Himachal Pradesh Horticulture Development Project Project ID : P151744 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan : Original: March 22, 2016 2. Date of General Procurement Notice: May 19, 2015 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Table 1: Procurement Methods Category Method of Threshold (US$ Equivalent) Procurement Goods and non- ICB >3,000,000 consulting services LIB Wherever agreed by the World (including IT Bank contracts) NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 100,000 From UN Agencies As per para 3.10 of Guidelines DC As per para 3.7 of Guidelines Force Account As per para 3.9 of Guidelines Framework Agreements As per para 3.6 of Guidelines Works ICB >40,000,000 NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 100,000 DC As per para 3.7 of Guidelines Force Account As per para 3.9 of Guidelines  Prior Review by the Bank : The World Bank will prior review all Terms of Reference and the following contracts: • Works: All contracts more than US$15.0 million equivalent; • Goods: All contracts more than US$3.0 million equivalent; March 22, 2015 • Non-Consulting Services: All contracts more than US$3.0 million equivalent;  The HPHDS will prior review the first contract issued by each implementing entity, if the estimates of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contracts whose estimates fall in the prior review threshold value. In addition, justifications for all contracts to be issued on Limited International Bidding (LIB), direct contracting or single sourcing (>US$100,000) basis will be subject to prior review by the World Bank. These thresholds are set for the initial 18 months of project implementation and are based on the procurement performance of the project, and may be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above.  All contracts below the specified prior review threshold value will be subject to Post Procurement Review (PPR). The implementing agency will prepare a list of contracts and submit it to the World Bank for this purpose. The PPR will be conducted on an annual basis. 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements:  International Competitive Bidding (ICB) is the preferred method for procurement of goods, works and non-consulting services using the World Bank’s standard bidding document. In addition, the following methods may be adopted depending upon size and complexity of subprojects in accordance with Procurement Guidelines, and as agreed in the Procurement Plan: (a) Limited International Bidding (LIB), (b) National Competitive Bidding (NCB), (c) Shopping, (d) Framework Agreements, (e) Direct Contracting, (f) Force Account, and (g) Procurement of UN agencies. Limited International Bidding is essentially ICB by direct invitation, is used only under exceptional circumstances, and will be adopted only for packages that are specifically agreed by the World Bank to be procured following LIB.  National Competitive Bidding (NCB) for procurement of goods and works will be conducted in accordance with paragraphs 3.3 and 3.4 of the Procurement Guidelines and the following provisions: March 22, 2015 (i) Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), will be used for bidding. (ii) Invitation to bid will be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids. (iii) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, government-owned enterprises, small-scale enterprises or enterprise from any given regional government; (iv) Except with the prior concurrence of the World Bank, there will be no negotiation of price with the bidders, even with the lowest evaluated bidder; (v) For prior review contracts, extension of bid validity will not be allowed without the prior concurrence of the World Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the World Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); (vi) For prior review contracts, re-bidding will not be carried out without the prior concurrence of the World Bank; (vii) The system of rejecting bids outside a pre-determined margin or “bracket” of prices will not be used in the Project; (viii) Rates contracts entered into by the Directorate General of Supplies and Disposal (DGS & D) will not be acceptable as a substitute for NCB procedures unless agreed with the World Bank on a case-by-case basis. Such contracts will be acceptable however, for any procurement under the shopping procedure; (ix) The two or three envelop system will not be used (expect when using the e-procurement system assessed and agreed by the World Bank).  Shopping. Procurement of goods, works and non-consulting services may be carried out using the shopping method (paragraph 3.5 of the Procurement Guidelines) for readily available, off-the-shelf products, or simple civil works valued at less than US$100,000 and which do not require tailor made designs as agreed with the World Bank or concerned expert agencies. Such method, if any, will be agreed in the Procurement Plan. The implementing agency and entities will solicit at least three price quotations for the purchase of goods, materials, small works, or services (non- March 22, 2015 consulting), to formulate a cost comparison report. If agreed by the World Bank, under exceptional circumstances, (such as design sensitivity due to location near a monument or appropriate technology), International Shopping may be used wherein quotations will be solicited from at least three suppliers in two different countries. Goods that otherwise qualify for shopping could be procured directly from UN agencies. In specific cases agreed with the World Bank, procurement may be made from UN agencies as per paragraph 3.10 of the Procurement Guidelines.  Direct Contracting. Direct contracting for the procurement of civil works and goods (paragraph 3.7 of the Procurement Guidelines) may be used to extend an existing contract or award a new contract. For such contracting to be justified, the World Bank must agree that the price is reasonable and that no advantage could be obtained by further competition. Direct contracting can be used to procure from the private sector, UN agencies/programs (for goods), or contractors or NGOs that are already mobilized and working in the target areas.  Force Account. When contractors/suppliers are unlikely to bid at reasonable prices because of the location and risk associated with the subproject or a certain government agency has exclusive rights to a certain type of works/supply, the borrower may use its own department’s personnel and equipment or government owned construction units, provided that the borrower has sufficient managerial capacity and possesses the required technical and financial controls to report to the World Bank on expenditure, as per paragraph 3.9 of the Procurement Guidelines.  Framework Agreements. Directorate General of Supplies and Disposal rate contracts will be acceptable as framework agreements for the procurement of goods. Regional government level rate contracts will be examined by the World Bank and if agreed upon, may also be used as framework agreements. Implementing entities also have the option to set up new framework agreements as per paragraph 3.6 of the Procurement Guidelines.  Use of government institutions and enterprise. Government owned enterprise or institutions in India may be hired based on their unique and exceptional nature if their participation is considered critical to the Project implementation. In such cases, the conditions given in clauses 1.13 of the Consultant Guidelines will be satisfied and each case will be subject to prior review by the World Bank. March 22, 2015 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness : Available in separate Excel file III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 2: Procurement Methods Category Method of Threshold (US$ Equivalent) Procurement Consultants’ QCBS As per Section II of Guidelines services CQS Up to 300,000 SSS As per para 3.8-3.11 of Guidelines Individuals As per Section V of Guidelines LCS As per para 3.6 of Guidelines QBS As per para 3.2 of Guidelines FBS As per para 3.5 of Guidelines (i) International >800,000 shortlist Up to 800,000 (ii) Shortlist may comprise national consultants only  The World Bank will prior review all Terms of Reference and the following contracts: • All contracts more than US$1.0 million equivalent for firm; and • All contracts more US$300,000 equivalent for individuals. The HPHDS will prior review the first contract issued by each implementing entity, if the estimates of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contracts whose estimates fall in the prior review threshold value. In addition, justifications for all contracts to be issued on direct contracting or single sourcing (>US$100,000) basis will be subject to prior review by the World Bank. These thresholds are set for the initial 18 months of project implementation and are based on the procurement performance of the project, and may be modified. In March 22, 2015 addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above. All contracts below the specified prior review threshold value will be subject to Post Procurement Review (PPR). The implementing agency will prepare a list of contracts and submit it to the World Bank for this purpose. The PPR will be conducted on an annual basis. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements:  Selection of Consultants—Quality and Cost Based Selection: Consultant Services may be procured under contracts awarded on the basis of Quality- and Cost-based Selection in accordance with the provisions of Section II of Consultant Guidelines using the World Bank’s Standard RFP. In addition, the following selection methods may be adopted depending upon size and complexity of tasks and as agreed in the Procurement Plan: • Quality Based Selection (QBS) • Selection under Fixed Budget (FBS) • Least Cost Selection (LCS) • Single Source Selection (SSS) • Individual Consultant (IC) Single-Source Selection of consulting firms or individual experts may be used only if it presents a clear advantage over competition for the required consulting services in accordance with paragraph 3.8 of the World Bank’s Consultant Guidelines. Selection of consulting firms based on Consultants’ Qualifications (CQS) may be appropriate for assignments estimated to cost up to US$300,000 or equivalent in accordance with paragraph 3.7 of the Consultant Guidelines. Advertisement for expression of interest may be limited to the regional level for assignments estimated to cost less than US$100,000. For assignments that are estimated to cost less than US$50,000, advertisement is not mandatory as long as a shortlist of at least three proven qualified firms is established. Shortlists of consultants for services estimated to cost less than US$800,000 or the equivalent per contract may be composed entirely of national consultants (paragraph 2.7 of Consultant Guidelines). Services for assignments that meet the requirements set forth in paragraph 5.1 of the Consultant Guidelines may be procured under contracts awarded to individual consultants in accordance with the provisions of paragraphs 5.2 to 5.5 of the Consultant Guidelines. Under the circumstances described in paragraph 5.6 of the March 22, 2015 Consultant Guidelines, such contracts may be awarded to individual consultants on a sole source basis. 4. Consultancy Assignments with Selection Methods and Time Schedule: Available in separate Excel file. March 22, 2015 PROCUREMENT India : Himachal Pradesh Horticulture Development Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-09-12 2021-04-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151744 GPN Date: 2017-04-03 Project Name: Himachal Pradesh Horticulture Development Project Loan / Credit No: IDA / 58380 H Executing Agency(ies): P Nurseries cum Demonstration Orchards Development and Management Society WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned HPHDP PIU SPV COE WORKS 1 Component A: Horticulture / Works related to Single Stage - Two 2018-09- IDA / 58380 Production and Post Request for Bids Open - National 1,120,000.00 0.00 Canceled 2017-10-16 2017-10-21 2017-12-02 2018-02-14 2018-03-21 establishment of centre of Envelope 17 Diversification excellence in temperate zone. HPHDP PIU SPV COE WORKS 2 / Works related to Component A: Horticulture Single Stage - Two 2018-09- establishing centre of IDA / 58380 Production and Post Request for Bids Open - National 800,000.00 0.00 Canceled 2017-10-25 2017-10-30 2017-12-11 2018-02-23 2018-03-30 Envelope 26 excellence of Subtropical Zone Diversification Palampur IN-HPHDP SPV-60821-CW- Component A: Horticulture Request for Single Stage - One 2018-08- RFQ / Providing Fencing at IDA / 58380 Production and Post Open - National 34,606.63 0.00 Canceled 2018-05-01 2018-06-26 Quotations Envelope 25 Centre of Excellence Shilaroo Diversification IN-HPHDP SPV-70670-CW- RFQ / Providing and fixing of Component D: Project electric wiring in SPV working Request for Single Stage - One 2019-03- IDA / 58380 Management, Monitoring and Post Open - National 4,597.00 4,063.15 Completed 2018-07-26 2018-09-20 2017-03-14 hall and new library hall at Quotations Envelope 19 Learning Horticulture Comples Navbahar IN-HPHDP SPV-70907-CW- Component A: Horticulture RFQ / Installation of Micro- Request for Single Stage - One 2019-03- IDA / 58380 Production and Post Open - National 9,933.13 8,919.04 Completed 2018-07-28 2018-09-22 2017-05-25 irrigation System at Quotations Envelope 21 Diversification Bagthan(Sirmour). IN-HPHDP SPV-70909-CW- Component A: Horticulture RFQ / Installation of Micro- Request for Single Stage - One 2019-03- IDA / 58380 Production and Post Open - National 9,822.43 8,756.31 Completed 2018-07-28 2018-09-22 2017-05-25 irrigation System at Bajaura Quotations Envelope 21 Diversification (Kullu) . IN-HPHDP SPV-70914-CW- Component A: Horticulture RFQ / Installation of Micro Request for Single Stage - One 2019-03- IDA / 58380 Production and Post Open - National 4,075.00 3,650.68 Completed 2018-07-28 2018-09-22 2017-06-27 Sprinkler system at PCDO Quotations Envelope 21 Diversification Bagthan in Sirmour District IN-HPHDP SPV-70917-CW- Component A: Horticulture RFQ / Installation of Micro- Request for Single Stage - One 2019-03- IDA / 58380 Production and Post Open - National 3,820.58 3,422.76 Completed 2018-07-28 2018-09-22 2017-06-27 sprinkler System at PCDO Quotations Envelope 21 Diversification ,Bajuara ,Distt. Kullu. IN-HPHDP SPV-70920-CW- RFQ / Work Station Component D: Project Request for Single Stage - One 2019-03- Installation in SPV(HP-NMS) IDA / 58380 Management, Monitoring and Post Open - National 16,132.61 14,464.72 Completed 2018-07-28 2018-09-22 2016-11-07 Quotations Envelope 21 library hall in Navbahar Learning Shimla. IN-HPHDP SPV-70922-CW- Component A: Horticulture Request for Single Stage - One 2019-03- RFQ / Fencing work at Center IDA / 58380 Production and Post Open - National 10,616.29 31,028.94 Completed 2018-07-28 2018-09-22 2017-09-27 Quotations Envelope 21 of Excellence Shilaroo. Diversification IN-HPHDP SPV-83741-CW- RFQ / Invitation of quotations for renovation work of Departmental office building , Component A: Horticulture Request for Single Stage - One 2019-06- providing & installation, water IDA / 58380 Production and Post Open - National 11,811.04 14,051.54 Completed 2018-10-30 2018-12-25 2018-11-26 Quotations Envelope 23 supply& sanitary installation Diversification including provision of saptic tank at Center of Excellence Shillaru. IN-HPHDP SPV-83756-CW- RFQ / Invitation for quotations Component A: Horticulture Request for Single Stage - One 2019-06- for installation and fabrication IDA / 58380 Production and Post Open - National 3,431.68 4,127.52 Completed 2018-10-30 2018-12-25 2018-11-26 Quotations Envelope 23 of steel gate at centre of Diversification excellence Shillaru. IN-HPHDP SPV-87984-CW- RFQ / Request for inviting Component A: Horticulture quotations for providing angle Request for Single Stage - One 2019-07- IDA / 58380 Production and Post Open - National 22,868.87 30,300.62 Signed 2018-12-01 2019-01-26 2019-01-11 iron fencing with G.I wire Quotations Envelope 25 Diversification mesh at Center of Excellence Palampur District Kangra,H.P. IN-HPHDP SPV-87992-CW- RFQ / Inviting quotations for Component A: Horticulture Under installation and fabrication of Request for Single Stage - One 2019-07- IDA / 58380 Production and Post Open - National 13,565.56 0.00 Implementat 2018-12-01 2019-01-26 of steel gate and C/O road in Quotations Envelope 25 Diversification ion Center of Excellence Palampur District Kangra,HP. IN-HPHDP SPV-70894-CW- RFQ / Providing , laying and Installation of Micro - irrigation Facilities at PEQ Sites. (Construction of Component A: Horticulture Request for Single Stage - One 2019-03- Providing , laying and joining IDA / 58380 Production and Post Open - National 36,155.99 36,325.65 Signed 2018-07-28 2018-09-22 2018-07-03 Quotations Envelope 21 of Drip Irrigation System to Diversification be executed at PCDOs - Bajaura,Janjheli,Kigas, Timbi,Guara, Model Farm,UHF Nauni, Pandah Farm Page 1 IN-HPHDP SPV-95354-CW- Component A: Horticulture RFB / Solar Fencing in 10 Single Stage - Two 2020-01- IDA / 58380 Production and Post Request for Bids Open - National 281,690.00 0.00 Canceled 2019-02-01 2019-01-25 2019-02-06 2019-02-12 2019-03-20 2019-03-05 2019-06-02 2019-07-07 Progeny cum Demonstration Envelope 03 Diversification Orchard (PCDOs) IN-HPHDP SPV-95410-CW- RFQ / Construction of RCC water Storage Tanks 2 No,poly Component A: Horticulture line ponds (300 mtr Cube and Request for Single Stage - One 2019-09- IDA / 58380 Production and Post Open - National 28,169.00 29,105.57 Completed 2019-01-23 2019-03-20 2019-03-01 400 mtr Cube) ,Check Dam 4 Quotations Envelope 16 Diversification No ,Construction of Intake Chamber for center of excellence Shillaroo Shimla IN-HPHDP SPV-95415-CW- Component A: Horticulture RFB / Renovation of Office Single Stage - Two 2020-03- IDA / 58380 Production and Post Request for Bids Open - National 14,084.00 0.00 Canceled 2019-04-01 2019-04-06 2019-05-18 2019-07-31 2019-09-04 Building (Construction of Envelope 02 Diversification Washrooms in NMS) IN-HPHDP SPV-103169-CW- Component A: Horticulture RFQ / Renovation of Office Request for Single Stage - One 2019-10- IDA / 58380 Production and Post Limited 28,169.01 0.00 Canceled 2019-03-06 2019-05-01 Building (Construction of Quotations Envelope 28 Diversification Washrooms in NMS) IN-HPHDP SPV-103170-CW- RFQ / Renovation of Office,Providing and laying of water supply and sanitary Component A: Horticulture Request for Single Stage - One 2019-10- fittings, construction of septic IDA / 58380 Production and Post Limited 21,126.76 16,885.03 Completed 2019-03-06 2019-02-16 2019-05-01 2019-05-29 Quotations Envelope 28 tank and soak pit and Diversification retaining walls 2 No. in front of the office,fabrications and installation of steel gates at PCDO Darlaghat. IN-HPHDP SPV-118647-CW- RFQ / Providing, laying and jointing/ Installation of drip irrigation system (Stool Bed & Component A: Horticulture Request for Single Stage - One 2020-02- BWB ) for PEQ Sites IDA / 58380 Production and Post Limited 35,714.00 32,004.73 Signed 2019-06-16 2019-03-08 2019-08-11 2019-06-14 Quotations Envelope 07 (Bajaura - Kullu, Annu- Diversification Shimla, Palampur- Kangra, Bagthan -Sirmour, Pangna- Mandi) IN-HPHDP SPV-123425-CW- Component A: Horticulture RFB / Solar Fencing in 10 Single Stage - Two 2020-07- IDA / 58380 Production and Post Request for Bids Open - National 281,690.00 329,418.47 Signed 2019-08-01 2019-11-15 2019-08-06 2019-12-03 2019-09-17 2020-01-03 2019-11-30 2020-01-23 2020-01-04 2020-02-25 Progeny cum Demonstration Envelope 02 Diversification Orchard (PCDOs) IN-HPHDP SPV-136729-CW- RFQ / Construction of Poly lined Pond and Providing Fencing Work around Farm Pond (Capacity: 600M3 and Component A: Horticulture Request for Single Stage - One 2020-05- 500 M3) and Site IDA / 58380 Production and Post Limited 42,253.52 0.00 Canceled 2019-10-06 2019-12-01 Quotations Envelope 29 Development work of Poly Diversification houses at Centre of Excellence Shillaroo, Teh. Theog, Distt. Shimla H.P. Under H.P. Horticulture Development Project IN-HPHDP SPV-154424-CW- RFQ / Providing, laying and Component A: Horticulture Request for Single Stage - One 2020-09- jointing/ Installation of drip & IDA / 58380 Production and Post Limited 71,369.01 66,701.50 Signed 2020-01-25 2020-01-18 2020-03-21 2020-02-19 Quotations Envelope 17 Sprinkler irrigation system for Diversification PCDO/PEQ Sites IN-HPHDP SPV-154529-CW- Component A: Horticulture Request for Single Stage - One 2020-11- RFQ / Construction of New IDA / 58380 Production and Post Limited 92,857.14 0.00 Canceled 2020-03-15 2020-05-10 Quotations Envelope 06 Building in 4 PCDO Diversification IN-HPHDP SPV-174778-CW- RFQ / Renovation/Repair of HDO Residence at PCDO Component A: Horticulture Request for Single Stage - One 2021-01- Bajaura Distt Kullu HP and IDA / 58380 Production and Post Limited 16,300.00 15,694.50 Signed 2020-05-26 2020-02-19 2020-07-21 2020-05-21 Quotations Envelope 17 Renovation/Repair of office Diversification cum store building at PCDO Pangna Distt Mandi HP IN-HPHDP SPV-174786-CW- Component A: Horticulture Single Stage - Two 2021-05- RFB / Cunstuction of New IDA / 58380 Production and Post Request for Bids Open - National 450,000.00 108,733.01 Signed 2020-06-01 2020-05-29 2020-06-06 2020-06-04 2020-07-18 2020-07-10 2020-09-30 2020-07-22 2020-11-04 2020-07-30 Envelope 03 Building at 6 PCDOs Diversification IN-HPHDP SPV-174791-CW- RFQ / Renovation/Repair of Component A: Horticulture Under office/Reseidence building at Request for Single Stage - One 2021-01- IDA / 58380 Production and Post Limited 42,353.52 0.00 Implementat 2020-06-06 2020-05-13 2020-08-01 different PCDOs and Quotations Envelope 28 Diversification ion Constuction/Repair of Water Tanks at different PCDOs IN-HPHDP SPV-187625-CW- Component A: Horticulture Under Single Stage - Two 2021-07- RFB / Cunstuction of New IDA / 58380 Production and Post Request for Bids Open - National 266,700.00 0.00 Implementat 2020-08-16 2020-08-05 2020-08-27 2020-08-17 2020-10-08 2020-09-19 2020-12-21 2020-12-09 2021-01-25 Envelope 24 Building at 4 PCDOs Diversification ion IN-HPHDP SPV-154531-CW- Component A: Horticulture Under Single Stage - Two 2022-02- RFB / Installation of Solar IDA / 58380 Production and Post Request for Bids Open - National 285,714.29 0.00 Implementat 2021-03-05 2021-02-10 2021-03-10 2021-02-12 2021-04-21 2021-07-04 2021-08-08 Envelope 04 Fencing in 11 PCDOs Diversification ion IN-HPHDP SPV-154532-CW- Component A: Horticulture Pending RFQ / Constuction of Bulding Request for Single Stage - One 2022-02- IDA / 58380 Production and Post Limited 71,428.57 0.00 Implementat 2021-06-10 2021-08-05 and Repair (Wash Room) in 10 Quotations Envelope 01 Diversification ion PCDOs IN-HPHDP SPV-209883-CW- Component A: Horticulture Under RFQ / Installation of Drip Request for Single Stage - One 2021-08- IDA / 58380 Production and Post Limited 99,998.00 0.00 Implementat 2020-12-25 2021-01-08 2021-02-19 irrigation System at Quotations Envelope 18 Diversification ion PCDOs/PEQ Sites Page 2 IN-HPHDP SPV-215134-CW- RFQ / Construction of farm Road at COE Shilaro Shimla , Component A: Horticulture Pending Request for Single Stage - One 2021-09- Installation of Angle Iron IDA / 58380 Production and Post Limited 47,945.00 0.00 Implementat 2021-02-01 2021-03-29 Quotations Envelope 25 fencing at COE Palampur and Diversification ion construction of Shadenet houses at PCDO Nihal Bilaspur IN-HPHDP SPV-216956-CW- RFB / Consruction of New Component A: Horticulture Pending Single Stage - Two 2022-01- Building at PCDOs (Nalhas Ditt IDA / 58380 Production and Post Request for Bids Open - National 153,425.00 0.00 Implementat 2021-02-05 2021-02-10 2021-03-24 2021-06-06 2021-07-11 Envelope 07 Mandi and Jubal Chandesh Diversification ion Distt Sirmour) IN-HPHDP SPV-231618-CW- RFB / Construction of Cold Request for Bids - Store cum Shops, Common Component A: Horticulture Pending Single Stage - Two Small Works SPD 2022-04- Toilets, Reception Rom cum IDA / 58380 Production and Post Request for Bids Open - National 149,000.00 0.00 Implementat 2021-05-01 2021-05-06 2021-06-17 2021-08-30 2021-10-04 Envelope (2 envelope 02 Accommodation, RPTDO Diversification ion process) building, 2 No. of Gazebo, Entrance gate(2 No) IN-HPHDP SPV-231624-CW- RFQ / construction of high- Component A: Horticulture Request for Pending Request for Single Stage - One 2021-12- tech Poly Carbonate Green IDA / 58380 Production and Post Limited Quotations (Non 99,200.00 0.00 Implementat 2021-05-06 2021-07-01 Quotations Envelope 28 house(2 No) and Mist Diversification Bank-SPD) ion Chamber IN-HPHDP SPV-231628-CW- Component A: Horticulture Request for Pending RFQ / Construction of New Request for Single Stage - One 2022-01- IDA / 58380 Production and Post Limited Quotations (Non 80,000.00 0.00 Implementat 2021-05-20 2021-07-15 Building at PCDO Rajpura, Quotations Envelope 11 Diversification Bank-SPD) ion Chamba GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HPHDP PIU SPV GOODS PUR 1 / Procurement of fruit Component A: Horticulture plants, orchids, tulips and Single Stage - Two IDA / 58380 Production and Post Request for Bids Open - International 240,000.00 0.00 Canceled 2017-11-15 2017-11-20 2018-01-01 2018-03-16 2018-04-20 2018-10-17 landscape plants for centre of Envelope Diversification excellence Shillaru Shimla and MFC Palampur. HPHDP PIU SPV GOODS PUR 2 / Purchase of Horticulture Component A: Horticulture Machinery tools Equipment Single Stage - One IDA / 58380 Production and Post Request for Bids Open - National 170,000.00 0.00 Canceled 2017-12-05 2017-12-10 2018-01-21 2018-02-20 2018-03-27 2018-09-23 under Centres of Excellence of Envelope Diversification Temperate as well as Sub temperate Regions HPHDP PIU SPV GOODS PUR Component A: Horticulture 3 / Purchase of equipment Single Stage - One IDA / 58380 Production and Post Request for Bids Open - National 610,000.00 0.00 Canceled 2017-11-15 2017-11-20 2018-01-01 2018-01-31 2018-03-07 2018-09-03 and machinery under Envelope Diversification protected culivation IN-HPHDP SPV-71082-GO- Component D: Project RFQ / Purchase of Pillar Request for Single Stage - One IDA / 58380 Management, Monitoring and Post Open - National 265.84 240.03 Signed 2018-07-29 2018-09-23 2017-12-07 2019-03-22 heaters for SPV HPNMS, Quotations Envelope Learning Navbhar. IN-HPHDP SPV-71084-GO- Component D: Project RFQ / Purchase of Computers IDA / 58380 Management, Monitoring and Post Direct Selection Direct 4,056.00 0.00 Canceled 2018-07-25 2018-07-30 2018-09-03 2019-03-02 for SPV-NMS Learning IN-HPHDP SPV-71085-GO- Component A: Horticulture Request for Single Stage - One RFQ / Purchase of Bamboo IDA / 58380 Production and Post Open - National 2,134.72 2,078.56 Signed 2018-07-29 2018-09-23 2018-03-12 2018-11-22 Quotations Envelope Poles for different PCDOS. Diversification IN-HPHDP SPV-71087-GO- Component A: Horticulture RFQ / Purchase of Hydrogen Request for Single Stage - One IDA / 58380 Production and Post Open - National 10,731.09 6,611.54 Signed 2018-07-29 2018-09-23 2018-04-13 2018-10-23 Peroxide for Soil Treatment at Quotations Envelope Diversification Different PQ Sites. IN-HPHDP SPV-71089-GO- Component A: Horticulture RFQ / Purchase of Formaline Request for Single Stage - One IDA / 58380 Production and Post Open - National 15,924.12 14,277.77 Signed 2018-07-29 2018-09-23 2018-03-12 2018-10-23 for Soil Treatment at Different Quotations Envelope Diversification PQ sites . IN-HPHDP SPV-71095-GO- Component A: Horticulture Request for Single Stage - One RFQ / Purchase of Black IDA / 58380 Production and Post Open - National 11,838.00 10,887.20 Signed 2018-07-29 2018-09-23 2018-03-12 2018-11-22 Quotations Envelope Polythene Sheet for PQ Sites Diversification IN-HPHDP SPV-71096-GO- RFQ / Purchase of Woowen Component A: Horticulture Request for Single Stage - One Polysheet for covering of IDA / 58380 Production and Post Open - National 11,722.46 10,510.50 Signed 2018-07-29 2018-09-23 2018-03-12 2019-03-22 Quotations Envelope Bounderies of different Diversification PCDOS. IN-HPHDP SPV-70926-GO- Component D: Project RFQ / Purchase of Fax Request for Single Stage - One IDA / 58380 Management, Monitoring and Post Open - National 139.00 0.00 Canceled 2018-07-28 2018-09-22 2019-03-21 Machine for SPV ,Navbhar Quotations Envelope Learning ,Shimla IN-HPHDP SPV-71083-GO- Component D: Project RFQ / Purchase of Multi Request for Single Stage - One IDA / 58380 Management, Monitoring and Post Open - National 258.38 0.00 Canceled 2018-07-29 2018-09-23 2018-10-23 Functional Printer for SPV - Quotations Envelope Learning HPNMS at Navbhar IN-HPHDP SPV-71079-GO- Component D: Project Request for Single Stage - One RFQ / Purchase of UPS and IDA / 58380 Management, Monitoring and Post Open - National 1,111.53 0.00 Canceled 2018-07-29 2018-09-23 2019-03-22 Quotations Envelope printer for SPV at Navbhar. Learning IN-HPHDP SPV-94088-GO- Component A: Horticulture Request for Single Stage - One RFQ / Hiring of Cold Storage IDA / 58380 Production and Post Open - National 35,603.00 32,550.12 Signed 2019-01-13 2019-03-10 2018-05-15 2019-09-06 Quotations Envelope for Imported Planting Material Diversification Page 3 IN-HPHDP SPV-95371-GO- RFB / Horticulture machinery, Component A: Horticulture Single Stage - Two Equipment and tools for COE- IDA / 58380 Production and Post Request for Bids Open - National 140,845.00 0.00 Canceled 2019-01-22 2019-01-27 2019-03-10 2019-05-23 2019-06-27 2019-12-24 Envelope Shillaru & COE- Palmpur and Diversification PCDOs IN-HPHDP SPV-95428-GO- RFQ / Initial set up cost Soil Component A: Horticulture Request for Single Stage - One Sterilization,Procurement of IDA / 58380 Production and Post Limited 42,253.00 10.61 Signed 2019-02-20 2019-02-01 2019-04-17 2019-03-08 2019-10-14 Quotations Envelope H2O2,Formalin/Black Poly Diversification Sheets,wooven Poly sheets IN-HPHDP SPV-103167-GO- RFQ / Purchase of Power Operated Machinery and attachments (Mini Tractor Component A: Horticulture Request for Single Stage - One (4x4) along with attachment & IDA / 58380 Production and Post Limited 70,422.54 0.00 Canceled 2019-03-06 2019-02-12 2019-05-01 2019-10-28 Quotations Envelope accessories (Cultivator, Diversification Rotary/Rotovator, Bund Maker, Excavator& Frontend loader, Augur, Trolley/Trailer) IN-HPHDP SPV-103171-GO- RFQ / Purchase of Agriculture Machinery (Power Tiller with cultivator, rotavator and Component A: Horticulture ridger Rotary Tiller/Power Request for Single Stage - One IDA / 58380 Production and Post Limited 84,507.04 3,483.22 Signed 2019-03-06 2019-12-06 2019-05-01 2020-02-15 2019-10-28 Weeder Wood cutter/chain Quotations Envelope Diversification saw Power Operated Brush Cutter, Power Operated Brush Cutter, Power Operated Power Sprayer, Foot Sprayer, Power Operate) IN-HPHDP SPV-103767-GO- Component A: Horticulture RFQ / Quotation for Hiring of Request for Single Stage - One IDA / 58380 Production and Post Limited 35,200.00 499.69 Signed 2019-03-06 2019-03-02 2019-05-01 2019-03-18 2019-10-28 Cold Storage for Imported Quotations Envelope Diversification planting material. IN-HPHDP SPV-103769-GO- RFQ / Invitation of Quotation Component A: Horticulture Request for Single Stage - One for providing refrigerated van IDA / 58380 Production and Post Limited 28,170.00 5.41 Signed 2019-03-06 2019-03-02 2019-05-01 2019-03-08 2019-10-28 Quotations Envelope for transportation of Imported Diversification Planting Material IN-HPHDP SPV-147097-GO- DIR / Import of Planting Component A: Horticulture Material from C & O IDA / 58380 Production and Post Direct Selection Direct 351,270.00 220,735.45 Signed 2019-11-26 2019-12-01 2019-12-01 2019-12-23 2020-01-02 2020-02-14 2020-04-30 Nursery,Wenatchee, Diversification Washington USA IN-HPHDP SPV-147101-GO- Component A: Horticulture DIR / Import of Plant Material IDA / 58380 Production and Post Direct Selection Direct 131,280.00 53,096.88 Signed 2019-11-26 2019-12-01 2019-12-01 2019-12-04 2020-01-01 2020-02-15 2020-04-30 from Vanwell, Wenatchee, WA Diversification , USA IN-HPHDP SPV-147102-GO- Component A: Horticulture DIR / Import of Plant Material IDA / 58380 Production and Post Direct Selection Direct 1,609,520.00 385,200.00 Signed 2019-11-26 2019-12-01 2019-12-01 2019-12-04 2020-01-03 2020-02-13 2020-04-30 from Tree Connection, Diversification Oregon, USA IN-HPHDP SPV-147104-GO- Component A: Horticulture DIR / Import of Plant Material IDA / 58380 Production and Post Direct Selection Direct 166,200.00 136,102.92 Signed 2019-11-26 2019-12-01 2019-12-01 2019-12-13 2020-01-01 2020-02-12 2020-04-30 from TRECO, Oregon, USA Diversification IN-HPHDP SPV-147105-GO- RFQ / Procurement of Goods for Post Entry Quarantine Sites Component A: Horticulture Request for Single Stage - One as per SOP of GOI for keeping IDA / 58380 Production and Post Limited 57,142.86 58,230.27 Signed 2019-12-01 2019-11-22 2020-01-26 2019-12-16 2020-07-24 Quotations Envelope plant material (Hydrogen Diversification Peroxide, Poly-sheets, Bamboo Poles and Net etc.) IN-HPHDP SPV-150865-GO- Component A: Horticulture DIR / Import of Plant Material IDA / 58380 Production and Post Direct Selection Direct 95,600.00 95,425.45 Completed 2019-12-18 2019-12-01 2019-12-23 2019-12-10 2020-01-23 2020-02-10 2020-05-22 2020-04-07 from A.C.N (Adams County Diversification Nursery) U.S.A IN-HPHDP SPV-123428-GO- RFQ / Purchase of Power Operated Machinery and attachments (Mini Tractor Component A: Horticulture Request for Single Stage - One (4x4) along with attachment & IDA / 58380 Production and Post Limited 70,422.54 0.00 Canceled 2019-08-06 2019-10-05 2019-10-01 2020-03-29 Quotations Envelope accessories (Cultivator, Diversification Rotary/Rotovator, Bund Maker, Excavator& Frontend loader, Augur, Trolley/Trailer) IN-HPHDP SPV-151372-GO- Component A: Horticulture Request for Single Stage - One RFQ / Procurement of Vermi IDA / 58380 Production and Post Limited 70,422.00 0.00 Canceled 2020-03-10 2020-05-05 2020-11-01 Quotations Envelope Compost for PCDOs Diversification IN-HPHDP SPV-107985-GO- RFQ / Purchase of Planting Component A: Horticulture Request for Single Stage - One material (Cymbidium orchid) IDA / 58380 Production and Post Limited 59,829.06 0.00 Canceled 2019-04-01 2019-02-26 2019-05-27 2019-11-23 Quotations Envelope for center of excellence Diversification Palampur and Shillaroo IN-HPHDP SPV-157914-GO- Component A: Horticulture DIR / Hiring of Cold Store in IDA / 58380 Production and Post Direct Selection Direct 35,800.00 842.59 Completed 2020-02-06 2020-01-13 2020-02-11 2020-01-24 2020-03-17 2020-02-15 2020-09-13 2020-06-10 Baddi for Imported planting Diversification material. IN-HPHDP SPV-157926-GO- Component A: Horticulture RFQ / Hiring of Refrigerator Request for Single Stage - One IDA / 58380 Production and Post Limited 35,800.00 3,910.92 Signed 2020-02-11 2020-01-20 2020-04-07 2020-02-11 2020-10-04 Van for Imported Planting Quotations Envelope Diversification Material IN-HPHDP SPV-95424-GO- Component A: Horticulture RFB / Purchase of office Request for Single Stage - One IDA / 58380 Production and Post Limited 28,170.00 0.00 Canceled 2020-02-15 2020-05-06 2020-04-11 2020-10-08 furniture (Computer Table and Quotations Envelope Diversification chair) for PCDOs Page 4 IN-HPHDP SPV-188070-GO- Component A: Horticulture Request for Single Stage - One RFQ / Purchase of Solar Insect IDA / 58380 Production and Post Limited 10,000.00 316.13 Signed 2020-08-23 2020-08-21 2020-10-18 2020-09-04 2021-04-16 Quotations Envelope Trap for PCOs Diversification IN-HPHDP SPV-188071-GO- Component A: Horticulture Request for Single Stage - One RFQ / Purchase of Vermi IDA / 58380 Production and Post Limited 40,000.00 0.00 Canceled 2020-09-05 2020-06-11 2020-10-31 2021-04-29 Quotations Envelope Compost for PCDOs Diversification IN-HPHDP SPV-192358-GO- Component A: Horticulture Under DIR / Import of Plant Material IDA / 58380 Production and Post Direct Selection Direct 500,000.00 0.00 Implementati 2020-11-01 2020-09-11 2020-11-06 2020-09-17 2020-12-07 2021-04-06 from A.C.N (Adams County Diversification on Nursery) U.S.A for 2020-21 IN-HPHDP SPV-192362-GO- Component A: Horticulture Under DIR / Import of Plant Material IDA / 58380 Production and Post Direct Selection Direct 611,200.00 0.00 Implementati 2020-11-01 2020-09-11 2020-11-06 2020-09-17 2020-12-09 2021-04-06 from Tree Connection, Diversification on Oregon, USA for 2020-21 IN-HPHDP SPV-192364-GO- Component A: Horticulture Under DIR / Import of Plant Material IDA / 58380 Production and Post Direct Selection Direct 300,000.00 0.00 Implementati 2020-11-01 2020-09-11 2020-11-06 2020-09-17 2020-12-07 2021-04-06 from TRECO, Oregon, USA for Diversification on 2020-21 IN-HPHDP SPV-192366-GO- Component A: Horticulture Under DIR / Import of Plant Material IDA / 58380 Production and Post Direct Selection Direct 350,000.00 0.00 Implementati 2020-11-01 2020-09-11 2020-11-06 2020-10-07 2020-12-07 2021-04-06 from Vanwell, Wenatchee, WA Diversification on , USA for 2020-21 IN-HPHDP SPV-192368-GO- DIR / Import of Planting Component A: Horticulture Under Material from C & O IDA / 58380 Production and Post Direct Selection Direct 550,000.00 0.00 Implementati 2020-11-01 2020-09-11 2020-11-06 2020-09-11 2020-12-08 2021-04-06 Nursery,Wenatchee, Diversification on Washington USA for 2020-21 IN-HPHDP SPV-196403-GO- RFQ / Procurement of Component A: Horticulture Under Request for Single Stage - One furniture (Office chair,Visitor IDA / 58380 Production and Post Limited 66,700.00 0.00 Implementati 2020-10-20 2020-10-19 2020-12-15 2021-06-13 Quotations Envelope chair,Office cum computer Diversification on table and Office Almira) IN-HPHDP SPV-196405-GO- RFQ / Procurement of Component A: Horticulture Pending Cocopeat (fertilizer) for Request for Single Stage - One IDA / 58380 Production and Post Limited 80,000.00 0.00 Implementati 2020-10-20 2020-12-15 2021-06-13 various PCDO's established Quotations Envelope Diversification on under Nurseries Management Society. IN-HPHDP SPV-194675-GO- RFQ / Procurement of Goods (Woven Poly Sheets,Bamboo Component A: Horticulture Request for Single Stage - One Poles, Net) for Post Entry IDA / 58380 Production and Post Limited 53,333.00 36.20 Signed 2020-11-07 2020-10-30 2021-01-02 2020-12-17 2021-07-01 Quotations Envelope Quarantine Sites as per SOP of Diversification GOI for keeping plant material. IN-HPHDP SPV-194672-GO- RFQ / Procurement of Hydrogen Peroxide for (soil Component A: Horticulture Request for Single Stage - One sterilization) Post Entry IDA / 58380 Production and Post Limited 94,666.00 3.02 Signed 2020-11-09 2020-10-30 2021-01-04 2020-12-17 2021-07-03 Quotations Envelope Quarantine Sites as per SOP of Diversification GOI for keeping plant material. IN-HPHDP SPV-191364-GO- Component A: Horticulture Under DIR / Procurement of Solar IDA / 58380 Production and Post Direct Selection Direct 64,500.00 0.00 Implementati 2020-10-26 2020-10-01 2020-10-31 2020-10-19 2020-12-05 2021-06-03 Lights for PCDOs Diversification on IN-HPHDP SPV-154536-GO- Component A: Horticulture Pending RFQ / Procurement of Power Request for Single Stage - One IDA / 58380 Production and Post Limited 71,428.57 0.00 Implementati 2021-04-06 2021-06-01 2021-11-28 operated Equipment - power Quotations Envelope Diversification on tiller,power weeder etc. IN-HPHDP SPV-201903-GO- Component A: Horticulture Under RFQ / Procurement of Flexi Request for Single Stage - One IDA / 58380 Production and Post Limited 40,000.00 0.00 Implementati 2020-11-11 2020-12-03 2021-01-06 2021-07-05 tanks (for storage of water) Quotations Envelope Diversification on for PCDO's under HPNMS. IN-HPHDP SPV-203726-GO- DIR / Hiring of Forwarder and CHA (Customs House Agent) for handling of Imported Component A: Horticulture Planting Material from USA IDA / 58380 Production and Post Direct Selection Direct 466,667.00 397,930.68 Signed 2020-11-25 2020-11-01 2020-11-30 2020-12-11 2021-01-04 2020-12-15 2021-07-03 Airport (Warehouse in Diversification Suppliers Country) to Cold Store Baddi Himachal Pradesh (Warehouse in Employer Country) IN-HPHDP SPV-203728-GO- DIR / Hiring of Cold Store in Component A: Horticulture Baddi for storage of Imported IDA / 58380 Production and Post Direct Selection Direct 66,666.00 69,641.81 Signed 2020-11-25 2020-10-26 2020-11-30 2020-12-11 2021-01-04 2021-01-18 2021-07-03 Planting Material under Diversification HPHDP 2020-21 IN-HPHDP SPV-213326-GO- DIR / Hiring refrigerated van for transportation of Imported Component A: Horticulture Under Planting Material under IDA / 58380 Production and Post Direct Selection Direct 35,000.00 0.00 Implementati 2021-01-12 2021-01-01 2021-01-17 2021-01-08 2021-02-21 2021-08-20 HPHDP - Nalagarh Truck Diversification on Operator’s Union (AC Size: 32’ x 8’ x 8’ (LxWxH) (±5%) IN-HPHDP SPV-213328-GO- DIR / Hiring refrigerated van for transportation of Imported Component A: Horticulture Under Planting Material under IDA / 58380 Production and Post Direct Selection Direct 30,000.00 0.00 Implementati 2021-01-12 2021-01-01 2021-01-17 2021-01-08 2021-02-21 2021-08-20 HPHDP - Doon Tempo Diversification on Operator Union Baddi (AC Size: 13.25’ x 6.5’ x 7’ (LxWxH) (±5%)) Page 5 IN-HPHDP SPV-216962-GO- DIR / Procurement of elite varieties/clonal Component A: Horticulture Pending Rootstocks/Seedlings of Stone IDA / 58380 Production and Post Direct Selection Direct 2,671.23 0.00 Implementati 2021-02-01 2021-02-06 2021-03-13 2021-09-09 Fruits and other temperate Diversification on Fruit Crops from Palagreen Nursery, Ghulam, Hasan Pala in J & K IN-HPHDP SPV-216958-GO- DIR / Procurement of elite varieties/clonal Rootstocks/Seedlings of Stone Component A: Horticulture Pending Fruits and other temperate IDA / 58380 Production and Post Direct Selection Direct 47,431.51 0.00 Implementati 2021-02-01 2021-02-06 2021-03-13 2021-09-09 Fruit Crops from Green Valley Diversification on Nursery, Mohammad shabanpala, Nowpura Kulgam at J & K IN-HPHDP SPV-231626-GO- Component A: Horticulture Pending RFQ / Providing and fixing Request for Single Stage - One IDA / 58380 Production and Post Limited 15,600.00 0.00 Implementati 2021-05-08 2021-07-03 2021-12-30 customized walking Quotations Envelope Diversification on Germination chamber NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-HPHDP SPV-171999-NC- Component A: Horticulture RFB / Hiring of Manpower Single Stage - One IDA / 58380 Production and Post Request for Bids Open - National 118,500.00 0.00 Canceled 2020-06-05 2020-06-10 2020-07-22 2020-08-21 2020-09-25 2021-03-24 Agency for providing Skilled Envelope Diversification and Non Skilled Manpower IN-HPHDP SPV-186744-NC- Component A: Horticulture RFB / Hiring of Manpower Single Stage - Two IDA / 58380 Production and Post Request for Bids Open - National 200,000.00 259,362.73 Signed 2020-08-17 2020-08-06 2020-08-22 2020-08-13 2020-10-03 2020-09-29 2020-12-16 2020-10-14 2021-01-20 2020-12-01 2021-07-19 Agency for providing Skilled Envelope Diversification and Non Skilled Manpower CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-HPHDP SPV-60827-CS- Component A: Horticulture QCBS / Preparation of DPR for Quality Based IDA / 58380 Production and Post Open - National 51,544.62 0.00 Canceled 2018-07-23 2017-01-21 2018-08-13 2018-09-26 2017-03-18 2018-10-24 2017-04-18 2018-11-23 2017-06-01 2018-12-23 2017-09-05 2019-01-27 2020-01-27 installation of irrigation Selection Diversification system in different PCDOs INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 6