EC Quito Metro Line One (P144489) Ecuador, IBRD/IDA, FY: 2014, Team Leader(s): Arturo Ardila Gomez, Alejandro Hoyos Guerrero , Lending Instrument: Investment Project Financing • PROCUREMENT Ecuador : Quito Metro Line One PLAN General Information Country: Ecuador Bank’s Approval Date of the Original Procurement Plan: 2017-08-08 2020-12-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P144489 GPN Date: Project Name: Quito Metro Line One Loan / Credit No: IBRD / 82850, IBRD / 88890 Quito Metro Private Enterprise Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-EPM METRO QUITO- 16706-CS-QCBS / Incorporación de la 5: Technical Studies to Selección basada perspectiva de género en el IBRD / 82850 Support Project Posterior Open - National 178,000.00 0.00 En ejecución 2017-08-11 2017-08-09 2017-08-29 2017-08-22 2017-09-12 2017-12-18 2017-10-03 2018-01-12 2017-10-10 2018-01-21 2017-10-20 2017-10-30 2018-10-30 en calidad y costo sistema Integrado de Implementation Transporte Público del Distrito Metropolitano de Quito EC-EPM METRO QUITO- 47039-CS-QCBS / Desarrollo e Implementación del Plan de 5: Technical Studies to Selección basada Capacitación y formación de IBRD / 82850 Support Project Previa Open - International 500,000.00 0.00 Cancelado 2018-03-05 2018-03-26 2018-05-09 2018-06-06 2018-07-06 2018-08-10 2018-09-14 2019-09-14 en calidad y costo personal para el período de Implementation transción y operación Metro de Quito EC-EPM METRO QUITO- 47319-CS-QCBS / Consultoría 5: Technical Studies to Selección basada para la actualización del IBRD / 82850 Support Project Posterior Open - International 300,000.00 0.00 En ejecución 2018-07-02 2018-09-18 2018-07-23 2020-02-04 2018-09-05 2020-09-03 2018-10-03 2020-10-12 2018-11-02 2018-12-07 2019-01-11 2019-07-10 en calidad y costo Estudio de Impacto Ambiental Implementation para la operación de la PLMQ EC-EPM METRO QUITO- 47036-CS-QCBS / Estudio 5: Technical Studies to para el Modelo de desarrollo, Selección basada IBRD / 82850 Support Project Posterior Open - International 345,000.00 0.00 Cancelado 2018-03-04 2018-03-25 2018-05-08 2018-06-05 2018-07-05 2018-08-09 2018-09-13 2019-05-11 manejo y adminsitración de en calidad y costo Implementation ingresos no tarifarios de Metro de Quito EC-EPM METRO QUITO- 5: Technical Studies to 16705-CS-QCBS / Selección basada IBRD / 82850 Support Project Previa Open - International 1,300,000.00 0.00 Cancelado 2018-02-01 2018-02-22 2018-04-07 2018-05-05 2018-06-04 2018-07-09 2018-08-13 2019-08-13 Elaboración del nuevo Plan en calidad y costo Implementation Maestro Integral de Movilidad EC-EPM METRO QUITO- 5: Technical Studies to 47038-CS-QCBS / Desarrollo Selección basada IBRD / 82850 Support Project Posterior Open - International 300,000.00 0.00 En ejecución 2018-05-21 2018-06-11 2018-07-25 2018-08-22 2018-09-21 2018-10-26 2018-11-30 2019-05-29 de la estrategia para el en calidad y costo Implementation fomento de Cultura Metro EC-EPM METRO QUITO- 16700-CS-QCBS / Estudio de 5: Technical Studies to Selección basada desarrollo urbano relacionado IBRD / 82850 Support Project Previa Open - International 550,000.00 0.00 En ejecución 2018-07-25 2018-08-24 2018-09-27 2018-09-21 2020-04-06 2018-10-19 2018-11-02 2018-11-15 2018-11-25 2019-11-25 en calidad y costo con el Sistema de Transporte Implementation Público Metro de Quito EC-EPM METRO QUITO- 16708-CS-QCBS / Implementación de mecanismos de prevención, 5: Technical Studies to atención y denuncia de la Selección basada IBRD / 82850 Support Project Posterior Open - National 100,000.00 0.00 Cancelado 2018-08-13 2018-08-27 2018-09-10 2018-10-01 2018-10-08 2018-10-18 2018-10-28 2019-04-26 violencia y el acoso sexual en calidad y costo Implementation hacia las mujeres y niñas en el Sistema Integrado de Transporte Público del distrito Metropolitano de Quito EC-EPM METRO QUITO- 5: Technical Studies to 16701-CS-QCBS / Estudio de Selección basada IBRD / 88890 Support Project Posterior Open - International 250,000.00 0.00 Cancelado 2019-05-03 2019-05-24 2019-07-07 2019-08-04 2019-09-03 2019-10-08 2019-11-12 2020-05-10 Intermodalidad y fomento del en calidad y costo Implementation transporte público EC-EPM METRO QUITO- 47040-CS-QCBS / Consultoría 5: Technical Studies to para el estudio de monitoreo Selección basada IBRD / 82850 Support Project Previa Open - International 500,000.00 0.00 Cancelado 2019-01-10 2019-01-31 2019-03-16 2019-04-13 2019-05-13 2019-06-17 2019-07-22 2020-01-07 de parámetros ambientales en calidad y costo Implementation adicionales solicitados por los multilaterales en el PAC Page 1 EC-EPM METRO QUITO- 112684-CS-QCBS / Plan maestro de Movilidad. Según 5: Technical Studies to lo acordado en la misión de Selección basada IBRD / 88890 Support Project Previa Open - International 1,300,000.00 0.00 Bajo Revision 2019-08-05 2019-11-14 2019-08-26 2019-11-18 2019-10-09 2020-11-17 2019-11-06 2019-12-06 2020-01-10 2020-02-14 2020-12-10 seguimiento de Abril de 2019, en calidad y costo Implementation se retoma este estudio con el mismo presupuesto planificado anteriormente. EC-EPM METRO QUITO- 47316-CS-QCBS / Estudio de remediación de pasivos ambientales y sociales en 5: Technical Studies to Selección basada escombrera Oyacoto, IBRD / 82850 Support Project Posterior Open - National 150,000.00 0.00 Cancelado 2018-06-04 2018-06-25 2018-08-08 2018-09-05 2018-10-05 2018-11-09 2018-12-14 2019-06-02 en calidad y costo generados por vertido de Implementation materiales de desalojo de la Primera Línea del Metro de Quito EC-EPM METRO QUITO- 47037-CS-QCBS / Estudio el 5: Technical Studies to Selección basada desarrollo del sistema de IBRD / 82850 Support Project Posterior Open - International 195,000.00 0.00 Cancelado 2019-03-29 2019-04-12 2019-05-10 2019-05-24 2019-06-07 2019-07-05 2019-08-02 2019-10-31 en calidad y costo control e inventario de bienes Implementation de la PLMQ EC-EPM METRO QUITO- 16699-CS-QCBS / Estudio sobre modelo de negocio de Metro de Quito y estructuración de la Empresa 5: Technical Studies to Metro de Quito. Incluye Selección basada IBRD / 82850 Support Project Previa Open - International 2,500,000.00 0.00 Cancelado 2017-09-22 2017-10-13 2017-11-10 2017-12-08 2017-12-22 2018-01-08 2018-01-18 2019-01-18 estudio para ingresos no en calidad y costo Implementation tarifarios y desarrollo e Implementación del Plan de Capacitación y formación para el personal de Metro durante la transición EC-EPM METRO QUITO- 142877-CS-QCBS / Estudio que permita estructurar y conformar la Entidad 5: Technical Studies to Selección basada Administradora del Sistema IBRD / 88890 Support Project Posterior Open - International 340,000.00 0.00 En ejecución 2019-11-08 2020-03-31 2019-11-29 2020-04-10 2020-01-12 2020-02-09 2020-03-10 2020-04-14 2020-05-19 2020-09-16 en calidad y costo Integrado de Transporte Implementation Público del Distrito Metropolitano de Quito - Autoridad Única de Transporte EC-EPM METRO QUITO- 142881-CS-QCBS / Asesoría técnica especializada para la elaboración de los pliegos 5: Technical Studies to para la contratación de la Selección basada Ejecución IBRD / 88890 Support Project Posterior Open - International 350,000.00 0.00 2019-11-08 2019-11-29 2020-01-12 2020-02-09 2020-03-10 2020-04-14 2020-05-19 2021-05-19 implementación, operación y en calidad y costo pendiente Implementation mantenimiento del SIR, SAE, SIU y sag para el Sistema Integrado de Transporte Público de Pasajeros del DMQ. EC-EPM METRO QUITO- 142885-CS-QCBS / Estudio 5: Technical Studies to que permita definir el modelo Selección basada IBRD / 88890 Support Project Posterior Open - International 250,000.00 0.00 Cancelado 2019-12-02 2019-12-23 2020-02-05 2020-03-04 2020-04-03 2020-05-08 2020-06-12 2021-06-12 de gestión del Sistema en calidad y costo Implementation Integrado de Transporte Público del DMQ. EC-EPM METRO QUITO- 144956-CS-QCBS / Estudio 5: Technical Studies to para la Determinación de los Selección basada IBRD / 82850 Support Project Posterior Open - International 500,000.00 0.00 Bajo Revision 2019-11-15 2020-11-13 2019-12-06 2020-10-27 2020-01-19 2020-02-16 2020-03-17 2020-04-21 2020-05-26 2021-05-26 Ingresos No Tarifarios en la en calidad y costo Implementation Primera Linea del Metro de Quito (PLMQ) EC-EPM METRO QUITO- 107968-CS-QCBS / Implementación de acciones 5: Technical Studies to Selección basada de Cultura Metro en IBRD / 88890 Support Project Posterior Open - International 500,000.00 0.00 Cancelado 2019-08-30 2019-09-20 2019-11-03 2019-12-01 2019-12-31 2020-02-04 2020-03-10 2021-03-10 en calidad y costo seguimiento al Desarrollo de Implementation la estrategia para el fomento de la misma EC-EPM METRO QUITO- 16709-CS-QCBS / Declaratoria anual de desechos peligrosos 2018. 5: Technical Studies to Este estudio corresponde al Selección basada IBRD / 82850 Support Project Posterior Open - National 30,000.00 0.00 Cancelado 2018-08-13 2018-08-27 2018-09-10 2018-09-24 2018-10-04 2018-10-21 2018-11-04 2019-01-03 período mencionado y es en calidad y costo Implementation parte del cumplimento de la normativa ambiental local, que se realiza anualmente. Es distinta a la de 2017. EC-EPM METRO QUITO- 146247-CS-CQS / 5: Technical Studies to Selección basada Estructuración legal para la IBRD / 88890 Support Project Posterior en calificaciones Open - International 180,000.00 0.00 Cancelado 2019-11-21 2020-02-14 2019-12-12 2020-01-25 2020-02-24 2020-03-30 2020-09-26 operación y mantenimiento de Implementation de consultores la Primera Linea del Metro de Quito EC-EPM METRO QUITO- 192320-CS-QCBS / SERVICIOS DE CONSULTORÍA PARA ESTABLECER LA METODOLOGÍA DE SELECCIÓN 5: Technical Studies to Selección basada DEL PROVEEDOR DE LOS IBRD / 88890 Support Project Posterior Open - International 180,000.00 0.00 En ejecución 2020-09-11 2020-10-13 2020-10-02 2020-10-14 2020-11-15 2020-12-13 2021-01-12 2021-02-16 2021-03-23 2022-03-23 en calidad y costo SERVICIOS DE OPERACIÓN, Implementation MANTENIMIENTO Y TRANSFERENCIA TECNOLÓGICA DE LA PRIMERA LÍNEA DEL METRO DE QUITO Page 2 EC-EPM METRO QUITO- 142888-CS-INDV / Actualización al modelo de integración tarifaria (Fase II). 5: Technical Studies to Determinación de la fórmula Selección basada IBRD / 88890 Support Project Posterior Open - International 300,000.00 0.00 En ejecución 2020-10-19 2020-10-20 2020-11-09 2020-12-23 2021-01-20 2021-02-19 2021-03-26 2021-04-30 2022-04-30 de distribución de ingresos a en calidad y costo Implementation distintos operadores del sistema integrado de transporte público de pasajeros del DMQ. EC-EPM METRO QUITO- 144958-CS-QCBS / Estudio de evaluación integral y 5: Technical Studies to propuesta de reestructuración Selección basada IBRD / 82850 Support Project Posterior Open - International 927,670.00 0.00 Bajo Revision 2020-11-06 2020-12-03 2020-11-27 2020-12-26 2021-01-23 2021-02-22 2021-03-29 2021-05-03 2022-05-03 institucional de la Empresa en calidad y costo Implementation Pública Metropolitana de Transporte de Pasajeros de Quito EC-EPM METRO QUITO- 203538-CS-QCBS / 5: Technical Studies to Estructuración técnica de la Selección basada IBRD / 82850 Support Project Previa Open - International 2,122,600.00 0.00 En ejecución 2020-11-06 2020-11-10 2020-11-27 2020-11-12 2021-01-10 2021-02-07 2021-03-09 2021-04-13 2021-05-18 2022-05-18 operación y el mantenimineto en calidad y costo Implementation de la Primera Línea del Metro de Quito EC-EPM METRO QUITO- 208964-CS-QCBS / Definición de la estrategia de comunicación a operadores y 5: Technical Studies to usuarios sobre la Selección basada Ejecución IBRD / 88890 Support Project Posterior Open - International 85,000.00 0.00 2020-12-14 2020-12-29 2021-01-27 2021-02-24 2021-03-26 2021-04-30 2021-06-04 2021-10-02 implementación del Sistema en calidad y costo pendiente Implementation integrado de Transporte y la Tarifa Integrada de Transporte del Distrito Metropolitano de Quito INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-EPM METRO QUITO- 16703-CS-CDS / 5: Technical Studies to Selección directa Contratación de un consultor IBRD / 82850 Support Project Posterior Direct 30,000.00 25,000.00 Finalizado 2017-08-11 2017-08-07 2017-08-13 2017-11-01 2017-09-15 2017-11-10 2017-10-30 2018-01-31 de consultores para asesoría en Contrato Implementation Fidic EC-EPM METRO QUITO- 47665-CS-INDV / Declaratoria anual de desechos peligrosos 2018. 5: Technical Studies to Este estudio corresponde al IBRD / 82850 Support Project Posterior Individual Limited 30,000.00 30,000.00 Finalizado 2018-09-14 2018-11-30 2018-09-19 2019-02-20 2018-10-10 2019-02-28 2018-11-14 2019-03-13 2019-02-22 2019-04-26 período mencionado y es Implementation parte del cumplimento de la normativa ambiental local, que se realiza anualmente. Es distinta a la de 2017. EC-EPM METRO QUITO- 16547-CS-CDS / 5: Technical Studies to Selección directa Ejecución Actualización del modelo de IBRD / 82850 Support Project Previa Direct 200,000.00 0.00 2017-05-30 2017-06-01 2018-04-30 2018-10-27 de consultores pendiente demanda para la Primera Implementation Línea del Metro de Quito del DMQ EC-EPM METRO QUITO- 56626-CS-INDV / Declaratoria anual de desechos peligrosos 2017. 5: Technical Studies to Este estudio corresponde al IBRD / 82850 Support Project Posterior Individual Limited 30,000.00 0.00 Cancelado 2018-02-05 2018-05-10 2018-05-31 2018-07-05 2018-08-04 período mencionado y es Implementation parte del cumplimento de la normativa ambiental local, que se realiza anualmente. Es distinta a la de 2018. EC-EPM METRO QUITO- 47318-CS-CDS / Actualización de la puesta en valor de los hallazgos 5: Technical Studies to arqueológicos en la Plaza San Selección directa IBRD / 82850 Support Project Posterior Direct 50,000.00 0.00 Cancelado 2018-04-30 2018-05-10 2018-07-14 2018-07-20 Francisco. Esta consultoría es de consultores Implementation un seguimiento del primer estudio realizado al respecto. Sería realizado por la misma firma: KATZAM EC-EPM METRO QUITO- 47320-CS-INDV / Asesoría técnica para la implementación del 5: Technical Studies to Componente V en el área de IBRD / 82850 Support Project Posterior Individual Limited 34,000.00 0.00 Cancelado 2018-05-02 2018-05-07 2018-05-28 2018-07-02 2018-08-31 Gestión Ambiental, que Implementation responde a la necesidad de la implementación inmediata de medidas solicitadas por los organismos multilaterales EC-EPM METRO QUITO- 134776-CS-CDS / Diseño de ingeniería básica y definición 5: Technical Studies to de presupuesto básico de la Selección directa IBRD / 82850 Support Project Previa Direct 1,100,000.00 1,451,563.50 Firmado 2019-09-17 2019-11-18 2019-09-27 2020-01-24 2019-12-01 2020-12-01 2020-05-29 construcción de la extensión de consultores Implementation de la Primera Línea del Metro de Quito (Tramo El Labrador - La Ofelia) Page 3 EC-EPM METRO QUITO- 107955-CS-INDV / Asesoría técnica para la implementación del 5: Technical Studies to Componente V en el área de IBRD / 82850 Support Project Posterior Individual Direct 34,000.00 34,000.00 Finalizado 2019-09-30 2019-04-16 2019-10-08 2019-05-28 2019-10-09 2019-06-05 2019-10-18 2019-09-09 2020-08-13 2020-07-05 Gestión Ambiental, que Implementation responde a la necesidad de la implementación inmediata de medidas solicitadas por los organismos multilaterales EC-EPM METRO QUITO- 142857-CS-INDV / Consultoría individual para la asistir a la Dirección 5: Technical Studies to Metropolitana de Políticas y IBRD / 88890 Support Project Posterior Individual Open 21,000.00 0.00 Cancelado 2019-11-08 2019-12-27 2020-01-17 2020-02-21 2020-08-19 Pleaneamiento de Movilidad Implementation de la Secretaría de Movilidad en la reestructuración de rutas de transporte público EC-EPM METRO QUITO- 142863-CS-INDV / Consultoría individual para asistir a la Dirección 5: Technical Studies to Metropolitana de Políticas y IBRD / 88890 Support Project Posterior Individual Open 70,000.00 0.00 En ejecución 2019-11-08 2020-02-14 2019-12-27 2020-01-17 2020-02-21 2020-08-19 Pleaneamiento de la Movilidad Implementation de la Secretaría de Movilidad en las negociaciones de la reestructuración de rutas. EC-EPM METRO QUITO- 142865-CS-INDV / Consultoría individual para asistir a la Dirección Metropolitana de Políticas y 5: Technical Studies to Planeamiento de la Movilidad IBRD / 88890 Support Project Posterior Individual Open 32,000.00 0.00 En ejecución 2019-11-08 2020-02-14 2019-12-27 2020-01-17 2020-02-21 2020-08-19 de la Secretaría de Movilidad Implementation en los sistemas de información geográficos orientadas al transporte público. EC-EPM METRO QUITO- 142868-CS-INDV / Consultoría individual para apoyo técnico a la implementación del 5: Technical Studies to componente AT en la IBRD / 88890 Support Project Posterior Individual Open 21,000.00 0.00 En ejecución 2019-11-08 2020-02-14 2019-12-27 2020-01-17 2020-02-21 2020-08-19 Dirección Metropolitana de Implementation Políticas y Planeamiento de la Movilidad de la Secretaría de Movilidad. Especialista en transporte urbano (modelador) EC-EPM METRO QUITO- 134941-CS-CDS / Asesoría 5: Technical Studies to Selección directa para la Selección del Operador IBRD / 82850 Support Project Posterior Direct 200,000.00 200,000.00 Firmado 2019-11-15 2020-02-06 2019-11-20 2020-03-03 2020-01-24 2020-05-08 2020-07-22 de consultores de la Primera Línea del Metro Implementation de Quito EC-EPM METRO QUITO- 159747-CS-CDS / Consultoría individual para la 5: Technical Studies to asesoría Técnica para la Selección directa IBRD / 88890 Support Project Posterior Direct 35,000.00 0.00 En ejecución 2020-02-14 2020-02-14 2020-02-24 2020-04-06 2020-04-29 2020-10-26 definición del Plan de de consultores Implementation Reestructuración de la Red de Rutas de Transporte Público del DMQ EC-EPM METRO QUITO- 202137-CS-INDV / Consultoría individual para el apoyo en los procesos, análisis y evaluación de la 5: Technical Studies to viabilidad financiera del IBRD / 88890 Support Project Posterior Individual Direct 7,000.00 0.00 En ejecución 2020-11-04 2020-11-11 2020-11-14 2020-12-05 2021-01-09 2021-07-08 Proyecto que permita la toma Implementation de decisiones y definición sobre el proceso de contratación e implementación del Sistema Inteligente de Transporte EC-EPM METRO QUITO- 202141-CS-INDV / Asesoría técnica para el apoyo en la implementación de 5: Technical Studies to Ejecución consultorías contratadas y a IBRD / 88890 Support Project Posterior Individual Direct 50,000.00 0.00 2020-11-04 2020-11-14 2020-12-05 2021-01-09 2021-07-08 pendiente contratar para la Implementation implementación del sistema integrado de transporte público del MDMQ EC-EPM METRO QUITO- 202139-CS-INDV / Asistencia técnica para la 5: Technical Studies to implementación de los IBRD / 88890 Support Project Posterior Individual Direct 28,000.00 0.00 Cancelado 2020-11-06 2020-11-16 2020-12-07 2021-01-11 2021-07-10 Sistemas Inteligentes de Implementation Transporte en la Empresa Pública Metropolitna de Transporte de Pasajeros Quito Page 4