: Berges de la rivière Component 2: Investments Single Stage - One En attente 2021-09- 2021-09- 2021-10- 2021-11- 2021-11- 2022-03- Iazafo COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 824,600.00 0.00 Envelope d'exécution 10 20 20 04 24 24 -Lot 02: Berges de la rivière selected landscapes Sahavaviana -Lot 03: Berges de rivière Sahafototra Lot 04: Berges de la rivière Sahave T 02-21/ANJ / Travaux de réhabilitation des pistes en terre dans le paysage d'Iazafo : -Lot 01:Piste Maromitety- Component 2: Investments Ampasimazava-Mahanoro Single Stage - One 1,786,700.0 En attente 2021-07- 2021-07- 2021-08- 2021-09- 2021-09- 2022-03- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 -Lot 02:Piste Maromitety- Envelope 0 d'exécution 08 18 17 01 21 20 selected landscapes Ambalakondro-Vavazahana -Lot 03: Piste Marofototra- Mahanoro -Lot 04: Piste Ambodinonoka- Mahatera T 03-21/ANJ / Travaux de réhabilitation des barrages et Component 2: Investments Single Stage - One En attente 2021-07- 2021-07- 2021-08- 2021-09- 2021-09- 2022-03- des ouvrages connexes de la COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 500,000.00 0.00 Envelope d'exécution 09 19 18 02 27 26 zone Ambatoharanana dans selected landscapes le paysage d'Iazafo T 04-21/ANJ / Travaux de réhabilitation des barrages et des ouvrages annexes dans le paysage de Soanierana Ivongo: Component 2: Investments -Lot 01: Périmètre Single Stage - One En attente 2021-06- 2021-07- 2021-08- 2021-08- 2021-09- 2022-01- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 750,750.00 0.00 Antanetilava Envelope d'exécution 30 10 09 29 18 16 selected landscapes -Lot 02:Périmètre Vohilava -Lot 03: Périmètre Ambodiboanara -Lot 04:Perimètre Diavolamaso -Lot 05:Périmètre Sahondrana Page 2 T 05-21/ANJ / Travaux de réhabilitation des canaux d'irrigation et des ouvrages de franchissement pour les périmètres hydroagricoles: Component 2: Investments -Lot 01:Périmètre Single Stage - One En attente 2021-06- 2021-07- 2021-08- 2021-08- 2021-09- 2022-01- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 775,800.00 0.00 Ampoezana Envelope d'exécution 28 08 07 22 11 09 selected landscapes -Lot 02:Périmètre Anamborano -Lot 03:Périmètre Fandrianomby -Lot 04:Périmètre Antsirabeniseva T 06-21/ANJ / Travaux de réhabilitation des réseaux d'irrigation et de drainage Component 2: Investments des périmètres suivants dans Single Stage - One En attente 2021-07- 2021-07- 2021-08- 2021-08- 2021-09- 2022-01- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 445,500.00 0.00 la Commune Antanifotsy : Envelope d'exécution 12 22 21 31 20 18 selected landscapes -Lot 01:Périmètre Tsaratanana -Lot 02:Périmètre Namatoana -Lot 03:Périmètre Sahasoa T 07-21/ANJ / Travaux de réhabilitation de la piste en terre reliant Antanifotsy- Component 2: Investments Single Stage - One En attente 2021-07- 2021-07- 2021-08- 2021-09- 2021-10- 2022-01- Marogisa-Marovinanto, dans COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 116,200.00 0.00 Envelope d'exécution 19 29 28 12 02 30 la Commune Antanifotsy, selected landscapes district de Soanierana Ivongo- Région Analabjirofo T 01-20/SAV / Travaux d'aménagement et d'installation des sites pépinières : Lot 1: Ambalamanasy II, Component 2: Investments Betsakotsako , Single Stage - One En attente 2020-11- 2020-12- 2021-01- 2021-01- 2021-02- 2021-06- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 654,000.00 0.00 Andranomena, Andasibe K, Envelope d'exécution 30 05 04 24 28 28 selected landscapes Marovato, Belaoka, Matsohely Lot 2: Ambodiangezoka, Ambodidivaina, Bealampona, Ankiakabe , Ambodimanga I, Tanandava, Andapa T 04-20/SAV / Travaux pour la protection et Component 2: Investments restauration des flancs de Single Stage - One 1,257,400.0 En attente 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2023-01- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 colline (bassins versants) du Envelope 0 d'exécution 10 20 19 08 15 18 selected landscapes Paysage d'Andapa, District d'Andapa, Région SAVA. T 07-19/SAV / Traitement et stabilisation des quatres (04) lavaka dans les Component 2: Investments Single Stage - One En attente 2021-01- 2021-02- 2021-03- 2021-03- 2021-05- 2021-07- anciennes zones IDA / 59790 and capacity building in the A posteriori Appel d'offres Open - National 61,820.00 0.00 Envelope d'exécution 25 09 11 31 05 24 d'exploitation minières à selected landscapes Andasinimaro, Commune Rurale Bealampona, District Andapa, Région SAVA GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Passation de F 18-17/CN / Acquisition Component 3: Project marchés auprès 2017-11- 2017-11- 2017-12- 2018-03- 2018-01- 2018-06- des 10 Voitures et des 20 IDA / V0430 Management Coordination A posteriori Direct 500,000.00 341,428.00 Signé des agences de 27 23 27 22 29 20 Motos and M&E l'ONU F 01-17/CN / Fournitures des matériels informatiques: - Lot 01:08 ordinateurs de bureau (desktop) avec 01 Component 3: Project onduleur de chaque et 10 Demande de Single Stage - One 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2017-12- 2018-01- IDA / V0430 Management Coordination A posteriori Limited 70,000.00 0.00 Annulé ordinateurs portable propositions Envelope 30 05 05 19 21 19 23 10 27 16 and M&E (Laptop). - Lot 02: fournitures des accessoires informatiques 09 imprimantes, 09 scanners, - lot 03: 06 phootcopieu MG-UGP PADAP-38789-GO- RFP / L'acquisition des Component 3: Project fournitures de bureau, Demande de Single Stage - One 2017-11- 2017-12- 2017-12- 2017-12- 2018-01- 2018-01- IDA / V0430 Management Coordination A posteriori Limited 20,000.00 0.00 Annulé consommables informatiques propositions Envelope 30 05 21 26 03 23 and M&E et produits d'entretien du PADAP. F 04-18/CN / Fournitures des matériels informatiques pour Quatre cellules Component 3: Project Single Stage - One 2018-03- 2018-02- 2018-05- 2018-03- 2018-06- 2018-03- régionales d'exécution : 08 IDA / V0430 Management Coordination A posteriori Demande de prix Limited 12,000.00 10,848.04 Achevé Envelope 26 05 20 16 19 30 ordinateurs de bureau and M&E (desktop) avec 01 onduleur de chaque. F 5-18/CN / Acquisition des matériels informatiques pour Quatre cellules régionales Component 3: Project Single Stage - One 2018-03- 2018-01- 2018-05- 2018-03- 2018-06- 2018-03- d'exécution : 40 ordinateurs IDA / V0430 Management Coordination A posteriori Demande de prix Limited 80,000.00 74,307.22 Achevé Envelope 24 24 20 08 19 28 portables (laptop) avec une and M&E disque dure externe de chaque. MG-UGP PADAP-55622-GO- DIR / Migration en version Component 3: Project Passation de 2018-03- 2018-03- 2018-04- 2018-03- 2018-05- 2018-03- 2018-06- web et Formation de logiciel IDA / V0430 Management Coordination A posteriori marché de gré à Direct 30,000.00 28,504.82 Signé 23 27 02 06 06 23 25 TOM²PRO licence PN-BVPI and M&E gré pour PADAP. F 15-18/CN / L'acquisition Component 3: Project des Consommables Single Stage - One 2018-07- 2018-07- 2018-09- 2018-08- 2018-10- 2018-08- IDA / 59790 Management Coordination A posteriori Demande de prix Limited 9,400.00 3,282.13 Achevé informatiques pour l'Unité de Envelope 25 20 05 14 05 21 and M&E Gestion de Projet PADAP F 06-18/CN / Acquisition de : lot 01 03 photocopieuses pour l'unité de gestion projet Component 3: Project Single Stage - One 2018-07- 2018-08- 2018-09- 2018-09- 2018-10- 2018-09- PADAP. IDA / 59790 Management Coordination A posteriori Demande de prix Limited 48,000.00 29,323.39 Achevé Envelope 25 08 05 07 05 14 lot 02 08 photocopieuses and M&E monochromes pour les quatre cellules d'exécution régionales du PADAP. MG-UGP PADAP-38789-GO- RFQ / L'acquisition des Component 3: Project fournitures de bureau, Single Stage - One 2017-12- 2017-07- 2018-02- 2017-07- 2018-03- 2017-08- IDA / V0430 Management Coordination A posteriori Demande de prix Limited 20,000.00 7,545.86 Achevé consommables informatiques Envelope 05 05 04 14 06 25 and M&E et produits d'entretien du PADAP. F 01B-17/CN / Fournitures des matériels informatiques:- Lot 01:08 ordinateurs de bureau (desktop) avec 01 Component 3: Project onduleur de chaque et 10 Single Stage - One 2017-09- 2017-09- 2017-11- 2017-10- 2017-12- 2017-11- IDA / V0430 Management Coordination A posteriori Demande de prix Limited 70,000.00 46,297.28 Achevé ordinateurs portable Envelope 19 06 27 27 17 06 and M&E (Laptop).- Lot 02: fournitures des accessoires informatiques 09 imprimantes, 09 scanners,- lot 03: 06 phootcopie F 12-18/CN / Acquisition de : - Lot 01 : Fournitures de Component 3: Project bureau pour l'Unité de Single Stage - One 2018-11- 2019-01- 2018-12- 2019-02- 2018-12- IDA / 59790 Management Coordination A posteriori Demande de prix Open - National 12,500.00 9,848.58 Achevé Gestion de Projet PADAP. Envelope 18 13 26 12 28 and M&E - Lot 02 : Produits d'entretien pour l'Unité de Gestion de Projet PADAP. MG-UGP PADAP-87379-GO- DIR / Acquisition du logiciel ArcGIS auprès de la société Passation de Component 1: Information 2018-11- 2018-12- 2018-11- 2018-12- 2019-01- 2019-01- 2019-01- MAKY Engineering et IDA / 59790 A posteriori marché de gré à Direct 35,000.00 22,299.71 Achevé and planning 16 24 26 30 11 29 25 formation sur son utilisation gré (Stockage et gestion des données). F 01-18/BOE / Dotation de Component 2: Investments tarares pour le Centre Single Stage - One 2018-11- 2019-01- 2019-03- 2019-03- IDA / 59790 and capacity building in the A posteriori Demande de prix Open - National 12,000.00 6,360.81 Résilié Multiplicateur de Semence de Envelope 30 31 22 02 selected landscapes Tsararano (Marovoay) F 01-18/SAV / Dotations de 02 moto pompes suivi d'une formation sur l'utilisation et Component 2: Investments Single Stage - One 2018-11- 2019-01- 2019-02- 2019-03- 2019-03- l'entretien aux deux IDA / 59790 and capacity building in the A posteriori Demande de prix Open - National 8,000.00 4,034.55 Achevé Envelope 30 31 28 02 27 Fédérations : MEVA selected landscapes Ambodidivaina et SOA Ankiakabe Nord F 9-18/CN / Acquisition des mobiliers de bureau pour les quatre Cellule d'Exécution Component 3: Project Régionale du PADAP repartis Single Stage - One 2018-11- 2019-01- 2019-04- 2019-02- 2019-05- IDA / 59790 Management Coordination A posteriori Demande de prix Open - National 40,000.00 64,583.70 Achevé en 04 lots : Lot 01 région Envelope 28 14 16 13 14 and M&E SOFIA, lot 02 région Boeny, lot 03 région SAVA et lot 04 région Analanjirofo. F 02-19/BOE / Acquisition Component 2: Investments des semences pour la Single Stage - One 2019-05- 2019-04- 2019-07- 2019-04- 2019-07- 2019-07- COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 4,400.00 4,361.57 Achevé diffusion des paquets Envelope 27 04 08 23 28 16 selected landscapes technique rizicole. MG-UGP PADAP-113663- Component 3: Project GO-RFQ / Acquisition de 09 Single Stage - One 2019-06- 2019-08- 2019-08- 2019-11- 2019-11- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 31,000.00 21,856.23 Achevé canopy pour les matériels Envelope 04 10 29 08 04 and M&E roulant du projet Page 3 F 1-18/ANJ / Acquisition : lot 01 des fournitures de Component 3: Project Single Stage - One 2018-12- 2019-01- 2019-03- bureau et lot 02 des IDA / 59790 Management Coordination A posteriori Demande de prix Open - National 4,500.00 0.00 Annulé Envelope 05 30 01 consommables informatiques and M&E pour le CER Analanjirofo. F 05-19/SAV / Acquisition Component 2: Investments Single Stage - One 2019-06- 2019-08- 2019-07- 2019-08- 2019-07- d'intrants au profit des COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 7,000.00 5,300.62 Achevé Envelope 10 16 05 26 12 paysans formateurs (PF). selected landscapes F 06-19/SAV / Acquisition Component 2: Investments de matériels pour le sarclage Single Stage - One 2019-06- 2019-08- 2019-07- 2019-11- 2019-10- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 10,620.00 7,662.18 Achevé et la récolte au profit des Envelope 10 16 05 29 17 selected landscapes paysans formateurs (PF). MG-UGP PADAP-87384-GO- RFQ / Acquisition des matériels informatiques (02 Component 1: Information Single Stage - One 2018-11- 2019-01- 2019-02- Desktop) et accessoires (02 IDA / 59790 A posteriori Demande de prix Open - National 35,000.00 0.00 Annulé and planning Envelope 21 20 19 imprimantes) pour le logiciel ArcGIS ( Stockage et gestion des données) plus 10 GPS. MG-UGP PADAP-113652- GO-RFQ / Acquisition des matériels et accessoires informatiques : Lot 1:11 Desktop Lot 2:11 onduleurs online Component 1: Information Single Stage - One 2019-06- 2019-08- 2019-12- 2019-09- 2020-02- COFN / C1540 A posteriori Demande de prix Open - National 33,000.00 134,817.17 Achevé Lot 3:09 Laptop avec 01 and planning Envelope 30 29 27 28 06 disque dur externe de chaque Lot 4: imprimante : 01 A1, 06 A3 et 01 jet d'encre A4 Lot 5: 09 vidéoprojecteurs avec écran MG-UGP PADAP-116266- GO-RFQ / Acquisition des : Component 3: Project Lot 01 : 10 GPS (Global Single Stage - One 2019-07- 2019-09- 2019-10- 2019-10- 2019-11- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 12,000.00 46,888.43 Achevé Positioning System). Envelope 03 01 18 01 22 and M&E Lot 02 : 10 appareils photos numériques. MG-UGP PADAP-120173- Component 3: Project Single Stage - One 2019-07- 2019-09- 2019-12- 2019-11- 2020-02- GO-RFQ / Materiel et mobiler COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 75,000.00 36,864.87 Achevé Envelope 11 23 27 22 03 de bureau de l'UGP. and M&E MG-UGP PADAP-120176- Component 3: Project GO-RFQ / Équipement de Single Stage - One 2019-08- 2019-10- 2019-12- 2019-11- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 3,000.00 5,206.72 Signé protection individuel (EPI) du Envelope 04 17 27 16 and M&E Projet. F 01-19/BOE / Acquisition de matériels pour les Component 2: Investments Single Stage - One 2019-06- 2019-08- 2019-10- AUEs/Fédérations (Mini pelle, COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 82,000.00 0.00 Annulé Envelope 06 20 19 mini compacteur motorisé et selected landscapes motopompe) F 01-19/SOF / Achats des Component 2: Investments Single Stage - One 2019-06- 2019-09- 2019-12- 2019-10- 2019-12- intrants agricole pour COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 11,800.00 1,487.51 Achevé Envelope 22 01 20 01 27 paysans leaders/adoptants selected landscapes F 02-20 /SAV / Acquisition d'intrants (semences et engrais) au profit des 111 Component 2: Investments Single Stage - One 2020-05- 2020-07- 2020-06- 2020-07- 2020-07- anciens paysans formateurs COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 8,110.00 6,732.54 Achevé Envelope 11 09 30 23 10 et de 50 nouveaux paysans selected landscapes formateurs dans le paysage d'Andapa, Région SAVA Component 2: Investments F 01-20/SOF / Achat de Single Stage - One En attente 2020-08- 2020-10- 2020-11- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 15,000.00 0.00 matériels agricoles. Envelope d'exécution 10 23 22 selected landscapes F 01-19/SAV / Acquisition Component 3: Project Single Stage - One 2019-08- 2019-10- 2019-11- de deux groupes COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 5,000.00 0.00 Annulé Envelope 19 29 28 électrogènes de la CER SAVA. and M&E F 02-19/SOF / Dotation en Component 2: Investments Single Stage - One 2019-04- 2019-06- 2019-07- matériels et équipements de COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 15,310.00 0.00 Annulé Envelope 03 13 13 surveillance des COBA selected landscapes F 02-19/ANJ / Acquisition de matériesl agricoles pour Component 2: Investments Single Stage - One 2019-10- 2019-12- 2020-01- le reboisement dans les COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 15,710.00 0.00 Annulé Envelope 05 15 04 paysages de Soanierana selected landscapes Ivongo et Iazafo. F 06-19/ANJ / Acquisition des jeunes plants pour les Component 2: Investments Single Stage - One 2019-09- 2019-11- 2020-01- activités de reboisement COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 23,270.00 0.00 Annulé Envelope 14 24 08 dans les paysages d'Iazafo et selected landscapes de Soanierana Ivongo. F 02-18/BOE / Acquisition de divers articles pour le Component 3: Project Single Stage - One 2018-11- 2019-01- 2019-03- fonctionnement du bureau IDA / 59790 Management Coordination A posteriori Demande de prix Limited 1,700.00 0.00 Annulé Envelope 30 30 01 du Projet (Marovoay et and M&E Mahajanga) F 05-19/BOE / Acquisition des matériels agricole Component 2: Investments (Sarcleuse, charrue à soc, Single Stage - One En attente 2020-09- 2020-11- 2020-12- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 43,800.00 0.00 herse à dents, pulvérisateur, Envelope d'exécution 23 29 29 selected landscapes batteuse à pédale, bâche) pour une année. F 03-20/BOE / Acquisition Component 2: Investments de tarare pour le centre Single Stage - One En cours 2020-06- 2020-08- 2020-11- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 21,875.00 20,276.70 multiplicateur de semence à Envelope d'exécution 04 30 28 selected landscapes Tsararano (RELANCE) F 04-20/SAV / Acquisition des balances automatiques Component 2: Investments Single Stage - One 2020-04- 2020-06- 2020-06- 2020-07- 2020-08- force de 20kg pour les COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 1,250.00 794.36 Achevé Envelope 20 23 30 23 19 semenciers dans le paysage selected landscapes d'Andapa, Région SAVA. F 03-20/SAV / Acquisition de 31 panneaux d'indication Component 2: Investments Single Stage - One 2020-03- 2020-05- 2020-06- pour les sites de reboisemnt COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 1,300.00 0.00 Annulé Envelope 12 25 24 dans le paysage d'Andapa, selected landscapes Région SAVA. F 03-19/SOF / Acquisition Component 1: Information Single Stage - One En attente 2020-10- 2020-12- 2021-01- d'un kit solaire pour la CER COFN / C1540 A posteriori Demande de prix Open - National 8,000.00 0.00 and planning Envelope d'exécution 10 20 19 Sofia. F 01-19/ANJ / Fourniture de Component 2: Investments Single Stage - One En attente 2020-10- 2020-12- 2022-12- bureau en 02 années pour la COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 40,000.00 0.00 Envelope d'exécution 06 14 04 CER Analanjirofo. selected landscapes F 04-19/ANJ / Acquisition Component 3: Project des consommables Single Stage - One En attente 2020-09- 2020-11- 2020-12- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 27,000.00 0.00 informatiques en 03 années Envelope d'exécution 20 15 15 and M&E pour la CER Analanjirofo. Passation de F 05-20/CN / Acquisition Component 3: Project marchés auprès 2020-02- 2020-03- 2020-04- 2020-10- d'un véhicule 4x4 pick-up du IDA / V0430 Management Coordination A posteriori Direct 83,500.00 0.00 Annulé des agences de 28 09 23 20 PADAP and M&E l'ONU F 01-20/CN / Acquisition de 4 véhicules (Motos) pour les Component 2: Investments Single Stage - One 2020-03- 2020-05- 2020-07- agents communaux chargés COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 16,000.00 0.00 Annulé Envelope 04 17 16 de l'appui aux Communautés selected landscapes Locales à l'approche LIFE MG-UGP PADAP-76372-GO- RFQ / Acquisition d’images satellitaires à haute Component 1: Information Open - Single Stage - One 2020-04- 2020-06- 2020-08- résolution avec modèle COFN / C1540 A posteriori Demande de prix 50,000.00 0.00 Annulé and planning International Envelope 08 18 17 numérique de terrain pour le paysage de Bealanana, d’une superficie de 2776 km2 environ. F 04-20/ANJ / Achat d'intrants agricoles: Lot 01: Engrais minéraux Lot 02: Engrais organiques Lot 03: Semences: riz Component 2: Investments améliorés, de base, maïs et Single Stage - One En attente 2021-06- 2021-09- 2021-10- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 89,280.00 0.00 haricot Envelope d'exécution 25 07 07 selected landscapes Lot 04: Semences: tephrosia et stylosanthes Lot 05: Eclats de souches de Bachiaria et Pennisetum Lot 06: Semence riz F 07-20/SOF / Acquisition des jeunes plants de caféier en 2 lots pour le paysage de Component 2: Investments Bealanana: Single Stage - One En attente 2020-10- 2020-11- 2021-04- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 91,450.00 0.00 Lot 01: 5 000 de caféier Envelope d'exécution 05 30 29 selected landscapes Robusta Lot 02: 75 000 de caféier Arabica F 04-20/SOF / Acquisition de fumier de parc pour la Component 2: Investments Single Stage - One En attente 2020-10- 2020-11- 2021-01- mise en œuvre de la COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 100,000.00 0.00 Envelope d'exécution 05 27 26 riziculture et de selected landscapes l'agroforesterie dans le paysage de Bealanana. F 01-20/ANJ / Achat de fournitures et équipements Component 2: Investments des deux (02) banques de Single Stage - One En attente 2021-06- 2021-09- 2021-10- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 95,600.00 0.00 semences dans les paysages Envelope d'exécution 20 08 08 selected landscapes d'Iazafo et de Soanierana Ivongo Page 4 F 02-20/ANJ / Acquisition de matériels agricoles: - Lot 01: 277 sarcleuses - Lot 02: 900 Sarcleuses, 180 charrues et 450 Component 2: Investments Single Stage - One En attente 2021-03- 2021-05- 2021-06- fourches COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 66,000.00 0.00 Envelope d'exécution 01 20 19 - Lot 03: 63 vanneuses et 63 selected landscapes batteuses - Lot 04: 90 Pulvérisateurs, 135 arrosoirs et 9 rouleau de 100 m de gaine en polypropylène F 06-20/BOE / Acquisition de manguiers Component 2: Investments Lot 01 : Site d'Ambolomoty Single Stage - One En attente 2020-10- 2020-12- 2021-02- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 97,500.00 0.00 Lot 02 : Site de Tsararano Envelope d'exécution 05 16 14 selected landscapes Lot 03: Site d'Anosinalainolona F 03-20/SOF / Acquisition arbres fruitiers: Lot1: 5 000 pommier porte- greffe Lot2: 20 000 variété améliorée de pommier Component 2: Investments Lot3: 5 000 pêcher porte- Single Stage - One En attente 2020-10- 2020-11- 2021-04- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 86,000.00 0.00 greffe Envelope d'exécution 05 25 24 selected landscapes Lot4: 20 000 variété améliorée de pêcher Lot5: 5 000 poirier porte- greffe Lot6: 20 000 variété améliorée de poirier F 05-20/SOF / Acquisition d'agrumes : Lot 1: 20 000 greffes de mandarinier ou de greffes Component 2: Investments d'oranger Single Stage - One En attente 2020-10- 2020-11- 2021-04- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 80,000.00 0.00 Lot 2: 10 000 de citronnier Envelope d'exécution 05 30 29 selected landscapes Lot 3: 10 000 greffes de Pamplemoussiers Lot 4: 30 000 porte-greffes de la famille de mandarinier F 09-20/SOF / Acquisition des jeunes plants pour Component 2: Investments Single Stage - One En attente 2020-10- 2020-12- 2021-03- stabilisation de terrains COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,500.00 0.00 Envelope d'exécution 15 09 09 dégradés (Ambararatabe selected landscapes Nord - Ambatoriha Est) F 18-20/SOF / Acquisition d'arbres autochtones à fruits Component 2: Investments comestibles : Single Stage - One En attente 2020-10- 2020-11- 2021-04- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 69,000.00 0.00 Lot 1: 30 000 Jacquier Envelope d'exécution 05 30 29 selected landscapes produit Lot 2: 30 000 jeunes plants d'Eugenia F 19-20/SOF / Acquisition des jeunes plaqueminiers, de bibaciers et de litchi: Lot 1: 30 000 variété Component 2: Investments améliorée de plaqueminier Single Stage - One En attente 2020-10- 2020-11- 2021-04- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 86,000.00 0.00 (Kaki) Envelope d'exécution 05 30 29 selected landscapes Lot 2: 25 000 variété améliorée de bibacier Lot 3: 20 000 jeunes plants de litchi F 20-20/SOF / Acquisition de manguiers 2 lots pour le paysage de Bealanana: Component 2: Investments Single Stage - One En attente 2020-10- 2020-11- 2021-04- Lot 01: 20 000 Manguier COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 69,000.00 0.00 Envelope d'exécution 05 30 29 porte-greffe selected landscapes Lot 02: 40 000 variétés améliorées de manguiers F 10-20/SOF / Fourniture Component 2: Investments des jeunes plants pour Single Stage - One En attente 2020-10- 2020-12- 2021-03- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,000.00 0.00 protection des pistes ruraux Envelope d'exécution 15 20 20 selected landscapes (Antsamaka -Beandrarezona) F 21-20/SOF / Acquisition de papayer en 2 lots : Lot 1: 40 000 de papayer Component 2: Investments Single Stage - One En attente 2020-10- 2020-11- 2021-04- (Solo Sunset, Solo COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 92,000.00 0.00 Envelope d'exécution 05 30 29 Waimanalo, Sunrise...) selected landscapes Lot2: 40 000 d'avocatier de race MEXICAIN. F 11-20/SOF / Achat des Component 2: Investments Single Stage - One En attente 2020-10- 2020-12- 2021-03- jeunes plants pour COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,500.00 0.00 Envelope d'exécution 10 15 15 production de bois énergie selected landscapes (Ambatosia) F 12-20/SOF / Achat des Component 2: Investments Single Stage - One En attente 2020-10- 2020-12- 2021-03- jeunes plants pour COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,400.00 0.00 Envelope d'exécution 05 10 10 production de bois d'œuvre selected landscapes (Ambatosia) F 13-20/SOF / Fourniture Component 2: Investments des jeunes plants pour Single Stage - One En attente 2020-10- 2020-11- 2021-02- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,000.00 0.00 protection des périmètres Envelope d'exécution 05 30 28 selected landscapes irrigués à réhabiliter par le Projet F 14-20/SOF / Acquisition Component 2: Investments de jeunes plants pour Single Stage - One En attente 2020-10- 2020-12- 2021-03- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 80,000.00 0.00 protection des Lacs et Etangs Envelope d'exécution 05 10 10 selected landscapes (Bealanana - Beandrarezona) F 07-20/BOE / Acquisition Component 2: Investments Single Stage - One 2020-09- 2020-12- 2020-11- 2021-03- d'acacia pour la protection COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,000.00 96,805.52 Signé Envelope 26 01 11 31 du sol selected landscapes F 15-20/SOF / Fourniture des plants pour restauration Component 2: Investments Single Stage - One En attente 2020-10- 2020-12- 2021-06- des forêts dégradées (Analila COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,000.00 0.00 Envelope d'exécution 05 10 08 - Anjozoromadosy- selected landscapes Marotolana - Ankazotokana) F 16-20/SOF / Acquisition des jeunes plants pour Component 2: Investments Single Stage - One En attente 2020-10- 2020-12- 2021-03- restauration/conservation COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,000.00 0.00 Envelope d'exécution 05 10 10 des sols (Bealanana - selected landscapes Ambodiampana) F 17-20/SOF / Fourniture des jeunes plants pour la Component 2: Investments protection autour des zones Single Stage - One En attente 2020-10- 2020-12- 2021-03- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,800.00 0.00 gérées par les COBA Envelope d'exécution 10 18 18 selected landscapes (Mangindrano - Ambovonomby) F 08-20/BOE / Acquisition Component 2: Investments d'eucalyptus pour le Single Stage - One 2020-09- 2020-12- 2020-11- 2021-03- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,500.00 101,868.48 Signé reboisement à vocation bois Envelope 26 01 11 31 selected landscapes d'œuvre F 09-20/BOE / Acquisition Component 2: Investments de plantule pour le Single Stage - One 2020-10- 2020-12- 2020-11- 2021-04- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 12,500.00 14,002.23 Signé regarnissage des terrains de Envelope 05 10 11 09 selected landscapes reboisement 2019 - 2020 F 06-19/BOE / Acquisition Component 2: Investments d'engrais Single Stage - One En cours 2020-09- 2020-11- 2021-11- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 97,000.00 0.00 Lot 1: Engrais organique Envelope d'exécution 22 28 28 selected landscapes Lot 2: NPK et Urée F 10-20/BOE / Acquisition de bouture et de haie vive Component 2: Investments Single Stage - One En attente 2020-10- 2020-12- 2021-03- Lot 1: Stylosanthès COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,000.00 0.00 Envelope d'exécution 05 10 10 lot 2: Brachiaria selected landscapes Lot 3: Vétiver F 11-20/BOE / Acquisition de matériel végétal et de Component 2: Investments culture vivrière Single Stage - One En attente 2020-09- 2020-12- 2021-01- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 96,000.00 0.00 Lot 1: arachide, riz pluvial, Envelope d'exécution 27 02 01 selected landscapes Maïs Lot 2: Bouture de manioc F 12-20/BOE / Acquisition des citronniers Component 2: Investments Lot 01 : Site d'Ambolomoty Single Stage - One En attente 2020-10- 2020-12- 2021-02- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 95,000.00 0.00 Lot 02 : Site de Tsararano Envelope d'exécution 05 10 08 selected landscapes Lot 03: Site d'Anosinalainolona F 13-20/BOE / Achat d'orangiers : Component 2: Investments Lot 01 : Site d'Ambolomoty Single Stage - One En attente 2020-10- 2020-12- 2021-02- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,400.00 0.00 Lot 02 : Site de Tsararano Envelope d'exécution 05 10 08 selected landscapes Lot 03: Site d'Anosinalainolona F 03-19/ANJ / Achat d'intrants agricoles pour:les payasns formateurs, semenciers, adoptants et Component 2: Investments banques de semences: Lot Single Stage - One 2020-09- 2020-11- 2020-12- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 89,500.00 0.00 Annulé 01: Engrais minéral et Envelope 01 11 26 selected landscapes organique Lot 02: Semences rizicoles Lot 03: Matériels végétaux pour l'agroécologie et production fourragère F 03-20/ANJ / Acquisition Component 2: Investments de jeunes plants de culture En cours 2020-08- 2020-11- 2021-01- COFN / C1540 and capacity building in the A posteriori Demande de prix 22,150.00 0.00 de rente pour l'agroforesterie d'exécution 28 10 09 selected landscapes à Iazafo et Soanierana Ivongo F 04-19/SOF / Achat des Component 2: Investments Single Stage - One 2019-06- 2019-09- 2019-10- équipement agricole pour COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 36,600.00 0.00 Annulé Envelope 23 02 02 paysans leaders/adoptants. selected landscapes Page 5 F 05-19/ANJ / Acquisition Component 3: Project des produits d'entretien en Single Stage - One En attente 2020-10- 2020-12- 2021-01- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 43,530.00 0.00 03 années pour la CER Envelope d'exécution 05 10 09 and M&E Analanjirofo Component 2: Investments F 07-19/BOE / Acquisition Single Stage - One 2019-09- 2019-11- 2019-12- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 33,000.00 0.00 Annulé des jeunes plants. Envelope 24 30 30 selected landscapes F 08-20/SOF / Acquisition Component 2: Investments d'Engrais organique de type Single Stage - One En attente 2020-10- 2020-11- 2021-01- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 54,400.00 0.00 Guano pour le Paysage de Envelope d'exécution 05 27 11 selected landscapes Bealanana F 02-20/SOF / Acquisitions de semences certifiées de riz Component 2: Investments irrigué pour le Paysage de Single Stage - One En attente 2020-10- 2020-12- 2021-02- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 75,000.00 0.00 Bealanana : Envelope d'exécution 24 19 02 selected landscapes LOT 01: riz certifiées X-265 Lot 02 : riz certifiées MK-34 F 09-20/CN / Acquisition de Component 3: Project fournitures de bureau pour Single Stage - One En attente 2020-12- 2021-01- 2021-02- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 4,000.00 0.00 l'Unité de Gestion de Projet Envelope d'exécution 10 24 23 and M&E PADAP F 01-20/BOE / Acquisition Component 2: Investments Single Stage - One 2021-02- 2021-05- 2021-11- de semence pour la diffusion COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 2,200.00 0.00 Annulé Envelope 20 25 21 des paquets techniques selected landscapes agricoles F 3-20/BOE / Acquisition de Component 2: Investments tarare pour le centre Single Stage - One En attente 2020-06- 2020-09- 2020-11- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 21,900.00 0.00 multiplicateur de semence à Envelope d'exécution 06 01 30 selected landscapes Tsararano. F 22-20/SOF / Acquisition Component 2: Investments de dolomie agricole de Single Stage - One En attente 2020-12- 2021-01- 2021-03- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 64,000.00 0.00 redressement du sol pour le Envelope d'exécution 05 30 16 selected landscapes Paysage de Bealanana F 23-20/SOF / Acquisition Component 2: Investments d'intrants agricoles de Single Stage - One En attente 2020-12- 2021-01- 2021-03- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 89,000.00 0.00 synthèse (NPK et Urée) pour Envelope d'exécution 04 29 15 selected landscapes le Paysage de Bealanana F 24-20/SOF / Acquisition Component 2: Investments de matériels végétaux pour Single Stage - One En attente 2020-10- 2021-01- 2021-02- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,000.00 0.00 plante de couverture dans le Envelope d'exécution 29 03 17 selected landscapes Paysage de Bealanana F 25-20/SOF / Acquisition Component 2: Investments de Semences de Brachiaria Single Stage - One En attente 2020-12- 2021-02- 2021-03- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 95,000.00 0.00 ou de Stylosanthès dans le Envelope d'exécution 10 12 14 selected landscapes paysage de Bealanana. F 06-20/CN / Acquisition Component 3: Project Single Stage - One En attente 2020-11- 2021-01- 2021-02- des matériels de lavage à COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 1,500.00 0.00 Envelope d'exécution 15 14 13 haute pression du PADAP. and M&E Component 3: Project F 04-20/CN / Acquisition de Single Stage - One En attente 2020-11- 2021-01- 2021-02- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 2,250.00 0.00 7 coffres forts du PADAP. Envelope d'exécution 15 14 13 and M&E F 07-20/CN / Acquisition de Component 3: Project Single Stage - One En attente 2020-11- 2021-01- 2021-03- matériels informatiques du COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 3,000.00 0.00 Envelope d'exécution 07 16 17 PADAP: 9 stabilisateurs and M&E F 02-20/CN / Conception et fourniture de supports de Component 2: Investments Single Stage - One En attente 2021-03- 2021-05- 2021-06- communication pour le COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 9,500.00 0.00 Envelope d'exécution 03 16 15 PADAP (Flyers, banderôles, T- selected landscapes shirt, Polo, …) F 08-20/CN / Acquisition Component 3: Project Single Stage - One En attente 2020-11- 2021-01- 2021-02- des 09 vidéoprojecteurs avec COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 25,000.00 0.00 Envelope d'exécution 07 06 05 écran du PADAP. and M&E Component 3: Project F 03-19/BOE / Acquisition Single Stage - One En attente 2020-11- 2021-03- 2021-04- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 3,400.00 0.00 des fournitures de bureau Envelope d'exécution 30 02 01 and M&E F 02-20/ BOE / Acquisition Component 3: Project Single Stage - One En attente 2020-12- 2021-03- 2021-09- de consommables COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 2,000.00 0.00 Envelope d'exécution 03 09 05 informatiques pour 2 années and M&E F 04-19/BOE / Achat pneus Component 3: Project Single Stage - One En attente 2020-11- 2021-02- 2021-03- pou 2 années pour la CER COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 4,000.00 0.00 Envelope d'exécution 30 23 25 Boeny and M&E F 10-20/CN / Acquisition de réfrigérateurs solaires (RS) et kits de vaccination (KV): Lot 1: 2 RS et 2 KV pour le Component 2: Investments Single Stage - One En attente 2020-12- 2021-01- 2021-03- Paysage d’Andapa COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 17,500.00 0.00 Envelope d'exécution 07 27 13 Lot 2: 3 RS et 3 KV pour le selected landscapes Paysage de Bealalana Lot 3: 2 RS et 2 KV pour le paysage de Marovoay F 03-19/SAV / Acquisition Component 3: Project Single Stage - One En attente 2020-11- 2021-01- 2021-02- des produits d'entretien pour COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 3,130.00 0.00 Envelope d'exécution 30 12 11 la CER SAVA and M&E F 04-19/SAV / Acquisition Component 3: Project des consommables Single Stage - One En attente 2020-11- 2021-01- 2021-02- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 21,880.00 0.00 informatiques pour la CER Envelope d'exécution 28 10 09 and M&E SAVA F 02-19/SAV / Acquisition Component 3: Project Single Stage - One En attente 2020-11- 2021-01- 2021-02- des fournitures de bureau COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 21,880.00 0.00 Envelope d'exécution 30 12 11 pour la CER SAVA. and M&E F 05-20/SAV / Acquisition d'intrants agricoles repartis en quatre lots: Lot1 : Semences de base Component 2: Investments Lot2 : semences certifiées de Single Stage - One En attente 2020-12- 2021-02- 2021-03- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 34,000.00 0.00 riz irrigué Envelope d'exécution 05 08 10 selected landscapes Lot 3 : Engrais organique Lot 4 : Urée Lot 5 : Graines pour 56 sites de pépinières permanente. F 01-20/SAV / Acquisition des panneaux d'indication des sites dans le paysage Component 2: Investments Single Stage - One En attente 2020-11- 2021-02- 2021-03- d'Andapa, Région SAVA : COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 8,600.00 0.00 Envelope d'exécution 28 11 13 Lot 01: sites de reboisement selected landscapes Lot 02 : sites de parcelle de démonstration F 07-20/SAV / Acquisition pour les vétérinaires mandataires en vue d’améliorer la santé des Component 2: Investments animaux d’élevage au niveau Single Stage - One En attente 2020-12- 2021-02- 2021-03- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 5,000.00 0.00 du paysage d’Andapa : Envelope d'exécution 12 25 27 selected landscapes Lot 1 : 02 (deux) réfrigérateurs solaires Lot 2 : 02 (deux) kits de vaccination F 11-20/CN / Acquisition de 43 motos pour les régions d'intervention du Projet (dont : 7 motos pour les Component 2: Investments Single Stage - One En attente 2020-11- 2020-12- 2021-01- 2021-01- 2021-03- 2021-09- fédérations des AUEs, 24 COFN / C1540 and capacity building in the A posteriori Appel d'offres Limited 253,520.00 0.00 Envelope d'exécution 30 10 09 29 05 01 motos pour les Services selected landscapes techniques déconcentrées et 12 motos pour les nouveaux agent du Projet. F 12-20/CN / Acquisition de : Lot 1: 29 ordinateurs portable. Component 2: Investments Single Stage - One En attente 2020-12- 2021-02- 2021-03- Lot 2: 05 ordinateurs de COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 95,000.00 0.00 Envelope d'exécution 10 18 20 bureau avec 1 onduleur de selected landscapes chaque pour les fédérations des AUEs. Lot 3: 04 imprimante laser pour les fédérations des AUEs. F 13-20/CN / Acquisition de Component 2: Investments Single Stage - One En attente 2020-12- 2021-02- 2021-03- 12 GPS pour les Services COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 7,000.00 0.00 Envelope d'exécution 10 18 20 techniques déconcentrées. selected landscapes F 14-20/CN / Achat de Component 3: Project Produits d'entretien pour Single Stage - One En attente 2020-12- 2021-01- 2021-02- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 3,000.00 0.00 l'Unité de Gestion de Projet Envelope d'exécution 10 24 23 and M&E PADAP F 15-20/CN / Achat de Component 3: Project consommable informatiques Single Stage - One En attente 2020-12- 2021-01- 2021-02- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 20,500.00 0.00 pour l'Unité de Gestion de Envelope d'exécution 10 24 23 and M&E Projet PADAP F 01-21/ANJ / Acquisition d'Alambics et accessoires d'alambics pour les paysans Component 2: Investments Single Stage - One En attente 2021-01- 2021-03- 2021-09- pratiquants la distillation COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 46,060.00 0.00 Envelope d'exécution 07 23 19 d'essence de girofle dans les selected landscapes paysages d'Iazafo et de Soanierana Ivongo. NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Page 6 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UGP PADAP-70332-NC- RFQ / Service de transit pour dédouanement de matériels Component 3: Project Single Stage - One 2018-07- 2018-09- 2018-07- 2018-10- roulants (10 voitures et 20 IDA / 59790 Management Coordination A posteriori Demande de prix Open - National 57,000.00 34,129.26 Signé Envelope 24 04 30 04 motos), et service de mise en and M&E circulation des véhicules et moto du PADAP. C 03-20/CN / Service de Component 3: Project transit et douane pour le Single Stage - One 2020-03- 2020-04- 2020-05- COFN / C1540 Management Coordination A posteriori Demande de prix Open - National 5,500.00 0.00 Annulé dédouanement des matériels Envelope 08 17 17 and M&E roulants du PADAP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C 6-18/CN / Etude d'aménagement (APS-APD- Component 2: Investments Sélection fondée EIES-PAR-DAO-MGE) et 2018-04- 2018-02- 2018-02- 2018-05- 2018-03- 2018-06- 2018-04- 2018-07- 2018-05- 2018-07- 2018-05- 2018-08- 2018-10- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 62,500.00 51,882.50 Signé 2018-01-22 surveillance des travaux dans 19 06 28 11 30 12 14 02 04 24 28 29 25 selected landscapes coût le périmètre d'Andranomafana Mangindrano, région Sofia. C 4-18/CN / Etude de rehabilitation des infrasrtuctures Component 2: Investments Sélection fondée 2018-03- 2018-02- 2018-02- 2018-05- 2018-03- 2018-06- 2018-04- 2018-07- 2018-05- 2018-07- 2018-05- 2018-09- 2018-11- hydroagricoles (APS-APD- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 500,000.00 287,114.06 Signé 2018-01-22 27 06 28 10 30 12 14 02 04 27 28 03 24 EIES-PAR-DAO-MGE) et selected landscapes coût surveillance des travaux dans le périmètre de Iazafo, Région Analanjirofo C 5-18/CN / Etude de reconstruction du barrage et réfection des réseaux Component 2: Investments Sélection fondée hydroagricoles (APD-EIES- 2018-04- 2018-02- 2018-02- 2018-05- 2018-03- 2018-06- 2018-04- 2018-07- 2018-05- 2018-07- 2018-05- 2018-08- 2018-10- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 87,500.00 23,197.46 Signé 2018-01-22 PAR-DAO-MGE) et 19 06 28 10 30 12 14 13 04 24 28 31 25 selected landscapes coût surveillance des travaux dans le périmètre d'Anjohibe Ambatosia, Région Sofia. C 7-18/CN / Etude de réhabilitation de périmètre Component 2: Investments Sélection fondée irrigué (APD-EIES-PAR-DAO- 2018-04- 2018-02- 2018-02- 2018-05- 2018-03- 2018-06- 2018-04- 2018-07- 2018-05- 2018-07- 2018-05- 2018-09- 2018-11- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 125,000.00 29,974.84 Signé 2018-01-22 MGE) et surveillance des 19 06 28 10 30 12 14 13 04 24 28 10 24 selected landscapes coût travaux dans le périmètre de Bealanana I, région Sofia. C 8-18/CN / Etude d'aménagement (APS-APD- Component 2: Investments Sélection fondée EIES-PAR-DAO-MGE) pour la 2018-02- 2018-02- 2018-03- 2018-04- 2018-05- 2018-05- 2018-11- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 54,000.00 0.00 Annulé 2018-01-22 stabilisation des terrasse à 06 28 30 14 04 28 24 selected landscapes coût Bealanana et surveillance des travaux. Component 3: Project C 03-18/CN / Un cabinet Sélection au 2018-01- 2018-01- 2018-02- 2018-04- 2018-03- 2018-05- 2018-03- 2018-05- 2018-04- 2018-05- 2018-04- 2018-05- 2018-07- IDA / 59790 Management Coordination A posteriori Open - National 30,000.00 8,305.01 Signé 2018-01-15 d'audit financier du PADAP. moindre coût 23 31 17 17 19 17 29 18 09 25 29 28 28 and M&E C 04-17/CN / Études préparatoires du Projet Agriculture Durable par une Approche Paysage (PADAP) Sélection fondée Component 1: Information 2017-06- 2018-02- 2018-03- 2017-09- 2018-04- 2017-10- 2018-05- 2017-11- 2018-05- 2018-02- 2018-06- 2018-02- 2018-09- Périmètre d'Iazafo dans le IDA / V0430 A posteriori sur la qualité et le Open - National 200,000.00 224,827.15 Signé 2018-01-24 and planning 28 14 30 28 27 30 07 08 21 02 14 05 12 district de Vavatenina et dans coût le district de Soanierana Ivongo, région ANALANJIROFO. C 02-17/CN / Études préparatoires du Projet Sélection fondée Agriculture Durable par une Component 1: Information 2017-06- 2018-02- 2018-03- 2017-09- 2018-04- 2017-10- 2018-05- 2017-11- 2018-05- 2017-12- 2018-06- 2018-02- 2018-09- IDA / V0430 A posteriori sur la qualité et le Open - National 150,000.00 156,130.05 Signé 2018-01-24 Approche Paysage (PADAP) and planning 28 14 30 28 27 30 07 08 21 07 14 09 12 coût dans le district de Marovoay, région BOENY C 01-17/CN / Études préparatoires du Projet Sélection fondée Agriculture Durable par une Component 1: Information 2017-06- 2018-02- 2018-03- 2017-09- 2018-04- 2017-10- 2018-05- 2017-11- 2018-05- 2018-02- 2018-06- 2018-03- 2018-09- IDA / V0430 A posteriori sur la qualité et le Open - National 150,000.00 234,393.50 Signé 2018-01-24 Approche Paysage (PADAP) and planning 28 14 30 28 27 30 07 08 21 06 14 05 12 coût dans le district d'Andapa, région SAVA C 01-18/CN / Développement d'un guide Component 1: Information Sélection fondée Open - 2018-05- 2018-05- 2018-05- 2018-07- 2018-08- 2018-08- 2018-09- 2018-09- 2018-12- IDA / 59790 A posteriori 100,000.00 0.00 Annulé 2018-04-30 pour l'élaboration des PAGDP and planning sur la qualité International 03 10 15 13 12 22 06 30 29 (Firme international) C 18-18/CN / Service de consultant pour Component 2: Investments Sélection fondée 2018-09- 2018-05- 2018-06- 2019-12- 2018-07- 2020-01- 2018-07- 2020-01- 2018-09- 2020-02- 2018-09- 2020-04- 2019-04- l'encadrement, formation et IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 50,000.00 22,725.03 Résilié 2018-05-09 18 30 19 02 19 03 29 20 02 04 26 01 24 suivi des agents communaux selected landscapes coût pour l'approche LIFE C 24-18/CN / Etude de traitement des points critiques de la RN31 route Component 2: Investments Sélection fondée En cours 2018-11- 2018-06- 2018-06- 2018-12- 2018-07- 2019-01- 2018-08- 2019-02- 2018-09- 2019-02- 2018-10- 2019-03- 2019-08- non revêtue reliant Bealanana- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 400,000.00 124,815.95 2018-05-14 d'exécution 06 04 28 27 28 28 17 15 21 25 26 01 22 Ambatoriha d'une longueur selected landscapes coût de 32 km - Contrôle et surveillance C 12-18/CN / Etude et Component 3: Project Sélection fondée contrôle-surveillance sur Les 2018-09- 2018-06- 2018-06- 2018-10- 2018-07- 2018-12- 2018-08- 2019-02- 2018-09- 2019-02- 2018-10- 2019-02- 2019-02- IDA / 59790 Management Coordination A posteriori sur la qualité et le Open - National 21,000.00 24,935.50 Signé 2018-05-14 travaux d'extension et de 24 04 28 30 28 03 07 12 11 15 16 25 13 and M&E coût Réhabilitation locaux Sofia C 15-18/CN / Etude et Component 3: Project Sélection fondée contrôle-surveillance sur Les 2018-05- 2018-06- 2018-06- 2018-06- 2018-07- 2018-07- 2018-08- 2018-08- 2018-09- 2018-10- 2018-10- 2018-11- 2019-02- IDA / 59790 Management Coordination A posteriori sur la qualité et le Open - National 10,500.00 3,669.43 Signé 2018-05-14 travaux d'extension et de 14 04 28 15 28 16 07 31 11 04 16 14 13 and M&E coût Réhabilitation locaux Sava C 37-18/CN / Inventaire : surfaces pâturables, espèces fourragères naturelles, points d'abreuvement, Sélection fondée infrastructures d'élevage Component 1: Information En cours 2018-09- 2018-08- 2018-08- 2018-11- 2018-09- 2018-09- 2018-10- 2018-12- 2019-04- IDA / 59790 A posteriori sur la qualité et le Open - National 125,000.00 0.00 2018-07-12 existantes dans la zone. and planning d'exécution 05 02 16 26 15 25 30 04 03 coût Lot 01 : de Bealanana. Lot 02 : d'Andapa. Lot 03 : de Marovoay Lot 04 : d'Iazafo C 01BIS-18/CN / Sélection fondée Développement d'un guide Component 1: Information sur les Open - 2018-05- 2018-07- 2018-08- 2018-08- 2018-11- IDA / 59790 A posteriori 100,000.00 0.00 Annulé 2018-05-03 pour l'élaboration des PAGDP and planning qualifications des International 24 07 06 30 28 (Firme international) consultants C 41-18/CN / Inventaire des périmètres hydroagricoles Sélection fondée Component 1: Information En cours 2018-09- 2018-10- 2018-11- 2018-11- 2018-12- 2018-12- 2019-01- 2019-02- 2019-06- repartis en quatre (04) lots IDA / 59790 A posteriori sur la qualité et le Open - National 230,000.00 0.00 2018-08-30 and planning d'exécution 04 14 17 21 17 27 20 24 24 pour les régions : Sava, coût Boeny, Sofia et Analanjirofo. C 01-18/BOE / Recrutement d'une ONG chargée du renforcement de capacités et Component 2: Investments Sélection fondée de l'appui des paysans 2018-11- 2018-12- 2019-01- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-08- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 23,500.00 0.00 Annulé 2018-11-20 pilotes sur les paquets 14 11 24 03 23 05 09 14 12 selected landscapes coût techniques de la production fourragère, agroécologie, agroforesterie et arboriculture C 02-18/BOE / Recrutement d'une ONG ou Association Component 2: Investments Sélection fondée chargée du diagnostic et 2018-12- 2018-12- 2019-01- 2019-02- 2019-02- 2019-03- 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- 2019-10- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 5,200.00 5,702.82 Achevé 2018-11-20 redynamisation des 03 05 11 24 06 23 07 05 20 09 12 14 07 12 15 selected landscapes coût Coopératives de producteurs de semences à Tsararano C 05-18/BOE / Etude spécifique de protection des Component 2: Investments Sélection fondée 2019-07- 2018-12- 2018-12- 2020-01- 2019-01- 2020-02- 2019-02- 2020-05- 2019-03- 2020-05- 2019-03- 2020-07- 2019-04- lavaka au niveau des SBV IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 47,000.00 77,973.66 Signé 2018-11-20 08 05 27 28 26 12 10 04 02 19 26 27 25 Ambarindahy, Androtra, selected landscapes coût Belafrika C 1-18/SAV / Amélioration de la disponibilité de Component 2: Investments Sélection fondée 2019-01- 2018-12- 2019-02- 2019-03- 2019-03- 2019-04- 2019-03- 2019-05- 2019-04- 2019-06- 2019-05- 2019-06- 2019-07- 2019-10- semences améliorées et IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 7,910.00 15,635.97 Achevé 2018-11-30 07 21 03 26 05 25 15 30 19 14 24 21 08 29 certifiées dans le paysage selected landscapes coût d'Andapa C 5-18/ANJ / Etude de rehabilitation des infrasrtuctures Component 2: Investments Sélection fondée hydroagricoles (APS-APD- 2019-01- 2018-12- 2019-01- 2019-01- 2019-02- 2019-02- 2019-02- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2020-08- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 79,200.00 46,026.84 Signé 2018-11-30 EIES-PAR-DAO-MGE) et 10 15 06 24 05 25 20 01 12 13 05 27 17 selected landscapes coût surveillance des travaux des périmètres Marovinanto et Sahafary dans le paysage Soanierana Ivongo. C 02-18/SAV / Amélioration de la disponibilité de Component 2: Investments Sélection fondée 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-07- semences améliorées et IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 7,910.00 0.00 Annulé 2018-11-20 11 24 23 10 14 19 03 certifiées dans le paysage selected landscapes coût d'Andapa C 01-19/SAV / Études de réhabilitation du barrage souple avec avant canal rive droite et réfection des Component 2: Investments Sélection fondée réseaux hydroagricoles, 2018-12- 2019-02- 2019-03- 2019-01- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- 2019-05- 2019-05- 2020-12- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 45,500.00 67,478.28 Signé 2019-01-30 digue de protection et pistes 11 14 02 31 01 04 15 09 27 17 17 17 12 selected landscapes coût (APS-APD-EIES-PAR-DAO- MGE) et contrôle - surveillance du périmètre Ambalafary sur 203 ha et Analambe Est Page 7 C 02-19/SAV / Études de réhabilitation du barrage en dur avec avant canal rive droite et renovation des réseaux hydroagricoles et Component 2: Investments Sélection fondée 2019-01- 2019-02- 2019-03- 2019-01- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-05- 2019-05- 2019-05- 2020-12- pistes (APS-APD-EIES-PAR- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 72,220.00 37,620.86 Signé 2019-01-30 18 14 02 31 01 04 15 09 27 02 17 17 12 DAO-MGE) et contrôle - selected landscapes coût surveillance du périmètre Ambodivitagnona sur 310ha, CR Ambalamanasy II, district d'Andap C 04-19/SAV / Études de réhabilitation d'un barrage avec avant canal rive gauche et de réfection des réseaux Component 2: Investments Sélection fondée hydroagricoles et les 2019-01- 2019-02- 2019-03- 2019-01- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-05- 2019-05- 2019-05- 2020-12- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 63,500.00 64,941.59 Signé 2019-01-30 ouvrages connexes du 25 14 02 31 01 04 15 09 27 03 17 17 12 selected landscapes coût grappe (APS-APD-EIES-PAR- DAO-MGE) et contrôle - surveillance du Périmètre Antanimbaribe et périmètre d'Ambatoharanan C 05-19/SAV / Études de réhabilitation du barrage en dur avec avant canal rive droite et réfection des Component 2: Investments Sélection fondée réseaux hydroagricoles (APS- 2019-01- 2019-02- 2019-03- 2019-01- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-05- 2019-05- 2019-05- 2020-12- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 94,470.00 45,623.17 Signé 2019-01-30 APD-EIES-PAR-DAO-MGE) et 25 14 02 31 01 04 15 09 27 03 17 17 12 selected landscapes coût contrôle - surveillance du périmètre Tanandava sur 399ha CR Tanandava, district d'Andapa C 08-19/SAV / Etude technique et maitrise d'œuvre de traitements et Component 2: Investments Sélection fondée stabilisation des « lavaka » 2019-11- 2019-03- 2019-04- 2019-12- 2019-05- 2020-01- 2019-05- 2020-03- 2019-06- 2020-05- 2019-07- 2020-06- 2020-02- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 16,510.00 23,156.10 Signé 2019-02-11 dans les anciennes zones 04 13 06 12 06 13 26 05 19 07 09 19 04 selected landscapes coût d'exploitation minières à Ankarierabe, Commune Rurale Bealampona, District d'Andapa C 06-19/SAV / Création et mise en place des huit (08) Component 2: Investments Sélection fondée 2019-09- 2019-03- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-06- 2019-09- 2019-07- 2019-10- 2020-07- nouveaux AUE sur les IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 40,500.00 13,786.27 Signé 2019-02-12 13 14 07 29 07 28 27 17 20 16 10 02 04 périmètres nouvellement à selected landscapes coût réhabiliter C 03-19/ANJ / Etude de rehabilitation des infrasrtuctures hydroagricoles (APS-APD- Component 2: Investments Sélection fondée 2019-02- 2019-03- 2019-04- 2019-02- 2019-05- 2019-03- 2019-05- 2019-03- 2019-06- 2019-03- 2019-07- 2019-04- 2021-02- 2019-04- EIES-PAR-DAO-MGE) et IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 207,200.00 52,228.62 Achevé 2019-02-20 08 22 13 14 13 18 28 22 17 28 11 23 20 24 Contrôle-surveillance des selected landscapes coût travaux dans les périmètres de Vohijiny et Ampasimbola- District de Soanierana Ivongo C 04-19/ANJ / Recrutement de firme pour la capitalisation des acquis sur Component 2: Investments Sélection fondée les paquets techniques 2019-02- 2019-03- 2019-04- 2019-06- 2019-05- 2019-07- 2019-05- 2019-08- 2019-06- 2019-08- 2019-07- 2019-09- 2022-10- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 55,500.00 65,328.45 Signé 2019-02-20 agroécologique, 08 22 13 06 13 08 28 13 17 23 11 18 23 selected landscapes coût agroforesterie, arbiriculture et culture fourragère dans les paysages d'Iazafo et Soanierana Ivongo C 01-19/BOE / Recrutement Component 2: Investments Sélection fondée d'une ONG chargée des En cours 2019-02- 2019-03- 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-06- 2019-07- 2019-10- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 16,090.00 11,039.03 2019-02-24 études de diagnostic des d'exécution 18 26 19 26 19 28 03 12 02 18 27 10 selected landscapes coût AUE dans les secteurs 04, 05 et 06 C 02-19/BOE / Recrutement d'une ONG chargée de l'étude de stabilisation des Component 2: Investments Sélection fondée 2019-02- 2019-03- 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-06- 2019-07- 2019-06- 2019-10- zones d'érosion et protection COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 10,000.00 7,934.21 Signé 2019-02-24 18 26 17 15 17 14 01 29 21 06 15 21 23 des réseaux hydroagricoles selected landscapes coût le long du CPRD et CSPC Ambolomoty (ONG) C 03-19/BOE / Etudes, contrôle et surveillance des Component 2: Investments Sélection fondée 2018-12- 2019-03- 2019-04- 2019-02- 2019-05- 2019-03- 2019-06- 2019-04- 2019-06- 2019-04- 2019-07- 2019-05- 2021-01- travaux de curage du drain COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 26,000.00 20,616.05 Signé 2019-02-24 18 26 17 19 17 19 01 12 21 24 15 08 25 de ceinture et reprofilage du selected landscapes coût drain naturel Manompo C 04-19/BOE / Etudes des Component 2: Investments Sélection fondée travaux de reprofilage des 2019-03- 2019-03- 2019-04- 2019-02- 2019-05- 2019-04- 2019-06- 2019-04- 2019-06- 2019-04- 2019-07- 2019-06- 2021-01- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 52,500.00 69,283.53 Signé 2019-02-24 réseaux de drainage des 03 26 17 28 17 01 01 09 21 30 15 06 25 selected landscapes coût secteurs 04, 05 et 06 C 16-18/CN / Analyse des Sélection fondée problématiques d'entretien Component 1: Information sur les 2018-10- 2018-08- 2018-09- 2018-11- 2018-10- 2018-11- 2019-02- des ouvrages hydroagricoles, IDA / 59790 A posteriori Open - National 30,000.00 0.00 Annulé 2018-06-28 and planning qualifications des 08 07 10 30 20 13 21 proposition d'instruments et consultants stratégies C 01-19/CN / Élaboration du Plans d'Aménagement et de Gestion Durable des Paysages (PAGDP) du PADAP Sélection fondée pour le : Component 1: Information Open - 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-07- 2019-08- 2019-07- 2019-08- 2019-08- 2019-10- 2019-09- 2020-02- COFN / C1540 A posteriori sur la qualité et le 967,463.00 1,014,833.73 Signé 2019-03-29 Lot 01 : Paysage d'Andapa and planning International 01 13 02 25 17 08 01 19 31 16 01 25 28 coût Lot 02 : Paysage de Bealalana Lot 03 : Paysage de Marovoay Lot 04 : Paysage d'Iazafo Lot 05 : Paysage de Soanierana Ivongo C 29-18/CN / Développement d'une Sélection fondée Component 1: Information 2018-09- 2018-10- 2018-11- 2018-12- 2018-12- 2019-01- 2019-02- 2019-06- méthodologie d'inventaire IDA / 59790 A posteriori sur la qualité et le Open - National 25,000.00 0.00 Annulé 2018-08-30 and planning 26 14 17 17 27 20 24 24 des ressources en eau et coût estimation des besoins C 04 BIS-18/BOE / Etudes et contrôle-surveillance des travaux de regabaritage des Component 2: Investments Sélection fondée 2019-03- 2018-12- 2019-02- 2018-12- 2019-03- 2019-01- 2019-04- 2019-02- 2019-05- 2019-02- 2019-06- 2019-03- 2020-06- cours d'eau exutoire du COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 145,000.00 90,071.60 Signé 2018-11-21 03 21 03 07 05 07 04 20 09 25 13 22 12 drainage de périmètre irrigué selected landscapes coût des secteurs 4, 5 et 6 de la plaine de Marovoay. C 04-18/BOE / Etudes de Réhabilitation des cours Component 2: Investments Sélection fondée 2018-11- 2018-12- 2019-01- 2019-02- 2019-02- 2019-03- 2019-04- 2019-12- d'eau exutoire du drainage IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 62,500.00 0.00 Annulé 2018-11-20 21 11 04 03 13 20 24 10 (Rivière Marovoay Aval, selected landscapes coût Rivière Karambo Aval) MG-UGP PADAP-117841-CS- QCBS / Agence de Component 3: Project Sélection fondée communication pour la 2019-04- 2019-07- 2019-08- 2019-05- 2019-09- 2019-10- 2019-10- 2019-11- 2019-11- 2019-12- 2019-11- 2019-12- 2020-01- COFN / C1540 Management Coordination A posteriori sur la qualité et le Open - National 28,500.00 20,587.41 Signé 2019-06-17 création, animation et 10 08 21 23 20 02 10 06 03 03 27 27 26 and M&E coût l'hébergement du site web du PADAP. MG-UGP PADAP-118799-CS- LCS / Recrutement d'un Component 3: Project Sélection au 2019-06- 2019-06- 2019-06- 2019-08- 2019-07- 2019-09- 2019-08- 2019-10- 2019-08- 2019-10- 2019-10- 2019-12- 2020-01- cabinet pour l'audit externe COFN / C1540 Management Coordination A posteriori Open - National 75,000.00 17,544.75 Signé 2019-06-20 moindre coût 27 20 22 29 22 30 06 04 21 21 04 27 02 des trois (03) exercices du and M&E PADAP : 2019, 2020 et 2021. C 01 BIS-18/BOE / Recrutement d'une ONG chargée du renforcement de capacités et de l'appui des Component 2: Investments Sélection fondée 2018-10- 2018-12- 2019-01- 2018-12- 2019-02- 2019-01- 2019-03- 2019-01- 2019-04- 2019-01- 2019-05- 2019-02- 2020-05- paysans pilotes sur les COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 70,500.00 49,883.77 Signé 2018-11-14 08 05 18 03 15 03 17 24 21 31 26 11 25 paquets techniques de la selected landscapes coût production fourragère, agroécologie, agroforesterie et arboriculture C 03-19/SAV / Etudes APS- APD-EIES-PAR-MGE-DAO- assistance passation de marché et contrôle- surveillance des travaux Component 2: Investments Sélection fondée 2019-01- 2019-02- 2019-03- 2019-01- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- 2019-05- 2019-05- 2020-12- reconstruction des deux IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 47,000.00 46,114.62 Signé 2019-01-30 25 14 02 31 01 04 15 09 27 19 17 17 12 barrages avec avant-canaux selected landscapes coût rive gauche & droite et des réseaux hydroagricoles d'Antsahameloka pour les PI Ambodiala et Andalamena. C 16 BIS-18/CN / Analyse des problématiques Component 2: Investments Sélection fondée d’entretien des ouvrages 2018-11- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-08- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 30,000.00 0.00 Annulé 2018-10-08 hydroagricoles à 07 21 20 19 26 30 08 selected landscapes coût Madagascar, proposition d’instrument et stratégies C 07-19/SAV / Mise en place des douze (12) Component 2: Investments Sélection fondée pépinières communautaires 2019-04- 2019-03- 2019-04- 2019-05- 2019-06- 2019-06- 2019-07- 2020-03- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 37,490.00 0.00 Annulé 2019-02-20 au niveau des villages et des 12 22 15 15 04 28 18 14 selected landscapes coût COBAS autour des aires protegées de la cuvette d'Andapa C 07-20/SOF / Contrôle et Surveillance des Travaux de Component 2: Investments Sélection fondée En cours 2020-04- 2020-03- 2020-04- 2020-04- 2020-05- 2020-06- 2020-06- 2020-07- 2020-06- 2020-08- 2020-07- 2020-08- réhabilitation du Périmètre COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 24,000.00 13,580.72 2020-02-28 d'exécution 02 09 02 30 02 02 01 21 26 01 21 05 d'Anjohibe Ambatosia dans selected landscapes coût le Paysage de Bealanana C 02-20/SAV / Etude de faisabilité, mise en place et opérationnalisation des Component 2: Investments Sélection fondée En cours 2020-05- 2020-03- 2020-04- 2020-09- 2020-05- 2020-10- 2020-06- 2020-07- 2020-08- 2020-10- comités de gestion des COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 10,500.00 0.00 2020-02-28 d'exécution 29 13 26 15 26 19 15 19 23 22 matériels agricoles dans le selected landscapes coût paysage d'Andapa, Région SAVA. C 04-19/SOF / Études, contrôle et surveillance de Component 2: Investments Sélection fondée 2019-10- 2020-03- 2020-04- 2019-10- 2020-05- 2019-11- 2020-05- 2020-01- 2020-06- 2020-02- 2020-07- 2020-03- 2020-12- travaux d'aménagement du COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 41,000.00 18,719.00 Signé 2020-02-20 04 01 05 04 05 06 25 23 24 28 24 18 21 périmètre de Doany,Paysage selected landscapes coût de Bealanana Page 8 C 01-20/CN / Service de consultant pour l'évaluation à Component 3: Project Sélection fondée En cours 2020-10- 2020-03- 2020-04- 2020-05- 2020-06- 2020-06- 2020-07- 2020-10- mi-parcours du Projet COFN / C1540 Management Coordination A posteriori sur la qualité et le Open - National 18,750.00 0.00 2020-02-28 d'exécution 16 29 20 20 04 24 18 16 Agriculture Durable par une and M&E coût Approche Paysage T 1-18/SOF / Travaux de stabilisation biologique des Sélection fondée Component 1: Information 2018-12- 2019-01- 2019-02- 2019-02- 2019-03- 2019-04- 2019-05- lavaka avec mise en place de IDA / 59790 A posteriori sur la qualité et le Open - National 9,800.00 0.00 Annulé 2018-11-30 and planning 15 06 05 20 12 05 05 fascines dans le sous coût paysage d'Ambatoriha C 01-19/SOF / ONG ou Component 2: Investments Sélection fondée Association pour le En attente 2020-05- 2020-06- 2020-07- 2020-08- 2020-09- 2020-10- 2021-01- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 32,120.00 0.00 2020-04-30 renouvellement des contrats d'exécution 30 29 29 18 21 20 28 selected landscapes coût de transfert gestion. MG-UGP PADAP-118793-CS- QCBS / Inventaire forestier et écologique : - Lot 01: dans le paysage d'Andapa Sélection fondée Component 1: Information 2019-07- 2019-08- 2019-09- 2019-09- 2019-10- 2019-11- 2020-03- - Lot 02 : dans le paysage de COFN / C1540 A posteriori sur la qualité et le Open - National 365,000.00 0.00 Annulé 2019-06-12 and planning 12 11 10 25 15 20 19 Bealalana coût - Lot 03 : dans le paysage de Marovoay - Lot 04 : dans le paysage Sonierana Ivongo et Iazafo MG-UGP PADAP-117852-CS- QCBS / Un cabinet spécialisé Component 3: Project Sélection fondée en communication en vue de 2019-06- 2019-07- 2019-08- 2019-09- 2019-09- 2019-10- 2019-12- COFN / C1540 Management Coordination A posteriori sur la qualité et le Open - National 22,900.00 0.00 Annulé 2019-06-03 la réalisation du film 24 18 17 06 30 24 23 and M&E coût documentaire sur le PADAP et le PAGDP. C 09-18/ANJ / Recrutement d'agence d'encadrement pour la communauté locale faisant Component 2: Investments Sélection fondée la création pépinière et la 2019-11- 2019-12- 2020-01- 2020-01- 2020-04- 2020-05- 2022-05- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 85,000.00 0.00 Annulé 2019-10-16 Plantation d'espèces 15 07 06 21 01 08 08 selected landscapes coût pérennes par les agro forêts et les espèces forestières à Iazafo et Soanierana Ivongo. C 06-19/ANJ / Mise en place/Actualisation de base Component 2: Investments Sélection fondée des données sur les 2019-05- 2019-06- 2019-07- 2019-08- 2019-08- 2019-09- 2019-12- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 37,500.00 0.00 Annulé 2019-04-30 référentiels technico 30 21 21 05 25 18 27 selected landscapes coût financiers des filières porteuses régionales C 02-19/ANJ / Formation de tous les membres des AUEs Component 2: Investments Sélection fondée 2019-09- 2019-06- 2019-07- 2019-08- 2019-09- 2019-10- 2019-10- 2020-01- sur la gestion des réseaux IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 56,100.00 0.00 Annulé 2019-05-31 02 30 24 23 07 06 31 29 transférables selected landscapes coût (Entretien/Maintenance) C 03-20/BOE / Diagnostic des banques de semences communautaires à Component 2: Investments Sélection fondée Madagascar et En cours 2020-02- 2020-06- 2020-08- 2020-05- 2020-08- 2020-06- 2020-09- 2020-06- 2020-10- 2020-11- 2021-08- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 20,000.00 0.00 2020-05-26 redynamisation de la banque d'exécution 10 10 01 15 31 15 20 30 20 23 23 selected landscapes coût de semence communautaire à Tsararano, district de Marovoay, Région Boeny C 01-20/BOE / Recrutement d'ONG/Association pour Component 2: Investments Sélection fondée En attente 2020-12- 2021-01- 2021-02- 2021-03- 2021-04- 2021-05- 2021-08- l'instauration et la COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 2,000.00 0.00 2020-12-02 d'exécution 22 28 27 19 20 22 21 formalisation de comités de selected landscapes coût gestion de matériels agricoles C 09-20/SOF / Recrutement d'une ONG ou Association pour l'Instauration et Formalisation des Comités Component 2: Investments Sélection fondée de Gestion des matériels En attente 2020-10- 2020-12- 2021-01- 2021-01- 2021-02- 2021-03- 2021-07- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 9,500.00 0.00 2020-09-30 agricoles : d'exécution 30 09 08 23 17 14 12 selected landscapes coût Lot 01 : dans le périmètre de Mangindrano Lot 02 : dans le périmètre de Bealanana C 03-19/SOF / Etudes et contrôle et surveillance de Component 2: Investments Sélection fondée 2021-03- 2021-04- 2021-05- 2021-06- 2021-06- 2021-07- 2022-11- travaux de construction du COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 27,810.00 0.00 Annulé 2021-02-25 27 18 18 02 22 16 18 centre de multiplication de selected landscapes coût semences à Betainkankana C 08-20/SOF / étude de faisabilité de la réouverture Component 2: Investments Sélection fondée du centre de sélection 2020-03- 2020-05- 2020-06- 2020-06- 2020-07- 2020-08- 2020-11- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 52,000.00 0.00 Annulé 2020-02-28 variétale et de multiplication 29 08 07 22 12 06 04 selected landscapes coût de semences Betaikankana dans le Paysage de Bealanana C 02-19/SOF / Élaboration Component 2: Investments Sélection fondée En attente 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- 2021-03- 2021-06- d'un cadre incitatif (Contrat COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 56,250.00 0.00 2020-09-30 d'exécution 30 23 23 07 05 02 10 Plan Pluriannuel) par AUE selected landscapes coût C 05-20/SOF / Etudes, mise en place et accompagnement d’une Structure de gestion Component 2: Investments Sélection fondée En attente 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- 2021-03- 2021-07- adaptée pour l’axe routier COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 245,000.00 0.00 2020-09-30 d'exécution 15 29 29 28 17 14 12 Bealanana – Ambatoriha (RIP selected landscapes coût 117) dans le district de Bealanana, région Sofia C 01-19/ANJ / Élaboration Component 2: Investments Sélection fondée d'un cadre incitatif (contrat En cours 2020-09- 2020-09- 2020-10- 2020-11- 2020-11- 2020-12- 2021-01- 2021-04- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 82,820.00 0.00 2020-08-19 plan pluriannuel) par AUE d'exécution 02 18 12 11 26 25 19 19 selected landscapes coût Iazafo et Soanierana Ivongo. C 02-20/CN / Service de consultant pour le Component 3: Project Sélection fondée développement d'un logiciel En cours 2020-08- 2020-08- 2020-10- 2020-11- 2020-11- 2020-12- 2021-01- 2022-01- COFN / C1540 Management Coordination A posteriori sur la qualité et le Open - National 25,000.00 0.00 2020-07-30 pour le suivi-évaluation du d'exécution 28 20 03 02 22 16 09 04 and M&E coût Projet Agriculture Durable par une Approche Paysage C 04-20/CN / Service de Consultant pour la caractérisation des Component 2: Investments Sélection fondée En attente 2020-08- 2020-10- 2020-11- 2020-11- 2020-12- 2021-01- 2021-04- ressources en eau et COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 351,300.00 0.00 2020-07-30 d'exécution 29 02 01 21 26 30 30 estimation des besoins dans selected landscapes coût les 5 paysages d'intervention du PADAP (5 lots) C 30-20/SOF / Recrutement d'un Bureau d'études pour la Component 2: Investments Sélection fondée réalisation d'études, contrôle En attente 2020-10- 2020-12- 2021-01- 2021-01- 2021-03- 2021-04- 2022-04- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 66,500.00 0.00 2020-09-30 et surveillance des travaux d'exécution 21 04 01 31 07 11 11 selected landscapes coût des travaux d'aménagement PI Beandrarezona (567 ha) C 05/19/SOF / Etudes et Component 2: Investments Sélection fondée contrôle et surveillance de 2019-07- 2019-06- 2019-07- 2019-10- 2019-08- 2020-01- 2019-09- 2020-02- 2019-09- 2020-06- 2019-10- 2019-12- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 58,590.00 0.00 Annulé 2019-05-30 travaux de stabilisation de 08 29 21 21 20 22 04 21 24 02 18 17 selected landscapes coût lavaka à Bealanana C 01-20/SAV / Elaboration contrat plan pluriannuel et Component 2: Investments Sélection fondée Accompagnement 2020-08- 2020-09- 2020-10- 2020-10- 2020-11- 2020-12- 2022-06- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 29,690.00 0.00 Annulé 2020-08-31 (Encadrement et Suivi) des 31 10 11 21 25 30 23 selected landscapes coût AUEs sur la mise en œuvre des Contrat Plan C 21-20/BOE / Firme pour les études, contrôle et surveillance des travaux de Component 2: Investments Sélection fondée En attente 2020-10- 2020-12- 2021-01- 2021-02- 2021-03- 2021-04- 2022-04- stabilisation des bassins COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 100,000.00 0.00 2020-10-07 d'exécution 28 11 08 07 14 18 18 versants des carneaux de selected landscapes coût périmètre de Marovoay secteur 4, 5 et 6. C 34-20/SOF / Recrutement d'une firme pour l'étude de faisabilité et la mise en place de Comités de gestion des Component 2: Investments Sélection fondée En attente 2020-09- 2020-10- 2020-11- 2020-12- 2020-12- 2021-01- 2021-04- matériels agricoles dans les COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 12,500.00 0.00 2020-09-15 d'exécution 25 25 24 08 28 17 17 périmètres d'Anjohibe, de selected landscapes coût Bealanana I et d'Andranomafana dans le paysage de Bealanana C 04-20/ANJ / Recrutement de firme pour l'instauration et la formalisation de neuf Component 2: Investments Sélection fondée En attente 2020-09- 2020-10- 2020-11- 2020-11- 2020-12- 2021-01- 2021-04- (09) comités de gestion des COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 12,000.00 0.00 2020-09-10 d'exécution 28 18 17 27 17 06 06 matériels agricole dans le selected landscapes coût paysage d'Iazafo et Soanierana Ivongo C 02-20/ANJ / Etudes et Contrôle-Surveillance des travaux de réhabilitation des périmètres dans le district de Component 2: Investments Sélection fondée En attente 2020-10- 2020-12- 2021-01- 2021-01- 2021-02- 2021-04- 2022-04- Soanierana Ivongo COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 91,000.00 0.00 2020-09-30 d'exécution 30 03 02 22 26 02 02 - Lot 01: PI d'Antanetilava et selected landscapes coût Vohilava - Lot 02: PI de Diavolamaso, Ambodiboanara et Sahondrana C 03-20/SOF / Recrutement d'une ONG ou association en vue de l’Élaboration des schémas d'aménagement Component 2: Investments Sélection fondée communaux (SAC) dans la En attente 2020-06- 2020-08- 2020-08- 2020-09- 2020-11- 2020-12- 2021-12- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 252,000.00 0.00 2020-05-29 district de Bealalana repartis d'exécution 19 02 30 29 03 08 08 selected landscapes coût en 03 lots: Lot 01: 06 communes Lot 02 : 05 communes Lot 03: 03 communes Page 9 C 06-20/SOF / Etude, Contrôle et surveillance des Component 2: Investments Sélection fondée travaux de réhabilitation 2020-09- 2020-11- 2020-12- 2020-12- 2021-01- 2021-02- 2021-06- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 187,500.00 0.00 Annulé 2020-08-31 (APD-EIES-PAR-DAO-MGE) 30 04 04 24 18 23 23 selected landscapes coût du Périmètre de Beandrarezona dans le paysage de Bealanana C 05-19/BOE / Recrutement d'une firme chargée de la redynamisation et à Component 2: Investments Sélection fondée En attente 2020-10- 2020-12- 2021-01- 2021-01- 2021-02- 2021-03- 2022-01- l'élaboration des contrats- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 95,000.00 0.00 2020-10-15 d'exécution 31 05 04 24 23 24 21 plans pluri-annuels des AUE selected landscapes coût dans les secteurs 4-5-6 de Marovoay C 04-20/BOE / Recrutement Component 2: Investments Sélection fondée d'une firme pour l'appui, 2020-10- 2020-11- 2020-12- 2020-12- 2021-01- 2021-02- 2022-02- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 125,000.00 0.00 Annulé 2020-09-18 encadrement et réalisation 03 08 09 29 31 25 25 selected landscapes coût des actions de reboisement C 06-19/BOE / Recrutement d'une ONG ou Association pour l'opérationnalisation du Component 2: Investments Sélection fondée En attente 2020-06- 2020-07- 2020-08- 2020-08- 2020-09- 2020-10- 2021-05- DINA Régionale et la mise en COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 55,000.00 0.00 2020-05-12 d'exécution 01 06 05 25 24 19 27 œuvre des plans d'action selected landscapes coût contre les feux de brousses, dans le paysage de Marovoay C 01-20/ANJ / Elaboration (PCD/SAC) au niveau des Component 2: Investments Sélection fondée En attente 2020-10- 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-06- communes dans les COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 33,140.00 0.00 2020-09-22 d'exécution 22 01 31 20 19 20 18 paysages d'intervention du selected landscapes coût PADAP CER Analanjirofo C 05-20/ANJ / Recrutement d'un Bureau d'Etude pour études, contrôle et Component 2: Investments Sélection fondée En attente 2020-10- 2020-12- 2021-01- 2021-01- 2021-02- 2021-03- 2022-03- surveillance des travaux de COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 15,200.00 0.00 2020-09-30 d'exécution 21 04 03 23 16 13 13 construction de bâtiment à selected landscapes coût usage de banque de semence à Iazafo et Soanierana Ivongo. C 15-20/SOF / Recrutement d'un bureau d'études pour la réalisation d'études, contrôle et surveillance des travaux Component 2: Investments Sélection fondée En attente 2020-11- 2020-12- 2021-01- 2021-02- 2021-03- 2021-03- 2022-03- d’extension du réseau COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 270,000.00 0.00 2020-11-04 d'exécution 24 21 20 19 08 28 28 d’irrigation du périmètre selected landscapes coût d'Ambalavelona Antsamaka Commune Rurale Antsamaka, du paysage de Belanana C 03-20/ANJ / Etudes et Contrôle-Surveillance des travaux de réhabilitation des réseaux d'irrigation et de drainage des périmètres Component 2: Investments Sélection fondée En attente 2021-01- 2021-02- 2021-03- 2021-04- 2021-05- 2021-06- 2022-06- Ampoezana, Anamborano, COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 94,000.00 0.00 2020-12-17 d'exécution 07 20 20 19 24 28 28 Fandrianomby et selected landscapes coût Antsirabeniseva; CR Soanierana Ivongo et Fotsialanana-District de Soanierana Ivongo C 16-20/ANJ / Etudes et Contrôle-Surveillance des travaux de réhabilitation des Component 2: Investments Sélection fondée barrages et des ouvrages En attente 2020-12- 2021-02- 2021-03- 2021-04- 2021-05- 2021-06- 2022-06- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 64,000.00 0.00 2020-11-30 connexes dans la zone d'exécution 21 03 03 02 07 11 11 selected landscapes coût Ambatoharanana du paysage d'Iazafo;CR Ambatoharanana- District de Fénérive Est C 17-20/ANJ / Etudes , Contrôle et surveillance des travaux de protection des berges par méthode Component 2: Investments Sélection fondée biologique et mécanique des En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-06- 2021-07- 2022-07- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 38,500.00 0.00 2020-12-30 rivières dans le paysage d'exécution 20 05 02 02 06 11 11 selected landscapes coût d'Iazafo : - Sahavaviana dans la Commune Maromitety - Iazafo C 18-20/ANJ / Etudes (APS, APD, DAO, EIE), Contrôle et surveillance des travaux de protection des berges des Component 2: Investments Sélection fondée rivières dans le paysage de En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-06- 2021-07- 2022-07- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 65,040.00 0.00 2020-12-29 Soanierana Ivongo : d'exécution 19 04 01 01 05 10 10 selected landscapes coût - Sahave dans la Commune Soanierana Ivongo - Sahafotra dans la Commune Antanifotsy C 11-20/BOE / Recrutement d'une firme pour l'étude de Component 2: Investments Sélection fondée faisabilité de la mise en place En attente 2020-12- 2021-01- 2021-02- 2021-03- 2021-05- 2021-06- 2021-10- COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 9,400.00 0.00 2020-11-25 et formalisation de comité de d'exécution 16 29 26 28 02 06 04 selected landscapes coût gestion de matériels agricoles dans le paysage de Marovoay C 16-20/SOF / Recrutement d'un Bureau d'études pour la réalisation d'études, contrôle et surveillance des travaux: LOT 1: piste depuis Component 2: Investments Sélection fondée En attente 2020-12- 2021-01- 2021-01- 2021-02- 2021-03- 2021-04- 2022-04- croisement de la route IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 234,000.00 0.00 2020-11-15 d'exécution 05 01 29 28 27 16 16 "Bealanana-antsamaka"- selected landscapes coût Beandrarezona ; LOT2: piste "Bealanana- antsamaka"de 15 km de longueur C 05-20/SAV / Recrutement d'une firme pour la diffusion d'itinéraire technique Component 2: Investments Sélection fondée En attente 2021-01- 2021-02- 2021-03- 2021-03- 2021-04- 2021-05- 2022-08- agricole et la promotion de COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 542,000.00 0.00 2020-12-15 d'exécution 02 06 08 28 14 04 17 l'élevage intensif du paysage selected landscapes coût d'Andapa, district d'Andapa, Région SAVA C 04-20/SAV / Etude, contrôle et surveillance des travaux de réhabilitation : Lot 1 : Périmètre irrigué Ankaibe Component 2: Investments Sélection fondée En attente 2020-12- 2021-02- 2021-03- 2021-03- 2021-04- 2021-06- 2022-06- Lot 2 : Périmètre Andasibe COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 481,350.00 0.00 2020-11-30 d'exécution 21 03 05 25 29 03 03 Mahaverika , Ambodipont, selected landscapes coût Antsahanibalana Lot 3 : Périmètre Ambodirafia I, Ambodirafia II, Antsahabe, Ambavala, Andasibe kobahina C 17-20/SOF / Recrutement d'un Bureau d'études pour la réalisation d'études, contrôle et surveillance de la mise en Component 2: Investments Sélection fondée En attente 2020-12- 2021-01- 2021-02- 2021-03- 2021-04- 2021-04- 2022-04- œuvre : LOT 01: Travaux IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 195,000.00 0.00 2020-11-29 d'exécution 19 15 12 14 08 28 28 Piste Ambatosia-Anjohibe selected landscapes coût LOT 02: travaux de réhabilitation d'un ouvrage de franchissement "pont Andranotakatra" C 18-20/SOF / Recrutement d'un Bureau d'études pour la réalisation d'études, contrôle et surveillance des travaux d'aménagement : Component 2: Investments Sélection fondée En attente 2020-12- 2021-01- 2021-02- 2021-03- 2021-03- 2021-04- 2022-04- LOT 01: Périmètre irrigué COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 622,000.00 0.00 2020-11-25 d'exécution 15 11 10 12 29 18 18 Ambararatabe Nord selected landscapes coût Ambahivahy Mahatsinjo - LOT 02 Périmètre Irrigué Nord Ouest Ambahivahy Ambararatabe Nord C 20-20/SOF / Recrutement d'un Bureau d'études pour la réalisation d'étude, contrôle et surveillance de la mise en Component 2: Investments Sélection fondée En attente 2020-12- 2021-01- 2021-02- 2021-03- 2021-04- 2021-04- 2022-04- œuvre des travaux pour le COFN / C1540 and capacity building in the A posteriori sur la qualité et le Open - National 27,000.00 0.00 2020-11-29 d'exécution 19 15 14 16 02 22 22 regabaritage des drains de la selected landscapes coût plaine d'Ankitrobaka, Antanimanga et Antsirakasada. C 21-20/SOF / Recrutement d'un Bureau d'études pour la réalisation d'études, contrôle Component 2: Investments Sélection fondée et surveillance de la mise en En attente 2020-12- 2021-01- 2021-02- 2021-03- 2021-03- 2021-04- 2022-04- IDA / 59790 and capacity building in the A posteriori sur la qualité et le Open - National 220,000.00 0.00 2020-11-29 œuvre des travaux pour d'exécution 09 05 02 04 31 17 17 selected landscapes coût amélioration de la voie d'accès ralliant Ambatoriha Est-Ambararatabe Nord INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UGP PADAP-38775-CS- INDV / Responsable de Component 3: Project 2017-08- 2017-12- 2018-02- 2018-01- 2018-03- 2018-02- 2018-03- 2019-02- Passation des marchés pour IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 11,178.36 Signé 2017-11-30 17 30 06 09 08 02 26 02 l'unité de Coordination and M&E Régionale d'Andapa. MG-UGP PADAP-38776-CS- INDV / Responsable de Component 3: Project 2017-08- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2019-02- Passation des Marchés (RPM) IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 13,209.42 Signé 2017-11-30 17 19 29 23 22 31 22 pour l'Unité de Coordination and M&E Régionale de Sofia. C 61-17/CN / Responsable Component 3: Project Administratif et Finacier 2017-09- 2017-12- 2017-11- 2018-01- 2018-02- 2018-02- 2018-02- 2019-02- IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 14,267.74 Signé 2017-11-30 (RAF) pour l'Unité de 05 30 02 09 09 02 27 02 and M&E Coordination Régionale d'Analanjirofo. Page 10 C 62-17/CN / Responsable de Passation des Marchés Component 3: Project 2017-08- 2018-01- 2018-04- 2018-01- 2018-04- 2018-02- 2018-05- 2019-02- (RPM) pour l'Unité de IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 12,272.69 Signé 2017-11-27 17 16 24 26 27 19 02 19 Coordination Régionale and M&E d'Analanjirofo. MG-UGP PADAP-38779-CS- INDV / Responsable Component 3: Project 2017-09- 2017-12- 2017-11- 2018-01- 2018-02- 2018-02- 2018-02- 2019-02- Administratif et Finacier IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 14,308.06 Signé 2017-11-30 05 30 02 09 16 02 27 02 (RAF) pour l'Unité de and M&E Coordination Régionale de Sava. MG-UGP PADAP-38780-CS- INDV / Responsable Component 3: Project 2017-09- 2017-12- 2017-11- 2018-01- 2018-02- 2018-02- 2018-02- 2019-02- Administratif et Finacier IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 11,889.78 Signé 2017-11-30 05 30 02 09 09 02 27 02 (RAF) pour l'Unité de and M&E Coordination Régionale de Sofia. C 63-14/CN / Comptable Component 3: Project 2017-09- 2017-12- 2018-02- 2018-01- 2018-02- 2018-02- 2018-02- 2019-02- pour l'Unité de Coordination IDA / 59790 Management Coordination A posteriori Individuel Open 12,000.00 8,181.79 Signé 2017-11-30 05 30 08 09 09 02 27 02 Régionale d'Analanjirofo. and M&E C 57-17/CN / Responsable Component 3: Project 2017-12- 2017-12- 2018-01- 2018-01- 2018-02- 2018-01- 2019-02- eau/irrigation national du IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 12,980.94 Signé 2017-12-01 22 31 10 03 03 18 03 Projet. and M&E Component 3: Project C 49-17/CN / Comptable 2017-09- 2017-12- 2017-11- 2018-01- 2018-02- 2018-02- 2018-02- 2019-02- IDA / 59790 Management Coordination A posteriori Individuel Open 24,000.00 11,923.38 Signé 2017-11-30 national du PADAP. 14 30 02 09 01 02 26 02 and M&E MG-UGP PADAP-38784-CS- Component 3: Project INDV / Comptable pour 2017-09- 2017-12- 2017-11- 2018-01- 2018-02- 2018-02- 2018-03- 2019-02- IDA / 59790 Management Coordination A posteriori Individuel Open 12,000.00 8,176.03 Signé 2017-11-30 l'Unité de Coordination 05 30 02 09 28 02 01 02 and M&E Régionale de Sofia. MG-UGP PADAP-38778-CS- INDV / Responsable Component 3: Project 2017-09- 2017-12- 2017-11- 2018-01- 2018-02- 2018-02- 2018-02- 2019-02- Administratif et Finacier IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 13,588.32 Signé 2017-11-30 05 30 02 09 09 02 27 02 (RAF) pour l'Unité de and M&E Coordination Régionale de Boeny. MG-UGP PADAP-38781-CS- Component 3: Project INDV / Comptable pour 2017-09- 2017-12- 2018-02- 2018-01- 2018-02- 2018-02- 2018-02- 2019-02- IDA / 59790 Management Coordination A posteriori Individuel Open 12,000.00 8,181.79 Signé 2017-11-30 l'Unité de Coordination 05 30 08 09 09 02 27 02 and M&E Régionale de Boeny. MG-UGP PADAP-38783-CS- Component 3: Project INDV / Comptable pour 2017-09- 2017-12- 2018-03- 2018-01- 2018-03- 2018-02- 2018-03- 2019-02- IDA / 59790 Management Coordination A posteriori Individuel Open 12,000.00 8,176.03 Signé 2017-11-30 l'Unité de Coordination 05 30 01 09 05 02 07 02 and M&E Régionale de Sava. MG-UGP PADAP-38445-CS- INDV / Responsable de Component 3: Project 2017-08- 2017-12- 2018-01- 2018-01- 2018-01- 2018-02- 2019-01- Passation des Marchés (RPM) IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 13,166.16 Signé 2017-11-27 17 27 06 23 30 15 30 pour l'Unité de Coordination and M&E Régionale de Boeny. C 65-17/CN / 04 Responsables en Agriculture pour les 04 Unités de Gestion régionale du PADAP : Component 3: Project 2018-01- 2018-02- 2018-04- 2018-03- 2018-04- 2018-04- 2018-05- 2019-04- 2018-05- Iazafo-Soanierana Ivongo IDA / 59790 Management Coordination A posteriori Individuel Open 192,000.00 23,032.99 Signé 2018-01-08 25 17 17 10 24 14 02 14 02 (Région Analanjirofo), and M&E Marovoay (Région Boeny), Bealalana (Région SOFIA) et Andapa (Région SAVA) C 69-17/CN / 04 Responsables Socio-orga et développement local pour les 04 Unités de Gestion Component 3: Project 2017-12- 2018-02- 2018-04- 2018-03- 2018-04- 2018-04- 2018-04- 2019-04- régionale du PADAP : Iazafo- IDA / 59790 Management Coordination A posteriori Individuel Open 192,000.00 40,130.70 Signé 2018-01-08 28 16 17 09 25 13 26 13 Soanierana Ivongo (Région and M&E Analanjirofo), Marovoay (Région Boeny), Bealalana (Région SOFIA) et Andapa (Région SAVA). C 67-17/CN / 04 Responsables en environnement et Foresterie pour les 04 Unités de Component 3: Project Gestion régionale du PADAP : 2018-02- 2018-02- 2018-04- 2018-03- 2018-05- 2018-04- 2018-05- 2019-04- IDA / 59790 Management Coordination A posteriori Individuel Open 192,000.00 43,958.48 Signé 2018-01-08 Iazafo-Soanierana Ivongo 07 17 19 10 02 14 14 14 and M&E (Région Analanjirofo), Marovoay (Région Boeny), Bealalana (Région SOFIA) et Andapa (Région SAVA). C 55-17/CN / Responsable Component 3: Project Sauvegarde 2018-02- 2018-02- 2018-03- 2018-03- 2018-04- 2018-04- 2018-05- 2019-04- IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 15,286.86 Signé 2018-01-08 Environnementale et Sociale 23 17 30 10 27 14 02 14 and M&E au niveau national (UGP) MG-UGP PADAP-44922-CS- INDV / 04 Responsables Eau et Irrigation pour les 04 Unités de Gestion régionale Component 3: Project 2018-02- 2018-03- 2018-04- 2018-04- 2018-04- 2018-05- 2018-05- 2019-05- du PADAP : Iazafo- IDA / 59790 Management Coordination A posteriori Individuel Open 192,000.00 43,958.48 Signé 2018-01-22 08 12 17 02 27 07 02 07 Soanierana Ivongo (Région and M&E Analanjirofo), Marovoay (Région Boeny), Bealalana (Région SOFIA) et Andapa (Région SAVA). C 60-17/CN / 04 Assistants techniques des Opérations pour chaque Unité de Gestion Régionale du PADAP Component 3: Project 2017-10- 2017-12- 2018-01- 2018-01- 2018-02- 2018-02- 2018-05- 2019-02- : Iazafo-Soanierana Ivongo IDA / 59790 Management Coordination A posteriori Individuel Open 384,000.00 58,083.89 Signé 2017-12-01 23 31 22 10 23 03 02 03 (Région Analanjirofo), and M&E Marovoay (Région Boeny), Bealalana (Région SOFIA) et Andapa (Région SAVA). Component 3: Project MG-UGP PADAP-44950-CS- 2018-03- 2018-02- 2018-05- 2018-03- 2018-06- 2018-03- 2018-06- 2019-03- IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 17,197.72 Signé 2018-01-22 INDV / Auditeur interne 21 26 18 13 27 28 29 28 and M&E MG-UGP PADAP-59456-CS- CDS / Recrutement d'un consultant international en Component 2: Investments Sélection de 2018-04- 2018-05- 2018-04- 2018-06- 2018-05- 2018-07- vue de la finalisation du plan IDA / V0430 and capacity building in the A posteriori consultants par Direct 30,250.00 40,425.00 Signé 2018-04-16 30 06 30 29 15 29 d'actions sur la gestion des selected landscapes entente directe bois précieux (Diospyros spp, Dalbergia spp) MG-UGP PADAP-59459-CS- INDV / Recrutement d'un consultant national Component 2: Investments francophone pour 2018-05- 2018-05- 2018-04- 2018-05- 2018-05- 2018-06- 2018-05- 2018-07- IDA / V0430 and capacity building in the A posteriori Individuel Limited 10,000.00 2,437.96 Signé 2018-04-16 l'assistance au consultant 14 16 19 26 21 15 21 15 selected landscapes international en vue de la finalisation du plan d'actions sur la gestion des bois précieux. C 11-18/CN / Etude sur la Component 3: Project 2018-06- 2018-06- 2018-06- 2018-06- 2018-08- 2018-06- 2018-09- Rénovation locaux de l'UGP à IDA / 59790 Management Coordination A posteriori Individuel Open 2,500.00 2,172.74 Signé 2018-05-09 06 07 28 14 02 29 01 Nanisana. and M&E MG-UGP PADAP-64943-CS- INDV / Prestations d'un consultant individuel pour le poste de Component 3: Project 2018-07- 2018-07- 2018-10- 2018-07- 2018-10- 2018-08- 2018-10- 2019-08- Responsable en Suivi- IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 12,229.49 Signé 2018-06-01 09 16 08 23 11 12 12 12 évaluation pour l'Unité de and M&E Coordination Régionale de PADAP-Région ANALANJIROFO MG-UGP PADAP-65206-CS- CDS / Prestations pour 03 Component 3: Project Sélection de ans d'un consultant 2018-04- 2018-06- 2018-07- 2018-04- 2021-07- IDA / 59790 Management Coordination A posteriori consultants par Direct 65,000.00 55,369.44 Signé 2018-06-04 individuel pour le poste de 19 14 18 23 17 and M&E entente directe RESPONSABLE ADMINISTRATIF ET FINANCIER du projet PADAP. MG-UGP PADAP-66144-CS- INDV / Prestations d'un Component 3: Project consultant individuel pour le 2018-02- 2018-07- 2018-03- 2018-08- 2018-03- 2018-09- 2018-03- 2019-09- IDA / 59790 Management Coordination A posteriori Individuel Open 10,000.00 7,459.85 Signé 2018-06-11 poste d'Assistant 20 20 21 10 22 03 26 03 and M&E Informatique pour l'Unité de Gestion du PADAP MG-UGP PADAP-75687-CS- CDS / Prestations pour 03 Component 3: Project Sélection de ans d'un consultant 2017-01- 2018-09- 2018-10- 2018-08- 2021-10- IDA / 59790 Management Coordination A posteriori consultants par Direct 65,000.00 18,531.97 Signé 2018-08-27 individuel pour le poste de 16 06 10 01 09 and M&E entente directe RESPONSABLE PASSATION DES MARCHES du projet PADAP C 42-18/CN / La mise en place d'un système Component 1: Information 2018-08- 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- 2019-02- 2019-04- d'information géographique IDA / 59790 A posteriori Individuel Open 10,000.00 7,436.62 Signé 2018-08-30 and planning 30 08 15 18 05 23 08 22 des périmètres hydroagricoles (SIGPHY) C 17-18/CN / Adaptation de la méthodologie et le Component 1: Information 2018-09- 2018-12- 2018-12- 2019-01- 2019-01- 2019-01- 2019-04- protocole du MEEF des IDA / 59790 A posteriori Individuel Open 25,000.00 15,699.95 Signé 2018-11-09 and planning 24 08 18 03 18 11 03 inventaires forestiers et écologiques. MG-UGP PADAP-86980-CS- CDS / Prestations d'un an Component 3: Project Sélection de d'un consultant individuel 2018-10- 2018-11- 2018-12- 2018-10- 2019-12- IDA / 59790 Management Coordination A posteriori consultants par Direct 20,250.00 18,284.62 Signé 2018-11-13 pour le poste d'Assistant 02 23 27 18 27 and M&E entente directe Technique des Opérations du projet PADAP C 54-17/CN / Responsable Component 3: Project 2018-02- 2018-03- 2018-04- 2019-04- en Agriculture au niveau IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 0.00 Annulé 2018-01-08 16 09 13 13 national (UGP) and M&E Page 11 C 10-19/ANJ / Recrutement Component 2: Investments 2019-05- 2019-05- 2019-06- 2019-09- d'agent de suivi et COFN / C1540 and capacity building in the A posteriori Individuel Open 6,560.00 0.00 Annulé 2019-03-12 18 28 17 25 d'accompagnement des selected landscapes COBA. MG-UGP PADAP-86978-CS- CDS / Protocole d'accord PAPRIZ pour les Chaînes de valeur riz irrigué Component 2: Investments Sélection de 2018-10- 2018-11- 2019-01- 2019-02- (Introduction des nouvelles IDA / 59790 and capacity building in the A posteriori consultants par Direct 31,400.00 0.00 Annulé 2018-11-13 16 30 13 12 technologie à travers de selected landscapes entente directe formation, Facilitation d'accés à des intrants et des materiels Agricoles) MG-UGP PADAP-87818-CS- CDS / Protocole d'accord avec la DREEF analanjirofo Component 2: Investments Sélection de 2018-12- 2019-01- 2019-05- pour la redynamisation et IDA / 59790 and capacity building in the A posteriori consultants par Direct 35,000.00 0.00 Annulé 2018-11-22 09 12 12 renforcement de capacité des selected landscapes entente directe COBA existants dans le paysage de Soanierana Ivongo MG-UGP PADAP-87819-CS- CDS / Protocole d'accord avec la DREEF Sofia pour la Component 2: Investments Sélection de 2018-12- 2019-01- 2019-05- redynamisation et IDA / 59790 and capacity building in the A posteriori consultants par Direct 25,000.00 0.00 Annulé 2018-11-22 09 12 12 renforcement de capacité des selected landscapes entente directe COBA existants dans le paysage de Soanierana Ivongo C 02-18/CN / Protocole avec DPV sur l'atelier de Component 2: Investments Sélection de 2018-05- 2018-07- 2019-04- formation et production des IDA / 59790 and capacity building in the A posteriori consultants par Direct 40,000.00 0.00 Annulé 2018-05-09 26 09 05 fiches techniques de gestion selected landscapes entente directe des pestes et pesticides MG-UGP PADAP-127049-CS- CDS / Contrôle et surveillance des travaux sur PI d’Iazafo : LOT 3: réseaux d’irrigation et Component 2: Investments Sélection de 2019-08- 2019-08- 2019-08- 2019-09- 2019-09- 2020-02- drainage zone COFN / C1540 and capacity building in the A posteriori consultants par Direct 72,900.00 68,676.43 Signé 2019-08-16 09 23 28 21 24 18 d’Antsiratenina-Nosibe selected landscapes entente directe LOT 4: réseaux d’irrigation et drainage zone d’Ambatomipaka-Maromitety LOT 6: réseaux d’irrigation zone de Mahatsara MG-UGP PADAP-127177-CS- CDS / Contrôle&surveillance des travaux sur PI Andranomafana Mangindrano-paysage Component 2: Investments Sélection de Bealanana : 2019-08- 2019-08- 2019-08- 2019-09- 2019-08- 2020-02- COFN / C1540 and capacity building in the A posteriori consultants par Direct 47,900.00 42,922.67 Signé 2019-08-16 -lot n°2: canal CPRD du pm 09 23 23 21 26 18 selected landscapes entente directe 2153 jusqu’au bout du réseau -lot n°3: canal CPRG 1er tronçon de 2921 m -lot n°4: canal CPRG 2ème tronçon de 3261 m -lot n°5: piste et pont C 22-18/CN / Protocole avec réseau des Sélection de Component 1: Information 2018-05- 2018-07- 2019-02- observatoires rureaux sur IDA / 59790 A posteriori consultants par Direct 20,000.00 0.00 Annulé 2018-04-30 and planning 17 21 16 l'observatoire des données entente directe socio-économiques pour le paysage de Bealanana. C 07-19/ANJ / Appui aux dialogues public-privé Component 2: Investments 2019-05- 2019-05- 2019-06- 2019-09- régionaux pour la promotion IDA / 59790 and capacity building in the A posteriori Individuel Open 4,000.00 0.00 Annulé 2019-03-12 11 21 10 18 de 3P dans l'agriculture et selected landscapes l'élevage C 04-20/SOF / Assistance technique pour Component 2: Investments En attente 2020-09- 2020-10- 2020-11- 2021-03- l'encadrement et appui- COFN / C1540 and capacity building in the A posteriori Individuel Open 6,000.00 0.00 2020-07-07 d'exécution 15 06 06 06 conseil de proximité des selected landscapes Paysans Formateurs et des paysans adoptants C 02-20/BOE / Recrutement de 3 Consultants Individuels pour la validation expérimentale des paquets techniques agroécologie, Component 2: Investments agroforesterie, arboriculture En cours 2020-05- 2020-07- 2020-07- 2020-08- 2022-08- COFN / C1540 and capacity building in the A posteriori Individuel Open 5,800.00 0.00 2020-05-22 et cultures fourragères d'exécution 08 16 27 26 26 selected landscapes Lot 1: Commune d'Ambolomoty Lot 2: Commune Tsararano Lot 3: Commune Anosinalainolona C 05-20/CN / Responsables en Agriculture pour la cellule Component 3: Project En cours 2020-04- 2020-06- 2020-07- 2020-08- 2022-08- d'exécution régionale du IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 0.00 2020-04-30 d'exécution 23 18 09 13 13 PADAP Région SOFIA (Basé à and M&E Bealalana). C 03-18/BOE / Recrutement d'un consultant individuel chargé du diagnostic du Component 2: Investments 2020-03- 2020-03- 2020-03- 2020-12- fonctionnement et IDA / 59790 and capacity building in the A posteriori Individuel Open 5,000.00 0.00 Annulé 2020-01-21 08 10 15 22 opérationnalisation de la selected landscapes Banque de semences au CMS Tsararano. C 06-20/CN / Responsables en environnement et Component 3: Project En cours 2020-01- 2020-07- 2020-05- 2020-07- 2020-05- 2020-08- 2022-07- Foresterie pour Unité de COFN / C1540 Management Coordination A posteriori Individuel Open 35,000.00 0.00 2020-05-18 d'exécution 20 06 13 27 15 31 30 Gestion régionale du PADAP and M&E Andapa (Région SAVA). C 07-20/CN / Responsable Component 3: Project Sélection de Administratif et Finacier En attente 2020-05- 2020-08- 2022-08- IDA / 59790 Management Coordination A posteriori consultants par Direct 170,000.00 0.00 2020-05-18 (RAF) pour les 04 CERs (Sava, d'exécution 28 01 01 and M&E entente directe Boeny, Analanjirofo et Sofia) C 08-20/CN / Responsable Component 3: Project Sélection de Passation des marchés pour En attente 2020-05- 2020-08- 2022-08- COFN / C1540 Management Coordination A posteriori consultants par Direct 170,000.00 0.00 2020-05-18 les 04 CERs (Sava, Sofia, d'exécution 28 01 01 and M&E entente directe Boeny et Analanjirofo). C 09-20/CN / Comptable Component 3: Project Sélection de En attente 2020-05- 2020-08- 2022-08- pour les 04 CERs (Sava, Sofia, COFN / C1540 Management Coordination A posteriori consultants par Direct 85,000.00 0.00 2020-05-18 d'exécution 28 01 01 Boeny et Analanjirofo). and M&E entente directe C 10-20/CN / Responsable Component 3: Project Sélection de Eau et Irrigation pour les 04 En attente 2020-05- 2020-08- 2022-08- COFN / C1540 Management Coordination A posteriori consultants par Direct 120,000.00 0.00 2020-05-18 CERs (Sava, Sofia, Boeny et d'exécution 28 01 01 and M&E entente directe Analanjirofo). C 11-20/CN / Responsables Socio-orga et développement local pour les Component 3: Project Sélection de 04 CERs du PADAP : Iazafo- En attente 2020-05- 2020-08- 2022-08- COFN / C1540 Management Coordination A posteriori consultants par Direct 115,000.00 0.00 2020-05-18 Soanierana Ivongo (Région d'exécution 28 01 01 and M&E entente directe Analanjirofo), Marovoay (Région Boeny), Bealalana (Région SOFIA) et Andapa (Région SAVA). C 12-20/CN / 04 Assistants techniques des Opérations pour chaque CER du PADAP : Component 3: Project Sélection de Iazafo-Soanierana Ivongo En attente 2020-05- 2020-08- 2022-08- COFN / C1540 Management Coordination A posteriori consultants par Direct 200,000.00 0.00 2020-05-18 (Région Analanjirofo), d'exécution 28 01 01 and M&E entente directe Marovoay (Région Boeny), Bealalana (Région SOFIA) et Andapa (Région SAVA). C 13-20/CN / 03 Responsables en environnement et Foresterie Component 3: Project Sélection de pour les 03 CER du PADAP : En attente 2020-05- 2020-08- 2022-08- COFN / C1540 Management Coordination A posteriori consultants par Direct 90,000.00 0.00 2020-05-18 Iazafo-Soanierana Ivongo d'exécution 28 01 01 and M&E entente directe (Région Analanjirofo), Marovoay (Région Boeny) et Bealalana (Région SOFIA). C 14-20/CN / 03 Responsables en Agriculture pour les 03 CER du PADAP : Component 3: Project Sélection de En attente 2020-05- 2020-08- 2022-08- Iazafo-Soanierana Ivongo COFN / C1540 Management Coordination A posteriori consultants par Direct 90,000.00 0.00 2020-05-18 d'exécution 28 01 01 (Région Analanjirofo), and M&E entente directe Marovoay (Région Boeny) et Andapa (Région SAVA) C 15-20/CN / Responsable Component 3: Project Sélection de en Suivi-évaluation pour la En attente 2020-05- 2020-08- 2022-08- COFN / C1540 Management Coordination A posteriori consultants par Direct 40,000.00 0.00 2020-05-18 Région ANALANJIROFO du d'exécution 28 01 01 and M&E entente directe PADAP. Component 3: Project Sélection de C 18-20/CN / Comptable En attente 2020-05- 2020-08- 2022-08- COFN / C1540 Management Coordination A posteriori consultants par Direct 40,000.00 0.00 2020-05-18 national du PADAP. d'exécution 28 01 01 and M&E entente directe C 16-20/CN / Responsable Component 3: Project Sélection de Sauvegarde En attente 2020-05- 2020-08- 2022-08- COFN / C1540 Management Coordination A posteriori consultants par Direct 40,000.00 0.00 2020-05-18 Environnementale et Sociale d'exécution 28 01 01 and M&E entente directe au niveau national (UGP). C 17-20/CN / Assistant Component 3: Project Sélection de Technique des Opérations du En attente 2020-05- 2020-08- 2022-08- COFN / C1540 Management Coordination A posteriori consultants par Direct 48,000.00 0.00 2020-05-18 projet PADAP au niveau de d'exécution 28 01 01 and M&E entente directe l'UGP. C 21-20/CN / Assistant Component 3: Project Sélection de En attente 2020-05- 2020-08- 2022-08- Informatique pour l'Unité de COFN / C1540 Management Coordination A posteriori consultants par Direct 21,000.00 0.00 2020-05-18 d'exécution 28 01 01 Gestion du PADAP. and M&E entente directe Component 3: Project Sélection de C 20-20/CN / Auditeur En attente 2020-05- 2020-08- 2022-08- COFN / C1540 Management Coordination A posteriori consultants par Direct 48,000.00 0.00 2020-05-18 interne du Projet. d'exécution 28 01 01 and M&E entente directe Page 12 C 19-20/CN / Responsable Component 3: Project Sélection de En attente 2020-05- 2020-08- 2022-08- eau et irrigation national du COFN / C1540 Management Coordination A posteriori consultants par Direct 37,000.00 0.00 2020-05-18 d'exécution 28 01 01 Projet. and M&E entente directe C 11-20/SOF / Recrutement d’un Consultant Spécialiste en Travaux Publics chargé de l’appui à la Cellule Component 2: Investments En attente 2020-07- 2020-08- 2020-08- 2021-06- d’exécution Régionale Sofia IDA / 59790 and capacity building in the A posteriori Individuel Open 9,500.00 0.00 2020-06-17 d'exécution 29 05 19 15 sur l’exécution des travaux selected landscapes de réhabilitation de la RIP 117 reliant Bealanana à Ambatoriha C 22-20 / CN / Responsable Environnement et Foresterie Component 3: Project au niveau de la Cellule En attente 2020-07- 2020-08- 2020-09- 2022-08- IDA / 59790 Management Coordination A posteriori Individuel Open 48,000.00 0.00 2020-06-10 d’Exécution Régionale du d'exécution 29 19 23 14 and M&E projet : Poste basé à Andapa (Région SAVA) C 26-18/ CN / Diagnostic agroécologique et Formation Component 2: Investments Sélection de 2018-10- 2018-05- 2018-11- 2018-07- 2018-12- des Organisations paysannes IDA / 59790 and capacity building in the A posteriori consultants par Direct 45,000.00 0.00 Annulé 2018-05-09 26 26 22 20 17 et des paysans sur les selected landscapes entente directe pratiques agroécologiques C 05-20/BOE / Recrutement de deux (02) agents communaux pour l'approche LIFE dans le district de Component 2: Investments En attente 2020-11- 2020-12- 2021-01- 2023-01- Marovoay, Région Boeny. COFN / C1540 and capacity building in the A posteriori Individuel Open 8,100.00 0.00 2020-10-08 d'exécution 26 11 07 17 Lot 1: Commune rurale de selected landscapes Tsararano Lot 2: Commune rurale d' Anosinalainolona C 03-20/SAV / Recrutement de 02 techniciens agricoles pour encadrer les 300 paysans adoptants en riziculture ameliorée dans le Component 2: Investments paysage d'Andapa: En cours 2020-08- 2020-09- 2020-10- 2020-11- 2021-05- COFN / C1540 and capacity building in the A posteriori Individuel Open 5,630.00 0.00 2020-08-05 Lot 1: Un technicien d'exécution 20 23 14 18 17 selected landscapes s'occupant des périmètres de l'axe nord Lot 2: Un technicien s'occupant des périmètres de l'axe ouest C 10-20/SOF / Recrutement de Consultants individuels Component 2: Investments pour l'encadrement et l'appui En attente 2020-12- 2021-01- 2021-02- 2021-05- COFN / C1540 and capacity building in the A posteriori Individuel Open 6,000.00 0.00 2020-09-30 conseils de proximité aux d'exécution 29 19 23 24 selected landscapes Paysans Formateurs et aux Paysans adoptants C 06-20/ANJ / Consultant Component 2: Investments individuel pour formation 2020-06- 2020-06- 2020-07- 2020-10- COFN / C1540 and capacity building in the A posteriori Individuel Open 5,140.00 0.00 Annulé 2020-04-17 des dirigeants du 13 21 22 20 selected landscapes Tranoben'ny Tantsaha C 09-19/ANJ / Recrutement d'un consultant individuel pour/ Lot 1: la formation en GIRE Component 2: Investments des personnels de 2020-06- 2020-06- 2020-07- 2020-12- COFN / C1540 and capacity building in the A posteriori Individuel Open 4,500.00 0.00 Annulé 2020-04-13 DREEH/DRAEP/DREDD 09 19 20 17 selected landscapes Lot 2: Diffuser et expliquer les rôles, responsabilités de l’Autorité Nationale de l’Eau et de l’Assainissement C 02-20/SOF / Recrutement de deux (02) agents Component 2: Investments communaux sur l'approche En attente 2020-11- 2020-12- 2021-01- 2022-10- COFN / C1540 and capacity building in the A posteriori Individuel Open 8,750.00 0.00 2020-09-30 LIFE : 01 Commune Rurale d'exécution 19 10 14 26 selected landscapes AMBODIAMPANA- 01 Commune Rurale AMBATOSIA C 05-19/ANJ / Consultant individuel pour appuyer la Component 2: Investments En attente 2020-12- 2020-12- 2021-01- 2021-05- redynamisation COFN / C1540 and capacity building in the A posteriori Individuel Open 5,630.00 0.00 2020-09-30 d'exécution 02 13 03 03 duTranoben'ny Tantsaha à selected landscapes Fenérive Est. C 12-20/ANJ / Contrôle et surveillance des travaux de réhabilitation des réseaux Component 2: Investments Sélection de En attente 2020-09- 2020-10- 2021-02- hydroagricoles de la zone COFN / C1540 and capacity building in the A posteriori consultants par Direct 24,500.00 0.00 2020-09-07 d'exécution 27 31 28 Mahatsara Sud- Andapatsra, selected landscapes entente directe dans la plaine d'Iazafo (Lot 06); District de Vavatenina. C 23-20/CN / Responsables en Agriculture pour la cellule Component 3: Project Sélection de En cours 2020-06- 2020-07- 2020-08- 2022-08- d'exécution régionale du COFN / C1540 Management Coordination A posteriori consultants par Direct 23,000.00 0.00 2020-06-30 d'exécution 30 10 09 09 PADAP Région SOFIA (Basé à and M&E entente directe Bealalana). C 07-20/BOE / Recrutement de 3 consultants individuels pour l'encadrement Component 2: Investments technique des agriculteurs En attente 2020-12- 2021-01- 2021-02- 2021-09- COFN / C1540 and capacity building in the A posteriori Individuel Open 10,000.00 0.00 2020-10-30 sur tanety dans le paysage d'exécution 29 19 23 21 selected landscapes de Marovoay Lot 1: Ambolomoty Lot 2: Tsararano Lot 3: Anosinalainolona. C 19-20/BOE / Recrutement de deux (2) techniciens forestiers Component 2: Investments En attente 2020-11- 2020-12- 2021-01- 2021-07- Lot 1: Zone Marosakoa- COFN / C1540 and capacity building in the A posteriori Individuel Open 21,000.00 0.00 2020-09-25 d'exécution 13 04 08 07 Ambolomoty selected landscapes Lot 2: Zone Tsararano- Anosinalainolona C 22-20/BOE / Recrutement d'un Consultant individuel pour le contrôle et Component 2: Investments surveillance des Travaux de En attente 2020-11- 2020-12- 2021-01- 2021-05- COFN / C1540 and capacity building in the A posteriori Individuel Open 5,000.00 0.00 2020-10-08 stabilisation des zones d'exécution 26 17 15 15 selected landscapes d'érosion et protection des réseaux hydroagricole le long du CPRD et CSPC Ambolomoty C 08-20/ANJ / Recrutement d'un consultant individuel pour la formation du Component 2: Investments En attente 2020-11- 2020-12- 2020-12- 2021-01- personnel des Ministères au COFN / C1540 and capacity building in the A posteriori Individuel Open 2,250.00 0.00 2020-10-09 d'exécution 21 01 21 05 niveau Régional à la selected landscapes construction et mise en œuvre du SIS (Formation) C 10-20/ANJ / Recrutement consultant individuel pour la Component 2: Investments formation en GIRE des En attente 2020-12- 2020-12- 2021-01- 2021-01- COFN / C1540 and capacity building in the A posteriori Individuel Open 2,925.00 0.00 2020-10-15 personnels des 03 Directions d'exécution 02 12 01 16 selected landscapes Régionales de tutelles et ceux de la CER C 27-20/CN / Recrutement d’un Responsable Agriculture Component 3: Project au niveau de l’Unité de En cours 2020-09- 2020-10- 2020-11- 2020-11- 2022-08- IDA / 59790 Management Coordination A posteriori Individuel Open 20,000.00 0.00 2020-09-28 Gestion du Projet Agriculture d'exécution 28 28 04 18 10 and M&E Durable par une Approche Paysage C 13-20/ANJ / Recrutement: Lot 1:Technicien 03 CR Vavatenina Lot 2:Technicien 02 CR Fénérive Est et 01 CR Component 2: Investments Vavatenina En attente 2020-11- 2020-11- 2020-12- 2021-06- COFN / C1540 and capacity building in the A posteriori Individuel Open 44,600.00 0.00 2020-09-30 Lot 3:Technicien 03 CR de d'exécution 18 28 27 25 selected landscapes Soanierana Ivongo Lot 4:Technicien CR Ambahoabe et Ambodiampana Lot 5:Technicien CR Antanifotsy et Manompana C 14-20/ANJ / Recrutement de 8 Techniciens en environnement: Lot 1:1/3 CR Vavatenina zone Sud Lot 2:1/1 CR Vavatenina Component 2: Investments zone Nord-2CR Fen Est En attente 2020-12- 2020-12- 2021-02- 2023-02- COFN / C1540 and capacity building in the A posteriori Individuel Open 71,300.00 0.00 2020-10-30 Lot 3:2/3CR Soanierana d'exécution 13 28 01 01 selected landscapes Ivongo zone Sud Lot 4:1/CR Antanifotsy- Manompana Lot 5: 1/CR Ambahoabe- Ambodiampana Lot 6:1/CR Antenina C 26-20/CN / Assistant Component 2: Investments Sélection de En attente 2020-09- 2020-10- 2021-01- technique pour la gestion COFN / C1540 and capacity building in the A posteriori consultants par Direct 90,000.00 0.00 2020-09-03 d'exécution 13 13 11 des contrats. selected landscapes entente directe C 12-20/SOF / Recrutement d'un Consultant Individuel Component 2: Investments En attente 2020-11- 2020-12- 2021-01- 2022-03- spécialiste en irrigation pour COFN / C1540 and capacity building in the A posteriori Individuel Open 13,500.00 0.00 2020-10-15 d'exécution 28 08 06 02 appuyer la Cellule selected landscapes d’exécution Régionale Sofia C 10-20/BOE / Recrutement d'un consultant individuel pour identification, formation des Paysans Component 2: Investments En attente 2021-03- 2021-03- 2021-05- 2021-12- formateurs et encadrement COFN / C1540 and capacity building in the A posteriori Individuel Open 5,400.00 0.00 2021-01-15 d'exécution 10 31 05 31 de 06 ateliers d'élevage selected landscapes bovin pilotes dans les CR d'Ambolomoty, de Tsararano et d'Anosinalainolona Page 13 C 12-20/BOE / Recrutement d'un consultant individuel pour l'étude - contrôle et surveillance des travaux de Component 2: Investments En attente 2021-02- 2021-03- 2021-04- 2021-09- construction de 3 couloirs COFN / C1540 and capacity building in the A posteriori Individuel Open 2,400.00 0.00 2021-01-08 d'exécution 26 19 23 20 de vaccination des bovidés selected landscapes dans les CR d'Ambolomoty, de Tsararano et d'Anosinalainolona C 13-20/BOE / Recrutement de 03 consultants individuels pour l'encadrement Component 2: Investments technique et suivi de En attente 2021-03- 2021-04- 2021-05- 2021-07- COFN / C1540 and capacity building in the A posteriori Individuel Open 12,600.00 0.00 2021-02-02 l'adoption du paquet d'exécution 28 18 23 22 selected landscapes technique par les riziculteurs dans les CR d'Ambolomoty, de Tsararano et d'Anosinalainolona C 35-20/SOF / Recrutement de trois (03) consultants individuels au titre de techniciens accompagnateurs Component 2: Investments pour l'encadrement et l'appui En attente 2020-11- 2020-11- 2020-12- 2021-06- COFN / C1540 and capacity building in the A posteriori Individuel Open 33,500.00 0.00 2020-10-01 conseils de proximité aux d'exécution 05 15 02 30 selected landscapes paysans formateurs et paysans adoptant la riziculture améliorée dans le paysage de Bealanana C 28-20/CN / 02 Responsables en Suivi- Component 3: Project évaluation dont 01 pour la En attente 2021-01- 2021-01- 2021-02- 2022-08- COFN / C1540 Management Coordination A posteriori Individuel Open 36,000.00 0.00 2020-11-30 Région ANALANJIROFO et 01 d'exécution 19 29 26 04 and M&E pour la région de SAVA du PADAP. C 29-20/CN / Recrutement Component 3: Project En attente 2021-01- 2021-01- 2021-02- 2022-08- d'un Assistant Administratif COFN / C1540 Management Coordination A posteriori Individuel Open 8,500.00 0.00 2020-11-30 d'exécution 19 29 26 04 et Financier. and M&E C 30-20/CN / Recrutement de 04 Secrétaires en Component 3: Project En attente 2021-01- 2021-01- 2021-02- 2022-08- passation des marchés en COFN / C1540 Management Coordination A posteriori Individuel Open 34,000.00 0.00 2020-11-30 d'exécution 19 29 26 04 tant que personnel d'appui and M&E pour les CER du PADAP. C 31-20/CN / Spécialiste en Component 3: Project En attente 2021-01- 2021-01- 2021-02- 2022-08- Passation des marchés au COFN / C1540 Management Coordination A posteriori Individuel Open 16,000.00 0.00 2020-11-30 d'exécution 19 29 26 04 niveau de l'UGP. and M&E Page 14