PROCUREMENT PLAN (Textual Part) Project information: [Haiti] [P163490 - Haiti Rural Accessibility & Resilience Project Project Implementation agency: [UCE] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. • PROCUREMENT Haiti : Haiti Rural Accessibility & Resilience Project PLAN General Information Country: Haiti Bank’s Approval Date of the Original Procurement Plan: 2019-02-27 2021-04-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163490 GPN Date: Project Name: Haiti Rural Accessibility & Resilience Project Loan / Credit No: IDA / D3230, IDA / D6690 Unité Centrale d'Exécution Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AON-001-PARR/2019 / Travaux de Traitement de Improving Resilience of Points critiques dans les Single Stage - One 2019-12- IDA / D3230 Transport Connecting A priori Appel d'offres Open - National 2,583,580.00 0.00 Annulé 2019-02-21 2019-03-01 2019-04-10 2019-05-02 2019-05-26 Départements du Sud, des Envelope 06 Infrastructure Nippes et de l'Ouest en quatre (4) Lots DC-001-PARR/2019 / Protection du Pont de Trou du Improving Resilience of Single Stage - One 2020-05- Nord dans la Commune du IDA / D3230 Transport Connecting A posteriori Demande de prix Limited 965,430.00 441,342.20 Signé 2019-02-28 2019-11-11 2019-05-05 2020-01-20 Envelope 01 même nom dans le Infrastructure Département du Nord'est DC-002-PARR/2019 / Protection de la Route Vieux Improving Resilience of Single Stage - One 2020-03- Bourg d'Aquin - L'Asile dans IDA / D3230 Transport Connecting A posteriori Demande de prix Limited 848,450.00 0.00 Annulé 2019-08-24 2019-10-20 Envelope 28 la localité de Kapol dans les Infrastructure Nippes DC-005-PARR/2019 / Protection et Réhabilitation de Improving Resilience of Deux (2) Ponts dans les Single Stage - One 2020-03- IDA / D3230 Transport Connecting A posteriori Demande de prix Limited 965,430.00 543,462.50 Signé 2019-08-26 2019-11-11 2019-10-22 2020-01-20 Communes de Grand-Goâve Envelope 30 Infrastructure et de Petit-Goâve (Département de l'Ouest) en deux (2) Lots AON-001-PARR/2020 / Protection de la RD22 Improving Resilience of Single Stage - One En cours 2020-07- (Tronçon Miragoane - Petite IDA / D3230 Transport Connecting A posteriori Appel d'offres Open - National 1,563,000.00 0.00 2019-10-14 2020-06-02 2019-10-19 2019-11-30 2020-08-07 2019-12-30 2020-09-28 2020-02-03 Envelope d'exécution 12 Rivière de Nippes) en deux Infrastructure lots DC-003-PARR/2019 / Improving Resilience of Single Stage - One 2020-06- Protection du Pont de Port-a- IDA / D3230 Transport Connecting A posteriori Demande de prix Limited 980,620.00 744,248.50 Signé 2019-11-27 2019-12-17 2020-01-06 2020-04-27 Envelope 14 Piment Infrastructure DC-004-PARR/2019 / Improving Resilience of Single Stage - One 2020-08- Protection de trois (3) Ponts IDA / D3230 Transport Connecting A posteriori Demande de prix Limited 831,600.00 534,415.50 Signé 2019-12-18 2019-12-17 2020-02-12 2020-04-27 Envelope 10 sur la RN2 Infrastructure AON-002-PARR/2020 / Traitement des points Single Stage - One En cours 2021-06- critiques sur le tronçon La IDA / D3230 Enhancing Rural Connectivity A posteriori Appel d'offres Open - National 6,124,225.00 0.00 2020-10-06 2020-10-06 2020-10-08 2020-11-19 2020-12-04 2020-12-28 Envelope d'exécution 06 Colline - Fond-des-Blancs en sept (7) lots AOI-001-PARR/2021 / Travaux de traitement des Single Stage - One En cours 2021-08- points critiques sur le tronçon IDA / D6690 Enhancing Rural Connectivity A priori Appel d'offres Open - International 9,257,469.56 0.00 2020-12-21 2020-12-26 2021-02-06 2021-02-21 2021-03-17 Envelope d'exécution 24 de route Dessalines - Saint- Michel en cinq (5) lots AON-003-PARR/2021 / Traitement des points Single Stage - One En cours 2021-08- critiques: Tronçon de Route IDA / D3230 Enhancing Rural Connectivity A posteriori Appel d'offres Open - National 4,732,550.00 0.00 2020-12-16 2020-12-28 2020-12-21 2021-02-01 2021-02-16 2021-03-12 Envelope d'exécution 19 Petit Trou - Baradères en quatre (4) lots AON-004-PARR/2020 / TRAITEMENT DE POINTS CRITIQUES SUR LE TRONÇON THIOTTE -- ANSE-À-PITRES Single Stage - One En cours 2021-10- IDA / D3230 Enhancing Rural Connectivity A posteriori Appel d'offres Open - National 2,334,124.00 0.00 2021-01-18 2021-01-22 2021-01-23 2021-03-06 2021-03-27 2021-04-25 Lot 1: Thiotte - Boucan Envelope d'exécution 02 Guillaume Lot 2: Boucan Guillaume - Anse-à-Pitres DP-002-PARR/2021 / RECONSTRUCTION D’OUVRAGES ENDOMMAGÉS Single Stage - One En cours 2021-10- IDA / D3230 Enhancing Rural Connectivity A posteriori Demande de prix Limited 2,109,490.00 0.00 2021-03-06 2021-03-01 2021-05-10 PAR LE CYCLONE LAURA DANS Envelope d'exécution 17 LE SUD-EST EN QUATRE (4) LOTS AON-005-PARR/2021 / Protection et Réhabilitation de Single Stage - One En cours 2021-11- IDA / D3230 Enhancing Rural Connectivity A posteriori Appel d'offres Open - National 3,251,760.00 0.00 2021-03-18 2021-04-05 2021-03-23 2021-05-04 2021-05-25 2021-06-23 quatre (4) Ponts sur la RN2 et Envelope d'exécution 30 la RD25 AON-006-PARR/2021 / Construction et Protection de Single Stage - One En attente 2021-12- quatre (4) Dalots dans les IDA / D3230 Enhancing Rural Connectivity A posteriori Appel d'offres Open - National 1,119,055.00 0.00 2021-03-25 2021-03-30 2021-05-11 2021-06-01 2021-06-30 Envelope d'exécution 07 Départements de l'Artibonite et du Sud AOI-001-UCE-2018-PBCA / Travaux de construction de quatre ponts dans les départements du Centre, du Single Stage - One 11,694,283.3 9,683,783.4 2020-09- Nord et de l'Artibonite (Ponts IDA / D6690 Enhancing Rural Connectivity A priori Appel d'offres Open - International Signé 2017-11-14 2021-04-13 2018-06-18 2018-08-24 2018-08-24 2018-12-19 2021-04-13 2019-03-28 2019-03-28 Envelope 5 9 18 sur les rivières Bonbon, Rio Frio, Wallondry et l'Attalaye) Lot 1 - Rio Frio, Bonbon Lot 2 - Wallondry, L'Attalaye Page 1 DC-001-BCA/2019 / Request for Traitement des Points Quotations - Small critiques dans les Communes Single Stage - One En attente 2020-08- IDA / D6690 Enhancing Rural Connectivity A posteriori Demande de prix Limited Works 1,350,342.49 0.00 2019-12-18 2020-02-12 de Saint-Michel de l'Attalaye Envelope d'exécution 10 (Emergency) SPD - et de Saint Raphaël en deux Competitive (2) lots Request for DC-003-BCA/2019 / Quotations - Small CONSTRUCTION D’UN DALOT Single Stage - One En attente 2020-10- IDA / D6690 Enhancing Rural Connectivity A posteriori Demande de prix Limited Works 339,829.40 0.00 2019-12-17 2020-04-27 4(3.5×4) SUR LA RIVIÈRE Envelope d'exécution 04 (Emergency) SPD - BRETELLE Competitive DC002/BCA/2018 / Construction de trois dalots en trois Lots sur la Ravine Sèche, la Rivière Yayou et la Request for Single Stage - One En attente 2019-05- Rivière Vébrine sur le tronçon IDA / D6690 Enhancing Rural Connectivity A posteriori Demande de prix Limited Quotations (Non 711,635.31 0.00 2018-05-30 2018-11-16 Envelope d'exécution 15 de route Dessalines - St- Bank-SPD) Michel - Lot 1 A - Ravine Sèche, Lot 1 B - Riviere Yayou, Lot 1 C - Riviere Vebrine DC003/UCE/BCA/2018 / Travaux de traitement des Request for points critiques sur le tronçon Single Stage - One En attente 2020-02- IDA / D6690 Enhancing Rural Connectivity A posteriori Demande de prix Limited Quotations (Non 2,178,143.84 0.00 2018-09-24 2019-09-11 de route Titanyen - Saut- Envelope d'exécution 18 Bank-SPD) d'eau - Lot 1, Lot 2, Lot 3, Lot4, Lot 5 GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO-001-PARR/2019 / Single Stage - One En attente IDA / D3230 Project Management A posteriori Demande de prix Limited 40,000.00 0.00 2019-03-09 2019-04-23 2019-06-22 Acquisition de vehicule Envelope d'exécution GO-002-PARR/2021 / Acquisition de 500 mini kits énergétiques solaires pour un Promoting Sustainable Single Stage - One En attente échantillon de ménages IDA / D3230 A posteriori Demande de prix Limited 45,000.00 0.00 2021-05-08 2021-06-22 2021-12-19 Mobility Development Envelope d'exécution devant participer à l'enquête Origine-Destination au Cap- Haïtien NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ED-001-PARR/2019 / Services en vue de Collecte de Improving Resilience of Passation de En attente Données Vidéo Aérienne à IDA / D3230 Transport Connecting A posteriori marché de gré à Direct 16,000.00 0.00 2019-04-25 2019-04-26 2019-04-30 2019-06-04 d'exécution l'aide de Drones au Cap- Infrastructure gré Haïtien ED-003-BCA/2019 / RECRUTEMENT D'UNE ÉQUIPE Passation de LOCALE POUR EFFECTUER LA Promoting Sustainable En cours IDA / D3230 A posteriori marché de gré à Direct 8,268.50 0.00 2019-07-09 2019-07-16 2019-07-14 2019-07-24 2019-08-05 COLLECTE DE DONNÉES À Mobility Development d'exécution gré L'AIDE DE L’APPLICATION COLLECTOR AU CAP-HAÏTIEN ED-004-PARR/2020 / Élaboration Plan de mobilité, exécution des travaux d'entretien et de réparation de Improving Resilience of Passation de routes rurales, et IDA / D3230 Transport Connecting A priori marché de gré à Direct 15,932,700.00 15,932,700.00 Signé 2019-10-28 2019-11-04 2019-10-31 2019-11-05 2019-11-13 2019-12-31 2022-03-31 renforcement des capacités Infrastructure gré communautaires dans les Départements du Sud-Est, des Nippes et du Sud ED-005-PARR/2020 / Services de Laboratoire en Appui à la Mission de Improving Resilience of Passation de Supervision des Travaux de En cours IDA / D3230 Transport Connecting A posteriori marché de gré à Direct 76,900.00 0.00 2020-04-29 2020-04-10 2020-05-02 2020-05-13 2021-02-10 Construction des Ponts Rio d'exécution Infrastructure gré Frio, Bonbon, Walondry et L'Attalaye de la Boucle Centre- Artibonite MTPTC/UCE/PARR-20/INV- 001 / Fourniture et Single Stage - One En attente IDA / D3230 Project Management A posteriori Demande de prix Limited 37,000.00 0.00 2021-03-21 2021-05-01 2021-10-08 implémentation d'un système Envelope d'exécution de comptabilité informatisée CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DP-003-PARR/2019 / Sélection fondée Improving Resilience of Réalisation d'une Etude de sur les IDA / D3230 Transport Connecting A posteriori Open - International 100,000.00 272,550.36 Signé 2019-02-25 2019-03-11 2019-04-15 2019-06-06 2019-04-29 2020-11-05 2019-05-24 2020-11-30 2019-11-24 vulnérabilité (Pilote) du qualifications des Infrastructure Réseau Routier en Haiti consultants DP-001-PARR/2019 / Audit Sélection au IDA / D3230 Project Management A posteriori Open - National 100,000.00 78,548.76 Signé 2019-02-22 2019-01-13 2019-02-23 2019-02-25 2019-03-08 2019-03-11 2019-03-25 2019-03-26 2019-04-26 2019-04-05 2019-04-29 2019-04-28 2019-08-01 2022-04-27 Financier du PARR moindre coût DP-004-PARR/2019 / Etudes Sélection fondée de mise en place d'un système sur les En cours IDA / D3230 Project Management A posteriori Open - International 120,000.00 0.00 2019-02-26 2019-03-19 2019-04-14 2019-04-19 2019-05-13 2019-11-13 d'Archivage électronique à qualifications des d'exécution l'UCE consultants Page 2 DP-002-PARR/2019 / Recrutement d'une Firme ou d'un Opérateur pour Sélection fondée Cartographie et Plans de IDA / D3230 Enhancing Rural Connectivity A priori sur la qualité et le Open - International 600,000.00 0.00 Annulé 2019-03-13 2019-03-27 2019-04-21 2019-06-02 2019-06-23 2019-07-10 2019-08-07 2020-02-07 Mobilité en Zone Rurale dans coût les Départements du Sud, du Sud-est et des Nippes Sélection fondée QC-001-PARR/2021 / Promoting Sustainable sur les En cours Enquête Origine-Destination IDA / D3230 A posteriori Limited 200,000.00 0.00 2020-11-10 2020-11-23 2020-11-24 2020-12-07 2020-12-09 2020-12-20 2021-02-21 Mobility Development qualifications des d'exécution au Cap-Haïtien consultants DP-005-PARR/2021 / ÉTUDES ROUTIÈRES SUR 107 Sélection fondée En cours KM DE ROUTES SUR LE IDA / D3230 Enhancing Rural Connectivity A priori sur la qualité et le Open - International 802,500.00 0.00 2021-02-01 2021-04-01 2021-02-22 2021-03-29 2021-04-26 2021-05-17 2021-06-10 2021-07-09 2022-01-05 d'exécution TRONÇON THIOTTE / coût MARIGOT DP-006-PARR/2021 / Assistance au Maitre d’Ouvrage dans le cadre de la Improving Resilience of Sélection fondée En cours reconstruction de quatre IDA / D3230 Transport Connecting A priori sur la qualité et le Open - International 1,700,000.00 0.00 2021-03-22 2021-04-01 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2023-08-22 d'exécution ouvrages d’art dans les Infrastructure coût départements de l’Ouest, du Sud et des Nippes QC-002-PARR/2021 / ÉTUDE Sélection fondée DE PRÉFAISABILITÉ POUR Promoting Sustainable sur les En cours AMÉLIORER LA MOBILITÉ SUR IDA / D3230 A posteriori Limited 200,000.00 0.00 2021-04-23 2021-04-23 2021-05-07 2021-05-22 2021-06-03 2021-11-30 Mobility Development qualifications des d'exécution LES PRINCIPAUX CORRIDORS consultants DE PORT-AU-PRINCE DP001/UCE/BCA/2019 / Supervision des travaux de construction de quatre ponts dans les départements du Sélection fondée Centre, du Nord et de En attente IDA / D6690 Enhancing Rural Connectivity A posteriori sur la qualité et le Open - International 1,281,328.82 0.00 2018-08-21 2018-09-04 2019-04-01 2019-05-27 2019-07-05 2019-08-09 2019-10-31 2021-05-23 l'Artibonite (Ponts sur les d'exécution coût rivières Bonbon, Rio Frio, Wallondry et l'Attalaye) - Lot 1 - Rio Frio, Bonbon Lot 2 - Wallondry, l'Attalaye INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDV-001-PARR/2019 / En attente Responsable conformité et IDA / D3230 Project Management A posteriori Individuel Open 36,000.00 0.00 2019-02-11 2019-03-14 2019-03-17 2019-04-01 2019-09-30 d'exécution des aspects de S&E à l'UCE INDV-003-PARR/2019 / En cours Spécialiste en Genre et en IDA / D3230 Project Management A posteriori Individuel Open 27,000.00 0.00 2019-02-11 2019-03-13 2019-03-14 2019-03-17 2019-04-01 2019-09-30 d'exécution Sauvegardes Sociales à l'UCE INDV-004-PARR/2019 / En cours Assistant en Passation des IDA / D3230 Project Management A posteriori Individuel Open 24,000.00 0.00 2019-02-11 2019-02-12 2019-03-14 2019-03-17 2019-04-01 2019-09-30 d'exécution Marchés à l'UCE INDV-005-PARR/2019 / En cours IDA / D3230 Project Management A posteriori Individuel Open 13,200.00 0.00 2019-02-11 2019-02-14 2019-03-14 2019-03-17 2019-04-01 2019-09-30 Assistant Administratif à l'UCE d'exécution INDV-006-PARR/2019 / En cours IDA / D3230 Project Management A posteriori Individuel Open 27,000.00 0.00 2019-02-11 2019-02-12 2019-03-14 2019-03-17 2019-04-01 2019-09-30 Comptable Sénior à l'UCE d'exécution INDV-007-PARR/2019 / En cours IDA / D3230 Project Management A posteriori Individuel Open 27,000.00 0.00 2019-02-11 2019-02-14 2019-03-14 2019-03-17 2019-04-01 2019-09-30 Informaticien à l'UCE d'exécution INDV-008-PARR/2019 / En attente IDA / D3230 Project Management A posteriori Individuel Open 30,000.00 0.00 2019-02-11 2019-03-14 2019-03-17 2019-04-01 2019-09-30 Specialiste en Suivi-Evaluation d'exécution ED-002-PARR/2019 / Assistance technique pour le Sélection de En attente renforcement de l’UCE dans la IDA / D3230 Project Management A posteriori consultants par Direct 131,000.00 0.00 2019-06-20 2019-06-30 2019-07-25 2020-05-20 d'exécution gestion des sauvegardes entente directe environnementales et sociales INDV-002-PARR/2019 / Chargé de Projet du PARR à IDA / D3230 Project Management A posteriori Individuel Open 48,000.00 0.00 Annulé 2019-02-11 2020-11-06 2019-03-14 2019-03-17 2019-04-01 2019-09-30 l'UCE INDV-002-PARR/2021 / En attente Chargé de Projet du PARR à IDA / D3230 Project Management A posteriori Individuel Open 54,000.00 0.00 2020-11-06 2020-12-25 2021-01-15 2021-02-19 2022-02-19 d'exécution l'UCE INDV-001-PARR/2021 / En attente Spécialiste en Sauvegardes IDA / D3230 Project Management A posteriori Individuel Open 24,300.00 0.00 2020-11-06 2020-12-25 2021-01-15 2021-02-19 2022-02-19 d'exécution Environnementales Page 3