FEDERAL REPUBLIC OF NIGERIA Nigeria Erosion and Watershed Management Project (NEWMAP) PROCUREMENT PLAN I. GENERAL 1. Project information: Country: Nigeria Borrower: Federal Government of Nigeria Project Name: Nigeria Erosion and Watershed Management Project-(NEWMAP) Loan / Credit No.: PIA: National NEWMAP Coordinating Unit. 2. Bank’s approval Date of the procurement Plan: March, 2012 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments (US$ equivalent) 1. ICB and LIB (Goods and services other > 750,000.00 ALL than consultancy services) 2. NCB 50,000.00 ≤ 750,000.00 NONE 3. ICB (Works) > 5,000,000.00 ALL 4. NCB (Works) 200,000 ≤ 5,000,000.00 NONE 5 Shopping-Goods < 50,000.00 NONE 6 Shopping-Works < 100,000.00 NONE 7 Training, Workshops, Study Tours All Values Based on Annual Work Plans & Budgets 2. Prequalification. Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Shall apply 4. Reference to (if any) Project Operational/Procurement Manual: shall apply 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages with Methods and Time Schedule Procurement of Goods : 1 2 3 4 5 6 7 8 9 Re Contract Estimate Procure Prequalificati Domestic Review Expected Comments f. (Description) d ment on (yes/no) Preference by Bank Bid- No Cost Method (yes/no) (Prior / Post) Opening . US$’000 Date 1 Computer Systems, Office, software and Accessories Computers and 684 NCB NO NO POST June 7, Procureme Accessories, software (see 2012 nt by each remark of the 7 packages, Photo- Colum) SPMU & copiers, UPS, Printers FPMU is and Scanners, Fax estimated Machines, Laptops, at ( USD Stationeries, 85.5) Consumables, LAN, Telephony,Lasers Software Licenses and Application,. 2 Office Furniture’s and Equipment Computer workstations 680 NCB NO NO PRIOR June 7, Procureme and Office Furniture (see 2012 nt by each remark of the 7 Water Dispenser, Colum) SPMU & Refrigerators, FPMU is Airconditioners, estimated Tables, Chairs, etc at ( USD 85) 3 Operational Vehicles 4-WD Vehicles (32 1440 NCB NO NO PRIOR June 7, Procureme units) (see 2012 nt by each remark of the 7 Colum) SPMU & FPMU is estimated at (180USD 4 Generator 40KVA Sound-Proof 240 NS NO NO PRIOR June 7, Procureme Electricity Generating (see 2012 nt by each Set-Purchase and remark of the 7 Installation (8 units) Colum) SPMU & FPMU is estimated at (30 USD 5 Training Communication, Presentation, Media Equipment and materials, etc Multimedia 364 NS NO NO PRIOR June 7, Procureme Projectors, (see 2012 nt by each remark of the 7 Flip Chart Stands, Colum) SPMU & Boards, GSM FPMU is TV/Video/Radio/Reco estimated rders and Digital at (45.5 Cameras, Internet USD Facilities, GPS, Raincoats and Enumerators bags, Program information kit, Program posters Community oriented Implementation manual 6 Field Equipment Purchase of Weather 2,400 NCB NO NO PRIOR June 7, Procureme Monitoring Stations, (see 2012 nt by each GPSs, Laser Measures, remark of the 7 Measuring Wheels, 1- Colum) SPMU & 2km Range Radios and FPMU is other survey equipment estimated and tools to gauge and at (300 trace watershed, USD terrestrial carbon and water flow 7 Geographic Information System Purchase of GIS 3520 NCB NO NO PRIOR June 7, Procureme data/Satellite Imagery,, (see 2012 nt by each Overhead photography, remark of the 7 etc Colum) SPMU & FPMU is estimated at (440 USD Sub Total 9,328.00 Procurement of Civil Works 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procure Prequalificati Domestic Review Expected Comments No. (Description) Cost ment on (yes/no) Preference by Bank Bid- US$’000 Method (yes/no) (Prior / Post) Opening Date 1 Civil works, and 252,000.00 ICB NO YES PRIOR October Procureme maintenance of flood 12, 2012 nt by ICB and gully erosion sites for all 7 SPMU 2 Office accommodation 240,000 NS NO NO PRIOR July, 2012 for 7 SPMU & FPCU SUB TOTAL 252,240.00 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1 Consultant Services-QCBS- All Values ALL International 2 Consultant Services-QCBS-National > 200,000.00 ALL 3 Consultant Services-CQS < 200,000.00 NONE 4 Consultant Services-lC > 50,000.00 ALL 5 Consultant Services-lC < 50,000.00 ToR only but ALL 6 Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref. Description of Assignment Estimated Selection Review Expected Comments No. Method by Bank Proposals Cost. (Prior / Submission US$’000 Post) Date 1 Consultancy for the detailed 3,395.24 QCBS Prior On-going Consultancy for Engineering designs and data (see remark Priority sites collation for 35 sites Colum by each of the 7 SPMU (see each State Proc. Plan). 2 Consultancy for the supervision 6,824.47 QCBS Prior September Consultancy for of Civil Works for 35sites (see remark 2012 Priority sites Colum by each of the 7 SPMU (see each State Proc. Plan). 3 Consultancy for the RAP study 875.00 IC Prior On-going Consultancy for for 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at (25 USD. 4 Consultancy for the ESIA study 875.00 IC Prior On-going Consultancy for for 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at (25 USD. 5 Consultancy for the Socio- 875.00 IC Prior On-going Consultancy for Economic study 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at 25 USD per site 6 Consultancy for GIS data 875.00 IC Prior On-going Consultancy for collection and Mapping for 35 (see remark Priority sites sites Colum by each of the 7 SPMU is estimated at 75 USD per site 7 Consultancy for the detailed 3500.00 QCBS Prior August, 2012 Consultancy for Engineering designs and data (see remark 5 additional collation for additional 35sites Colum sites by each of the 7 SPMU is estimated at 100 USD per site 8 Consultancy for the detailed 2625.00 QCBS Prior June, 2013 Consultancy for ESIA, RAP and Socio (see remark 5 additional Economic Studies for Colum sites by each of additional 35 sites the 7 SPMU is estimated at 75 USD per site 9 Environmental engineering and 800 QCBS 9 design consultancy, 10 Procurement consultancy for 800 QCBS 10 June 1012 support of FPMU and SPMUs 11 M&E consultancy 400 QCBS 11 12 Consultancy for the support of 800.00 QCBS 12 Sept., 2012 Consultancy by SPMUs and FPMU (see remark each of the 7 Colum SPMU & FPMU is estimated at (100 USD 13 Consultancy for Legal Services 800.00 IC 13 Sept., 2012 Consultancy by each of the 7 (see remark SPMU & Colum FPMU is estimated at (100 USD 14 Consultancy for valuation and 3500.00 14 Sept., 2012 Consultancy by resettlement implementation (see remark each of the 7 Colum SPMU, to cover all sites is estimated at (500 USD per SPMU 15 Consultancy for Training and 1600.00 QCBS Prior August, 2012 Consultancy by Capacity Building (see remark each of the 7 Colum SPMU & FPMU is estimated at (200 USD 16 Consultancy-External Auditor 400.00 QCBS Prior March, 2013 Consultancy by (see remark FPMU to cover Colum each SPMU 17 Consultancy on Community 800.00 IC Prior Sept., 2012 Consultancy by consultation, Public Education (see remark each of the 7 and Erosion Management and Colum SPMU & awareness Techniques, FPMU is estimated at (100 USD Sub Total 27,744.71 IV. Implementing Agency Capacity Building Activities with Time Schedule 1. In this section the agreed Capacity Building Activities are listed with time schedule below; No. Expected outcome / Estimated Estimated Start Date Com Activity Description Cost US$ Duration m ‘000 e n t s A. TRAINING 1 3. Nos. Training courses for August 2012 Capacity Building PMU staff; Project activities for each Coordinator, Procurement of the 7 SPMU & Specialist, and financial mgt, FPMU is estimated at (90 USD M&E, Environmental specialists, Communication, Livelihood, Engineering 720.00(see 2WKS, specialists remark Colum each 2 Training of project finance August 2012 Capacity Building staff(FMS, APA, FO, IA) on 160.00(see activities for each flexible accounting software remark Colum 1wk of the 7 SPMU & FPMU is estimated at (20 USD B. WORKSHOP 3 September Capacity Building 2012 activities for each of the 7 SPMU & Capacity Building for key 240.00(see FPMU is estimated stakeholders remark Colum 3 days at (30 USD 4 September, Capacity Building 2012 activities for each of the 7 SPMU & 160(see FPMU is estimated ICT Training remark Colum 1 wk at (20 USD 5 Various Capacity Building activities for each Professional of the 7 SPMU & Seminars/Workshops/ 120.00(see FPMU is estimated subscriptions remark Colum Various at (15 USD 6 September Capacity Building 2 Days Sensitization/ activities for each 2012 Workshop for State and Local of the 7 SPMU & Govt. Officials on erosion and 200.00(see FPMU is estimated watershed management remark Colum 2 days at (25 USD 7 October Capacity Building 3 Day workshop for Line activities for each 2012 Ministries and MDAs on of the 7 SPMU & addressing and prevention of 240.00(see FPMU is estimated Land Degradation remark Colum 3- days at (30 USD 8 3 Day workshop for local October Capacity Building Govt. Focal Persons and 2012 activities for each Community Erosion watch of the 7 SPMU & Dogs on prevention of erosion FPMU is estimated 240.00(see at (30 USD and land degradation remark Colum 3-days 9 2013 Capacity Building activities for each Capacity Building on use of of the 7 SPMU & Metrological and GPS 200.00(see FPMU is estimated Equipment remark Colum 5-days at (25 USD C. STUDY/TOURS 10 240.00(see Various October Capacity Building remark Colum times 2012 activities for each Baseline survey/ Community of the 7 SPMU & needs assessment and capacity FPMU is estimated building at (30 USD 11 240.00(see Various August, Capacity Building remark Colum times 2012 activities for each Sensitization/ Awareness of the 7 SPMU & creation of NEWMAP in the FPMU is estimated 18 LGA at (30 USD 12 160.00(see WB and Capacity Building remark Colum FAO to activities for each Participation in watershed of the 7 SPMU & determine studies organized by the world FPMU is estimated bank and FAO at (20 USD 13 240.00(see Various December, Capacity Building remark Colum 2012 activities for each of the 7 SPMU & Launching of ESIA and RAP FPMU is estimated for priority sites at (30 USD 14 160.00(see Various Oct., 2012 Capacity Building remark Colum activities for each of the 7 SPMU & FPMU is estimated livelihood studies at (20 USD 15 160.00(see Various World Bank Capacity Building Participation in remark Colum activities for each determined Biodiversity/forest carbon of the 7 SPMU & study organized by the World FPMU is estimated Bank at (20 USD 16 120.00(see 4-days each July 2012 Capacity Building remark Colum activities for each Recognizance survey of of the 7 SPMU & Project sites (Erosion and FPMU is estimated Watershed) at (15 USD 17 2480.00(see 4-wks February., Capacity Building remark Colum 2013 activities for each of the 7 SPMU & International Training and FPMU is estimated study tours at (310 USD 18 Various World Bank Capacity Building determined activities for each Attendance of World Bank of the 7 SPMU & Organized training, meetings, 800.00(see FPMU is estimated seminar and workshops remark Colum at (100 USD Sub Total 6,880.00 PROCUREMENT Nigeria : Nigeria Erosion and Watershed Management Project PLAN General Information Country: Nigeria Banks Approval Date of the Original Procurement Plan: 2017-06-12 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-10-09 Project ID: P124905 GPN Date: Project Name: Nigeria Erosion and Watershed Management Project Loan / Credit No: IDA / 51050 Executing Agency(ies): ABIA STATE PROJECT MANAGEMENT UNIT, ENUGU SPMU, EDO SPMU, CROSS RIVER STATE NEWMAP SPMU, EBONYI STATE NEWMAP SPMU, ANAMBRA SPMU, Akwa Ibom SPMU, Delta SPMU, KOGI SPMU, KANO SPMU, Gombe SPMU, Plateau SPMU, Sokoto SPMU, NEWMAP - Federal Projects Management Unit WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ABS/NEWMAP/NCB/CW/14/02 Component 1: Erosion and / Amuda Achara and Amuzukwu Single Stage - One Under IDA / 51050 Watershed Management Post Request for Bids Open - National 3,013,000.00 0.00 2013-11-08 2014-02-05 2014-01-07 2014-01-28 2014-02-18 2014-03-25 2015-11-15 Gully Erosion Remediation Envelope Implementation Infrastructure Investments Works ABS/NEWMAP/NCB/CW/17/01 / Umuda Isingwu/Ibeku Complex Component 1: Erosion and Gully Erosion Remediation Single Stage - One Under IDA / 51050 Watershed Management Prior Request for Bids Open - National 5,200,000.00 0.00 2017-02-13 2017-02-27 2017-03-20 2017-04-10 2017-05-08 2018-08-31 Works and Umuogele Umuakwu Envelope Implementation Infrastructure Investments Nsulu Gully Erosion Remediation Works ABS/NEWMAP/NCB/CW/17/03 / Procurement and Component 1: Erosion and Single Stage - One Pending implementation of Household and IDA / 51050 Watershed Management Post Request for Bids Open - National 400,000.00 0.00 2017-12-06 2017-12-13 2018-01-10 2018-01-24 2018-02-14 2018-06-14 Envelope Implementation community water harvesting for Infrastructure Investments seven Multiple sites. ABS/NEWMAP/NS/CW/16/03 / Renovation of New Office Complex (Paintings, electricals, Component 4: Project Request for Single Stage - One Pending plumbing, perimeter fencing, IDA / 51050 Post Open - National 100,000.00 0.00 2017-06-12 2017-07-24 2017-08-23 Management Quotations Envelope Implementation transformer, roofing, room restructuring, ashphalting, drainage, etc) ABS/NEWMAP/NS/CW/16/01 / Component 1: Erosion and Provision for the Routine Request for Single Stage - One Pending IDA / 51050 Watershed Management Post Open - National 100,000.00 0.00 2017-12-25 2018-03-19 2019-03-19 Maintenance of the Civil Works Quotations Envelope Implementation Infrastructure Investments at the Completed Sites ABS/NEWMAP/NCB/CW/16/02 / Emergency and Temporary Component 1: Erosion and Request for Single Stage - One Pending Stabilization of Gullies and Slide IDA / 51050 Watershed Management Post Open - National 100,000.00 0.00 2017-07-17 2017-08-19 2019-01-25 Quotations Envelope Implementation Management for the New Wave Infrastructure Investments of Gullies ENS/NEWMAP/WKS/NCB/14/01 Component 1: Erosion and A / Reclammation,channelling Single Stage - One Pending IDA / 51050 Watershed Management Prior Request for Bids Open - National 1,700,000.00 0.00 2014-02-03 2014-02-24 2014-03-13 2014-04-21 2014-05-12 2015-06-16 and remmediation works at 9th Envelope Implementation Infrastructure Investments Mile Erosion site ENS/NEWMAP/WKS/NCB/17/01 / Reclammation,channelling and Component 1: Erosion and Single Stage - One Pending remmediation works at IDA / 51050 Watershed Management Post Request for Bids Open - National 3,938,000.00 0.00 2016-11-01 2016-11-14 2016-12-20 2017-02-22 2017-04-05 2018-05-10 Envelope Implementation Umuavulu Abor Gully Erosion Infrastructure Investments site ENS/NEWMAP/WKS/NCB/17/02 / Reclammation,channeling and Component 1: Erosion and Single Stage - One Pending remediation works at Agbaja IDA / 51050 Watershed Management Post Request for Bids Open - National 12,166,000.00 0.00 2017-03-14 2017-04-24 2017-05-24 2017-06-14 2017-06-28 2018-08-02 Envelope Implementation Ngwo, Udi-Ozalla and Enugu Infrastructure Investments Ngwo Gully Erosion Sites ENS/NEWMAP/WKS/NCB/17/03 / Reclammation,channeling and Component 1: Erosion and remediation works at Onuiyi Single Stage - One Pending IDA / 51050 Watershed Management Post Request for Bids Open - National 6,269,000.00 0.00 2017-10-10 2017-10-10 2017-11-09 2017-11-30 2018-01-11 2019-02-15 Nsukka-Alor, Imilike Etiti and Envelope Implementation Infrastructure Investments Ngene Owele-Ohaji Gully Erosion Sites. ENS/NEWMAP/WKS/NCB/16/01 Component 1: Erosion and / Rehabilitation of Okwojo Ngwo Single Stage - One Pending IDA / 51050 Watershed Management Post Request for Bids Open - National 200,000.00 0.00 2017-08-15 2017-08-15 2017-09-14 2017-10-24 2017-11-14 2018-07-12 Community buster pump water Envelope Implementation Infrastructure Investments station/reticulation ENS/NEWMAP/WKS/NCB/16/02 Component 1: Erosion and Single Stage - One Pending / Household and community IDA / 51050 Watershed Management Post Request for Bids Open - National 500,000.00 0.00 2017-07-13 2017-08-12 2017-09-02 2017-09-23 2017-10-14 2018-01-12 Envelope Implementation water harvesting Infrastructure Investments NG-EDO SPMU-17119-CW-RFB / Reclamation, channeling and Component 1: Erosion and remediation works at Ekehuan Single Stage - One Pending IDA / 51050 Watershed Management Prior Request for Bids Open - National 2,500,000.00 0.00 2017-06-06 2017-06-06 2018-09-10 2018-12-30 2019-01-15 2020-01-14 Road Gully/West Moat Flood and Envelope Implementation Infrastructure Investments Gully Erosion catchment area Phase 1 in Benin City NG-EDO SPMU-17117-CW-RFB / Reclamation, channeling and Component 1: Erosion and Single Stage - One Pending remediation works at Oshiobugie IDA / 51050 Watershed Management Prior Request for Bids Open - International 42,500,000.00 0.00 2012-07-13 2012-07-13 2014-08-27 2014-12-18 2015-01-22 2017-01-20 Envelope Implementation Flood and Gully Erosion site at Infrastructure Investments Auchi NG-EDO SPMU-17125-CW-RFB / Reclamation, channeling and Component 1: Erosion and Single Stage - One Pending remediation works at NEW Flood IDA / 51050 Watershed Management Prior Request for Bids Open - National 18,700,000.00 0.00 2012-07-13 2012-07-13 2017-01-09 2017-02-21 2017-03-24 2018-09-21 Envelope Implementation and Gully Erosion Sites in Edo Infrastructure Investments State-EWU and IBORE NG-EDO SPMU-17122-CW-RFB / Reclamation, channeling and Component 1: Erosion and Single Stage - One remediation works at NEW Flood IDA / 51050 Watershed Management Prior Request for Bids Open - International 52,000,000.00 0.00 Under Review 2012-07-13 2012-07-13 2017-04-25 2017-05-30 2017-04-25 2017-07-04 2019-07-03 Envelope and Gully Erosion Sites in Edo Infrastructure Investments State-GAPIONA AND URORA NG-EDO SPMU-17128-CW-RFB / Reclamation, channeling and remediation works at NEW Flood Component 1: Erosion and Single Stage - One and Gully Erosion Sites in Edo IDA / 51050 Watershed Management Prior Request for Bids Open - International 25,600,000.00 0.00 Under Review 2012-07-13 2012-07-13 2017-07-19 2017-08-18 2017-09-01 2019-08-30 Envelope State-OGISO, EDO COLLEGE, Infrastructure Investments AAU, Emu, Igbe Quarters and Fugar-Agenebode road NG-EDO SPMU-17126-CW-RFB Component 1: Erosion and / Reclamation, channeling and Single Stage - One Pending IDA / 51050 Watershed Management Post Request for Bids Open - National 2,500,000.00 0.00 2012-07-13 2012-07-13 2017-04-10 2017-06-08 2017-07-04 2017-12-19 remediation works at Ikpoba Hill Envelope Implementation Infrastructure Investments Gully Erosion site CRS/NEWMAP/WKS/NCB/14/01- 001 / Ikot Ekpo Gulley Component 1: Erosion and Single Stage - One Pending Construction Works (Preliminary IDA / 51050 Watershed Management Post Request for Bids Open - National 394,730.00 0.00 2013-04-08 2013-04-08 2013-04-08 2014-03-03 2014-05-09 2017-03-31 Envelope Implementation Earthworks and Soil Infrastructure Investments Stabilization) CRS/NEWMAP/WKS/NCB/14/01- Component 1: Erosion and 002 / Atakpa Gulley Construction Single Stage - One Pending IDA / 51050 Watershed Management Post Request for Bids Open - National 3,545,240.00 0.00 2013-04-08 2013-04-08 2013-04-08 2014-03-03 2014-05-09 2017-03-31 (Preliminary Earthworks and Soil Envelope Implementation Infrastructure Investments Stabilization) Page 1 CRS/NEWMAP/WKS/NCB/14/01- 003 / Nyagasang Gulley Component 1: Erosion and Single Stage - One Pending Construction Works (Preliminary IDA / 51050 Watershed Management Post Request for Bids Open - National 2,204,030.00 0.00 2013-04-07 2013-04-07 2013-04-07 2014-03-03 2014-05-09 2017-03-31 Envelope Implementation Earthworks and Soil Infrastructure Investments Stabilization) CRS/NEWMAP/WKS/NCB/14/01- 004 / Edim Otop Gulley Component 1: Erosion and Single Stage - One Pending Construction Works (Preliminary IDA / 51050 Watershed Management Post Request for Bids Open - National 6,385.00 0.00 2017-02-24 2017-02-24 2017-03-10 2017-03-10 2017-09-15 2018-10-12 Envelope Implementation Earthworks and Soil Infrastructure Investments Stabilization) - Additional Works CRS/NEWMAP/WKS/NCB/14/02 / Ikot Anwatim Gulley Component 1: Erosion and Single Stage - One Pending Construction Works (Preliminary IDA / 51050 Watershed Management Post Request for Bids Open - National 6,818,150.00 0.00 2013-04-29 2013-04-29 2013-06-10 2013-06-10 2013-10-21 2017-03-31 Envelope Implementation Earthworks and Soil Infrastructure Investments Stabilization) CRS/NEWMAP/WKS/NCB/16/02 Component 1: Erosion and / Ikot Nkebre Gulley Construction Single Stage - One Under IDA / 51050 Watershed Management Post Request for Bids Open - National 7,419,350.00 0.00 2016-09-06 2016-11-15 2016-09-06 2016-11-08 2016-12-13 2016-11-08 2017-05-02 2019-03-21 Works (Preliminary Earthworks Envelope Implementation Infrastructure Investments and Soil Stabilization) CRS/NEWMAP/WKS/NCB/16/03 / Lemna/Fed Agric. Gulley Component 1: Erosion and Single Stage - One Under Construction Works (Preliminary IDA / 51050 Watershed Management Post Request for Bids Open - National 1,741,980.00 0.00 2016-06-22 2016-11-15 2016-06-22 2016-12-13 2017-03-14 2017-05-02 2019-03-21 Envelope Implementation Earthworks and Soil Infrastructure Investments Stabilization) CRS/NEWMAP/WKS/NS/15/01 Component 1: Erosion and / Post Construction Maintenance Pending IDA / 51050 Watershed Management Post Direct Selection Direct 170,000.00 0.00 2017-09-12 2017-09-12 2018-02-20 2018-03-22 Works at Ikot Ekpo Intervention Implementation Infrastructure Investments Erosion site CRS/NEWMAP/WKS/NS/15/02 Component 1: Erosion and / Post Construction Maintenance Pending IDA / 51050 Watershed Management Post Direct Selection Direct 130,000.00 0.00 2017-09-12 2017-09-12 2018-01-30 2018-03-22 Works at Atakpa Intervention Implementation Infrastructure Investments Erosion site CRS/NEWMAP/WKS/NS/15/03 Component 1: Erosion and / Post Construction Maintenance Pending IDA / 51050 Watershed Management Post Direct Selection Direct 150,000.00 0.00 2017-09-12 2017-09-12 2018-01-30 2018-03-22 Works at Nyagasang Intervention Implementation Infrastructure Investments Erosion site CRS/NEWMAP/WKS/NS/14/05 Component 1: Erosion and / Post Construction Maintenance Pending IDA / 51050 Watershed Management Post Direct Selection Direct 180,000.00 0.00 2017-10-15 2017-10-15 2018-03-26 2018-04-24 Works at Ikot Anwatim Implementation Infrastructure Investments Intervention Erosion site CRS/NEWMAP/WKS/NCB/16/05 Component 1: Erosion and / Construction and Installation of Single Stage - One Pending IDA / 51050 Watershed Management Post Request for Bids Open - National 300,000.00 0.00 2017-11-13 2017-11-13 2017-12-27 2017-12-27 2018-04-16 2020-03-11 Household and Community Rain Envelope Implementation Infrastructure Investments Water Harvesting Facilities NG-EDO SPMU-17112-CW-RFB / Reclamation, channeling and Component 1: Erosion and remediation works at Queen Ede Single Stage - One Pending IDA / 51050 Watershed Management Prior Request for Bids Open - National 19,850,000.00 0.00 2012-07-13 2012-07-13 2014-07-22 2014-08-20 2014-09-22 2016-03-18 Secondary School Flood and Envelope Implementation Infrastructure Investments Gully Erosion catchment area in Benin City EBNEWMAP/NS/CW/17/01/1 / Component 1: Erosion and Request for Single Stage - One Pending Renovation of SPMU Office IDA / 51050 Watershed Management Post Open - National 31,750.00 0.00 2017-03-06 2017-08-18 2018-11-09 Quotations Envelope Implementation Annex Infrastructure Investments EBNEWMAP/NCB/CW/17/01/02 / PROCUREMENT OF Component 1: Erosion and Single Stage - One Pending CONTRACTOR FOR THE IDA / 51050 Watershed Management Post Request for Bids Open - National 350,000.00 0.00 2017-03-01 2017-03-06 2017-04-17 2017-06-02 2017-07-14 2018-01-10 Envelope Implementation CONSTRUCTION OF Infrastructure Investments RAINWATER HARVESTING EBNWEMAP/ICB/CW/16/03 / REMEDIATION WORKS AT IYI- OKWU - ABAKILIKI INT'L Component 1: Erosion and Single Stage - One Under MARKET - ODUNUKWE - IDA / 51050 Watershed Management Prior Request for Bids Open - National 50,786,880.00 0.00 2016-03-15 2016-04-28 2016-06-09 2017-02-10 2017-03-31 2017-06-22 Envelope Implementation NKALIKI HATCHERY Infrastructure Investments ROAD/EBIA RIVER-IYIUDELE FLOOD SITES - EBONYI STATE ANS/NEWMAP/WKS/NCB/14- Component 1: Erosion and Single Stage - One Pending 02 / Construction of Erosion IDA / 51050 Watershed Management Prior Request for Bids Open - National 3,800,000.00 0.00 2013-11-13 2014-01-27 2014-02-24 2014-05-01 2014-11-27 2015-11-22 Envelope Implementation Control at Umudunu, Abagana Infrastructure Investments ANS/NEWMAP/WKS/ICB/17-03 Component 1: Erosion and / Construction of Erosion Control Single Stage - One Pending IDA / 51050 Watershed Management Prior Request for Bids Open - International 2,500,000.00 0.00 2016-12-05 2017-02-14 2017-04-17 2017-05-17 2017-06-28 2019-06-18 at St. Thomas Aquinas/Neros Envelope Implementation Infrastructure Investments Plaza, Ifite Awka ANS/NEWMAP/WKS/NCB/14- Component 1: Erosion and Single Stage - One Pending 03 / Construction of Erosion IDA / 51050 Watershed Management Prior Request for Bids Open - National 2,500,000.00 0.00 2013-11-13 2014-01-27 2014-02-24 2014-05-01 2014-11-27 2015-11-22 Envelope Implementation Control at Amachalla, Awka Infrastructure Investments ANS/NEWMAP/WKS/NCB/14- Component 1: Erosion and Single Stage - One Pending 01 / Construction of Erosion IDA / 51050 Watershed Management Prior Request for Bids Open - National 1,700,000.00 0.00 2013-10-25 2013-11-13 2014-01-27 2014-02-24 2015-04-30 2016-04-24 Envelope Implementation Control at Omagba, Onitsha Infrastructure Investments ANS/NEWMAP/WKS/ICB/16-01 Component 1: Erosion and / Construction of Erosion Control Single Stage - One IDA / 51050 Watershed Management Prior Request for Bids Open - International 63,291,110.00 0.00 Under Review 2016-06-20 2016-09-02 2016-10-28 2016-10-28 2017-02-08 2017-03-22 2019-03-12 at Ugamuma-Obosi and Ndiagu- Envelope Infrastructure Investments Ikenga, Ogidi ANS/NEWMAP/WKS/ICB/16-02 Component 1: Erosion and / Construction of Erosion Control Single Stage - One IDA / 51050 Watershed Management Prior Request for Bids Open - International 63,291,110.00 0.00 Under Review 2016-06-02 2016-09-02 2016-10-28 2016-10-28 2017-02-02 2017-04-05 2019-03-26 at Abidi, Umuoji and Enugu- Envelope Infrastructure Investments Ukwu Erosion Site, Enugu-Ukwu ANS/NEWMAP/WKS/ICB/17-02 Component 1: Erosion and / Construction of Erosion Control Single Stage - One Under IDA / 51050 Watershed Management Prior Request for Bids Open - International 15,823,000.00 0.00 2016-06-19 2016-09-02 2016-10-28 2017-05-02 2017-02-02 2017-03-22 2019-03-12 at Ire-Obosi and Nkpor Flyover, Envelope Implementation Infrastructure Investments Onitsha - Phase 2 (Lot 2) ANS/NEWMAP/WKS/NS/17-02 / Renovation of Project Financial Component 1: Erosion and Request for Single Stage - One Pending Management Office Block - Flood IDA / 51050 Watershed Management Post Open - National 30,000.00 0.00 2017-05-29 2017-07-10 2017-08-09 Quotations Envelope Implementation Control and Construction and of Infrastructure Investments Overhead Tank ABS/NEWMAP/NCB/CW/14/01 Component 1: Erosion and / Umuezeukwu Gully Erosion Single Stage - One Under IDA / 51050 Watershed Management Prior Request for Bids Open - National 1,980,000.00 0.00 2013-11-08 2014-01-29 2014-02-26 2014-03-12 2014-04-23 2017-03-31 Remediation Works and Extra Envelope Implementation Infrastructure Investments Works EBSPMU/NCB/CW/14/01 / Component 1: Erosion and ONGOING REMEDIATION Single Stage - One Pending IDA / 51050 Watershed Management Prior Request for Bids Open - National 1,130,130.00 0.00 2014-01-08 2014-01-29 2014-02-01 2014-02-15 2014-03-29 2016-09-27 WORKS AT NGUZU EDDA SITE- Envelope Implementation Infrastructure Investments EBONYI STATE AKSPMU/WKS/NCB/17/01 / Component 1: Erosion and Construction of St. Luke's Single Stage - One Pending IDA / 51050 Watershed Management Prior Request for Bids Open - International 24,563.00 0.00 2017-05-25 2017-06-19 2017-07-24 2017-08-07 2017-10-06 2019-02-01 Hospital and Etim Umanah gully Envelope Implementation Infrastructure Investments erosion sites AKSPMU/WKS/NS/17/01 / Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 32.00 0.00 2017-03-06 2017-03-06 2017-03-06 Renovation of Office Building Management Quotations Envelope Implementation AKSPMU/WKS/NS/17/02 / Component 4: Project Request for Single Stage - One Pending Procurement and installation of IDA / 51050 Post Open - National 22.00 0.00 2017-03-06 2017-04-08 2017-04-29 Management Quotations Envelope Implementation 30kVA inverter and batteries Page 2 AKSPMU/WKS/NS/17/03 / Component 4: Project Request for Single Stage - One Pending Procurement and installation of IDA / 51050 Post Open - National 20.00 0.00 2017-03-06 2017-04-10 2017-05-10 Management Quotations Envelope Implementation internet facilities and subscription SOK/NEWMAP/WK/NS/001/17 Component 4: Project Single Stage - One Pending / Renovation of NEWMAP SPMU IDA / 51050 Post Request for Bids Open - National 70,000.00 0.00 2017-02-03 2017-02-10 2017-03-31 2017-04-21 2017-05-19 2017-07-18 Management Envelope Implementation office SOK/NEWMAP/WK/NS/002/17 Component 4: Project Single Stage - One Pending / Drilling of borehole and IDA / 51050 Post Request for Bids Open - National 45,000.00 0.00 2017-02-03 2017-02-03 2017-03-14 2017-06-03 2017-06-17 2017-09-15 Management Envelope Implementation overhead tank SKO/NEWMAP/WK/NS/003/07 / Degraded land rehabilitation, Component 4: Project Single Stage - One Pending IDA / 51050 Post Request for Bids Open - National 300,000.00 0.00 2017-02-14 2017-02-21 2017-03-07 2017-03-21 2017-04-11 2017-07-10 Establishment of wood lots and Management Envelope Implementation orchards ANS/NEWMAP/WKS/NCB/17- Component 1: Erosion and 01 / Re-tendering of Erosion Single Stage - One IDA / 51050 Watershed Management Prior Request for Bids Open - National 10,000,000.00 0.00 Under Review 2017-06-23 2017-07-31 2017-09-15 2017-10-31 2017-12-05 2019-11-25 Control Works at Umudunu, Envelope Infrastructure Investments Abagana AKS/PMU/EMERG/WKS/DIR/17 /01 / Construction of emergency Component 1: Erosion and Under intervention works at Etim IDA / 51050 Watershed Management Prior Direct Selection Direct 741,000.00 0.00 2017-09-12 2017-09-05 2017-09-14 2017-09-15 2017-09-22 2017-11-21 Implementation Umana gully Erosion site- Uyo, Infrastructure Investments Akwa Ibom State AKSPMU/CW/RFB/17/01 / Component 1: Erosion and Construction of St. Luke's Single Stage - One Pending IDA / 51050 Watershed Management Prior Request for Bids Open - International 24,563.00 0.00 2017-11-13 2017-11-27 2018-01-08 2018-01-29 2018-03-05 2019-02-04 Hospital and Etim Umanah gully Envelope Implementation Infrastructure Investments erosion sites AKSPMU/CW/RFQ/17/02 / Component 4: Project Request for Single Stage - One Pending Procurement and installation of IDA / 51050 Post Open - National 22.00 0.00 2017-10-14 2017-12-09 2018-06-07 Management Quotations Envelope Implementation 30kVA inverter and batteries AKSPMU/CW/RFQ/17/03 / Component 4: Project Request for Single Stage - One Pending Procurement and installation of IDA / 51050 Post Open - National 20.00 0.00 2017-10-01 2017-11-26 2017-12-18 Management Quotations Envelope Implementation internet facilities and subscription GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ABS/NEWMAP/CP/GDS/17/01 / Community sub grants for management of Soil & Water conservation zones and Support Component 1: Erosion and Request for Single Stage - One Pending to communities & Line MDAs to IDA / 51050 Watershed Management Post Open - National 50,000.00 0.00 2017-03-28 2017-07-11 2017-08-20 Quotations Envelope Implementation establish nurseries, plant trees, Infrastructure Investments grasses of assorted indigenous species; construction of renno mattreasses and gabion boxes. ABS/NEWMAP/CP/GDS/16/02 / Sub-grants to community Component 1: Erosion and Request for Single Stage - One Pending associations on livelihood IDA / 51050 Watershed Management Post Open - National 338,000.00 0.00 2017-03-26 2017-08-08 2018-09-12 Quotations Envelope Implementation enhancements,employment and Infrastructure Investments skill acquisition ABS/NEWMAP/CP/GDS/17/04 / Community disaster risk Component 1: Erosion and Request for Single Stage - One Pending management activities for flood IDA / 51050 Watershed Management Post Open - National 100,000.00 0.00 2017-08-21 2017-09-04 2017-09-18 2017-09-25 2017-10-16 2018-01-24 Quotations Envelope Implementation and landslide/gully expansion for Infrastructure Investments prioritized sites. ABS/NEWMAP/NS/GDS/17/01 / Computers and Accessories, software packages, Photo- Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 130,000.00 0.00 Completed 2017-03-14 2017-05-30 2017-04-13 2017-07-29 2017-04-26 copiers, UPS, Printers and Management Quotations Envelope Scanners,Fax Machines, Laptops, etc ABS/NEWMAP/NS/GDS/17/02 / Office Furniture Water Dispenser, Refrigerators, Air conditioners, Tables, Chairs for the project Component 4: Project Request for Single Stage - One office. Procure office internet for IDA / 51050 Post Open - National 100,000.00 12,446.53 Completed 2017-03-21 2017-05-23 2017-04-13 2017-06-22 2017-04-26 Management Quotations Envelope Engineering design and supervision firm and basic office furniture and equipment for PMU and EDSF ABS/NEWMAP/NS/GDS/17/03 / 1Nos. 16- seater Bus for Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 210,000.00 0.00 2017-02-24 2017-04-14 2017-05-24 PMUand 2NOS 4 x4 2016 Management Quotations Envelope Implementation Pickup Van with bootcover. ABS/NEWMAP/NS/GDS/17/05 / Personal Protective Equipment for site works ( Cover alls, Component 4: Project Request for Single Stage - One Under IDA / 51050 Post Open - National 10,000.00 0.00 2017-06-19 2017-07-22 2017-08-19 helmets, safety boots, nose, eye Management Quotations Envelope Implementation and ear masks, rain coats, rain boots, etc ABS/NEWMAP/NS/GDS/17/07 / Component 4: Project Request for Single Stage - One Provide for ABIA NEWMAP IDA / 51050 Post Open - National 13,000.00 9,974.57 Completed 2017-06-10 2017-07-10 2017-04-18 2017-08-07 2017-05-03 Management Quotations Envelope branding products and activities. ABS/NEWMAP/NS/GDS/17/10 / Provision of 33KVA transformer Component 4: Project Request for Single Stage - One for NEWMAP OFFICE and IDA / 51050 Post Open - National 40,000.00 54,011.04 Completed 2017-03-27 2017-05-22 2017-05-08 2017-06-21 2017-05-09 Management Quotations Envelope Provision of 16KVA Generating set. ENS/NEWMAP/GDS/NS/17/01 / 4 ESRI ArcGIS software for desktop(single-user Licensed),4 Nos High speed Desktop Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 60,000.00 0.00 2017-02-15 2017-04-05 2017-05-05 computers, 4 Nos Image Management Quotations Envelope Implementation Processing software,1 No A0 Plotter ,1 terabyte external hard drive. ENS/NEWMAP/GDS/NS/17/02 / 3 Nos Steel shelves, office Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 50,000.00 2,084.99 Completed 2017-02-15 2017-04-07 2017-04-07 2017-04-28 2017-05-08 equipment and 1 No 2Hp Split Air Management Quotations Envelope Conditioner ENS/NEWMAP/GDS/NS/17/03 / Component 4: Project Request for Single Stage - One Office consumables and sundry IDA / 51050 Post Open - National 90,000.00 16,361.46 Completed 2017-02-15 2017-04-05 2017-04-28 2017-05-05 2017-05-17 Management Quotations Envelope items ENS/NEWMAP/GDS/NS/17/04 / Camera with all accessories inclusive of 2 Nos Batteries,Charger,cables and Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 18,000.00 0.00 2017-03-22 2017-05-03 2017-06-02 bag. 5 No Laptops, 12 Laptop Management Quotations Envelope Implementation bags, Printer inclusive of additional Refillable ink Cartridges and ink ENS/NEWMAP/GDS/NS/17/05 / Component 4: Project Request for Single Stage - One Pending Additional Procurement of IDA / 51050 Post Open - National 20,000.00 0.00 2017-03-22 2017-04-26 2017-05-26 Management Quotations Envelope Implementation software packages (Antivirus) Page 3 NG-EDO SPMU-17135-GO-RFQ / Procurement of Computer Component 4: Project Request for Single Stage - One Pending Systems, Office, software, ICT IDA / 51050 Post Open - National 20,000.00 0.00 2017-06-11 2017-07-09 2017-08-29 Management Quotations Envelope Implementation equiment, Inverter and battery bank, and office Consumables NG-EDO SPMU-17138-GO-RFQ / Office furniture's and Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 5,000.00 0.00 2017-06-11 2017-07-09 2017-07-20 Equipment, and electrical and Management Quotations Envelope Implementation electronics equipment NG-EDO SPMU-17143-GO-RFQ Component 4: Project Request for Single Stage - One Pending / procurement of 2 N0S.4-WD IDA / 51050 Post Open - National 400,000.00 0.00 2017-03-26 2017-04-14 2017-05-26 Management Quotations Envelope Implementation Pick up Vehicle and SUV. NG-EDO SPMU-17146-GO-RFQ / Procurement of Training Communication, Presentation, Media Equipment and materials, Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 30,000.00 0.00 2017-06-11 2017-07-07 2017-08-20 etc Raincoats, PPE and Management Quotations Envelope Implementation Enumerators bags, P IEC materials, Community oriented Implementation manuals. NG-EDO SPMU-17150-GO-RFQ / Procurement of Weather Monitoring Stations, GPSs, Component 4: Project Request for Single Stage - One Pending Laser Measures and Measuring IDA / 51050 Post Open - National 10,000.00 0.00 2017-06-11 2017-07-07 2017-08-18 Management Quotations Envelope Implementation Wheels, 1-2km Range Radios and other survey equipment and tools to gauge and CRSPMU/NS/GD/16/01-001 / Component 4: Project Request for Single Stage - One Under Procurement of office IDA / 51050 Post Open - National 30,000.00 0.00 2017-04-19 2017-04-19 2017-04-19 Management Quotations Envelope Implementation Equipements CRSPMU/NS/GD/16/01-002 / Component 4: Project Request for Single Stage - One Under Procurement of office IDA / 51050 Post Open - National 5,000.00 0.00 2017-04-19 2017-05-24 2017-07-07 Management Quotations Envelope Implementation Consumables CRSPMU/NS/GD/16/01-003 / Component 4: Project Request for Single Stage - One Under Procurement of office IDA / 51050 Post Open - National 15,000.00 0.00 2017-04-19 2017-05-17 2017-06-23 Management Quotations Envelope Implementation Stationaries CRSPMU/NS/GD/15/02 / Production of Newspaper and Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 20,000.00 0.00 2016-01-25 2016-02-15 2017-06-23 Magazine(on-going) Quaterly Management Quotations Envelope Implementation Production CRSPMU/NS/GD/17/02 / Procurement of Office Furniture Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 15,000.00 8,573.46 Completed 2017-02-16 2017-03-17 2017-04-28 2017-04-24 2017-05-15 and Installation of Wooden Office Management Quotations Envelope Shelve CRSPMU/NS/GD/16/03 / Procurement and Installation of Component 4: Project Request for Single Stage - One shade cover and purchase of IDA / 51050 Post Open - National 12,000.00 4,856.32 Signed 2017-02-16 2017-03-10 2017-06-23 2017-04-24 Management Quotations Envelope bucket covers for 2nos. Pickup Vehicles CRSPMU/NS/GD/16/05 / Component 4: Project Request for Single Stage - One Pending Procurment of Project Vehicle for IDA / 51050 Post Open - National 60,000.00 0.00 2017-02-20 2017-03-20 2017-04-26 Management Quotations Envelope Implementation Focal NGO CRSPMU/NS/GD/16/06 / Procurement and Installation of Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 5,000.00 0.00 2016-07-14 2016-08-04 2016-09-19 5nos. Bill board for the 5 priority Management Quotations Envelope Implementation sites of CRS-NEWMAP. CRSPMU/NS/GD/16/04 / Component 4: Project Request for Single Stage - One Pending Procurement of a 30KVA Backup IDA / 51050 Post Open - National 15,000.00 0.00 2017-09-12 2017-10-10 2017-11-16 Management Quotations Envelope Implementation Generator for the Project Office CRSPMU/NS/GD/17/08 / Procurement of Environmental Portable Equipments (Pulser Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 31,570.00 0.00 2017-03-20 2017-04-17 2017-05-24 Nose Meter, Mephelo meter, Air Management Quotations Envelope Implementation Quality monitoring Detector, Water CRSPMU/NS/GD/17/09 / Component 4: Project Request for Single Stage - One Procurement of Personal IDA / 51050 Post Open - National 16,500.00 2,989.37 Signed 2017-03-20 2017-04-17 2017-04-26 2017-05-24 Management Quotations Envelope Protective Equipments (PPEs) EBSPMU/NS/GDS/16/01 / Component 4: Project Request for Single Stage - One Pending Ongoing Branding for Ebonyi IDA / 51050 Post Open - National 27,500.00 0.00 2016-01-20 2016-03-07 2016-03-28 Management Quotations Envelope Implementation NEWMAP. EBSPMU/NS/GDS/16/02 / Ongoing Creation, Hosting and Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 15,000.00 0.00 2016-02-20 2016-03-28 2016-04-25 Maintenance of Ebonyi state Management Quotations Envelope Implementation SPMU website EBSNEWMAP/NS/GDS/17/01 / Procurement of Laptop Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 50,000.00 0.00 2017-02-06 2017-03-08 2017-04-05 Computers, Scanner, UPS, Management Quotations Envelope Implementation Software Packages, etc ANS/NEWMAP/GDS/NS/16/11 / Procurement of Personal Protective Equipments: Rain Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 20,000.00 0.00 2016-12-08 2016-12-21 2017-01-20 Coat, Rain Boot, Tip Toe Boat, Management Quotations Envelope Implementation Hig Visibility VEST, Helmet and Gloves for SPMU/Site Visit Use ANS/NEWMAP/GDS/NS/17/01 / Procurement of three Number Work Stations, Five Number Andriod Tablets, Four Number Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 70,000.00 0.00 2017-01-31 2017-03-21 2017-04-20 HD Cameras, Six Number I7 Management Quotations Envelope Implementation laptops, Two Number Coloured Printers and Networking of Office Equipment ANS/NEWMAP/GDS/NS/17/04 / Component 4: Project Request for Single Stage - One Pending Procurement of Two 4x4 Pickups IDA / 51050 Post Open - National 122,000.00 0.00 2017-02-07 2017-03-28 2017-04-27 Management Quotations Envelope Implementation for SPMU ANS/NEWMAP/GDS/NS/17/03 / Procurement of 8 Nos. High Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 5,000.00 0.00 2017-06-12 2017-07-24 2017-08-23 Efficiency Hand Held GPS for Management Quotations Envelope Implementation Anambra NEWMAP SPMU AKSPMU/GD/NS/17/01 / Office Equipment: Computers and Accessories, software packages, Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 110.00 0.00 2017-02-13 2017-03-20 2017-04-11 Photo-copiers, UPS, Printers and Management Quotations Envelope Implementation Scanners, Fax Machines, Laptops, Stationeries, etc AKSPMU/GD/NS/17/02 / Office Furniture: Water Dispenser, Component 4: Project Request for Single Stage - One Pending Refrigerators, Air conditioners, IDA / 51050 Post Open - National 180.00 0.00 2017-02-13 2017-03-20 2017-04-18 Management Quotations Envelope Implementation Tables, Chairs, book shelves, filing cabinet, etc Page 4 AKSPMU/GD/NCB/17/01 / Motor vehicles: (A) 6 No. double cabin 4-WD Pick up Vehicle (this Component 4: Project Single Stage - One Pending includes 1 each for focal NGO IDA / 51050 Prior Request for Bids Open - National 670.00 0.00 2017-05-08 2017-05-08 2017-06-12 2017-06-26 2017-07-13 2017-09-14 Management Envelope Implementation and Engineering and Supervision firm) (B) 1 No. 18 seater bus (C) 1 No. SUV 4WD AKSPMU/GD/NS/17/03 / 1 No. 40KVA Sound Proof Electricity Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 32.00 0.00 2017-02-13 2017-03-20 2017-04-12 Generating Set-Procurement and Management Quotations Envelope Implementation Installation AKSPMU/GD/NCB/17/02 / Procurement of Weather Monitoring Stations, GPSs, Component 4: Project Single Stage - One Pending IDA / 51050 Post Request for Bids Open - National 350.00 0.00 2017-05-29 2017-05-29 2017-07-03 2017-07-17 2017-08-24 2017-10-17 Laser Measures and Measuring Management Envelope Implementation Wheels; 4-5km Range Radios and other survey equipment AKSPMU/GD/NS/17/04 / Procurement of GIS equipment, Unmanned Aerial Vehicle (UAV) Component 4: Project Request for Single Stage - One Pending to Support GIS unit in the State IDA / 51050 Post Open - National 64.00 0.00 2017-05-16 2017-06-20 2017-07-19 Management Quotations Envelope Implementation to map erosion sites, infrastructure, watersheds, wetlands and drainage basins. AKSPMU/GD/NS/17/06 / Printing of project documents (accounting and procurement), Component 4: Project Request for Single Stage - One Pending memo pads, file jackets, IDA / 51050 Post Open - National 135.00 0.00 2017-02-13 2017-03-20 2017-04-10 Management Quotations Envelope Implementation envelops, , information, communication and education (ICE) materials DTSPMU/NS/GD/17/01 / Operational Vehicles : 2 Nos Component 4: Project Request for Single Stage - One 4WD PICK UP Vehicles, 1 No IDA / 51050 Post Open - National 400,000.00 224,484.73 Completed 2017-02-06 2017-04-13 2017-06-23 2017-05-15 2017-06-28 Management Quotations Envelope SUV JEEP AND 1 NO 14 SEATER BUS DTSPMU/NS/GD/17/02 / (Supply of Office Equipment) 6 nos swivel chairs, 6 nos Executive Tables, 12 visitors chairs, 3 set of settees in Component 4: Project Request for Single Stage - One Under IDA / 51050 Post Open - National 70,000.00 0.00 2017-02-06 2017-04-13 2017-05-10 Chairman, STC and PC'S Management Quotations Envelope Implementation Offices,ICT EQUIPMENT(10 No laptop,10 No small printer, 8 No I- pad and 4 No Standing air- conditional DTSPMU/NS/GD/17/03 / Procurement of 20 Carton of A4, 10 ctns of foolscap, 10 ctns of Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 25,000.00 0.00 2017-10-04 2017-10-30 2017-11-23 blue miniting sheets, 10 pkts of Management Quotations Envelope Implementation each blue, red and black biro, printer and photocoping ink DTSPMU/NS/GD/17/4 / Pr0duction of customise 1000 Component 4: Project Request for Single Stage - One parket shirt, 1000 T-shirt,1000 IDA / 51050 Post Open - National 70,000.00 47,560.18 Completed 2017-02-20 2017-03-17 2017-06-19 2017-04-20 2017-07-21 Management Quotations Envelope biro, 1000 bags and 1000 face cap KGSPMU/NS/GD/17/02 / ICT Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 60,000.00 42,546.29 Completed 2017-02-13 2017-03-20 2017-06-12 2017-04-19 2017-09-27 Equipment Management Quotations Envelope KGSPMU/NS/GD/17/03 / Office Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 45,000.00 0.00 2017-02-20 2017-03-13 2017-04-03 Equipment Management Quotations Envelope Implementation KGSPMU/NS/GD/16/07 / Component 4: Project Request for Single Stage - One Branding and Sensitsation IDA / 51050 Post Open - National 30,230.00 19,777.98 Completed 2017-02-13 2017-03-13 2017-07-21 2017-04-19 2017-07-28 Management Quotations Envelope materials KNSPMU/GD/NS/17/2/5 / Component 4: Project Request for Single Stage - One Pending Procurement of Survey IDA / 51050 Post Open - National 10,000.00 0.00 2017-01-03 2017-04-26 2017-05-10 Management Quotations Envelope Implementation Equipment. KNSPMU/GD/NS/17/2/6 / Media Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 40,000.00 0.00 2017-02-03 2017-05-10 2017-05-24 and Communication Equipment Management Quotations Envelope Implementation GMS/NEWMAP/NS/GD/17/01 / PROCURMENT OF I NO 4WD Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 327,000.00 0.00 2017-03-20 2017-05-08 2017-06-05 DD CABIN HILUX, ONE NO 18 Management Quotations Envelope Implementation SEATER BUS, 1 NO SUV PLSPMU/NSGD/17/06 / Field Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 75,000.00 0.00 2017-05-29 2017-07-17 2017-08-14 Equipment Management Quotations Envelope Implementation PLSPMU/NSGD/17/07 / Purchase of GIS data/Satellite Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 50,000.00 0.00 2017-06-20 2017-08-01 2017-08-29 Imagery, GPS and Overhead Management Quotations Envelope Implementation photography, etc PLSPMU/NSGD/17/04 / Component 4: Project Request for Single Stage - One Pending Procurement of Communiction IDA / 51050 Post Open - National 20,800.00 0.00 2017-05-22 2017-07-10 2017-08-07 Management Quotations Envelope Implementation Equipment SKO/NEWMAP/GD/NS/005/17 / Component 4: Project Request for Single Stage - One Pending PROCUREMENT OF OFFCE IDA / 51050 Post Open - National 50,000.00 0.00 2017-03-02 2017-04-13 2017-05-13 Management Quotations Envelope Implementation AC &REPRIGERATORS SKO/NEWMAP/GD/NS/009/17 / Component 4: Project Request for Single Stage - One Pending PROCUREMENT OF 50KVA IDA / 51050 Post Open - National 35,000.00 0.00 2017-03-03 2017-05-05 2017-08-03 Management Quotations Envelope Implementation GENERATOR SKO/NEWMAP/GD/NS/010/17 / Component 4: Project Request for Single Stage - One Pending PROCUREMENT OF/PRINT OF IDA / 51050 Post Open - National 5,000.00 0.00 2017-03-24 2017-05-19 2017-06-18 Management Quotations Envelope Implementation TV/RADIO JINGLES SKO/NEWMAP/GD/NS/011/17 / Component 4: Project Request for Single Stage - One Pending PROCUREMENT OF OFFICE IDA / 51050 Post Open - National 5,000.00 0.00 2017-03-17 2017-05-05 2017-06-02 Management Quotations Envelope Implementation STATIONARIES SKO/NEWMAP/GD/NS/001/17 / Procurement of vehicles: 1no 18 Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 400,000.00 0.00 2017-02-12 2017-04-02 2017-07-01 seater bus, 1no SUV and 3no Management Quotations Envelope Implementation double cabin 4WD SKO/NEWMAP/GD/NS/002/17 / Furnishing of SPMU Offices and Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 50,000.00 0.00 2017-02-09 2017-04-06 2017-05-04 procurement of office furniture Management Quotations Envelope Implementation and equipment SKO/NEWMAP/GD/NS/003/17 / Procurement of laptops, desktops computers, printers, Component 4: Project Request for Single Stage - One Pending photocopiers, scanners, IDA / 51050 Post Open - National 50,000.00 0.00 2017-02-15 2017-04-12 2017-05-12 Management Quotations Envelope Implementation cameras, projector, screen and relevant software and accessories SKO/NEWMAP/GD/NS/004/17 / Component 4: Project Request for Single Stage - One Pending Procurement and installation of IDA / 51050 Post Open - National 5,000.00 0.00 2017-03-03 2017-04-14 2017-05-12 Management Quotations Envelope Implementation internet facilities Page 5 NG-NEWMAP-FPMU-19527-GO- Component 4: Project Request for Single Stage - One Pending RFQ / Procurement of ICT IDA / 51050 Post Open - National 16,000.00 0.00 2017-07-22 2017-09-16 2018-03-15 Management Quotations Envelope Implementation equipment for GEF desk office NG-NEWMAP-FPMU-19535-GO- RFB / Procurement of ICT Component 4: Project Single Stage - One Pending IDA / 51050 Post Request for Bids Open - National 200,000.00 0.00 2017-07-19 2017-07-24 2017-09-04 2017-10-04 2017-11-08 2018-05-07 Equipments and Internet Management Envelope Implementation Provision. NG-NEWMAP-FPMU-19584-GO- RFQ / Production of IEC Materials & Newsletters on Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 96,000.00 0.00 2017-07-30 2017-09-24 2018-03-23 Activities of NEWMAP (for Management Quotations Envelope Implementation Awareness Raising and Advocacy purposes) Component 2: Erosion and NG-NEWMAP-FPMU-19537-GO- Watershed Management Single Stage - One Pending RFB / Upscaling of National EA IDA / 51050 Post Request for Bids Open - National 138,000.00 0.00 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 Institutions and Information Envelope Implementation Portal Services NG-NEWMAP-FPMU-19572-GO- Component 2: Erosion and RFB / Procurement of statistical Watershed Management Single Stage - One Pending and analytical software tools and IDA / 51050 Post Request for Bids Open - National 250,000.00 0.00 2017-08-07 2017-08-12 2017-09-23 2017-10-23 2017-11-27 2018-05-26 Institutions and Information Envelope Implementation equipment for DPRS of the Services FMEnv NG-NEWMAP-FPMU-19516-GO- RFB / Operationalisation of Component 3: Climate Change Single Stage - One Pending IDA / 51050 Post Request for Bids Open - National 175,000.00 0.00 2017-08-16 2017-08-21 2017-10-02 2017-11-01 2017-12-06 2018-06-04 National Climate Change GHG Response Envelope Implementation Data Management System- AKSPMU/GO/FRQ/17/02 / Office furniture: water dispensers, Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - International 180.00 0.00 2017-09-30 2017-11-25 2017-11-27 refrigerators, airconditioners, Management Quotations Envelope Implementation tables, chairs,bookshleves etc AKSPMU/GO/RFB/17/01 / Motor vehicles: (A) 6 No. double cabin 4-WD Pick up Vehicle (this Component 4: Project Single Stage - One includes 1 each for focal NGO IDA / 51050 Prior Request for Bids Open - National 670.00 0.00 Under Review 2017-09-29 2017-10-04 2017-11-06 2017-11-20 2017-12-20 2017-12-27 Management Envelope and Engineering and Supervision firm) (B) 1 No. 18 seater bus (C) 1 No. SUV 4WD AKSPMU/GO/RFQ/17/06 / Printing of project documents (accounting and procurement), Component 4: Project Request for Single Stage - One Pending memo pads, file jackets, IDA / 51050 Post Open - National 135.00 0.00 2017-10-09 2017-12-04 2017-12-19 Management Quotations Envelope Implementation envelops, cash books, information, communication and education (ICE): materials, etc AKSPMU/GO/RFQ/17/04 / GIS equipment, Unmanned Aerial Component 4: Project Request for Single Stage - One Pending Vehicle (UAV) to Support GIS IDA / 51050 Post Open - National 64.00 0.00 2017-10-08 2017-12-01 2017-12-08 Management Quotations Envelope Implementation unit, infrastructure, watersheds, wetlands and drainage basins. AKSPMU/GO/RFB/17/02 / Weather Monitoring Stations, GPSs, Laser Measures and Component 4: Project Single Stage - One Pending IDA / 51050 Post Request for Bids Open - National 350.00 0.00 2017-11-02 2017-11-07 2017-12-06 2017-12-20 2018-01-03 2018-01-24 Measuring Wheels; 4-5km Range Management Envelope Implementation Radios and other survey equipment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ANS/NEWMAP/GDS/NS/17/04/0 Component 1: Erosion and 1C-RFQ / Procurement & Request for Single Stage - One Pending IDA / 51050 Watershed Management Post Open - National 20,000.00 0.00 2017-06-02 2017-07-07 2017-08-06 Installation of Advance ArcGIS Quotations Envelope Implementation Infrastructure Investments Software for the SPMU GIS Unit ANS/NEWMAP/GDS/NCB/17/05 / Non-Consultancy Services for Resuscitation of MoEnv and Min. Component 1: Erosion and Request for Single Stage - One Pending of Agric Nurseries for the IDA / 51050 Watershed Management Post Open - National 500,000.00 0.00 2017-03-01 2017-05-31 2017-06-30 Quotations Envelope Implementation Producution of Trees and Infrastructure Investments Seedlings for Bio-remediation and Gully Prevention Projects ANS/NEWMAP/GDS/SS/17/08 / Renewal of Annual Subscription Component 4: Project Pending IDA / 51050 Post Direct Selection Direct 7,000.00 0.00 2017-01-31 2017-01-31 2017-04-04 2018-04-04 and upgrading of Interenet Management Implementation Service for Anambra NEWMAP NG-ANAMBRA SPMU-17277- NC-DIR / Renewal of Microsoft Component 4: Project Pending IDA / 51050 Post Direct Selection Direct 19,000.00 0.00 2017-01-31 2017-02-14 2017-03-21 2018-03-16 Windows, Microsoft Office and Management Implementation Antivirus Licenses for One Year ANS/NEWMAP/GDS/SS/17/10 / Renewal of Comprehensive Fleet Component 4: Project Pending IDA / 51050 Post Direct Selection Direct 16,000.00 0.00 2017-07-03 2017-07-17 2017-08-21 2018-08-16 Insurance Cover for Project Management Implementation Vehicles NG-ANAMBRA SPMU-17269- NC-RFQ / Provision of Insurance Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 15,000.00 0.00 2017-07-04 2017-08-29 2018-08-24 Cover for Office Equipment and Management Quotations Envelope Implementation Furniture KNSPMU/WKS/NCB/17/1/7 / Degraded Land Rehabilitation Component 4: Project Request for Single Stage - One Pending IDA / 51050 Post Open - National 150,000.00 0.00 2017-03-28 2017-03-28 2017-03-28 Scheme( woodlot orchard, Management Quotations Envelope Implementation plantation) . Component 2: Erosion and NG-NEWMAP-FPMU-19582-NC- Watershed Management Single Stage - One Under RFB / Consultancy Services for IDA / 51050 Post Request for Bids Open - National 250,000.00 0.00 2017-07-03 2017-07-08 2017-08-19 2017-09-18 2017-08-22 2017-10-23 2018-04-21 Institutions and Information Envelope Implementation EA Archiival Digital cataloguing Services NG-NEWMAP-FPMU-19575-NC- Component 2: Erosion and RFB / Bathymetry & Watershed Management Single Stage - One Pending IDA / 51050 Prior Request for Bids Open - International 1,400,000.00 0.00 2017-07-03 2017-07-08 2017-08-19 2017-09-18 2017-10-23 2018-04-21 Geomorphological Study of the Institutions and Information Envelope Implementation River Benue System & Kiridam Services CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ABS/NEWMAP/QCBS/CON/16/0 1 / Consultancy for the Component 1: Erosion and Quality And Cost- generation of LRID for erosion IDA / 51050 Watershed Management Post Open - International 160,000.00 152,447.55 Signed 2016-08-15 2016-01-05 2016-09-26 2016-11-21 2017-03-16 2016-12-05 2017-05-24 2016-12-26 2017-05-24 2017-01-09 2017-07-04 2017-02-06 2017-07-05 2017-05-17 Based Selection and watersheds, drainage basins Infrastructure Investments of storm water multiple sites ABS/NEWMAP/QCBS/CON/15/0 Component 2: Erosion and 1 / Consultancy for the Aba Watershed Management Quality And Cost- Pending IDA / 51050 Prior Open - International 900,000.00 0.00 2015-05-27 2015-06-10 2015-09-02 2015-09-16 2015-10-07 2015-11-18 2015-12-23 2016-12-22 Urban Storm Water Management Institutions and Information Based Selection Implementation MasterPlan Services Page 6 ABS/NEWMAP/CQS/CON/16/02 / Consultancy for sensitization, Component 1: Erosion and Consultant Under design and supervision of IDA / 51050 Watershed Management Post Qualification Open - National 160,000.00 0.00 2017-02-07 2017-03-21 2017-05-31 2017-06-14 2017-07-11 2018-01-27 Implementation Household and community water Infrastructure Investments Selection harvesting ABS/NEWMAP/QCBS/CON/14/0 1 / Procurement of consultants for Study, Designs,and Component 1: Erosion and Quality And Cost- Under Supervision of erosion/flood sites IDA / 51050 Watershed Management Prior Open - International 1,900,000.00 0.00 2017-07-24 2017-09-04 2017-11-13 2017-11-27 2017-12-11 2018-01-08 2018-01-29 2020-02-18 Based Selection Implementation and re-adcertisement of a new Infrastructure Investments one at the expiration of existing one ABS/NEWMAP/CQS/CON/17/01 / Support to communities & Line MDAs to establish nurseries, plant trees, grasses of assorted Component 1: Erosion and Consultant indigenous species; Pending IDA / 51050 Watershed Management Post Qualification Open - National 210,000.00 0.00 2017-06-26 2017-07-17 2017-08-28 2017-09-11 2017-10-09 2018-01-07 construction of renno Implementation Infrastructure Investments Selection mattreasses and gabion boxes.(Multiple contracts) to enhance capacities of Line ministries and ICT tools ENS/NEWMAP/CON/QCBS/14/0 Component 1: Erosion and 1 / Selection of consultant for the Quality And Cost- Pending IDA / 51050 Watershed Management Prior Open - International 900,000.00 0.00 2013-11-02 2013-12-10 2014-01-21 2014-03-14 2014-04-21 2014-06-04 2014-09-25 2017-03-13 detailed designs/supervision for Based Selection Implementation Infrastructure Investments Enugu SPMU. ENS/NEWMAP/CON/CQS/15/01 / GIS Survey of the state to map Component 1: Erosion and Consultant erosion sites, infrastructure, Pending IDA / 51050 Watershed Management Post Qualification Open - National 300,000.00 0.00 2015-04-16 2015-05-07 2015-06-18 2015-07-02 2015-07-16 2015-09-14 watersheds, wetlands and Implementation Infrastructure Investments Selection drainage basins.( Three (3) contracts) ENS/NEWMAP/CON/CQS/15/02 Component 1: Erosion and Consultant / Consultancy for rehabilitation of Pending IDA / 51050 Watershed Management Post Qualification Open - National 100,000.00 0.00 2016-05-20 2016-06-19 2016-07-24 2016-08-07 2016-08-21 2016-10-20 Okwojo Ngwo Community buster Implementation Infrastructure Investments Selection pump water station/reticulation. Component 1: Erosion and Consultant ENS/NEWMAP/CON/CQ/14/07 Pending IDA / 51050 Watershed Management Post Qualification Open - National 260,000.00 0.00 2014-06-30 2014-06-30 2014-08-11 2014-10-06 2014-10-27 2016-10-16 / Selection of Focal NGO Implementation Infrastructure Investments Selection ENS/NEWMAP/CON/CQS/15/04 Component 1: Erosion and Consultant Pending / Consultancy for household IDA / 51050 Watershed Management Post Qualification Open - National 150,000.00 0.00 2016-04-20 2016-04-20 2016-05-18 2016-06-01 2016-06-15 2016-08-14 Implementation water harvesting. Infrastructure Investments Selection NG-EDO SPMU-17109-CS- QCBS / Procurement of consultants for study/ designs of Component 1: Erosion and Quality And Cost- Pending Ten (10) additional erosion sites IDA / 51050 Watershed Management Prior Open - International 2,400,000.00 0.00 2013-09-06 2013-10-24 2013-12-27 2014-02-04 2014-02-19 2014-03-07 2014-04-09 2016-04-08 Based Selection Implementation and supervision of civil Infrastructure Investments works+Supervision of Ekehuan, Auchi and Queen ede sites NG-EDO SPMU-17098-CS- QCBS / Procurement of Component 1: Erosion and Quality And Cost- Pending consultants for supervision of civil IDA / 51050 Watershed Management Prior Open - International 960,000.00 0.00 2013-09-07 2013-10-29 2014-01-07 2014-02-04 2014-02-19 2014-03-07 2014-04-09 2017-09-29 Based Selection Implementation works at Ekehuan, Auchi and Infrastructure Investments Queen ede sites and new sites NG-EDO SPMU-17077-CS-CQS Component 1: Erosion and Consultant Pending / Consultancy for Water IDA / 51050 Watershed Management Post Qualification Open - National 150,000.00 0.00 2016-02-05 2016-02-05 2016-02-05 2016-02-26 2017-02-16 2017-05-16 Implementation Harvesting-ONGOING Infrastructure Investments Selection NG-EDO SPMU-17069-CS-CQS / Consultancy for the generation Component 1: Erosion and Consultant of Land Resources Inventory Pending IDA / 51050 Watershed Management Post Qualification Open - National 95,000.00 0.00 2015-02-05 2015-02-05 2016-02-05 2016-02-26 2017-02-16 2017-05-16 Data (LRID) for erosion sites, Implementation Infrastructure Investments Selection infrastructure, watersheds, wetlands (GIS survey)-ONGOING Component 1: Erosion and NG-EDO SPMU-17051-CS-CQS Watershed Management Consultant Pending / Consultancy of Sevices of Focal IDA / 51050 Infrastructure Investments Post Qualification Open - National 200,000.00 0.00 2014-12-22 2014-12-22 2015-04-10 2015-04-28 2015-05-12 2017-06-20 Implementation NGO Component 4: Project Selection Management Component 2: Erosion and NG-EDO SPMU-17096-CS- Watershed Management Quality And Cost- Pending QCBS / Urban and Storm Water IDA / 51050 Prior Open - International 4,000,000.00 0.00 2017-06-30 2017-08-31 2017-10-31 2018-01-08 2018-02-09 2018-03-29 2018-04-27 2018-11-30 Institutions and Information Based Selection Implementation Master Plan for larger Benin City Services CRS/NEWMAP/QCBS/13/01 / Component 4: Project Quality And Cost- Pending Consultancy for Design and IDA / 51050 Prior Open - National 1,975,400.00 0.00 2013-02-04 2013-03-26 2013-03-26 2013-03-26 2013-07-22 2014-01-26 2014-03-09 2017-08-24 Management Based Selection Implementation Supervision of Civil works CRS/NEWMAP/QCS/15/01 / Consultant Consultancy for GIS upgrade and Component 4: Project Pending IDA / 51050 Post Qualification Open - National 188,000.00 0.00 2015-06-15 2015-06-15 2016-03-08 2016-03-15 2016-06-02 2016-07-07 mapping of erosion and water Management Implementation Selection shed sites in the State CRS/NEWMAP/QCS/14/01 / Component 1: Erosion and Consultant Contract Renewal - Engagement Pending IDA / 51050 Watershed Management Post Qualification Open - National 100,000.00 0.00 2014-05-01 2014-05-14 2015-01-09 2015-01-23 2016-10-24 2017-10-23 of focal NGO to support SPMU Implementation Infrastructure Investments Selection activities in all intervention sites. CRS/NEWMAP/CQ/16/02 / Consultancy for Sensitisation, Consultant Component 4: Project Pending Design and Supervision of IDA / 51050 Post Qualification Open - National 200,000.00 0.00 2017-03-06 2017-03-06 2017-03-06 2017-03-06 2017-03-06 2017-03-06 Management Implementation Household and Community Selection Water Harvesting for new sites CRS/NEWMAP/CQS/17/01 / Component 1: Erosion and Consultant Pending Consultancy of design for six IDA / 51050 Watershed Management Post Qualification Open - National 300,000.00 0.00 2017-02-20 2017-02-20 2017-04-17 2017-05-01 2017-05-22 2019-06-19 Implementation additional sites Infrastructure Investments Selection EBSNEWMAP/CQS/16/04 / Ongoing Consultancy for Component 1: Erosion and Consultant Pending Sensitization, Design and IDA / 51050 Watershed Management Post Qualification Open - National 178,860.00 0.00 2016-07-01 2016-07-01 2016-07-01 2016-09-23 2016-10-07 2017-06-01 Implementation Supervision of Household and Infrastructure Investments Selection Community Water Harvesting EBNEWMAP/CQS/CS/14/14 / Component 1: Erosion and Consultant Pending Ongoing Focal NGO Consultancy IDA / 51050 Watershed Management Post Qualification Open - National 180,000.00 0.00 2014-10-08 2014-10-29 2014-12-12 2015-02-24 2015-03-10 2017-05-18 Implementation for EB- SPMU Infrastructure Investments Selection EBSNEWMAP/CQS/CS/16/03 / Ongoing Conduct Needs Component 1: Erosion and Assessment of Livelihood Pending IDA / 51050 Watershed Management Post Least Cost Selection Open - National 135,000.00 0.00 2016-02-15 2016-02-15 2016-02-29 2016-05-04 2016-05-11 2016-05-25 2016-06-15 2017-04-05 Options in the Seven (7) Implementation Infrastructure Investments Selected Intervention Sub- Catchment Areas EBSNEWMAP/QCBS/CS15/01 Component 2: Erosion and / Consultancy for production of Watershed Management Quality And Cost- Under IDA / 51050 Prior Open - International 750,000.00 0.00 2015-04-28 2015-05-11 2015-06-09 2017-02-15 2017-03-01 2017-03-01 2017-09-18 2017-04-26 2017-08-01 Urban Storm Water Master Plan Institutions and Information Based Selection Implementation for Abakiliki Capital City Services EBSNEWMAP/CQS/CS/16/01 / Ongoing Consultancy for M&E Consultant Component 4: Project Pending Baseline Studies for Six(6) IDA / 51050 Post Qualification Open - National 260,000.00 0.00 2015-12-30 2015-12-30 2016-03-04 2016-07-01 2016-08-05 2017-02-10 Management Implementation Intervenvation Sites in Ebonyi Selection state Page 7 EBNEWMAP/CQSS/17/01 / Component 2: Erosion and Consultant Production of Disaster Risk Watershed Management Under IDA / 51050 Post Qualification Open - National 97,440.00 0.00 2017-04-01 2017-07-24 2017-04-01 2017-04-01 2017-06-24 2017-07-08 2017-10-13 Management Plan for Ebonyi Institutions and Information Implementation Selection State Services EBSNEWMAP/CQS/CS/17/02 / Component 1: Erosion and Consultant Pending Engagement/Renewal of Services IDA / 51050 Watershed Management Post Qualification Open - National 222,220.00 0.00 2017-02-01 2017-02-22 2017-06-09 2017-07-14 2017-09-22 2019-10-28 Implementation of Focal NGO Infrastructure Investments Selection ANS/NEWMAP/CS/CQS2014/01 / Consultancy Services for GIS Component 1: Erosion and Consultant Pending Data Collection and Mapping of IDA / 51050 Watershed Management Post Qualification Open - National 199,000.00 0.00 2015-06-04 2015-10-22 2016-04-21 2016-04-25 2016-05-30 2016-07-29 Implementation Flood and Gully Erosion Sites in Infrastructure Investments Selection Anambra State ANS/NEWMAP/CS/QCBS/2014/ 02 / Engagement of Consultant Component 1: Erosion and Quality And Cost- Pending for Engineering Design and IDA / 51050 Watershed Management Prior Open - International 4,000,000.00 0.00 2013-09-25 2014-01-27 2015-02-06 2015-04-30 2015-05-18 2015-05-28 2015-07-03 2018-06-17 Based Selection Implementation Supervision of Gully Erosion Infrastructure Investments Sites ANS/NWEMAP/CS/CQS/2014/0 Component 1: Erosion and Consultant Pending 3 / Engagement of Consultant for IDA / 51050 Watershed Management Post Qualification Open - National 240,000.00 0.00 2014-05-21 2014-12-08 2015-03-26 2015-04-09 2015-05-14 2017-05-03 Implementation Focal NGO for AnamNEWMAP Infrastructure Investments Selection ANS/NEWMAP/CS/QCBS/2015/ Component 2: Erosion and 01 / Engagement of Consultant Watershed Management Quality And Cost- IDA / 51050 Prior Open - International 1,000,000.00 0.00 Under Review 2015-09-28 2015-11-05 2016-10-27 2017-03-06 2017-03-06 2017-03-20 2017-05-15 2018-02-19 for Onitsha Urban Stormwater Institutions and Information Based Selection Management Master Services ANS/NEWMAP/CS/CQS/2015/0 2 / Consultancy Services for Environmental & Social Consultant Component 4: Project Pending Management Plan (ESMP) and IDA / 51050 Post Qualification Open - National 130,000.00 0.00 2015-09-14 2015-12-14 2016-03-11 2016-03-22 2016-04-26 2016-06-25 Management Implementation Abbreviated Resettlement Action Selection Plan (ARAP) for Abidi-Umuoji and Enugu-Ukwu Erosion Sites ANS/NEWMAP/CS/CQS/2015/0 2/A / Consultancy Services for Environmental & Social Consultant Management Plan (ESMP) and Component 4: Project Pending IDA / 51050 Post Qualification Open - National 130,000.00 0.00 2015-09-14 2016-01-04 2016-03-17 2016-03-24 2016-04-21 2016-06-20 Abbreviated Resettlement Action Management Implementation Selection Plan (ARAP) for Ugamuma- Obosi and Ndiagu-Ikenga, Ogidi Erosion Sites ANS/NEWMAP/CS/CQS/2016/0 7 / Consultancy Services to Develop and Implement Risk Assessment, Flood Mapping and Component 1: Erosion and Quality And Cost- Under Risk Management Plans in IDA / 51050 Watershed Management Prior Open - International 800,000.00 0.00 2016-12-13 2017-03-08 2017-05-10 2017-05-30 2017-06-20 2017-08-22 2017-10-09 2018-10-04 Based Selection Implementation Anambra East, Anambra West, Infrastructure Investments Ayamelum, Onitsha, Ogbaru, Awka/Igbariam, Oraukwu/Alor Catchment Areas ANS/NEWMAP/CS/CQS/2016/0 4 / Consultancy Services for the Consultant Design and Supervision of Component 4: Project Pending IDA / 51050 Post Qualification Open - National 199,000.00 0.00 2016-01-27 2016-01-27 2016-03-30 2016-04-13 2016-05-11 2016-07-10 Household & Community Rain Management Implementation Selection Water Harvesting for Communities in Anambra State ANS/NEWMAP/CS/CQS/2017/0 5 / Consultancy Services for Environmental & Social Consultant Component 4: Project Pending Management Plan (ESMP) and IDA / 51050 Post Qualification Open - National 160,000.00 0.00 2017-01-30 2017-02-13 2017-04-24 2017-07-03 2017-08-14 2017-10-13 Management Implementation Abbreviated Resettlement Action Selection Plan (ARAP) for Ire-Obosi and Nkpor-Flyover ANS/NEWMAP/CS/CQS/2017/0 6 / Consultancy Services for Environmental & Social Consultant Component 4: Project Pending Management Plan (ESMP) and IDA / 51050 Post Qualification Open - National 160,000.00 0.00 2016-11-30 2017-01-30 2017-03-13 2017-04-24 2017-06-19 2017-08-18 Management Implementation Abbreviated Resettlement Action Selection Plan (ARAP) for Nnewi-Ichi and Ojoto Component 1: Erosion and Consultant ABS/NEWMAP/CQS/CON/15/01 Under IDA / 51050 Watershed Management Prior Qualification Open - International 183,000.00 0.00 2014-02-03 2014-04-28 2014-04-28 2014-08-18 2014-09-29 2017-06-09 / Procurement of Focal NGO Implementation Infrastructure Investments Selection EBSNEWMAP/QCBS/CS/14/01/ 1 / Ongoing Procurement of Component 1: Erosion and Quality And Cost- Pending Consultants for IDA / 51050 Watershed Management Prior Open - International 2,812,500.00 0.00 2014-02-26 2014-04-09 2014-05-14 2014-08-06 2014-08-27 2014-10-18 2015-05-18 2015-06-18 Based Selection Implementation Designs/Supervision of Eight (8) Infrastructure Investments erosion/flood sites. AKS/PMU/QCBS/17/01 / Component 4: Project Quality And Cost- Pending Selection of Design and IDA / 51050 Prior Open - International 5,050.00 0.00 2017-02-13 2017-04-20 2017-06-01 2017-06-19 2017-06-19 2017-07-14 2017-09-01 2018-12-03 Management Based Selection Implementation Supervision Engineering firm AKS/PMU/CQS/17/01 / Selection of Consultant for Consultant Component 4: Project Pending generation of Land Resource IDA / 51050 Post Qualification Open - National 150.00 0.00 2017-05-26 2017-05-26 2017-09-01 2017-09-22 2017-10-10 2017-11-23 Management Implementation Inventory Data (LRID) for Selection watershed management. Consultant AKS/PMU/CQS/17/02 / Component 4: Project Pending IDA / 51050 Post Qualification Open - National 186.00 0.00 2017-03-17 2017-03-31 2017-06-30 2017-07-07 2017-07-25 2017-08-08 Selection of Focal NGO Management Implementation Selection DTS/NEWMAP/ QCBS/17/01 / Selection of consultant for Component 4: Project Quality And Cost- Pending IDA / 51050 Prior Open - International 1,270,000.00 0.00 2017-03-01 2017-03-01 2017-04-05 2017-06-12 2017-06-12 2017-07-25 2017-09-13 2017-11-29 Designs and supervision of Four Management Based Selection Implementation (4) erosion/flood sites. DTS/NEWMAP/ CQS/17/01 / Consultant Selection of consultant for Component 4: Project Pending IDA / 51050 Post Qualification Open - National 290,000.00 0.00 2017-04-05 2017-04-05 2017-04-05 2017-06-26 2017-08-21 2017-11-02 Designs and supervision of Management Implementation Selection JESSE flood site. DTNEWMAP/CQS/17/2 / Consultant Component 4: Project Pending Appointment of Focal NGO for IDA / 51050 Post Qualification Open - National 250,000.00 0.00 2016-09-30 2016-09-30 2016-09-30 2017-02-09 2017-03-06 2018-04-11 Management Implementation State Selection DTS/NEWMAP/CQS/17/3 / Consultant GENERATION OF LRID FOR Component 4: Project IDA / 51050 Post Qualification Open - National 250,000.00 162,823.56 Signed 2016-10-16 2016-08-23 2016-10-16 2016-10-16 2017-03-14 2017-02-10 2017-04-03 2017-03-03 2017-04-10 2017-04-24 EROSION AND WATERSHED Management Selection MGT(GIS) KGS/NEWMAP/CQS/15/05 / Consultant Component 4: Project Pending Consultancy for Engineering IDA / 51050 Post Qualification Open - National 295,000.00 0.00 2017-01-20 2017-01-20 2017-04-11 2017-04-11 2017-05-02 2017-06-22 Management Implementation design Ozuri Erosion Site Selection KGSPMU/CQS/15/03 / Consultant Component 4: Project consultancy for M&E Baseline IDA / 51050 Post Qualification Open - National 197,000.00 140,964.25 Signed 2016-12-20 2016-09-07 2017-01-10 2017-03-03 2017-03-14 2017-03-10 2017-05-23 2017-04-14 2017-06-02 2017-06-05 Management Survey Selection KGS/NEWMAP/CQS/02 / Consultant Generate LRID for Erosion and Component 4: Project Pending IDA / 51050 Post Qualification Open - National 295,000.00 0.00 2016-12-20 2016-12-20 2017-03-03 2017-03-24 2017-04-14 2017-09-04 watershed management (GIS Management Implementation Selection Study) for Kogi State KGS/NEWMAP/CQS/15/07 / Component 1: Erosion and Consultant Pending Flood Vulnerability assessment IDA / 51050 Watershed Management Post Qualification Open - National 295,000.00 0.00 2017-07-24 2017-07-24 2017-08-21 2017-08-21 2017-10-09 2017-12-20 Implementation and Mapping in Kogi State Infrastructure Investments Selection Page 8 KNSPMU/CQS/17/4/6 / Consultant Component 4: Project Pending Consultancy for M & E Baseline IDA / 51050 Post Qualification Open - National 290,000.00 0.00 2017-02-05 2017-02-05 2017-02-05 2017-02-05 2017-02-05 2017-02-05 Management Implementation data Selection GMS/NEWMAP/CQS/16/01 / CONSULTANCY FOR GIS Component 1: Erosion and Consultant Pending SURVEY IN THE STATE TO IDA / 51050 Watershed Management Post Qualification Open - National 295,000.00 0.00 2017-01-03 2017-01-17 2017-02-14 2017-02-21 2017-03-07 2017-06-05 Implementation MAP EROSION SITES AND Infrastructure Investments Selection WATERSHED DELINEATION GMS/NEWMAP/QCBS/16/01 / CONSULTANCY FOR DESIGN Component 1: Erosion and AND SUPERVISION OF Quality And Cost- Pending IDA / 51050 Watershed Management Prior Open - National 1,500,000.00 0.00 2017-01-03 2017-01-17 2017-01-31 2017-02-14 2017-02-28 2017-03-21 2017-04-04 2018-05-15 CIVILWORKS & Based Selection Implementation Infrastructure Investments CONTINGENCIES OF 5 TARGETED SITES GMS/NEWAP/CQS/17/02 / Consultant Component 4: Project Pending Consulatancy for Design of one IDA / 51050 Post Qualification Open - National 285,000.00 0.00 2017-03-27 2017-04-10 2017-05-08 2017-05-15 2017-05-29 2017-09-26 Management Implementation targeted site. Selection GMS/NEWMAP/CQS/16/02 / Component 1: Erosion and Consultant Pending Consultancy for appointment of IDA / 51050 Watershed Management Post Qualification Open - National 214,000.00 0.00 2017-01-03 2017-01-17 2017-02-14 2017-02-21 2017-03-07 2019-08-24 Implementation focal NGO for state Infrastructure Investments Selection PLSNEWMAP/QCBS/17/01 / Component 1: Erosion and Procurement of consultants for Quality And Cost- IDA / 51050 Watershed Management Prior Open - National 500,000.00 0.00 Under Review 2017-01-09 2017-02-06 2017-02-13 2017-04-24 2017-05-08 2017-05-08 2017-05-31 2017-07-30 study/ designs of 5 proposed Based Selection Infrastructure Investments erosion /dam sites. PLSNEWMAP/CQS/17/04 / Consultant Procurement of consultants for Component 4: Project Under IDA / 51050 Post Qualification Open - National 145,000.00 0.00 2017-01-10 2017-07-30 2017-01-24 2017-03-14 2017-03-21 2017-04-11 2017-07-20 study/ designs of One proposed Management Implementation Selection erosion sites. PLSNEWMAP/QCBS/17/02 / 1. Livelihood sites identification and preparation for support , to Component 1: Erosion and Quality And Cost- Under include Sub-grants for IDA / 51050 Watershed Management Prior Open - International 450,000.00 0.00 2017-04-07 2017-04-07 2017-04-07 2017-04-07 2017-04-07 2017-04-07 2017-04-07 2017-04-07 Based Selection Implementation community sub-projects on Infrastructure Investments employment and skills acquisition. KGSPM/LC/15/01 / Consultancy Component 4: Project Pending IDA / 51050 Post Least Cost Selection Open - National 19,680.00 0.00 2016-12-05 2017-03-21 2017-05-09 2017-05-23 2017-05-23 2017-05-30 2017-05-30 2017-07-04 for External Audit assignment Management Implementation KGS/NEWMAP/CQS/15/01 / Consultant Component 4: Project Pending Consultancy for Focal NGO IDA / 51050 Post Qualification Open - National 241,000.00 0.00 2016-12-20 2016-12-20 2017-02-03 2017-03-03 2017-04-14 2017-06-05 Management Implementation (FONGO) Selection SOK/NEWMAP/QCBS/O1/17 / Procurement of consultant for Component 1: Erosion and Quality And Cost- Designs of Eight (8) and IDA / 51050 Watershed Management Prior Open - International 1,750,000.00 0.00 Under Review 2017-02-02 2017-02-16 2017-04-13 2017-04-27 2017-05-11 2017-06-01 2017-06-22 2019-05-23 Based Selection Supervision of Ten (10) Infrastructure Investments erosion/flood sites. SOK/NEWMAP/CQS/O1/17 / Consultant Procurement of consultant for Component 4: Project Pending IDA / 51050 Post Qualification Open - National 297,000.00 0.00 2017-02-13 2017-02-27 2017-03-06 2017-03-13 2017-04-03 2017-05-01 Designs of Two (2) erosion/flood Management Implementation Selection sites. SOK/NEWMAP/CQS/O2/17 / Consultant Component 4: Project Pending Generation of LRID for / erosion IDA / 51050 Post Qualification Open - National 200,000.00 0.00 2017-02-08 2017-02-15 2017-04-10 2017-04-10 2017-05-01 2018-01-06 Management Implementation and watershed management. Selection SOK/NEWMAP/CQS/O3/17 / Component 1: Erosion and Consultant Consultancy for sensitization, Pending IDA / 51050 Watershed Management Prior Qualification Open - National 100,000.00 0.00 2017-01-03 2017-01-17 2017-02-14 2017-02-21 2017-03-14 2017-11-19 design and supervision of water Implementation Infrastructure Investments Selection harvesting systems. Component 1: Erosion and Consultant SOK/NEWMAP/CQS/O4/17 / Pending IDA / 51050 Watershed Management Post Qualification Open - National 200,000.00 0.00 2017-02-06 2017-02-08 2017-03-17 2017-03-31 2017-04-21 2019-10-08 Engagement of Focal NGO Implementation Infrastructure Investments Selection SOK/NEWMAP/CQS/O5/17 / Component 1: Erosion and Consultant Consultancy for integrated Pending IDA / 51050 Watershed Management Post Qualification Open - National 100,000.00 0.00 2017-01-16 2017-02-08 2017-03-17 2017-03-31 2017-04-21 2017-07-20 subwatershed management and Implementation Infrastructure Investments Selection monitoring. SOK/NEWMAP/CQS/O6/17 / Component 1: Erosion and Consultant Pending Consultancy for RAP studies for IDA / 51050 Watershed Management Post Qualification Open - National 100,000.00 0.00 2017-02-08 2017-03-03 2017-03-24 2017-03-31 2017-04-21 2017-07-20 Implementation 10 priority project sites Infrastructure Investments Selection SOK/NEWMAP/CQS/O7/17 / Consultant Consultancy for Livelihood Needs Component 4: Project Pending IDA / 51050 Post Qualification Open - National 100,000.00 0.00 2017-01-24 2017-02-08 2017-03-17 2017-03-31 2017-04-21 2017-07-20 Assesment for Communities in Management Implementation Selection all the 10 sites. SOK/NEWMAP/CQS/O8/17 / Consultant Component 4: Project Pending Consultancy for M & E Baseline IDA / 51050 Post Qualification Open - National 100,000.00 0.00 2017-01-10 2017-02-08 2017-03-17 2017-03-31 2017-04-21 2017-07-20 Management Implementation for State Selection SOK/NEWMAP/CQS/O9/17 / Consultant Component 4: Project Pending Consultancy for ESMP Studies IDA / 51050 Post Qualification Open - National 100,000.00 0.00 2017-01-23 2017-02-08 2017-03-17 2017-03-31 2017-04-21 2017-07-20 Management Implementation for the 10 Project Sites Selection KNSPMU/QCBS/17/1/1 / Component 1: Erosion and Engagement of Design and Quality And Cost- IDA / 51050 Watershed Management Prior Open - International 1,258,000.00 0.00 Under Review 2017-03-01 2017-03-29 2017-04-26 2017-09-09 2017-09-16 2017-11-06 2017-12-19 2018-02-22 Supervision Engineering Firm for Based Selection Infrastructure Investments Five (5) erosion sites . KNSPMU/QCBS/17/2/1 / ENGAGEMENT OF DESIGN Component 1: Erosion and Consultant FOR FOUR (4) WATER Pending IDA / 51050 Watershed Management Post Qualification Open - National 295,000.00 0.00 2017-03-01 2017-03-29 2017-04-26 2017-11-22 2017-12-20 2018-01-10 CONSERVATION STRUCTURES Implementation Infrastructure Investments Selection AND MINOR IRRIGATION FACILITIES KNSPMU/IC/17/2/3 / Component 1: Erosion and Consultant GENERATION OF LRID Pending IDA / 51050 Watershed Management Post Qualification Open - National 220,000.00 0.00 2017-03-15 2017-04-12 2017-05-24 2017-06-07 2017-06-21 2018-02-26 FORFLOOD/EROSIONAND Implementation Infrastructure Investments Selection WATERSHED MANAGEMENT Component 1: Erosion and Consultant KNSPMU/QCBS/17/1 / Pending IDA / 51050 Watershed Management Post Qualification Open - National 250,000.00 0.00 2017-02-22 2017-03-22 2017-04-05 2017-10-20 2017-11-06 2017-12-04 Engagement of Focal NGO Implementation Infrastructure Investments Selection SOK/NEWMAP/CQS/011/017 / Consultancy for the GIS survey of Component 1: Erosion and Consultant the state to map erosion sites, Pending IDA / 51050 Watershed Management Post Qualification Open - National 200,000.00 0.00 2017-02-08 2017-03-08 2017-04-13 2017-04-27 2017-05-11 2017-10-08 infrastructure, watersheds, Implementation Infrastructure Investments Selection wetlands and drainage basins in Sokoto state NG-NEWMAP-FPMU-19512-CS- Component 4: Project Quality And Cost- Pending QCBS / Extension of IDA / 51050 Prior Open - International 1,500,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 Management Based Selection Implementation Procurement Consultancy Firm NG-NEWMAP-FPMU-19539-CS- QCBS / Federal Quality Control and Engineering Design Firm (FQCEDF)- EXTENSION- for Component 1: Erosion and Quality And Cost- Pending additional area for the aerial IDA / 51050 Watershed Management Prior Open - International 1,100,000.00 0.00 2017-07-03 2017-07-24 2017-09-06 2017-10-04 2017-11-03 2017-12-08 2018-01-12 2019-01-12 Based Selection Implementation photography/survey of erosion Infrastructure Investments sites Including capacity building and GIS software, archiving system. Page 9 Component 2: Erosion and NG-NEWMAP-FPMU-19561-CS- Watershed Management Quality And Cost- Pending IDA / 51050 Prior Open - International 500,000.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-21 2017-07-21 2017-08-25 2017-09-29 2018-09-29 QCBS / Engagement of IUCN Institutions and Information Based Selection Implementation Services NG-NEWMAP-FPMU-19530-CS- Component 3: Climate Change Quality And Cost- Pending QCBS / Vulnerability Mapping IDA / 51050 Prior Open - International 500,000.00 0.00 2017-09-04 2017-09-25 2017-11-08 2017-12-06 2018-01-05 2018-02-09 2018-03-16 2019-03-16 Response Based Selection Implementation and Action Plan for Nigeria. NG-NEWMAP-FPMU-19533-CS- Consultant Component 3: Climate Change Pending CQS / Development of Climate IDA / 51050 Post Qualification Open - National 100,000.00 0.00 2017-07-22 2017-08-12 2017-09-25 2017-10-25 2017-11-29 2018-05-28 Response Implementation Smart Agriculture. Selection NG-NEWMAP-FPMU-19586-CS- CQS / Technology Needs Consultant Component 3: Climate Change Pending Assessment for Climate Change IDA / 51050 Post Qualification Open - National 100,000.00 0.00 2017-07-22 2017-08-12 2017-09-25 2017-10-25 2017-11-29 2018-05-28 Response Implementation in Nigeria Towards low Carbon Selection Development NG-NEWMAP-FPMU-19580-CS- QCBS / Spatial Baseline Modelling of Electricity Component 3: Climate Change Quality And Cost- Infrastructure for Remote and Off- IDA / 51050 Prior Open - International 3,000,000.00 0.00 Under Review 2017-07-26 2017-08-16 2017-09-29 2017-10-27 2017-11-26 2017-12-31 2018-02-04 2019-02-04 Response Based Selection Grid Power Supply and Demonstration Projects on Low Carbon Off-Grid/mini-grid options NG-NEWMAP-FPMU-19567-CS- QCBS / Consulting services for the development of framework for Component 3: Climate Change Quality And Cost- the adoption of LPG as Low IDA / 51050 Prior Open - International 3,500,000.00 0.00 Under Review 2017-02-06 2017-02-27 2017-04-12 2017-05-10 2017-06-09 2017-07-14 2017-08-18 2018-08-18 Response Based Selection Carbon Alternative to Firewood and Kerosene and Supervision of the Implementation. NG-NEWMAP-FPMU-19578-CS- QCBS / Federal quality control Component 1: Erosion and Quality And Cost- Pending and engineering design firm of IDA / 51050 Watershed Management Prior Open - International 3,000,000.00 0.00 2017-07-17 2017-08-07 2017-09-20 2017-10-18 2017-11-17 2017-12-22 2018-01-26 2019-01-26 Based Selection Implementation erosion control sites Old and Infrastructure Investments New States. NG-NEWMAP-FPMU-19531-CS- Component 2: Erosion and QCBS / Engagement of an Watershed Management Quality And Cost- Pending IDA / 51050 Prior Open - International 600,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 Umbrella NGO in Old and New Institutions and Information Based Selection Implementation States. Services NG-NEWMAP-FPMU-19589-CS- QCBS / Procurement of Component 4: Project Quality And Cost- Pending IDA / 51050 Prior Open - International 2,000,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 Procurement firm in Old and New Management Based Selection Implementation States. NG-NEWMAP-FPMU-19585-CS- Component 2: Erosion and CQS / Procurement of Consultant Watershed Management Pending Consultant for the Spatial IDA / 51050 Post Qualification Open - National 290,000.00 0.00 2017-08-21 2017-09-11 2017-10-25 2017-11-24 2017-12-29 2018-06-27 Institutions and Information Implementation Knowledge Information System Selection Services on Erosion and Watershed ANS/NEWMAP/CS/CQS/2017/0 8 / Consultancy Services for a Consultant Full Environmental & Social Component 4: Project Pending IDA / 51050 Post Qualification Open - National 300,000.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 Impact Assessment (ESIA) for Management Implementation Selection Agulu-Nanka-Oko Gully Erosion Site ANS/NEWMAP/CS/CQS/2017/0 9 / Consultancy Services for a Consultant Component 4: Project Pending Full Resettlement Action Plan IDA / 51050 Post Qualification Open - National 300,000.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 Management Implementation (RAP) for Agulu-Nanka-Oko Gully Selection Erosion Site ANS/NEWMAP/CS/CQS/2017/1 0 / Engagement of Consultant to Consultant Component 4: Project Pending Prepare M&E Baseline Studies IDA / 51050 Post Qualification Open - National 200,000.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 Management Implementation for Agulu-Nanka-Oko Gully Selection Erosion Site ANS/NEWMAP/CS/CQS/2017/1 1 / Engagement of Consultant to Consultant Component 4: Project Pending Prepare Livelihood Needs IDA / 51050 Post Qualification Open - National 200,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Management Implementation Assessment for Agulu-Nanka- Selection Oko Gully Erosion Site ANS/NEWMAP/CS/CQS/2017/1 2 / Consultancy Services for Environmental & Social Consultant Component 4: Project Pending Management Plan (ESMP) and IDA / 51050 Post Qualification Open - National 100,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Management Implementation Abbreviated Resettlement Action Selection Plan (ARAP) for Omagba Downstream Gully Erosion Site KGS/NEWMAP/QCBS/15/01 / Consultancy for Engineering Component 4: Project Quality And Cost- Pending IDA / 51050 Prior Open - International 1,525,000.00 0.00 2016-09-16 2016-09-26 2017-03-14 2017-05-19 2017-05-19 2017-07-07 2017-09-15 2019-03-29 design of Seven sites and Management Based Selection Implementation Supervision of Eight sites INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ABS/NEWMAP/IC/CON/16/01 / Component 1: Erosion and Consultancy for the production of Individual Consultant Pending IDA / 51050 Watershed Management Post Open 35,000.00 0.00 2017-02-03 2017-04-07 2017-04-28 2017-06-02 2017-08-31 Sub-Catchment Management Selection Implementation Infrastructure Investments Planning maps and 3D models ABS/NEWMAP/IC/CON/17/04 / Delineation of the newly Component 4: Project Individual Consultant Under IDA / 51050 Post Open 60,000.00 0.00 2017-02-13 2017-02-07 2017-03-20 2017-03-27 2017-04-24 2017-06-13 prioritized sites(multiple Management Selection Implementation contract) ENS/NEWMAP/CON/IC/15/03 / Component 4: Project Individual Consultant Pending Consultancy for ESMP for Enugu IDA / 51050 Post Open 110,000.00 0.00 2015-06-01 2015-06-29 2015-07-06 2015-07-27 2015-09-25 Management Selection Implementation Ngwo ENS/NEWMAP/CON/IC/15/04 / Component 4: Project Individual Consultant Pending Consultancy for ESMP for IDA / 51050 Post Open 85,000.00 0.00 2015-06-01 2015-07-20 2015-07-27 2015-08-10 2015-10-09 Management Selection Implementation Agbaja Ngwo ENS/NEWMAP/CON/IC/17/01 / Component 4: Project Individual Consultant Pending Consultancy for ESMP for IDA / 51050 Post Open 105,000.00 0.00 2017-02-15 2017-04-14 2017-04-28 2017-05-12 2017-07-11 Management Selection Implementation Umuavulu Abor and Udi Ozalla ENS/NEWMAP/CON/IC/17/02 / Consultancy for ESMP for Onuiyi Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 150,000.00 0.00 2017-07-27 2017-09-14 2017-09-21 2017-10-05 2017-12-04 Nsukka-Alor, Imiki Etiti and Management Selection Implementation Ngene Owele Ohaji. ENS/NEWMAP/CON/IC/15/12 / Component 4: Project Individual Consultant Pending Consultancy for RAP for Enugu IDA / 51050 Post Open 80,000.00 0.00 2015-06-01 2015-07-13 2015-07-20 2015-08-03 2015-10-02 Management Selection Implementation Ngwo ENS/NEWMAP/CON/IC/15/13 / Component 4: Project Individual Consultant Pending Consultancy for RAP for Agbaja IDA / 51050 Post Open 37,000.00 0.00 2015-06-01 2015-06-29 2015-07-13 2015-07-27 2015-09-25 Management Selection Implementation Ngwo Page 10 ENS/NEWMAP/CON/IC/17/03 / Component 4: Project Individual Consultant Pending Consultancy for RAP for IDA / 51050 Post Open 110,000.00 0.00 2017-02-15 2017-04-21 2017-05-05 2017-06-02 2017-08-01 Management Selection Implementation Umuavulu Abor and Udi Ozalla ENS/NEWMAP/CON/IC/17/04 / Consultancy for RAP for Onuiyi Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 150,000.00 0.00 2017-08-10 2017-09-28 2017-10-12 2017-10-26 2017-12-25 Nsukka-Alor, Imiki Etiti and Management Selection Implementation Ngene Owele Ohaji. ENS/NEWMAP/CON/IC/14/06 / Component 4: Project Individual Consultant Pending Engagement of procurement IDA / 51050 Prior Open 100,000.00 0.00 2014-09-01 2014-10-13 2014-10-27 2014-11-17 2015-11-12 Management Selection Implementation consultant for SPMU ENS/NEWMAP/CON/IC/17/05 / Consultancy for M&E Baseline Studies for Umuavulu Abor,Enugu Ngwo,Agbaja Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 300,000.00 0.00 2017-04-17 2017-05-29 2017-06-05 2017-06-19 2017-08-18 Ngwo,Udi Ozalla,Imilike Management Selection Implementation Etiti,Ngene Owelle Ohaji and Anyazuru Ohom Orba (Eight Contracts) ENS/NEWMAP/CON/IC/17/06 / Delineation and development of site specific Catchment Component 4: Project Individual Consultant Pending Management Plans for Enugu IDA / 51050 Post Open 300,000.00 0.00 2017-07-18 2017-08-29 2017-09-05 2017-09-19 2017-11-18 Management Selection Implementation Ngwo,Agbaja Ngwo,Umuavulu Abor,Udi Ozalla, Onuiyi Nsukka,Imilike Etiti,Ngene ENS/NEWMAP/CON/IC/17/07 / Development/Implementation of Component 4: Project Individual Consultant Pending Community Action Plans(CAP) IDA / 51050 Post Open 500,000.00 0.00 2017-07-17 2017-09-04 2017-09-11 2017-09-25 2017-11-24 Management Selection Implementation for 5 communities in Enugu NEWMAP ENS/NEWMAP/CON/IC/17/10 / Consultancy for Livelihood Needs Component 4: Project Individual Consultant Pending Assessment (LNA) for Agbaja IDA / 51050 Post Open 250,000.00 0.00 2017-04-17 2017-06-05 2017-06-12 2017-06-26 2017-08-25 Management Selection Implementation Ngwo,Enugu Ngwo,Umuavulu Abor,Udi Ozalla,Onuiyi Nsukka ENS/NEWMAP/CON/CQS/17/01 / Integrated sub-watershed Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 150,000.00 0.00 2017-06-15 2017-08-03 2017-08-17 2017-08-31 2017-09-30 Management Plans and related Management Selection Implementation technical Guidelines / manuals NG-EDO SPMU-17081-CS-INDV / Consultancy for Environmental Component 4: Project Individual Consultant Pending and Social Safeguard IDA / 51050 Post Open 90,000.00 0.00 2014-05-27 2014-07-07 2014-07-31 2014-08-08 2015-04-27 Management Selection Implementation Sensitization on Erosion Control- on going NG-EDO SPMU-17062-CS-INDV / Consultancy for sensitization on Livelihood, Watershed Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 90,000.00 0.00 2014-05-27 2014-07-07 2014-07-31 2014-08-08 2015-04-27 Management & Engineering Management Selection Implementation designs for Erosion Management- ON GOING NG-EDO SPMU-17064-CS-INDV Component 4: Project Individual Consultant Pending / Consultancy for Livelihood IDA / 51050 Post Open 90,000.00 0.00 2014-07-07 2014-07-07 2014-07-31 2014-08-08 2015-04-27 Management Selection Implementation Needs Assessment-ON-GOING NG-EDO SPMU-17088-CS-INDV / Consultancy for M & E Baseline Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 60,000.00 0.00 2017-01-13 2017-01-13 2017-02-10 2017-02-20 2017-05-03 data for New Sites-Gapiona and Management Selection Implementation Urora NG-EDO SPMU-17085-CS-INDV Component 1: Erosion and Individual Consultant Pending / Consultancy on Bioremediation IDA / 51050 Watershed Management Post Open 30,000.00 0.00 2017-02-06 2017-06-06 2017-06-30 2017-06-30 2017-09-22 Selection Implementation works Infrastructure Investments NG-EDO SPMU-17094-CS-CDS / Consultancy for design of Component 1: Erosion and Pending emergency works for incipient IDA / 51050 Watershed Management Post Direct Selection Direct 100,000.00 0.00 2017-06-06 2017-06-06 2017-06-30 2017-09-22 Implementation gullies requiring rapid action- Infrastructure Investments several NG-EDO SPMU-17040-CS-INDV Component 1: Erosion and / Consultancy for M & E Baseline Individual Consultant Pending IDA / 51050 Watershed Management Post Open 100,000.00 0.00 2017-01-13 2017-01-13 2017-02-10 2017-02-20 2017-05-03 data for New Sites-Ibore, Ewu Selection Implementation Infrastructure Investments and Fugar-Agenebode Road NG-EDO SPMU-17048-CS-INDV Component 1: Erosion and / Consultancy for M & E Baseline Individual Consultant Pending IDA / 51050 Watershed Management Post Open 95,000.00 0.00 2017-02-06 2017-02-06 2017-02-24 2017-02-24 2017-05-23 data for New Sites-Edo College Selection Implementation Infrastructure Investments and Ogiso-Osunde NG-EDO SPMU-17042-CS-INDV Component 1: Erosion and / Consultancy for M & E Baseline Individual Consultant Pending IDA / 51050 Watershed Management Post Open 95,000.00 0.00 2017-02-06 2017-02-06 2017-02-24 2017-02-24 2017-05-23 data for New Sites-Emu, AAU Selection Implementation Infrastructure Investments and Igbe Quarters NG-EDO SPMU-17029-CS-INDV / Consultancy for the detailed Component 1: Erosion and Individual Consultant Pending RAP, and Socio-Economic IDA / 51050 Watershed Management Post Open 95,000.00 0.00 2017-02-06 2017-02-06 2017-02-24 2017-02-24 2017-05-23 Selection Implementation Studies for New Sites-Edo Infrastructure Investments College, Ogiso-Osunde and AAU NG-EDO SPMU-17032-CS-INDV / Consultancy for the detailed Component 1: Erosion and RAP, and Socio-Economic Individual Consultant Pending IDA / 51050 Watershed Management Post Open 95,000.00 0.00 2017-02-06 2017-02-06 2017-02-24 2017-02-24 2017-05-23 Studies for New Sites-EMU, Igbe Selection Implementation Infrastructure Investments quarters and Fugar-Agenebode road NG-EDO SPMU-17037-CS-INDV / Consultancy for the detailed Component 1: Erosion and Individual Consultant Pending ESIA, for Flood and Gully IDA / 51050 Watershed Management Post Open 100,000.00 0.00 2017-01-13 2017-01-13 2017-02-10 2017-02-20 2017-05-03 Selection Implementation Erosion in Edo State-NEW-1- Infrastructure Investments GAPIONA and URORA NG-EDO SPMU-17044-CS-INDV / Consultancy for the detailed Component 1: Erosion and Individual Consultant Pending ESIA, for Flood and Gully IDA / 51050 Watershed Management Post Open 100,000.00 0.00 2017-01-13 2017-01-13 2017-02-10 2017-02-20 2017-05-03 Selection Implementation Erosion in Edo State-NEW-2- Infrastructure Investments IBORE, EWU NG-EDO SPMU-17038-CS-INDV / Consultancy for the detailed Component 1: Erosion and ESIA, for Flood and Gully Individual Consultant Pending IDA / 51050 Watershed Management Post Open 90,000.00 0.00 2017-02-06 2017-02-06 2017-02-24 2017-02-24 2017-05-23 Erosion in Edo State-New Sites- Selection Implementation Infrastructure Investments AAU, Edo College and Ogiso- Osunde NG-EDO SPMU-17050-CS-INDV / Consultancy for the detailed Component 1: Erosion and ESIA, for Flood and Gully Individual Consultant Pending IDA / 51050 Watershed Management Post Open 90,000.00 0.00 2017-02-06 2017-02-06 2017-02-24 2017-02-24 2017-05-23 Erosion in Edo State-New Sites- Selection Implementation Infrastructure Investments Emu-Ohodua, Igbe Quarters and FUGAR AGENEBODE ROAD CRS/NEWMAP/IC/14/29 / Component 4: Project Individual Consultant Under Consultancy for the engagement IDA / 51050 Post Open 50,000.00 0.00 2016-06-07 2015-02-10 2016-06-07 2016-06-07 2016-06-07 2017-06-07 Management Selection Implementation of SPMU Consultant CRS/NEWMAP/IC/16/03 / Conduct needs assesment of Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 50,000.00 0.00 2016-08-19 2016-09-15 2016-09-19 2016-09-26 2016-09-30 livelihood options in Ikot Nkebre/ Management Selection Implementation Lemna/ Fed. Agric Invention sites Page 11 CRS/NEWMAP/IC/16/04/001 / Component 4: Project Individual Consultant Under Consultancy for M & E Baseline IDA / 51050 Post Open 24,060.00 0.00 2016-08-16 2016-09-28 2016-10-18 2016-11-01 2016-12-13 2017-03-15 Management Selection Implementation data for Ikot Nkebre Gully Site CRS/NEWMAP/IC/16/05/001 / Component 4: Project Individual Consultant Under Safeguards (ESMP) studies for IDA / 51050 Post Open 23,000.00 0.00 2016-03-18 2016-04-29 2016-04-25 2016-07-01 2016-05-13 2016-07-08 2016-06-24 2017-03-20 Management Selection Implementation Ikot Nkebre Gully site CRS/NEWMAP/IC/16/06/001 / Component 4: Project Individual Consultant Under Safeguards (RAP) studies for Ikot IDA / 51050 Post Open 23,000.00 0.00 2016-03-18 2016-06-02 2016-04-25 2016-06-27 2016-05-13 2016-07-08 2016-06-24 2017-03-20 Management Selection Implementation Nkebre Gully site CRS/NEWMAP/IC/16/05/002 / Component 4: Project Individual Consultant Under Safeguards (ESMP) studies for IDA / 51050 Post Open 20,000.00 0.00 2016-10-31 2016-10-31 2016-11-16 2017-02-02 2017-02-03 2017-02-14 2017-04-06 Management Selection Implementation LEMNA Agric Gully Erosion site CRS/NEWMAP/IC/16/06/002 / Component 4: Project Individual Consultant Under Safeguards (RAP) studies for IDA / 51050 Post Open 18,000.00 0.00 2016-03-18 2016-10-20 2016-12-15 2016-12-22 2017-01-30 2016-12-22 2017-02-14 2017-04-21 Management Selection Implementation LEMNA Agric Gully Erosion site CRS/NEWMAP/IC/16/04/002 / Component 4: Project Individual Consultant Under Consultancy for M & E Baseline IDA / 51050 Post Open 23,750.00 0.00 2017-03-13 2017-05-11 2017-05-08 2017-05-24 2017-05-22 2017-06-05 2017-06-12 2017-08-23 Management Selection Implementation data for LEMNA Agric Gully Site CRS/NEWMAP/IC/16/04/012 / Engagement of Media Consultant Component 4: Project Individual Consultant Pending for coverage of Project activities IDA / 51050 Post Open 70,000.00 0.00 2017-03-20 2017-05-15 2017-05-30 2017-06-19 2017-08-07 Management Selection Implementation for production and airing of documentaries on Radio and Tv CRS/NEWMAP/IC/16/15 / Support to Communities to Component 4: Project Individual Consultant Pending establish Nurseries, Plant trees, IDA / 51050 Post Open 100,000.00 0.00 2017-05-15 2017-06-12 2017-07-10 2017-08-14 2017-10-18 Management Selection Implementation grasses of assorted Indegenous species for Catchment areas CRS/NEWMAP/IC/16/13 / Consultancy for Design and Component 1: Erosion and Individual Consultant Pending Hosting and management of IDA / 51050 Watershed Management Post Open 10,000.00 0.00 2017-03-27 2017-03-27 2017-03-27 2017-03-27 2017-03-27 Selection Implementation interactive website ion of Civil Infrastructure Investments works CRS/NEWMAP/IC/16/14 / Impact Assessment of Component 4: Project Individual Consultant Pending CRSNEWMAP Gully works IDA / 51050 Post Open 10,000.00 0.00 2017-07-06 2017-08-17 2017-08-21 2017-10-05 2017-11-23 Management Selection Implementation intervention activities from inception till date CRS/NEWMAP/IC/17/01 / Consultancy Study to develop Component 4: Project Individual Consultant and produce a soil map to IDA / 51050 Post Open 30,000.00 37,807.73 Signed 2017-05-15 2017-06-28 2017-07-07 2017-07-24 2017-07-10 2017-08-14 2017-07-20 2017-10-18 Management Selection determine soil vulnerability to Erosion in Cross River State EBNEWMAP/IC/17/02 / Engagement of a Consultant for the facilitation of a Workshop for Component 4: Project Individual Consultant Under the Strengthening of Capacity of IDA / 51050 Post Open 80,000.00 0.00 2017-07-01 2017-07-01 2017-08-21 2017-09-04 2017-10-23 Management Selection Implementation LGA Institutions on Sustaining Operations and Maintenance of project works EBSNEWMAP/IC/CS/17/01 / Engagement of a Consultant for Component 2: Erosion and the facilitation of a Workshop for Watershed Management Individual Consultant Pending the Strenghtening of State & IDA / 51050 Post Open 80,000.00 0.00 2017-03-06 2017-05-06 2017-06-24 2017-07-08 2017-10-13 Institutions and Information Selection Implementation Local Govt. Agencies for Services Preparedness on Disaster Risk Management EBNEWMAP/IC/CS/17/03 / Engagement of Procurement Component 4: Project Individual Consultant Pending IDA / 51050 Prior Open 50,000.00 0.00 2017-02-01 2017-02-22 2017-03-08 2017-03-15 2017-11-17 Consultant for the support of Management Selection Implementation SPMU ANS/NEWMAP/CS/CQS/2016/0 5 / Engagement of Consultant for Component 1: Erosion and Livelihood Needs Assessment in Individual Consultant Pending IDA / 51050 Watershed Management Post Open 99,000.00 0.00 2016-03-16 2016-03-30 2016-04-13 2016-05-11 2016-07-10 4 Erosion Sites: Enugwu-Ukwu, Selection Implementation Infrastructure Investments Ikenga-Ogidi, Ugamuma-Obosi and Abidi-Umuoji ANS/NEWMAP/CS/IC/2016/08 / Engagement of Consultant to Conduct M&E Baseline Studies Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 99,000.00 0.00 2016-04-29 2016-05-13 2016-05-27 2016-06-17 2016-08-16 in 4 Erosion Sites: Enugwu- Management Selection Implementation Ukwu, Ikenga-Ogidi, Ugamuma- Obosi and Abidi-Umuoji ANS/NEWMAP/CS/IC/2016/12 / Engagement of Consultant to Conduct M&E Baseline Studies Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 99,000.00 0.00 2017-01-31 2017-02-14 2017-02-28 2017-03-14 2017-05-13 in 4 Erosion Sites - Ire-Obosi, Management Selection Implementation Nkpor-Flyover, Nnewi-Ichi and Ojoto ANS/NEWMAP/CS/IC/2017/03 / Engagement of Consultant for Component 1: Erosion and Individual Consultant Pending Livelihood Needs Assessment in IDA / 51050 Watershed Management Post Open 60,000.00 0.00 2017-01-10 2017-03-25 2017-04-08 2017-04-29 2017-06-28 Selection Implementation 4 Erosion Sites: Ire-Obosi, Nkpor- Infrastructure Investments Flyover, Nnewi-Ichi and Ojoto ANS/NEWMAP/CS/IC/2017/09 / Engagement of Procurement Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 99,000.00 0.00 2017-02-08 2017-04-05 2017-04-12 2017-05-10 2018-05-05 Consultant to Assist SPMU in Management Selection Implementation Procurement Activities ANS/NEWMAP/CS/SSS/2017/1 1 / Extention of Current Focal Component 1: Erosion and NGO's contract for Additional Pending IDA / 51050 Watershed Management Post Direct Selection Direct 190,000.00 0.00 2017-03-22 2017-06-21 2017-06-30 2019-06-20 Period of 2-years to Implementation Infrastructure Investments Accommodate New Erosion Sites ANS/NEWMAP/CS/SSS/2017/1 2 / Extension of Current Design Component 1: Erosion and and Supervision Firms' Contract Pending IDA / 51050 Watershed Management Prior Direct Selection Direct 2,000,000.00 0.00 2017-03-22 2017-06-19 2017-06-30 2018-06-25 to conclude on-going Site Implementation Infrastructure Investments Designs and Accommodate Additional Gully Designs ABS/NEWMAP/IC/CON/17/01 / Safeguards (ESMP Studies for 6 Component 4: Project Individual Consultant Under IDA / 51050 Post Open 175,000.00 0.00 2017-02-01 2017-03-15 2017-05-03 2017-05-24 2017-08-22 newly prioritized sites ) (Multiple Management Selection Implementation contracts) ABS/NEWMAP/IC/CON/17/02 / Safeguards (RAP Studies for 6 Component 4: Project Individual Consultant Under IDA / 51050 Post Open 168,000.00 0.00 2017-01-02 2017-03-15 2017-04-12 2017-05-24 2017-08-22 newly prioritized sites ) (Multiple Management Selection Implementation contracts) ABS/NEWMAP/IC/CON/17/03 / Component 1: Erosion and Livelihood need assesment Individual Consultant Under IDA / 51050 Watershed Management Post Open 75,000.00 0.00 2017-02-02 2017-03-15 2017-05-03 2017-05-24 2017-08-22 Studies for 6 newly prioritized Selection Implementation Infrastructure Investments sites) (Multiple contracts) ABS/NEWMAP/IC/CON/17/05 / Baseline Studies for Studies for Component 4: Project Individual Consultant Under IDA / 51050 Post Open 125,000.00 0.00 2017-02-01 2017-03-08 2017-05-03 2017-05-24 2017-08-22 6 newly prioritized sites ) Management Selection Implementation (Multiple contracts) Page 12 ABS/NEWMAP/IC/CON/15/01 / Procurement of Individual Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 50,000.00 0.00 2015-02-02 2015-03-02 2016-02-29 2016-03-28 2017-04-10 Procurement Consultant to Management Selection Implementation support the PMU AKS/PMU/IC/17/01 / Engagement of Consultant to conduct needs assessment of Component 4: Project Individual Consultant Pending livelihood options in the IDA / 51050 Post Open 60.00 0.00 2017-03-27 2017-05-22 2017-06-05 2017-06-19 2017-08-14 Management Selection Implementation community: St. Luke's Hospital, Etim Umanah gully erosion sites & IBB flood control site. AKS/PMU/IC/17/02 / Selection of Consultant for M & E Baseline Component 4: Project Individual Consultant Pending data: St. Luke's Hospital, Etim IDA / 51050 Post Open 74.00 0.00 2017-03-27 2017-05-08 2017-06-05 2017-06-19 2017-08-14 Management Selection Implementation Umanah gully erosion sites and IBB flood control site. AKS/PMU/IC/17/03 / Selection of Consultant for ESMP: St. Component 4: Project Individual Consultant Pending Luke's Hospital, Etim Umanah IDA / 51050 Post Open 82.00 0.00 2017-03-20 2017-05-01 2017-05-29 2017-06-12 2017-09-18 Management Selection Implementation gully erosion sites & IBB flood control site. AKS/PMU/IC/17/04 / Selection of Consultant for RAP: St. Luke's Component 4: Project Individual Consultant Pending Hospital, Etim Umanah gully IDA / 51050 Post Open 74.00 0.00 2017-03-20 2017-05-01 2017-05-29 2017-06-12 2017-08-07 Management Selection Implementation erosion sites & IBB flood control site. AKS/PMU/IC/17/05 / Selection Component 4: Project Individual Consultant Pending of Consultant for procurement IDA / 51050 Prior Open 30.00 0.00 2017-03-09 2017-07-10 2017-08-02 2017-09-01 2018-09-14 Management Selection Implementation support DTS/NEWMAP/IC/17/1 / Selection of procurement Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 36,000.00 0.00 2017-04-01 2017-04-01 2017-04-19 2017-06-06 2017-10-11 consultant for the support of Management Selection Implementation SPMU DTS/NEWMAP/IC/17/04 / Consultancy for Environmental Component 4: Project Individual Consultant Pending and Social Management Plan for IDA / 51050 Post Open 200,000.00 0.00 2017-06-01 2017-06-01 2017-06-21 2017-07-07 2017-11-13 Management Selection Implementation five (5) sites(multiple contract of USD100,000 DT/NEWMAP/IC/17/5 / Conduct Component 4: Project Individual Consultant Pending needs assessment of Iivelihood IDA / 51050 Post Open 63,000.00 0.00 2017-06-01 2017-06-01 2017-07-28 2017-08-11 2017-10-03 Management Selection Implementation options in the community DT/NEWMAP/IC/17/6 / Component 4: Project Individual Consultant Pending Consultancy for M & E Baseline IDA / 51050 Post Open 80,000.00 0.00 2017-02-06 2017-02-20 2017-03-06 2017-03-20 2017-05-19 Management Selection Implementation data DTSPMU/IC/17/7 / Consultancy on Resetlement Action Component 4: Project Individual Consultant Pending Plan(RAP) for the five IDA / 51050 Post Open 200,000.00 0.00 2017-05-01 2017-05-01 2017-06-15 2017-06-22 2017-07-06 Management Selection Implementation sites(multiple contract of USD100,000 DTS/NEWMAP/IC/17/8 / Consultancy for Sensitisation on Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 200,000.00 0.00 2017-06-15 2017-06-15 2017-07-19 2017-08-03 2017-09-25 Livelihood, Watershed Management Selection Implementation Management DTS/NEWMAP/IC/17/9 / Component 4: Project Individual Consultant Pending Conduct needs assessement in IDA / 51050 Post Open 40,000.00 0.00 2017-03-01 2017-06-01 2017-07-28 2017-08-11 2017-10-03 Management Selection Implementation relevant MDAs KGSPMU/IC/15/01 / Component 4: Project Individual Consultant Pending Procurement Consultant to IDA / 51050 Post Open 4,500.00 0.00 2017-01-06 2017-03-07 2017-03-21 2017-04-04 2018-01-29 Management Selection Implementation assist SPMU KGSNEWMAP/IC/15/02 / Component 4: Project Individual Consultant Pending Consultancy for web design for IDA / 51050 Post Open 4,500.00 0.00 2017-03-23 2017-03-23 2017-03-23 2017-03-23 2017-03-23 Management Selection Implementation SPMU KGS/NEWMAP/IC/15/03 / Sensitization on Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 82,630.00 0.00 2017-07-12 2017-08-02 2017-08-02 2017-08-30 2017-10-25 Livelihood,Watershed Management Selection Implementation management KGSNEWMAP/IC/15/04 / Needs Component 4: Project Individual Consultant Pending assessment on Livelihood IDA / 51050 Post Open 50,000.00 0.00 2017-06-14 2017-07-05 2017-07-19 2017-08-02 2017-09-22 Management Selection Implementation options in the communities KNSPMU/SVR/IC/17/3/2 / Consultancy for sensitization on household water harvesting, Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 200,000.00 0.00 2017-03-01 2017-06-14 2017-09-13 2017-11-03 2017-12-08 engineering design and Management Selection Implementation alternative livelihoodin watershed mgt. KNSPMU/SVR/IC/17 / Institutional capacity Component 4: Project Individual Consultant Pending development for strategic IDA / 51050 Post Open 40,000.00 0.00 2017-02-28 2017-03-27 2017-05-25 2017-06-01 2017-07-13 Management Selection Implementation environmental issues for Ministry of Environment KNSPMU/SVR/IC/17/1 / Institutional capacity Component 4: Project Individual Consultant Pending development to SEMA on IDA / 51050 Post Open 50,000.00 0.00 2017-02-28 2017-04-27 2017-05-11 2017-06-08 2017-07-27 Management Selection Implementation respond to natural disaster related emergencies. KNSPMU/IC/17/4/3 / Component 4: Project Individual Consultant Under CONSULTANCY FOR IDA / 51050 Post Open 100,000.00 0.00 2017-02-01 2017-02-07 2017-02-16 2017-06-13 2017-03-16 2017-06-01 2017-07-13 Management Selection Implementation PROCUREMENT KNSPMU/IC/17/17 / Component 4: Project Individual Consultant Pending CONSULTANCY FOR RAP(5 IDA / 51050 Post Open 195,000.00 0.00 2017-02-03 2017-02-20 2017-05-25 2017-07-20 2017-08-29 Management Selection Implementation Erosion Sites) KNSPMU/IC/17/1/8 / Component 4: Project Individual Consultant Pending Consultancy for RAP for 4 Water IDA / 51050 Post Open 195,000.00 0.00 2017-01-12 2017-06-17 2017-06-17 2017-08-24 2017-08-24 Management Selection Implementation Conservation site KNSPMU/IC/17/19 / Component 4: Project Individual Consultant Pending Consultancy for Watershed IDA / 51050 Post Open 150,000.00 0.00 2017-02-28 2017-02-28 2017-04-26 2017-06-20 2017-07-18 Management Selection Implementation Management Expart GMS/NEWMAP/IC/17/01 / consultant for Preventive erosion Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 150,000.00 0.00 2017-03-27 2017-04-26 2017-04-26 2017-05-24 2017-08-22 advocacy enviromental & social Management Selection Implementation adaptability. GMS/NEWMAP/IC/17/02 / Consultancy for need assesment Component 4: Project Individual Consultant Pending of livelihood option in five 5 IDA / 51050 Post Open 5,000.00 0.00 2017-03-27 2017-05-01 2017-05-08 2017-05-22 2017-07-17 Management Selection Implementation communities with newmap intervention. GMS/NEWMAP/IC/17/03 / Consultancy for public Component 1: Erosion and awareness/sensitization Individual Consultant Pending IDA / 51050 Watershed Management Post Open 140,000.00 0.00 2017-04-24 2017-05-29 2017-06-05 2017-06-26 2017-09-24 engineering designs and Selection Implementation Infrastructure Investments alternative livelyhood in erosion and watershed management Page 13 GMS/NEWMAP/IC/17/06 / Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 196,000.00 0.00 2017-05-30 2017-07-04 2017-07-11 2017-08-01 2017-09-26 Consultancy for M&E baseline. Management Selection Implementation GMS/NEWMAP/IC/170/7 / Consultancy for safeguards GMP Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 197,000.00 0.00 2017-05-29 2017-05-29 2017-05-29 2017-05-29 2017-05-29 studies for GSU, FCE(TECH), Management Selection Implementation etc. GMS/NEWMAP/IC/17/08 / Component 4: Project Individual Consultant Pending Consultancy for Safe guard s IDA / 51050 Post Open 170,000.00 0.00 2017-05-29 2017-07-03 2017-07-10 2017-07-24 2017-11-21 Management Selection Implementation RAP studies for five 5 sites GMS/NEWMAP/IC/17/11 / Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 100,000.00 0.00 2017-05-29 2017-07-03 2017-07-10 2017-07-24 2018-06-09 SPMU Procurement consultant Management Selection Implementation PLSNEWMAP/IC/17/02 / Consultancy on Community Component 4: Project Individual Consultant Pending consultation, Pubic Education & IDA / 51050 Post Open 99,000.00 0.00 2017-02-28 2017-04-04 2017-04-11 2017-05-02 2017-07-31 Management Selection Implementation Erosion Management and awareness Techniques PLSNEWMAP/IC/17/03 / Baseline survey/ Community Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 30,000.00 0.00 2017-03-06 2017-04-10 2017-04-17 2017-05-01 2017-07-30 needs assessment and capacity Management Selection Implementation building PLSNEWMAP/IC/17/04 / Component 1: Erosion and Consultancy Services on Individual Consultant Under IDA / 51050 Watershed Management Post Open 99,000.00 0.00 2017-03-08 2017-03-08 2017-03-08 2017-03-08 2017-03-08 bathymetry Survey and Selection Implementation Infrastructure Investments catchment management PLSNEWMAP/IC/17/07 / Conduct NEEDS assessment in relevant MDAs, PFMU and Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 75,000.00 0.00 2017-04-04 2017-04-04 2017-04-04 2017-04-04 2017-04-04 LGAs, for Institutional Capacity Management Selection Implementation development for strategic environmental issues PLSNEWMAP/IC/17/09 / Component 4: Project Individual Consultant Pending Consultancy for RAP for five IDA / 51050 Post Open 125,000.00 0.00 2017-02-05 2017-02-05 2017-02-05 2017-02-05 2017-02-05 Management Selection Implementation selected sites PLSNEWMAP/IC/17/10 / Component 2: Erosion and Consultancy for sensitization on Watershed Management Individual Consultant Under livelihhod and Watershed IDA / 51050 Post Open 125,000.00 0.00 2017-02-05 2017-02-05 2017-02-05 2017-08-28 2017-10-30 Institutions and Information Selection Implementation management for five selected Services sites PLSNEWMAP/CQS/17/03 / Component 4: Project Individual Consultant Pending Consultancy for valuation and IDA / 51050 Post Open 200,000.00 0.00 2017-04-20 2017-04-20 2017-05-10 2017-07-13 2017-08-03 Management Selection Implementation resettlement implementation SOK/NEWMAP/IC/10/17 / Component 4: Project Individual Consultant Pending Engagement of Procurement IDA / 51050 Post Open 50,000.00 0.00 2017-02-08 2017-03-15 2017-03-29 2017-04-26 2018-04-26 Management Selection Implementation consultant. KNSPMU/IC/17/3/1 / Procurement & implementation of Component 4: Project Individual Consultant Pending IDA / 51050 Post Open 80,000.00 0.00 2017-02-28 2017-04-04 2017-04-11 2017-05-09 2018-01-14 Household and community water Management Selection Implementation harvesting activities Component 2: Erosion and NG-NEWMAP-FPMU-19571-CS- Watershed Management Pending CDS / Engagement of an IDA / 51050 Prior Direct Selection Direct 85,000.00 0.00 2017-07-10 2017-07-20 2017-09-23 2018-03-22 Institutions and Information Implementation Umbrella NGO -EXTENSION Services NG-NEWMAP-FPMU-19587-CS- Component 1: Erosion and Individual Consultant Pending INDV / Engagement of a Senior IDA / 51050 Watershed Management Post Open 50,000.00 0.00 2017-07-29 2017-09-16 2017-10-07 2017-11-11 2018-05-10 Selection Implementation Engineering Advisor Infrastructure Investments NG-NEWMAP-FPMU-19525-CS- Component 4: Project Individual Consultant Pending INDV / Engagement of HR Firm IDA / 51050 Post Open 90,000.00 0.00 2017-08-31 2017-10-19 2017-11-09 2017-12-14 2018-06-12 Management Selection Implementation International and National. NG-NEWMAP-FPMU-19524-CS- INDV / Activities towards Component 3: Climate Change Individual Consultant Pending IDA / 51050 Post Open 500,000.00 0.00 2017-01-30 2017-03-20 2017-04-10 2017-05-15 2017-11-11 establishing and issuance of Response Selection Implementation Nigeria Green Bond. NG-NEWMAP-FPMU-19565-CS- INDV / Consultancy Services for Component 3: Climate Change Individual Consultant Pending IDA / 51050 Post Open 100,000.00 0.00 2017-01-30 2017-03-20 2017-04-10 2017-05-15 2017-11-11 the preparation of Restructuring Response Selection Implementation paper for NEWMAP. Component 2: Erosion and NG-NEWMAP-FPMU-19563-CS- Watershed Management Individual Consultant Pending INDV / Engagement of EA Expert IDA / 51050 Post Open 75,000.00 0.00 2017-01-09 2017-02-27 2017-03-20 2017-04-24 2017-10-21 Institutions and Information Selection Implementation Advisor (International) Services NG-NEWMAP-FPMU-19662-CS- Component 4: Project Individual Consultant Under INDV / Engagement of Expert for IDA / 51050 Post Open 40,000.00 0.00 2017-08-15 2017-10-09 2017-10-03 2017-10-24 2017-11-28 2018-05-27 Management Selection Implementation Mid-Term Review NG-NEWMAP-FPMU-19560-CS- Component 4: Project Individual Consultant Pending INDV / Engagement of IDA / 51050 Post Open 45,000.00 0.00 2017-08-08 2017-09-26 2017-10-17 2017-11-21 2018-05-20 Management Selection Implementation Ombudsman NG-NEWMAP-FPMU-19583-CS- Component 4: Project Individual Consultant Pending INDV / Re-imaging of NEWMAP IDA / 51050 Post Open 50,000.00 0.00 2017-08-17 2017-10-05 2017-10-26 2017-11-30 2018-05-29 Management Selection Implementation interactive Website NG-NEWMAP-FPMU-19522-CS- Component 4: Project Pending CDS / Update of accounting IDA / 51050 Post Direct Selection Direct 30,000.00 0.00 2017-10-24 2017-11-03 2018-01-07 2018-07-06 Management Implementation system NG-EBONYI SPMU-26141-CS- CDS / Resettlement Action Plan (RAP) Implementation Corridor Component 1: Erosion and Pending Setting-out for Odunukwe- Nkaliki IDA / 51050 Watershed Management Post Direct Selection Direct 47.62 0.00 2017-08-24 2017-09-03 2017-10-22 2017-12-21 Implementation Hatchery Road, Iyiokwu- Infrastructure Investments Abakaliki Int'l Mkt Flood, Ebia River and Iyi-Udele Flood Sites. AKS/PMU/IND/17/05 / Selection Component 4: Project Individual Consultant Pending of Consultant for procurement IDA / 51050 Prior Open 30.00 0.00 2017-09-13 2017-10-07 2017-10-09 2017-10-30 2018-10-29 Management Selection Implementation support ANS/NEWMAP/CS/INDV/2017/0 3 / Engagement of Consultant to Component 4: Project Individual Consultant Pending Prepare M&E Baseline Studies IDA / 51050 Post Open 50,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Management Selection Implementation for Omagba Downstream Gully Erosion Site ANS/NEWMAP/CS/INDV/2017/0 4 / Engagement of Consultant to Component 1: Erosion and Individual Consultant Pending Prepare Livelihood Needs IDA / 51050 Watershed Management Post Open 50,000.00 0.00 2017-10-06 2017-11-24 2017-12-15 2018-01-19 2018-07-18 Selection Implementation Assessment for Omagba Infrastructure Investments Downstream Gully Erosion Site KGSNEWMAP/IC/15/041 / Component 1: Erosion and Engagement of Consultant for Individual Consultant Pending IDA / 51050 Watershed Management Post Open 64,065.00 0.00 2017-07-17 2017-09-04 2017-09-25 2017-10-30 2018-04-28 ESMP for Ozuri and Agassa Selection Implementation Infrastructure Investments Erosion sites Page 14 KGSNEWMAP/IC/15/042 / Component 1: Erosion and Engagement of Consultant for Individual Consultant Pending IDA / 51050 Watershed Management Post Open 64,065.00 0.00 2017-07-19 2017-09-06 2017-09-27 2017-11-01 2018-04-30 ESMP for Etahi and Omigbo Selection Implementation Infrastructure Investments Erosion sites KGSNEWMAP/IC/15/043 / Component 1: Erosion and Engagement of Consultant for Individual Consultant Pending IDA / 51050 Watershed Management Post Open 64,065.00 0.00 2017-07-21 2017-09-08 2017-09-29 2017-11-03 2018-05-02 ESMP for Adumu Road and Selection Implementation Infrastructure Investments Ankpa Erosion Sites KGSNEWMAP/IC/15/044 / Component 1: Erosion and Engagement of Consultant for Individual Consultant Pending IDA / 51050 Watershed Management Post Open 64,065.00 0.00 2017-07-24 2017-09-11 2017-10-02 2017-11-06 2018-05-05 ESMP for Ogane Aji and Selection Implementation Infrastructure Investments Ugwolawo Erosion Sites KGSNEWMAP/IC/15/061 / Component 1: Erosion and Engagement of Consultant for Individual Consultant Pending IDA / 51050 Watershed Management Post Open 64,065.00 0.00 2017-07-17 2017-09-04 2017-09-25 2017-10-30 2018-04-28 RAP for Ozuri and Agassa Selection Implementation Infrastructure Investments Erosion sites KGSNEWMAP/IC/15/062 / Component 1: Erosion and Engagement of Consultant for Individual Consultant Pending IDA / 51050 Watershed Management Post Open 64,065.00 0.00 2017-07-19 2017-09-06 2017-09-27 2017-11-01 2018-04-30 RAP for Etahi and Omigbo Selection Implementation Infrastructure Investments Erosion sites KGSNEWMAP/IC/15/063 / Component 1: Erosion and Engagement of Consultant for Individual Consultant Pending IDA / 51050 Watershed Management Post Open 64,065.00 0.00 2017-07-21 2017-09-08 2017-09-29 2017-11-03 2018-05-02 RAP for Adumu Road and Ankpa Selection Implementation Infrastructure Investments Erosion Sites KGSNEWMAP/IC/15/064 / Component 1: Erosion and Engagement of Consultant for Individual Consultant Pending IDA / 51050 Watershed Management Post Open 64,065.00 0.00 2017-07-24 2017-09-11 2017-10-02 2017-11-06 2018-05-05 RAP for Ogane Aji and Ugwolawo Selection Implementation Infrastructure Investments Erosion Sites ANS/NEWMAP/CS/INDV/17-02 / Consultancy Services for Component 4: Project Individual Consultant Pending Resettlement Action Plan (RAP) IDA / 51050 Post Limited 30,000.00 0.00 2017-10-09 2017-10-14 2017-11-04 2017-12-09 2018-06-07 Management Selection Implementation for Abagana Redesigned Erosion Works - Addendum Page 15