18 Months Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 19, 2016 2. Date of General Procurement Notice: August 5, 2016 3. Period covered by this procurement plan: June 2016 to December 2017 4. Implementing Agencies: • Component 1: Ministry of Agriculture, Forestry and Fisheries (MAFF): Fisheries Administration (FiA) • Component 2: Cambodian National Mekong Committee (CNMC) II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. Procurement Method Prior Review Comments Threshold US$ 1. Each package estimated Goods to cost more than 2,000,000 2. Each package estimated Works to cost more than 10,000,000 3. (Non-Consultant Services) Each package estimated to cost more than 2,000,000 2. Prequalification. Not applicable. 3. Any Other Special Procurement Arrangements: Not Applicable 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) Component 1: Fisheries and Aquatic Resources Management in Northern Cambodia 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior / US$ ence Post) (yes/n o) Office equipment, office furniture, Shopping boats, and NCB Laboratory methods FiA- Aquatic life will be G001 and water 343,000 8 No Post followed -008 quality to monitoring procure equipment these , Mapping goods. Equipment, motorbikes , vehicles, Constructio n of Office for FiA Stung Shopping FiA- Treng and and NCB CW00 Kratie, 660,000 3 No Post methods 1- Hatchery will be 003 constructio followed n, and FiA office renovation Component 2: Support for WRM in the Northern Cambodia and trans- boundary dialogue 1 2 3 4 5 6 7 Ref. Description Estimate Package Domestic Review Comments No. d s Preferenc by Bank Cost e (Prior / US$ (yes/no) Post) Office furniture, office equipment, Hydro- metrological equipment, Shopping and G01- Water and NCB methods 1,000,50 10 hydrological 10 No Post will be followed 0 (goods) measurement to procure equipment, these goods. vehicles, motorbikes, Supply and Installation of Meteorology measurement equipment, ect. Construction of PDOWRAM office building in Kratie, W01a Steung Treng 390,000 1 No Post NCB (Works) , Rattanakiri, and Mondulkiri Province ( 4 buildings) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Each package estimated Selection of Consulting firms to cost more than 1,000,000 2. Each package estimated Selection of Individual Consultant to cost more than 300,000 2. Any Other Special Selection Arrangements: Not Applicable 3. Consultancy Assignments with Selection Methods Component 1: Fisheries and Aquatic Resources Management in Northern Cambodia 1 2 3 4 5 6 Ref. Description of Estimate Packa Review Comments No. Assignment d ges by Cost Bank US$ (Prior / million Post) FiA-CS FM consultants, 001- Procurement 26 individual 026 Consultants, national and 1,873,00 International 26 Post international 0 Fishery Resource consultants will Management be engaged. Specialist, International Community Fishery Specialist, National Lead Fishery Resource Specialist, National Lead Community Fishery Specialist, National Environmental and Social (safeguards) specialist, National Gender Specialist, Regional Aquaculture Specialist, National Infrastructure Engineer, etc. Component 2: Support for WRM in the Northern Cambodia and trans- boundary dialogue 1 2 3 4 5 6 Ref. Description of Estimate Packa Review Comments No. Assignment d ges by Cost Bank US$ (Prior / million Post) 2 FM consultants, 2 5 individual Procurement national and CS 01- Consultants, 302,000 5 Post international 05 Project consultants will accountant be engaged. consultant. Bundled auditor selected by MEF. SSS method will CS07 External audit 50,000 1 Post be followed to firm engage the auditor for this project Technical Water 2,500,00 QCBS method will CS08 1 Prior Resource 0 be followed. Management Firm NIS upgrading CS09 support CQS method will 50,000 1 Post consultant ( be followed. Firm) PROCUREMENT Cambodia : Mekong Integrated Water Resources Management Project- Phase III PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2017-03-21 2021-04-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148647 GPN Date: Project Name: Mekong Integrated Water Resources Management Project- Phase III Loan / Credit No: IDA / 57770 Fisheries Administration Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 1. Fisheries and Aquatic FIA-CW-003 / Office Request for Single Stage - One 2017-12- IDA / 57770 Resources Management in Post Open - National 20,000.00 19,995.83 Signed 2017-07-26 2017-10-08 2017-08-24 Renovation for FiA Quotations Envelope 07 Northern Cambodia FIA-CW-001 / Construction of New Office Buildings for 1. Fisheries and Aquatic Request for Single Stage - One 2019-10- PFiA Stung Treng and Kratie IDA / 57770 Resources Management in Post Open - National 140,000.00 247,481.42 Completed 2019-03-04 2019-04-23 2019-05-17 Quotations Envelope 20 (Including renovation of Northern Cambodia existing office of PFiA Kratie) FIA-CW-074 / Natural Laterite Road Reconstruction (Length 690m Width 4m Earth 1. Fisheries and Aquatic Community Driven 2019-06- Work Heigh t0.3m Natural IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-02-08 2019-02-04 2019-02-13 2019-02-08 2019-03-04 2019-02-22 Development 02 Gravel Height 0.1m) in Preaek Northern Cambodia Prasab Commune, Preaek Prasab District, Kratie Province FIA-CW-075 / Natural Laterite Road Reconstruction (Length 630m Width 5m Earth 1. Fisheries and Aquatic Community Driven 2019-06- Work Height 0.3m Natural IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-02-08 2019-02-10 2019-02-13 2019-02-10 2019-03-04 2019-02-21 Development 02 Gravel Height 0.15m) in Bos Northern Cambodia Leav Commune, Chetr Borei District, Kratie Province FIA-CW-076 / Laterite Road Reconstruction (Length 1278m Width 6m, Earth Work 1. Fisheries and Aquatic Community Driven 2019-06- Height 0.2m, Laterite Height IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-02-08 2019-02-10 2019-02-13 2019-02-10 2019-03-04 2019-02-22 Development 02 0.15m) in Preah Rumkel Northern Cambodia Commune, Thalaborivat District, Stung Treng Province FIA-CW-077 / Pipe Culverts Construction (4 Pipe Culverts 1. Fisheries and Aquatic Diameter of Pipe 1m, Length Community Driven 2019-05- IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-02-08 2019-02-10 2019-02-13 2019-02-10 2019-03-04 2019-02-22 6m) in Koh Sampeay Development 03 Northern Cambodia Commune, Siem Bouk District, Stung Treng Province FIA-CW-078 / Pipe Culverts Construction and Earth Road 125m (Pipe Culverts and 1. Fisheries and Aquatic Community Driven 2019-06- Double Pipe Culvert, Diameter IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-02-08 2019-02-10 2019-02-13 2019-02-10 2019-03-04 2019-02-22 Development 02 of Pipe 1m, Length 6m) in Northern Cambodia Sdao Commune, Se San District, Stung Treng Province FIA-CW-079 / Natural Gravel Road Reconstruction (Length 690m, Width 4m, 1. Fisheries and Aquatic Earth Work Height 0.3m, Community Driven 2019-07- IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-03-18 2019-03-29 2019-03-23 2019-03-29 2019-04-11 2019-04-08 Natural Gravel Height 0.15m) Development 10 Northern Cambodia in Ruseykeo Commune, Sambour District, Kratie Province FIA-CW-081 / Natural Gravel Road Reconstruction and Culvert (Length 1300m, Width 3m, Earth Work Height 0.2m, 1. Fisheries and Aquatic Community Driven 2019-07- Natural Gravel Height 0.15m, IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-03-18 2019-03-29 2019-03-23 2019-03-29 2019-04-11 2019-04-08 Development 10 and Single Culvert Length 5m, Northern Cambodia Diameter 0.6m) in Sambour Commune, Sambour District, Kratie Province FIA-CW-082 / Natural Gravel Road Reconstruction (Length 800m, Width 4m, 1. Fisheries and Aquatic Community Driven 2019-07- Natural Gravel Height 0.2m) in IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-03-18 2019-03-29 2019-03-23 2019-03-29 2019-04-11 2019-04-08 Development 10 Kampong Cham Commune, Northern Cambodia Sambour District, Kratie Province FIA-CW-083 / Laterite Road Reconstruction (Length 930m, Width 5m, Earth Work Height 1. Fisheries and Aquatic Community Driven 2019-08- 0.2m, Laterite Height 0.15m) IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-05-06 2019-05-07 2019-05-11 2019-05-07 2019-05-30 2019-05-17 Development 28 in Koh Pras Commune, Siem Northern Cambodia Bouk District, Stung Treng Province FIA-CW-084 / 2 Culverts Construction and Fill Earth 1. Fisheries and Aquatic Works (Length 60m, Width 6m Community Driven 2019-08- IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-05-06 2019-05-07 2019-05-11 2019-05-07 2019-05-30 2019-05-17 and Height 3m) in Ou Mreah Development 28 Northern Cambodia Commune, Ou Mreah District, Stung Treng Province FIA-CW-085 / Laterite Road Reconstruction (Length 1,043m, Width 5m, Earth 1. Fisheries and Aquatic Community Driven 2019-08- Work Height 0.5m, Laterite IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-05-06 2019-05-07 2019-05-11 2019-05-07 2019-05-30 2019-05-17 Development 28 Height 0.15m) in Kang Cham Northern Cambodia Commune, Thalaborivat District, Stung Treng Province Page 1 FIA-CW-080 / Natural Gravel Road Reconstruction and Culvert (Length 730m, Width 4m, Earth Work Height 0.2m, 1. Fisheries and Aquatic Community Driven 2019-07- Natural Gravel Height 0.15m, IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-03-18 2019-03-29 2019-03-23 2019-03-29 2019-04-11 2019-04-08 Development 10 and Single Culvert Length 5m, Northern Cambodia Diameter 1.00m) in Voathonak Commune, Sambour District, Kratie Province FIA-CW-086 / 4 Pipe Culverts 1. Fisheries and Aquatic Construction in Ou Krieng Community Driven 2019-11- IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-07-17 2019-07-16 2019-07-22 2019-07-16 2019-08-10 2019-07-23 Commune, Sambour District, Development 08 Northern Cambodia Kratie Province FIA-CW-087 / 2 Pipe Culverts 1. Fisheries and Aquatic Construction in Boeng Char Community Driven 2019-11- IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-07-17 2019-07-17 2019-07-22 2019-07-17 2019-08-10 2019-07-23 Commune, Sambour District, Development 08 Northern Cambodia Kratie Province FIA-CW-088 / Earth Work Road Construction (Length 1. Fisheries and Aquatic 500m, Width 4m, Height Community Driven 2020-01- IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-09-30 2019-10-10 2019-10-05 2019-10-17 2019-10-24 2019-10-30 0.5m) in Kaoh Sneng Development 22 Northern Cambodia Commune, Thalaborivat District, Stung Treng Province FIA-CW-089 / Earth Work Road Construction (Length 1. Fisheries and Aquatic 610mm, Width 3m, Height Community Driven 2020-01- IDA / 57770 Resources Management in Post Direct 10,000.00 10,000.00 Signed 2019-09-30 2019-10-10 2019-10-05 2019-10-17 2019-10-24 2019-10-30 0.6m) in Ou Svay Commune, Development 22 Northern Cambodia Thalaborivat District, Stung Treng Province FIA-CW-012 / Demarcation of CFi Fishery Boundary 1. Fisheries and Aquatic (Poles, Signboard) and Community Driven 2020-06- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2019-12-01 2019-12-02 2019-12-06 2019-12-05 2019-12-26 2019-12-12 Infrastructure (Cfi Office) in Development 23 Northern Cambodia Krala Peas Community Fisheries in Stung Treng province FIA-CW-013 / Demarcation of CFi Fishery Boundary 1. Fisheries and Aquatic (Poles, Signboard) and Community Driven 2020-06- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2019-12-01 2019-12-02 2019-12-06 2019-12-05 2019-12-25 2019-12-12 Infrastructure (Cfi Office) in Development 22 Northern Cambodia Pong Tuek Community Fisheries in Stung Treng province FIA-CW-021 / Demarcation of CFi Fishery Boundary 1. Fisheries and Aquatic (Poles, Signboard) and Community Driven 2020-06- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2019-12-01 2019-12-02 2019-12-06 2019-12-05 2019-12-18 2019-12-12 Infrastructure (Cfi Office) in Development 15 Northern Cambodia Damrei Phong Community Fisheries in Stung Treng province FIA-CW-041 / Demarcation of CFi Fishery Boundary 1. Fisheries and Aquatic (Poles, Signboard) and Community Driven 2020-07- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2019-12-10 2019-12-10 2019-12-15 2019-12-13 2020-01-03 2019-12-25 Infrastructure (Cfi Office) in Development 01 Northern Cambodia Tomnub Pak+A20 Community Fisheries in Kratie province FIA-CW-042 / Demarcation of CFi Fishery Boundary 1. Fisheries and Aquatic (Poles, Signboard) and Community Driven 2020-07- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2019-12-10 2019-12-10 2019-12-15 2019-12-13 2020-01-03 2019-12-25 Infrastructure (Cfi Office) in Development 01 Northern Cambodia Kampong Roteh Community Fisheries in Kratie province FIA-CW-043 / Demarcation of CFi Fishery Boundary 1. Fisheries and Aquatic (Poles, Signboard) and Community Driven 2020-07- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2019-12-10 2019-12-10 2019-12-15 2019-12-13 2020-01-03 2019-12-25 Infrastructure (Cfi Office) in Development 01 Northern Cambodia Damrae Community Fisheries in Kratie province FIA-CW-045 / Demarcation of CFi Fishery Boundary 1. Fisheries and Aquatic (Poles, Signboard) and Community Driven 2020-07- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2019-12-10 2019-12-10 2019-12-15 2019-12-13 2020-01-03 2019-12-25 Infrastructure (Cfi Office) in Development 01 Northern Cambodia Koh Dambang Community Fisheries in Kratie province FIA-CW033 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-09- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-03-06 2020-03-06 2020-03-11 2020-03-08 2020-03-28 2020-03-17 (Cfi Office) in Khsach Leav Development 24 Northern Cambodia Community Fisheries in Kratie province FIA-CW034 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-09- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-03-06 2020-03-06 2020-03-11 2020-03-08 2020-03-28 2020-03-17 (Cfi Office) in Koh Khnhaer Development 24 Northern Cambodia Community Fisheries in Kratie province FIA-CW035 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-09- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-03-06 2020-03-06 2020-03-11 2020-03-08 2020-03-28 2020-03-17 (Cfi Office) in Pon Chea Development 24 Northern Cambodia Community Fisheries in Kratie province FIA-CW047 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-03-06 2020-03-06 2020-03-11 2020-03-08 2020-04-04 2020-03-17 (Cfi Office) in Rusey Keo Development 01 Northern Cambodia Community Fisheries in Kratie province Page 2 FIA-CW048 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-09- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-03-06 2020-03-06 2020-03-11 2020-03-08 2020-03-28 2020-03-17 (Cfi Office) in Ou lung Development 24 Northern Cambodia Community Fisheries in Kratie province FIA-CW006 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-03-18 2020-03-15 2020-03-23 2020-03-17 2020-04-07 2020-03-23 (Cfi Office) in Kaoh Sampeay Development 04 Northern Cambodia Community Fisheries in Stung Treng province FIA-CW014 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,000.00 Signed 2020-03-18 2020-03-15 2020-03-23 2020-03-17 2020-04-07 2020-03-23 (Cfi Office) in Anlong Svay 1 Development 04 Northern Cambodia Community Fisheries in Stung Treng province FIA-CW016 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-03-18 2020-03-15 2020-03-23 2020-03-17 2020-04-07 2020-03-23 (Cfi Office) in Kaoh Pnov Development 04 Northern Cambodia Community Fisheries in Stung Treng province FIA-CW018 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-03-18 2020-03-15 2020-03-23 2020-03-17 2020-04-07 2020-03-23 (Cfi Office) in Thmei Development 04 Northern Cambodia Community Fisheries in Stung Treng province FIA-CW022 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-03-18 2020-03-15 2020-03-23 2020-03-17 2020-04-07 2020-03-23 (Cfi Office) in Anlong Svay 2 Development 04 Northern Cambodia Community Fisheries in Stung Treng province FIA-CW004 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-04-01 2020-04-06 2020-04-06 2020-04-09 2020-04-21 2020-04-22 (Cfi Office) in Stao 2 Development 18 Northern Cambodia Community Fisheries in Stung Treng province FIA-CW019 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-04-01 2020-04-06 2020-04-06 2020-04-09 2020-04-21 2020-04-22 (Cfi Office) in Stao 1 Development 18 Northern Cambodia Community Fisheries in Stung Treng province FIA-CW-090 / Natural Gravel Road Reconstruction (Length 1250m, Width 4m, Earth Work 1. Fisheries and Aquatic Community Driven 2020-10- Height 0.25m, Natural Gravel IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-04-06 2020-04-06 2020-04-11 2020-04-09 2020-04-26 2020-04-21 Development 23 Height 0.15m) in Voadthonak Northern Cambodia Commune, Sambour District, Kratie FIA-CW-091 / Natural Gravel Road Reconstruction and Culvert (Length 820m, Width 4m, Earth Work Height 0.35m, 1. Fisheries and Aquatic Community Driven 2020-10- Natural Gravel Height 0.15m, IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-04-06 2020-04-06 2020-04-11 2020-04-09 2020-04-26 2020-04-21 Development 23 and 2 Single Culvert Length Northern Cambodia 6m, Diameter 0.60m) in Sambour Commune, Sambour District, Kratie FIA-CW-092 / Natural Gravel Road Reconstruction (Length 1250m, Width 4m, Earth Work 1. Fisheries and Aquatic Community Driven 2020-10- Height 0.25m, Natural Gravel IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-04-06 2020-04-06 2020-04-11 2020-04-09 2020-04-26 2020-04-21 Development 23 Height 0.15m) in Russey Keo Northern Cambodia Commune, Prek Prasab District, Kratie FIA-CW-093 / Natural Gravel Road Reconstruction (Length 1250m, Width 4m, Earth Work 1. Fisheries and Aquatic Community Driven 2020-10- Height 0.25m, Natural Gravel IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-04-06 2020-04-06 2020-04-11 2020-04-13 2020-04-26 2020-04-21 Development 23 Height 0.15m) in Ta Mao Northern Cambodia Commune, Prek Prasab District, Kratie FIA-CW-094 / Natural Gravel Road Reconstruction and Culvert (Length 820m, Width 4m, Earth Work Height 0.35m, 1. Fisheries and Aquatic Community Driven 2020-10- Natural Gravel Height 0.15m, IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-04-06 2020-04-06 2020-04-11 2020-04-09 2020-04-26 2020-04-21 Development 23 and 2 Single Culvert Length Northern Cambodia 6m, Diameter 0.60m) in Preak Prasab Commune, Prek Prasab District, Kratie FIA-CW-095 / Natural Gravel Road Reconstruction (Length 1250m, Width 4m, Earth Work 1. Fisheries and Aquatic Community Driven 2020-10- Height 0.25m, Natural Gravel IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-04-06 2020-04-06 2020-04-11 2020-04-09 2020-04-26 2020-04-21 Development 23 Height 0.15m) in Saob Northern Cambodia Commune, Prek Prasab District, Kratie FIA-CW029 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-04-06 2020-04-06 2020-04-11 2020-04-09 2020-04-26 2020-04-22 (Cfi Office) in Koh Phdau Development 23 Northern Cambodia Community Fisheries in Kratie province Page 3 FIA-CW030 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-04-06 2020-04-06 2020-04-11 2020-04-09 2020-04-26 2020-04-22 (Cfi Office) in Ampil Teuk Development 23 Northern Cambodia Community Fisheries in Kratie province FIA-CW031 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-04-06 2020-04-06 2020-04-11 2020-04-09 2020-04-26 2020-04-22 (Cfi Office) in Kampong Krabei Development 23 Northern Cambodia Community Fisheries in Kratie province FIA-CW032 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-10- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-04-06 2020-04-06 2020-04-11 2020-04-09 2020-04-26 2020-04-22 (Cfi Office) in Somphen Development 23 Northern Cambodia Community Fisheries in Kratie province FIA-CW096 / Natural Gravel Road Reconstruction (Length 1300m, Width 4m, Earth 1. Fisheries and Aquatic Community Driven 2020-11- Work(900m) Height 0.3m, IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-04-27 2020-05-01 2020-05-02 2020-05-04 2020-05-19 2020-05-13 Development 15 Natural Gravel Height 0.15m) Northern Cambodia in Bos Leav Commune, Chetr Borei District, Kratie FIA-CW097 / Natural Gravel Road Reconstruction (Length 1250m, Width 4m, Earth Work 1. Fisheries and Aquatic Community Driven 2020-11- Height 0.25m, Natural Gravel IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-04-27 2020-05-01 2020-05-02 2020-05-04 2020-05-19 2020-05-13 Development 15 Height 0.15m) in Kanhchor Northern Cambodia Commune, Chhlong District, Kratie FIA-CW098 / Natural Gravel Road Reconstruction (Length 1000m, Width 5m, Earth Work 1. Fisheries and Aquatic Community Driven 2020-11- Height 0.3m, Natural Gravel IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-04-27 2020-05-01 2020-05-02 2020-05-04 2020-05-19 2020-05-13 Development 15 Height 0.15m) in Preak Saman Northern Cambodia Commune,, Chhlong District, Kratie FIA-CW099 / The Earth Work Road Reconstruction (Length 1. Fisheries and Aquatic 900m,Width 3m and Height Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-05-21 2020-05-21 2020-05-26 2020-05-22 2020-06-10 2020-05-29 0.6m) in OuSvay Commune, Development 07 Northern Cambodia Thalaborivat District, Stung Treng FIA-CW100 / The Earth Work Road Reconstruction (Length 1. Fisheries and Aquatic 760m,Width 4m and Height Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-05-21 2020-05-21 2020-05-26 2020-05-22 2020-06-10 2020-05-29 0.6m) in KoahSneng Development 07 Northern Cambodia Commune, Thalaborivat District, Stung Treng FIA-CW011 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2020-12- (Cfi Office) in Koh Sneng IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-08 2020-06-08 2020-06-13 2020-06-10 2020-06-26 2020-06-17 Development 23 Commune, Borei OuSvay San Northern Cambodia Chey District, Stung Treng province FIA-CW015 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-08 2020-06-08 2020-06-13 2020-06-10 2020-06-26 2020-06-17 (Cfi Office) in Kang Cham Development 23 Northern Cambodia Commune, Thalaborivat District, Stung Teng province FIA-CW017 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-08 2020-06-08 2020-06-13 2020-06-10 2020-06-26 2020-06-17 (Cfi Office) in Thalaborivat Development 23 Northern Cambodia Commune, Thalaborivat District, Stung Teng province FIA-CW020 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-08 2020-06-08 2020-06-13 2020-06-10 2020-06-26 2020-06-17 (Cfi Office) in Phlouk Development 23 Northern Cambodia Commune, Sesan District, Stung Teng province FIA-CW023 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-08 2020-06-08 2020-06-13 2020-06-10 2020-06-26 2020-06-17 (Cfi Office) in Kang Cham Development 23 Northern Cambodia Commune, Thalaborivat District, Stung Teng province FIA-CW101 / Earth work road reconstruction (Length 1. Fisheries and Aquatic 1000m, Width 6m, Height Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-06-08 2020-06-12 2020-06-13 2020-06-15 2020-06-26 2020-06-23 0.5m) in Thmar Kreae Development 23 Northern Cambodia Commune, Chetr Borei District, Kratie FIA-CW102 / Natural Gravel Road Reconstruction (Length 1. Fisheries and Aquatic Community Driven 2020-12- 1900m, Width 5m, Height IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-06-08 2020-06-12 2020-06-13 2020-06-15 2020-06-26 2020-06-23 Development 23 0.25m) in Sambok Commune, Northern Cambodia Chetr Borei District, Kratie FIA-CW103 / Natural Gravel Road Reconstruction (Length 1. Fisheries and Aquatic 1200m, Width 4m, Height Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-06-08 2020-06-12 2020-06-13 2020-06-15 2020-06-26 2020-06-23 0.30m) in Kaoh Khnhaer Development 23 Northern Cambodia Commune, Sambour District, Kratie Page 4 FIA-CW104 / Natural Gravel Road Reconstruction (Length 1. Fisheries and Aquatic 1400m, Width 4m, Height Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-06-08 2020-06-12 2020-06-13 2020-06-15 2020-06-30 2020-06-23 0.30m) in Ou Krieng Development 27 Northern Cambodia Commune, Sambour District, Kratie FIA-CW105 / Triple Pipe Culvert (1mx10m) and Single 1. Fisheries and Aquatic Community Driven 2020-12- Pipe Culvert (1mx10m) in IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-06-15 2020-06-19 2020-06-20 2020-06-25 2020-07-03 2020-07-08 Development 30 Samki Commune, Stung Treng Northern Cambodia District, Stung Treng Province FIA-CW007 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-12 2020-06-19 2020-06-17 2020-06-25 2020-06-30 2020-07-08 (Cfi Office) in Ou Mreah Development 27 Northern Cambodia Commune, Siem Bouk District, Stung Teng province FIA-CW008 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-12 2020-06-19 2020-06-17 2020-06-25 2020-06-30 2020-07-08 (Cfi Office) in Ou Mreah Development 27 Northern Cambodia Commune, Siem Bouk District, Stung Teng province. FIA-CW009 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-12 2020-06-19 2020-06-17 2020-06-25 2020-06-25 2020-07-08 (Cfi Office) in Ou Mreah Development 22 Northern Cambodia Commune, Siem Bouk District, Stung Teng province. FIA-CW010 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-12 2020-06-19 2020-06-17 2020-06-25 2020-06-30 2020-07-08 (Cfi Office) in Kaoh Preah Development 27 Northern Cambodia Commune, Siem Bouk District, Stung Teng province. FIA-CW027 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-12 2020-06-19 2020-06-17 2020-06-25 2020-06-30 2020-07-08 (Cfi Office) in Samaki Sangkat, Development 27 Northern Cambodia Stungn Treng City, Stung Teng province. FIA-CW005 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-15 2020-06-19 2020-06-20 2020-06-25 2020-07-03 2020-07-08 (Cfi Office) in Talat Commune, Development 30 Northern Cambodia Sesan District, Stung Treng province. FIA-CW024 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2020-12- (Cfi Office) in IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-15 2020-06-19 2020-06-20 2020-06-25 2020-07-03 2020-07-08 Development 30 Koh Snaeng Commune, Borei Northern Cambodia Ou Svay Sen Chey District, Stung Treng province. FIA-CW025 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2020-12- (Cfi Office) in Koh Snaeng IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-15 2020-06-19 2020-06-20 2020-06-25 2020-07-03 2020-07-08 Development 30 Commune, Borei Ou Svay Sen Northern Cambodia Chey District, Stung Treng province FIA-CW026 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2020-12- (Cfi Office) in Koh Snaeng IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-15 2020-06-19 2020-06-20 2020-06-25 2020-07-03 2020-07-08 Development 30 Commune, Borei Ou Svay Sen Northern Cambodia Chey District, Stung Treng province. FIA-CW028 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2020-12- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-06-15 2020-06-19 2020-06-20 2020-06-25 2020-07-03 2020-07-08 (Cfi Office) in Development 30 Northern Cambodia Samaki Sangkat, Stung Treng City, Stung Teng province. FIA-CW038 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2021-01- (Cfi Office) in Sambour IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-15 2020-07-25 2020-07-23 Development 21 Commune, Kratie District, Northern Cambodia Kratie Province, CFi: Voadthonak FIA-CW039 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2021-01- (Cfi Office) in Sambour IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-17 2020-07-25 2020-07-23 Development 21 Commune, Kratie District, Northern Cambodia Kratie Province, CFi: Anlong Preah Kou FIA-CW040 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2021-01- (Cfi Office) in Sambour IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-17 2020-07-25 2020-07-23 Development 21 Commune, Kratie District, Northern Cambodia Kratie Province, CFi: Prek Krieng FIA-CW051 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2021-01- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-15 2020-07-25 2020-07-23 (Cfi Office) in Sambour Development 21 Northern Cambodia Commune, Kratie District, Kratie Province, CFi: Ta Nguon Page 5 FIA-CW053 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2021-01- (Cfi Office) in Sambour IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-15 2020-07-25 2020-07-23 Development 21 Commune, Kratie District, Northern Cambodia Kratie Province, CFi: Kampong Kboeng FIA-CW037 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2021-01- (Cfi Office) in Kaoh Khnhaer IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-15 2020-07-25 2020-07-23 Development 21 Commune, Sambour District, Northern Cambodia Kratie province, CFi: Takikhlastu FIA-CW044 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2021-01- (Cfi Office) in Boeng Char IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-15 2020-07-25 2020-07-23 Development 21 Commune, Sambour District, Northern Cambodia Kratie Province, CFi: O Krasaang FIA-CW046 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2021-01- (Cfi Office) in Bos Leav IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-15 2020-07-25 2020-07-23 Development 21 Commune , Chetr Borei Northern Cambodia district and Kratie Province, CFi: Prek Ta Am FIA-CW049 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2021-01- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-15 2020-07-20 2020-07-23 (Cfi Office) in Soab Commune, Development 16 Northern Cambodia Preaek Prasab District, Kratie Province, CFi: Saob Leu FIA-CW050 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2021-02- (Cfi Office) in Sombok IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-15 2020-08-12 2020-07-23 Development 08 Commune, Chetr Borei Northern Cambodia District, Kratie Province, CFi: Kampi FIA-CW052 / Demarcation of CFi Fishery Boundary (Poles, 1. Fisheries and Aquatic Signboard) and Infrastructure Community Driven 2021-01- IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-15 2020-07-25 2020-07-23 (Cfi Office) in Sambour Development 21 Northern Cambodia Commune, Sambour District, Kratie province, CFi: Koh Sam FIA-CW106 / Drilled 2 Wells with Afridev Pump and 3 1. Fisheries and Aquatic Community Driven 2021-01- Latrines 2 Rooms in Ou Rie IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-15 2020-07-25 2020-07-23 Development 21 commune, Thalaborivate Northern Cambodia District, Stung Teng Province FIA-CW107 / The Construction of Single 4 Pipe 1. Fisheries and Aquatic Culverts (0.6mx7m) in Community Driven 2021-01- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-07-07 2020-07-13 2020-07-12 2020-07-15 2020-07-25 2020-07-23 Thalaborivate Commune, Development 21 Northern Cambodia Thalaborivate District, Stung Teng Province FIA-CW-002RE / 1. Fisheries and Aquatic Construction of Fish Hatchery Single Stage - One 1,750,253.0 2021-10- IDA / 57770 Resources Management in Post Request for Bids Open - National 1,731,110.31 Signed 2020-07-07 2020-07-13 2020-07-12 2020-08-21 2020-08-14 2020-09-30 2020-09-30 2020-10-21 2020-10-23 in Stung Treng Province, Envelope 6 21 Northern Cambodia Cambodia FIA-CW-002 / Construction 1. Fisheries and Aquatic Single Stage - One 2021-04- of Fish Hatchery in Stung IDA / 57770 Resources Management in Post Request for Bids Open - National 1,501,073.00 0.00 Canceled 2020-03-09 2020-03-23 2020-03-14 2020-04-23 2020-04-23 2020-05-23 2020-05-22 2020-06-20 Envelope 16 Treng Province, Cambodia Northern Cambodia FIA-CW036 / Demarcation of CFi Fishery Boundary (Poles, Signboard) and Infrastructure 1. Fisheries and Aquatic Community Driven 2021-01- (Cfi Office) in Kaoh Khnhaer IDA / 57770 Resources Management in Post Direct 9,000.00 9,500.00 Signed 2020-07-07 2020-07-20 2020-07-12 2020-07-22 2020-07-25 2020-07-31 Development 21 Commune, Sambour District Northern Cambodia Kratie province, CFi:Anlong Kamnob FIA-CW108 / Natural Gravel Road (1300mx5mx0.15m) in 1. Fisheries and Aquatic Community Driven 2021-02- Kangcham Commune, IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-07-30 2020-07-30 2020-08-04 2020-07-31 2020-08-23 2020-08-06 Development 19 Thalaborivate District in Stung Northern Cambodia Treng Province FIA-CW109 / Earth Work Road (520mx4mx0.5m) and 1. Fisheries and Aquatic Community Driven 2021-02- Pipe Culvert (0.8mx6m) in Ou IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-07-30 2020-07-30 2020-08-04 2020-07-31 2020-08-19 2020-08-06 Development 15 Mreah Commune, Siem Bouk Northern Cambodia District, Stung Treng Province. FIA-CW-110 / Natural Gravel Road (300m x 6m x 0.15m) 1. Fisheries and Aquatic Community Driven 2021-02- and Double Culvert (0.8m x IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-08-10 2020-09-21 2020-08-15 2020-09-28 2020-08-30 2020-10-16 Development 26 8m) in Sdoa Commune, Sesan Northern Cambodia District, Stung Treng Province FIA-CW-111 / Natural Gravel Road (1230mx5m x 0.15m) 1. Fisheries and Aquatic and Earth Work Road (100m x Community Driven 2021-02- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-08-10 2020-09-21 2020-08-15 2020-09-28 2020-08-25 2020-10-16 5m x 0.5m) in Talat Development 21 Northern Cambodia Commune, Sesan District, Stung Treng Province FIA-CW-112 / Natural Gravel Road (1150m x 3m) and 1. Fisheries and Aquatic Single Culvert (0.8m x 13m) in Community Driven 2021-02- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-08-10 2020-09-21 2020-08-15 2020-09-28 2020-08-30 2020-10-16 Kampong Cham Commune, Development 26 Northern Cambodia Sambour District, Kratie Province. Page 6 FIA-CW-113 / Natural Gravel 1. Fisheries and Aquatic Road (1150m x 4m) in Boeng Community Driven 2021-03- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-08-10 2020-09-21 2020-08-15 2020-09-28 2020-09-08 2020-10-16 Char Commune, Sambour Development 07 Northern Cambodia District, Kratie Province. FIA-CW-114 / Natural Gravel Road (1350m x 5.5m x 1. Fisheries and Aquatic 0.15m) and Earth Worth Road Community Driven 2021-02- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-08-10 2020-09-21 2020-08-15 2020-09-28 2020-08-30 2020-10-16 (100m x 6m x 0.5m) in Kam Development 26 Northern Cambodia Phun Commune, Sesan District, Stung Treng Province. FIA-CW-115 / Natural Gravel Road (1230m x 5m x 0.15m) 1. Fisheries and Aquatic and Earth Worth Road (100m Community Driven 2021-02- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-08-10 2020-09-21 2020-08-15 2020-09-28 2020-08-30 2020-10-16 x 5m x 0.5m) in Phluk Development 26 Northern Cambodia Commune, Sesan District, Stung Treng Province. FIA-CW-116 / Natural Gravel Road (835m x 5m x 0.15m) in 1. Fisheries and Aquatic Community Driven 2021-02- Preas Romkel Commune, Borei IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-08-10 2020-09-21 2020-08-15 2020-09-28 2020-08-30 2020-10-16 Development 26 OuSvay San Chey Ddistrict, Northern Cambodia Stung Treng Province. FIA-CW-117 / 2 Single Culverts (1m x 8m) and 1 1. Fisheries and Aquatic Double Culvert (1m x 13m) in Community Driven 2021-02- IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-08-10 2020-09-21 2020-08-15 2020-09-28 2020-08-30 2020-10-16 Koah Preas Commune, Development 26 Northern Cambodia Siembouk District, Stung Treng Province. FIA-CW-118 / 2 Lines Natural Gravel Road (430m x 4m x 0.15m) and Double 1. Fisheries and Aquatic Community Driven 2021-02- Culvert (1m x 7m) in Koah IDA / 57770 Resources Management in Post Direct 15,000.00 15,000.00 Signed 2020-08-10 2020-09-21 2020-08-15 2020-09-28 2020-08-30 2020-10-16 Development 26 Sampeay Commune, Siem Northern Cambodia Bouk District, Stung Treng Province. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIA-G-001 / Supply, Delivery 1. Fisheries and Aquatic Request for Single Stage - One and Installation of Office IDA / 57770 Resources Management in Post Open - National 35,000.00 32,723.90 Completed 2017-04-12 2017-04-12 2017-06-28 2017-06-06 2017-08-09 2017-08-02 Quotations Envelope Equipment Northern Cambodia 1. Fisheries and Aquatic FIA-G-007 / Supply and Single Stage - One IDA / 57770 Resources Management in Post Request for Bids Open - National 150,000.00 136,500.00 Signed 2017-04-20 2017-04-06 2017-04-25 2017-04-12 2017-06-06 2017-05-17 2017-07-06 2017-05-26 2017-08-10 2017-06-13 2017-10-05 Delivery of 5 Pick Up Trucks Envelope Northern Cambodia 1. Fisheries and Aquatic FIA-G-009 / Office Furniture Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 8,000.00 0.00 Canceled 2017-04-24 2017-07-10 2017-09-04 for FiA Quotations Envelope Northern Cambodia FIA-G-004 / Supply and 1. Fisheries and Aquatic Delivery of 12 Motorcycles for Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 24,000.00 0.00 Canceled 2017-04-25 2017-07-04 2017-08-29 FiA/IFReDI and PFiA Quotations Envelope Northern Cambodia Kratie/Stung Treng FIA-G-010 / Supply and 1. Fisheries and Aquatic Installation of 6 Licensed Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 9,000.00 0.00 Canceled 2017-05-24 2017-08-09 2017-10-08 Accounting Software with 6 Quotations Envelope Northern Cambodia Desktop Computers FIA-G-004RE / Supply and 1. Fisheries and Aquatic Delivery of 12 Motorcycles for Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 24,000.00 16,560.00 Completed 2017-06-17 2017-08-26 2017-07-13 2017-09-23 2017-08-09 FiA/IFReDI and PFiA Quotations Envelope Northern Cambodia Kratie/Stung Treng FIA-G-009RE / Supply and 1. Fisheries and Aquatic Request for Single Stage - One Delivery of Office Furniture for IDA / 57770 Resources Management in Post Open - National 8,000.00 7,949.70 Completed 2017-06-17 2017-08-26 2017-07-19 2017-10-07 2017-09-15 Quotations Envelope FiA Northern Cambodia FIA-G-010RE / Supply and 1. Fisheries and Aquatic Request for Single Stage - One Installation of Licensed IDA / 57770 Resources Management in Post Open - National 9,000.00 4,600.00 Completed 2017-06-17 2017-08-26 2017-07-13 2017-10-07 2017-09-01 Quotations Envelope Accounting Software Northern Cambodia 1. Fisheries and Aquatic FIA-G-002 / Office Furniture Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 10,000.00 9,820.00 Completed 2018-01-20 2018-03-17 2018-05-11 2018-04-30 2018-06-11 for PFiA, Kratie/Stung Treng Quotations Envelope Northern Cambodia FIA-G-011 / Printing and 1. Fisheries and Aquatic Delivery of Training Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 10,500.00 11,322.30 Completed 2018-09-19 2018-11-14 2019-01-21 2018-12-28 2019-03-04 Documents of Cfi Co- Quotations Envelope Northern Cambodia Management 1. Fisheries and Aquatic FIA-G-015 / Supply and UN Agencies IDA / 57770 Resources Management in Post Direct 30,000.00 39,670.50 Completed 2019-03-01 2019-04-02 2019-03-08 2019-04-02 2019-04-12 2019-08-14 2019-08-10 2020-03-27 Delivery of One (1) Vehicle (Direct) Northern Cambodia FIA-G-008 / Supply, Delivery 1. Fisheries and Aquatic Request for Single Stage - One and Installation of Mapping IDA / 57770 Resources Management in Post Open - National 8,000.00 7,549.30 Completed 2019-04-03 2019-05-17 2019-05-07 2019-06-14 2019-06-28 Quotations Envelope Equipment Northern Cambodia FIA-G-014 / Supply and 1. Fisheries and Aquatic Delivery of 6 Motorcycles for Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 10,500.00 10,662.00 Completed 2019-04-03 2019-05-17 2019-05-07 2019-06-14 2019-05-24 FiA/IFReDI and PFiA Quotations Envelope Northern Cambodia Kratie/Stung Treng FIA-G-018 / Supply, Delivery 1. Fisheries and Aquatic and Installation of Boats with Single Stage - One IDA / 57770 Resources Management in Post Request for Bids Open - National 175,000.00 132,200.00 Completed 2019-04-12 2019-04-22 2019-04-19 2019-05-29 2019-05-24 2019-06-19 2019-06-14 2019-07-10 2019-06-27 2019-10-02 2019-08-30 Engines for 50 Community Envelope Northern Cambodia Fisheries Page 7 FIA-G-013 / Supply, Delivery 1. Fisheries and Aquatic and Installation of Laptops Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 10,000.00 9,827.40 Completed 2019-04-17 2019-06-07 2019-05-28 2019-07-05 2019-06-12 and Quotations Envelope Northern Cambodia Color Laser Printers FIA-G-012 / Supply and 1. Fisheries and Aquatic Request for Single Stage - One Delivery of Fisheries IDA / 57770 Resources Management in Post Open - National 15,000.00 14,557.76 Completed 2019-07-06 2019-08-26 2019-08-08 2019-10-07 2019-08-16 Quotations Envelope Monitoring Equipment Northern Cambodia FIA-G-017 / Supply and 1. Fisheries and Aquatic Request for Single Stage - One Delivery of Equipment for IDA / 57770 Resources Management in Post Open - National 9,500.00 7,889.20 Completed 2019-06-04 2019-07-16 2019-07-16 2019-09-10 2019-08-19 Quotations Envelope Engineering Works Northern Cambodia FIA-G-019 / Supply and 1. Fisheries and Aquatic Request for Single Stage - One Delivery of Monitoring IDA / 57770 Resources Management in Post Open - National 50,000.00 47,421.00 Completed 2020-02-08 2020-03-28 2020-03-27 2020-05-09 2020-06-08 Quotations Envelope Equipment and Kits for 50 Northern Cambodia Cfis FIA-G-003 / Supply, Delivery 1. Fisheries and Aquatic and Installation of 2 Boats Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 50,000.00 59,200.00 Completed 2020-02-22 2020-04-16 2020-03-27 2020-04-22 2020-05-08 with Engines for PFiA-Kratie Quotations Envelope Northern Cambodia and PFiA-Stung Treng FIA-G-021 / Supply and 1. Fisheries and Aquatic Delivery of Office Furniture for Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 14,000.00 15,213.00 Completed 2020-05-15 2020-07-10 2020-06-19 2020-08-21 2020-07-24 New Office Buildings in Kratie Quotations Envelope Northern Cambodia and Stung Treng 1. Fisheries and Aquatic FIA-G-023 / Supply and Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 5,000.00 5,445.00 Completed 2020-07-06 2020-08-18 2020-08-05 2020-09-29 2020-09-04 Delivery of Server for FiA Quotations Envelope Northern Cambodia FIA-G-025 / Supply and 1. Fisheries and Aquatic Under Request for Single Stage - One Installation of Video IDA / 57770 Resources Management in Post Open - National 85,000.00 0.00 Implementati 2021-04-01 2021-05-10 2021-05-31 Quotations Envelope Conference Equipment Northern Cambodia on FIA-G-024 / Supply and 1. Fisheries and Aquatic Pending Request for Single Stage - One Delivery of Broodstock for IDA / 57770 Resources Management in Post Open - National 24,000.00 0.00 Implementati 2021-04-23 2021-05-31 2021-12-13 Quotations Envelope Fish Hatchery Northern Cambodia on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIA-CS-024 / Engineering Design and Construction 1. Fisheries and Aquatic Consultant Supervision for a fish hatchery IDA / 57770 Resources Management in Post Qualification Open - National 75,000.00 82,128.00 Signed 2018-04-02 2018-04-12 2018-04-19 2018-06-18 2018-12-24 2018-07-18 2019-03-26 2018-08-18 2019-04-04 2019-02-18 in Stung Treng Province, Northern Cambodia Selection Cambodia INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIA-CS-008 / International 1. Fisheries and Aquatic Individual Fishery Resource Management IDA / 57770 Resources Management in Post Consultant Open 200,000.00 224,327.44 Signed 2016-11-01 2016-12-22 2017-02-09 2017-03-23 2017-03-02 2017-03-30 2017-04-06 2017-04-12 2021-04-05 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-009 / International IDA / 57770 Resources Management in Post Consultant Open 200,000.00 198,746.05 Signed 2016-11-01 2016-12-22 2017-02-09 2017-03-23 2017-03-02 2017-03-30 2017-04-06 2017-04-12 2021-04-05 Community Fishery Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-010 / National IDA / 57770 Resources Management in Post Consultant Open 108,000.00 127,468.24 Signed 2016-11-01 2016-12-22 2017-02-09 2017-03-23 2017-03-02 2017-03-30 2017-04-06 2017-04-12 2021-04-05 Component Coordinator Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-014 / National IDA / 57770 Resources Management in Post Consultant Open 30,000.00 58,458.82 Signed 2016-11-01 2016-12-22 2017-02-09 2017-03-23 2017-03-02 2017-03-30 2017-04-06 2017-04-12 2021-04-05 Gender Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-013 / National Lead IDA / 57770 Resources Management in Post Consultant Open 90,000.00 107,985.88 Terminated 2016-11-01 2016-12-22 2017-02-09 2017-03-23 2017-03-02 2017-03-30 2017-04-06 2017-04-12 2021-04-05 Community Fishery Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-001 / National IDA / 57770 Resources Management in Post Consultant Open 90,000.00 141,176.00 Terminated 2016-07-01 2016-08-25 2016-11-08 2017-01-06 2016-11-29 2017-01-09 2017-01-03 2017-02-01 2021-01-02 Procurement Consultant Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-002 / National IDA / 57770 Resources Management in Post Consultant Open 90,000.00 110,552.94 Signed 2016-07-01 2016-08-25 2016-11-08 2017-01-06 2016-11-29 2017-01-10 2017-01-03 2017-02-01 2021-01-02 Financial Consultant Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-003 / National IDA / 57770 Resources Management in Post Consultant Open 60,000.00 65,094.12 Terminated 2016-07-01 2016-08-25 2016-11-08 2017-01-06 2016-11-29 2017-01-09 2017-01-03 2017-02-06 2021-01-02 Project Accountant Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-025 / Regional IDA / 57770 Resources Management in Post Consultant Open 50,000.00 0.00 Canceled 2016-11-01 2017-02-23 2017-02-09 2017-03-02 2017-04-06 2021-04-05 Aquaculture Specialist (RAS) Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-012 / National Lead IDA / 57770 Resources Management in Post Consultant Open 90,000.00 0.00 Canceled 2016-11-01 2016-12-22 2017-02-09 2017-03-23 2017-03-02 2017-03-30 2017-04-06 2021-04-05 Fishery Resource Specialist Northern Cambodia Selection Page 8 FIA-CS-015 / National 1. Fisheries and Aquatic Individual Environmental Safeguards IDA / 57770 Resources Management in Post Consultant Open 15,000.00 34,432.95 Signed 2017-06-01 2017-05-31 2017-08-17 2017-11-28 2017-08-31 2017-12-20 2017-09-28 2018-01-12 2021-09-27 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-027 / National Social IDA / 57770 Resources Management in Post Consultant Open 15,000.00 23,169.00 Terminated 2017-06-01 2017-05-31 2017-08-17 2017-08-30 2017-08-31 2017-09-06 2017-09-28 2017-12-27 2021-09-27 Safeguards Specialist Northern Cambodia Selection FIA-CS-006 / National 1. Fisheries and Aquatic Individual Finance Consultant at PFiA IDA / 57770 Resources Management in Post Consultant Open 60,000.00 60,223.52 Terminated 2017-06-09 2017-05-31 2017-08-25 2017-08-30 2017-09-08 2017-09-06 2017-10-06 2017-10-12 2021-10-05 Kratie Northern Cambodia Selection FIA-CS-007 / National 1. Fisheries and Aquatic Individual Finance Consultant at PFiA IDA / 57770 Resources Management in Post Consultant Open 60,000.00 60,223.52 Terminated 2017-06-09 2017-05-31 2017-08-25 2017-08-30 2017-09-08 2017-09-06 2017-10-06 2017-10-12 2021-10-05 Stung Treng Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-017 / Kratie National IDA / 57770 Resources Management in Post Consultant Open 60,000.00 0.00 Canceled 2017-08-01 2017-07-25 2017-10-17 2018-01-08 2017-11-07 2017-12-05 2021-12-04 Community Fishery Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-018 / Kratie National IDA / 57770 Resources Management in Post Consultant Open 60,000.00 81,871.00 Terminated 2017-08-01 2017-07-25 2017-10-17 2017-11-28 2017-11-07 2017-12-20 2017-12-05 2018-01-12 2021-12-04 Livelihood Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-019 / Kratie National IDA / 57770 Resources Management in Post Consultant Open 60,000.00 68,341.00 Signed 2017-08-01 2017-07-25 2017-10-17 2018-01-08 2017-11-07 2018-01-22 2017-12-05 2018-01-29 2021-12-04 Community Facilitator Northern Cambodia Selection FIA-CS-021 / Stung Treng 1. Fisheries and Aquatic Individual National Community Fishery IDA / 57770 Resources Management in Post Consultant Open 60,000.00 58,871.00 Signed 2017-08-01 2017-07-25 2017-10-17 2017-11-28 2017-11-07 2017-12-20 2017-12-05 2018-01-12 2021-12-04 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-022 / Stung Treng IDA / 57770 Resources Management in Post Consultant Open 60,000.00 72,738.00 Signed 2017-08-01 2017-07-25 2017-10-17 2017-11-28 2017-11-07 2017-12-20 2017-12-05 2018-01-12 2021-12-04 National Livelihood Specialist Northern Cambodia Selection FIA-CS-023 / Stung Treng 1. Fisheries and Aquatic Individual National Community IDA / 57770 Resources Management in Post Consultant Open 60,000.00 74,125.00 Terminated 2017-08-01 2017-07-25 2017-10-17 2017-11-28 2017-11-07 2017-12-20 2017-12-05 2018-01-12 2021-12-04 Facilitator Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-028 / National M&E IDA / 57770 Resources Management in Post Consultant Open 90,000.00 131,662.00 Signed 2017-08-01 2017-07-25 2017-10-17 2017-11-28 2017-11-07 2017-12-20 2017-12-05 2018-01-12 2021-12-04 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-025RE / International IDA / 57770 Resources Management in Post Consultant Open 152,000.00 147,819.00 Signed 2017-08-01 2017-07-25 2017-10-17 2018-01-08 2017-11-07 2018-01-18 2017-12-05 2018-02-19 2021-12-04 Aquaculture Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-001RE / National IDA / 57770 Resources Management in Post Consultant Open 36,000.00 40,949.81 Terminated 2017-08-10 2017-08-08 2017-10-26 2017-10-05 2017-11-09 2017-10-16 2017-12-07 2017-10-19 2019-12-07 Procurement Consultant Northern Cambodia Selection FIA-CS-012RE / National 1. Fisheries and Aquatic Individual Lead Fisheries Resources IDA / 57770 Resources Management in Post Consultant Open 90,000.00 0.00 Canceled 2017-05-19 2017-05-31 2017-08-04 2017-08-18 2017-09-15 2021-09-14 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-016 / Kratie National IDA / 57770 Resources Management in Post Consultant Open 60,000.00 0.00 Canceled 2017-08-01 2017-07-25 2017-10-17 2017-11-07 2017-12-05 2021-12-04 Fishery Resource Specialist Northern Cambodia Selection FIA-CS-020 / Stung Treng 1. Fisheries and Aquatic Individual National Fishery Resource IDA / 57770 Resources Management in Post Consultant Open 60,000.00 0.00 Canceled 2017-08-01 2017-07-25 2017-10-17 2017-11-07 2017-12-05 2021-12-04 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-030 / Sampling IDA / 57770 Resources Management in Post Consultant Open 2,800.00 0.00 Canceled 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2017-12-13 Framework Design Specialist Northern Cambodia Selection FIA-CS-026 / National 1. Fisheries and Aquatic Individual Infrastructure Engineer IDA / 57770 Resources Management in Post Consultant Open 20,000.00 81,139.28 Signed 2018-01-15 2018-01-15 2018-03-05 2018-03-09 2018-03-26 2018-03-16 2018-04-30 2018-04-02 2021-04-30 Consultant Northern Cambodia Selection FIA-CS-032 / National 1. Fisheries and Aquatic Individual Community Development IDA / 57770 Resources Management in Post Consultant Open 8,000.00 14,706.00 Signed 2018-01-15 2018-01-17 2018-03-05 2018-03-20 2018-03-26 2018-03-22 2018-04-30 2018-03-23 2018-08-31 Training Specialist Northern Cambodia Selection FIA-CS-033 / National 1. Fisheries and Aquatic Individual Specialist on Geographic IDA / 57770 Resources Management in Post Consultant Open 76,000.00 195,664.00 Signed 2018-01-15 2018-01-17 2018-03-05 2018-03-09 2018-03-26 2018-03-16 2018-04-30 2018-04-02 2021-04-30 Information System and Northern Cambodia Selection Database Management FIA-CS-012RE2 / National 1. Fisheries and Aquatic Individual Lead Fishery Resource IDA / 57770 Resources Management in Post Consultant Open 90,000.00 234,040.00 Signed 2018-01-15 2018-01-15 2018-03-05 2018-03-09 2018-03-26 2018-03-16 2018-04-30 2018-04-02 2021-04-30 Specialist Northern Cambodia Selection FIA-CS-016RE / Kratie 1. Fisheries and Aquatic Individual National Fishery Resource IDA / 57770 Resources Management in Post Consultant Open 60,000.00 0.00 Canceled 2018-01-15 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-30 Specialist Northern Cambodia Selection FIA-CS-020RE / Stung Streng 1. Fisheries and Aquatic Individual National Fishery Resource IDA / 57770 Resources Management in Post Consultant Open 60,000.00 0.00 Canceled 2018-01-15 2018-01-15 2018-03-05 2018-03-09 2018-03-26 2018-04-30 2021-04-30 Specialist Northern Cambodia Selection FIA-CS-029 / Provincial 1. Fisheries and Aquatic Individual Project Engineer Consultant IDA / 57770 Resources Management in Post Consultant Open 54,000.00 55,488.00 Terminated 2018-01-26 2018-01-23 2018-03-16 2018-06-19 2018-04-06 2018-06-28 2018-05-11 2018-07-05 2021-05-11 for Kratie Northern Cambodia Selection FIA-CS-035 / Provincial 1. Fisheries and Aquatic Individual Project Engineer Consultant IDA / 57770 Resources Management in Post Consultant Open 54,000.00 59,336.00 Terminated 2018-01-26 2018-01-23 2018-03-16 2018-03-20 2018-04-06 2018-03-27 2018-05-11 2018-04-10 2021-05-11 for Stung Treng Northern Cambodia Selection FIA-CS-017RE / Kratie 1. Fisheries and Aquatic Individual National Community Fisheries IDA / 57770 Resources Management in Post Consultant Open 60,000.00 74,480.00 Terminated 2018-02-12 2018-04-02 2018-04-02 2018-06-19 2018-04-23 2018-07-16 2018-05-28 2018-07-23 2021-06-01 Specialist Northern Cambodia Selection Page 9 1. Fisheries and Aquatic Individual FIA-CS-034 / National IDA / 57770 Resources Management in Post Consultant Open 30,000.00 27,191.00 Signed 2018-04-02 2018-04-02 2018-05-21 2018-06-19 2018-06-11 2018-07-07 2018-07-16 2018-07-13 2021-06-01 Internal Audit Consultant Northern Cambodia Selection FIA-CS-020RE2 / Stung 1. Fisheries and Aquatic Individual Streng National Fishery IDA / 57770 Resources Management in Post Consultant Open 60,000.00 64,005.00 Signed 2018-04-30 2018-04-27 2018-06-18 2018-06-19 2018-07-09 2018-06-28 2018-08-13 2018-07-09 2021-06-01 Resource Specialist Northern Cambodia Selection FIA-CS-016RE2 / Kratie 1. Fisheries and Aquatic Individual National Fishery Resource IDA / 57770 Resources Management in Post Consultant Open 60,000.00 53,550.00 Signed 2018-04-30 2018-04-27 2018-06-18 2018-06-19 2018-07-09 2018-07-16 2018-08-13 2018-07-27 2021-06-01 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-027RE / National IDA / 57770 Resources Management in Post Consultant Open 15,000.00 24,628.24 Signed 2018-07-03 2018-08-01 2018-08-21 2018-11-15 2018-09-11 2018-11-20 2018-10-16 2018-12-24 2019-04-14 Social Safeguards Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-001RE1 / National IDA / 57770 Resources Management in Post Consultant Open 36,000.00 90,335.82 Signed 2018-07-03 2018-08-01 2018-08-21 2018-11-15 2018-09-11 2018-11-20 2018-10-16 2018-12-12 2019-04-14 Procurement Consultant Northern Cambodia Selection FIA-CS-013RE / National 1. Fisheries and Aquatic Individual Lead Community Fisheries IDA / 57770 Resources Management in Post Consultant Open 62,000.00 58,427.50 Signed 2018-08-01 2018-09-25 2018-09-19 2018-11-15 2018-10-10 2018-11-20 2018-11-14 2018-12-17 2021-05-13 Specialist Northern Cambodia Selection FIA-CS-023RE / Stung Treng 1. Fisheries and Aquatic Individual National Community IDA / 57770 Resources Management in Post Consultant Open 45,000.00 56,367.64 Signed 2018-10-01 2018-09-25 2018-11-17 2018-11-15 2018-11-24 2018-11-20 2018-12-03 2018-12-19 2021-05-13 Facilitator Northern Cambodia Selection FIA-CS-006RE / National 1. Fisheries and Aquatic Individual Finance Consultant at PFiA IDA / 57770 Resources Management in Post Consultant Open 29,000.00 35,180.00 Terminated 2018-12-10 2018-12-27 2019-01-28 2019-02-04 2019-03-07 2019-02-11 2019-03-13 2021-06-30 Kratie Northern Cambodia Selection FIA-CS-035RE / Provincial 1. Fisheries and Aquatic Individual Project Engineer Consultant IDA / 57770 Resources Management in Post Consultant Open 40,000.00 52,462.35 Terminated 2019-01-12 2019-01-17 2019-03-02 2019-03-09 2019-03-06 2019-03-16 2019-03-11 2021-07-03 for Stung Treng Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-003RE / Project IDA / 57770 Resources Management in Post Consultant Open 32,500.00 39,603.53 Terminated 2019-01-28 2019-01-28 2019-03-18 2019-03-25 2019-03-25 2019-04-01 2019-04-04 2021-05-20 Accountant Consultant (PAC) Northern Cambodia Selection FIA-CS029RE / Provincial 1. Fisheries and Aquatic Individual Project Engineer Consultant IDA / 57770 Resources Management in Post Consultant Open 30,000.00 32,941.18 Signed 2019-07-01 2019-07-02 2019-08-12 2019-08-27 2019-08-17 2019-08-30 2019-08-24 2019-09-06 2021-05-15 for Kratie Northern Cambodia Selection FIA-CS017RE1 / Kratie 1. Fisheries and Aquatic Individual National Community Fisheries IDA / 57770 Resources Management in Post Consultant Open 35,000.00 36,452.94 Signed 2019-08-01 2019-08-05 2019-09-19 2019-10-28 2019-10-10 2019-10-30 2019-11-14 2019-11-27 2020-05-12 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-003RE1 / Project IDA / 57770 Resources Management in Post Consultant Open 22,100.00 21,573.34 Signed 2019-10-23 2019-10-23 2019-12-13 2020-01-06 2019-12-20 2020-02-06 2020-01-01 2020-02-10 2021-05-25 Accountant Consultant Northern Cambodia Selection FIA-CS-006RE1 / National 1. Fisheries and Aquatic Individual Finance Consultant at PFiA- IDA / 57770 Resources Management in Post Consultant Open 20,400.00 0.00 Canceled 2019-10-23 2019-10-23 2019-12-13 2020-01-02 2019-12-20 2020-01-13 2020-01-01 2021-05-25 Kratie Northern Cambodia Selection FIA-CS-020RE3 / Stung 1. Fisheries and Aquatic Individual Treng National Fisheries IDA / 57770 Resources Management in Post Consultant Open 16,100.00 20,200.00 Signed 2020-01-01 2020-01-17 2020-02-26 2020-03-10 2020-03-04 2020-03-17 2020-03-25 2020-03-27 2021-05-19 Resources Specialist Northern Cambodia Selection FIA-CS-007RE / National 1. Fisheries and Aquatic Individual Finance Consultant at PFiA- IDA / 57770 Resources Management in Post Consultant Open 18,200.00 21,800.00 Signed 2020-01-21 2020-02-01 2020-03-17 2020-04-13 2020-03-24 2020-04-20 2020-04-07 2020-04-24 2021-06-01 Stung Treng Northern Cambodia Selection FIA-CS-006RE2 / National 1. Fisheries and Aquatic Individual Finance Consultant at PFiA- IDA / 57770 Resources Management in Post Consultant Open 18,200.00 18,280.46 Signed 2020-01-21 2020-02-01 2020-03-19 2020-04-13 2020-04-02 2020-04-20 2020-04-16 2020-04-28 2021-06-10 Kratie Northern Cambodia Selection FIA-CS-035RE1 / Provincial 1. Fisheries and Aquatic Individual Project Engineer Consultant IDA / 57770 Resources Management in Post Consultant Open 19,600.00 0.00 Canceled 2020-02-01 2020-03-21 2020-03-28 2020-04-04 2021-05-29 for Stung Treng Northern Cambodia Selection Page 10