Procurement Plan I General 1 Project Information Project Name: Integrated Irrigation Improvement & Management Project Country: Arab Republic of Egypt Project ID: P073977 Loan/Credit Numbers: EGT-7291 Component Meet Yazid 2 Bank's approval date of Procurement Plan Original:28/2/2008 Revision 1:3/12/2008 Update 16/11/2011 Update 10/9/2012 Update 4/2/2013 Update January 16, 2014 3 Date of General Procurement Notice 1 May 2005 II Goods, Work and Non-Consulting Services Thresholds 1 Prior Review Threshold Procurement Decisions subject to Prior Review by the Bank as stated in the Loan Agreement. The Loan Agreement was amended on 2 November 2012. The amended Loan Agreement stated that "The Procurement Plan shall set forth those contracts, which shall be subject to the Bank's Prior Review. All other contracts shall be subject to Post Review by the Bank" 1a Procurement Category Prior Review Threshold (USD) Comments Goods more than or equal 250,000 Works more than or equal 500,000 Procurement Method Threshold 1b Procurement Method (USD) Comments ICB (Goods) more than or equal 500,000 NCB (Goods) Less than 500,000 Shopping (Goods) Less than or equal 20,000 ICB (Works) More than or equal 10,000,000 NCB (Works) Less than 10,000,000 Shopping (Works) Less than 50,000 Procurement Plan for Goods Updated 12/12/2013 Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Proc Plan Updated on January 16, 2014 Completed Review by Domestic Preparation of Bank’s No Bid Invitation Bid Closing Bid Opening BER Bank’s No Contract Package reference No/ Procurement Fund Estimated Bank Preference Bid Document Objection to Objection to Contract Contract Contract Name, City, and Completion SLNo Description of Goods Status Currency Contract No method Source(s) Cost Bidding BER and Signing (Date) Value Currency Country of Contractor (prior/post) (yes/no) (Date) Document (Date) (Date) (Date) (Date) Contract Award (Date) Planned Global Cars & Spare Vehicles(Lot A) 64 Double cabin Pick- IBRD (70%) 1 IIIMP/ICB/G- 01-2007 ICB Revised Prior No 8,146,461.00 EGP Parts Up and Spare Parts increased to 73 GoE (30%) Actual 19/Oct/06 21/Dec/06 10/Feb/07 2/Apr/07 2/Apr/07 9/Aug/07 14/Aug/07 9/Sep/07 14/Nov/07 Vehicles(Lot B) 20 4X4 Wheel Drive Planned Global Cars & Spare IBRD (70%) 2 IIIMP/ICB/G- 01-2007 Utility Vehicles and Spare Parts ICB Revised Prior No 3,542,269.08 EGP Parts GoE (30%) increased to 23 Actual 19/Oct/06 21/Dec/06 10/Feb/07 2/Apr/07 2/Apr/07 18/Jul/07 18/Jul/07 4/Sep/07 21/Feb/08 Planned 31/Jan/08 Supply of Subsurface Drainage Laterals Steenbergen 3 IIIMP/ICB/G- 08-2007 ICB IBRD Revised Prior No 489,750.00 EUR Laying Machines Hollanddrain B.V Actual 12/Feb/07 22/Feb/07 18/Mar/07 30/Apr/07 30/Apr/07 18/Jul/07 18/Jul/07 30/Sep/07 Completed Planned 16/Jan/08 Supply of Subsurface Drainage 4 IIIMP/ICB/G- 09-2007 ICB IBRD Revised Prior No 439,500+7000 EUR+LE Inter - Drain Sales B.V Collectors Laying Machines Actual 12/Feb/07 22/Feb/07 18/Mar/07 2/May/07 2/May/07 18/Jul/07 18/Jul/07 17/Sep/07 Completed Planned 31/May/08 150 km PVC pipes with different IBRD (70%) 5 IIIMP/ICB/G- 04-2008 ICB Revised Prior No 2,853,510.00 EGP Al-Hakeem Plast diameters GoE (30%) Actual 15/Jul/07 18/Jul/07 2/Aug/07 26/Aug/07 26/Aug/07 8/Nov/07 5/Dec/07 2/Jan/08 11/Jun/08 IIIMP/SHOPPING 01- 6000 m PVC pipes with 200 mm Planned IBRD (70%) Inter-Plast for PVC 6 Shopping Revised Post No N/A N/A 113,816.00 EGP 2007 diameters GoE (30%) Pipes Actual 31/May/07 31/May/07 7/Jun/07 7/Jun/07 14/Jun/07 10/Jul/07 21/Jul/07 IIIMP/SHOPPING 02- Planned IBRD (70%) Quality Standard 7 ArcEditor licence PMU Shopping Revised Post No N/A N/A 74,200.00 EGP 2008 GoE (30%) Actual 26/Feb/08 27/Feb/08 10/Mar/08 20/Mar/08 26/Mar/08 IIIMP/SHOPPING 03- Planned IBRD (70%) Quality Standard 8 ArcEditor licence for Behira Shopping Revised Post No N/A N/A 74,200.00 EGP 2008 GoE (30%) Actual 26/Feb/08 27/Feb/08 10/Mar/08 20/Mar/08 26/Mar/08 IIIMP/SHOPPING 04- Planned IBRD (70%) Quality Standard 9 ArcEditor licence for Kafr El-Sheikh Shopping Revised Post No N/A N/A 74,200.00 EGP 2008 GoE (30%) Actual 26/Feb/08 27/Feb/08 9/Mar/08 20/Mar/08 26/Mar/08 IIIMP/SHOPPING 05- Planned IBRD (70%) Quality Standard 10 ArcEditor licence for Tanta Shopping Revised Post No N/A N/A 74,200.00 EGP 2008 GoE (30%) Actual 26/Feb/08 27/Feb/08 13/Mar/08 20/Mar/08 26/Mar/08 IIIMP/SHOPPING 06- Planned IBRD (70%) 11 A0 Plotters (3) Shopping Revised Post No N/A N/A 97,500.00 EGP Global Computec 2008 GoE (30%) Actual 18/Aug/08 8/Sep/08 11/Sep/08 28/Sep/08 IIIMP/SHOPPING 07- Planned IBRD (70%) 12 A0 scanner (1) Shopping Revised Post No N/A N/A 99,000.00 EGP TIC Computing 2008 GoE (30%) Actual 18/Aug/08 2/Sep/08 11/Sep/08 23/Oct/08 IIIMPSHOPPING 09- Planned IBRD (70%) Chemical&Technical 13 Water quality testing instruments (8) Shopping Revised Post No N/A N/A 108,072.00 EGP 2008 GoE (30%) services Actual 20/Nov/08 4/Dec/08 19/Dec/08 19/Dec/08 24/Dec/08 6/Jan/09 11/May/09 IIIMP/SHOPPING 10- 4000 m PVC pipes with 180 mm Planned IBRD (70%) 14 Shopping Revised Post No N/A 88,469.00 EGP Al-Ameen for Pipes 2009 diameters GoE (30%) Actual 31/Mar/09 2/Apr/09 6/Apr/09 14/Apr/09 14/Apr/09 23/Apr/09 30/Apr/09 21/May/09 IIIMP/SHOPPING 11- 5000 m PVC pipes with 180 & 200 mm Planned IBRD (70%) 15 Shopping Revised Post No N/A N/A 108,979.00 EGP Al-Ameen for Pipes 2009 diameters GoE (30%) Actual 8/Jun/09 14/Jun/09 21/Jun/09 21/Jun/09 28/Jun/09 5/Jul/09 20/Oct/09 Planned 5/Dec/10 IIIMP/PMU/G6- 400 km PVC pipes with different IBRD (70%) Canal Plastic Company 16 ICB Revised Prior No 6,106,046.00 EGP 5/Jun/11 ICB/2009 diameters GoE (30%) for Pipes & Fittings Actual 12/Feb/09 10/May/09 27/May/09 12/Jul/09 12/Jul/09 19/Aug/09 23/Aug/09 6/Dec/09 23/May/11 IIIMP/SHOPPING 08- 4000 m PVC pipes with 200 mm Planned IBRD (70%) Goldan Pipe for make 17 Shopping Revised Post No N/A N/A N/A 105,464.00 EGP 2008 diameters GoE (30%) PVC Actual 20/Nov/08 4/Dec/08 4/Dec/08 25/Dec/08 6/Jan/09 4/Feb/09 Planned IIIMP/SHOPPING/ 12- 1 Total Station + 2 Theodolite + 10 spirit IBRD (70%) Cairo Engineering & 18 Shopping Revised Post No N/A N/A N/A 106,602.05 EGP 2009 level GoE (30%) Technical Actual 20/Jul/09 20/Jul/09 17/Aug/09 3/Sep/09 16/Sep/09 Planned Surveying systems IIIMP/SHOPPING/G13- 19 10 GPS + 6 Steel Measuring Tape Shopping CA (100%) Revised Post No N/A N/A N/A 33,899.00 EGP company 2009 Actual 1/Oct/09 1/Oct/09 9/Nov/09 10/Nov/09 19/Nov/09 Conductivity, Salinity, TDS, Specific Planned IIIMP/SHOPPING/G14- 20 conductance temperature meter +6 Shopping CA (100%) Revised Post No N/A N/A N/A 20,493.00 EGP Giga systems company 2009 Rechargeable battery Actual 1/Oct/09 1/Oct/09 9/Nov/09 10/Nov/09 9/Dec/09 Procurement Plan for Goods Updated 12/12/2013 Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Proc Plan Updated on January 16, 2014 Revised Ibrahem Mahmoud 2/Apr/12 IIIMP/PMU/G7- The Supply of Motorcycles and IBRD (70%) Revised 14/Dec/10 23/Jan/11 21/Mar/11 2/May/11 2/May/11 21/Jun/11 27/Jun/11 Tend. Ibrahem company for 21 NCB Prior No 731,280.00 EGP NCB/2011 Tricycles GoE (30%) Revised 20/Jul/11 19/Aug/11 18/Sep/11 18/Sep/11 18/Oct/11 17/Nov/11 Production of Actual 19/Jul/11 24/Jul/11 24/Aug/11 29/Sep/11 29/Sep/11 13/Dec/11 13/Dec/11 28/Dec/11 Motorcycles and its 1/Feb/12 Planned 1/Jun/11 1/Jul/11 30/Aug/11 14/Sep/11 IIIMP/SHOPPING/G 21- 22 Supply of GPSs Shopping CA (100%) Revised Post No N/A N/A 11,000.00 EGP Zoom Technologies 2010 Actual 24/Nov/10 24/Nov/10 2/Dec/10 4/Dec/10 19/Dec/10 14/Mar/11 Planned 1/Jun/11 1/Sep/11 31/Jul/11 30/Aug/11 14/Sep/11 IIIMP/PMU/SHORT- Supply of Current meters and survey SHORT- Cairo Engineeering & 23 CA (100%) Revised Prior No N/A N/A 303,380.00 EGP LIST/G22-2010 equipment LIST Manufacturing Co. Actual 15-Dec.-10 16/Jun/11 Planned IIIMP/PMU/NCB/G25- 24 Supply of Spinit Level Shopping CA (100%) Revised Post No N/A N/A 27,720.00 EGP Technoscient 2011 Actual 4/Jan/11 5/Jan/11 13/Jan/11 26/Jan/11 14/Mar/11 Actual IIIMP/PMU/NCB/G26- 25 Supply of Total Station Shopping CA (100%) Post No N/A N/A 46,000.00 EGP Surveying Syatems 2011 4/Jan/11 5/Jan/11 13/Jan/11 19/Jan/11 20/Jan/11 26/Jan/11 14/Mar/11 IIIMP/PMU/G8-NCBG27- Planned 15/Jan/12 16/Apr/12 CNS Group Company 26 Supply of Computers & Printers NCB CA (100%) Revised Post No N/A N/A 48,300.00 EGP + Leaders for 2012 Actual 27/Feb/12 14/Mar/12 14/Mar/12 8/Apr/12 22/Apr/12 Computers and 28/May/12 Planned 1/Jun/11 1/Jul/11 30/Aug/11 5/Nov/12 IIIMP/SHOPPING/G 15- IBRD (70%) Cairo Center for 27 Supply of PVC Welding Machines Shopping Revised Post No 20/Dec/12 N/A 25/Dec/12 N/A 9/Jan/13 32,725.00 EGP 2012 GoE (30%) Tools&Machinery Actual 10/Sep/12 15/Sep/12 30/Sep/12 30/Sep/12 3/Oct/12 24/Oct/12 15/Dec/12 Planned 1/Jun/11 1/Jul/11 30/Aug/11 24/Dec/12 IIIMP/SHOPPING/G16- IBRD (70%) Cairo Center for 28 Supply of Angle Grinders Shopping Revised Post No 20/Dec/12 N/A 25/Dec/12 N/A 9/Jan/13 5,720.00 EGP 2012 GoE (30%) Tools&Machinery Actual 10/Sep/12 15/Sep/12 30/Sep/12 30/Sep/12 3/Oct/12 24/Oct/12 15/Dec/12 Planned 1/Jun/11 1/Jul/11 30/Aug/11 5/Nov/12 IIIMP/SHOPPING/G 17- IBRD (70%) Cairo Center for 29 Supply of Water Pumps Shopping Revised Post No 25/Dec/12 N/A 30/Dec/12 N/A 14/Jan/13 30,250.00 EGP 2012 GoE (30%) Tools&Machinery Actual 10/Sep/12 15/Sep/12 30/Sep/12 30/Sep/12 3/Oct/12 24/Oct/12 15/Dec/12 IBRD (70%) Planned 1/Jun/11 1/Jul/11 30/Aug/11 24/Dec/12 IIIMP/SHOPPING/G 18- Cairo Center for 30 Supply of Generators Shopping Revised Post No 25/Dec/12 N/A 30/Dec/12 N/A 14/Jan/13 68,200.00 EGP 2012 GoE (30%) Tools&Machinery Actual 10/Sep/12 15/Sep/12 30/Sep/12 30/Sep/12 3/Oct/12 24/Oct/12 6/Feb/13 Ongoing Review by Domestic Preparation of Bank’s No Bid Invitation Bid Closing Bid Opening BER Bank’s No Contract Package reference No/ Procurement Fund Estimated Bank Preference Bid Document Objection to Objection to Contract Contract Contract Name, City, and Completion SLNo Description of Goods Status Currency Contract No method Source(s) Cost Bidding BER and Signing (Date) Value Currency Country of Contractor (prior/post) (yes/no) (Date) Document (Date) (Date) (Date) (Date) Contract Award (Date) Supply, delivery, Installation and Planned 1/May/10 20/Mar/11 commissioning of Ultra Sonic Flow 1 IIIMP/ICB/G- 05-2009 ICB IBRD Revised Prior No 3,918,360.00 EGP Hydro Vision Gmbh. 31/Dec/13 Measurement Equipment Including Data Actual 9/Jul/09 9/Aug/09 6/Sep/09 4/Nov/09 4/Nov/09 28/Mar/10 31/Mar/10 3/Jun/10 Processing and Interpretation Software Planned 1/Jun/11 1/Jul/11 31/Jul/11 30/Aug/11 29/Jun/12 IIIMP/PMU/NCB/G20- IBRD (70%) Al-Ameen company for 2 Supply of PVC Pipes for Marwa NCB Revised Post No 10/Jul/13 9/Aug/13 8/Sep/13 8/Oct/13 2,055,000.00 EGP 6/Apr/14 2013 GoE (30%) PVC Pipes Actual 2/Jul/13 21/Aug/13 29/Aug/13 30/Sep/13 30/Sep/13 5/Nov/13 10/Nov/13 Planned Review by Domestic Preparation of Bank’s No Bid Invitation Bid Closing Bid Opening BER Bank’s No Contract Package reference No/ Procurement Fund Estimated Bank Preference Bid Document Objection to Objection to Contract Contract Contract Name, City, and Completion SL No Description of Goods Status Currency Contract No method Source(s) Cost Bidding BER and Signing (Date) Value Currency Country of Contractor (prior/post) (yes/no) (Date) Document (Date) (Date) (Date) (Date) Contract Award (Date) Procurement Plan for Electrification Work Updated 12/12/2013 (Meet Yazeed Area) Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Completed Bank’s&or Review by Domestic Preparation of Pmu No Bid Bid Opening BER Bank’s&or Pmu Contract Procuremen Bid Invitation Contract Signing Contract SL Package reference No/ Fund Bank Preference Bid Document Objection to Closing No Objection to Contract Name, City, and Country of Completion District Description of Works t Status Estimated Cost Currency Commencement Contract Value No Contract No Source(s) Bidding BER and Contract Currency Contractor method (Date) (Date) (Date) (prior/post) (yes/no) (Date) Document (Date) (Date) (Date) Award (Date) (Date) (Date) IIIMP/IIS/MTYZ/ELL&ELM- Low and Medium Volt Planned 1/Aug/10 1-Nov-10 The North Delta for electricity 27/Feb/11 1 Sidi Ghazy Direct GoE Revised n/a No 1,611,126.00 EGP 20/Jul/11 04-2010 Electrification Moheet distribution Actual 6/Apr/10 10/28/2010 10/28/2010 20/Jul/11 Total completed contracts Ongoing Bank’s&or Review by Domestic Preparation of Pmu No Bid Bid Opening BER Bank’s&or Pmu Contract Procuremen Bid Invitation Contract Signing Contract SL Package reference No/ Fund Bank Preference Bid Document Objection to Closing No Objection to Contract Name, City, and Country of Completion District Description of Works t Status Estimated Cost Currency Commencement Contract Value No Contract No Source(s) Bidding BER and Contract Currency Contractor method (Date) (Date) (Date) (prior/post) (yes/no) (Date) Document (Date) (Date) (Date) Award (Date) (Date) (Date) Gharb El- Planned 28/Apr/09 7/Jun/09 26/Jun/09 26/Jun/09 5/Jul/09 18/Jul/09 23/Jul/09 27/Aug/09 El-Sherka El-Ama General 25/Sep/11 IIIMP/IIS/MTYZ/ELM-01- Medium Volt Electrification for 1 Mahalla NCB GoE Revised n/a No 11,859,940.00 EGP Company for Electrical 25/Mar/13 2009 Gharb El-Mahalla +Qotor Actual 28/May/09 7/Jul/09 26/Jul/09 26/Jul/09 4/Aug/09 17/Aug/09 22/Aug/09 26-Sep-09 Projects (ELEGECT) 25/Jul/13 Gharb El- Planned 30/Jul/09 24/Aug/09 15/Sep/09 15/Sep/09 25/Sep/09 17/Oct/09 24/Oct/09 20/Nov/09 El-Sherka El-Ama General 19/Dec/11 IIIMP/IIS/MTYZ/ELL-01- Low Volt Electrification for Gharb 2 Mahalla NCB GoE Revised n/a No 11,296,244.00 EGP Company for Electrical 19/Apr/13 2009 El-Mahalla +Qotor Actual 29/Aug/09 23/Sep/09 15/Oct/09 15/Oct/09 25/Oct/09 16/Nov/09 23/Nov/09 20-Dec-09 Projects (ELEGECT) 20/Jul/13 Gharb El- Double Medium Volt Planned 15/Sep/09 24/Oct/09 14/Nov/09 14/Nov/09 23/Nov/09 5/Dec/09 8/Jan/10 17/Jan/10 Electoro ElHany for 15/Oct/10 IIIMP/IIS/MTYZ/ELM-02- 3 Mahalla Electrification for Gharb El- NCB GoE Revised n/a No 4,179,047.00 EGP Contracting and Electrical 9/Jun/11 2009 +Qotor Mahalla and Qotor Actual 15/Oct/09 23/Nov/09 14/Dec/09 14/Dec/09 23/Dec/09 4/Jan/10 7/Feb/10 16-Feb-10 installations Company 9/Jun/11 Sidi Ghazy Medium Volt Electrification for Planned 16/Jul/10 30/Jul/10 16/Aug/10 16/Aug/10 31/Aug/10 11/Sep/10 14/Sep/10 28/Oct/10 Electoro ElHany for 26/Nov/11 IIIMP/IIS/MTYZ/ELM-03- 4 + Kafr El Marsa EL Gamal & El Zawya NCB GoE Revised n/a No 8,385,222.50 EGP Contracting and Electrical 26/Apr/13 2010 Shiekh (Phase 1) Actual 15/Aug/10 29/Aug/10 15/Sep/10 15/Sep/10 30/Sep/10 11/Oct/10 14/Oct/10 11/27/2010 installations Company 26/Nov/13 Planned 4/Apr/12 4/May/12 3/Jun/12 07/03/2011 Electoro ElHany for 7/May/12 Kafr El- IIIMP/IIS/MTYZ/ELL-02- Low Volt Electrification for Marsa 5 NCB GoE Revised n/a No 8,785,382.45 EGP Contracting and Electrical 7/May/13 Sheikh 2010 EL Gamal & El Zawya (Phase 1) Actual 25/Nov/10 25/Dec/10 16/Jan/11 16/Jan/11 20/Jan/11 15/Mar/11 29/Mar/11 8/May/11 installations Company 7/Nov/13 Sidi Ghazy IBRD Planned 1/Dec/12 8/Dec/12 29/Dec/12 29/Dec/12 13/Jan/13 28/Jan/13 12/Feb/13 14/Mar/13 29/Jul/14 IIIMP/IIS/MTYZ/ELL-03- Low Volt Electrification for Kafr El El Alamia for Engineering & 6 + Kafr El NCB (90%)GoE Revised Post No 1/Mar/13 8/Mar/13 24/Mar/13 21/Apr/13 21/Apr/13 1/Jun/13 16/Jun/13 16/Jul/13 31/Jul/13 4,544,748.00 EGP 2013 Shiekh 1 (El Halafy) Contracting Shiekh (10%) Actual 7/Feb/13 3/Mar/13 17/Mar/13 16/Apr/13 16/Apr/13 30/May/13 27/Jun/13 30/Jul/13 30/Jul/13 Sidi Ghazy IBRD Planned 20/Nov/12 27/Nov/12 18/Dec/12 18/Dec/12 2/Jan/13 17/Jan/13 1/Feb/13 3/Mar/13 29/Jul/14 Medium Volt Electrification for El Alamia for Engineering & 7 + Kafr El IIIMP/IIS/MTYZ/ELM-04 NCB (90%)GoE Revised Post No 20/Mar/13 27/Mar/13 24/Mar/13 21/Apr/13 21/Apr/13 1/Jun/13 16/Jun/13 16/Jul/13 31/Jul/13 5,248,887.52 EGP Kafr El Shiekh 1 (El Halafy) 7/Feb/13 3/Mar/13 17/Mar/13 17/Apr/13 17/Apr/13 30/May/13 27/Jun/13 30/Jul/13 30/Jul/13 Contracting Shiekh (10%) Actual Sidi Ghazy IBRD Planned 10/Dec/12 17/Dec/12 7/Jan/13 7/Jan/13 22/Jan/13 6/Feb/13 21/Feb/13 23/Mar/13 29/Jul/14 IIIMP/IIS/MTYZ/ELM-05- Medium Volt Electrification for El Alamia for Engineering & 8 + Kafr El NCB (90%)GoE Revised Post No 10/Mar/13 17/Mar/13 24/Mar/13 21/Apr/13 21/Apr/13 1/Jun/13 16/Jun/13 16/Jul/13 31/Jul/13 3,845,427.77 EGP 2013 Kafr El Shiekh 2 (Feeder) Contracting Shiekh (10%) Actual 7/Feb/13 3/Mar/13 17/Mar/13 18/Apr/13 18/Apr/13 30/May/13 27/Jun/13 30/Jul/13 30/Jul/13 Total ongoing contracts Planned Bank’s&or Review by Domestic Preparation of Pmu No Bid Bid Opening BER Bank’s&or Pmu Contract Procuremen Bid Invitation Contract Signing Contract SL Package reference No/ Fund Bank Preference Bid Document Objection to Closing No Objection to Contract Name, City, and Country of Completion District Description of Works t Status Estimated Cost Currency Commencement Contract Value No Contract No Source(s) Bidding BER and Contract Currency Contractor method (Date) (Date) (Date) (prior/post) (yes/no) (Date) Document (Date) (Date) (Date) Award (Date) (Date) (Date) Sidi Ghazy Medium Volt Electrification for the IBRD Planned 1/Jul/13 8/Jul/13 29/Jul/13 29/Jul/13 13/Aug/13 28/Aug/13 12/Sep/13 12/Oct/13 12/Oct/14 1 + Kafr El IIIMP/IIS/MTYZ/ELM-06 rest of Kafr El Shiekh 3 NCB (90%)GoE Revised Post No 1/Jul/13 8/Jul/13 1/Feb/14 1/Mar/14 1/Mar/14 22/Mar/14 6/Apr/14 6/May/14 21/May/14 20/May/15 Shiekh (Daramally) (10%) Actual 9/Oct/13 12/Nov/13 Sidi Ghazy IBRD Planned 1/Dec/13 8/Dec/13 29/Dec/13 29/Dec/13 13/Jan/14 28/Jan/14 12/Feb/14 14/Mar/14 14/Mar/15 Low Volt Electrification for Kafr El 2 + Kafr El IIIMP/IIS/MTYZ/ELL-04 NCB (90%)GoE Revised Post No 1/Jul/13 8/Jul/13 1/Feb/14 1/Mar/14 1/Mar/14 22/Mar/14 6/Apr/14 6/May/14 21/May/14 20/May/15 Shiekh 2 (Daramally) Shiekh (10%) Actual 9/Oct/13 12/Nov/13 Electric connections for the Planned 1/Mar/12 16/Mar/12 30/Jan/00 28/Nov/12 3 Various Ultrasonic equipment sites at Direct GoE Revised Post No 1/Aug/12 16/Aug/12 30/Aug/12 1/Jun/14 Meet Yazeed- South Actual Done Done Done N/A N/A N/A N/A Done Electric connections for the Planned 1/Mar/12 16/Mar/12 30/Jan/00 28/Nov/12 4 Various Ultrasonic equipment sites at Direct GoE Revised Post No 15/Aug/12 30/Aug/12 6/Sep/12 1/Jun/14 Meet Yazeed- North Actual Done Done Done N/A N/A N/A N/A Done Procurement Plan for Main Canal Updated 12/12/2013 Rehabilitation Works (Meet Yazid Area) Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Completed Bank’s&or Pmu Review by Domestic Bid Bid Opening BER Bank’s&or Pmu Contract Contract Preparation of No Objection to Bid Invitation Contract Package reference No/ Procurement Fund Bank Preference Closing No Objection to Signing Contract Name, City, and Country of Completion SL No District Description of Works Status Estimated Cost Currency Bid Document Bidding Commencement Contract Value Contract No method Source(s) BER and Contract Currency Contractor (Date) Document (Date) (Date) (prior/post) (yes/no) (Date) (Date) (Date) Award (Date) (Date) (Date) (Date) Total completed contracts Ongoing Bank’s&or Pmu Review by Domestic Bid Bid Opening BER Bank’s&or Pmu Contract Contract Preparation of No Objection to Bid Invitation Contract Package reference No/ Procurement Fund Bank Preference Closing No Objection to Signing Contract Name, City, and Country of Completion SL No District Description of Works Status Estimated Cost Currency Bid Document Bidding Commencement Contract Value Contract No method Source(s) BER and Contract Currency Contractor (Date) Document (Date) (Date) (prior/post) (yes/no) (Date) (Date) (Date) Award (Date) (Date) (Date) (Date) IBRD Planned 1/Feb/11 3/Mar/11 2/Apr/11 2/Apr/11 2/May/11 28/Feb/14 IIIMP/MAIN-CANAL/MTYZ/3- Stabilize Embankments at km 24.330 Egyptian Integrated for 1 Qotor NCB (90%)GoE Revised Post No 15/Sep/12 15/Dec/12 14/Jan/13 14/Jan/13 16/Mar/13 23/Mar/13 1,418,250.00 EGP 2012 to km 26.754 contracting(Medeco) (10%) Actual 6/Sep/12 12/Sep/12 15/Dec/12 15/Jan/13 15/Jan/13 1/Apr/13 24/Apr/13 28/Apr/13 Raise & Widen Embankments of Meet Planned 15/Feb/11 17/Mar/11 16/Apr/11 16/Apr/11 16/May/11 18/Apr/14 Yazeed Canal at Different Locations IBRD Revised 15/Sep/12 15/Dec/12 14/Jan/13 14/Jan/13 17/Mar/13 24/Mar/13 IIIMP/MAIN-CANAL/MTYZ/4- moradex Company for 2 Qotor From Km 21.500 to Km 34.00 & NCB (90%)GoE Actual Post No 3/Oct/12 5/Nov/12 15/Dec/12 16/Jan/13 16/Jan/13 Retendering 6,761,000.00 EGP 2012 Construction Removal of Remains at Bridge Mit (10%) Revised 18/Mar/13 1/Apr/13 1/May/13 1/May/13 1/Jun/13 8/Jun/13 15/Jun/13 22/Jun/13 Yazid km 33+160 Actual 18/Mar/13 18/Mar/13 11/Apr/13 13/May/13 13/May/13 2/Jul/13 28/Jul/13 19/Aug/13 19/Aug/13 IBRD Planned 28/Feb/11 30/Mar/11 29/Apr/11 29/Apr/11 29/May/11 19/Nov/12 Kafr El- IIIMP/MAIN- Embankment Stability El Zawia at km Abo Taleb Company for 3 NCB (90%)GoE Revised Post No 10/Dec/12 15/Dec/12 14/Jan/13 14/Jan/13 16/May/13 23/May/13 30/May/13 6/Jun/13 8,816,053.06 EGP 5/Apr/14 Sheikh CANAL/MTYZ/10-2013 19.110 - 19.730 Contracting (10%) Actual 5/Nov/12 16/Nov/12 9/Feb/13 13/Mar/13 13/Mar/13 19/May/13 IBRD Planned 28/Feb/11 30/Mar/11 29/Apr/11 29/Apr/11 29/May/11 19/Nov/12 Kafr El- IIIMP/MAIN- Embankment Stability El Zawia at km 4 NCB (90%)GoE Revised Post No 20/Dec/12 15/Dec/12 14/Jan/13 14/Jan/13 16/May/13 23/May/13 30/May/13 6/Jun/13 8,768,147.20 EGP Manetso Masr for Contracting 5/Apr/14 Sheikh CANAL/MTYZ/11-2013 19.730 -20.360 (10%) Actual 5/Nov/12 16/Nov/12 9/Feb/13 14/Mar/13 14/Mar/13 19/May/13 Total ongoing contracts Planned Bank’s&or Pmu Review by Domestic Bid Bid Opening BER Bank’s&or Pmu Contract Contract Preparation of No Objection to Bid Invitation Contract Package reference No/ Procurement Fund Bank Preference Closing No Objection to Signing Contract Name, City, and Country of Completion SL No District Description of Works Status Bid Document Bidding Commencement Contract Value Contract No method Source(s) BER and Contract Currency Contractor (Date) Document (Date) (Date) (prior/post) (yes/no) (Date) (Date) (Date) Award (Date) (Date) (Date) (Date) IBRD Planned 1/Jan/11 1/Jun/11 1/Jul/11 1/Jul/11 31/Jul/11 28/Nov/11 Gharb El IIIMP/MAIN-CANAL/MTYZ/1- Repair Road Bridge at Mit-Yazid km 1 NCB (90%)GoE Revised Post No 15/Dec/12 14/Jan/13 14/Jan/13 4/Mar/13 11/Mar/13 18/Mar/13 25/Mar/13 24/Jul/13 Mahalla 2012 4+745 (10%) Actual 20/Jul/11 4/Oct/11 15/Dec/12 17/Jan/13 17/Jan/13 16/May/13 Retendering Revised 1/Feb/14 3/Mar/14 3/Mar/14 2/Apr/14 17/Apr/14 2/May/14 9/May/14 7/Sep/14 Actual IBRD Planned 28/Feb/11 30/Mar/11 29/Apr/11 29/Apr/11 29/May/11 24/Mar/13 Kafr El- Embankment Stability Meet Yazeed 2 IIIMP/MAIN-CANAL/MTYZ/6- Cancelled (90%)GoE Revised Post No 15/Nov/12 1/Apr/14 2/May/14 2/May/14 1/Jun/14 16/Jun/14 1/Jul/14 8/Jul/14 7/May/15 Sheikh km 61.300 - 62.100 (10%) Actual 4/Nov/12 16/Nov/12 IBRD Planned 28/Feb/11 30/Mar/11 29/Apr/11 29/Apr/11 29/May/11 24/Mar/13 Kafr El- Embankment Stability Meet Yazeed km 3 IIIMP/MAIN-CANAL/MTYZ/7- Cancelled (90%)GoE Revised Post No 15/Nov/12 1/Apr/14 2/May/14 2/May/14 1/Jun/14 16/Jun/14 1/Jul/14 8/Jul/14 7/May/15 Sheikh 61.800 - 62.600 (10%) Actual 4/Nov/12 16/Nov/12 IBRD Planned 28/Feb/11 30/Mar/11 29/Apr/11 29/Apr/11 29/May/11 24/Mar/13 Kafr El- Embankment Stability Meet Yazeed 4 IIIMP/MAIN-CANAL/MTYZ/8- Cancelled (90%)GoE Revised Post No 15/Nov/12 1/Apr/14 2/May/14 2/May/14 1/Jun/14 16/Jun/14 1/Jul/14 8/Jul/14 7/May/15 Sheikh km 62.600 - 63.300 (10%) Actual 4/Nov/12 16/Nov/12 Inspection and Rehabilitation of Beltag Done by force IIIMP/MAIN-CANAL/MTYZ/2- 5 Qotor Siphons at Samatay and Beltag,Mit account and Samaty 2012 Yazid Km 19-21 investigation done Cancelled 6 Qotor IIIMP/MAIN-CANAL/MTYZ/5- Scour at bridge Mit Yazid km33+160 Included in another contract Cancelled IBRD Planned 15/Mar/11 14/Apr/11 14/May/11 14/May/11 13/Jun/11 4/Dec/12 Kafr El- Raising Embankment El Zawia LS km 7 IIIMP/MAIN-CANAL/MTYZ/9- Cancelled (90%)GoE Revised Post No 25/Feb/14 27/Mar/14 26/Apr/14 26/Apr/14 12/May/14 19/May/14 26/May/14 2/Jun/14 26/Aug/15 Sheikh 3.7-4.0 and km 6.20-7.80 (10%) Actual Under Planned 1/Jan/12 31/Jan/12 1/Mar/12 1/Mar/12 31/Mar/12 30/Sep/12 IBRD Gharb El IIIMP/MAIN- Scour at bridge cluster at Mit Yazid km investig. Revised 1/Apr/14 1/May/14 31/May/14 31/May/14 16/Jun/14 23/Jun/14 30/Jun/14 7/Jul/14 3/Jan/15 8 (90%)GoE Post No Mahalla CANAL/MTYZ/12- 4+721 stable or Under (10%) Actual active investigation IBRD Planned 5/Jan/12 4/Feb/12 5/Mar/12 5/Mar/12 4/Apr/12 3/Mar/14 Gharb El IIIMP/MAIN- Replacement of siphon at Samatai, km 9 NCB (90%)GoE Revised Post No 15/Feb/14 17/Mar/14 16/Apr/14 16/Apr/14 1/Jun/14 8/Jun/14 15/Jun/14 22/Jun/14 20/Dec/15 Mahalla CANAL/MTYZ/13- 19+777 (10%) Actual IBRD Planned 20/Dec/12 25/Dec/12 8/Feb/13 10/Mar/13 Gharb El IIIMP/MAIN- Scour at Samatai Siphon at Mit Yazid 1/May/14 31/May/14 31/May/14 16/Jun/14 23/Jun/14 30/Jun/14 16/May/14 15/Jul/14 10 Cancelled (90%)GoE Revised Post No Mahalla CANAL/MTYZ/14- km 19+777 (10%) Actual 28/Feb/13 PS Contract No. IIIMP/MAIN-CANAL/MTYZ/14 will be funded by Gov or included with Contract No. IIIMP/MAIN-CANAL/MTYZ/13 Procurement Plan for Branch Canal Updated 12/12/2013 Rehabilitation Works (Meet Yazeed Area) Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Completed Bank’s&or Pmu Review by Domestic Preparation of Bank’s&or Pmu Bid Invitation Bid Bid Opening BER No Objection to Contract Signing Contract Package reference No/ Procurement Fund Bank Preference Bid Document No Objection to Closing Contract Name, City, and Country of SL No District Description of Works Status Estimated Cost Currency BER and Commenceme Contract Value Contract No method Source(s) Bidding Document Currency Contractor Contract Award (Date) nt (Date) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Mesqa intake contract for Mit Yazid Planned 26/Jun/07 14/Jul/07 21/Jul/07 15/Aug/07 15/Aug/07 8/Sep/07 3/Oct/07 24/Oct/07 Gharb El- IBRD (70%) Adel Abdel Azez El- Shahawy 1 IIIMP/IIS/MITYZ/W01-2008 direct NCB Revised Prior No 1,536,757.20 EGP Mahalla GoE (30%) Company Right from intake to km 21.600 Actual 18/Sep/07 28/Nov/07 9/Feb/08 1/Mar/08 1/Mar/08 27/Mar/08 6/Apr/08 21/Apr/08 22/Apr/08 Mesqa intake contract for Mit Yazid Planned 26/Jun/07 14/Jul/07 21/Jul/07 15/Aug/07 15/Aug/07 8/Sep/07 3/Oct/07 30/Oct/07 Gharb El- direct IBRD (70%) Adel Abdel Azez El- Shahawy 2 IIIMP/IIS/MTYZ/W02-2008 NCB Revised Prior No 2,707,429.19 EGP Mahalla Left from intake to km 21.601 & Nisheel GoE (30%) Company Actual 10/Oct/07 3/Jan/08 9/Feb/08 2/Mar/08 2/Mar/08 25/Mar/08 6/Apr/08 21/Apr/08 22/Apr/08 El-Gededa & Khadiga Planned 26/Jun/07 2/Jul/07 14/Jul/07 21/Jul/07 15/Aug/07 8/Sep/07 22/Sep/07 3/Oct/07 Gharb El- Improvement of Works for Nesheel Canal IBRD (70%) Ibrahem Mohammed Abo Borda 3 IIIMP/IIS/MTYZ/W03-2008 NCB Revised Prior No 4,701,350.00 EGP Mahalla and its Branches GoE (30%) Office Actual 25/Nov/08 1/Dec/08 18/Dec/08 17/Jan/09 17/Jan/09 3/Mar/09 24/Mar/09 30/Apr/09 9/May/09 Planned 26/Jun/07 14/Jul/07 21/Jul/07 15/Aug/07 15/Aug/07 8/Sep/07 3/Oct/07 24/Oct/07 Gharb El- Mesqa Intakes along Bahr Nemra El- IBRD (70%) 4 IIIMP/IIS/MTYZ/W04-2008 NCB Revised Prior No 3,640,600.00 EGP El Asar Office for Contracting Mahalla Banwan & Ahmed Basha Rashid Canals GoE (30%) Actual 18/Sep/07 21/Nov/07 9/Feb/08 3/Mar/08 3/Mar/08 25/Mar/08 6/Apr/08 21/Apr/08 21/Apr/08 Improvement of Mesqa intakes on Planned 1/Jan/11 1/Apr/11 Kafr El- Mares EL - Gamle from head to km IBRD (70%) 5 IIIMP/IIS/MTYZ/W05-2010 NCB Revised Prior No 1/Jul/10 5,854,660.00 EGP El Asar Office for Contracting Sheikh 10.000& Kafr EL Morabeen& El Bashair& GoE (30%) Actual 9/May/10 13/May/10 22/May/10 22/Jun/10 22/Jun/10 1/Jul/10 21/Jul/10 15/Sep/10 15/Sep/10 Mafroza El Sheikh ( KafrWorks Mesqa intake for District - Kafr El EL - Shamarka Planned 15/Jun/11 Kafr El- EL - Gedida & Shorafa canals and IBRD (70%) Cooperative Society for 6 IIIMP/IIS/MTYZ/W06-2010 NCB Revised Prior No 1,221,750.00 EGP Sheikh Direct El Zawia canal Right Side from km GoE (30%) Architectural Works Actual 22/Sep/10 6/Dec/10 18/Dec/10 31/Jan/11 31/Jan/11 28/Feb/11 23/May/11 10/Jul/11 10/Jul/11 5.963 to 6.252 Mit Yazeed Command Preparation of civil works for ultrasonic Planned 15/Feb/11 1/Jun/11 1/Jul/11 1/Jul/11 31/Jul/11 IBRD (70%) 7 Various IIIMP/IS/MTYZ/W2 2011 flow meters and water levels equipment NCB Revised Post No 30/Sep/11 1/Oct/11 1,140,068.75 EGP Eng. Abrahem Abo Bourda Office GoE (30%) along meet yazeed canal and its Actual 3/Mar/11 N/A 9/Apr/11 9/May/11 9/May/11 N/A 10/Aug/11 10/Aug/11 Total completed contracts Ongoing Bank’s&or Pmu Review by Domestic Preparation of Bank’s&or Pmu Bid Invitation Bid Bid Opening BER No Objection to Contract Signing Contract Package reference No/ Procurement Fund Bank Preference Bid Document No Objection to Closing Contract Name, City, and Country of SL No District Description of Works Status Estimated Cost Currency BER and Commenceme Contract Value Contract No method Source(s) Bidding Document Currency Contractor Contract Award (Date) nt (Date) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Mesqa intakes contract for El Zawia Planned 2/Jun/11 2/Jul/11 1/Aug/11 1/Aug/11 31/Aug/11 15/Sep/11 Kafr El- Right Side Ganabias No. 2,3,4 and the IBRD (70%) Revised 9/Nov/10 21/Jul/11 20/Aug/11 20/Aug/11 19/Nov/11 26/Nov/11 Cooperative Socicty for 1 IIIMP/IIS/MTYZ/W-07-2010 NCB Prior No 4,030,495.50 EGP Sheikh Branch of Ganabia 3, and the Al Zawia GoE (30%) Construction &Development Actual 27/Jan/11 7/Jul/11 25/Jul/11 25/Aug/11 25/Aug/11 16/Oct/11 19/Oct/11 1/Dec/11 1/Dec/11 Left Side Ganabias No. 2,3,4,5,6 and Planned 3/Jun/11 3/Jul/11 2/Aug/11 2/Aug/11 1/Sep/11 16/Sep/11 Gharb El- Bahr Nemra and Other Branch Canals IBRD (70%) 2 IIIMP/IIS/MTYZ/W08/2012 NCB Revised Prior No 1/Feb/12 2/Mar/12 2/Mar/12 1/Apr/12 8/Apr/12 6,137,721.00 EGP El Asar Office for contracting Mahalla Rehabilitation Mit Yazid Command Area GoE (30%) Actual 2/May/11 18/Oct/11 4/Jan/12 6/Feb/12 6/Feb/12 11/Mar/12 12/Mar/12 21/Apr/12 21/Apr/12 Planned 5/Jun/11 5/Jul/11 4/Aug/11 4/Aug/11 3/Sep/11 18/Sep/11 Revised 1/Feb/12 2/Mar/12 2/Mar/12 1/Apr/12 8/Apr/12 IBRD Kafr El- Dakalt and Other Branch Canals Revised 2/May/11 18/Oct/11 4/Jan/12 7/Feb/12 7/Feb/12 19/Mar/12 20/Mar/12 Tender Cancelled 3 IIIMP/IIS/MTYZ/W09-2012 NCB (90%)GoE Post No 8,994,600.00 EGP Ahmed Abo Eleneen Sheikh Rehabilitation Mit Yazid Command Area (10%) Revised 10/Oct/12 9/Nov/12 9/Nov/12 8/Apr/13 15/Apr/13 Actual 19/Mar/12 20/Mar/12 Done 17/Nov/12 17/Nov/12 19/Mar/12 20/Mar/12 17/Oct/12 17/Nov/12 17/Nov/12 17/Mar/13 31/Mar/13 30/Apr/13 2/May/13 NesheelEl Gedeeda and El Shoka 1/Mar/12 31/Mar/12 30/Apr/12 30/Apr/12 30/May/12 6/Jun/12 Gharb El- IBRD (90%)GoE Planned 4 IIIMP/IIS/MTYZ/W10-A Branch Canals Rehabilitation Mit Yazid NCB Revised Post No 15/Aug/12 14/Sep/12 14/Oct/12 14/Oct/12 1/Apr/13 8/Apr/13 2,658,275.00 EGP El Asar Office for contracting Mahalla (10%) Command Area Actual 23/Aug/12 12/Sep/12 17/Oct/12 18/Nov/12 18/Nov/12 16/Dec/12 18/Feb/13 1/Apr/13 1/Apr/13 1/Mar/12 31/Mar/12 30/Apr/12 30/Apr/12 30/May/12 6/Jun/12 Kafr El- Mars El Gamal and Other Canals IBRD (90%)GoE Planned Al-Amro Office for Contracting 5 IIIMP/IIS/MTYZ/W10-B-2012 NCB Revised Post No 15/Sep/12 20/Nov/12 20/Dec/12 20/Dec/12 29/Mar/13 5/Apr/13 1,842,968.89 EGP Sheikh Rehabilitation Mit Yazid Command Area (10%) Actual 4/Oct/12 5/Nov/12 5/12/25012 15/Jan/13 15/Jan/13 21/Jan/13 18/Feb/13 24/Mar/13 24/Mar/13 Koum EL Roz El Kadeema and Other Planned 1/Mar/12 31/Mar/12 30/Apr/12 30/Apr/12 30/May/12 6/Jun/12 Kafr El- IBRD (90%)GoE Cooperative Socicty for 6 IIIMP/IIS/MTYZ/W10-C-2012 Canals Rehabilitation Mit Yazid NCB Revised Post No 10/Sep/12 10/Oct/12 9/Nov/12 9/Nov/12 24/Mar/13 31/Mar/13 4,417,252.00 EGP Sheikh (10%) Construction &Development Command Area Actual 5/Sep/12 13/Sep/12 17/Oct/12 19/Nov/12 19/Nov/12 16/Dec/12 18/Feb/13 23/Mar/13 24/Mar/13 1/Mar/12 31/Mar/12 30/Apr/12 30/Apr/12 30/May/12 6/Jun/12 Kafr El- El Halafy and Other Branch Canals IBRD (90%)GoE Planned 7 IIIMP/IIS/MTYZ/W11-2012 NCB Revised Post No 15/Sep/12 20/Nov/12 20/Dec/12 20/Dec/12 1/Apr/13 8/Apr/13 5,111,825.00 EGP el Amana for General Contracting Sheikh Rehabilitation Mit Yazid Command Area (10%) Actual 4/Oct/12 5/Nov/12 7/Dec/12 6/Jan/13 6/Jan/13 21/Jan/13 4/Mar/13 1/Apr/13 1/Apr/13 Total ongoing contracts Planned Bank’s&or Pmu Review by Domestic Preparation of Bank’s&or Pmu Bid Invitation Bid Bid Opening BER No Objection to Contract Signing Contract Package reference No/ Procurement Fund Bank Preference Bid Document No Objection to Closing Contract Name, City, and Country of SL No District Description of Works Status Estimated Cost Currency BER and Commenceme Contract Value Contract No method Source(s) Bidding Document Currency Contractor Contract Award (Date) nt (Date) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Procurement Plan for Branch CanalUpdated 12/12/2013 Rehabilitation Works (Meet Yazeed Area) Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Completed Contract Package reference No/ Completion SL No District Contract No (Date) 14/Mar/09 Gharb El- 1 IIIMP/IIS/MITYZ/W01-2008 20/Oct/09 Mahalla 1/Mar/10 14/Mar/09 Gharb El- 2 IIIMP/IIS/MTYZ/W02-2008 20/Apr/09 Mahalla 20/Oct/09 8/May/10 Gharb El- 3 IIIMP/IIS/MTYZ/W03-2008 Mahalla 8/May/10 20/Apr/09 Gharb El- 4 IIIMP/IIS/MTYZ/W04-2008 20/Jun/09 Mahalla 20/Jun/09 14/Jul/11 Kafr El- 5 IIIMP/IIS/MTYZ/W05-2010 Sheikh 13/Oct/11 9/Mar/12 Kafr El- 6 IIIMP/IIS/MTYZ/W06-2010 9/Mar/13 Sheikh 9/Dec/12 6/Feb/12 7 Various IIIMP/IS/MTYZ/W2 2011 5/Mar/13 5/Jan/13 Total completed contracts Ongoing Contract Package reference No/ Completion SL No District Contract No (Date) 30/Sep/12 Kafr El- 31/Dec/12 1 IIIMP/IIS/MTYZ/W-07-2010 Sheikh 20/Mar/13 Gharb El- 2 IIIMP/IIS/MTYZ/W08/2012 20/Mar/13 Mahalla 16/Mar/12 Kafr El- 3 IIIMP/IIS/MTYZ/W09-2012 Sheikh 29/Mar/14 30/Nov/13 Gharb El- 4 IIIMP/IIS/MTYZ/W10-A Mahalla 23/Nov/13 Kafr El- 5 IIIMP/IIS/MTYZ/W10-B-2012 Sheikh 23/Feb/14 Kafr El- 6 IIIMP/IIS/MTYZ/W10-C-2012 Sheikh 27/Feb/14 Kafr El- 7 IIIMP/IIS/MTYZ/W11-2012 Sheikh Total ongoing contracts Planned Contract Package reference No/ Completion SL No District Contract No (Date) Procurement Plan for Meska Improvement Updated 12/12/2013 Rehabilitation Works (Meet Yazeed Area) Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Completed Area Review by Domestic Preparation of Bid Invitation Bid Bid Opening BER Bank’s&or Pmu No Contract Bank’s&or Pmu No Contract Signing Contract Package reference No/ Procurement Fund Bank Preference Bid Document Closing Objection to BER Contract Name, City, and Country of Completion SL No District Description of Works Status Estimated Cost Currency Objection to Bidding Commencement Contract Value Contract No method Source(s) and Contract Award Currency Contractor Document (Date) (Date) (Date) (fed) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Planned 1/Oct/09 11/Oct/09 27/Jun/09 28/Jul/09 28/Jul/09 5/Aug/09 19/Aug/09 10/Jan/10 9/Jul/10 Gharb El- Meska Improvement Works for Bahr Nemra Left IBRD (70%) Al-Amro Office for Contracting 1 IIIMP/IIS/MTYZ/MQ-02-2009 990 NCB Revised Prior No 3/May/09 19/Mar/09 15/Apr/09 15/May/09 15/May/09 10/Oct/09 18/Oct/09 18/Nov/09 5,229,560.00 EGP 31/Dec/10 Mahalla Side from Intake to the Km 4.8 GoE (30%) Actual 28/Apr/09 24/May/09 27/Jun/09 27/Jul/09 27/Jul/09 13/Aug/09 17/Aug/09 10/Sep/09 10/Sep/09 30/Dec/10 Gharb El- Meska Improvement Works for Bahr Nemra IBRD (70%) Planned 1/Apr/09 11/Apr/09 18/Apr/09 19/May/09 19/May/09 19/Jun/09 2/Sep/09 14/Sep/09 Al-Amro Office for Contracting 9/Jul/10 2 IIIMP/IIS/MTYZ/MQ-03-2009 1,447 NCB Revised Prior No 7,995,413.30 EGP 31/Dec/10 Mahalla Right Side from Intake to the Km 4.8 GoE (30%) Actual 30/Apr/09 24/May/09 27/Jun/09 28/Jul/09 28/Jul/09 13/Aug/09 19/Aug/09 10/Sep/09 10/Sep/09 31/Dec/10 Mesqa Improvement Works in El Banawan Planned 3/Jan/10 13/Jan/10 20/Jan/10 21/Feb/10 21/Feb/10 21/Mar/10 4/Apr/10 18/Apr/10 2/Aug/10 Gharb El- IBRD (70%) Al-Amro Office for Contracting 3 IIIMP/IIS/MTYZ/MQ-06-2009 Branch Canal - Left Side from the intake to the 1,218 NCB Revised Prior No 23/Aug/09 12/Oct/09 26/Oct/09 7,049,083.00 EGP Mahalla GoE (30%) End Actual 21/Jun/09 23/Jun/09 8/Jul/09 9/Aug/09 9/Aug/10 23/Aug/09 30/Aug/09 3/Oct/09 3/Oct/09 19/Jul/10 Improvement of Mesqas and Delivery Works for Planned 1/Jun/12 1/Jul/12 31/Jul/12 31/Jul/12 30/Aug/12 6/Sep/12 25/Dec/10 IBRD (70%) Al-Amro Office for Contracting 4 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-09-2009 Al Mohet canal (Sidi Gazi District - Kafr Elshiekh 1,001 NCB Revised Prior No 1/Jan/11 1/Mar/11 5,283,708.00 EGP 25/Feb/11 GoE (30%) ) Actual 21/Jul/09 23/Aug/09 10/Feb/10 10/Mar/10 10/Mar/10 21/Mar/10 31/Mar/10 26/Apr/10 26/Apr/10 25/Feb/11 Mesqa Improvement Works in Nesheel El- Planned 1/Oct/09 12/Oct/09 19/Oct/09 19/Nov/09 19/Nov/09 19/Dec/09 2/Jan/10 22/Jan/10 Abnaa Ahmed Hamed Samaha 1/Sep/10 Gharb El- IBRD (70%) 5 IIIMP/IIS/MTYZ/MQ-10-2009 Kadima Branch Canal Right Bank from the 1,109 NCB Revised Prior No 30/Aug/09 18/Oct/09 7,824,367.20 EGP Company 1/Jan/11 Mahalla GoE (30%) Intake to the End Actual 13/Aug/09 1/Sep/09 12/Sep/09 13/Oct/09 13/Oct/09 8/Nov/09 23/Nov/09 2/Jan/10 2/Jan/10 Alexandria 1/Jan/11 Meska Improvement Works in Neshil El-Kadima Planned 1/Oct/09 12/Oct/09 19/Oct/09 19/Nov/09 19/Nov/09 19/Dec/09 2/Jan/10 22/Jan/10 25/Aug/10 Gharb El- IBRD (70%) Al-Huda Company for Contracting 6 IIIMP/IIS/MTYZ/MQ-11-2009 Branch canal Left bank from Km 8.145 to the 910 NCB Revised Prior No 5,745,916.80 EGP 25/Jan/11 Mahalla GoE (30%) end Actual 13/Aug/09 1/Sep/09 12/Sep/09 14/Oct/09 14/Oct/09 29/Oct/09 23/Nov/09 26/Dec/09 26/Dec/09 25/Jan/11 Planned 1/Oct/09 12/Oct/09 19/Oct/09 19/Nov/09 19/Nov/09 19/Dec/09 2/Jan/10 22/Jan/10 19/Sep/10 Gharb El- Mesqa Improvement Works for Waslet Nesheel IBRD (70%) Al-Amro Office for Contracting 7 IIIMP/IIS/MTYZ/MQ-13-2009 1,028 NCB Revised Prior No 5,494,475.00 EGP 19/Jan/11 Mahalla and El-Shiekha Branch canals GoE (30%) Actual 16/Sep/09 18/Oct/09 7/Nov/09 6/Dec/09 6/Dec/09 27/Dec/09 5/Jan/10 20/Jan/10 20/Jan/10 19/Jan/11 Mesqa Improvement Works for Nesheel El- Planned 1/Nov/09 12/Nov/09 19/Nov/09 20/Dec/09 20/Dec/09 20/Jan/10 3/Feb/10 17/Feb/10 14/Nov/10 Gharb El- IBRD (70%) 8 IIIMP/IIS/MTYZ/MQ-14-2009 Kadima Branch canal Left bank from intake to 944 NCB Revised Prior No 5,494,892.60 EGP El- Aaser for Contracting 14/Jan/11 Mahalla GoE (30%) Km 8.145 Actual 22/Nov/09 8/Dec/09 22/Dec/09 19/Jan/10 19/Jan/10 4/Feb/10 21/Feb/10 15/Mar/10 15/Mar/10 14/Jan/11 Mesqa Improvement Works for Bahr Nemra Planned 1/Oct/09 11/Oct/09 18/Oct/09 19/Nov/09 19/Nov/09 19/Dec/09 2/Jan/10 14/Jan/10 9/Nov/10 Gharb El- IBRD (70%) Adel Abdel Azez El- Shahawy 9 IIIMP/IIS/MTYZ/MQ-15-2009 Branch canal left Bank from km. 4.800 to km 834 NCB Revised Prior No 3,643,182.50 EGP Mahalla GoE (30%) Company 7.000 Actual 18/Nov/09 7/Dec/09 22/Dec/09 20/Jan/10 20/Jan/10 4/Feb/10 21/Feb/10 10/Mar/10 10/Mar/10 9/Nov/10 Planned 3/May/10 13/May/10 20/May/10 21/Jun/10 21/Jun/10 21/Jul/10 4/Aug/10 18/Aug/10 9/Nov/10 Gharb El- Mesqa Improvement Works for Direct Mit Yazid IBRD (70%) Upper Egypt General Contracting 10 IIIMP/IIS/MTYZ/MQ-16-2009 978 NCB Revised Prior No 4,352,865.00 EGP 8/Jan/11 Mahalla canal Right Bank from KM 12.480 to KM 19.900 GoE (30%) Company Actual 18/Nov/09 8/Dec/09 21/Dec/09 21/Jan/10 21/Jan/10 4/Feb/10 21/Feb/10 10/Mar/10 10/Mar/10 Completed Mesqas Improvement Works for Direct Mit Yazid Planned 1/Mar/10 15/Mar/10 31/Mar/10 30/Apr/10 30/Apr/10 30/May/10 6/Jun/10 25/Feb/11 IBRD (70%) Al Amro Contracting Office 11 Qotor IIIMP/IIS/MTYZ/MQ-19-2010 left Bank from KM 20.515 to KM 22.065 - Qptor 1,215 NCB Revised Prior No 5,316,344.82 EGP 25/Mar/11 GoE (30%) Damanhour Egypt District Actual 26/Jan/10 25/Feb/10 6/Mar/10 6/Apr/10 6/Apr/10 9/May/10 27/May/10 26/Jun/10 26/Jun/10 14/Mar/11 Planned 1/Mar/10 31/Mar/10 30/Apr/10 30/Apr/10 10/May/10 20/May/10 30/May/10 6/Jun/10 9/Mar/10 Completion of improvement of Civil Works in IBRD (70%) Al-Amro Office for Contracting 12 Desok IIIMP/IIS/MTYZ/F/COM 1 2008 4,127 NCB Revised Prior No 1/Jul/10 7,194,607.20 EGP Manaifa area (IIP-1) GoE (30%) Actual 26/Aug/08 2/Sep/08 26/Oct/08 16/Nov/08 16/Nov/08 18/Dec/08 11/Feb/09 1/Mar/09 10/Mar/09 13/Mar/10 Mesqas Improvement Works for Mars El Gamle Planned 1/Mar/10 15/Mar/10 25/Mar/10 25/Apr/10 25/Apr/10 10/May/10 20/May/10 1/Jun/10 10/Jun/10 31/Jul/11 Kafr El- IBRD (70%) 13 IIIMP/IIS/MTYZ/MQ-22-2010 (RS) - from head to km 6.504 in Kafr El-Shiekh 972 NCB Revised Prior No 1/Oct/10 1/Nov/10 15/Nov/10 4,545,531.76 EGP Dar El - Sahaba company Sheikh GoE (30%) District Actual 9/May/10 13/May/10 7/Aug/10 21/Sep/10 21/Sep/10 5/Oct/10 27/Oct/10 1/Dec/10 1/Dec/10 30/Jul/11 Mesqa Improvement Works for Mars EL - Gamle Planned 1/Dec/12 1/Mar/10 31/Jul/11 Kafr El- IBRD (70%) Revised 8/Aug/10 5/Nov/10 15/Nov/10 Al-Amro Office for Contracting 31/Jul/13 14 IIIMP/IIS/MTYZ/MQ-24-2010 (RS), from Km 6.686 to km 9.886 and in Kafr El- 957 NCB Prior No 3,990,886.74 EGP Sheikh GoE (30%) Morabin ,Kafr El-Shiekh District Actual 7/Jun/10 28/Jun/10 7/Aug/10 23/Sep/10 23/Sep/10 5/Oct/10 24/Oct/10 1/Dec/10 1/Dec/10 28/Mar/13 Planned 1/Sep/10 1/Oct/10 31/Oct/10 31/Oct/10 30/Nov/10 15/Dec/10 25/Mar/12 Mesqa Improvement of Mars El Gamal Canal Kafr El- IBRD (70%) Revised 13/Feb/11 13/Mar/11 18/Jul/11 Al-Amro Office for Contracting 25/Oct/12 15 IIIMP/IIS/MTYZ/MQ-25-2010 Left Bank from 3.835 km to 9.828 km - Mit 1,446 NCB Prior No 7,654,842.00 EGP Sheikh GoE (30%) Revised 8/Aug/10 22/Sep/10 27/Sep/10 8/Nov/10 8/Nov/11 9/Jan/11 13/Jan/11 Tender Cancelled 25/Jun/13 Yazeed Command Area Actual 21/Sep/10 27/Jan/11 22/Jan/11 26/Feb/11 26/Feb/11 12/Apr/11 21/Jun/11 26/Jul/11 26/Jul/11 Planned 1/Oct/09 1/Sep/09 14/Feb/12 Mesqa Improvement Works Contract for Kom Al Kafr El- IBRD (70%) Revised 1/Dec/10 24/Dec/10 24/Jan/11 24/Jan/11 15/Jun/11 15/Jun/11 Mansour Company for Trde& 14/Dec/13 16 IIIMP/IIS/MTYZ/MQ-32-2010 - Roz Al- Kadeema Canal from Km 3.8 to end - 1,285 NCB Prior No 6,759,847.20 EGP Sheikh GoE (30%) Contracting Mit Yazeed Command Area Area Actual 24/Oct/10 6/Dec/10 18-dec2010 30/Jan/11 30/Jan/11 20/Mar/11 13/Apr/11 15/Jun/11 15/Jun/11 16/Jan/13 Total completed contracts 12,646 Sheet Mesqa Improvement, page 9 of 13 Area Review by Domestic Preparation of Bid Invitation Bid Bid Opening BER Bank’s&or Pmu No Contract Bank’s&or Pmu No Contract Signing Contract Package reference No/ Procurement Fund Bank Preference Bid Document Closing Objection to BER Contract Name, City, and Country of Completion SL No District Description of Works Status Estimated Cost Currency Objection to Bidding Commencement Contract Value Contract No method Source(s) and Contract Award Currency Contractor Document (Date) (Date) (Date) (fed) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Ongoing Area Review by Domestic Preparation of Bid Invitation Bid Bid Opening BER Bank’s&or Pmu No Contract Bank’s&or Pmu No Contract Signing Contract Package reference No/ Procurement Fund Bank Preference Bid Document Closing Objection to BER Contract Name, City, and Country of Completion SL No District Description of Works Status Estimated Cost Currency Objection to Bidding Commencement Contract Value Contract No method Source(s) and Contract Award Currency Contractor Document (Date) (Date) (Date) (fed) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Planned 1/Oct/09 11/Oct/09 18/Oct/09 18/Nov/09 18/Nov/09 17/Dec/09 31/Dec/09 10/Jan/10 14/Sep/10 Revised Ali Youssry Company for 29/Jan/11 Gharb El- Meska Improvement Works in Mit Yazid Direct IBRD (70%) 1 IIIMP/IIS/MTYZ/MQ-01-2009 1,144 NCB Revised Prior No Tender Cancelled 5,495,136.00 EGP Contracting Mahalla from intake km 9.120 GoE (30%) Revised Tender Cancelled 15/Jul/13 Actual 5/Feb/09 19/Mar/09 29/Aug/09 28/Sep/09 28/Sep/09 15/Oct/09 29/Oct/09 9/Nov/09 15/Nov/09 Planned 1/Nov/09 12/Nov/09 19/Nov/09 20/Dec/09 20/Dec/09 20/Jan/10 3/Feb/10 17/Feb/10 4/Oct/10 Gharb El- Meska Improvement Works for Direct Mit Yazid IBRD (70%) 2 IIIMP/IIS/MTYZ/MQ-04-2009 1,524 NCB Revised Prior No Tender Cancelled 6,789,465.00 EGP Benass company for Constraction 5/Sep/13 Mahalla canal Direct -Left side km 10.410 to KM 19.900 GoE (30%) Actual 3/May/09 27/May/09 29/Aug/09 26/Sep/09 26/Sep/09 26/Oct/09 5/Nov/09 15/Dec/09 5/Dec/09 Meska Improvement Works in Bahr Nemra Planned 3/Jan/10 13/Jan/10 20/Jan/10 21/Feb/10 21/Feb/10 21/Mar/10 4/Apr/10 18/Apr/10 Ali Youssry Company for 25/Jul/10 Gharb El- IBRD (70%) 3 IIIMP/IIS/MTYZ/MQ-05-2009 Branch Canal - Right Side from Km 4.8 to the 1,071 NCB Revised Prior No 26/Sep/09 5,766,755.00 EGP Contracting 5/Sep/13 Mahalla GoE (30%) end Actual 21/Jun/09 23/Jun/09 8/Jul/09 8/Aug/09 8/Aug/09 23/Aug/09 30/Aug/09 26/Sep/09 3/Dec/09 Planned 1/Mar/10 11/Mar/10 18/Mar/10 18/Apr/10 18/Apr/10 18/May/10 1/Jun/10 15/Jun/10 14/Sep/10 Gharb El- Mesqa Improvement Works in El Banawan IBRD (70%) Revised 13/Oct/09 26/Oct/09 4 IIIMP/IIS/MTYZ/MQ-07-2009 1,103 NCB Prior No 4,795,585.00 EGP Benass company for Constraction Mahalla Branch canal Right Side GoE (30%) Revised 21/Jun/09 23/Jun/09 8/Jul/09 8/Aug/09 8/Aug/09 15/Oct/09 Tender Cancelled 5/Sep/13 Actual 21/Jun/09 23/Jun/09 29/Aug/09 27/Sep/09 27/Sep/09 15/Oct/09 29/Oct/09 12/Nov/09 15/Nov/09 Planned 1/Oct/09 12/Oct/09 29/Oct/09 19/Nov/09 19/Nov/09 19/Dec/09 2/Jan/10 22/Jan/10 Ali Youssry Company for 25/Aug/10 Gharb El- Mesqa Improvement Works in Khadiga Branch IBRD (70%) 5 IIIMP/IIS/MTYZ/MQ-08-2009 1,305 NCB Revised Prior No 1/Sep/09 14/Oct/09 7,628,525.00 EGP Contracting 5/Sep/13 Mahalla canal GoE (30%) Actual 11/Jul/09 23/Aug/09 12/Sep/09 12/Oct/09 12/Oct/09 8/Nov/09 23/Nov/09 26/Dec/09 26/Dec/09 Planned 6/Feb/10 13/Feb/10 20/Feb/10 23/Mar/10 23/Mar/10 22/Apr/10 2/May/10 15/May/10 Ali Youssry Company for 30/Sep/10 Gharb El- Meska Improvement Works in Nesheel El- IBRD (70%) 6 IIIMP/IIS/MTYZ/MQ-12-2009 960 NCB Revised Prior No 4,858,162.00 EGP Contracting 5/Sep/13 Mahalla Gadida Branch canal from Head to the End GoE (30%) Actual 1/Sep/09 18/Oct/09 7/Nov/09 5/Dec/09 5/Dec/09 27/Dec/09 5/Jan/10 1/Feb/10 1/Feb/10 Mesqas Improvement Works for Direct Mit Yazid Planned 3/Jun/10 13/Jun/10 20/Jun/10 21/Jul/10 21/Jul/10 21/Aug/10 4/Sep/10 18/Sep/10 1/May/10 25/Jan/11 IBRD (70%) Upper Egypt General Contracting 7 Qotor IIIMP/IIS/MTYZ/MQ-17-2009 -Right Bank- from KM 20.530 to KM 26.340 823 NCB Revised Prior No 16/May/10 3,235,810.00 EGP 25/Sep/13 GoE (30%) Company (Qotor District) Actual 23/Dec/09 10/Jan/10 31/Jan/10 28/Feb/10 28/Feb/10 11/Mar/10 6/May/10 26/May/10 26/May/10 Planned 3/Jul/10 13/Jul/10 20/Jul/10 21/Aug/10 21/Aug/10 21/Sep/10 4/Oct/10 18/Oct/10 1/May/10 25/Jan/11 Mesqas Improvement Works for Direct Mit Yazid IBRD (70%) Upper Egypt General Contracting 8 Qotor IIIMP/IIS/MTYZ/MQ-18-2009 986 NCB Revised Prior No 2/Mar/10 6/Mar/10 8/Apr/10 8/Apr/10 9/May/10 16/May/10 1/May/10 4,298,790.00 EGP 25/Nov/13 -left Bank- from KM 20.270 to KM 20.500 GoE (30%) Company Actual 30/Dec/09 24/Jan/10 31/Jan/10 1/Mar/10 1/Mar/10 11/Mar/10 6/May/10 26/May/10 26/May/10 Mesqas Improvement Works for Mit Yazid Dir Planned 5/Feb/09 19/Mar/09 15/Apr/09 16/May/09 16/May/09 10/Oct/09 18/Oct/09 18/Nov/09 14/May/11 IBRD (70%) Al Amro Contracting Office 9 Qotor IIIMP/IIS/MTYZ/MQ-20-2010 Right Bank from KM 31.580 to KM 32.610 - 1,357 NCB Revised Prior No 7,123,249.50 EGP 14/Dec/13 GoE (30%) Damanhour Egypt Qotor District Actual 4/Feb/10 25/Feb/10 6/Mar/10 7/Apr/10 7/Apr/10 9/May/10 12/Aug/10 15/Sep/10 15/Sep/10 Planned 17/Jun/08 27/Jun/08 27/Jul/08 27/Aug/08 27/Aug/08 27/Oct/08 25/Nov/08 17/Dec/08 30/Jul/11 Mesqa Improvement Works for Mit Yazid Dir IBRD (70%) Revised 1/Jul/10 30/Nov/10 Al-Amro Office for Contracting 10 Qotor IIIMP/IIS/MTYZ/MQ-21-2010 (LS) from KM 24.780 - KM 26.650 in Qotor 1,082 NCB Prior No 6,054,433.75 EGP GoE (30%) Revised 23/Feb/10 2/Mar/10 6/Mar/10 8/Apr/10 8/Apr/10 9/May/10 21/Jul/10 Tender Cancelled 31/Oct/13 District Actual 23/Feb/10 21/Jul/10 7/Aug/10 7/Sep/10 7/Sep/10 8/Nov/10 10/Nov/10 1/Dec/10 1/Dec/10 Mesqa Improvement Works for Mars El- Gamle Planned 1/Nov/12 1/Feb/10 31/Jul/11 Kafr El- IBRD (70%) Egyptian Contracting Company 11 IIIMP/IIS/MTYZ/MQ-23-2010 (LS)- from head to km 3.439 and kafr El-Morabin 1,040 NCB Revised Prior No 6/Jun/10 1/Nov/10 2/Nov/10 4,436,071.15 EGP 31/Oct/13 Sheikh GoE (30%) (Mokhtar Ibrahim) in Kafr El-Shiekh District Actual 7/Jun/10 23/Jun/10 7/Aug/10 22/Sep/10 22/Sep/10 5/Oct/10 25/Oct/10 1/Dec/10 1/Dec/10 Planned 1/Sep/10 1/Dec/10 14/Apr/12 Mesqa Improvement Works Contract for Al- Kafr El- IBRD (70%) Revised 1/Jan/11 13/Feb/11 13/Mar/11 15/Jul/11 Adel Abdel Azez El- Shahawy 14/Oct/12 12 IIIMP/IIS/MTYZ/MQ-26-2010 Mafrooza- Right Bank and Al Mafrooza AL 1,048 NCB Prior No 4,327,417.15 EGP Sheikh GoE (30%) Revised 8/Aug/10 22/Sep/10 27/Sep/10 9/Nov/10 9/Nov/10 9/Jan/11 13/Jan/11 Tender Cancelled Company 14/Nov/13 Sharkia canal - Mit Yazeed Command Area Actual 21/Sep/10 27/Jan/11 22/Jan/11 27/Feb/11 27/Feb/11 10/May/11 11/Jul/11 15/Aug/11 15/Aug/11 Planned 1/Sep/10 1/Dec/10 14/Apr/12 Mesqa Improvement Works Contract for Al- Kafr El- IBRD (70%) Revised 13/Feb/11 13/Mar/11 15/Jul/11 Al-Amro Office for Contracting 14/Feb/13 13 IIIMP/IIS/MTYZ/MQ-27-2010 Mafrooza- left Bank and Al Mafrooza AL 979 NCB Prior No 3,867,722.72 EGP Sheikh GoE (30%) Revised 8/Aug/10 22/Sep/10 27/Sep/10 10/Nov/10 10/Nov/10 9/Jan/11 13/Jan/11 Tender Cancelled 14/Nov/13 Gadeeda - Mit Yazeed Command Area Actual 21/Sep/10 27/Jan/11 22/Jan/11 28/Feb/11 28/Feb/11 12/Apr/11 12/Jul/11 15/Aug/11 15/Aug/11 Planned 1/Sep/10 1/Dec/10 9/Mar/12 Mesqa Improvement Works Contract for Al Kafr El- IBRD (70%) Revised 1/Mar/11 13/Feb/11 13/Mar/11 15/Jul/11 9/Nov/12 14 IIIMP/IIS/MTYZ/MQ-28-2010 Bashair canal - Branch from Mars El Gamal 1,464 NCB Prior No 6,078,248.70 EGP Dar El - Sahaba company Sheikh GoE (30%) Revised 8/Aug/10 22/Sep/10 27/Sep/10 11/Nov/10 11/Nov/10 9/Jan/11 13/Jan/11 Tender Cancelled 9/Nov/13 canal - Mit Yazeed Command Area Actual 21/Sep/10 27/Jan/11 22/Jan/11 1/Mar/11 1/Mar/11 12/Apr/11 20/Jun/11 10/Jul/11 10/Jul/11 Mesqa Improvement Works Contract for El Planned 1/Jan/11 1/Apr/11 4/Nov/11 Kafr El IBRD (70%) Al-Amro Office for Contracting 15 IIIMP/IIS/MTYZ/MQ-29-2010 Shorafa canal and direct El Zawia from km 5.963 1,084 NCB Revised Prior No 1/Feb/11 5/Dec/10 5/Jan/11 5/Jan/11 1/Mar/11 8/Mar/11 5,717,101.15 EGP 4/Nov/13 Sheikh GoE (30%) to 6.252 km Actual 22/Sep/10 2/Nov/10 10/Nov/10 9/Jan/11 9/Jan/11 18/Jan/11 23/Jan/11 30/Jan/11 5/Mar/11 Meska Improvement Works contracts for Kom Planned 1/Oct/11 30/Dec/11 6/Jan/12 4/Nov/11 Kafr El IBRD (70%) Revised 5/Dec/10 5/Jan/11 5/Jan/11 1/Mar/11 Al-Amro Office for Contracting 4/Nov/13 16 IIIMP/IIS/MTYZ/MQ-30-2010 El Roz El Kadima from intake to km 3.80 and 1,143 NCB Prior No 5,773,506.76 EGP Shiekh GoE (30%) Tahwelet Kom El Roz El Kadima canal Actual 22/Sep/10 4/Nov/10 10/Nov/10 10/Jan/11 10/Jan/11 18/Jan/11 23/Jan/11 26-Fer-2011 5/Mar/11 Mesqa Improvement Works Contract for Al - Planned 1/Oct/12 1/Jan/11 14/Feb/12 Kafr El- IBRD (70%) Egyptian Contracting Company 17 IIIMP/IIS/MTYZ/MQ-31-2010 Shamarqa Al- Gededa Canal - Mit Yazeed 1,039 NCB Revised Prior No 30/Oct/10 5/Dec/10 5/Jan/11 5/Jan/11 15/Jun/11 15/Jun/11 5,086,437.15 EGP 14/Dec/13 Sheikh GoE (30%) (Mokhtar Ibrahim) Command Area Actual 24/Oct/10 9/Nov/10 18-dec2010 29/Jan/11 29/Jan/11 20/Mar/11 12/Apr/11 15/Jun/11 15/Jun/11 1,780 Planned 1/Jan/12 31/Jan/12 1/Mar/12 1/Mar/12 31/Mar/12 7/Apr/12 21/Aug/14 Mesqa Improvement Works Contract for Kom IBRD Kafr El- 1,360 Revised 1/Jan/11 13/Mar/13 12/Apr/13 12/Apr/13 29/May/13 12/Jun/13 26/Jun/13 3/Jul/13 Cooperative Socicty for 18 IIIMP/IIS/MTYZ/MQ-33-2010 EL - Roz EL - Gedida Canal - Mit Yazeed NCB (90%)GoE Post No 10,145,056.52 EGP Sheikh (10%) Actual 16/Jan/13 26/Feb/13 8/Apr/13 8/May/13 8/May/13 27/Jun/13 Tender Cancelled Construction &Development Command Area 7/Jul/13 11/Jul/13 18/Jul/13 18/Aug/13 18/Aug/13 9/Sep/13 19/Sep/13 22/Oct/13 22/Oct/13 Revised 1/Dec/10 1/Apr/12 7/Apr/12 3/Dec/12 Actual 9/Nov/10 12/Dec/10 25/Jul/11 23/Aug/11 23/Aug/11 5/Apr/12 9/Apr/12 Tender Cancelled Mesqa Improvement Works Contract for Al - IBRD Kafr El- Revised 13/Mar/13 12/Apr/13 12/Apr/13 30/May/13 13/Jun/13 27/Jun/13 4/Jul/13 Cooperative Socicty for 5/Mar/14 19 IIIMP/IIS/MTYZ/MQ-34-2010 Gnabia 2 canal the Right side of Al Zawia Canal - 752 NCB (90%)GoE Post No 5,544,402.50 EGP Sheikh (10%) Actual 16/Jan/13 26/Feb/13 8/Apr/13 9/May/13 9/May/13 Tender Cancelled Construction &Development Mit Yazeed Command Area 7/Jul/13 11/Jul/13 9/Sep/13 Tender Cancelled 9/Sep/13 17/Sep/13 25/Sep/13 27/Oct/13 27/Oct/13 5/Dec/13 12/Dec/13 Planned 1/Nov/11 1/Jan/11 1/Feb/11 1/Feb/11 1/Feb/12 16/Feb/12 13/Oct/12 Meska Improvement Works for Kafr El Sheekh IBRD Revised 8/Mar/13 14/Mar/13 13/Apr/13 13/Apr/13 2/Jun/13 16/Jun/13 30/Jun/13 7/Jul/13 8/Mar/14 Kafr El- Al-Amro Office for Contracting 20 IIIMP/IIS/MTYZ/MQ-36-2012 15 on El Ganabiet (3) RS El Zawiet from km 918 NCB (90%)GoE Actual Post No 16/Jan/13 27/Feb/13 8/Apr/13 12/May/13 12/May/13 Tender Cancelled 6,229,337.30 EGP Sheikh 1.300m until the end and El Ganabiet (10%) 7/Jul/13 11/Jul/13 18/Jul/13 20/Aug/13 20/Aug/13 9/Sep/13 Tender Cancelled 9/Sep/13 17/Sep/13 25/Sep/13 28/Oct/13 28/Oct/13 5/Dec/13 12/Dec/13 Planned 26/Dec/10 20/Nov/11 20/Dec/11 20/Dec/11 19/Jan/12 26/Jan/12 26/Aug/14 IBRD Meska Improvement Works for Sidi Gazy 2 on Revised 10/Mar/13 18/Mar/13 17/Apr/13 17/Apr/13 3/Jun/13 17/Jun/13 1/Jul/13 8/Jul/13 Al-Amro Office for Contracting 21 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-37-2012 910 NCB (90%)GoE Post No 5,578,886.00 EGP El Halafey canal LS from km 6.00 (10%) Actual 16/Jan/13 3/Mar/13 8/Apr/13 13/May/13 13/May/13 27/Jun/13 Tender Cancelled Actual 7/Jul/13 11/Jul/13 18/Jul/13 21/Aug/13 21/Aug/13 9/Sep/13 19/Sep/13 27/Oct/13 IBRD Planned 26/Dec/10 20/Nov/11 20/Dec/11 20/Dec/11 19/Jan/12 26/Jan/12 22/Sep/12 Meska Improvement Works for Sidi Gazy 3 on khtab & Sawahly for General 22 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-38-2013 648 NCB (90%)GoE Revised Post No 12/Mar/13 10/May/13 9/Jun/13 9/Jun/13 30/Jun/13 14/Jul/13 28/Jul/13 4/Aug/13 5,354,243.60 EGP 5/Apr/14 El Halafey canal LS from km 6.00 until km 7.500 (10%) Contracting Actual 17/Apr/13 24/Apr/13 29/May/13 7/Jul/13 7/Jul/13 27/Oct/13 IBRD Planned 1/Jan/12 31/Jan/12 1/Mar/12 1/Mar/12 31/Mar/12 7/Apr/12 3/Dec/12 Meska Improvement Works for Sidi Gazy 6 on Cooperative Socicty for 23 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-42-2013 622 NCB (90%)GoE Revised Post No 25/Mar/13 12/May/13 11/Jun/13 11/Jun/13 2/Jul/13 16/Jul/13 30/Jul/13 6/Aug/13 4,088,367.05 EGP 6/Apr/14 RS El Halafey from intake to km 6.950 (10%) Construction &Development Actual 17/Apr/13 24/Apr/13 29/May/13 8/Jul/13 8/Jul/13 25/Jul/13 6/Aug/13 15/Sep/13 15/Sep/13 Planned 1/Jan/12 31/Jan/12 1/Mar/12 1/Mar/12 31/Mar/12 7/Apr/12 9/Sep/14 IBRD Meska Improvement Works for Sidi Gazy 7 on Revised 27/Mar/13 26/Apr/13 26/May/13 26/May/13 13/Jun/13 27/Jun/13 11/Jul/13 18/Jul/13 khtab & Sawahly for General 24 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-43 926 NCB (90%)GoE Post No 8,517,480.00 EGP RS El Halafey from km 5.800 until km 9.490 (10%) Actual 20/Mar/13 1/Apr/13 23/Apr/13 23/May/13 23/May/13 8/Jul/13 11/Jul/13 Tender Cancelled Contracting Actual 8/Jul/13 11/Jul/13 24/Jul/13 25/Aug/13 25/Aug/13 15/Sep/13 24/Sep/13 Done 10/Nov/13 IBRD Planned 15/Jan/12 14/Feb/12 15/Mar/12 15/Mar/12 14/Apr/12 21/Apr/12 16/Jan/14 25 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-44/2012 El Halafey canal LS from km 9,940 to km 14,445 1,328 NCB (90%)GoE Revised Prior No 1/Nov/12 1/Dec/12 31/Dec/12 31/Dec/12 30/Jan/13 6/Feb/13 6,972,726.90 EGP Dar El - Sahaba company (10%) Actual 5/Sep/12 13/Sep/12 17/Oct/12 20/Nov/12 20/Nov/12 16/Jan/13 9/Feb/13 17/Mar/13 17/Mar/13 Planned 1/Feb/12 2/Mar/12 1/Apr/12 1/Apr/12 1/May/12 8/May/12 10 month contract IBRD Meska Improvement Works for Sidi Gazy 9 on Revised 1/Mar/13 15/Mar/13 14/Apr/13 14/Apr/13 4/Jun/13 18/Jun/13 2/Jul/13 9/Jul/13 26 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-45-2013 1,665 NCB (90%)GoE Post No 12,635,247.00 EGP Dar El - Sahaba company El Halafy canal RS from K 14,914 until end (10%) Actual 27/Nov/12 28/Feb/13 8/Apr/13 14/May/13 14/May/13 Tender Cancelled Actual 7/Jul/13 11/Jul/13 18/Jul/13 22/Aug/13 22/Aug/13 9/Sep/13 19/Sep/13 IBRD Planned 15/Feb/12 16/Mar/12 15/Apr/12 15/Apr/12 15/May/12 22/May/12 16/Jan/14 27 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-47-2012 El Halafey canal LS from km 13,500 to km 17,435 1,436 NCB (90%)GoE Revised Prior No 1/Jan/13 31/Jan/13 2/Mar/13 2/Mar/13 1/Apr/13 8/Apr/13 9,322,364.80 EGP Dar El - Sahaba company (10%) Actual 5/Sep/12 13/Sep/12 17/Oct/12 21/Nov/12 21/Nov/12 24/Dec/12 9/Feb/13 17/Mar/13 17/Mar/13 Planned 15/Feb/12 16/Mar/12 15/Apr/12 15/Apr/12 15/May/12 22/May/12 10 month contract IBRD Meska Improvement Works for Sidi Gazy 12 on Revised 5/Mar/13 4/Apr/13 4/May/13 4/May/13 16/Jun/13 30/Jun/13 14/Jul/13 21/Jul/13 28 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-48-2013 831 NCB (90%)GoE Post No 6,815,595.40 EGP Dar El - Sahaba company LS El Halafey from km 17.435 until the end (10%) Actual 20/Mar/13 1/Apr/13 23/Apr/13 26/May/13 26/May/13 8/Jul/13 11/Jul/13 Tender Cancelled Actual 8/Jul/13 11/Jul/13 24/Jul/13 26/Aug/13 26/Aug/13 15/Sep/13 24/Sep/13 27/Oct/13 Done IBRD Planned 20/Feb/12 21/Mar/12 20/Apr/12 20/Apr/12 20/May/12 27/May/12 26/Aug/14 Meska Improvement Works for Sidi Gazy 13 on Al-Amro Office for Contracting 29 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-49 1,153 NCB (90%)GoE Revised Post No 5/Mar/13 14/Jul/13 13/Aug/13 13/Aug/13 3/Sep/13 17/Sep/13 1/Oct/13 8/Oct/13 9,955,112.32 EGP LS El Marbet from km 5.580 + El Melaha (10%) Actual 12/May/13 9/Jun/13 10/Jul/13 12/Aug/13 12/Aug/13 26/Aug/13 27/Oct/13 27/Oct/13 Planned 3/Mar/12 2/Apr/12 2/May/12 2/May/12 1/Jun/12 8/Jun/12 10 month contract Meska Improvement Works for Sidi Gazy 14 on IBRD Revised 1/Apr/13 15/Jul/13 14/Aug/13 14/Aug/13 4/Sep/13 18/Sep/13 2/Oct/13 9/Oct/13 Al-Amro Office for Contracting 30 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-50 LS El Marbet from km 5.580 until the end + El 1,073 NCB (90%)GoE Post No 8,770,645.60 EGP (10%) Actual 12/May/13 9/Jun/13 10/Jul/13 13/Aug/13 13/Aug/13 26/Aug/13 1/Sep/13 Tender Cancelled Sant Actual 26/Aug/13 1/Sep/13 25/Sep/13 29/Oct/13 29/Oct/13 5/Dec/13 12/Dec/13 Planned 21/Mar/13 20/Apr/13 20/May/13 20/May/13 19/Jun/13 26/Jun/13 26/Aug/14 IBRD Meska Improvement Works for Sidi Gazy 18 on Revised 17/Jun/13 1/Jul/13 15/Jul/13 22/Jul/13 Al-Amro Office for Contracting 31 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-54 1,130 NCB (90%)GoE Post No 10,985,850.88 EGP LS El Daramly from intake until km 3.500 (10%) Actual 20/Mar/13 1/Apr/13 23/Apr/13 27/May/13 27/May/13 8/Jul/13 11/Jul/13 Tender Cancelled 8/Jul/13 11/Jul/13 24/Jul/13 27/Aug/13 27/Aug/13 26/Sep/13 27/Oct/13 27/Oct/13 IBRD Planned 9/Apr/13 9/May/13 8/Jun/13 8/Jun/13 24/Jun/13 1/Jul/13 8/Jul/13 15/Jul/13 14/Mar/14 Meska Improvement Works for Sidi Gazy 19 on khtab & Sawahly for General 32 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-55 1,063 NCB (90%)GoE Revised Post No 9,198,069.95 EGP LS El Daramly from km 4.800 until km 7.400 (10%) Contracting Actual 17/Apr/13 24/Apr/13 29/May/13 9/Jul/13 9/Jul/13 25/Jul/13 6/Aug/13 IBRD Planned 17/Apr/13 17/May/13 16/Jun/13 16/Jun/13 2/Jul/13 9/Jul/13 16/Jul/13 23/Jul/13 14/Aug/14 Meska Improvement Works for Sidi Gazy 20 on Cooperative Socicty for 33 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-56 1,314 NCB (90%)GoE Revised Post No 12,602,131.00 EGP LS El Daramly from km7.527 until the end (10%) Construction &Development Actual 17/Apr/13 24/Apr/13 29/May/13 10/Jul/13 10/Jul/13 25/Jul/13 6/Aug/13 15/Sep/13 15/Sep/13 IBRD Planned 22/Apr/13 22/May/13 21/Jun/13 21/Jun/13 7/Jul/13 14/Jul/13 21/Jul/13 28/Jul/13 27/Mar/14 Meska Improvement Works for Sidi Gazy 21 on 34 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-57 1,086 NCB (90%)GoE Revised Post No 15/Jul/13 14/Aug/13 14/Aug/13 4/Sep/13 18/Sep/13 2/Oct/13 9/Oct/13 9,438,540.00 EGP El safa company for Contracting 8/Jun/14 RS El Daramly from intake to km 6.300 (10%) Actual 12/May/13 9/Jun/13 10/Jul/13 14/Aug/13 14/Aug/13 2/Sep/13 16/Sep/13 IBRD Planned 22/Apr/13 22/May/13 21/Jun/13 21/Jun/13 7/Jul/13 14/Jul/13 21/Jul/13 28/Jul/13 27/Mar/14 Meska Improvement Works for Sidi Gazy 22 on 35 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-58 1,353 NCB (90%)GoE Revised Post No 15/Jul/13 14/Aug/13 14/Aug/13 4/Sep/13 18/Sep/13 2/Oct/13 9/Oct/13 11,769,915.70 EGP Eliet for Contracting 8/Jun/14 RS El Daramly from km 6.300 to the end (10%) Actual 12/May/13 9/Jun/13 10/Jul/13 15/Aug/13 15/Aug/13 2/Sep/13 16/Sep/13 3/Nov/13 Total ongoing contracts 31,497.30 Sheet Mesqa Improvement, page 10 of 13 Area Review by Domestic Preparation of Bid Invitation Bid Bid Opening BER Bank’s&or Pmu No Contract Bank’s&or Pmu No Contract Signing Contract Package reference No/ Procurement Fund Bank Preference Bid Document Closing Objection to BER Contract Name, City, and Country of Completion SL No District Description of Works Status Estimated Cost Currency Objection to Bidding Commencement Contract Value Contract No method Source(s) and Contract Award Currency Contractor Document (Date) (Date) (Date) (fed) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Planned Area Review by Domestic Preparation of Bid Invitation Bid Bid Opening BER Bank’s&or Pmu No Contract Bank’s&or Pmu No Contract Signing Contract Package reference No/ Procurement Fund Bank Preference Bid Document Closing Objection to BER Contract Name, City, and Country of Completion SL No District Description of Works Status Estimated Cost Currency Objection to Bidding Commencement Contract Value Contract No method Source(s) and Contract Award Currency Contractor Document (Date) (Date) (Date) (fed) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Mesqa Improvement Works Contract for Al IIIMP/IIS/MTYZ/MQ-35-2010 IBRD Planned 1/Nov/12 25/Jul/11 24/Aug/11 24/Aug/11 23/Nov/11 30/Nov/11 27/Jul/12 Kafr El- Ganabia 3 and its Branch Canal the Right Side 1 Contract MTYZ/MQ-21 moved to 1,458 Cancelled (90%)GoE Revised Post No 1/Dec/10 1/Apr/12 7/Apr/12 EGP 3/Dec/12 Sheikh of EL Zawia Canal from head to km 1.300 - Mit this area (10%) Actual 9/Nov/10 12/Dec/10 25/Jul/11 24/Aug/11 24/Aug/11 5/Apr/12 9/Apr/12 Tender Cancelled Yazeed Command Area IBRD Planned 1/Feb/11 20/Nov/11 20/Dec/11 20/Dec/11 19/Jan/12 26/Jan/12 22/Sep/12 2 Sidi Ghazey IIIMP/IIS/MTYZ/MQ-39- Meska Improvement Works for Sidi Gazy 4 1,359.6 Cancelled (90%)GoE Revised Post No 1/Oct/13 10/Jun/13 10/Jul/13 10/Jul/13 31/Jul/13 14/Aug/13 28/Aug/13 4/Sep/13 6/May/14 (10%) Actual IBRD Planned 1/Jan/12 31/Jan/12 1/Mar/12 1/Mar/12 31/Mar/12 7/Apr/12 3/Dec/12 Kafr El- Meska Improvement Works for Kafr El Sheekh 3 IIIMP/IIS/MTYZ/MQ-40 1,150 NCB (90%)GoE Revised Post No 1/Apr/14 5/Jun/14 5/Jul/14 5/Jul/14 26/Jul/14 9/Aug/14 23/Aug/14 30/Aug/14 29/Apr/15 Sheikh 16 (10%) Actual IBRD Planned 1/Jan/12 31/Jan/12 1/Mar/12 1/Mar/12 31/Mar/12 7/Apr/12 3/Dec/12 Kafr El- Meska Improvement Works for Kafr El Sheekh 4 IIIMP/IIS/MTYZ/MQ-41 1,250 NCB (90%)GoE Revised Post No 15/Apr/14 19/Jun/14 19/Jul/14 19/Jul/14 9/Aug/14 23/Aug/14 6/Sep/14 13/Sep/14 15/May/15 Sheikh 17 (10%) Actual PS The Area of Contract No. IIIMP/IIS/MTYZ/MQ-35-2010 is now implemented under the Contract No. IIIMP/IIS/MTYZ/21 /2010, as the area of Contract 21 was disputed by the farmers. Sheet Mesqa Improvement, page 11 of 13 Procurement Plan for Drainage Rehabilitation Works Updated 12/12/2013 (Meet Yazeed Area) Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Completed Bid Area Review by Domestic Preparation of Bid Invitation Bid Opening BER Bank’s&or Pmu Contract Bank’s&or Pmu No Closing Contract Signing Contract SL Package reference No/ Procurement Fund Bank Preference Bid Document No Objection to Contract Name, City, and Country of Completion District Description of Works Status Estimated Cost Currency Objection to Bidding Commencement Contract Value No Contract No method Source(s) BER and Contract Currency Contractor Document (Date) (Date) (Date) (fed) (prior/post) (yes/no) (Date) (Date) (Date) (Date) Award (Date) (Date) (Date) Planned 15/May/07 14/Jun/07 14/Jul/07 14/Jul/07 21/Nov/07 31/May/09 Gharb El- IBRD (70%) Mohamed Ibrahim Saeid Abo 1 IIIMP/EPAD/MTYZ/W01-2007 Open drainage works of Gharb ElMehalla Drains - NCB Revised Prior No 1,489,700.00 EGP Mahalla GoE (30%) Taleb Actual 31/May/07 12/Aug/07 29/Aug/07 29/Aug/07 9/Oct/07 7/Nov/07 1/Dec/07 1/Dec/07 31/May/09 Rehabilitation of Brides and Pitching of Open Planned 15/Sep/08 15/Oct/08 14/Nov/08 14/Nov/08 1/Feb/09 30/Apr/11 IBRD (70%) Hamid Ahmed Ali El Banna 2 Sidi Ghazy IIIMP/EPAD/MTYZ/W02-2008 Drains in Sidy Ghazi District -Meet Yazid - NCB Revised Prior No 6,724,500.00 EGP GoE (30%) Office Commmand Area Actual 17/Nov/08 24/Nov/08 21/Jan/09 23/Feb/09 23/Feb/09 19/Mar/09 19/Mar/09 29/Apr/09 1/May/09 30/Apr/11 Planned 1/Apr/10 1/May/10 31/May/10 31/May/10 1/Jun/10 15/Dec/10 1/May/12 East Sidi IBRD (70%) El-Masrea for Integrated 3 IIIMP/EPAD/MTYZ/W03-2010 Pitching work on Nemra Thamnia El Asfal Drain - NCB Revised Prior No 26/Aug/10 15/Sep/10 15/May/11 20/May/11 2,535,950.00 EGP Salem GoE (30%) Contracting Actual 11/Jan/10 21/Mar/10 25/Aug/10 15/Sep/10 15/Sep/10 6/Mar/11 28/Mar/11 2/May/11 2/May/11 10/Apr/12 Planned 15/Sep/08 15/Oct/08 14/Nov/08 14/Nov/08 1/Feb/09 16/Jan/12 East Sidi Subsurface Drainage works in Nemra Thamnia Al IBRD (70%) Revised El-Rashedia Company for 4 IIIMP/EPAD/MTYZ/SSD01 2009 4,000 NCB Prior No 9,949,250.00 EGP Salem Asfal area ) GoE (30%) General Contracting Actual 2/Jul/09 14/Jul/09 19/Aug/09 27/Sep/09 27/Sep/09 13/Dec/09 16/Dec/09 9/Jan/10 16/Jan/10 31/Jul/11 Planned 1/Jan/10 31/Jan/10 2/Mar/10 2/Mar/10 6/May/10 31/Dec/10 31/Aug/12 Gharb El- Replacement and Rehabilitation of Subsurface IBRD (70%) Al - Eman company for 5 IIIMP/EPADP/MTYZ/SSD03 2010 3,000 NCB Revised Prior No 1/Jun/10 10/Jan/11 15/Jan/11 6,694,970.10 EGP Mahalla Drainage Network in Abshaway 1st GoE (30%) contracting Actual 13/Jun/10 23/Jun/10 24/Aug/10 27/Sep/10 27/Sep/10 22/Dec/10 18/Jan/11 1/Mar/11 1/Mar/11 30/Aug/12 Replacement and Rehabilitation of Subsurface Planned 1/Feb/11 3/Mar/11 2/Apr/11 2/Apr/11 1/Jun/11 4/Jun/13 IBRD (70%) El Halowagi Company and his 6 Qotor IIIMP/EPADP/MTYZ/SSD04 2010 Drainage works in Matbool 2nd (A) Meet Yazied 1,700 NCB Revised Prior No 1/Aug/10 7/Apr/11 7/May/11 7/May/11 1/Oct/11 1/Oct/11 4,769,940.00 EGP GoE (30%) Partner Commmand Area Actual 30/Sep/10 11/Nov/10 5/Apr/11 7/May/11 7/May/11 5/Sep/11 20/Sep/11 1/Oct/11 5/Oct/11 10/Jul/12 Planned 1/Feb/11 3/Mar/11 2/Apr/11 2/Apr/11 1/Jun/11 31/May/13 Replacement and Rehabilitation of Subsurface IBRD (70%) El Salam Company for General 7 Qotor IIIMP/EPADP/MTYZ/SSD05 2010 2,200 NCB Revised Prior No 1/Aug/10 7/Apr/11 7/May/11 7/May/11 23/Sep/11 1/Oct/11 6,264,510.00 EGP 31/Mar/13 Drainage works in Matbool 2 nd (B) GoE (30%) Contracting Actual 30/Sep/10 11/Nov/10 5/Apr/11 10/May/11 10/May/11 5/Sep/11 20/Sep/11 1/Oct/11 1/Oct/11 16/Sep/12 Planned 1/Mar/10 31/Mar/10 30/Apr/10 30/Apr/10 1/Jul/10 31/Dec/10 1/Dec/13 Kafr El Replacement and Rehabilitation of Subsurface IBRD (70%) Revised 1/Jun/10 7/Apr/11 7/May/11 7/May/11 10/Apr/12 25/Apr/12 El Halowagi Company and his 1/Dec/13 8 IIIMP/EPADP/MTYZ/SSD06 2010 2,900 NCB Prior No 7,408,193.75 EGP Shiekh Drainage works in El-Khadima and Al-Boteita (B) GoE (30%) Partner Actual 30/Sep/10 4/Nov/10 4/Apr/11 12/May/11 12/May/11 29/Mar/12 4/Apr/12 2/Jun/12 7/Jun/12 Planned 01-Jan-12 31/Jan/12 1/Mar/12 1/Mar/12 31-Mar-12 15/Apr/12 14/Apr/14 Gharb El- Replacement and Rehabilitation of Subsurface IBRD (70%) El Salam Company for General 9 IIIMP/EPADP/MTYZ/SSD10-B 1,850 NCB Revised Prior No 1/Feb/12 20/Apr/12 2/Jul/12 2/Jul/12 20/Sep/12 5/Oct/12 4,277,850.00 EGP 14/Apr/14 Mahalla Drainage works in Neshil (B) GoE (30%) Contracting Actual 23/Jan/12 26/Feb/12 5/May/12 12/Jun/12 12/Jun/12 26/Aug/12 10/Sep/12 15/Oct/12 15/Oct/12 29/Apr/13 Total completed contracts 8,700 21,414,160.10 2,461.40 unit rate Ongoing Bid Area Review by Domestic Preparation of Bid Invitation Bid Opening BER Bank’s&or Pmu Contract Bank’s&or Pmu No Closing Contract Signing Contract SL Package reference No/ Procurement Fund Bank Preference Bid Document No Objection to Contract Name, City, and Country of Completion District Description of Works Status Estimated Cost Currency Objection to Bidding Commencement Contract Value No Contract No method Source(s) BER and Contract Currency Contractor Document (Date) (Date) (Date) (fed) (prior/post) (yes/no) (Date) (Date) (Date) (Date) Award (Date) (Date) (Date) Replacement and Rehabilitation of Subsurface Planned 14/Aug/10 13/Sep/10 13/Oct/10 13/Oct/10 15/Nov/10 1/Dec/10 9/Nov/12 Gharb El- IBRD (70%) Egyptian Company for 1 IIIMP/EPADP/MTYZ/SSD02 2009 Drainage works in the command area of 3,000 NCB Revised Prior No 2/Dec/10 10/Jan/11 15/Jan/11 7,417,499.25 EGP 9/Nov/12 Mahalla GoE (30%) Irrigation and Drainage Abshoway 2nd Actual 21/Apr/10 27/Apr/10 9/May/10 12/Jun/10 12/Jun/10 30/Dec/10 28/Mar/11 27/Apr/11 10/May/11 Planned 1/Mar/11 31/Mar/11 30/Apr/11 30/Apr/11 1/Jul/11 7/Jul/11 30/Sep/13 Kafr El Replacement and Rehabilitation of Subsurface IBRD (70%) El Halowagi Company and his 2 IIIMP/EPADP/MTYZ/SSD14-2011 2,600 NCB Revised Prior No 1/Aug/11 31/Aug/11 31/Aug/11 10/Apr/12 25/Apr/12 6,903,051.00 EGP 30/Sep/13 Shiekh Drainage works in El-Khadima frist(A) GoE (30%) Partner Actual 9/Jan/11 29/May/11 28/Aug/11 29/Sep/11 29/Sep/11 21/Feb/12 23/Feb/12 22/Mar/12 1/Apr/12 Replacement and Rehabilitation of Subsurface Planned 1/Mar/11 31/Mar/11 30/Apr/11 30/Apr/11 1/Jul/11 31/Dec/10 20/Apr/13 IBRD (70%) El Salam Company for General 3 Qotor IIIMP/EPADP/MTYZ/SSD07-A Drainage works in Matbool 1st and Kafr El-Taifa 2,900 NCB Revised Prior No 1/Dec/12 15/Sep/12 15/Oct/12 15/Oct/12 14/Nov/12 29/Nov/12 6,932,502.50 EGP 14/May/14 GoE (30%) Contracting (A) Actual 4/Jan/12 26/Feb/12 4/Jun/12 9/Jul/12 9/Jul/12 27/Sep/12 1/Oct/12 15/Nov/12 15/Nov/12 Replacement and Rehabilitation of Subsurface IBRD Planned 1/Mar/11 31/Mar/11 30/Apr/11 30/Apr/11 1/Jul/11 31/Dec/10 1/Nov/14 Revised 15/Dec/12 15/Nov/12 15/Dec/12 15/Dec/12 30/Mar/13 14/Apr/13 El Salam Company for General 4 Qotor IIIMP/EPADP/MTYZ/SSD07-B Drainage works in Matbool 1st and Kafr El-Taifa 2,200 NCB (90%)GoE Post No 5,469,780.10 EGP Contracting (B) (10%) Actual 4/Jan/12 26/Feb/12 14/Nov/12 18/Dec/12 18/Dec/12 13/Feb/13 13/Feb/13 11/Feb/13 2/May/13 Planned 1/Apr/12 1/May/12 31/May/12 31/May/12 30/Jun/12 7/Mar/11 28/Feb/14 Gharb El- Replacement and Rehabilitation of Subsurface IBRD (70%) 5 IIIMP/EPADP/MTYZ/SSD08-2012 2,800 NCB Revised Prior No 1/Jan/11 1/May/12 31/May/12 31/May/12 31/Jul/12 15/Aug/12 8,262,580.00 EGP El Tokhy for Contracting 28/Feb/14 Mahalla Drainage works in samtay first GoE (30%) Actual 23/Jan/12 26/Jan/12 8/Apr/12 13/May/12 13/May/12 17/Jul/12 18/Jul/12 1/Sep/12 1/Sep/12 Planned 1/Apr/12 1/May/12 31/May/12 31/May/12 30/Jun/12 15/Jul/12 14/Jul/13 Gharb El- Replacement and Rehabilitation of Subsurface IBRD (70%) Revised 1/Mar/11 15/Aug/11 14/Sep/11 14/Sep/11 1/Mar/12 16/Mar/12 Al - Iman company for General 14/Jul/13 6 IIIMP/EPADP/MTYZ/SSD09-2011 3,000 NCB Prior No 6,669,810.65 EGP Mahalla Drainage works in samtay Scond GoE (30%) contracting Actual 10/Feb/11 29/May/11 9/Aug/11 12/Sep/11 12/Sep/11 4/Dec/11 7/Dec/11 15/Jan/12 15/Jan/12 Planned 01-Apr-13 1/May/13 31/May/13 31/May/13 30-Jun-13 15/Jul/13 30/Apr/14 Kafr El Replacement and Rehabilitation of Subsurface IBRD (70%) Engineer Awad Taha Gad 7 IIIMP/EPADP/MTYZ/SSD11-A 2,400 NCB Revised Prior No 5/Apr/12 5/May/12 4/Jun/12 4/Jun/12 1/Aug/12 16/Aug/12 5,673,270.00 EGP 30/Apr/14 Shiekh Drainage works in El Arian (A) GoE (30%) Osman Actual 17/Aug/11 27/Oct/11 5/May/12 10/Jun/12 10/Jun/12 26/Aug/12 12/Sep/12 1/Nov/12 1/Nov/12 Planned 01-Apr-13 1/May/13 31/May/13 31/May/13 30-Jun-13 15/Jul/13 14/May/14 Kafr El Replacement and Rehabilitation of Subsurface IBRD (70%) El Salam Company for General 8 IIIMP/EPADP/MTYZ/SSD11-B 2,300 NCB Revised Prior No 16/Mar/12 15/Apr/12 15/May/12 15/May/12 1/Aug/12 16/Aug/12 5,604,823.36 EGP 14/May/14 Shiekh Drainage works in El Arian (B) GoE (30%) Contracting Actual 17/Aug/11 27/Oct/11 5/May/12 11/Jun/12 11/Jun/12 28/Aug/12 27/Sep/12 15/Nov/12 15/Nov/12 Planned 01-Jan-12 31/Jan/12 1/Mar/12 1/Mar/12 31-Mar-12 15/Apr/12 14/May/14 Gharb El- Replacement and Rehabilitation of Subsurface IBRD (70%) Upper Egypt for General 9 IIIMP/EPADP/MTYZ/SSD10-A 2,700 NCB Revised Prior No 1/Feb/12 15/Sep/12 15/Oct/12 15/Oct/12 14/Nov/12 29/Nov/12 6,327,046.75 EGP 14/May/14 Mahalla Drainage works in Neshil (A) GoE (30%) Contracting Actual 23/Jan/12 26/Feb/12 4/Jun/12 8/Jul/12 8/Jul/12 13/Sep/12 26/Sep/12 15/Nov/12 15/Nov/12 IBRD Planned 01-May-13 31/May/13 30/Jun/13 30/Jun/13 30-Jul-13 14/Aug/13 18 month Replacement and Rehabilitation of Subsurface El Halowagi Company and his 10 Qotor IIIMP/EPADP/MTYZ/SSD12-2012 3,350 NCB (90%)GoE Revised Post No 25/Feb/13 27/Mar/13 26/Apr/13 26/Apr/13 11/Jul/13 18/Jul/13 25/Jul/13 9/Aug/13 7,191,888.00 EGP Drainage works in Meniat Maser Partner (10%) Actual 23/Aug/12 27/Sep/12 8/Dec/12 8/Jan/13 8/Jan/13 18/May/13 6/Nov/13 Done Done Replacement and Rehabilitation of Subsurface IBRD Planned 01-Jul-13 31/Jul/13 30/Aug/13 30/Aug/13 29-Sep-13 14/Oct/13 18 month Kafr El Revised 15/Mar/13 27/Mar/13 26/Apr/13 26/Apr/13 11/Jul/13 18/Jul/13 25/Jul/13 9/Aug/13 11 IIIMP/EPADP/MTYZ/SSD13-A/2013 Drainage works for the extension Nemra Thamnia 2,250 NCB (90%)GoE Post No 5,175,056.00 EGP Mohamed Abdalla Zaid Shiekh El Asfal Drain (10%) Actual 19/Feb/13 25/Feb/13 10/Apr/13 13/May/13 13/May/13 30/Jul/13 Done Done Total ongoing contracts 04-May-00 Planned Bid Area Review by Domestic Preparation of Bid Invitation Bid Opening BER Bank’s&or Pmu Contract Bank’s&or Pmu No Closing Contract Signing Contract SL Package reference No/ Procurement Fund Bank Preference Bid Document No Objection to Contract Name, City, and Country of Completion District Description of Works Status Estimated Cost Currency Objection to Bidding Commencement Contract Value No Contract No method Source(s) BER and Contract Currency Contractor Document (Date) (Date) (Date) (fed) (prior/post) (yes/no) (Date) (Date) (Date) (Date) Award (Date) (Date) (Date) Procurement Plan for Miscellaneous Works (Meet Yazeed Area) Updated 12/12/2013 Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Proc Plan Updated on January 16, 2014 Completed Bid Bank’s No Review by Domestic Preparation of Bank’s No Bid Bid Opening BER Contract Procureme Invitation Objection to Contract Contract Package reference No/ Fund Bank Preference Bid Document Objection to Closing Signing Contract Name, City, and Country of Completion SL No District Description of Works nt Status Estimated Cost Currency BER and Commencem Contract Value Contract No Source(s) Bidding Currency Contractor method Contract Award ent (Date) (Date) (prior/post) (yes/no) (Date) Document (Date) (Date) (Date) (Date) (Date) (Date) (Date) Planned 18/Dec/09 IIIMP/IS/MTYZ/MIS 02 Civil works of Integrated Irrigation CA (75%) Revised Waled Abd El Fatah 1 Qotor NCB Post No N/A N/A 247,175.00 EGP 2009 district in Qotor GoE (25%) Actual 15/Aug/09 8/Sep/09 13/Sep/09 13/Sep/09 19/Oct/09 Darawesh 4/Feb/10 Planned 14/Dec/09 Gharb El- IIIMP/IS/MTYZ/MIS 01 Civil works of Integrated Irrigation CA (75%) Revised 2 NCB Post No N/A N/A 250,368.00 EGP Ramdon Morce Morce Mahalla 2009 district in Gharb El-Mahalla GoE (25%) Actual 15/Aug/09 8/Sep/09 12/Sep/09 12/Sep/09 15/Oct/09 14/Dec/09 Civil works and preparation of Planned 31/May/10 IIIMP/IS/MTYZ/MIS 03 CA (75%) Revised Hamdi Hamed Abd El 3 Sidi Ghazy Integrated Irrigation district in Sidi NCB Post No N/A N/A 1,152,988.00 EGP 2009 GoE (25%) Actual 1/Jun/09 30/Sep/09 1/Oct/09 Moghaney 29/May/10 Ghazy Civil works and preparation of Planned Kafr El IIIMP/IS/MTYZ/MIS 05 Revised 4 Integrated Irrigation district in Kafr Shopping Post No N/A N/A 26,186.00 EGP Osama Hamad Shiekh 2010 GoE El Shiekh Actual 30/Nov/08 26/Jan/09 Planned 1/Jan/10 New Metal for mineral 1/Nov/10 Kafr El IIIMP/IS/MTYZ/MIS 01 Steel Sheds for Storage and IBRD (70%) 5 NCB Revised Post No N/A N/A 387,757.50 EGP constructions and Shiekh 2010 protection kafr El Shiekh GoE (30%) Actual 12/Feb/10 23/Mar/10 23/Mar/10 18/May/10 28/Jun/12 2/May/10 contracting 6/Jul/10 Civil works of Integrated Irrigation Planned IIIMP/IS/MTYZ/MIS 06 CA (75%) 6 Various district in Samanud & Gharb El- NCB N/A 1,199,218.80 EGP El Rehab For Contracting 2011 GoE (25%) Revised Mahalla Actual 12/Mar/11 21/Mar/11 21/Mar/11 2/May/11 1/Jun/12 1/Jun/11 15/Mar/12 Civil works of Integrated Irrigation Planned IIIMP/IS/MTYZ/MIS 07 CA (75%) 7 Various district in Shark El-Mahalla- NCB N/A 1,175,876.50 EGP Ibraheem Ali El Issaway 2011 GoE (25%) Revised Bshbesh& Qotor Actual 12/Mar/11 22/Mar/11 22/Mar/11 20/Apr/11 1/Jun/11 1/Jun/11 10/May/12 Planned IIIMP/IS/MTYZ/MIS 08 Civil works of Integrated Irrigation CA (75%) 8 Various NCB Revised N/A 1,805,258.90 EGP Khatab El Sawahely 2011 district in Basuon & Kafr El-Ziat GoE (25%) Actual 12/Mar/11 21/Mar/11 21/Mar/11 2/May/11 1/Jun/11 1/Jun/11 10/Mar/12