PROCUREMENT PLAN (Textual Part) Project information: The Gambia, Electricity Restoration and Modernization Project, P163568 Project Implementation agency: National Water and Electricity Company NAWEC Date of the Procurement Plan: February 2017 Period covered by this Procurement Plan: February 2018 to December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Gambian Public Procurement Authority Act 2014, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable Other Relevant Procurement Information. PROCUREMENT Gambia, The : Gambia Electricity Restoration and Modernization Project PLAN General Information Country: Gambia, The Bank’s Approval Date of the Original Procurement Plan: 2018-02-28 2020-07-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163568 GPN Date: 2018-04-18 Project Name: Gambia Electricity Restoration and Modernization Project Loan / Credit No: IDA / V1120, IDA / D3090, IDA / D6530 Executing Agency(ies): NATIONAL WATER AND ELECTRICITY COMPANY WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GERMP/WORKS/C1/01 / Design, Supply, Installation, On-grid solar PV with Request for Open - Operation and Maintenance IDA / D3090 Prior Multi Stage 28,400,000.00 0.00 Canceled 2018-08-09 2018-08-14 2018-10-23 2019-02-04 2019-10-01 2021-03-24 storage Proposals International of a Solar PV Plant with storage GM-NAWEC-77938-CW-RFP Transmission and / Design and Build of distribution (T&D) Request for Open - Single Stage - One IDA / D3090 Prior 12,000,000.00 0.00 Canceled 2018-09-21 2018-11-13 2018-12-07 2019-07-22 2018-12-07 2020-01-28 2018-09-26 2018-11-13 2019-02-15 2019-03-17 2019-04-21 2020-10-12 Transmission Infrastructure restoration and Proposals International Envelope between Brikama and Kotu modernization GERMP/WORKS/C1/01BIS / Design, Supply, Installation, On-grid solar PV with Open - Single Stage - Two Operation and Maintenance IDA / V1120 Prior Request for Bids 28,400,000.00 0.00 Canceled 2018-11-26 2019-02-11 2019-02-11 2018-12-01 2019-04-22 2019-07-05 2019-08-09 2021-01-30 storage International Envelope of a Solar PV Plant with Storage GM-NAWEC-88924-CW-RFP / Lamin Koto - Diabugu Transmission and Batapa : 33kv line with distribution (T&D) Open - Single Stage - One Under distribution network and IDA / D3090 Prior Request for Bids 10,000,000.00 0.00 2019-01-17 2020-07-13 2019-01-22 2019-03-05 2019-04-04 2019-05-09 2019-11-05 restoration and International Envelope Review secondary substations for modernization Sami and Sandu districts villages GM-NAWEC-93509-CW-RFQ Urgent institutional support Request for Single Stage - One / Clearing of corridor for IDA / V1120 Post Limited 3,945.00 3,834.34 Signed 2019-10-27 2019-02-12 2019-12-22 2019-03-06 2020-06-19 for sector turnaround Quotations Envelope Solar PV Plant GM-NAWEC-141971-CW- Urgent institutional support Request for Single Stage - One RFQ / Pegging Perimeter of IDA / D3090 Post Limited 3,580.00 3,482.49 Signed 2019-10-29 2019-02-04 2019-12-24 2019-02-06 2020-06-21 for sector turnaround Quotations Envelope Solar PV Plant GM-NAWEC-141979-CW- Pending Urgent institutional support Request for Single Stage - One RFQ / Fencing of Solar PV IDA / D3090 Post Limited 52,475.00 0.00 Implementat 2019-12-03 2020-01-28 2020-07-26 for sector turnaround Quotations Envelope Plant ion GM-NAWEC-143327-CW- RFP / Design, Supply, Under On-grid solar PV with Request for Open - Single Stage - Two Installation, Operation and IDA / V1120 Prior 28,400,000.00 0.00 Implementat 2019-11-01 2019-11-28 2020-01-17 2020-05-07 2020-01-17 2019-11-06 2019-12-10 2020-03-27 2020-06-09 2020-07-14 2022-01-05 storage Proposals International Envelope Maintenance of a Solar PV ion Plant with Storage GM-NAWEC-153230-CW- Transmission and Under RFB / Design and Build of distribution (T&D) Open - Single Stage - One IDA / D3090 Prior Request for Bids 19,900,000.00 0.00 Implementat 2018-11-13 2019-01-29 2019-01-29 2020-02-05 2018-11-18 2019-04-09 2019-05-09 2019-06-13 2020-12-04 Transmission Infrastructure restoration and International Envelope ion between Brikama and Kotu modernization Page 1 GM-NAWEC-179863-CW- Transmission and RFB / GBA Secondary Pending distribution (T&D) Open - Single Stage - One substations upgrade (design, IDA / D3090 Post Request for Bids 3,200,000.00 0.00 Implementat 2020-07-01 2020-07-06 2020-08-17 2020-09-16 2020-10-21 2021-04-19 restoration and International Envelope supply and installation ion modernization contract) GM-NAWEC-182428-CW- Pending Urgent actions to support Request for Single Stage - One RFQ / Rehabilitate 5 IDA / D6530 Post Limited 80,000.00 0.00 Implementat 2020-07-13 2020-09-07 2021-03-06 the COVID-19 response Quotations Envelope existing boreholes ion GM-NAWEC-182426-CW- Pending RFQ / Intervention boreholes Urgent actions to support Request for Single Stage - One IDA / D6530 Post Limited 200,000.00 0.00 Implementat 2020-07-12 2020-09-06 2021-03-05 and treatment within the COVID-19 response Quotations Envelope ion existing facilities GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Under GERMP/GOODS/C4/07 / Urgent institutional support Request for Single Stage - One IDA / V1120 Post Limited 50,000.00 0.00 Implementati 2017-09-02 2018-10-16 2017-10-28 2018-04-26 Vehicle for Project Purpose for sector turnaround Quotations Envelope on GERMP/GOODS/C4/06 / Urgent institutional support Single Stage - One IDA / V1120 Post Request for Bids Limited 225,600.00 225,600.00 Signed 2017-08-21 2017-09-29 2017-08-26 2017-10-07 2017-10-17 2017-11-06 2017-10-23 2018-03-12 2018-03-06 2018-09-08 Replacement of Streetlights for sector turnaround Envelope GM-NAWEC-72939-GO-RFB Transmission and / Supply of 31,000 distribution (T&D) Open - Single Stage - One IDA / D3090 Post Request for Bids 1,300,000.00 1,088,586.62 Signed 2018-08-15 2019-02-22 2018-08-20 2019-02-27 2018-10-01 2019-04-15 2018-10-31 2019-06-13 2019-02-01 2019-08-09 2019-10-01 Prepayment Meters for restoration and International Envelope NAWEC modernization GERMP/GOODS/C3/06 / Under Procurement and Supply of Urgent institutional support Request for Single Stage - One IDA / V1120 Post Limited 61,000.00 0.00 Implementati 2018-12-08 2018-12-27 2019-02-02 2019-08-01 office equipment for GERMP for sector turnaround Quotations Envelope on PMU and IMS Project Team GM-NAWEC-88520-GO-RFQ / Procurement and supply of Urgent institutional support Request for Single Stage - One IDA / V1120 Post Limited 10,000.00 5,578.28 Signed 2018-12-19 2019-02-27 2019-02-13 2019-03-27 2019-08-12 office stationery and for sector turnaround Quotations Envelope cartridges for GERMP PMU GM-NAWEC-88516-GO-RFQ / Procurement and supply of office furniture, Provisions Urgent institutional support Request for Single Stage - One IDA / V1120 Post Limited 40,000.00 37,439.21 Signed 2018-12-22 2018-12-04 2019-02-16 2018-12-18 2019-08-15 and Cleaning Materials for for sector turnaround Quotations Envelope GERMP new office and IMS Project office GERMP/GOODS/03/09 / Urgent institutional support Request for Single Stage - One Procurement and Supply of IDA / V1120 Post Limited 50,000.00 0.00 Canceled 2019-02-24 2019-04-21 2019-10-18 for sector turnaround Quotations Envelope Vehicle for PMU GM-NAWEC-129781-GO-DIR Urgent institutional support / Procurement, supply and IDA / D3090 Post Direct Selection Direct 150,000.00 150,000.00 Signed 2019-09-18 2019-10-29 2019-09-23 2019-10-29 2019-10-28 2019-11-13 2020-04-25 for sector turnaround installation of Streetlights Transmission and GM-NAWEC-180789-GO- Pending distribution (T&D) Open - Single Stage - One RFB / Procurement of IDA / D3090 Post Request for Bids 1,500,000.00 0.00 Implementati 2020-06-30 2020-07-05 2020-08-16 2020-09-15 2020-10-20 2021-04-18 restoration and International Envelope 30,000 prepayment meters on modernization Page 2 GM-NAWEC-182159-GO-DIR / Supply and installation of 233 2000L and 112 of Under Urgent institutional support 5000L water tanks with IDA / D3090 Prior Direct Selection Direct 440,000.00 0.00 Implementati 2020-06-29 2020-07-04 2020-08-08 2021-02-04 for sector turnaround associated plumbing on materials and accessories by Plastico Industrials. GM-NAWEC-182430-GO- Pending Urgent actions to support Request for Single Stage - One RFQ / Supply of Hand wash IDA / D6530 Post Limited 207,000.00 0.00 Implementati 2020-07-13 2020-09-07 2021-03-06 the COVID-19 response Quotations Envelope materials on GM-NAWEC-182421-GO- Pending Urgent actions to support Request for Single Stage - One RFQ / Supply of Water IDA / D6530 Post Limited 120,000.00 0.00 Implementati 2020-07-19 2020-09-13 2021-03-12 the COVID-19 response Quotations Envelope Tanker (vehicle) on GM-NAWEC-182433-GO- Pending Urgent actions to support Request for Single Stage - One RFQ / Procurement and IDA / D6530 Post Limited 86,000.00 0.00 Implementati 2020-07-17 2020-09-11 2021-03-10 the COVID-19 response Quotations Envelope supply of 2 motor vehicles on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-NAWEC-72937-NC-RFB / Design, Supply and Urgent institutional support Open - Single Stage - One Installation of Integrated IDA / D3090 Prior Request for Bids 5,500,000.00 20,373,611.95 Signed 2018-09-03 2019-03-19 2018-09-08 2019-03-19 2018-10-20 2019-06-10 2018-11-19 2019-11-27 2019-08-01 2020-04-20 2020-01-28 for sector turnaround International Envelope Management System for NAWEC GERMP/NONCON/C3/08 / Procurement of a software Urgent institutional support IDA / V1120 Post Direct Selection Direct 2,000.00 840.00 Signed 2018-09-06 2019-09-13 2018-09-11 2019-09-13 2018-10-16 2019-09-22 2019-04-14 for monitoring and tracking for sector turnaround procurement activities GM-NAWEC-179869-NC-DIR Under / Extension of IMS system Urgent institutional support IDA / D3090 Prior Direct Selection Direct 1,700,000.00 0.00 Implementati 2020-06-17 2020-07-16 2020-06-22 2020-07-27 2021-01-23 by inclusion of water-related for sector turnaround on modules GM-NAWEC-182431-NC- Pending Urgent actions to support Request for Single Stage - One RFQ / Communications IDA / D6530 Post Limited 16,000.00 0.00 Implementati 2020-07-13 2020-09-07 2021-03-06 the COVID-19 response Quotations Envelope (stickers, stationery, internet on GM-NAWEC-182211-NC- Pending Urgent actions to support Request for Single Stage - One RFQ / Leasing of Water IDA / D6530 Prior Limited 900,000.00 0.00 Implementati 2020-07-19 2020-09-13 2021-03-12 the COVID-19 response Quotations Envelope Tankers for refilling of tanks on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GERMP/SERVICES/C4/04 / Urgent institutional support Quality And Cost- Open - Recruitment of Service IDA / V1120 Prior 1,700,000.00 2,617,838.00 Signed 2016-08-03 2018-03-12 2016-08-24 2016-10-07 2018-03-14 2016-11-04 2017-02-20 2016-12-04 2017-01-08 2018-03-19 2017-02-12 2017-10-24 2018-02-12 for sector turnaround Based Selection International Contractor GERMP/SERVICES/C4/02 / Feasibility Study for Urgent institutional support Quality And Cost- Open - Transmission Modernization IDA / V1120 Prior 655,000.00 902,128.47 Signed 2017-08-02 2018-08-03 2017-08-23 2017-10-06 2017-11-03 2017-12-07 2017-12-03 2019-08-13 2018-01-07 2019-05-30 2018-03-13 2018-04-03 2019-03-13 for sector turnaround Based Selection International Project in The Greater Banjul Area Page 3 GERMP/SERVICES/C4/05 / Urgent institutional support Quality And Cost- Open - IDA / V1120 Post 340,000.00 428,502.38 Signed 2017-04-26 2017-03-07 2017-05-17 2017-06-30 2017-06-14 2017-07-28 2017-08-31 2017-08-27 2017-09-15 2017-10-01 2017-11-24 2018-01-22 2018-01-22 2019-01-22 Solar Feasibility Study for sector turnaround Based Selection International Consultant GM-NAWEC-73512-CS-CQS Urgent institutional support IDA / V1120 Post Qualification Open - National 50,000.00 0.00 Canceled 2018-09-03 2018-09-24 2018-11-07 2018-12-07 2019-01-08 2019-07-07 / ESIA for Solar Plant for sector turnaround Selection GERMP/SERVICES/C3/10 / Urgent institutional support Quality And Cost- Open - IDA / V1120 Prior 750,000.00 0.00 Canceled 2018-09-10 2018-09-20 2018-10-01 2018-10-04 2018-11-14 2018-12-12 2019-01-11 2019-02-15 2019-03-22 2020-03-21 Electricity Road Map Update for sector turnaround Based Selection International GM-NAWEC-82968-CS-CQS Consultant Urgent institutional support / Additional Local Finance IDA / V1120 Post Qualification Open - National 30,000.00 110,260.80 Signed 2018-11-13 2018-11-07 2018-12-04 2019-01-17 2019-01-14 2019-02-16 2019-03-01 2019-03-23 2019-03-07 2019-09-19 for sector turnaround Resources Selection GM-NAWEC-99366-CS-CQS Consultant Urgent institutional support Under / ESIA for Laminkoto IDA / V1120 Post Qualification Open - National 50,000.00 0.00 2019-02-11 2019-02-07 2019-03-04 2019-04-17 2019-02-05 2019-05-17 2019-04-24 2019-06-21 2019-12-18 for sector turnaround Implementation Diabugu Line Network Selection GM-NAWEC-100229-CS- Urgent institutional support Least Cost Open - QCBS / Recruitment of IDA / V1120 Post 150,000.00 40,563.00 Signed 2019-02-20 2019-03-26 2019-03-13 2019-04-17 2019-04-26 2019-06-12 2019-05-24 2019-08-08 2019-06-23 2019-10-04 2019-07-28 2019-11-06 2019-09-01 2019-12-11 2020-02-28 for sector turnaround Selection International External Auditor for GERMP GERMP/SERVICES/C3/10BIS Urgent institutional support Quality And Cost- Open - / Electricity Road Map IDA / V1120 Post 750,000.00 619,550.00 Signed 2019-05-03 2019-05-02 2019-05-24 2019-07-07 2018-01-11 2019-08-04 2019-07-31 2019-09-03 2019-09-03 2019-10-08 2019-10-09 2019-11-12 2019-11-01 2020-11-11 for sector turnaround Based Selection International Update GERMP/SERVICES/C3/02 / Consultant Urgent institutional support Open - Under RAP implementation support IDA / V1120 Post Qualification 125,000.00 0.00 2019-09-04 2019-11-21 2019-09-25 2020-03-26 2019-11-08 2019-12-08 2020-01-12 2020-07-10 for sector turnaround International Implementation for Solar Selection GM-NAWEC-166470-CS-CQS Consultant Urgent institutional support Open - Under / RAP for Laminkoto IDA / D3090 Post Qualification 15,000.00 0.00 2020-03-31 2020-04-30 2020-04-21 2020-06-02 2020-06-04 2020-07-04 2020-08-08 2021-02-04 for sector turnaround International Implementation Diabugu Lines Selection GM-NAWEC-181510-CS-CQS / Recruitment of Consultant Consultant Urgent institutional support to Implement Gender-Based IDA / D6530 Post Qualification Limited 50,000.00 0.00 Under Review 2020-07-07 2020-07-14 2020-07-21 2020-08-20 2020-09-24 2021-03-23 for sector turnaround Violence Prevention and Selection Response (GBV) Activities GERMP/SERVICES/C4/01 / Urgent institutional support Quality And Cost- Open - Owner's Engineer for IDA / V1120 Prior 1,000,000.00 0.00 Canceled 2018-08-15 2018-08-13 2018-09-05 2018-09-05 2018-10-19 2019-11-11 2018-11-16 2020-01-13 2018-12-16 2020-03-31 2019-01-20 2019-05-01 2020-04-30 for sector turnaround Based Selection International GERMP GERMP/SERVICES/C4/01BIS Urgent institutional support Quality And Cost- Open - Pending / Owner's Engineer for IDA / D3090 Prior 1,500,000.00 0.00 2020-07-20 2020-08-10 2020-09-23 2020-10-21 2020-11-20 2020-12-25 2021-01-29 2022-01-29 for sector turnaround Based Selection International Implementation GERMP INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GERMP/SERVICES/C3/04 / Individual Consultants for Urgent institutional support IDA / V1120 Post Direct Selection Direct 50,000.00 81,512.00 Signed 2018-04-25 2018-04-03 2018-05-05 2018-05-07 2018-07-09 2018-05-17 2019-01-05 NAWEC - Procurement for sector turnaround Specialist GERMP/SERVICES/C3/03 / Individual Individual Consultants for Urgent institutional support IDA / V1120 Post Consultant Limited 100,000.00 0.00 Canceled 2018-04-25 2018-04-30 2018-05-21 2018-06-25 2018-12-22 NAWEC, PIU - Procurement for sector turnaround Selection Specialist Page 4 GERMP/SERVICES/C3/06 / Individual Individual Consultant for Urgent institutional support IDA / V1120 Post Consultant Limited 100,000.00 0.00 Canceled 2018-04-25 2018-04-30 2018-05-21 2018-06-25 2018-12-22 NAWEC, PIU-Social for sector turnaround Selection Specialist GERMP/SERVICES/C3/05 / Individual Individual Consultant for Urgent institutional support IDA / V1120 Post Consultant Limited 100,000.00 0.00 Canceled 2018-04-25 2018-04-30 2018-05-21 2018-06-25 2018-12-22 NAWEC, PIU-Environmental for sector turnaround Selection Specialist GM-NAWEC-73522-CS-INDV Individual Urgent institutional support / Recruitment of FM IDA / V1120 Post Consultant Open 110,000.00 1,800.00 Signed 2018-08-15 2018-09-04 2018-10-03 2018-09-28 2018-10-24 2018-10-01 2018-11-11 2018-10-01 2019-05-10 for sector turnaround Specialist Selection GM-NAWEC-73528-CS-INDV Individual Urgent institutional support / Recruitment of IDA / V1120 Prior Consultant Open 100,000.00 1,764.04 Signed 2018-08-14 2018-09-20 2018-10-02 2018-10-08 2018-10-23 2019-07-12 2018-11-27 2018-11-19 2019-05-26 for sector turnaround Procurement Specialist Selection GERMP/SERVICES/C4/06 / Individual Urgent institutional support Recruitment of International IDA / V1120 Prior Consultant Open 185,000.00 433,520.00 Signed 2018-08-15 2018-09-14 2018-10-03 2018-11-01 2018-10-24 2018-11-13 2018-11-28 2018-11-01 2019-05-27 for sector turnaround Procurement Specialist Selection GERMP/SERVICES/C3/11 / Individual Urgent institutional support MOPE Safeguard Study - IDA / V1120 Post Consultant Open 50,000.00 44,362.03 Signed 2018-08-27 2018-10-15 2018-10-15 2018-12-03 2018-11-05 2018-12-12 2018-12-10 2018-12-31 2019-06-08 for sector turnaround Preparation ESMF and RPF Selection GERMP/SERVICES/C3/08 / Individual Recruitment of an Urgent institutional support IDA / V1120 Post Consultant Open 100,000.00 0.00 Canceled 2018-08-15 2018-09-05 2018-10-03 2018-10-24 2018-11-28 2019-05-27 Environmental Specialist for for sector turnaround Selection NAWEC PIU GERMP/SERVICES/C3/09 / Individual Urgent institutional support Recruitment of a Social IDA / V1120 Post Consultant Open 100,000.00 0.00 Canceled 2018-08-15 2018-09-05 2018-10-03 2018-10-24 2018-11-28 2019-05-27 for sector turnaround Specialist for NAWEC PIU Selection GM-NAWEC-73614-CS-INDV Individual / Consultant for the Urgent institutional support IDA / V1120 Post Consultant Open 4,000.00 0.00 Canceled 2018-08-15 2018-10-03 2018-10-24 2018-11-28 2019-05-27 preparation of Project for sector turnaround Selection Implementation Manual GERMP/SERVICES/C3/07 / Consultant to prepare the Urgent institutional support IDA / V1120 Post Direct Selection Direct 4,000.00 3,907.82 Signed 2018-09-06 2018-09-13 2018-09-16 2018-11-20 2018-09-18 2019-05-19 Project Implementation for sector turnaround Manual GERMP/SERVICES/C1/11 / On-grid solar PV with IDA / V1120 Post Direct Selection Direct 50,000.00 14,310.95 Signed 2018-11-12 2018-11-13 2018-11-22 2018-11-14 2019-01-26 2018-12-03 2019-07-25 ESIA for Solar Plant storage GM-NAWEC-87163-CS-INDV Individual Urgent institutional support / Safeguard expert to IDA / D3090 Post Consultant Limited 90,000.00 174,800.00 Signed 2018-11-14 2018-10-23 2018-11-19 2018-11-05 2018-12-10 2018-11-12 2019-01-14 2018-11-12 2019-07-13 for sector turnaround support PMU ESO and SSO Selection Individual GM-NAWEC-93511-CS-INDV Urgent institutional support IDA / V1120 Post Consultant Limited 50,000.00 21,836.23 Signed 2019-01-07 2019-01-11 2019-01-12 2019-01-14 2019-02-02 2019-01-31 2019-03-09 2019-02-05 2019-09-05 / RAP for Solar PV Plant for sector turnaround Selection GM-NAWEC-93513-CS-INDV Individual / ESIA for Lamin koto - Urgent institutional support IDA / V1120 Post Consultant Limited 50,000.00 0.00 Canceled 2019-01-17 2019-01-14 2019-01-22 2019-02-12 2019-03-19 2019-09-15 Diabugu MV line and for sector turnaround Selection Distribution Network GM-NAWEC-102978-CS-CDS Urgent institutional support / Individual Consultant for IDA / D3090 Post Direct Selection Direct 10,500.00 9,785.62 Signed 2019-03-28 2019-03-26 2019-04-07 2019-03-11 2019-06-11 2019-03-20 2019-12-08 for sector turnaround implementation support Page 5 GM-NAWEC-120002-CS-CDS Urgent institutional support IDA / D3090 Post Direct Selection Direct 165,000.00 2,627.90 Signed 2019-06-28 2019-08-01 2019-07-08 2019-08-02 2019-09-11 2019-09-01 2020-03-09 / Project Coordinator for sector turnaround GM-NAWEC-152000-CS-CDS Urgent institutional support / IMS Customer Data and IDA / D3090 Post Direct Selection Direct 350,000.00 341,463.50 Signed 2020-01-02 2020-01-09 2020-01-12 2020-01-09 2020-03-17 2020-03-17 2020-09-13 for sector turnaround Network Data Collection GM-NAWEC-179861-CS- Individual Urgent institutional support Under INDV / Recruitment of IDA / D3090 Post Consultant Open 100,000.00 0.00 2020-06-24 2020-06-22 2020-08-12 2020-09-02 2020-10-07 2021-04-05 for sector turnaround Implementation Water Engineer Selection GM-NAWEC-179856-CS- Individual Urgent institutional support Under INDV / Recruitment of IDA / D3090 Post Consultant Open 100,000.00 0.00 2020-06-24 2020-06-23 2020-08-12 2020-09-02 2020-10-07 2021-04-05 for sector turnaround Implementation Gender Focal Person Selection GM-NAWEC-180734-CS-CDS / Financial Consultancy – Power Purchase Agreements Urgent institutional support IDA / D3090 Post Direct Selection Direct 75,000.00 75,000.00 Signed 2020-06-24 2020-06-19 2020-07-04 2020-06-19 2020-09-07 2020-06-23 2021-03-06 for the National Water and for sector turnaround Electricity Company Limited (NAWEC) GM-NAWEC-180787-CS- INDV / Individual Individual Urgent institutional support Under International Procurement IDA / D3090 Prior Consultant Open 361,240.00 0.00 2020-07-21 2020-07-14 2020-09-08 2020-09-29 2020-11-03 2021-05-02 for sector turnaround Implementation and contract management Selection consultant Page 6