PROCUREMENT PLAN (Textual Part) Project information: Uzbekistan ETMMD (P171683) Project Implementation agency: PIU under NES Date of the Procurement Plan: January 11, 2021 Period covered by this Procurement Plan: from Jan 11,2021 to June 30, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the PPL dated April, 2018, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. None PROCUREMENT Uzbekistan : Electricity Sector Transformation and Resilient Transmission PLAN General Information Country: Uzbekistan Bank’s Approval Date of the Original Procurement Plan: 2021-08-18 2021-08-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171683 GPN Date: Project Name: Electricity Sector Transformation and Resilient Transmission Loan / Credit No: TF / B3778, TF / B4241 Uzbekistan National Power Grid Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ETMMD/CS/CQ-01 / Consulting Services for preparation of Feasibility COMPONENT 1: Digitalization Quality And Cost- Pending Study and Procurement TF / B3778 of the electricity transmission Post Open - International 0.00 2021-01-11 2021-02-01 2021-03-17 2021-04-14 2021-05-14 2021-06-18 2021-07-23 2022-07-23 Based Selection Implementation Documents for sector SCADA/EMS/RTU and Telecommunications ETMMD/CS-02 / Consultanting service to prepare the Project Procurement Strategy for COMPONENT 2: Power grid Fixed Budget Pending Development and TF / B4241 strengthening and renewable Post Open - National 0.00 2021-01-11 2021-02-01 2021-03-17 2021-04-14 2021-05-14 2021-06-18 2021-07-23 2022-07-23 Selection Implementation Procurement Plan for energy integration Electricity Transmission System Modernization and Market Development Project INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ESTART/CS/2021-01 / Construction of new 500 kV COMPONENT 2: Power grid Individual Pending substation ‘Koltsevaya’ with TF / B4241 strengthening and renewable Post Consultant Open 0.00 2021-08-19 2021-10-07 2021-10-28 2021-12-02 2022-05-31 Implementation overhead lines 500KV and energy integration Selection 220 KV Page 1