Procurement Plan I. General 1. Project Information Project Name: Transportation Corridors Project Country: Iraq Project ID: Loan/Credit Numbers: P131550 2. Bank's approval date of Procurement Plan Original: 9/24/2013 Revision 1: 3. Date of General Procurement Notice 7/12/2013 II. Goods, Work and Non-Consulting Services Thresholds Prior Review Threshold. Procurement Decisions subject to Prior Review by the Bank as stated in 1. Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Prior Review Threshold 1a. Procurement Category (USD) >= 0.5 million and any direct contract regardless Goods of value >= 5 million and any direct contract regardless of Works value >= 0.5 million and any direct contract regardless Non-Consultant Services of value Procurement Method 1b. Procurement Method Threshold (USD) ICB and LIB (Goods) > 500,000 NCB (Goods) ≤ 500,000 Shopping (Goods) ≤ 100,000 ICB (Works) > 5 million NCB (Works) ≤ 5 million Shopping (Works) ≤ 200,000 2. Prequalification. Bidders for R7, R8 , and R9 shall be prequlified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. No 3. Proposed Procedures for CDD Components (as per paragraph 3.17 of the Guidelines): Refer to the relevant CDD project implementation document approved by the Bank: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Master Implmnetation Manual 5. Any Other Special Procurement Arrangements: advance procurement and retroactive financing is applicable under this project 6. Procurement Packages with Methods and Time Schedule: See attached "Goods and Works" sheet III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Threshold 1a. Procurement Category (USD) Consulting Firms (Competitive) 0.2 million Consulting Firms (Sole Source) All Individual Consultants (Competitive) 0.1 million Individual Consultants (Sole Source) All Procurement Method 1b. Procurement Method Threshold (USD) QCBS QCB FCS LCS CQS 0.3 million Consulting Firms (Sole Source) Individual Consultants (Competitive) Individual Consultants (Sole Source) ICB (Non-Consultant Services) Include all methods authorized by the loan agreement 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to less than costOPCPR Note: list $_200,000 ______equivalent of ceilings can per contract, be found here: may comprise entirely of national consultants http://go.worldbank.org/MKXO98RY40 3. Any Other Special Selection Arrangements:advance procurement and retroactive financing is applicable under this project 4. Consultancy Assignments with Selection Methods and Time Schedule: See attached "Consulting Services" sheet Corridors Project ew by the Bank as stated in ble procurement methods (not alist /Procurement Accredited ] Comments Comments ordance with the provisions of of the Guidelines): Refer to the Not Applicable ster Implmnetation Manual ent and retroactive financing is ched "Goods and Works" sheet y Bank as stated in Appendix 1 to Comments Comments onsultants for services, estimated se entirely of national consultants nk.org/MKXO98RY40 nd retroactive financing is dule: See attached "Consulting Revised Procurement Plan: May,2 2017 procurement method interval (day) interval (day) interval (day) interval (day) interval (day) interval (day) interval (day) Financed by Plan /Actual length(km) Deadline for Review Submission of WB No Invitation to PQ Evaluation WB No Procurement Ref.# Description Governorate submission Issue BDs By Bank BID Objection BID Report Objection Application of BID To be implemendted by GDRB P 01-Mar-14 7 08-Mar-14 7 15-Mar-14 42 26-Apr-14 42 07-Jun-14 14 21-Jun-14 7 28-Jun-14 45 Construction of Girshen and Suheila TCP.W.KRG.A6 Duhok Governorate 20 WB ICB PRIOR R 23-May-16 7 30-May-16 3 04-Aug-16 49 22-Sep-16 21 13-Oct-16 14 27-Oct-16 3 30-Oct-16 42 Highway A 56 29-Sep-16 Not applicable because no prequalification was required y,2 2017 Duration Date interval (day) interval (day) interval (day) interval (day) interval (day) Contract Bids Evaluation WB No Bids Opening Award Contract Signing Commencement Completion Comments Report Objection 12-Aug-14 28 09-Sep-14 14 23-Sep-14 7 30-Sep-14 28 28-Oct-14 21 18-Nov-14 1095 17-Nov-17 11-Dec-16 28 08-Jan-17 14 22-Jan-17 7 29-Jan-17 28 26-Feb-17 21 19-Mar-17 900 05-Sep-19 HGG - Turkey 29-Sep-16 28 15-Jan-17 57 13-Mar-17 43 25-Apr-17 . Engineering Supervision Services - Road Prior QCBS P 15-Feb-14 28 15-Mar-14 28 12-Apr-14 7 19-Apr-14 3 22-Apr-14 42 03-Jun-14 42 TCP.CON.QCBS.KRG.A7 Prior QCBS R 19-May-16 19 07-Jun-16 14 28-Jul-16 3 31-Jul-16 5 05-Aug-16 45 19-Sep-16 21 section between Girshen & Suheila QCBS A 19-May-16 19 7-Jun-16 47 24-Jul-16 5 29-Jul-16 25 23-Aug-16 52 26-Sep-16 83 . Technical Assistance - Organization and Prior QCBS P 01-Feb-14 28 01-Mar-14 28 29-Mar-14 7 05-Apr-14 3 08-Apr-14 42 20-May-14 42 TCP.CON.QCBS.KRG.B2 (A)-(C) Post R 15-Jan-16 28 12-Feb-16 28 11-Mar-16 7 18-Mar-16 3 21-Mar-16 42 02-May-16 42 Capacity Improvement A . Technical Assistance -Information and Prior QCBS P 01-Sep-14 28 29-Sep-14 28 27-Oct-14 7 03-Nov-14 3 06-Nov-14 42 18-Dec-14 42 TCP.CON.QCBS.KRG.B2 (D) Post CQS R 1-Mar-16 28 29-Mar-16 28 26-Apr-16 7 03-May-16 3 06-May-16 42 17-Jun-16 42 Communication System A Technical Assistance -update and complete Prior QCBS P 01-Jul-14 28 29-Jul-14 28 26-Aug-14 7 02-Sep-14 3 05-Sep-14 42 17-Oct-14 42 TCP.CON.QCBS.KRG.B2 (D2) R 1-Jun-16 28 29-Jun-16 28 27-Jul-16 7 03-Aug-16 3 06-Aug-16 42 17-Sep-16 42 the road asset management Training and Study Tours for managerial and Prior QCBS P 01-Sep-14 28 29-Sep-14 28 27-Oct-14 7 03-Nov-14 3 06-Nov-14 42 18-Dec-14 42 TCP.CON.QCBS.KRG.B2 (E&H) Post CQS R 1-Mar-16 28 29-Mar-16 28 26-Apr-16 7 03-May-16 3 06-May-16 42 17-Jun-16 42 technical staff of GDRB A Prior CQS P 01-Mar-17 14 15-Mar-17 0 15-Mar-17 14 29-Mar-17 0 Call of proposals 30 Technical Assistance - Training of Local TCP.CON.QCBS.KRG.B4 (B) Post R Contractors and Consultants A Prior QCBS P 01-Jun-14 28 29-Jun-14 28 27-Jul-14 7 03-Aug-14 3 06-Aug-14 42 17-Sep-14 42 TCP.CON.C2 (A) Technical Audit R 1-Feb-16 28 29-Feb-16 28 28-Mar-16 7 04-Apr-16 3 07-Apr-16 42 19-May-16 42 A Prior CQS P 01-Jun-14 28 29-Jun-14 28 27-Jul-14 7 03-Aug-14 3 06-Aug-14 42 17-Sep-14 42 TCP.CON.C2 (B) FInancial Audit R 1-Jun-16 28 29-Jun-16 28 27-Jul-16 7 03-Aug-16 3 06-Aug-16 42 17-Sep-16 42 A 16-Jun-15 72 27-Aug-15 Two companies submit proposal Prior\Post IC P 01-Jun-14 6 7-Jun-14 TCP.CON.IC.C2 (C1) Individual Technical Expert / Procurement R 21-May-15 6 27-May-15 Prior A 3-Jul-15 TCP.CON.IC.C2 (C1) -A1 Post A 3-Jul-16 Post IC P 01-Jun-14 6 7-Jun-14 TCP.CON.IC.C2 (C2) Individual Technical Expert /Social expert R 15-Jan-16 6 21-Jan-16 A Post IC P 01-Jun-14 6 7-Jun-14 Individual Technical Expert / Environmental TCP.CON.IC.C2 (C3) R 15-Jan-16 6 21-Jan-16 expert A 15-Jul-14 7 22-Jul-14 28 19-Aug-14 7 26-Aug-14 3 29-Aug-14 14 12-Sep-14 10-Oct-16 7 17-Oct-16 28 14-Nov-16 7 21-Nov-16 3 24-Nov-16 14 08-Dec-16 18-Dec-16 2 20-Dec-16 24 13-Jan-17 13 26-Jan-17 89 25-Apr-17 01-Jul-14 7 08-Jul-14 28 05-Aug-14 7 12-Aug-14 3 15-Aug-14 14 29-Aug-14 13-Jun-16 7 20-Jun-16 29 19-Jul-16 7 26-Jul-16 3 29-Jul-16 14 12-Aug-16 29-Jan-15 7 05-Feb-15 28 05-Mar-15 7 12-Mar-15 3 15-Mar-15 14 29-Mar-15 29-Jul-16 7 05-Aug-16 28 02-Sep-16 7 09-Sep-16 3 12-Sep-16 14 26-Sep-16 28-Nov-14 7 05-Dec-14 28 02-Jan-15 7 09-Jan-15 3 12-Jan-15 14 26-Jan-15 29-Oct-16 7 05-Nov-16 28 03-Dec-16 7 10-Dec-16 3 13-Dec-16 14 27-Dec-16 29-Jan-15 7 05-Feb-15 28 05-Mar-15 7 12-Mar-15 3 15-Mar-15 14 29-Mar-15 29-Jul-16 7 05-Aug-16 28 02-Sep-16 7 09-Sep-16 3 12-Sep-16 14 26-Sep-16 28-Apr-17 14 Not Applicable 7 05-May-17 7 12-May-17 7 19-May-17 29-Oct-14 7 05-Nov-14 28 03-Dec-14 7 10-Dec-14 3 13-Dec-14 14 27-Dec-14 30-Jun-16 7 07-Jul-16 28 04-Aug-16 7 11-Aug-16 3 14-Aug-16 14 28-Aug-16 29-Oct-14 7 05-Nov-14 28 03-Dec-14 7 10-Dec-14 3 13-Dec-14 14 27-Dec-14 29-Oct-16 7 05-Nov-16 28 03-Dec-16 7 10-Dec-16 3 13-Dec-16 14 27-Dec-16 04-Oct-16 28 29-Jun-14 14 13-Jul-14 6-Jan-15 14 20-Jan-15 30/7/2015 8-Aug-15 29 6-Sep-15 30/7/2015 5-Sep-16 1 6-Sep-16 28 29-Jun-14 14 13-Jul-14 2-Jan-16 14 16-Jan-16 28 29-Jun-14 14 13-Jul-14 1-Feb-16 14 15-Feb-16