Procurement Plan I. General 1. Project information: • Country: Mozambique • Borrower: Government of Mozambique • Project Name: Mining and Gas Technical Assistance Project (MAGTAP) • Loan/Credit No.: 5199-MZ - Project ID P129847 • Project Implementing Agency: Ministry of Mineral Resources and Energy (Project Management Unit- PMU) 2. Bank’s approval Date of the procurement Plan: November, 2013 2. Date of General Procurement Notice: 30 of September, 2013 3. Date of Procurement Plan Updated: 12 of April of 2017 4. Period covered by this procurement plan: 18 months from January 2017 – June 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior Review Threshold Procurement Method Comments (US$) 1. ICB and LIB (Goods) ≥ USD 3,000,000 All NCB (Goods and Non- First two contracts will be subject to 2. < USD 3,000,000 consultant Services) prior review by the bank First two contracts will be subject to 3 Shopping (Goods) < USD 50,000 prior review by the bank 3. ICB (Works) N/A N/A First two contracts will be subject to 4. NCB (Works) < USD 15,000,000 prior review by the bank First two contracts will be subject to 5. Shoping (Works) < USD 50,000 prior review by the bank 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: A Project Implementation Manual covering both Financial Operations and Procurement and other procedures has been presented by MIREME and approved by the WB as per the requirements for project effectiveness. 4. Any Other Special Procurement Arrangements: N/A 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness : 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 0.00 0 No Prior the ICB (Works) Summary of 0.00 0 No Prior the ICB (Goods) Summary of 0.3 1 No Post the NCB (Works) Summary of 1.38 3 No Post the NCB (Goods) Summary of 0.00 0 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Threshold Procurement Method Comments (US$) 1. Competitive Method (Firms) >1,000,000 Single Source (Firms & 2. ALL Individual Consultant) 3 Individual Consultant >200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 13.26 19 Prior/Post 3 contracts number of under prior contracts that review will be let under QCBS Summary of 2.23 17 Post CQS/IND/ number of SSS contracts that will be let under other methods PROCUREMENT Mozambique : Mozambique Mining and Gas Technical Assistance Project PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2017-02-10 2019-08-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P129847 GPN Date: Project Name: Mozambique Mining and Gas Technical Assistance Project Loan / Credit No: IDA / 51990, TF / 16113, IDA / D2390 Executing Agency(ies): Ministry of Mineral Resources WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component C: Cross-cutting W2/C43 / Transformation of Mining/ Natural Gas Request for Single Stage - One DNGM Laboratory to IDA / 51990 Post Limited 45,000.00 0.00 Canceled 2017-03-11 2017-05-06 2017-11-02 Capacity Building and Quotations Envelope Archive/Library Reforms Component C: Cross-cutting W1/C43 / Rehabilitation of Mining/ Natural Gas Single Stage - One IDA / 51990 Post Request for Bids Open - National 300,000.00 1,008,408.03 Signed 2017-02-06 2017-02-11 2017-03-25 2017-04-24 2017-05-29 2017-05-31 DNGM Building Capacity Building and Envelope Reforms Component C: Cross-cutting W2-C4A / Transformation of Mining/ Natural Gas Single Stage - One DNGM Laboratory to IDA / 51990 Post Request for Bids Open - National 55,000.00 56,384.29 Signed 2018-05-10 2018-05-15 2018-06-26 2018-07-26 2018-08-30 2018-10-29 Capacity Building and Envelope Archive/Library Reforms Component C: Cross-cutting W3/C7 / Rehabilitation of Mining/ Natural Gas Single Stage - One IDA / 51990 Post Request for Bids Open - National 100,000.00 54,503.13 Signed 2018-09-28 2018-10-03 2018-11-14 2018-12-14 2019-01-18 2019-04-18 new ITIE office Capacity Building and Envelope Reforms W4/A5 / Rehabilitation of Component A: Mining Pending Single Stage - One MIS workspace and server IDA / 51990 Governance Capacity Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-06-30 2019-07-05 2019-08-16 2019-09-15 2019-10-20 2020-04-17 Envelope room Building and Reform on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Mining G4/A56 / Coreshed & Single Stage - One IDA / 51990 Governance Capacity Post Request for Bids Open - National 800,000.00 137,383.14 Signed 2017-02-09 2017-02-14 2017-03-28 2017-04-27 2017-06-01 2017-08-30 related equipment Envelope Building and Reform Component C: Cross-cutting G31/V / Furniture for Mining/ Natural Gas Single Stage - One IDA / 51990 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2017-03-06 2017-03-11 2017-04-22 2017-05-22 2017-06-26 2017-08-25 IGREME and MIREME Capacity Building and Envelope Reforms Component C: Cross-cutting G35/C43 / Promotional Mining/ Natural Gas Request for Single Stage - One material for Geology IDA / 51990 Post Limited 20,000.00 3,315.31 Signed 2017-02-13 2017-04-10 2017-04-13 Capacity Building and Quotations Envelope Museum Reforms Page 1 Component C: Cross-cutting G37-V / IT Equipment for Mining/ Natural Gas Request for Single Stage - One IDA / 51990 Post Limited 20,000.00 36,136.24 Signed 2017-04-23 2017-06-18 2017-06-21 MIREME Capacity Building and Quotations Envelope Reforms Component A: Mining Under G38/A5 / Coreshed & Single Stage - One IDA / 51990 Governance Capacity Post Request for Bids Open - National 250,000.00 0.00 Implementati 2017-11-15 2017-11-20 2018-01-01 2018-01-31 2018-03-07 2018-06-05 related equipment - Part 2 Envelope Building and Reform on Component A: Mining Under G39/A5 / Geodata Field Single Stage - One IDA / 51990 Governance Capacity Post Request for Bids Open - National 400,000.00 0.00 Implementati 2017-11-14 2017-11-19 2017-12-31 2018-01-30 2018-03-06 2018-06-04 Equipment - First package Envelope Building and Reform on Component C: Cross-cutting Pending G202-C4 / IT infrastructure Mining/ Natural Gas Single Stage - One IDA / D2390 Post Request for Bids Open - National 700,000.00 0.00 Implementati 2018-11-12 2018-11-17 2018-12-17 2019-01-16 2019-02-20 2019-05-21 for MIREME Capacity Building and Envelope on Reforms Component B: Natural Gas G204-B3 / Software Skill IDA / D2390 Capacity Building and Post Direct Selection Direct 120,000.00 106,875.00 Signed 2018-05-09 2018-05-14 2018-06-18 2018-07-18 Based (Competency Model) Governance Reform G205-A4 / Specialised Component A: Mining Under Single Stage - One Equipment for Mineral IDA / 51990 Governance Capacity Post Request for Bids Open - National 120,000.00 0.00 Implementati 2018-05-21 2018-05-26 2018-07-07 2018-08-06 2018-09-10 2018-12-09 Envelope Information System (MIS) Building and Reform on Component C: Cross-cutting Under G203-C4 / Vehicles for Mining/ Natural Gas Single Stage - One IDA / D2390 Post Request for Bids Open - National 150,000.00 0.00 Implementati 2018-04-30 2018-05-05 2018-06-04 2018-07-04 2018-08-08 2018-11-06 MIREME Capacity Building and Envelope on Reforms Component C: Cross-cutting Under G200-C4 / IT Equipment Mining/ Natural Gas Single Stage - One IDA / D2390 Post Request for Bids Open - National 200,000.00 0.00 Implementati 2018-05-10 2018-05-15 2018-06-14 2018-07-14 2018-08-18 2018-09-17 for MIREME Capacity Building and Envelope on Reforms G8-C23 / Equipment to general inspectorate Component A: Mining Under Single Stage - One (provincial offices) and IDA / 51990 Governance Capacity Post Request for Bids Open - National 375,000.00 0.00 Implementati 2018-05-15 2018-05-20 2018-07-01 2018-07-31 2018-09-04 2018-12-03 Envelope Camping Equipment and Building and Reform on Material for DNGM Component C: Cross-cutting Pending G33/C43 / Archive Software Mining/ Natural Gas Request for Single Stage - One IDA / 51990 Post Limited 8,000.00 0.00 Implementati 2018-09-04 2018-10-30 2019-01-28 for MIREME Capacity Building and Quotations Envelope on Reforms Component C: Cross-cutting G201- C4 / Furniture for Mining/ Natural Gas Request for Single Stage - One IDA / D2390 Post Limited 45,000.00 0.00 Canceled 2018-04-30 2018-06-25 2018-07-25 MIREME Capacity Building and Quotations Envelope Reforms Component A: Mining Pending G206/A5 / Mapping Request for Single Stage - One IDA / 51990 Governance Capacity Post Limited 20,000.00 0.00 Implementati 2018-09-22 2018-11-17 2019-02-15 Equipment - Trailers Quotations Envelope Building and Reform on G207/A5 / Mapping Component A: Mining Pending Equipment - Spare Parts IDA / 51990 Governance Capacity Post Direct Selection Direct 30,000.00 0.00 Implementati 2018-11-01 2018-11-06 2018-12-11 2019-02-09 and Accessories Building and Reform on G208/A5 / Mapping Component A: Mining Equipment - Quad Bikes IDA / 51990 Governance Capacity Post Direct Selection Direct 6,000.00 5,313.53 Signed 2018-11-01 2018-11-06 2018-12-11 2019-02-09 Tyres Building and Reform G209/A5 / Mapping Component A: Mining Pending Request for Single Stage - One Equipment - Vehicles IDA / 51990 Governance Capacity Post Limited 7,500.00 0.00 Implementati 2018-09-29 2018-11-24 2019-02-22 Quotations Envelope Generic Accessories Building and Reform on Page 2 G210/A5 / Mapping Component A: Mining Under Single Stage - One Equipment - Camping IDA / 51990 Governance Capacity Post Request for Bids Open - National 150,000.00 0.00 Implementati 2018-09-10 2018-09-15 2018-10-27 2018-11-26 2018-12-31 2019-03-31 Envelope Equipment and hardware Building and Reform on Component A: Mining Under Single Stage - One G211/AC / Motorbikes IDA / 51990 Governance Capacity Post Request for Bids Open - National 160,000.00 0.00 Implementati 2018-09-26 2018-10-01 2018-11-12 2018-12-12 2019-01-16 2019-04-16 Envelope Building and Reform on Component C: Cross-cutting Under G212 / Furniture for Mining/ Natural Gas Single Stage - One IDA / 51990 Post Request for Bids Open - National 245,000.00 0.00 Implementati 2018-09-12 2018-09-17 2018-10-29 2018-11-28 2019-01-02 2019-07-01 MIREME Capacity Building and Envelope on Reforms Component A: Mining Under G214/A5 / Equipment for Single Stage - One IDA / 51990 Governance Capacity Post Request for Bids Open - National 150,000.00 0.00 Implementati 2018-10-10 2018-10-15 2018-11-26 2018-12-26 2019-01-30 2019-07-29 Seismic Stations Envelope Building and Reform on Component C: Cross-cutting G215 / Field Vehicle for Mining/ Natural Gas Request for Single Stage - One IDA / D2390 Post Limited 75,000.00 122,709.13 Signed 2018-11-19 2019-01-14 2019-04-14 MIREME Capacity Building and Quotations Envelope Reforms Component A: Mining Pending G217/A5 / IT equipment for Request for Single Stage - One IDA / 51990 Governance Capacity Post Limited 45,000.00 0.00 Implementati 2019-07-30 2019-09-24 2019-12-23 Coreshed Quotations Envelope Building and Reform on Component A: Mining Pending G218/A5 / Software for Single Stage - One IDA / 51990 Governance Capacity Post Request for Bids Open - National 70,000.00 0.00 Implementati 2019-08-20 2019-08-25 2019-10-06 2019-11-05 2019-12-10 2020-06-07 Coreshed Envelope Building and Reform on Component A: Mining Pending G219/A5 / Equipment for Single Stage - One IDA / 51990 Governance Capacity Post Request for Bids Open - National 300,000.00 0.00 Implementati 2019-11-26 2019-12-01 2020-01-12 2020-02-11 2020-03-17 2020-09-13 Geoscience Laboratory Envelope Building and Reform on Component C: Cross-cutting Pending G219/C4 / Furniture for Mining/ Natural Gas Request for Single Stage - One IDA / 51990 Post Limited 30,000.00 0.00 Implementati 2019-07-05 2019-08-30 2019-10-29 MIREME Capacity Building and Quotations Envelope on Reforms Component C: Cross-cutting Pending G220/C4 / Air Conditioners Mining/ Natural Gas Request for Single Stage - One IDA / 51990 Post Limited 20,000.00 0.00 Implementati 2019-06-28 2019-08-23 2019-08-26 for MIREME Capacity Building and Quotations Envelope on Reforms NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NC201- A5 / Airborne Component A: Mining Under Open - Single Stage - One geophysical survey Blok 8 IDA / D2390 Governance Capacity Post Request for Bids 1,700,000.00 0.00 Implementati 2018-04-30 2018-05-05 2018-06-04 2018-07-04 2018-08-08 2019-08-08 International Envelope and 8A Building and Reform on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component C: Cross-cutting C37/C1 / Update of Mining/ Natural Gas Quality And Cost- Open - Under Environmental Regulations TF / 16113 Post 200,000.00 0.00 2017-02-10 2017-03-03 2017-04-16 2017-05-14 2017-06-13 2017-07-18 2017-08-22 2017-08-23 Capacity Building and Based Selection International Implementation applicable to Mining Sector Reforms Page 3 Component C: Cross-cutting C39/C22 / Development of Mining/ Natural Gas Quality And Cost- Open - Mining and Gas inspectors IDA / 51990 Post 200,000.00 138,493.75 Signed 2017-02-21 2017-03-14 2017-04-27 2017-05-25 2017-06-24 2017-07-29 2017-09-02 2017-09-03 Capacity Building and Based Selection International function and Guidelines Reforms C47/A55 / Upgrade of Component A: Mining Quality And Cost- Open - Mineral Information System IDA / 51990 Governance Capacity Post 250,000.00 744,046.88 Signed 2017-02-14 2017-03-07 2017-04-20 2017-05-18 2017-06-17 2017-07-22 2017-08-26 2018-08-26 Based Selection International and Library Building and Reform C55/C33 / Consultancy Component C: Cross-cutting service to support Data Mining/ Natural Gas Quality And Cost- Open - TF / 16113 Post 200,000.00 0.00 Canceled 2017-06-20 2017-07-11 2017-08-24 2017-09-21 2017-10-21 2017-11-25 2017-12-30 2018-12-30 collection & statistics for Capacity Building and Based Selection International DPD Reforms C77/C71 / Consultant Component C: Cross-cutting Consultant Services to Prepare the Mining/ Natural Gas Open - TF / 16113 Post Qualification 150,000.00 108,660.20 Signed 2017-02-20 2017-03-13 2017-04-26 2017-05-26 2017-06-30 2017-12-27 Framework of MEITI E - Capacity Building and International Selection report Reforms C78/C71 / Consultant Component C: Cross-cutting Consultant Services of Mining/ Natural Gas Open - TF / 16113 Post Qualification 100,000.00 129,280.00 Signed 2017-02-20 2017-03-13 2017-04-26 2017-05-26 2017-06-30 2017-12-27 Institutionalization of the Capacity Building and International Selection EITI Reforms Component C: Cross-cutting C82/C25 / Development of Mining/ Natural Gas Quality And Cost- Open - Hydrocarbon inspectors IDA / 51990 Post 200,000.00 0.00 Canceled 2017-03-27 2017-04-17 2017-05-31 2017-06-28 2017-07-28 2017-09-01 2017-10-06 2017-10-24 Capacity Building and Based Selection International function Reforms Component C: Cross-cutting C83/C21 / Design of Mining/ Natural Gas Quality And Cost- Open - procedure manual and IDA / 51990 Post 200,000.00 0.00 Canceled 2017-03-27 2017-04-17 2017-05-31 2017-06-28 2017-07-28 2017-09-01 2017-10-06 2018-10-06 Capacity Building and Based Selection International guidelines for hydrocarbon Reforms C84/C12 / Environmental Component C: Cross-cutting inspection guideline for Mining/ Natural Gas Quality And Cost- Open - IDA / 51990 Post 150,000.00 0.00 Canceled 2017-03-14 2017-04-04 2017-05-18 2017-06-15 2017-07-15 2017-08-19 2017-09-23 2017-09-24 mining and hydrocarbon Capacity Building and Based Selection International sectors Reforms Component A: Mining C86/A51 / Geological Quality And Cost- Open - IDA / 51990 Governance Capacity Prior 3,300,000.00 4,413,964.58 Signed 2017-02-15 2017-03-08 2017-04-21 2017-05-19 2017-06-18 2017-07-23 2017-08-27 2018-08-27 mapping Based Selection International Building and Reform Component C: Cross-cutting C90/C71 / 7th EITI Mining/ Natural Gas Quality And Cost- Open - TF / 16113 Post 160,000.00 80,859.73 Signed 2017-02-10 2017-03-03 2017-04-16 2017-05-14 2017-06-13 2017-07-18 2017-08-22 2018-08-22 Report Capacity Building and Based Selection International Reforms C96/B11 / Evaluation of Component B: Natural Gas Quality And Cost- Open - Gas Demand (Domestic and IDA / 51990 Capacity Building and Post 500,000.00 616,025.00 Signed 2017-04-20 2017-05-11 2017-06-24 2017-07-22 2017-08-21 2017-09-25 2017-10-30 2017-10-31 Based Selection International Regional) and Pricing Governance Reform Component B: Natural Gas C99-B31 / Financial Service Quality And Cost- Open - IDA / 51990 Capacity Building and Prior 1,000,000.00 980,312.50 Signed 2017-04-04 2017-04-25 2017-06-08 2017-07-06 2017-08-05 2017-09-09 2017-10-14 2018-10-14 Arranger For ENH Based Selection International Governance Reform Component B: Natural Gas C100-B4 / LNG Transaction Quality And Cost- Open - Under IDA / 51990 Capacity Building and Prior 5,000,000.00 0.00 2017-04-04 2017-04-25 2017-06-08 2017-07-06 2017-08-05 2017-09-09 2017-10-14 2018-10-14 Assistance for Area 1 and 4 Based Selection International Implementation Governance Reform Component C: Cross-cutting C104/C43 / Supervision of Consultant Mining/ Natural Gas Rehabilitation of DNGM IDA / 51990 Post Qualification Open - National 100,000.00 0.00 Canceled 2017-08-07 2017-08-08 2017-08-27 2017-08-28 2017-09-19 2018-05-17 Capacity Building and Building Selection Reforms Page 4 C105/C3 / Update of Component C: Cross-cutting Institutional and Functional Mining/ Natural Gas Quality And Cost- Open - Under IDA / 51990 Post 250,000.00 208,188.20 2017-09-04 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2018-03-14 management review of Capacity Building and Based Selection International Implementation MIREME Reforms C106/A5 / Supervision of Component A: Mining Quality And Cost- Open - Geoscientific Infrastructure IDA / 51990 Governance Capacity Prior 1,550,000.00 1,538,081.25 Signed 2017-10-20 2017-11-04 2017-12-18 2018-01-15 2018-02-14 2018-03-21 2018-04-25 2019-04-25 Based Selection International Development Programme Building and Reform Component C: Cross-cutting C16-C63 / Resettlement Mining/ Natural Gas Quality And Cost- Open - Under guidelines for mining and IDA / 51990 Post 250,000.00 0.00 2017-11-06 2017-11-27 2018-01-10 2018-02-07 2018-03-09 2018-04-13 2018-05-18 2019-05-18 Capacity Building and Based Selection International Implementation gas Reforms C50/A51 / Write a new Component A: Mining Quality And Cost- Open - handbook on the geology of IDA / 51990 Governance Capacity Post 150,000.00 0.00 Canceled 2017-05-30 2017-06-20 2017-08-03 2017-08-31 2017-09-30 2017-11-04 2017-12-09 2017-12-10 Based Selection International Mozambique Building and Reform C51/A51 / Mapping and Component A: Mining inventory of thermal and Quality And Cost- Open - IDA / 51990 Governance Capacity Post 150,000.00 0.00 Canceled 2017-02-28 2017-03-21 2017-05-04 2017-06-01 2017-07-01 2017-08-05 2017-09-09 2018-09-09 mineral water occurrences in Based Selection International Building and Reform selected areas C204- B1 / Assess the Component B: Natural Gas Quality And Cost- Open - Pending demand of petroleum product IDA / D2390 Capacity Building and Post 300,000.00 0.00 2018-09-28 2018-10-19 2018-12-02 2018-12-30 2019-01-29 2019-03-05 2019-04-09 2019-07-08 Based Selection International Implementation in Mozambique Governance Reform C205-B2 / Audit and the Area 1 and Area 4 Component B: Natural Gas Quality And Cost- Open - Exploration and Pre- IDA / D2390 Capacity Building and Post 600,000.00 844,080.00 Signed 2018-01-31 2018-02-21 2018-04-06 2018-05-04 2018-06-03 2018-07-08 2018-08-12 2019-02-08 Based Selection International Development recovered costs Governance Reform and training C208-D2 / Local Content Component D: Cross-Sectoral Quality And Cost- Open - Pending policies and regulations for IDA / D2390 Post 400,000.00 0.00 2018-09-14 2018-10-05 2018-11-18 2018-12-16 2019-01-15 2019-02-19 2019-03-26 2019-09-22 Reforms Based Selection International Implementation mining, oil and petroleum C213-C1 / Revision and Component C: Cross-cutting updating of health and Mining/ Natural Gas Quality And Cost- Open - Under IDA / D2390 Post 250,000.00 0.00 2018-09-28 2018-10-19 2018-12-02 2018-12-30 2019-01-29 2019-03-05 2019-04-09 2019-10-06 safety activities (Decree Capacity Building and Based Selection International Implementation 6/2006) Reforms C215-A5 / Preparation of a Component A: Mining Quality And Cost- Open - Under code for Estimation of IDA / D2390 Governance Capacity Post 200,000.00 0.00 2018-07-18 2018-08-08 2018-09-21 2018-10-19 2018-11-18 2018-12-23 2019-01-27 2019-04-27 Based Selection International Implementation mineral reserves Building and Reform C218-A6 / EMEM - Component A: Mining Quality And Cost- Open - Pending Elaboration of Marketing IDA / D2390 Governance Capacity Post 150,000.00 0.00 2018-07-31 2018-08-21 2018-10-04 2018-11-01 2018-12-01 2019-01-05 2019-02-09 2019-05-10 Based Selection International Implementation Plan for Minerals Building and Reform C255-B2 / Response Component B: Natural Gas Quality And Cost- Open - Under notification procedures IDA / D2390 Capacity Building and Post 150,000.00 0.00 2018-08-30 2018-09-20 2018-11-03 2018-12-01 2018-12-31 2019-02-04 2019-03-11 2019-09-07 Based Selection International Implementation System Governance Reform Component B: Natural Gas C202-B3 / Financial Service Quality And Cost- Open - Pending IDA / D2390 Capacity Building and Prior 1,000,000.00 0.00 2019-03-15 2019-04-05 2019-05-19 2019-06-16 2019-07-16 2019-08-20 2019-09-24 2020-09-23 Arranger For ENH Phase II Based Selection International Implementation Governance Reform C6/A7 / Transaction Component A: Mining Quality And Cost- Open - advisory services for mining IDA / 51990 Governance Capacity Post 500,000.00 0.00 Canceled 2017-02-27 2017-03-20 2017-05-03 2017-05-31 2017-06-30 2017-08-04 2017-09-08 2018-09-08 Based Selection International & related infrastructure Building and Reform Component B: Natural Gas C203-B3 / Legal Consultant Quality And Cost- Open - Pending IDA / D2390 Capacity Building and Prior 1,000,000.00 0.00 2018-07-30 2018-08-20 2018-10-03 2018-10-31 2018-11-30 2019-01-04 2019-02-08 2020-02-08 for ENH Based Selection International Implementation Governance Reform Page 5 Component B: Natural Gas C207-B2 / Emergency Quality And Cost- Open - Under IDA / D2390 Capacity Building and Post 150,000.00 0.00 2018-05-15 2018-06-05 2018-07-19 2018-08-16 2018-09-15 2018-10-20 2018-11-24 2019-02-22 Procedures Based Selection International Implementation Governance Reform Component A: Mining C98-A5 / Geo-magnetic Quality And Cost- Open - IDA / 51990 Governance Capacity Post 300,000.00 0.00 Under Review 2018-04-16 2018-05-07 2018-06-20 2018-07-18 2018-08-17 2018-09-21 2018-10-26 2019-04-24 Mapping Based Selection International Building and Reform C223-D2 / Develop the operational model and Component D: Cross-Sectoral Quality And Cost- Open - Under implementation plan for TF / 16113 Post 300,000.00 0.00 2018-05-31 2018-06-21 2018-08-04 2018-09-01 2018-10-01 2018-11-05 2018-12-10 2019-06-08 Reforms Based Selection International Implementation linkage center for oil, gas and mining industry C216-A6 / EMEM - Component A: Mining Quality And Cost- Open - Under National survey of mining IDA / D2390 Governance Capacity Post 150,000.00 0.00 2018-05-07 2018-05-28 2018-07-11 2018-08-08 2018-09-07 2018-10-12 2018-11-16 2019-02-14 Based Selection International Implementation activity Building and Reform C230-C6 / Preparation of Component C: Cross-cutting Cumulative Impact Mining/ Natural Gas Quality And Cost- Open - Under Assessment guidelines and IDA / D2390 Post 500,000.00 0.00 2018-05-15 2018-06-05 2018-07-19 2018-08-16 2018-09-15 2018-10-20 2018-11-24 2019-11-24 Capacity Building and Based Selection International Implementation Procedures and data Reforms collection C210-A3 / ASM Component A: Mining Quality And Cost- Open - Under Institutional Strengthening & IDA / D2390 Governance Capacity Post 350,000.00 0.00 2018-04-26 2018-05-17 2018-06-30 2018-07-28 2018-08-27 2018-10-01 2018-11-05 2019-05-04 Based Selection International Implementation Alignment Building and Reform Component C: Cross-cutting C219-C1 / Legal and Mining/ Natural Gas Quality And Cost- Open - Pending Regulatory framework for IDA / D2390 Post 300,000.00 0.00 2018-05-30 2018-06-20 2018-08-03 2018-08-31 2018-09-30 2018-11-04 2018-12-09 2019-06-07 Capacity Building and Based Selection International Implementation mining and hydrocarbons Reforms C209-C6 / Study on woman Component C: Cross-cutting and children participation in Mining/ Natural Gas Quality And Cost- Open - Pending IDA / D2390 Post 300,000.00 0.00 2018-05-15 2018-06-05 2018-07-19 2018-08-16 2018-09-15 2018-10-20 2018-11-24 2019-05-23 artisanal mining in Capacity Building and Based Selection International Implementation Mozambique Reforms Component B: Natural Gas C228-B2 / Strategic Plan Quality And Cost- Open - Under IDA / D2390 Capacity Building and Post 200,000.00 0.00 2018-04-27 2018-05-18 2018-07-01 2018-07-29 2018-08-28 2018-10-02 2018-11-06 2019-05-05 for ENH Based Selection International Implementation Governance Reform C206-B2 / Develop a New Component B: Natural Gas Quality And Cost- Open - Under HSE Regulation for Oil and IDA / D2390 Capacity Building and Post 400,000.00 0.00 2018-05-30 2018-06-20 2018-08-03 2018-08-31 2018-09-30 2018-11-04 2018-12-09 2019-06-07 Based Selection International Implementation Gas Governance Reform Component C: Cross-cutting C229-C6 / Community Mining/ Natural Gas Quality And Cost- Open - Pending IDA / D2390 Post 150,000.00 0.00 2018-05-30 2018-06-20 2018-08-03 2018-08-31 2018-09-30 2018-11-04 2018-12-09 2019-03-09 based Agreements Model Capacity Building and Based Selection International Implementation Reforms C214-A7 / Transaction Component A: Mining Quality And Cost- Open - Pending advisory services for mining IDA / 51990 Governance Capacity Prior 1,500,000.00 0.00 2018-05-30 2018-06-20 2018-08-03 2018-08-31 2018-09-30 2018-11-04 2018-12-09 2019-12-09 Based Selection International Implementation &related infrastructure Building and Reform Component A: Mining C101-A5 / Geochemical Quality And Cost- Open - Pending IDA / 51990 Governance Capacity Post 300,000.00 0.00 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2019-10-23 Mapping Based Selection International Implementation Building and Reform Component A: Mining C102-A5 / Geo- Quality And Cost- Open - IDA / 51990 Governance Capacity Post 200,000.00 0.00 Under Review 2018-10-24 2018-11-14 2018-12-28 2019-01-25 2019-02-24 2019-03-31 2019-05-05 2019-11-01 environmental mapping Based Selection International Building and Reform Component C: Cross-cutting Consultant C76/C67 / Gender Strategy Mining/ Natural Gas Open - Pending IDA / 51990 Post Qualification 100,000.00 0.00 2018-10-04 2018-10-25 2018-12-08 2019-01-07 2019-02-11 2019-08-10 in Mining and Gas Sector Capacity Building and International Implementation Selection Reforms Page 6 Component C: Cross-cutting C92/C5 / Financial Consultant Mining/ Natural Gas Open - Pending supervision, Auditing Account IDA / 51990 Post Qualification 180,000.00 0.00 2018-09-18 2018-10-09 2018-11-22 2018-12-22 2019-01-26 2019-04-26 Capacity Building and International Implementation for petroleum and Gas Selection Reforms C85 /C5 / Development of Component C: Cross-cutting fiscal risk assessment and Mining/ Natural Gas Quality And Cost- Open - Pending TF / 16113 Post 300,000.00 0.00 2018-08-01 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2020-02-10 management in extractive Capacity Building and Based Selection International Implementation industry projects Reforms Component C: Cross-cutting C222-C6 / Evaluation of Mining/ Natural Gas Quality And Cost- Open - the implementation of CSR IDA / D2390 Post 100,000.00 0.00 Canceled 2018-04-25 2018-05-16 2018-06-29 2018-07-27 2018-08-26 2018-09-30 2018-11-04 2019-02-02 Capacity Building and Based Selection International in extractive industry Reforms C100A/B4 / LNG Component B: Natural Gas Quality And Cost- Open - Transaction Assistance for IDA / 51990 Capacity Building and Prior 3,000,000.00 2,369,490.00 Signed 2018-09-10 2018-10-01 2018-11-14 2018-12-12 2019-01-11 2019-02-15 2019-03-22 2020-03-21 Based Selection International Area 1 and 4 Governance Reform C234/C6 / Management of Component C: Cross-cutting community expectations and Mining/ Natural Gas Quality And Cost- Open - Under IDA / 51990 Post 200,000.00 0.00 2018-09-17 2018-10-08 2018-11-21 2018-12-19 2019-01-18 2019-02-22 2019-03-29 2019-09-25 benefits provided by the Capacity Building and Based Selection International Implementation extractive industry. Reforms Component C: Cross-cutting C235/C8 / CSR and Gender Mining/ Natural Gas Quality And Cost- Pending IDA / 51990 Post Open - National 600,000.00 0.00 2018-11-12 2018-12-03 2019-01-16 2019-02-13 2019-03-15 2019-04-19 2019-05-24 2020-05-23 Pilots-NGOS Capacity Building and Based Selection Implementation Reforms C237 / Development of environmental sensitivity atlases to identify areas Component B: Natural Gas under pressure from Quality And Cost- Open - IDA / 51990 Capacity Building and Post 200,000.00 0.00 Under Review 2018-10-29 2018-11-19 2019-01-02 2019-01-30 2019-03-01 2019-04-05 2019-05-10 2019-11-06 petroleum operations and Based Selection International Governance Reform mapping areas with ecosystems sensitive to hydrocarbon exploration. C238/C6 / Elaboration of guidelines for the implementation of Component C: Cross-cutting compensation rates for Mining/ Natural Gas Quality And Cost- Open - Pending IDA / 51990 Post 200,000.00 0.00 2018-10-31 2018-11-21 2019-01-04 2019-02-01 2019-03-03 2019-04-07 2019-05-12 2019-11-08 affected communities in the Capacity Building and Based Selection International Implementation scope of activities and Reforms projects related to petroleum operations. C241/C1 / GAP analysis of the capacity of MIREME Component C: Cross-cutting and other relevant Mining/ Natural Gas Quality And Cost- Open - Pending institutions, to provide IDA / 51990 Post 200,000.00 0.00 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2019-10-23 Capacity Building and Based Selection International Implementation environmental and social Reforms stewardship for the mining and oil & gas sectors. C258/A6 / EMEM - Component A: Mining Assessment on Chire Quality And Cost- Open - Pending IDA / 51990 Governance Capacity Post 150,000.00 0.00 2019-07-31 2019-08-21 2019-10-04 2019-11-01 2019-12-01 2020-01-05 2020-02-09 2020-08-07 limestone for Cement Based Selection International Implementation Building and Reform Production Component C: Cross-cutting C261/A7 / ITIEM 8th Mining/ Natural Gas Quality And Cost- Open - Pending IDA / 51990 Post 150,000.00 0.00 2019-07-15 2019-08-05 2019-09-18 2019-10-16 2019-11-15 2019-12-20 2020-01-24 2020-07-22 RePORT Capacity Building and Based Selection International Implementation Reforms C211-A3 / ASM Component A: Mining Quality And Cost- Open - Strengthening of Miners' IDA / D2390 Governance Capacity Post 450,000.00 0.00 Canceled 2018-07-20 2018-08-10 2018-09-23 2018-10-21 2018-11-20 2018-12-25 2019-01-29 2019-07-28 Based Selection International Associations & Cooperatives Building and Reform Page 7 C212-A3 / ASM Component A: Mining Quality And Cost- Open - Implementation of Extension IDA / D2390 Governance Capacity Prior 1,700,000.00 0.00 Canceled 2018-10-30 2018-11-20 2019-01-03 2019-01-31 2019-03-02 2019-04-06 2019-05-11 2020-05-10 Based Selection International Services Program Building and Reform INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component E: Project Individual C24/E / Environmental IDA / 51990 Management and Post Consultant Open 72,000.00 202,000.00 Signed 2017-04-24 2017-06-12 2017-07-03 2017-08-07 2018-02-03 consultant Coordination Selection Component A: Mining Individual C46/A53 / Upgrade of IDA / 51990 Governance Capacity Post Consultant Open 60,000.00 89,747.74 Signed 2017-02-16 2017-04-06 2017-04-27 2017-06-01 2017-11-28 Seismic Stations Building and Reform Selection C48/A51 / Translation into Portuguese and publication Component A: Mining Individual of the Explanation of the IDA / 51990 Governance Capacity Post Consultant Open 85,000.00 63,176.49 Signed 2017-02-14 2017-04-04 2017-04-25 2017-05-30 2017-11-26 Geological Map of Building and Reform Selection Mozambique Component C: Cross-cutting C56/C33 / Training Services Individual Mining/ Natural Gas (Economy and Management TF / 16113 Post Consultant Open 50,000.00 0.00 Canceled 2017-04-12 2017-05-31 2017-06-21 2017-07-26 2018-01-22 Capacity Building and of Oil and Gas) Selection Reforms Component C: Cross-cutting C70/C32 / Institution of Individual Mining/ Natural Gas High Authority for the TF / 16113 Prior Consultant Open 300,000.00 123,250.39 Signed 2017-05-25 2017-07-13 2017-08-03 2017-09-07 2018-03-06 Capacity Building and Extractive Industry Selection Reforms Component C: Cross-cutting C97/C67 / Training Services Individual Mining/ Natural Gas in Wast Management in the TF / 16113 Post Consultant Open 30,000.00 12,600.00 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2017-12-10 Capacity Building and extractive sector Selection Reforms Component B: Natural Gas Individual C93/B4 / LNG Financial IDA / 51990 Capacity Building and Prior Consultant Open 200,000.00 0.00 Canceled 2017-02-15 2017-04-05 2017-04-26 2017-05-31 2017-11-27 Advisor Services for INP Governance Reform Selection Component B: Natural Gas Individual C94/B4 / LNG Commercial IDA / 51990 Capacity Building and Prior Consultant Open 200,000.00 0.00 Canceled 2017-02-15 2017-04-05 2017-04-26 2017-05-31 2017-11-27 Advisor Services for INP Governance Reform Selection Component B: Natural Gas Individual C95/B4 / LNG Legal IDA / 51990 Capacity Building and Prior Consultant Open 200,000.00 0.00 Canceled 2017-02-15 2017-04-05 2017-04-26 2017-05-31 2017-11-27 Advisor Services for INP Governance Reform Selection Component C: Cross-cutting C16/C63 / Resettlement Individual Mining/ Natural Gas guidelines for mining and IDA / 51990 Post Consultant Open 250,000.00 0.00 Canceled 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2018-02-17 Capacity Building and gas Selection Reforms C103-A5 / Specialized Component A: Mining Translation services of IDA / 51990 Governance Capacity Prior Direct Selection Direct 100,000.00 0.00 Canceled 2017-04-05 2017-04-15 2017-06-19 2017-12-16 Mining Regulations Building and Reform C51-A5 / Mapping and Component A: Mining Individual inventory of thermal and Under IDA / 51990 Governance Capacity Post Consultant Open 150,000.00 0.00 2017-11-15 2018-01-03 2018-01-24 2018-02-28 2018-08-27 mineral water occurrences in Implementation Building and Reform Selection selected areas Page 8 C227-B2 / Review & Component B: Natural Gas Evaluation of LNG Project IDA / D2390 Capacity Building and Post Direct Selection Direct 400,000.00 501,250.00 Signed 2018-05-09 2018-05-19 2018-07-23 2019-01-19 Development Plan - Governance Reform Prosperidade and Mamba Component C: Cross-cutting C220- C4 / Assessment and Individual Mining/ Natural Gas Under design of MIREME IT IDA / D2390 Post Consultant Open 50,000.00 0.00 2018-04-30 2018-06-18 2018-07-09 2018-08-13 2018-11-11 Capacity Building and Implementation Infrastructure Selection Reforms C221-D2 / Definition of Individual Component D: Cross-Sectoral Pending poles / clusters in extractive TF / 16113 Post Consultant Open 50,000.00 0.00 2018-09-20 2018-11-08 2018-11-29 2019-01-03 2019-04-03 Reforms Implementation sector Selection C224-D2 / Harmonization of Individual Procurement procedures in Component D: Cross-Sectoral Pending TF / 16113 Post Consultant Open 200,000.00 0.00 2018-05-30 2018-07-18 2018-08-08 2018-09-12 2019-03-11 extractive industry and Reforms Implementation Selection develop a guideline for SME C109/A5 / Translation into Portuguese and publication Component A: Mining Individual of the Explanation of the IDA / 51990 Governance Capacity Post Consultant Open 50,000.00 50,000.00 Signed 2018-04-30 2018-06-18 2018-07-09 2018-08-13 2019-02-09 Geological Map of Building and Reform Selection Mozambique - Part 2 C107/A5 / Specialized Component A: Mining Individual Translation services of IDA / 51990 Governance Capacity Post Consultant Open 50,000.00 26,048.03 Signed 2018-04-30 2018-06-18 2018-07-09 2018-08-13 2018-11-11 Mining Regulations Building and Reform Selection C108/A5 / Review/Proofing Component A: Mining Individual Under of Translation of Mining IDA / 51990 Governance Capacity Post Consultant Open 30,000.00 0.00 2018-05-17 2018-07-05 2018-07-26 2018-08-30 2019-02-26 Implementation Regulations Building and Reform Selection Component C: Cross-cutting C72/C22 / Training on HSE Mining/ Natural Gas Under Risk Prevention on Solid IDA / 51990 Post Direct Selection Direct 150,000.00 0.00 2017-03-15 2017-03-25 2017-05-29 2017-06-07 Capacity Building and Implementation Minerals Extractive Industry Reforms Component C: Cross-cutting C71/C24 / Guidelines and Individual Mining/ Natural Gas Pending Procedures Manual for IDA / 51990 Post Consultant Open 100,000.00 0.00 2018-07-18 2018-09-05 2018-09-26 2018-10-31 2019-04-29 Capacity Building and Implementation Auditing Mining Inspectors Selection Reforms Component B: Natural Gas Individual C231 - B4 / LNG Adviser Under IDA / D2390 Capacity Building and Prior Consultant Open 300,000.00 491,150.00 2018-05-10 2018-06-28 2018-07-19 2018-08-23 2019-08-23 for MIREME Implementation Governance Reform Selection C232 - C3 / Component C: Cross-cutting Individual Implementation of Mining/ Natural Gas Under TF / 16113 Post Consultant Open 200,000.00 45,000.00 2018-05-10 2018-06-28 2018-07-19 2018-08-23 2019-08-23 Communication Strategy in Capacity Building and Implementation Selection the Extractive Sector Reforms C233-A3 / Consultancy Service for Technical Support Component A: Mining in the Validation Seminary IDA / 51990 Governance Capacity Post Direct Selection Direct 20,000.00 20,000.00 Signed 2018-06-20 2018-06-30 2018-09-03 2018-10-03 of ASM Implementation Building and Reform Strategy C236/C6 / Definition of Component C: Cross-cutting Individual responsibilities for Mining/ Natural Gas Pending IDA / 51990 Post Consultant Open 100,000.00 0.00 2018-11-05 2018-12-24 2019-01-14 2019-02-18 2019-08-17 environmental issues within Capacity Building and Implementation Selection MIREME. Reforms Component C: Cross-cutting C239/C6 / Evaluation of Individual Mining/ Natural Gas Under Incidence of HIV in small IDA / 51990 Post Consultant Open 100,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Capacity Building and Implementation mining scale in Mozambique Selection Reforms Page 9 Component C: Cross-cutting C240/C6 / Design of Social Individual Mining/ Natural Gas Impact Assessment IDA / 51990 Post Consultant Open 150,000.00 0.00 Under Review 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Capacity Building and Guidelines Selection Reforms Component C: Cross-cutting C242/C7 / ITIEM Concept Mining/ Natural Gas Under Note and Work plan (2019- IDA / 51990 Post Direct Selection Direct 50,000.00 0.00 2018-09-17 2018-09-27 2018-12-01 2019-03-01 Capacity Building and Implementation 2021) Reforms Component E: Project C243/E / PIU Coordinator IDA / 51990 Management and Post Direct Selection Direct 235,000.00 231,336.00 Signed 2018-09-26 2018-10-06 2018-12-10 2020-11-29 Coordination Component E: Project C246/E / Financial IDA / 51990 Management and Post Direct Selection Direct 205,000.00 203,439.60 Signed 2018-09-26 2018-10-06 2018-12-10 2020-11-29 Specialist Coordination Component E: Project C247/E / Gas Specialist IDA / 51990 Management and Post Direct Selection Direct 180,000.00 55,080.00 Signed 2018-09-26 2018-10-06 2018-12-10 2020-11-29 Coordination Component E: Project C248/E / Mining Specialist IDA / 51990 Management and Post Direct Selection Direct 195,000.00 48,568.75 Signed 2018-09-26 2018-10-06 2018-12-10 2020-11-29 Coordination Component E: Project C250/E / Accounting IDA / 51990 Management and Post Direct Selection Direct 85,000.00 81,181.44 Signed 2018-09-26 2018-10-06 2018-12-10 2020-11-29 Assistant Coordination Component E: Project C251/E / Accounting IDA / 51990 Management and Post Direct Selection Direct 85,000.00 20,275.92 Signed 2018-09-26 2018-10-06 2018-12-10 2020-11-29 Assistant II Coordination C252/E / Extractive Sector Component E: Project Individual Under Communication Consultant IDA / 51990 Management and Post Consultant Open 50,000.00 0.00 2018-10-15 2018-12-03 2018-12-24 2019-01-28 2020-01-28 Implementation for MAGTAP Coordination Selection Component E: Project C249/E / Procurement IDA / 51990 Management and Prior Direct Selection Direct 100,000.00 95,014.69 Signed 2018-09-26 2018-10-06 2018-12-10 2020-11-29 Assistant Coordination Component E: Project C244/E / Procurement IDA / 51990 Management and Prior Direct Selection Direct 170,000.00 41,883.92 Signed 2018-09-26 2018-10-06 2018-12-10 2020-11-29 Specialist Coordination Component E: Project C245/E / Procurement IDA / 51990 Management and Prior Direct Selection Direct 170,000.00 168,016.03 Signed 2018-09-26 2018-10-06 2018-12-10 2020-11-29 Specialist II Coordination Component A: Mining Individual C257/A5 / Support to Pending IDA / 51990 Governance Capacity Post Consultant Open 30,000.00 0.00 2019-07-21 2019-09-08 2019-09-29 2019-11-03 2020-05-01 Geoscience Laboratory Implementation Building and Reform Selection Page 10