PROCUREMENT PLAN (Textual Part) Project information: Mauritania, Productive & Resilient Intermediate Cities Support Project (Moudoun), P169332 Project Implementation agency: Ministry of Economy and Industry Date of the Procurement Plan: May 10, 2020 Period covered by this Procurement Plan: 05 years Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. “Not Applicable” Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: “Not Applicable” Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable only for the activities related to the COVID-19 crises. Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Mauritania : Decentralization and Productive Intermediate Cities Support Project PLAN General Information Country: Mauritania Bank’s Approval Date of the Original Procurement Plan: 2020-05-20 2020-09-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169332 GPN Date: Project Name: Decentralization and Productive Intermediate Cities Support Project Loan / Credit No: IDA / D5750 Executing Agency(ies): Local Government Development Program WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MR-PNIDDLE-172635-CW- RFB / Infrastructures urbaines (Voiries urbaines, Improving Access to Single Stage - One En attente Assainissement des eaux IDA / D5750 Infrastructure and Services A posteriori Appel d'offres Open - National 2,000,000.00 0.00 2020-12-31 2021-01-05 2021-02-16 2021-03-18 2021-04-22 2021-10-19 Envelope d'exécution usées et pluviales , for Economic Development Extension des réseaux d'électricité et d’AEP, etc) MR-PNIDDLE-172636-CW- RFB / Extension des réseaux Strengthening Single Stage - One En attente et du parc de production IDA / D5750 Decentralization and Local A posteriori Appel d'offres Open - National 3,500,000.00 0.00 2021-05-30 2021-06-04 2021-07-16 2021-08-15 2021-09-19 2022-03-18 Envelope d'exécution électriques de la ville de Government Capacity Bassiknou MR-PNIDDLE-172625-CW- RFB / Recrutement d’un concessionnaire chargé de Improving Access to Open - Single Stage - One En attente construction et de IDA / D5750 Infrastructure and Services A priori Appel d'offres 9,000,000.00 0.00 2020-12-31 2021-01-05 2021-02-16 2021-03-18 2021-04-22 2021-10-19 International Envelope d'exécution l’exploitation des ouvrages de for Economic Development production et de distribution de l’énergie électrique. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-PNIDDLE-172612-GO- Strengthening RFB / Acquisition des Single Stage - One En attente IDA / D5750 Decentralization and Local A posteriori Appel d'offres Open - National 42,000.00 0.00 2020-05-30 2020-06-04 2020-07-16 2020-08-15 2020-09-19 2021-03-18 équipements informatiques & Envelope d'exécution Government Capacity Bureautiques pour la CCP MR-PNIDDLE-172611-GO- Single Stage - One En attente RFB / Acquisition de IDA / D5750 Project Management A posteriori Appel d'offres Open - National 210,000.00 0.00 2020-05-30 2020-06-04 2020-07-16 2020-08-15 2020-09-19 2021-03-18 Envelope d'exécution véhicules pour la CCP MR-PNIDDLE-167152-GO- RFB / Fourniture En attente IDA / D5750 Project Management A posteriori Appel d'offres Open - National 87,000.00 0.00 2020-05-30 2020-05-30 2020-05-30 2020-05-30 2020-05-30 2020-05-30 informatique ( logiciels et d'exécution matériels) MR-PNIDDLE-167148-GO- RFB / Acquisition des En attente équipements informatiques & IDA / D5750 Project Management A posteriori Appel d'offres Open - National 42,000.00 0.00 2020-05-30 2020-05-30 2020-05-30 2020-05-30 2020-05-30 2020-05-30 d'exécution Bureautiques pour la SOMELEC Page 1 MR-PNIDDLE-167151-GO- En attente RFB / Acquisition de IDA / D5750 Project Management A posteriori Appel d'offres Open - National 210,000.00 0.00 2020-05-30 2020-05-30 2020-05-30 2020-05-30 2020-05-30 2020-05-30 d'exécution véhicules pour la SOMELEC MR-PNIDDLE-174836-GO- RFQ / Impression d'entêtes Single Stage - One En attente et de cartes de visite et IDA / D5750 Project Management A posteriori Demande de prix Open - National 10,000.00 0.00 2020-07-05 2020-08-30 2021-02-26 Envelope d'exécution d'invitation pour la CC du projet MOUDOUN MR-PNIDDLE-177656-GO- RFQ / Fourniture et Single Stage - One En attente installation d’un système de IDA / D5750 Project Management A posteriori Demande de prix Limited 20,000.00 0.00 2020-06-13 2020-08-08 2021-02-04 Envelope d'exécution vision conférence au niveau de la CCP NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-PNIDDLE-167149-NC- RFQ / Entretien et Single Stage - One En attente IDA / D5750 Project Management A posteriori Demande de prix Limited 15,000.00 0.00 2020-10-05 2020-11-30 2021-05-29 réparation parc automobile Envelope d'exécution de la CC MR-PNIDDLE-167147-NC- RFQ / Entretien, réparation Single Stage - One En attente matériel informatique et de IDA / D5750 Project Management A posteriori Demande de prix Limited 5,000.00 0.00 2020-10-05 2020-11-30 2021-05-29 Envelope d'exécution bureau de la Cellule de Coordination MR-PNIDDLE-167150-NC- Passation de En attente DIR / Publication avis IDA / D5750 Project Management A posteriori marché de gré à Direct 15,000.00 0.00 2020-05-30 2020-06-04 2020-07-09 2021-01-05 d'exécution Cellule Coordination gré MR-PNIDDLE-174859-NC- RFQ / Assurance maladie du Single Stage - One En attente IDA / D5750 Project Management A posteriori Demande de prix Limited 30,000.00 0.00 2020-08-05 2020-09-30 2021-03-29 personnel de la CC du Envelope d'exécution projet MOUDOUN CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-PNIDDLE-174847-CS- QCBS / Recrutement d’un consultant pour l’élaboration du plan de gestion des Improving Access to Sélection fondée déchets solides, des études En attente IDA / D5750 Infrastructure and Services A posteriori sur la qualité et Open - National 150,000.00 0.00 2020-06-30 2020-07-21 2020-09-03 2020-10-01 2020-10-31 2020-12-05 2021-01-09 2022-01-09 d’impacts environnementales d'exécution for Economic Development le coût et sociales et préparation des dossiers d’appel d’offres des infrastructures à réaliser pour la commune de Rosso Page 2 MR-PNIDDLE-174850-CS- QCBS / Recrutement d’un consultant pour l’élaboration du plan de gestion des Improving Access to Sélection fondée déchets solides, des études En attente IDA / D5750 Infrastructure and Services A posteriori sur la qualité et Open - National 150,000.00 0.00 2020-05-31 2020-06-21 2020-08-04 2020-09-01 2020-10-01 2020-11-05 2020-12-10 2021-12-10 d’impacts environnementales d'exécution for Economic Development le coût et sociales et préparation des dossiers d’appel d’offres des infrastructures à réaliser pour la commune de Kiffa MR-PNIDDLE-174858-CS- Strengthening Sélection fondée QCBS / Etudes de En attente IDA / D5750 Decentralization and Local A posteriori sur la qualité et Open - National 150,000.00 0.00 2020-07-31 2020-08-21 2020-10-04 2020-11-01 2020-12-01 2021-01-05 2021-02-09 2022-02-09 faisabilité des projets de la d'exécution Government Capacity le coût zone 1 MR-PNIDDLE-174851-CS- Strengthening Sélection fondée QCBS / Etudes de En attente IDA / D5750 Decentralization and Local A posteriori sur la qualité et Open - National 150,000.00 0.00 2020-07-31 2020-08-21 2020-10-04 2020-11-01 2020-12-01 2021-01-05 2021-02-09 2022-02-09 faisabilité des projets de la d'exécution Government Capacity le coût zone 2 MR-PNIDDLE-174842-CS- Strengthening Sélection fondée QCBS / Etudes techniques En attente IDA / D5750 Decentralization and Local A posteriori sur la qualité et Open - National 377,000.00 0.00 2020-08-31 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2022-03-12 des projets de la zone d'exécution Government Capacity le coût 1(Rosso) MR-PNIDDLE-172604-GO- Improving Access to Sélection fondée RFP / Etudes techniques des En attente IDA / D5750 Infrastructure and Services A posteriori sur la qualité et Open - National 706,000.00 0.00 2020-07-31 2020-08-21 2020-10-04 2020-11-01 2020-12-01 2021-01-05 2021-02-09 2022-02-09 projets de la zone 2 d'exécution for Economic Development le coût (Selibaby, Kiffa et Aioun) MR-PNIDDLE-172595-GO- RFP / Etudes techniques des Improving Access to Sélection fondée En attente projets de la zone 3 IDA / D5750 Infrastructure and Services A posteriori sur la qualité et Open - National 543,000.00 0.00 2020-07-31 2020-08-21 2020-10-04 2020-11-01 2020-12-01 2021-01-05 2021-02-09 2022-02-09 d'exécution (Nema, Bassiknou et Adele for Economic Development le coût Bagrou) MR-PNIDDLE-172592-GO- Improving Access to Sélection fondée En attente RFP / Suivi des travaux des IDA / D5750 Infrastructure and Services A posteriori sur la qualité et Open - National 162,000.00 0.00 2020-07-31 2020-08-21 2020-10-04 2020-11-01 2020-12-01 2021-01-05 2021-02-09 2022-02-09 d'exécution projets de la zone 1(Rosso) for Economic Development le coût MR-PNIDDLE-174849-CS- Strengthening Sélection fondée QCBS / Suivi des travaux En attente IDA / D5750 Decentralization and Local A posteriori sur la qualité et Open - National 471,000.00 0.00 2020-07-31 2020-08-21 2020-10-04 2020-11-01 2020-12-01 2021-01-05 2021-02-09 2022-02-09 des projets de la zone 2 d'exécution Government Capacity le coût (Selibaby, Kiffa et Aioun) MR-PNIDDLE-174835-CS- QCBS / Suivi des travaux Improving Access to Sélection fondée En attente des projets de la zone IDA / D5750 Infrastructure and Services A posteriori sur la qualité et Open - National 543,000.00 0.00 2020-07-31 2020-08-21 2020-10-04 2020-11-01 2020-12-01 2021-01-05 2021-02-09 2022-02-09 d'exécution 3(Nema, Bassiknou et Adele for Economic Development le coût Bagrou) MR-PNIDDLE-174857-CS- QCBS / Recrutement d’un Ingénieur Conseil assistant Improving Access to Sélection fondée le Maitre d’ouvrage pour Open - En attente IDA / D5750 Infrastructure and Services A priori sur la qualité et 1,500,000.00 0.00 2020-08-31 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2022-03-12 l’étude, l’élaboration du International d'exécution for Economic Development le coût dossier d’appel d’offres, la supervision et le suivi de réalisation des travaux MR-PNIDDLE-174843-CS- Strengthening Sélection fondée QCBS / Evaluation du En attente IDA / D5750 Decentralization and Local A posteriori sur la qualité et Open - National 200,000.00 0.00 2020-06-30 2020-07-21 2020-09-03 2020-10-01 2020-10-31 2020-12-05 2021-01-09 2022-01-09 Programme de regroupement d'exécution Government Capacity le coût volontaire des populations Page 3 Sélection fondée MR-PNIDDLE-172601-GO- sur les En attente IDA / D5750 Project Management A posteriori Open - National 200,000.00 0.00 2020-12-31 2021-01-21 2021-03-06 2021-04-05 2021-05-10 2021-11-06 RFP / Formations qualifications des d'exécution consultants MR-PNIDDLE-172596-GO- RFP / Elaboration des plans Strengthening Sélection fondée En attente de développement régionaux IDA / D5750 Decentralization and Local A posteriori sur la qualité et Open - National 135,000.00 0.00 2020-07-31 2020-08-21 2020-10-04 2020-11-01 2020-12-01 2021-01-05 2021-02-09 2022-02-09 d'exécution et Plans d’investissement Government Capacity le coût associés MR-PNIDDLE-174852-CS- QCBS / Appui à la Strengthening Sélection fondée En attente planification urbaine ( IDA / D5750 Decentralization and Local A posteriori sur la qualité et Open - National 100,000.00 0.00 2021-01-31 2021-02-21 2021-04-06 2021-05-04 2021-06-03 2021-07-08 2021-08-12 2022-08-12 d'exécution Elaboration des schéma Government Capacity le coût d’urbanisme simplifiés ) MR-PNIDDLE-172606-GO- Sélection au En attente RFP / Audits financiers du IDA / D5750 Project Management A posteriori Open - National 30,000.00 0.00 2020-09-30 2020-10-21 2020-12-04 2021-01-01 2021-01-31 2021-03-07 2021-04-11 2021-10-08 moindre coût d'exécution Projet 2020/2021 MR-PNIDDLE-176103-CS- QCBS / Assistance technique Strengthening Sélection fondée Open - En attente (appui à la DGCT pour la IDA / D5750 Decentralization and Local A posteriori sur la qualité et 800,000.00 0.00 2020-06-30 2020-07-21 2020-09-03 2020-10-01 2020-10-31 2020-12-05 2021-01-09 2022-01-09 International d'exécution mise e n œuvre et le suivi Government Capacity le coût des activités) Sélection fondée Strengthening MR-PNIDDLE-174855-CS- sur les En attente IDA / D5750 Decentralization and Local A posteriori Open - National 17,000.00 0.00 2021-07-31 2021-08-21 2021-10-04 2021-11-03 2021-12-08 2022-06-06 QCBS / Audit technique qualifications des d'exécution Government Capacity consultants MR-PNIDDLE-176105-CS- QCBS / Recrutement d’une Strengthening Sélection fondée firme (consultant) pour la En attente IDA / D5750 Decentralization and Local A posteriori sur la qualité et Open - National 100,000.00 0.00 2020-05-28 2020-06-18 2020-08-01 2020-08-29 2020-09-28 2020-11-02 2020-12-07 2021-12-07 conception et d'exécution Government Capacity le coût l’accompagnement d’une plateforme d’E-Procurement INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-PNIDDLE-174848-CS- INDV / Développement des modules additionnels au Strengthening En attente logiciel de gestion des CT IDA / D5750 Decentralization and Local A posteriori Individuel Open 40,000.00 0.00 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-04-11 d'exécution (gestion du personnel des Government Capacity CT, passation des marches, etc) MR-PNIDDLE-172587-GO- RFP / Amélioration de la base de données de la Strengthening DGCT sur les CTs afin En attente IDA / D5750 Decentralization and Local A posteriori Individuel Open 27,000.00 0.00 2020-05-30 2020-07-18 2020-08-08 2020-09-12 2021-03-11 d’inclure l’investissement d'exécution Government Capacity public et les infrastructures disponibles au niveau des CT (inclut géo localisation) MR-PNIDDLE-174856-CS- INDV / Evaluation et Strengthening En attente simplification du cadre IDA / D5750 Decentralization and Local A posteriori Individuel Open 30,000.00 0.00 2020-10-31 2020-12-19 2021-01-09 2021-02-13 2021-08-12 d'exécution légal pour la gestion foncière Government Capacity en milieu urbain Page 4 MR-PNIDDLE-174844-CS- Strengthening En attente INDV / Appuis à la mise en IDA / D5750 Decentralization and Local A posteriori Individuel Open 42,000.00 0.00 2020-11-30 2021-01-18 2021-02-08 2021-03-15 2021-09-11 d'exécution œuvre de la SNDDL Government Capacity MR-PNIDDLE-172590-GO- Strengthening RFP / Appui à l'élaboration En attente IDA / D5750 Decentralization and Local A posteriori Individuel Open 40,000.00 0.00 2020-10-31 2020-12-19 2021-01-09 2021-02-13 2021-08-12 de la Stratégie RFELA ( d'exécution Government Capacity Egalité genre ) et son PA MR-PNIDDLE-174831-CS- Strengthening INDV / Appui mise en En attente IDA / D5750 Decentralization and Local A posteriori Individuel Open 100,000.00 0.00 2020-05-30 2020-07-18 2020-08-08 2020-09-12 2021-03-11 œuvre de la Stratégie du d'exécution Government Capacity REFELA MR-PNIDDLE-174834-CS- INDV / Amélioration et Strengthening mobilisation des recettes En attente IDA / D5750 Decentralization and Local A posteriori Individuel Open 40,000.00 0.00 2020-12-31 2021-02-18 2021-03-11 2021-04-15 2021-10-12 locales à travers le d'exécution Government Capacity renforcement de capacités et l’utilisation des outils TIC MR-PNIDDLE-174840-CS- INDV / Redéploiement et Strengthening En attente Installation du logiciel IDA / D5750 Decentralization and Local A posteriori Individuel Open 27,000.00 0.00 2021-08-31 2021-10-19 2021-11-09 2021-12-14 2022-06-12 d'exécution budgétaro-comptable Government Capacity développé par le Trésor MR-PNIDDLE-174838-CS- Strengthening En attente INDV / Amélioration de la IDA / D5750 Decentralization and Local A posteriori Individuel Open 40,000.00 0.00 2021-01-31 2021-03-21 2021-04-11 2021-05-16 2021-11-12 d'exécution GRH des communes ciblées Government Capacity MR-PNIDDLE-172591-GO- En attente IDA / D5750 Project Management A posteriori Individuel Open 200,000.00 0.00 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-04-11 RFP / Assistance technique d'exécution MR-PNIDDLE-172597-GO- En attente RFP / Manuels de IDA / D5750 Project Management A posteriori Individuel Open 30,000.00 0.00 2020-05-30 2020-07-18 2020-08-08 2020-09-12 2021-03-11 d'exécution procédures du projet (2) MR-PNIDDLE-174832-CS- Strengthening En attente INDV / Enquête de IDA / D5750 Decentralization and Local A posteriori Individuel Open 20,000.00 0.00 2021-09-30 2021-11-18 2021-12-09 2022-01-13 2022-07-12 d'exécution satisfaction Government Capacity MR-PNIDDLE-172586-GO- Strengthening RFP / Etude de référence En attente IDA / D5750 Decentralization and Local A posteriori Individuel Open 35,000.00 0.00 2020-05-30 2020-07-18 2020-08-08 2020-09-12 2021-03-11 sur les opérateurs d'exécution Government Capacity économiques MR-PNIDDLE-174830-CS- INDV / Assistance technique En attente IDA / D5750 Project Management A posteriori Individuel Open 100,000.00 0.00 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-04-11 (Ingénieurs contrôle de d'exécution qualité ) MR-PNIDDLE-174846-CS- En attente INDV / Elaboration plan de IDA / D5750 Project Management A posteriori Individuel Open 27,000.00 0.00 2020-08-31 2020-10-19 2020-11-09 2020-12-14 2021-06-12 d'exécution communication MR-PNIDDLE-172607-GO- En attente RFP / Recrutement du IDA / D5750 Project Management A priori Individuel Open 1,019,000.00 0.00 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-04-11 d'exécution personnel clé du projet MR-PNIDDLE-177651-CS- INDV / Accompagnement et suivi technique pour la mise En attente IDA / D5750 Project Management A posteriori Individuel Limited 3,000.00 0.00 2020-06-03 2020-06-08 2020-06-29 2020-08-03 2021-01-30 en place d’un système d'exécution complet pour la visioconférence pour la CCP Page 5 MR-PNIDDLE-177650-CS- Strengthening Sélection de CDS / Elaboration du Plan En attente IDA / D5750 Decentralization and Local A posteriori consultants par Direct 30,000.00 0.00 2020-06-03 2020-06-13 2020-08-17 2021-02-13 de Développement Local d'exécution Government Capacity entente directe (PDL) de MBerra MR-PNIDDLE-191733-CS- En attente INDV / Recrutement d'un IDA / D5750 Project Management A posteriori Individuel Limited 35,000.00 0.00 2020-09-03 2020-09-08 2020-09-29 2020-11-03 2021-05-02 d'exécution Chef d'antenne Kiffa MR-PNIDDLE-191734-CS- INDV / Recrutement d'un En attente IDA / D5750 Project Management A posteriori Individuel Limited 25,000.00 0.00 2020-09-03 2020-09-08 2020-09-29 2020-11-03 2021-05-02 spécialiste Environnement d'exécution Antenne de Kiffa MR-PNIDDLE-191735-CS- INDV / Recrutement d'un En attente IDA / D5750 Project Management A posteriori Individuel Limited 25,000.00 0.00 2020-09-03 2020-09-08 2020-09-29 2020-11-03 2021-05-02 spécialiste Social et Genre d'exécution Antenne de Kiffa MR-PNIDDLE-191736-CS- En attente INDV / Recrutement d'un IDA / D5750 Project Management A posteriori Individuel Limited 30,000.00 0.00 2020-09-03 2020-09-08 2020-09-29 2020-11-03 2021-05-02 d'exécution spécialiste infrastructure MR-PNIDDLE-191737-CS- En attente INDV / Recrutement d'un IDA / D5750 Project Management A posteriori Individuel Limited 30,000.00 0.00 2020-09-03 2020-09-08 2020-09-29 2020-11-03 2021-05-02 d'exécution Responsable Environnement MR-PNIDDLE-191738-CS- En attente INDV / Recrutement IDA / D5750 Project Management A posteriori Individuel Limited 30,000.00 0.00 2020-09-03 2020-09-08 2020-09-29 2020-11-03 2021-05-02 d'exécution Responsable Social et Genre MR-PNIDDLE-191739-CS- En attente INDV / Recrutement d'un IDA / D5750 Project Management A posteriori Individuel Limited 30,000.00 0.00 2020-09-03 2020-09-08 2020-09-29 2020-11-03 2021-05-02 d'exécution Responsable communication Page 6