84111 VAHIP AF PROJECT-PERIOD 2011-2014 PROCUREMENT PLAN 2014 Unit: USD Activities Procurement Implementing Start-complete Revised Implementing Code Counterpart Contract type Bank review No Name method Unit time time AHI fund Improving the Technical Quality of Surveillance and B1 - - Response System from central to local levels B1.5 Assessment on the infectious disease surveillances system Post-assessment in 11 project B1.5.2 24 - - CS/IC Lump sum post CPMU Q4/2013 Q1-2014 provinces Total B1.5 - - Strengthening behavioral change communication & risk B3 - - communication for emerging infectious diseases B3.2 Development of the toolkit for BCC and RC on EIDs B3.2.1 Development of RC toolkit Printing/production of RC B3.2.2 49 - - G/SH Lump sum post CPMU Q3-4/2013 Q1-2014 materials/toolkits for 11 provinces Printing and distribution of periodic document on human B3.2.4 51 - - G/SH Lump sum post CPMU 2013 Q1-2014 health and diseases control (GDPM is in charge) Total B3.2 - - B3.6 Assessment of BCC & RC impacts Post-assessment in 03 new and 03 B3.6.1 62 - - CS/CQS Lump sum post CPMU Q3-4/2013 Q1-2014 old provinces Develop documentary film about B3.6.5 65a - - CS/CQS Lump sum post CPMU Q3-4/2013 Q1-2014 the VAHIP project Total B3.6 - - Improving capacity for local B4 - - preventive medicine B4.5 Assessment on the development of the district preventive medicine model Assessment on the development B4.5.2 77 of the district preventive medicine - - CS/CQS Lump sum post CPMU Q3-4/2013 Q1-2014 model KH 2013 DA VAHIP, giai đoạn 2011-2014 - BQLDA TƯ và 11 BQLDA tỉnh/thành phố 1 Activities Procurement Implementing Start-complete Revised Implementing Code Counterpart Contract type Bank review No Name method Unit time time AHI fund Assessment and Development of B4.5.5 77c Scheme for Supporting District - Preventive Medicine level National Consultant (Assessment and Development of Scheme for B4.5.5.1 77c1 - - CS/CQS Lump sum post CPMU Q1-2/2013 Q1-2014 Supporting District Preventive Medicine level) Total B4. 5 - - Total B - - COMPONENT C: Project coordination, M&E and management C2 M&E Activities C2.2 M&E annual activities of PCU - MOH C2.2.6 86 Project phase out assessment - - CS/IC Lump sum post CPMU Q4/2013 Q1-2/2014 Total C2.2 - - Total Comp. C - - Total Comp. B and C - - KH 2013 DA VAHIP, giai đoạn 2011-2014 - BQLDA TƯ và 11 BQLDA tỉnh/thành phố 2