Large Scale Irrigation Modernization Project Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: 5 may 2015]: Revision 2 of Updated Procurement Plan, March 28, 2017 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. Works Above US$ 15 million All 2. Goods Above US$ 4 million All 3. Non-Consultant Services Above US$ 4 million All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements: 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 2 million 2. Single Source All 3. Individual Above US$ 400,000 July 9, 2010 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule July 9, 2010 PROCUREMENT Morocco : MA-Large Scale Irrigation Modernization Project PLAN General Information Country: Morocco Banks Approval Date of the Original Procurement Plan: 2017-03-28 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-01-02 Project ID: P150930 GPN Date: Project Name: MA-Large Scale Irrigation Modernization Project Loan / Credit No: IBRD / 85140 Executing Agency(ies): ORMVA GHARB, ORMVA DOUKKALA, Office Regionale de Mise en Valeur Agricole de TADLA (ORMVA TADLA, ORMVA HAOUZ WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO NO 75-2016-DAM / Travaux d adaptation, de rénovation et de maintenance des equipements Component 1: Improving Single Stage - One IBRD / 85140 Post Request for Bids Open - National 1,830,542.13 Signed 2016-05-02 2016-05-12 2016-06-15 2016-07-05 2016-06-23 2016-09-08 2016-09-08 2018-12-31 hydromecaniques et Irrigation Network Infrastructure Envelope electromecaniques de la station de pompage SMPN4 AO NO 38-2016-DAM / Travaux Component 1: Improving Single Stage - One de reconversion du réseau d IBRD / 85140 Post Request for Bids Open - National 5,026,333.03 Signed 2016-02-07 2016-02-23 2016-04-06 2016-05-04 2016-05-04 2016-06-23 2016-06-23 2019-08-31 Irrigation Network Infrastructure Envelope irrigation du secteur Nord3 AO NO 18-2016-DAM / Travaux d adaptation, de rénovation et de maintenance des equipements Component 1: Improving Single Stage - One IBRD / 85140 Post Request for Bids Open - National 2,638,568.99 Signed 2015-12-08 2016-01-28 2016-02-24 2016-05-02 2016-03-23 2016-06-09 2016-06-15 2018-12-31 hydromecaniques et Irrigation Network Infrastructure Envelope electromecaniques de la station de pompage SMPN3 AO NO 42-2016-DAM / Travaux Component 1: Improving Single Stage - One de reconversion du réseau d IBRD / 85140 Post Request for Bids Open - National 2,515,779.46 Signed 2016-02-21 2016-03-07 2016-04-13 2016-05-11 2016-05-11 2016-06-28 2016-06-28 2019-08-31 Irrigation Network Infrastructure Envelope irrigation du secteur Nord 4 AO NO 3-2017-DDA / Réalisation d'une campagne de Component 2: Supporting Single Stage - One suivi de la qualité IBRD / 85140 Farmers Access to Improved Post Request for Bids Open - National 16,419.09 Signed 2017-01-16 2017-02-09 2017-03-22 2017-03-28 2017-03-02 2017-04-14 2017-04-20 2019-01-15 Envelope environnementale des ressources Irrigation Technologies en eau et en sol Component 3: Supporting the AO NO ALERTE IRRIG / Project Implementing Entities to Single Stage - One Pending IBRD / 85140 Post Request for Bids Open - National 0.00 2018-01-29 2018-03-12 2018-04-18 2018-05-06 2018-05-17 2019-02-13 Système d'alerte à l'irrigation Manage the Irrigation Network Envelope Implementation and to Implement the Project ORMVADT1 / Travaux de réalisation du réseau de Component 1: Improving Single Stage - One IBRD / 85140 Post Request for Bids Open - National 13,011,285.87 Signed 2017-03-20 2017-03-25 2017-05-02 2017-04-24 2017-06-13 2017-05-24 2017-07-28 2017-07-04 2017-09-14 2019-10-04 conduites et des bornes du Irrigation Network Infrastructure Envelope secteur Z0. Component 3: Supporting the ORMVADT9 / Mise en place Project Implementing Entities to Single Stage - One Pending d'un observatoire de suivi de la IBRD / 85140 Post Request for Bids Open - National 0.00 2018-10-03 2018-10-08 2018-11-07 2018-12-07 2019-01-17 2022-05-01 Manage the Irrigation Network Envelope Implementation qualité des sols et des eaux. and to Implement the Project Component 3: Supporting the ORMVADT7 / Atelier pour Project Implementing Entities to Single Stage - One Pending entretien et etalonage des IBRD / 85140 Post Request for Bids Open - National 0.00 2018-04-03 2018-04-08 2018-05-08 2018-06-07 2018-07-18 2019-11-18 Manage the Irrigation Network Envelope Implementation compteurs. and to Implement the Project ORMVADT5 / Rénovation des Component 2: Supporting Request for Single Stage - One bâtiments pour association pour IBRD / 85140 Farmers Access to Improved Post Limited 43,273.75 Signed 2016-09-09 2016-08-12 2017-03-08 2016-12-30 2017-07-06 Quotations Envelope Z0. Irrigation Technologies ORMVADT8 / Essais et analyses pour t é ablissement de Component 2: Supporting Single Stage - One é ence la situation de réfr IBRD / 85140 Farmers Access to Improved Post Request for Bids Open - National 23,946.75 Signed 2016-11-01 2016-11-01 2016-11-07 2016-12-01 2016-12-01 2016-12-01 2016-12-01 2017-03-15 2016-12-29 2018-03-15 Envelope environnementale 1ERE PHASE Irrigation Technologies ET 2EME PHASE. ORMVADT2 / Travaux de réalisation du réseau de Component 1: Improving Single Stage - One IBRD / 85140 Post Request for Bids Open - National 3,873,977.12 Signed 2016-05-23 2016-05-23 2016-08-17 2016-09-15 2016-09-15 2016-11-10 2016-10-26 2017-03-01 2017-04-07 2018-12-31 conduites et des bornes du Irrigation Network Infrastructure Envelope secteur EXTENSION FAREGH. ORMVADT3 / Prestations de laboratoires pour le contrôle de la Component 1: Improving Single Stage - One qualité des travaux de IBRD / 85140 Post Request for Bids Open - National 40,834.85 Signed 2016-05-20 2016-05-20 2016-08-16 2016-09-15 2016-09-15 2016-10-20 2016-10-26 2016-12-15 2016-12-30 2020-01-17 Irrigation Network Infrastructure Envelope modernisation des systèmes d'irrigation des 2 secteurs. ORMVAH-REF-2 / FOURNITURE, TRANSPORT ET POSE DE LA CONDUITE Component 1: Improving Single Stage - One DADDUCTION ET SES IBRD / 85140 Post Request for Bids Open - National 2,059,151.69 Signed 2017-02-27 2017-03-04 2017-04-15 2017-03-24 2017-05-15 2017-04-19 2017-06-19 2017-05-22 2017-12-16 Irrigation Network Infrastructure Envelope OUVRAGES ANNEXES DU SECTEUR BOUIDA CONDUITE SOUS-PRESSION REF-14/2016/TA-DA / Travaux du laboratoire pour le contrôle de Component 1: Improving Single Stage - One IBRD / 85140 Post Request for Bids Open - National 215,224.65 Signed 2016-03-16 2016-03-28 2016-04-21 2016-04-21 2016-05-24 2016-04-21 2016-06-17 2016-04-21 qualité pour secteur M et G et Irrigation Network Infrastructure Envelope travaux bassin REF-28/2016/TA-DA / Travaux d'exécution des conduites du Component 1: Improving Single Stage - One réseau de distribution y compris IBRD / 85140 Post Request for Bids Open - National 10,333,713.35 Signed 2016-06-28 2016-07-12 2016-09-06 2016-09-06 2016-09-23 2016-09-06 2016-10-25 2016-09-06 Irrigation Network Infrastructure Envelope ouvrage annexes des secteurs M10-M18 ( L1 ) Page 1 REF-29/2016/TA-DA / Travaux d'exécution de la conduite Component 1: Improving Single Stage - One IBRD / 85140 Post Request for Bids Open - National 7,025,507.78 Signed 2016-06-28 2016-07-12 2016-09-06 2016-09-06 2016-09-23 2016-09-06 2016-10-25 2016-09-06 d'adducteur A5 des secteurs Irrigation Network Infrastructure Envelope M10-M18 ( L2 ) REF-10/2017/TA-DA / Travaux de réalisation des prises é bornes,prises propriéts et les Component 1: Improving Single Stage - One IBRD / 85140 Post Request for Bids Open - National 4,909,254.84 Signed 2017-01-03 2017-01-17 2017-02-28 2017-02-28 2017-04-05 2017-02-28 2017-04-28 2017-02-28 conduite de raccordement y Irrigation Network Infrastructure Envelope é estion des compris la télg secteurs M10-M13 (Lot 1) REF-15/2017/TA-DA / Travaux d'exécution des conduites Component 1: Improving Single Stage - One IBRD / 85140 Post Request for Bids Open - National 7,211,688.62 Signed 2017-02-07 2017-02-17 2017-03-14 2017-03-14 2017-04-18 2017-03-14 2017-05-22 2017-03-14 d'adducteur A6 des secteurs G13- Irrigation Network Infrastructure Envelope G18 REF-11/2017/TA-DA / Travaux de réalisation des prises é bornes,prises propriéts et les Component 1: Improving Single Stage - One IBRD / 85140 Post Request for Bids Open - National 4,047,710.58 Signed 2017-01-03 2017-01-17 2017-02-28 2017-02-28 2017-04-05 2017-02-28 2017-04-28 2017-02-28 conduite de raccordement y Irrigation Network Infrastructure Envelope é estion des compris la télg secteurs M14-M18 (Lot 2) ORMVADT4 / Réhabilitation du Component 1: Improving Single Stage - One Pending IBRD / 85140 Post Request for Bids Open - National 0.00 2018-10-01 2018-10-08 2018-11-07 2018-12-07 2019-01-28 2022-06-01 Canal Principal Bas Service. Irrigation Network Infrastructure Envelope Implementation REF-40/2015/TA-DA / Travaux d'exécution des conduites des adducteurs A5, A6-1 et A6-2 de Component 1: Improving Single Stage - One Pending IBRD / 85140 Post Request for Bids Open - National 0.00 2015-11-10 2015-11-23 2015-12-17 2015-12-17 2015-12-17 2015-12-17 la partie amont sur 5.3 km y Irrigation Network Infrastructure Envelope Implementation compris les ouvrages de prises principaux ORMVADT6 / Rénovation des Component 2: Supporting Request for Single Stage - One Pending bâtiments pour association pour IBRD / 85140 Farmers Access to Improved Post Limited 0.00 2018-02-22 2018-05-11 2018-08-09 Quotations Envelope Implementation Extension Faregh. Irrigation Technologies REF-30/2017/TA-DA / Fourniture et installation du matériel Component 1: Improving Single Stage - One Pending d'équipement de la station de IBRD / 85140 Post Request for Bids Open - National 0.00 2017-03-24 2017-03-29 2017-05-10 2017-06-09 2017-07-14 2018-01-10 Irrigation Network Infrastructure Envelope Implementation filtration du secteur M10/M18 y compris génie civil. REF-32/2017/TA-DA / Travaux de construction d'un bassin de Component 1: Improving Single Stage - One Pending IBRD / 85140 Post Request for Bids Open - National 0.00 2017-05-25 2017-05-30 2017-07-11 2017-08-10 2017-09-14 2018-03-13 régulation hydraulique ( 1ère Irrigation Network Infrastructure Envelope Implementation Tranche ) GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Supporting the AO-TELERELEVE-2016-DAM / Project Implementing Entities to Single Stage - One Pending Acquisition et mise en service IBRD / 85140 Post Request for Bids Open - National 0.00 2018-01-29 2018-03-12 2018-04-18 2018-05-09 2018-05-28 2018-11-24 Manage the Irrigation Network Envelope Implementation é relève d'un système de tél- and to Implement the Project AO NO 19-2017-DDA / Component 3: Supporting the Acquisition du matériel et des Project Implementing Entities to Single Stage - One IBRD / 85140 Post Request for Bids Open - National 8,051.94 Signed 2017-01-16 2017-02-01 2017-03-16 2017-04-07 2017-03-22 2017-04-19 2017-05-19 2017-10-16 produits chimiques Manage the Irrigation Network Envelope de laboratoire de l'environnement and to Implement the Project Component 3: Supporting the AO NO 6-2017-DPF / Project Implementing Entities to Single Stage - One Acquisition matériels IBRD / 85140 Post Request for Bids Open - National 12,146.38 Signed 2017-01-17 2017-02-01 2017-02-23 2017-03-16 2017-03-01 2017-04-20 2017-05-24 2017-10-17 Manage the Irrigation Network Envelope informatiques and to Implement the Project AO NO EQUIPEMENTS DETEC Component 3: Supporting the FUITES / Acquisition Project Implementing Entities to Single Stage - One Pending d'équipements de détection des IBRD / 85140 Post Request for Bids Open - National 0.00 2018-01-29 2018-03-12 2018-04-18 2018-05-06 2018-05-28 2018-12-14 Manage the Irrigation Network Envelope Implementation fuites des conuites souterraine et and to Implement the Project mesure de débit CF-SMG-FOURNITURE DE Component 3: Supporting the VEHICULES-2016 / Acquisition Project Implementing Entities to Request for Single Stage - One IBRD / 85140 Post Open - National 142,867.98 Signed 2016-11-22 2016-12-30 2016-12-29 2017-01-10 de véhicules pour l'équipe de Manage the Irrigation Network Quotations Envelope suivi d'éxecution du projet and to Implement the Project ORMVADF1 / Fourniture et installation du matériel d'équipement des stations de pompage et de filtration du Component 1: Improving Single Stage - One Under IBRD / 85140 Post Request for Bids Open - National 0.00 2017-04-26 2017-05-01 2017-09-21 2017-05-31 2017-06-30 2017-08-10 2019-04-12 secteur Z0 du casier Zemamra. Irrigation Network Infrastructure Envelope Implementation Lot N°1: Fourniture et installation du matériel d'équipement de la station de pompage. ORMVADF2 / Fourniture et installation du matériel d'équipement des stations de pompage et de filtration du Component 1: Improving Single Stage - One Under secteur Z0 du casier Zemamra. IBRD / 85140 Post Request for Bids Open - National 0.00 2017-04-26 2017-05-01 2017-09-21 2017-05-31 2017-06-30 2017-08-10 2018-12-11 Irrigation Network Infrastructure Envelope Implementation Lot N°2: Fourniture et installation du matériel d'équipement de la station de filtration y compris génie civil. Component 3: Supporting the ORMVADF7 / Acquistions ou Project Implementing Entities to Request for Single Stage - One IBRD / 85140 Post Limited 147,213.17 Signed 2017-04-08 2016-12-19 2017-07-18 2016-12-30 2017-11-15 locations de véhicules Manage the Irrigation Network Quotations Envelope and to Implement the Project Page 2 Component 3: Supporting the ORMVADF8 / Fourniture des Project Implementing Entities to Single Stage - One Pending IBRD / 85140 Post Request for Bids Open - National 0.00 2019-06-03 2019-06-08 2019-07-08 2019-08-07 2019-09-17 2020-07-18 é elevé Equipements du télr Manage the Irrigation Network Envelope Implementation and to Implement the Project ORMVADF9 / Appareillage pour Component 2: Supporting le suivi des performances Single Stage - One Pending IBRD / 85140 Farmers Access to Improved Post Request for Bids Open - National 0.00 2019-02-03 2019-02-08 2019-03-10 2019-04-09 2019-05-20 2020-01-15 d'irrigation et l'avertissement à Envelope Implementation Irrigation Technologies l'irrigation ORMVADF3 / Fourniture et installation du matériel d'équipement des stations de pompage et de filtration du Component 1: Improving Single Stage - One Under secteur Extension Faregh du IBRD / 85140 Post Request for Bids Open - National 0.00 2017-03-20 2017-03-25 2017-05-02 2017-04-24 2017-06-13 2017-05-24 2017-07-04 2018-11-04 Irrigation Network Infrastructure Envelope Implementation casier Faregh. Lot N°1: Fourniture et installation du matériel d'équipement de la station de pompage. ORMVADF4 / Fourniture et installation du materiel d'equipement des stations de pompage et de filtration du secteur Extension Faregh du Component 1: Improving Single Stage - One IBRD / 85140 Post Request for Bids Open - National 521,658.03 Signed 2017-03-20 2017-03-25 2017-05-02 2017-04-24 2017-06-13 2017-05-24 2017-07-28 2017-07-04 2017-09-14 2018-09-04 casier Faregh. Irrigation Network Infrastructure Envelope Lot N°2: Fourniture et installation du materiel d'équipement de la station de filtration y compris genie civil. ORMVAH-REF-1 / REALISATION DE CAMPAGNES DANALYSESDE CARACTERISATION DE Component 1: Improving Single Stage - One Pending REFERENCES DES IBRD / 85140 Post Request for Bids Open - National 0.00 2017-01-11 2017-01-16 2017-02-27 2017-03-29 2017-05-03 2017-10-30 Irrigation Network Infrastructure Envelope Implementation PARAMETRES ENVIRONNEMENTAUX LOCALISEE DANSSECTEUR BOUIDA Component 3: Supporting the AO NO 26-2017-SMG / Project Implementing Entities to Single Stage - One Acquisition matériel et mobilier IBRD / 85140 Post Request for Bids Open - National 0.00 Canceled 2017-01-17 2017-02-07 2017-03-01 2017-03-31 2017-05-05 2017-11-01 Manage the Irrigation Network Envelope de bureau et matériel technique and to Implement the Project Component 2: Supporting Farmers Access to Improved ORMVADF5 / Acquisitions du Irrigation Technologies Single Stage - One Pending matériel informatique pour IBRD / 85140 Component 3: Supporting the Post Request for Bids Open - National 0.00 2018-04-02 2018-04-09 2018-05-09 2018-06-08 2018-07-19 2018-10-17 Envelope Implementation ORMVAD et Association Project Implementing Entities to Manage the Irrigation Network and to Implement the Project Component 2: Supporting Farmers Access to Improved ORMVADF6 / Acquisitions du Irrigation Technologies Single Stage - One Pending mobilier de bureau pour IBRD / 85140 Component 3: Supporting the Post Request for Bids Open - National 0.00 2018-02-01 2018-02-08 2018-03-12 2018-03-28 2018-05-10 2018-08-08 Envelope Implementation ORMVAD et ASSOCIATION Project Implementing Entities to Manage the Irrigation Network and to Implement the Project NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ORMVADF10 / Organisation de Component 3: Supporting the voyages techniques au Maroc et Project Implementing Entities to Request for Single Stage - One Pending à l'étranger y compris logistique IBRD / 85140 Post Limited 0.00 2017-04-08 2017-06-03 2017-07-03 Manage the Irrigation Network Quotations Envelope Implementation de transport et de prise en and to Implement the Project charge AO NO 54-2017-DDA / Formation des fils d'agriculteurs Component 3: Supporting the dans le cadre du plan de gestion Project Implementing Entities to Single Stage - One IBRD / 85140 Post Request for Bids Open - National 16,953.47 Signed 2017-04-14 2017-04-26 2017-06-07 2017-07-07 2017-06-14 2017-07-24 2017-07-12 2017-12-28 environnemental du Projet de Manage the Irrigation Network Envelope Modernisation de Grande and to Implement the Project Irrigation du Gharb REF-29/2017/TA-DGRID / Mise Component 3: Supporting the à niveau de la station des Project Implementing Entities to Request for Single Stage - One Pending xé périmentations hydro agricoles IBRD / 85140 Post Limited 0.00 2017-02-19 2017-04-16 2017-10-13 Manage the Irrigation Network Quotations Envelope Implementation de Oulad Gnaou ( Expertise + and to Implement the Project Etude) REF-21/2017/DGRID / Component 3: Supporting the Réalisation de la situation de Project Implementing Entities to Single Stage - One Under é ence des paramètres réfr IBRD / 85140 Post Request for Bids Open - National 0.00 2017-05-08 2017-05-11 2017-06-20 2017-06-30 2017-08-09 2018-02-05 Manage the Irrigation Network Envelope Implementation environnenomentaux et mise en and to Implement the Project place d'un PGES AO NO 64-2017-DDA / Formation des cadres de Component 3: Supporting the l'ORMVA du Gharb dans le cadre Project Implementing Entities to Single Stage - One du plan de gestion IBRD / 85140 Post Request for Bids Open - National 0.00 Canceled 2017-04-14 2017-09-01 2017-09-27 2017-10-27 2017-12-01 2018-12-28 Manage the Irrigation Network Envelope environnemental du Projet de and to Implement the Project Modernisation de Grande Irrigation du Gharb AO NO 52-2017-DDA / Formation des cadres de Component 3: Supporting the l'ORMVA du Gharb dans le cadre Project Implementing Entities to Single Stage - One du plan de gestion IBRD / 85140 Post Request for Bids Open - National 0.00 Canceled 2017-04-14 2017-04-26 2017-06-07 2017-07-07 2017-07-24 2018-12-28 Manage the Irrigation Network Envelope environnemental du Projet de and to Implement the Project Modernisation de Grande Irrigation du Gharb CONSULTING FIRMS Page 3 Activity Reference No. / Combined Evaluation Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DP-70-2016-DAM / Assistance technique pour le suivi et le contrôle des travaux d'adaptation Component 1: Improving Quality And Cost- de la station de pompage IBRD / 85140 Prior Open - International 430,877.24 Signed 2016-01-12 2016-01-26 2016-04-08 2016-06-02 2016-09-23 2016-11-10 2017-06-21 2016-12-30 2016-12-30 2020-11-30 Irrigation Network Infrastructure Based Selection SMPN4 et des travaux de reconversion du réseau d'irrigation collectif du secteur N4 DP-6-2016-DAM / Assistance technique pour le suivi et le contrôle des travaux d'adaptation Component 1: Improving Quality And Cost- de la station de pompage IBRD / 85140 Prior Open - International 532,340.79 Signed 2015-05-11 2015-05-25 2015-12-21 2016-02-03 2016-03-11 2016-06-21 2017-06-20 2016-06-28 2016-06-28 2020-11-30 Irrigation Network Infrastructure Based Selection SMPN3 et des travaux de reconversion du réseau d'irrigation collectif du secteur N3 AO ASSIS-CONTROLE ETUDE Component 3: Supporting the EQUI INTERNE / Assistance Project Implementing Entities to Quality And Cost- Pending technique pour le contrôle IBRD / 85140 Prior Open - International 0.00 2017-04-16 2017-04-30 2017-08-30 2017-10-29 2017-11-30 2017-12-28 2018-02-05 2020-12-31 Manage the Irrigation Network Based Selection Implementation é udes technique des t and to Implement the Project d'équipements internes DP NO89-2016-DDA / Assistance technique pour Component 2: Supporting Quality And Cost- l'accompagnement des IBRD / 85140 Farmers Access to Improved Prior Open - International 1,281,307.03 Signed 2015-11-02 2015-11-18 2016-08-16 2016-09-26 2016-12-05 2017-02-06 2017-09-26 2017-03-13 2017-05-18 2023-05-30 Based Selection agriculteurs pour la réalisation Irrigation Technologies des aménagements internes Component 3: Supporting the ORMVADSC8 / Appui à la Project Implementing Entities to Quality And Cost- Pending IBRD / 85140 Post Open - International 0.00 2017-03-01 2017-03-23 2017-05-17 2017-06-16 2017-07-16 2017-09-05 2017-10-10 2022-04-14 gestion et au suivi du projet. Manage the Irrigation Network Based Selection Implementation and to Implement the Project ORMVADSC3 / Etude de Component 1: Improving Quality And Cost- rhéabilitation du Canal Principal IBRD / 85140 Prior Open - International 233,868.26 Signed 2015-09-08 2015-10-20 2016-03-15 2016-06-22 2016-06-22 2016-07-17 2016-09-26 2017-10-14 2017-04-05 2017-07-19 2018-01-31 Irrigation Network Infrastructure Based Selection Bas Service ORMVADSC1 / Prestations de service pour le contrôle des Component 1: Improving Quality And Cost- IBRD / 85140 Prior Open - International 1,303,734.37 Signed 2015-03-17 2015-10-27 2016-02-16 2016-04-28 2016-04-28 2016-05-26 2016-10-17 2017-06-09 2017-03-15 2017-04-07 2021-03-19 travaux de modernisation des Irrigation Network Infrastructure Based Selection systèmes d'irrigation. ORMVADSC6 / Formations et Component 3: Supporting the assistance technique à Project Implementing Entities to Quality And Cost- Pending IBRD / 85140 Post Open - International 0.00 2017-05-01 2017-05-23 2017-07-17 2017-08-16 2017-09-15 2017-11-05 2017-12-10 2019-04-12 l'ORMVAD pour la maintenance Manage the Irrigation Network Based Selection Implementation et l'exploitation. and to Implement the Project Component 3: Supporting the ORMVADSC7 / Etude et mise Project Implementing Entities to Quality And Cost- Pending en place de l'extension du SIG et IBRD / 85140 Post Open - International 0.00 2018-02-01 2018-02-23 2018-04-19 2018-05-19 2018-06-18 2018-08-08 2018-09-12 2020-01-13 Manage the Irrigation Network Based Selection Implementation é t Téld é ection. and to Implement the Project MOF-REF-23 / Assistance technique pour le suivi et contrôle Component 1: Improving Quality And Cost- IBRD / 85140 Prior Open - International 1,407,946.04 Signed 2015-04-23 2015-05-24 2015-07-07 2016-03-10 2016-04-07 2016-05-04 2017-05-30 2016-08-08 2016-07-28 2020-08-21 des travaux des secteurs M10- Irrigation Network Infrastructure Based Selection M18 MOF-REF-24 / Assistance technique pour le suivi et contrôle Component 1: Improving Quality And Cost- IBRD / 85140 Prior Open - International 1,095,553.21 Signed 2016-07-26 2016-08-16 2016-09-29 2016-10-27 2016-11-26 2016-12-31 2017-04-27 2017-02-04 2017-04-26 2018-02-04 des travaux des secteurs G13- Irrigation Network Infrastructure Based Selection G18 ORMVAH-REF-3 / LAssistance technique pour le suivi et le contrôle des travaux de Component 1: Improving Quality And Cost- Under IBRD / 85140 Post Open - International 0.00 2016-10-07 2016-10-28 2016-12-11 2017-01-08 2017-04-27 2017-02-07 2017-04-27 2017-03-14 2017-04-28 2017-04-18 2018-04-18 reconversion à l'irrigation Irrigation Network Infrastructure Based Selection Implementation localisée du secteur Bouida du périmètre de la Tessaout Amont. ORMVAH-REF-4 / La Mission d'assistance technique consiste en la réalisation des prestations Component 2: Supporting suivantes: Quality And Cost- Pending IBRD / 85140 Farmers Access to Improved Post Open - International 0.00 2017-04-26 2017-05-17 2017-06-30 2017-07-28 2017-08-27 2017-10-01 2017-11-05 2018-11-05 Formation des agriculteurs Based Selection Implementation Irrigation Technologies Formation du personnel d'encadrement Essais et démonstrations AMI NO62-2017-DGR / Component 3: Supporting the Assistance technique et Project Implementing Entities to Quality And Cost- Pending formation de l'ORMVAG pour IBRD / 85140 Post Open - International 0.00 2017-06-19 2017-07-20 2017-10-09 2017-11-30 2017-12-29 2018-02-06 2018-03-12 2022-12-30 Manage the Irrigation Network Based Selection Implementation l'exploitation et la maintenance and to Implement the Project des qé uipements hydro-agricoles AMI N017-2017-DGR / Component 3: Supporting the Assistance technique et Project Implementing Entities to Quality And Cost- formation à l'ORMVAG pour IBRD / 85140 Post Open - International 0.00 Canceled 2017-04-19 2017-06-07 2017-07-19 2017-09-04 2017-10-05 2017-11-14 2017-12-14 2022-12-30 Manage the Irrigation Network Based Selection l'exploitation et la maintenance and to Implement the Project des qé uipements hydro-agricole REF-01/2017/DDA / Appuis aux Component 2: Supporting Quality And Cost- Under agriculteurs pour la valorisation IBRD / 85140 Farmers Access to Improved Prior Open - International 0.00 2016-08-27 2016-09-17 2016-10-31 2016-11-28 2017-06-06 2016-12-28 2017-02-01 2017-03-08 2018-03-08 Based Selection Implementation de l'eau d'irrigation Irrigation Technologies ORMVADSC2 / Assistance technique pour la réalisation d'un Component 2: Supporting Quality And Cost- programme d'appui aux AUEA IBRD / 85140 Farmers Access to Improved Post Open - International 0.00 Canceled 2016-08-16 2016-08-30 2017-02-22 2017-02-22 2017-04-10 2017-06-13 2017-05-10 2017-06-28 2017-08-29 2021-06-29 Based Selection pour la reconversion interne et la Irrigation Technologies valorisation de la production ORMVADSC4 / Assistace pour Component 1: Improving Quality And Cost- Pending le suivi des travaux des SP et IBRD / 85140 Post Open - International 0.00 2018-06-01 2018-06-23 2018-08-17 2018-09-16 2018-10-16 2018-12-06 2019-01-10 2020-07-13 Irrigation Network Infrastructure Based Selection Implementation canal Bas Service. Page 4 ORMVADSC5 / Prestations de service pour le contrôle des Component 2: Supporting Quality And Cost- Pending é udes et des installations des t IBRD / 85140 Farmers Access to Improved Post Open - International 0.00 2018-03-01 2018-03-23 2018-05-07 2018-06-13 2018-06-27 2018-07-25 2018-08-29 2021-03-01 Based Selection Implementation qé uipements d'irrigation Irrigation Technologies localisée. ORMVADS2-C2 / Assistance technique pour la réalisation d'un Component 2: Supporting Quality And Cost- Pending programme d'appui aux AUEA IBRD / 85140 Farmers Access to Improved Post Open - International 0.00 2016-08-16 2017-12-19 2018-01-31 2018-02-28 2018-03-12 2018-03-30 2018-04-13 2023-04-17 Based Selection Implementation pour la reconversion interne et la Irrigation Technologies valorisation de la production ORMVADS2 / Assistance technique pour la réalisation d'un Component 2: Supporting Quality And Cost- programme d'appui aux AUEA IBRD / 85140 Farmers Access to Improved Post Open - International 0.00 Canceled 2016-08-16 2016-08-30 2017-12-19 2017-09-15 2017-11-07 2017-12-07 2018-01-11 2018-02-15 2019-02-15 Based Selection pour la reconversion interne et la Irrigation Technologies valorisation de la production INDIVIDUAL CONSULTANTS Page 5