Procurement Plan for WBADMI Project (P105311) I. General 1. Bank’s approval Date of the procurement Plan Aug 25 2011 2. Date of General Procurement Notice: May 10 2010 3. Period covered by this procurement plan: The procurement period of project covered from year 1st June 2011 to 31st May 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above 1000 000 LIB above 200 000 2. NCB (Goods) >50 000 & < 1000 000 3. NCB (Non-Consultant Services) Do 4. ICB (Works) Above 5000 000 5. NCB (Works) Upto 5000 000 6. National shopping < 50 000 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Project is using a procurement manual, which is agreed with World Bank 5. Any Other Special Procurement Arrangements: Retroactive financing is applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of Nil - no - - the ICB (Works) July 9, 2010 Summary of Nil Nil the ICB (Goods) Summary of 22 150 no post 10 pkgs the NCB are (Works) through shopping Summary of Nil All goods the NCB are (Goods) through shopping (75 pkgs) Summary of Nil Nil the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 300,000 2. Single Source (Firms) Above USD 100 000 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Retroactive financing applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 1.4 4 - All post number of review contracts that will be let under QCBS Summary of 5.5 4 Prior Two Post number of review contracts that July 9, 2010 will be let under other methods July 9, 2010 PROCUREMENT India : IN West Bengal Accelerated Development of Minor Irrigation PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-09-06 2018-10-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P105311 GPN Date: Project Name: IN West Bengal Accelerated Development of Minor Irrigation Loan / Credit No: IBRD / 80900, IDA / 50140 West Bengal Accelerated Development of Minor Irrigation Project, DPMU - JALPAIGURI, DPMU Birbhum, DPMU, SOUTH 24 PARGANAS, DPMU Hooghly, DPMU - Darjeeling, DPMU - Coochbehar, DPMU - PASCHIM Medinipur, DPMU - PURBA MEDINIPUR, DPMU Nadia, DPMU Bardhaman, DPMU Purulia, DPMU, Howrah, SWID, DPMU - Bankura, DPMU - North 24 Parganas, DPMU - Malda, DPMU UTTAR Dinajpur, DPMU - Dakshin Dinajpur Executing Agency(ies): WORKS Bid Evaluation Activity Reference Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificati Process Prequalification Bidding Documents Report and Contract No. / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process on (Y/N) Status Evaluation Report as Issued Recommendation Completion (US$) Documents Justification / Invitation Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DPMU BIRBHUM- 15970-CW-RFB / Construction of Bhabanandapur_Gamarkun Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- da, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 02 07 18 18 22 21 Bhabanandapur_Haripur, ation Gangmuri, Kushma- Natungram, Nutangram Check Dam cum Weir under WBADMI Project in Birbhum District. IN-DPMU - SOUTH P- 16093-CW-RFB / All in one bid for construction of 1 no Water Detention Structures (WDS) Sub Pending Request for Single Stage - 2017-07- 2017-07- 2017-08- 2017-09- 2017-10- 2018-01- Projects at Kailashnagar IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 28 31 30 29 20 18 WDS at Mouza- ation Kailashnagar (J.L.-118) , Block -Kultali in the District of South 24 Parganas under WBADMI Project. IN-DPMU - SOUTH P- 16104-CW-RFB / All in one Bid for Construction of 3 nos WDS Sub Projects at Madhukhali WDS(Jl- Pending 170) , Garkhali Paschim Request for Single Stage - 2017-07- 2017-07- 2017-08- 2017-09- 2017-10- 2018-04- IBRD / 80900 Post Open - National 0.00 Implement WDS (Jl-105) , Dakshin Bids One Envelope 28 31 30 29 20 18 ation Redokhali WDS (Jl-106), Block -Canning I , in the District of South 24 Parganas under WBADMI Project. IN-DPMU - SOUTH P- 16106-CW-RFB / All in one Bid for Construction of 2 nos Water Detention Structures (WDS) Sub Pending Request for Single Stage - 2017-07- 2017-07- 2017-08- 2017-09- 2017-10- 2018-01- Projects at Narayangar IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 28 31 30 29 20 18 Dakshin WDS (Jl-81) and ation Narayangar Uttar WDS (Jl-81), Block -Canning-I in the District of South 24 Pgs under WBADMIP IN-DPMU - SOUTH P- 16107-CW-RFB / All in one Bid for Construction of 3 nos Water Detention Structure (WDS) Sub Projects at Gopalpur Pending Request for Single Stage - 2017-07- 2017-07- 2017-08- 2017-09- 2017-10- 2018-04- Dakshin WDS(Jl-99) , IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 28 31 30 29 20 18 Sundipukuria WDS(Jl-85) ation , Ramamari WDS (J.L.- 88) , Block - Canning- I in the District of South 24 Parganas under WBADMI Project. IN-DPMU - DARJEELING-20093-CW- Pending Request for Single Stage - 2017-07- 2017-07- 2017-08- 2017-09- 2017-10- 2018-04- RFB / Restoration & IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 11 16 27 26 31 29 repair works of DPMU , ation Darjeeling office building under WBADMI Project. IN-DPMU - DARJEELING-20100-CW- RFB / Construction and installation including supply ,electrical works Under and energisation of 3 Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 0.00 Implement nos.TW(H) at (1 no. Bids One Envelope 24 29 09 09 13 12 ation TW(H) cluster structures at Uttar Bansgaon Kismat mouza, Phansidewa G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Uttar Ban IN-DPMU - DARJEELING-20110-CW- RFB / Construction and installation including supply ,electrical works Under and energisation of 3 Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 0.00 Implement nos.TW(H) at (1 no. Bids One Envelope 24 29 09 09 13 12 ation TW(H) cluster structures at Uttar Bansgaon Kismat mouza, Phansidewa G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Uttar Ban IN-DPMU - DARJEELING-20114-CW- RFB / Construction and installation including supply ,electrical works Under and energisation of 3 Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 0.00 Implement nos.TW(H) at (1 no. Bids One Envelope 24 29 09 09 13 12 ation TW(H) cluster structures at Madhya Bansgaon mouza, Chathat G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Madhya Bansgaon- IN-DPMU - VI DARJEELING-20116-CW- RFB / Construction and installation including supply ,electrical works Under and energisation of 3 Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 0.00 Implement nos.TW(H) at (1 no. Bids One Envelope 24 29 09 09 13 12 ation TW(H) cluster structures at Madhya Bansgaon mouza, Chathat G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Madhya Bansgaon- IX IN-DPMU - DARJEELING-20117-CW- RFB / Construction and installation including supply ,electrical works Under and energisation of 3 Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 0.00 Implement nos.TW(H) at (1 no. Bids One Envelope 24 29 09 09 13 12 ation TW(H) cluster structures at Madhya Bansgaon mouza, Chathat G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Madhya Bansgaon- IN-DPMU - XI DARJEELING-20118-CW- RFB / Construction and installation including supply ,electrical works Under and energisation of 4 Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 0.00 Implement nos.TW(H) at (1 no. Bids One Envelope 24 29 09 09 13 12 ation TW(H) cluster structures at Madhya Bansgaon mouza, Chathat G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Madhya Bansgaon- IN-DPMU - XI DARJEELING-21577-CW- RFB / Construction and installation including supply ,electrical works and energisation of 2 Pending Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- nos.TW(E) at (1 no. TW(E) IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 24 29 09 09 13 12 cluster structures at ation Nipania mouza Changa Panighata G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-I TW(E) scheme IN-DPMU - DARJEELING-21579-CW- RFB / Construction and installation including supply ,electrical works and energisation of 2 Pending Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- nos.TW(E) at (1 no. TW(E) IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 24 29 09 09 13 12 cluster structures at ation Nipania mouza Changa Panighata G.P,M irik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-II TW(E) schem IN-DPMU - DARJEELING-21581-CW- RFB / Construction and installation including supply ,electrical works and energisation of 2 Pending Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- nos.TW(E) at (1 no. TW(E) IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 24 29 09 09 13 12 cluster structures at ation Nipania mouza Changa Panighata G.P,M irik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-III TW(E) sche IN-DPMU - DARJEELING-21582-CW- RFB / Construction and installation including supply ,electrical works and energisation of 3 Pending Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- nos.TW(E) at (1 no. TW(E) IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 24 29 09 09 13 12 cluster structures at ation Nipania mouza Changa Panighata G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-IV TW(E) scheme Page 1 IN-DPMU - DARJEELING-21583-CW- RFB / Construction and installation including supply ,electrical works and energisation of 3 Pending Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- nos.TW(E) at (1 no. TW(E) IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 24 29 09 09 13 12 cluster structures at ation Nipania mouza Changa Panighata G.P,M irik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-V TW(E) scheme IN-DPMU - DARJEELING-21584-CW- RFB / Construction and installation including supply ,electrical works Pending and energisation of 3 Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 0.00 Implement nos.TW(E) at (1 no. TW(E) Bids One Envelope 25 30 10 10 14 13 ation cluster structures at Nipania mouza Maniram G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-VI TW(E) scheme IN-DPMU - DARJEELING-21585-CW- RFB / Construction and installation including supply ,electrical works Pending and energisation of 3 Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 0.00 Implement nos.TW(E) at (1 no. TW(E) Bids One Envelope 26 31 11 11 15 14 ation cluster structures at Nipania mouza Maniram G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-VII TW(E) scheme IN-DPMU - DARJEELING-21587-CW- RFB / Construction and installation including supply ,electrical works Pending and energisation of 3 Request for Single Stage - 2017-07- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 0.00 Implement nos.TW(E) at (1 no. TW(E) Bids One Envelope 28 02 13 13 17 16 ation cluster structures at Nipania mouza Maniram G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-VIII TW(E) scheme IN-DPMU - DARJEELING-21591-CW- RFB / Construction and installation including supply ,electrical works Pending and energisation of 3 Request for Single Stage - 2017-07- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 0.00 Implement nos.TW(E) at (1 no. TW(E) Bids One Envelope 27 01 12 12 16 15 ation cluster structures at Nipania mouza Maniram G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-IX TW(E) scheme IN-DPMU - DARJEELING-21594-CW- RFB / Construction and installation including supply ,electrical works and energisation of 2 Pending Request for Single Stage - 2017-07- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- nos.TW(E) at (1 no. TW(E) IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 27 01 12 12 16 15 cluster structures at ation Rangamohan mouza, Saureni-II G.P,M irik Block,Darjeeling District under WBADMIP,Name of scheme Rangamohan-I TW(E) schem IN-DPMU - DARJEELING-21596-CW- RFB / Construction and installation including supply ,electrical works and energisation of 2 Pending Request for Single Stage - 2017-07- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- nos.TW(E) at (1 no. TW(E) IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 27 01 12 12 16 15 cluster structures at ation Rangamohan mouza, Saureni-II G.P,M irik Block,Darjeeling District under WBADMIP,Name of scheme Rangamohan-II TW(E) sche IN-DPMU - DARJEELING-21599-CW- RFB / Constraction of Pending Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- Elley jhora SFMI scheme IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 26 31 11 11 15 14 at Mirik Khasmahal ation Mouza, Duptin GP in Mirik Block,District Darjeeling IN-DPMU - DARJEELING-21600-CW- RFB / Constraction of Pending Gattey jhora SFMI scheme Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 0.00 Implement at Mirik Khasmahal Bids One Envelope 25 30 10 10 14 13 ation Mouza Pahila Gaon School dara II GP in Mirik Block,District Darjeeling IN-DPMU - JALPAIGURI- 21617-CW-RFB / Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-09- 2017-09- 2018-03- Construction & installation IBRD / 80900 Post Open - National 203,299.62 Completed Bids One Envelope 26 27 05 12 29 28 of Solar power Operated 10 Nos. Tube Well IN-DPMU - JALPAIGURI- 21655-CW-RFB / Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-09- 2017-09- 2018-03- Construction & installation IBRD / 80900 Post Open - National 155,125.69 Completed Bids One Envelope 26 27 05 12 29 28 of Solar power Operated 8 Nos. Tube Well IN-DPMU - JALPAIGURI- 21676-CW-RFB / Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-09- 2017-09- 2018-03- Construction & installation IBRD / 80900 Post Open - National 155,125.69 Completed Bids One Envelope 26 27 05 12 29 28 of Solar power Operated 8 Nos. Tube Well IN-DPMU - JALPAIGURI- 21684-CW-RFB / Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-09- 2017-09- 2018-03- Construction & installation IBRD / 80900 Post Open - National 155,760.66 Completed Bids One Envelope 26 27 05 12 29 28 of Solar power Operated 8 Nos. Tube Well IN-DPMU - JALPAIGURI- 21702-CW-RFB / Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-09- 2017-09- 2018-03- Construction & installation IBRD / 80900 Post Open - National 150,944.38 Completed Bids One Envelope 26 27 05 12 29 28 of Solar power Operated 8 Nos. Tube Well IN-DPMU - JALPAIGURI- 21703-CW-RFB / Under Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-09- 2017-09- 2018-03- Construction & installation IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 26 27 05 12 29 28 of Solar power Operated 8 ation Nos. Tube Well IN-DPMU - JALPAIGURI- 21704-CW-RFB / Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-09- 2017-09- 2018-03- Construction & installation IBRD / 80900 Post Open - National 153,222.78 Completed Bids One Envelope 26 27 05 12 29 28 of Solar power Operated 8 Nos. Tube Well IN-DPMU - JALPAIGURI- 21705-CW-RFB / Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-09- 2017-09- 2018-03- Construction & installation IBRD / 80900 Post Open - National 152,525.27 Completed Bids One Envelope 26 27 05 12 29 28 of Solar power Operated 8 Nos. Tube Well IN-DPMU - JALPAIGURI- 21706-CW-RFB / Under Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-09- 2017-09- 2018-03- Construction & installation IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 26 27 05 12 29 28 of Solar power Operated 4 ation Nos. Tube Well IN-DPMU - JALPAIGURI- 21707-CW-RFB / Pending Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-09- 2017-09- 2018-03- Construction & installation IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 26 27 05 12 29 28 of Solar power Operated 5 ation Nos. Tube Well IN-DPMU - B-23424-CW- RFB / All in one Bid for construction of Bhadda-I & Bhadda-II Tube Well (11 Request for Single Stage - 2017-09- 2017-09- 2017-10- 2017-11- 2017-12- 2018-06- IBRD / 80900 Post Open - National 0.00 Canceled nos) at Mouza-Bhada, J.L.- Bids One Envelope 01 06 18 17 22 20 146 Block-Ausgram-I under WBADMI Project under Burdwan District IN-DPMU - B-23667-CW- RFB / All in one Bid for construction of Bhadda-III Pending & Bhadda-V Tube Well Request for Single Stage - 2017-09- 2017-09- 2017-10- 2017-11- 2017-12- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (11 nos) at Mouza-Bhada, Bids One Envelope 01 06 18 17 22 20 ation J.L.-146 Block-Ausgram-I under WBADMI Project under Burdwan District IN-DPMU - B-23671-CW- RFB / All in one Bid for construction of Brajapur-I Pending & Brajapur-II Tube Well Request for Single Stage - 2017-09- 2017-09- 2017-10- 2017-11- 2017-12- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (10nos) at Mouza-Brajapur, Bids One Envelope 01 06 18 17 22 20 ation J.L.-145 Block-Ausgram-I under WBADMI Project under Burdwan District IN-DPMU - B-23672-CW- RFB / All in one Bid for construction of Gonna-I & Pending Gonna-II Tube Well (13 Request for Single Stage - 2017-09- 2017-09- 2017-10- 2017-11- 2017-12- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement nos) at Mouza-Gonna, J.L.- Bids One Envelope 01 06 18 17 22 20 ation 134 Block-Ausgram-I under WBADMI Project under Burdwan District IN-DPMU - B-23673-CW- RFB / All in one Bid for construction of Gonna-III & Kayrapur-III Tube Well Pending Request for Single Stage - 2017-09- 2017-09- 2017-10- 2017-11- 2017-12- 2018-06- (10 nos) at Mouza-Gonna, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 01 06 18 17 22 20 Jadabganj J.L.-134, 150 ation Block-Ausgram-I under WBADMI Project under Burdwan District IN-DPMU - B-23675-CW- RFB / All in one Bid for construction of Kayrapur- Pending IV & Kayrapur-V Tube Request for Single Stage - 2017-09- 2017-09- 2017-10- 2017-11- 2017-12- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement Well (12 nos) at Mouza- Bids One Envelope 01 06 18 17 22 20 ation Kayrapur, J.L.150, Block- Ausgram-I under WBADMI Project under Burdwan District Page 2 IN-DPMU - PASCHIM- 24228-CW-RFB / Irrigation Potential Development in Watershed (PAS2PMWS09) by Constructing various Type of M.I Schemes ( Pending Request for Single Stage - 2017-09- 2017-09- 2017-10- 2017-11- 2018-01- 2018-07- Pump Dugwell,Tube IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 17 29 28 02 01 Well,WDS & CheckDam) ation at Garhbeta-II Blcok within Paschim Medinipur District under Executive Engineer (A-I) Midnapore (A-I) Division IN-DPMU - PASCHIM- 24377-CW-RFB / Construction Water Pending Detention Structure (WDS) Request for Single Stage - 2017-09- 2017-09- 2017-10- 2017-11- 2018-01- 2018-07- IBRD / 80900 Post Open - National 0.00 Implement at Mouza- Chakla, Block- Bids One Envelope 12 17 29 28 02 01 ation Keshiyary, J.L No. 103 G.P- Baghasti Under DPMU, Paschim Medinipur IN-DPMU BIRBHUM- 24432-CW-RFB / Construction of Kharikabad- I PDW, Kharikabad-II Under PDW, Kharikabad-III Request for Single Stage - 2017-08- 2017-08- 2017-10- 2017-11- 2017-12- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement PDW, Kharikabad-IV PDW, Bids One Envelope 18 23 04 03 08 06 ation Kharikabad-V PDW, Kharikabad-VI PDW under WBADMI Project in Birbhum District. IN-DPMU BIRBHUM- 24436-CW-RFB / Construction of Kharikabad- VII PDW, Kharikabad-VIII Under PDW, Kharikabad-IX PDW, Request for Single Stage - 2017-08- 2017-08- 2017-10- 2017-11- 2017-12- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement Kharikabad-X PDW, Bids One Envelope 18 23 04 03 08 06 ation Kharikabad-XI PDW, Kharikabad-XII PDW under WBADMI Project in Birbhum District. IN-DPMU BIRBHUM- 24439-CW-RFB / Construction of Kharikabad- XIII PDW, Kharikabad-XIV Under Request for Single Stage - 2017-08- 2017-08- 2017-10- 2017-11- 2017-12- 2018-06- PDW, Kharikabad-XV IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 04 03 08 06 PDW, Kharikabad-XVI ation PDW, Kharikabad-XVII PDW under WBADMI Project in Birbhum District. IN-DPMU - PURULIA- 25143-CW-RFB / Construction of Pump Dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Ulda PDW-02 Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Ulda Block Barabazar in ation the district of Purulia under WBADMIP IN-DPMU - PURULIA- 25210-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Ulda PDW-03, Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 29 28 -Ulda, Block- barabazar ation under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25216-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Ulda PDW-07, Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 -Ulda, Block- barabazar ation under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25329-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Ulda PDW-08, Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 -Ulda, Block- barabazar ation under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25331-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Kuda PDW-02, Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 -Kuda, Block- Manbazar-I ation under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25332-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Kuda PDW-03, Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 22 21 -Kuda, Block- Manbazar-I ation under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25335-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Kuda PDW-04, Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 -Kuda, Block- Manbazar-I ation under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25336-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Kuda PDW-06, Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 -Kuda, Block- Manbazar-I ation under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25338-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Kuda PDW-08, Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 -Kuda, Block- Manbazar-I ation under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25339-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Banjora PDW-03, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Banjora, Block- ation Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25340-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Banjora PDW-04, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Banjora, Block- ation Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25341-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Banjora PDW-05, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Banjora, Block- ation Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25342-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Banjora PDW-06, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Banjora, Block- ation Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25343-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Banjora PDW-07, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Banjora, Block- ation Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25344-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Sarishabahal PDW-03, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Sorishabahal, Block- ation Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25345-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Sarishabahal PDW-06, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Sorishabahal, Block- ation Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25346-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Sarishabahal PDW-07, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Sorishabahal, Block- ation Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25347-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Sarishabahal PDW-08, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Sorishabahal, Block- ation Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25348-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Sarishabahal PDW-09, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Sorishabahal, Block- ation Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25349-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-02, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- ation Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25350-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-03, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- ation Bandwan under WBADMI Project for the year 2017- 18 Page 3 IN-DPMU - PURULIA- 25351-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-04, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- ation Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25352-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-05, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- ation Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25353-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-06, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- ation Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25354-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-07, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- ation Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25355-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-08, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- ation Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25356-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-09, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- ation Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25357-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-11, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- ation Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25358-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-12, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- ation Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25360-CW-RFB / Construction of Pump dug Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-14, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- ation Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25362-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 42,563.20 Signed Banjora WDS-02, Mouza - Bids One Envelope 18 23 25 18 21 20 Banjora, JL No.-75, Plot No.-951, Block- Barabazar under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25363-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Banjora WDS-05, Mouza - IBRD / 80900 Post Open - National 25,523.79 Signed Bids One Envelope 18 23 25 18 21 20 Banjora, JL No.-75, Plot No.-745 & 746, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25364-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 23,889.00 Signed Banjora WDS-06, Mouza - Bids One Envelope 18 23 25 18 21 20 Banjora, JL No.-75, Plot No.-599, Block- Barabazar under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25365-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Banjora WDS-07, Mouza - IBRD / 80900 Post Open - National 36,432.97 Signed Bids One Envelope 18 23 25 18 21 20 Banjora, JL No.-75, Plot No.-88, 89 & 90, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25366-CW-RFB / Construction of Water Detention Structure Kuda Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 18,847.61 Signed WDS-01, Mouza -Kuda, JL Bids One Envelope 18 23 25 18 21 20 No.-15, Plot No.-500, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25367-CW-RFB / Construction of Water Detention Structure Mahilidih WDS-02, Mouza Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 44,126.66 Signed -Mahilidih, JL No.-10, Plot Bids One Envelope 18 23 25 18 21 20 No.-413 to 416 & 252, 253 Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25368-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Krishnanagar WDS-02, IBRD / 80900 Post Open - National 28,553.98 Signed Bids One Envelope 18 23 25 18 21 20 Mouza -Krishnanagar, JL No.-46, Plot No.-1003, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25371-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Krishnanagar WDS-05, IBRD / 80900 Post Open - National 32,950.97 Signed Bids One Envelope 18 23 25 18 21 20 Mouza -Krishnanagar, JL No.-46, Plot No.-286, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25372-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Hullung WDS-01, Mouza - IBRD / 80900 Post Open - National 28,773.96 Signed Bids One Envelope 18 23 25 18 21 20 Hullung, JL No.-29, Plot No.-341, 350 & 351, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25383-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Hatinda IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza -Hatinda, ation Block- Joypur under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25384-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Shyampur IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza -Chargali, ation Block- Purulia-II under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25385-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Manipur IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza -Manipur, ation Block- Purulia-II under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25386-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Dumdumi IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza - ation Dumdumi, Block- Purulia- II under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25387-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Raghabpur IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza - ation Raghabpur, Block- Purulia- II under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25388-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Pirargarya IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza - ation Pirargarya, Block- Purulia- II under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25389-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Bagdadih IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza -Bagdadih, ation Block- Purulia-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25390-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Kuchung IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-02, Mouza -Kuchung, ation Block- Puncha under WBADMI Project for the year 2017-18 Page 4 IN-DPMU - PURULIA- 25391-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Chandra IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-02, Mouza -Chandra, ation Block- Puncha under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25392-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Chandra IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza -Chandra, ation Block- Puncha under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25403-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Anara IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-IV, Mouza -Anara, ation Block- Para under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25404-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Anara IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-III, Mouza -Anara, ation Block- Para under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25405-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Anara IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-II, Mouza -Anara, ation Block- Para under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25406-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Anara IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-I, Mouza -Anara, ation Block- Para under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25408-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Chautala IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-I, Mouza -Chautala, ation Block- Para under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25409-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Udaypur IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-I, Mouza -Udaypur, ation Block- Joypur under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25410-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Hatinada IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-III, Mouza -Hatinada, ation Block- Joypur under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25411-CW-RFB / Construction of Solar Under Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Hatinada IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 25 18 21 20 PDW-II, Mouza -Hatinada, ation Block- Joypur under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 26034-CW-RFB / Construction of Chinese Pending carp hatchery with supply Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-09- 2017-10- 2017-11- IBRD / 80900 Post Open - National 0.00 Implement of input for operational at Bids One Envelope 28 30 15 22 13 13 ation Mouza- Joyramdi, Jl No.- 178, Plot-163 under WBADMI Project IN-DPMU BIRBHUM- 26848-CW-RFB / Construction of Charicha_1, Pending Charicha_2, Charicha_3 Request for Single Stage - 2017-09- 2017-09- 2017-10- 2017-11- 2018-01- 2018-07- IBRD / 80900 Post Open - National 0.00 Implement Check Dam cum Weir & Bids One Envelope 13 18 30 29 03 02 ation Allied Works at Mouza- Raspur, Block-Mohammad Bazar in Birbhum District. IN-DPMU BIRBHUM- 26849-CW-RFB / Construction of Pending Kharikabad_1, Request for Single Stage - 2017-09- 2017-09- 2017-10- 2017-11- 2018-01- 2018-07- IBRD / 80900 Post Open - National 0.00 Implement Kharikabad_2, Bids One Envelope 13 18 30 29 03 02 ation Kharikabad_3 Check Dam cum Weir & Allied Works at Mouza-Kharikabad, Block-Khayrasole in Birbhum District. IN-DPMU - JALPAIGURI- 21685-CW-RFB / Pending Request for Single Stage - 2017-07- 2017-07- 2017-09- 2017-09- 2017-09- 2018-03- Construction & installation IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 26 27 05 12 29 28 of Solar power Operated 8 ation Nos. Tube Well IN-DPMU - SOUTH P- 27419-CW-RFB / All in one bid for construction of 1 no Water Detention Structures (WDS) Sub Pending Request for Single Stage - 2017-10- 2017-10- 2017-11- 2017-12- 2018-02- 2018-08- Projects at Gordaha WDS IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 13 18 29 29 02 01 at Mouza-Gordaha (J.L.- ation 133) & Nabagram (J.L.- 135) , Block -Baruipur in the District of South 24 Parganas under WBADMI Project. IN-DPMU - SOUTH P- 27425-CW-RFB / All in one Bid for Construction of 3 nos Water Detention Structure (WDS) Sub Pending Projects at Gopalpur Purba Request for Single Stage - 2017-10- 2017-10- 2017-11- 2017-12- 2018-02- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement WDS(Jl-99) , Dharmatala Bids One Envelope 13 18 29 29 02 01 ation WDS(Jl-96) Block - Canning- I and Purba Tentulberia WDS (J.L.-120) Block- Kultali in the District of South 24 Parganas . IN-DPMU - SOUTH P- 27432-CW-RFB / All in one Bid for Construction of 3 nos Water Detention Structure (WDS) Sub Pending Projects at Kulaghurani Request for Single Stage - 2017-10- 2017-10- 2017-11- 2017-12- 2018-02- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement Uttar WDS(Jl-98) , Bids One Envelope 13 18 29 29 02 01 ation Kulaghurani Purba WDS(Jl- 98) , Kulaghurani Paschim WDS (J.L.-98) , Block - Canning- I in the District of South 24 Parganas IN-DPMU - SOUTH P- 27434-CW-RFB / All in one Bid for Construction of 3 nos Water Detention Structure (WDS) Sub Pending Projects at Tentulberia Request for Single Stage - 2017-10- 2017-10- 2017-11- 2017-12- 2018-02- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement Purba WDS(Jl-91) , Bids One Envelope 13 18 29 29 02 01 ation Tentulberia Paschim WDS(Jl-91) , Badukalu WDS (J.L.-103) , Block - Canning- I in the District of South 24 Parganas IN-DPMU - SOUTH P- 27437-CW-RFB / All in one Bid for Construction of 3 nos Water Detention Structure (WDS) Sub Pending Projects at Teurhat Request for Single Stage - 2017-10- 2017-10- 2017-11- 2017-12- 2018-02- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement WDS(Jl-95) , Beledahari Bids One Envelope 13 18 29 29 02 01 ation WDS(Jl-96) , Block - Baruipur and Dutta Babur Abad WDS (J.L.-97) Block- Canning-I in the District of South 24 Parganas IN-DPMU - SOUTH P- 27438-CW-RFB / All in one Bid for Construction of 2 nos Water Detention Pending Structure (WDS) Sub Request for Single Stage - 2017-10- 2017-10- 2017-11- 2017-12- 2017-12- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement Projects at Sudhanshupur Bids One Envelope 13 18 17 02 30 28 ation WDS(Jl-101) , Satjelia WDS(Jl-97) , Block - Gosaba in the District of South 24 Parganas IN-DPMU - PASCHIM- 28193-CW-RFB / Irrigation potential Development in Micro Watershed ( PAS2PMWS02 Phase-I ) by Pending Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- constructing various types IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 20 25 06 06 10 09 of M.I schemes ( Pump ation dug well (solar),Tube Well (solar), Check Dam, WDS) at Keshiary block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28196-CW-RFB / Irrigation potential Development in Micro Watershed ( Pending PAS2PMWS02 Phase-II ) Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- IBRD / 80900 Post Open - National 0.00 Implement by constructing various Bids One Envelope 20 25 06 06 10 09 ation types of M.I schemes ( Pump dug well (solar), WDS) at Keshiary block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28212-CW-RFB / Construction Water Pending Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- Detention Structure (WDS) IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 20 25 06 06 10 09 at Block- Keshiyary ation Within the district Paschim Medinipur. Page 5 IN-DPMU - PASCHIM- 28266-CW-RFB / Irrigation potential Development in Micro Watershed ( PAS5PMWS06 ) by Pending constructing various types Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- IBRD / 80900 Post Open - National 0.00 Implement of M.I schemes ( Pump Bids One Envelope 22 27 08 08 12 11 ation dug well (solar),Drip irrigation system for Pump dug well, Check Dam) at Binpur-I block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28429-CW-RFB / Irrigation potential Development in Micro Watershed( PAS2PMWS01 & PAS6PMMWS13 ) by Pending Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- constructing various types IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 27 08 08 12 11 of M.I schemes ( Pump ation dug well (solar),Drip irrigation system for Pump dug well, Tube Well) at Binpur-II block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28443-CW-RFB / Irrigation potential Development in Micro Watershed ( PASPMWS02 ) by Pending constructing various types Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- IBRD / 80900 Post Open - National 0.00 Implement of M.I schemes ( Pump Bids One Envelope 22 27 08 08 12 11 ation dug well (solar),Drip irrigation system for Pump dug well, Check Dam) at Jamboni block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28445-CW-RFB / Irrigation potential Development in Micro Watershed ( Pending PASPMWS02 Kharampara Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- IBRD / 80900 Post Open - National 0.00 Implement ) by constructing M.I Bids One Envelope 22 27 08 08 12 11 ation schemes ( Pump dug well (solar)) at Jmboni block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28447-CW-RFB / Irrigation potential Development in Micro Watershed ( PASPMWS02 Chawlishole ) Pending by constructing various Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- IBRD / 80900 Post Open - National 0.00 Implement types of M.I schemes ( Bids One Envelope 22 27 08 08 12 11 ation Pump dug well (solar),Drip irrigation system for Pump dug well, WDS) at Jamboni block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28470-CW-RFB / Irrigation potential Development in Micro Watershed ( PASPMWS12 ) by constructing various types Pending Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- of M.I schemes ( Pump IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 27 08 08 12 11 dug well (solar),Drip ation irrigation system for Pump dug well,TW,WDS, Check Dam) at Midnapore Sadar block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28474-CW-RFB / Irrigation potential Development in Micro Watershed ( PAS2PMWS07 ) by Pending constructing various types Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- IBRD / 80900 Post Open - National 0.00 Implement of M.I schemes ( Pump Bids One Envelope 22 27 08 08 12 11 ation dug well (solar),Drip irrigation system for Pump dug well,TW,WDS, Check Dam) at Binpur-I block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28477-CW-RFB / Irrigation potential Development in Micro Watershed ( PAS2PMWS07 Pending SARASBEDIA ) by Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- IBRD / 80900 Post Open - National 0.00 Implement constructing various types Bids One Envelope 22 27 08 08 12 11 ation of M.I schemes ( Pump dug well (solar),Drip irrigation system for Pump dug well,TW, WDS) at Binpur-I block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28479-CW-RFB / Irrigation potential Development in Micro Watershed ( Pending Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- PASMWS02 ) by IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 27 08 08 12 11 constructing M.I schemes ation ( Pump dug well (solar)) at Jamboni block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28480-CW-RFB / Irrigation potential Development in Micro Watershed ( PAS2PMWS01 ) by Pending constructing various types Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- IBRD / 80900 Post Open - National 0.00 Implement of M.I schemes ( Pump Bids One Envelope 22 27 08 08 12 11 ation dug well (solar),Drip irrigation system for Pump dug well, Check Dam,TW,WDS) at Binpur- II block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28482-CW-RFB / Irrigation potential Development in Micro Watershed ( PAS5PMWS07 KANKRADARA ) by Pending Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- constructing various types IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 27 08 08 12 11 of M.I schemes ( Pump ation dug well (solar),Drip irrigation system for Pump dug well, TW,WDS) at Binpur-I block within Paschim Medinipur District. IN-DPMU - PASCHIM- 28533-CW-RFB / Irrigation potential Development in Micro Watershed ( PAS2PMWS07 TASARARA ) by constructing various Pending Request for Single Stage - 2017-09- 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- types of M.I schemes ( IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 27 08 08 12 11 Pump dug well (solar),Drip ation irrigation system for Pump dug well, TW,WDS) at Midnapore Sadar block within Paschim Medinipur District. IN-DPMU BIRBHUM- 32483-CW-RFB / Construction of Surul_1, Pending Request for Single Stage - 2017-10- 2017-10- 2017-12- 2018-01- 2018-02- 2018-08- Surul_2, Surul_3, Surul_4 IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 17 22 03 02 06 05 Pump Dug Well (Solar) at ation Mouza- Surul, Block- Bolpur-Sriniketan in Birbhum District. IN-DPMU BIRBHUM- 32486-CW-RFB / Construction of Surul_5, Pending Request for Single Stage - 2017-10- 2017-10- 2017-12- 2018-01- 2018-02- 2018-08- Surul_6, Surul_7 Pump IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 17 22 03 02 06 05 Dug Well (Solar) at Mouza- ation Surul, Block- Bolpur- Sriniketan in Birbhum District. IN-DPMU - B-33558-CW- RFB / All in one Bid for construction of Bolpur-I & Pending Bolpur-II Tube Well (10 Request for Single Stage - 2017-10- 2017-10- 2017-12- 2018-01- 2018-02- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement nos) at Mouza-Bahadurpur, Bids One Envelope 26 31 12 11 15 14 ation J.L.131, Block-Ausgram-II under WBADMI Project under Burdwan District IN-DPMU - B-33562-CW- RFB / All in one Bid for construction of Bolpur-III Pending & Bolpur-IV Tube Well (10 Request for Single Stage - 2017-10- 2017-10- 2017-12- 2018-01- 2018-02- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement nos) at Mouza-Bahadurpur, Bids One Envelope 26 31 12 11 15 14 ation J.L.131, Block-Ausgram-II under WBADMI Project under Burdwan District IN-DPMU - B-33564-CW- RFB / All in one Bid for construction of Kalaijhuti-I & Kalaijhuti-II Tube Well Pending Request for Single Stage - 2017-10- 2017-10- 2017-12- 2018-01- 2018-02- 2018-08- (10 nos) at Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 26 31 12 11 15 14 Kalaijhuti, J.L.138, Block- ation Ausgram-II under WBADMI Project under Burdwan District IN-DPMU - B-33567-CW- RFB / All in one Bid for construction of Paharpur-I Pending & Paharpur-II Tube Well Request for Single Stage - 2017-10- 2017-10- 2017-12- 2018-01- 2018-02- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement (12nos) at Mouza- Eral, Bids One Envelope 26 31 12 11 15 14 ation J.L.130, Block-Ausgram-II under WBADMI Project under Burdwan District IN-DPMU - B-33568-CW- RFB / All in one Bid for construction of Suili-I & Pending Suili-II Tube Well (8 nos) Request for Single Stage - 2017-10- 2017-10- 2017-12- 2018-01- 2018-02- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement at Mouza- Suili, J.L.139, Bids One Envelope 26 31 12 11 15 14 ation Block-Ausgram-II under WBADMI Project under Burdwan District IN-DPMU - PM-39675-CW- RFB / New WDS Pending construction for irrigation Request for Single Stage - 2017-12- 2017-12- 2018-01- 2018-03- 2018-04- 2018-10- IBRD / 80900 Post Open - National 0.00 Implement potential development in Bids One Envelope 15 20 31 02 06 03 ation the district of Purba Medinipur. IN-DPMU - PASCHIM- 40471-CW-RFB / Construction of NEW WDS Pending AT GOPIBALLAVPUR-II & Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-04- 2018-10- IBRD / 80900 Post Open - National 0.00 Implement SANKRAIL BLOCK IN Bids One Envelope 29 03 14 16 20 17 ation THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR Page 6 IN-DPMU BIRBHUM- 40626-CW-RFB / Construction of Raspur I, Raspur II, Raspur III, Pending Raspur IV, Raspur V, Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-03- 2018-04- 2018-10- IBRD / 80900 Post Open - National 0.00 Implement Raspur VI, Raspur VII, Bids One Envelope 03 08 19 21 25 22 ation Raspur VIII, Raspur IX Pump Dug Well at Mouza- Charicha-Raspur, JL No- 101, Block- Md. Bazar in Birbhum District. IN-DPMU BIRBHUM- 40670-CW-RFB / Construction of Chandpur I, Chandpur II, Chandpur III, Chandpur IV, Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-03- 2018-04- 2018-10- Chandpur V, Chandpur VI, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 03 08 19 21 25 22 Dalimba I, Dalimba II, ation Dalimba III, Dalimba IV Pump Dug Well at Mouza- Chandpur, Dalimba, Block- Rampurhat-I, Murarai-I in Birbhum District. IN-DPMU BIRBHUM- 40684-CW-RFB / Construction of Kamarpara I, Kamarpara II, Ramnagar I, Ramnagar II, Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-03- 2018-04- 2018-10- Ramnagar III, Ramnagar IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 03 08 19 21 25 22 IV, Benuria I, Benuria II, ation Benuria III Pump Dug Well at Mouza- Kamarpara, Ramnagar, Benuria Block-Illambazar, Bolpur-Sriniketan in Birbhum District. IN-DPMU BIRBHUM- 40786-CW-RFB / Construction of Surul Pending Check Dam 1, Surul Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-03- 2018-04- 2018-10- IBRD / 80900 Post Open - National 0.00 Implement Check Dam 2, Mahidapur Bids One Envelope 03 08 19 21 25 22 ation Check Dam 2 at Mouza- Surul, Mahidapur, Block- Bolpur-Sriniketan in Birbhum District. IN-DPMU - NADIA-40991- CW-RFB / WORK FOR CONSTRUCTION OF WATER HARVESTING Pending STRUCTURE AT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- IBRD / 80900 Post Open - National 0.00 Implement CHAKGOBINDAPUR, Bids Two Envelope 29 02 01 03 11 23 ation HATGOBINDAPUR-1 & 2 , BHARATPUR AT NADIA DISTRICT UNDER WBADMIP IN-DPMU - NADIA-40999- CW-RFB / WORK FOR CONSTRUCTION OF WATER HARVESTING Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- STRUCTURE AT IBRD / 80900 Post Open - National 0.00 Implement Bids Two Envelope 29 02 01 03 11 23 CHOTO CHANDGHAR, ation BARACHANDGHAR I & II AT NADIA DISTRICT UNDER WBADMIP IN-DPMU - NADIA-41000- CW-RFB / WORK FOR CONSTRUCTION OF WATER HARVESTING Pending STRUCTURE AT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- IBRD / 80900 Post Open - National 0.00 Implement SABAIPUR , Bids Two Envelope 29 02 01 03 11 23 ation CHANDANPUR I & II AND JAGANNATHPUR AT NADIA DISTRICT UNDER WBADMIP IN-SWID-42804-CW-RFQ / Construction of protection work including washing Under cleaning of 100 numbers of Request for Single Stage - 2018-01- 2018-03- 2018-09- IBRD / 80900 Post Open - National 0.00 Implement Permanent Hydrograph Quotations One Envelope 19 20 21 ation Station in the Districts of South Bengal under WBADMIP. IN-SWID-42806-CW-RFQ / Construction of protection work including washing Under cleaning of 100 numbers of Request for Single Stage - 2018-01- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement Permanent Hydrograph Quotations One Envelope 19 16 14 ation Station in the Districts of North Bengal under WBADMIP. IN-DPMU - PASCHIM- 44012-CW-RFB / Irrigation potential developmentin Watershed Pending Juardhara(PAS6PMWS07) Request for Single Stage - 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- IBRD / 80900 Post Open - National 0.00 Implement by constructing various Bids One Envelope 29 03 17 16 21 17 ation type of MI schemes( PDW,WDS) at Binpur-II block within Paschim Medinipur District under WBADMIP. IN-DPMU - PASCHIM- 44027-CW-RFB / Irrigation Potential development in watershed Bagla-Daishanda Pending Request for Single Stage - 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- by constructing various IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 29 03 17 16 21 17 type of schemes ation (PDW,WDS) AT NARAYANGRAH block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 44030-CW-RFB / Irrigation Potential development in watershed Jabla by Pending Request for Single Stage - 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 29 03 17 16 21 17 of schemes (PDW,WDS) at ation Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 44035-CW-RFB / Irrigation Potential development in watershed Dadra by Pending Request for Single Stage - 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 29 03 17 16 21 17 of schemes (PDW,WDS) AT ation Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 44041-CW-RFB / Irrigation Potential development in watershed Loyada by Pending Request for Single Stage - 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 29 03 17 16 21 17 of schemes (PDW,WDS) AT ation Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 44126-CW-RFB / Irrigation Potential development in watershed Amlasole & Pending Request for Single Stage - 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- Amjharna by constructing IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 29 03 17 16 21 17 various type of MI ation schemes (PDW,WDS) at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 44131-CW-RFB / Irrigation Potential development in watershed Kankrajhor by Pending Request for Single Stage - 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 29 03 17 16 21 17 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 44134-CW-RFB / Irrigation Potential development in watershed Kodalboni by Pending Request for Single Stage - 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 29 03 17 16 21 17 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 44135-CW-RFB / Irrigation Potential development in watershed Barogahira by Pending Request for Single Stage - 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 29 03 17 16 21 17 of MI schemes (PDW,WDS) ation at Jhargram block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 44136-CW-RFB / Irrigation Potential development in watershed Sagarbhanga by Pending Request for Single Stage - 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 29 03 17 16 21 17 of MI schemes (PDW,WDS) ation at Jhargram block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 44137-CW-RFB / Irrigation Potential development in watershed Indkhara by Pending Request for Single Stage - 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 29 03 17 16 21 17 of MI schemes (PDW,WDS) ation at Jhargram block within Paschim Medinipur under WBADMIP. IN-DPMU - PURULIA- 33448-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 27,609.90 Signed Banjora WDS 8, Mouza - Bids One Envelope 01 06 18 19 26 24 Banjora, Block - Barabazar , in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 32581-CW-RFB / Construction of Water Request for Single Stage - 2017-10- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Detention Structure IBRD / 80900 Post Open - National 25,630.22 Signed Bids One Envelope 31 05 17 19 26 24 Banjora WDS-3, Mouza- Banjora, Block- barabazar in the district of Purulia IN-DPMU - PURULIA- 33909-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 33,935.67 Signed Jasodih WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Jasodih, Block - Balarampur, in Purulia District under WBADMI Project. Page 7 IN-DPMU - PURULIA- 33910-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 123,547.20 Signed Jasodih WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Jasodih, Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33923-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 38,023.80 Signed WDS 8, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 32580-CW-RFB / Construction of Water Request for Single Stage - 2017-10- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Detention Structure Ulda IBRD / 80900 Post Open - National 23,183.60 Signed Bids One Envelope 31 05 17 19 26 24 WDS-3, Mouza-Ulda, Block- barabazar in the district of Purulia IN-DPMU - PURULIA- 32343-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-10- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 39,345.30 Signed Gitinglahar WDS-I, Mouza Bids One Envelope 31 05 17 19 26 24 -Gitinglahar, Block- Balrampur under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 33449-CW-RFB / Construction of Water Detention Structure Loto Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 47,057.28 Signed WDS 1, Mouza - Loto, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33455-CW-RFB / Construction of Water Detention Structure Karma Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 40,463.46 Signed WDS 1, Mouza - Karma, Bids One Envelope 01 06 18 19 26 24 Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33958-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Jadublabra WDS), Mouza Bids One Envelope 01 06 18 19 26 24 ation - Goyalberia, Block - Santuri, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33646-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 27,674.26 Signed Salghati WDS - I, Mouza - Bids One Envelope 01 06 18 19 26 24 Salghati, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33654-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 25,600.26 Signed Gosaidih WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Gosaidih, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33655-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 30,592.22 Signed Gosaidih WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Gosaidih, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33656-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 17,191.76 Signed Gosaidih WDS 4, Mouza - Bids One Envelope 01 06 18 19 26 24 Gosaidih, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33657-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 57,898.48 Signed Raiddih WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Raiddih, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33667-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 15,767.63 Signed JaragoraWDS 6, Mouza - Bids One Envelope 01 06 18 19 26 24 Jaragora, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33675-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Gokulnagar WDS 3, Mouza IBRD / 80900 Post Open - National 31,405.60 Signed Bids One Envelope 01 06 18 19 26 24 - Gokulnagar, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33316-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 24,111.70 Signed Sorisabahal WDS-1, Mouza Bids One Envelope 01 06 18 19 26 24 - Sorisabahal, Block- Barabazar in the district of Purulia Under WBADMI Project. IN-DPMU - PURULIA- 34423-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Kiribera WDS -2), Mouza Bids One Envelope 01 06 18 19 26 24 ation - Kiribera, Block - Jhalda 1 in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34424-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Kiribera WDS -3), Mouza Bids One Envelope 01 06 18 19 26 24 ation - Kiribera, Block - Jhalda 1 in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34430-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Sutabai WDS), Mouza - Bids One Envelope 01 06 18 19 26 24 ation Sutabai, Block - Kashipur in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33903-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Bankudih WDS 1, Mouza - IBRD / 80900 Post Open - National 41,580.30 Signed Bids One Envelope 01 06 18 19 26 24 Bankudih, Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33911-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 17,662.40 Signed Susunia WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Susunia, Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33912-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 31,191.26 Signed Susunia WDS 3, Mouza - Bids One Envelope 01 06 18 19 26 24 Susunia, Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33913-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 20,930.82 Signed Purdaha WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Purdaha, Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33914-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 21,546.20 Signed Purdaha WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Purdaha, Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33915-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 23,878.53 Signed Purdaha WDS 3, Mouza - Bids One Envelope 01 06 18 19 26 24 Purdaha, Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33916-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 50,159.76 Signed WDS 1, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. Page 8 IN-DPMU - PURULIA- 33917-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 34,785.35 Signed WDS 2, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33918-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 26,848.95 Signed WDS 3, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33919-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 14,806.47 Signed WDS 4, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33920-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 24,464.39 Signed WDS 5, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33921-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 39,969.71 Signed WDS 6, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33922-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 38,303.68 Signed WDS 7, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33924-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Chandanpur WDS 1, IBRD / 80900 Post Open - National 17,381.72 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Chandanpur , Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33926-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Gohaldanga WDS 1, Mouza IBRD / 80900 Post Open - National 210,037.28 Signed Bids One Envelope 01 06 18 19 26 24 - Gohaldanga, Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34553-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Harada WDS 1), Mouza - Bids One Envelope 01 06 18 19 26 24 ation Harada, Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34554-CW-RFB / Construction of Water Pending Detention Structure (Polpol Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement WDS 1), Mouza - Polpol , Bids One Envelope 01 06 18 19 26 24 ation Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34555-CW-RFB / Construction of Water Pending Detention Structure (Polpol Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement WDS 2), Mouza - Polpol, Bids One Envelope 01 06 18 19 26 24 ation Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34556-CW-RFB / Construction of Water Pending Detention Structure (Rugri Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement WDS 1), Mouza - Rugri , Bids One Envelope 01 06 18 19 26 24 ation Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34557-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Kadampur WDS 1), Bids One Envelope 01 06 18 19 26 24 ation Mouza - Kadampur , Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34558-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Karandih WDS 1), Mouza Bids One Envelope 01 06 18 19 26 24 ation - Karandih, Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33658-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Raghunathpur WDS 1, IBRD / 80900 Post Open - National 27,262.75 Signed Bids One Envelope 01 06 18 19 26 24 Mouza Raghunathpur, Block - Manbazar 2, in Purulia District under WBADMI Project IN-DPMU - PURULIA- 33659-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Raghunathpur WDS 2, IBRD / 80900 Post Open - National 49,050.07 Signed Bids One Envelope 01 06 18 19 26 24 Mouza Raghunathpur, Block - Manbazar 2, in Purulia District under WBADMI Project IN-DPMU - PURULIA- 33661-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 16,305.64 Signed Jambedi WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Jambedi, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33662-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 27,628.66 Signed Jambedi WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Jambedi, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33663-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 11,668.15 Signed Dhabani WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Dhabani, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33664-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 33,550.90 Signed Dhabani WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Dhabani, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33665-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 35,676.93 Signed JaragoraWDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Jaragora, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33666-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 32,026.04 Signed Jaragora WDS 3, Mouza - Bids One Envelope 01 06 18 19 26 24 Jaragora, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33668-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 26,981.25 Signed Murgadi WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Murgadi, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33669-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Radhamohanpur WDS 2, IBRD / 80900 Post Open - National 39,331.60 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Radhamohanpur, Block - Manbazar 2, in Purulia District under WBADMI Project. Page 9 IN-DPMU - PURULIA- 33670-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Radhamohanpur WDS 3, IBRD / 80900 Post Open - National 32,098.47 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Radhamohanpur, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33671-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Radhamohanpur WDS 4, IBRD / 80900 Post Open - National 31,928.11 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Radhamohanpur, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33672-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Radhamohanpur WDS 6, IBRD / 80900 Post Open - National 37,093.81 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Radhamohanpur, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33673-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Gokulnagar WDS 1, Mouza IBRD / 80900 Post Open - National 11,484.98 Signed Bids One Envelope 01 06 18 19 26 24 - Gokulnagar, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33674-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Gokulnagar WDS 2, Mouza IBRD / 80900 Post Open - National 17,688.03 Signed Bids One Envelope 01 06 18 19 26 24 - Gokulnagar, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33676-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Gokulnagar WDS 6, Mouza IBRD / 80900 Post Open - National 12,377.00 Signed Bids One Envelope 01 06 18 19 26 24 - Gokulnagar, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33678-CW-RFB / Construction of Water Detention Structure Karma Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 54,457.61 Signed WDS 2, Mouza - Karma, Bids One Envelope 01 06 18 19 26 24 Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33679-CW-RFB / Construction of Water Detention Structure Karma Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 52,655.32 Signed WDS 3, Mouza - Karma, Bids One Envelope 01 06 18 19 26 24 Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33680-CW-RFB / Construction of Water Detention Structure Dava Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 102,008.76 Signed WDS 1, Mouza - Dava , Bids One Envelope 01 06 18 19 26 24 Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33681-CW-RFB / Construction of Water Detention Structure Dava Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 94,049.60 Signed WDS 2, Mouza - Dava , Bids One Envelope 01 06 18 19 26 24 Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33436-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Krishnanagar WDS 1, IBRD / 80900 Post Open - National 16,127.18 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Krishananagar, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33437-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Krishnanagar WDS 6, IBRD / 80900 Post Open - National 20,047.42 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Krishananagar, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33438-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Amakoncha WDS 1, Mouza IBRD / 80900 Post Open - National 19,983.30 Signed Bids One Envelope 01 06 18 19 26 24 - Amakoncha, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33439-CW-RFB / Construction of Water Detention Structure Sijadih Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 19,183.04 Signed WDS 1, Mouza - Sijadih, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33440-CW-RFB / Construction of Water Detention Structure Sijadih Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 34,322.94 Signed WDS 2, Mouza - Sijadih, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33441-CW-RFB / Construction of Water Detention Structure Sijadih Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 19,228.66 Signed WDS 4, Mouza - Sijadih, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33443-CW-RFB / Construction of Water Detention Structure Sijadih Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 15,256.04 Signed WDS 5, Mouza - Sijadih, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33444-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 16,570.66 Signed Jangidiri WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Jangidiri, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33445-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 10,613.44 Signed Jangidiri WDS 4, Mouza - Bids One Envelope 01 06 18 19 26 24 Jangidiri, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33446-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 23,747.29 Signed Jangidiri WDS 8, Mouza - Bids One Envelope 01 06 18 19 26 24 Jangidiri, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33447-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 31,001.32 Signed Banjora WDS 4, Mouza - Bids One Envelope 01 06 18 19 26 24 Banjora, Block - Barabazar , in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33967-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Malancha Asta WDS), Bids One Envelope 01 06 18 19 26 24 ation Mouza - Malancha , Block - Kashipur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33972-CW-RFB / Construction of Water Pending Detention Structure (Chelia Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement I WDS), Mouza - Chelia , Bids One Envelope 01 06 18 19 26 24 ation Block - Kashipur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33973-CW-RFB / Construction of Water Pending Detention Structure (Chelia Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement II WDS), Mouza - Chelia , Bids One Envelope 01 06 18 19 26 24 ation Block - Kashipur, in Purulia District under WBADMI Project. Page 10 IN-DPMU - PURULIA- 33974-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Mazarmura WDS), Mouza Bids One Envelope 01 06 18 19 26 24 ation - Mazarmura , Block - Kashipur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33976-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Khanna WDS), Mouza - Bids One Envelope 01 06 18 19 26 24 ation Anandapur, Block - Neturia, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33977-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- (Metyalsahar WDS), Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 01 06 18 19 26 24 - Metyalsahar , Block - ation Raghunathpur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33979-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Mahatomara WDS 2), Bids One Envelope 01 06 18 19 26 24 ation Mouza - Mahatomara , Block - Jhalda 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33319-CW-RFB / Construction of Water Detention Structure, Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Lakrahonda WDS-1, Mouza IBRD / 80900 Post Open - National 13,006.29 Signed Bids One Envelope 01 06 18 19 26 24 - Lakrahonda, Block- barabazar in the district of Purulia Under WBADMI Project. IN-DPMU - PURULIA- 33285-CW-RFB / Construction of Water Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Detention Structure IBRD / 80900 Post Open - National 38,828.88 Signed Bids One Envelope 01 06 18 19 26 24 Chotosagen WDS 1, Mouza- Chotosagen, Block- Manbazar 1 in the district of Purulia IN-DPMU - PURULIA- 36114-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 42,530.40 Signed Dhelatbamu WDS-I, Mouza Bids One Envelope 10 10 22 19 26 24 -Dhelatbamu, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 36132-CW-RFB / Construction of water detention structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 17,809.98 Signed Haludbani WDS-01, mouza- Bids One Envelope 10 10 22 19 26 24 Haludbani, Block-Bundwan under WBADMIP for the year 2017-18 IN-DPMU - PURULIA- 36134-CW-RFB / Construction of water detention structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 16,397.21 Signed Gokulnagar WDS-07, Bids One Envelope 10 10 22 19 26 24 mouza-Gokulnagar , Block- Barabazar under WBADMIP for the year 2017-18 IN-DPMU - PURULIA- 36171-CW-RFB / Construction of Water Detention structure Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-02- 2018-03- 2018-06- Gokulnagar WDS-09, IBRD / 80900 Post Open - National 10,498.06 Signed Bids One Envelope 24 24 05 19 26 24 Mouza- Gokulnagar, Block- Barabazar in Purulia District under WBADMIP for the year 2017-18. IN-DPMU - PURULIA- 36172-CW-RFB / Construction of Water Pending Detention structure Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement Jaragora WDS-07, Mouza- Bids One Envelope 24 24 05 19 26 24 ation Jaragora, Block- Manbazar- II in Purulia District under WBADMIP IN-DPMU - PURULIA- 36117-CW-RFB / Construction of Water Detention Structure Raidih Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 35,794.18 Signed WDS-01, Mouza-Raidih, Bids One Envelope 10 10 22 19 26 24 Block-Barabazar under WBADMI project for ther yera 2017-18 IN-DPMU - PASCHIM- 46826-CW-RFB / Irrigation Potential development in watershed Dakai by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46840-CW-RFB / Irrigation Potential development in watershed Sagarbhanga & Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- Hariadhara by constructing IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 various type of MI ation schemes (PDW,WDS) at Jhargram block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46844-CW-RFB / Irrigation Potential development in watershed KHARAGPUR I Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- & II by constructing IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 various type of MI ation schemes (WDS) at Kharagpur-I block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46863-CW-RFB / Irrigation Potential development in watershed Sakhabhanga by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46870-CW-RFB / Irrigation Potential development in watershed Khasjangal by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Jhargram block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46874-CW-RFB / Irrigation Potential development in watershed Patharchakri by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46879-CW-RFB / Irrigation Potential development in watershed Dhatmul by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Jhargram block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46885-CW-RFB / Irrigation Potential development in watershed Sankarboni by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Jhargram block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46890-CW-RFB / Irrigation Potential development in watershed Dahatmul by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46892-CW-RFB / Irrigation Potential development in watershed Sitapur by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46897-CW-RFB / Irrigation Potential development in watershed Joybandhi by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46899-CW-RFB / Irrigation Potential development in watershed Madhupur by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. Page 11 IN-DPMU - PASCHIM- 46901-CW-RFB / Irrigation Potential development in watershed CHUTIYABHUDRI Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- DUBLAKONA by IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 constructing various type ation of MI schemes (PDW,WDS) at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46905-CW-RFB / Irrigation Potential development in watershed Dadra by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46914-CW-RFB / Irrigation Potential development in watershed Dakai by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - PASCHIM- 46915-CW-RFB / Irrigation Potential development in watershed SITAPUR by Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-04- 2018-06- 2018-11- constructing various type IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 09 14 28 27 01 28 of MI schemes (PDW,WDS) ation at Binpur-II block within Paschim Medinipur under WBADMIP. IN-DPMU - BANKURA- 55074-CW-RFB / Construction of Surface Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Flow Minor lrrigation IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Scheme Lapuriya SFMIS , ation Mouza - Lapuriya , Block - Bankura II. IN-DPMU - BANKURA- 55085-CW-RFB / Construction of Surface Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Flow Minor lrrigation IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Scheme Ukradihi SFMIS , ation Mouza - Karonjora , Block - Bankura II. IN-DPMU - BANKURA- 55087-CW-RFB / Pending Construction of Water Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- IBRD / 80900 Post Open - National 0.00 Implement Detention Structure Bids One Envelope 21 26 07 06 11 07 ation Keshiara WDS , Mouza - Keshiara, Block - G.ghati. IN-DPMU - BANKURA- 55095-CW-RFB / Pending Construction of Water Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- IBRD / 80900 Post Open - National 0.00 Implement Detention Structure Adhuri Bids One Envelope 21 26 07 06 11 07 ation Al WDS , Mouza - Adhuri, Block - Saltora. IN-DPMU - BANKURA- 55103-CW-RFB / Pending Construction of Water Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- IBRD / 80900 Post Open - National 0.00 Implement Detention Structure Bids One Envelope 21 26 07 06 11 07 ation Ekchala WDS 1 , Mouza - Ekchala, Block - G.ghati. IN-DPMU - BANKURA- 55130-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Dhansimul WDS , Mouza - ation Dhansimul, Block - Bankura II. IN-DPMU - BANKURA- 55135-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Bhaktabundh WDS , ation Mouza - Bhaktabundh, Block - Block - G.ghati IN-DPMU - BANKURA- 55136-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Banskopa WDS, Mouza- ation Banskopa , Block - Taldangra. IN-DPMU - BANKURA- 55137-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Pathordoba WDS , Mouza- ation Pathordoba, Block - Simlapal. IN-DPMU - BANKURA- 55139-CW-RFB / Pending Construction of Water Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- IBRD / 80900 Post Open - National 0.00 Implement Detention Structure Bids One Envelope 21 26 07 06 11 07 ation Kadmagarh WDS , Mouza - Kadmagarh, Block - Raipur. IN-DPMU - BANKURA- 55140-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Dhengasimul WDS , ation Mouza -Dhengasimul, Block - Taldangra. IN-DPMU - BANKURA- 55143-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Nachna WDS , Mouza - ation Narahampur, Block - Taldangra. IN-DPMU - BANKURA- 55146-CW-RFB / Construction of Surface Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Flow Minor lrrigation IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Scheme Bankata SFMIS , ation Mouza - Bankata, Block - Khatra. IN-DPMU - BANKURA- 55150-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Niamatpur -7 WDS , ation Mouza - Niamatpur, Block - Indpur. IN-DPMU - BANKURA- 55151-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- IBRD / 80900 Post Open - National 0.00 Implement Niamatpur(Mohanapara)-6 Bids One Envelope 21 26 07 06 11 07 ation WDS , Mouza - Niamatpur(Mohanapara), Block - Indpur. IN-DPMU - BANKURA- 55154-CW-RFB / Pending Construction of Water Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- IBRD / 80900 Post Open - National 0.00 Implement Detention Structure Bids One Envelope 21 26 07 06 11 07 ation Sindurpeti-1 WDS , Mouza - Sindurpeti, Block - Khatra. IN-DPMU - BANKURA- 55157-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Niamatpur -2 WDS , ation Mouza - Niamatpur, Block - Indpur. IN-DPMU - BANKURA- 55158-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Niamatpur -3 WDS , ation Mouza - Niamatpur, Block - Indpur. IN-DPMU - BANKURA- 55160-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Niamatpur -4 WDS , ation Mouza - Niamatpur, Block - Indpur. IN-DPMU - BANKURA- 55161-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 07 Niamatpur -1 WDS , ation Mouza - Niamatpur, Block - Indpur. IN-DPMU - BANKURA- 55164-CW-RFB / Pending Construction of Water Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- IBRD / 80900 Post Open - National 0.00 Implement Detention Structure Bids One Envelope 21 26 07 06 11 07 ation Kenboni WDS , Mouza - Kenboni, Block - Bankura II. IN-DPMU - BANKURA- 55170-CW-RFB / Pending Construction of Water Request for Single Stage - 2018-03- 2018-03- 2018-05- 2018-06- 2018-07- 2019-01- IBRD / 80900 Post Open - National 0.00 Implement Detention Structure Bids One Envelope 21 26 07 06 11 07 ation Bhalukathol, Mouza - Bhalukathol, Block - G.ghati. IN-DPMU - PASCHIM- 59916-CW-RFB / Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2019-02- Construction of new WDS IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 10 15 26 26 30 26 at Nichubankinala mouza ation in the district of Jhargram. IN-DPMU - PASCHIM- 59918-CW-RFB / Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2019-02- Construction of new WDS IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 10 15 26 26 30 26 at KASHIA mouza in the ation district of Jhargram. Page 12 IN-DPMU - PASCHIM- 59922-CW-RFB / Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2019-02- Construction of new WDS IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 10 15 26 26 30 26 at KASHIA mouza in the ation District of Jhargram IN-DPMU - PASCHIM- 59925-CW-RFB / Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2019-02- Construction of new WDS IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 10 15 26 26 30 26 at SINGDHUI mouza in ation the District of Jhargram. IN-DPMU - PASCHIM- 59927-CW-RFB / Pending Request for Single Stage - 2018-05- 2018-05- 2018-07- 2018-08- 2018-09- 2019-03- Construction of new WDS IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 27 08 07 11 10 at SINGDHUI mouza in ation the District of Jhargram. IN-DPMU - PASCHIM- 59931-CW-RFB / Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2019-02- Construction of new WDS IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 10 15 26 26 30 26 at SINGDHUI mouza in ation the District of Jhargram. IN-DPMU - PASCHIM- 59933-CW-RFB / Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2019-02- Construction of new WDS IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 10 15 26 26 30 26 at BISWANATHPUR ation mouza in the District of Jhargram IN-DPMU - PURULIA- 64446-CW-RFQ / Topographical survey of proposed reservoir/ Pending Request for Single Stage - 2018-06- 2018-07- 2018-08- irrigation tank/SFMIS/WDS IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 03 29 28 preparation of 34 Nos. ation DPRs of WDS in the district of Purulia und WBADMIP IN-DPMU - BANKURA- 64820-CW-RFB / Pending Construction of Water Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement Detention Structure Bids One Envelope 19 24 05 04 09 07 ation Nachna 1 WDS , Mouza - Nachna , Block - Taldangra. IN-DPMU - BANKURA- 65359-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 19 24 05 04 09 07 Jagatpur WDS , Mouza - ation Narottampur, Block - Taldangra. IN-DPMU - BANKURA- 65360-CW-RFB / Pending Construction of Water Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement Detention Structure Bids One Envelope 19 24 05 04 09 07 ation Nachna 2 WDS , Mouza - Nachna, Block - Taldangra. IN-DPMU - BANKURA- 65363-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 19 24 05 04 09 07 Namadudhiyadoba WDS , ation Mouza - Namadudhiyadoba, Block - Simlapal. IN-DPMU - BANKURA- 65364-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 19 24 05 04 09 07 Kadmagarh 2 WDS , ation Mouza - Kadmagarh, Block - Raipur IN-DPMU - BANKURA- 65366-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 19 24 05 04 09 07 Kansachora WDS , Mouza ation - Kansachora, Block - Simlapal. IN-DPMU - BANKURA- 65369-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 19 24 05 04 09 07 Pathardoba 2 WDS , ation Mouza - Pathardoba, Block - Simlapal. IN-DPMU - BANKURA- 65395-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 19 24 05 04 09 07 Harialgera 1 WDS , ation Mouza - Narottampur, Block - Taldangra. IN-DPMU - BANKURA- 65397-CW-RFB / Pending Construction of Water Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement Detention Structure Bids One Envelope 19 24 05 04 09 07 ation Pukhuria 1 WDS , Mouza - Pukhuria, Block - Raipur. IN-DPMU - BANKURA- 65399-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement Purnapani baro tung 1 Bids One Envelope 19 24 05 04 09 07 ation WDS , Mouza - Purnapani baro tung, Block - Ranibundh. IN-DPMU - PASCHIM- 65557-CW-RFB / CONSTRUCTION OF 4 NOS NEW WDS AT Pending MOUZA BANMALIPUR Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement BLOCK SALBONI IN THE Bids One Envelope 20 25 06 05 10 08 ation DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - PASCHIM- 65559-CW-RFB / CONSTRUCTION OF 5 NOS NEW WDS AT Pending MOUZA MIRGA BLOCK Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement SALBONI IN THE Bids One Envelope 20 25 06 05 10 08 ation DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - PASCHIM- 65561-CW-RFB / CONSTRUCTION OF 4 NOS NEW WDS AT Pending MOUZA MAHISAMURA Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement BLOCK KESHIARY IN Bids One Envelope 20 25 06 05 10 08 ation THE DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - BANKURA- 65564-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 19 24 05 04 09 07 Gobindasol 1 WDS , ation Mouza - Gobindasol, Block - Ranibundh. IN-DPMU - PASCHIM- 65565-CW-RFB / CONSTRUCTION OF 2 NOS NEW WDS AT Pending MOUZA AMBI BLOCK Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement KESHIARY IN THE Bids One Envelope 20 25 06 05 10 08 ation DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - PASCHIM- 65568-CW-RFB / CONSTRUCTION OF 3 NOS NEW WDS AT Pending MOUZA ANANDANAGAR Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement & THUNGI BLOCK Bids One Envelope 20 25 06 05 10 08 ation SALBONI IN THE DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - PASCHIM- 65569-CW-RFB / CONSTRUCTION OF 3 NOS NEW WDS AT MOUZA BRINANDAPUR , Pending CHOTODAINMARI , Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement RANBNIA BLOCK Bids One Envelope 20 25 06 05 10 08 ation KESHIARY IN THE DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - PASCHIM- 65571-CW-RFB / CONSTRUCTION OF 2 NOS NEW WDS AT Pending MOUZA AMRATARYA Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement BLOCK KESHIARY IN Bids One Envelope 20 25 06 05 10 08 ation THE DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - PASCHIM- 65577-CW-RFB / CONSTRUCTION OF 3 NOS NEW WDS AT Pending MOUZA AMRATARYA Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement BLOCK KESHIARY IN Bids One Envelope 20 25 06 05 10 08 ation THE DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - PASCHIM- 65589-CW-RFB / CONSTRUCTION OF 2 NOS NEW WDS AT Pending MOUZA AMRATARYA Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement BLOCK KESHIARY IN Bids One Envelope 20 25 06 05 10 08 ation THE DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. Page 13 IN-DPMU - PASCHIM- 65592-CW-RFB / CONSTRUCTION OF 3 NOS NEW WDS AT Pending MOUZA BARIDA BLOCK Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement KESHIARY IN THE Bids One Envelope 20 25 06 05 10 08 ation DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - PASCHIM- 65603-CW-RFB / CONSTRUCTION OF 2 NOS NEW WDS AT Pending MOUZA BARIDA BLOCK Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement KESHIARY IN THE Bids One Envelope 20 25 06 05 10 08 ation DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - PASCHIM- 65606-CW-RFB / CONSTRUCTION OF 4 NOS NEW WDS AT Pending MOUZA BARIDA BLOCK Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement KESHIARY IN THE Bids One Envelope 20 25 06 05 10 08 ation DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - PASCHIM- 65612-CW-RFB / CONSTRUCTION OF 1 NO NEW WDS AT Pending Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- MOUZA BARIDA BLOCK IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 20 25 06 05 10 08 KESHIARY IN THE ation DISTRICT OF PASCHIM MEDINIPUR UNDER MIDNAPORE (AI) DIVISION. IN-DPMU - BANKURA- 65738-CW-RFB / Pending Construction of Water Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement Detention Structure LEP- Bids One Envelope 19 24 05 04 09 07 ation AM WDS , Mouza - LEP- AM , Block - Ranibundh. IN-DPMU - BANKURA- 65740-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 19 24 05 04 09 07 Khejuria WDS , Mouza - ation Khejuria , Block - Ranibundh. IN-DPMU - BANKURA- 65742-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement Purnapani chhota tung Bids One Envelope 19 24 05 04 09 07 ation WDS , Mouza - Purnapani chhota tung, Block - Ranibundh. IN-DPMU - BANKURA- 65745-CW-RFB / Construction of Water Pending Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- Detention Structure IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 19 24 05 04 09 07 Harialgera 2 WDS , ation Mouza - Narottampur, Block - Taldangra. IN-DPMU - PASCHIM- 66614-CW-RFB / CONSTRUCTION OF 10 Pending Request for Single Stage - 2018-06- 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- NOS NEW WDS AT IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 21 26 07 06 11 09 BLOCK NAYAGRAM & ation SANKRAIL IN THE DISTRICT OF JHARGRAM. IN-DPMU - PASCHIM- 69305-CW-RFB / CONSTRUCTION OF 2 NEW WDS AT MOUZA Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- RAJPARA & KANTASOLE IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 UNDER BINPUR-II IN ation THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69309-CW-RFB / CONSTRUCTION OF 2 NEW WDS AT MOUZA Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- BHURSATORA UNDER IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 BINPUR-II IN THE ation DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69312-CW-RFB / CONSTRUCTION OF 2 Pending NEW WDS AT MOUZA Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- IBRD / 80900 Post Open - National 0.00 Implement JAMUI UNDER BINPUR- Bids One Envelope 18 23 03 03 07 06 ation II IN THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69325-CW-RFB / CONSTRUCTION OF 3 NOS NEW WDS AT Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- MOUZA CHAKADOBA IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 UNDER BINPUR-II IN ation THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69327-CW-RFB / CONSTRUCTION OF 3 NOS NEW WDS AT Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- MOUZA KESHMAR IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 UNDER BINPUR-II IN ation THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69329-CW-RFB / CONSTRUCTION OF 4 NOS NEW WDS AT MOUZA SARISABASA , Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- SARENGASULI & IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 AMLATORA UNDER ation BINPUR-II IN THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69333-CW-RFB / CONSTRUCTION OF 2 NOS NEW WDS AT Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- MOUZA BANSHPAHARI IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 UNDER BINPUR-II IN ation THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69337-CW-RFB / CONSTRUCTION OF 1 NO NEW WDS AT Pending MOUZA BAGGHARA Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- IBRD / 80900 Post Open - National 0.00 Implement UNDER MIDNAPORE Bids One Envelope 18 23 03 03 07 06 ation SADAR BLOCK IN THE DISTRICT OF PASCHIM MEDINIPUR UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69340-CW-RFB / CONSTRUCTION OF 1 NO CHECK DAM AT Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- MOUZA KANTASOLE IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 UNDER BINPUR-II IN ation THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69342-CW-RFB / CONSTRUCTION OF 1 NO CHECK DAM AT Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- MOUZA JOYBANDHI IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 UNDER JHARGRAM ation BLOCK IN THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69346-CW-RFB / CONSTRUCTION OF 1 NO CHECK DAM AT Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- MOUZA DAHATMUL IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 UNDER JHARGRAM IN ation THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69350-CW-RFB / CONSTRUCTION OF 1 NO CHECK DAM AT Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- MOUZA RAJPARA IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 UNDER JHARGRAM ation BLOCK IN THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69353-CW-RFB / Construction of one no Pending Check Dam at Mouza Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- IBRD / 80900 Post Open - National 0.00 Implement Dahatmul under Jhargram Bids One Envelope 18 23 03 03 07 06 ation Block in the district of Jhargram under DPMU Paschim Medinipur IN-DPMU - PASCHIM- 69539-CW-RFB / CONSTRUCTION OF 1 NO CHECK DAM AT Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- MOUZA DAHATMUL IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 UNDER JHARGRAM ation BLOCK IN THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. Page 14 IN-DPMU - PASCHIM- 69541-CW-RFB / CONSTRUCTION OF 1 NO CHECK DAM AT Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- MOUZA MAHATOBANDH IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 UNDER BINPUR-II IN ation THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - PASCHIM- 69544-CW-RFB / CONSTRUCTION OF 1 NO CHECK DAM AT Pending Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- MOUZA JOYBANDHI IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 23 03 03 07 06 UNDER JHARGRAM ation BLOCK IN THE DISTRICT OF JHARGRAM UNDER DPMU PASCHIM MEDINIPUR. IN-DPMU - JALPAIGURI- 74070-CW-RFQ / Construction & Installation Pending of Permanent Desi magur Request for Single Stage - 2018-08- 2018-09- 2018-10- IBRD / 80900 Post Open - National 0.00 Implement hatchery shed in different Quotations One Envelope 21 25 25 ation WUA in different blocks of DPMU, Jalpaiguri under WBADMI Project IN-DPMU - PURULIA- 76102-CW-RFB / Construction of Water Under Detention Structure Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- IBRD / 80900 Post Open - National 0.00 Implement Hullung WDS 2, Mouza - Bids One Envelope 12 14 29 31 04 05 ation Hullung, Block - Manbazar I, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 76103-CW-RFB / Construction of Water Detention Structure Bari Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 3, Mouza - Bari, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in ation Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76104-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Majhihira WDS 1, Mouza - IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Majhihira, Block - ation Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76106-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Baliguma WDS 4, Mouza - IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Baliguma, Block - ation Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76107-CW-RFB / Construction of Water Detention Structure Bamni Under WDS 1, Mouza - Chokya Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- IBRD / 80900 Post Open - National 0.00 Implement Bhabanipur, Block - Bids One Envelope 12 14 29 31 04 05 ation Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76108-CW-RFB / Construction of Water Detention Structure Bari Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 2, Mouza - Bari, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in ation Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76110-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Majhihira WDS 2, Mouza - IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Majhihira, Block - ation Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76111-CW-RFB / Construction of Water Detention Structure Tukya Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 5, Mouza - Tukya, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in ation Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76112-CW-RFB / Construction of Water Detention Structure Bamni Under WDS 2, Mouza - Chokya Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- IBRD / 80900 Post Open - National 0.00 Implement Bhabanipur, Block - Bids One Envelope 12 14 29 31 04 05 ation Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76113-CW-RFB / Construction of Water Detention Structure Tukya Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 2, Mouza - Tukya, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in ation Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76114-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Baliguma WDS 2, Mouza - IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Baliguma, Block - ation Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76130-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Jangidiri WDS 12, Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 - Jangidiri, Block - ation Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76134-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Baliguma WDS 5, Mouza - IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Baliguma, Block - ation Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76135-CW-RFB / Construction of Water Detention Structure Tukya Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 3, Mouza - Tukya, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in ation Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76136-CW-RFB / Construction of Water Detention Structure Tukya Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 1, Mouza - Tukya, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in ation Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76137-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Jangidiri WDS 10, Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 - Jangidiri, Block - ation Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76138-CW-RFB / Construction of Water Detention Structure Tukya Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 4, Mouza - Tukya, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in ation Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76139-CW-RFB / Construction of Water Detention Structure Kesya Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 1, Mouza - Kesya, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in ation Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - B-76308-CW- RFB / All in one Bid for construction of Bhadda-I & Pending Bhadda-II Tube Well (11 Request for Single Stage - 2018-08- 2018-09- 2018-10- 2018-11- 2018-12- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement nos) at Mouza-Bhada, J.L.- Bids One Envelope 30 04 16 15 20 18 ation 146 Block-Ausgram-I under WBADMI Project under Burdwan District. IN-DPMU BIRBHUM- 76348-CW-RFB / Construction of Masonary Dug Well at Khedamara I, Pending Khedamara II, Khedamara Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-11- 2018-12- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement III, Khedamara IV, Bids One Envelope 10 15 27 26 31 29 ation Khedamara V, Khedamara VI, Khedamara VII,Khedamara VIII of Rampurhat I Block in Birbhum District. Page 15 IN-DPMU BIRBHUM- 78504-CW-RFB / Construction of Gobindachak WDS - I and Pending Request for Single Stage - 2018-10- 2018-10- 2018-11- 2018-12- 2019-01- 2019-07- Gobindachak WDS - II & IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 10 15 26 26 30 29 Tabadumra WDS, Mouza - ation Gobindachak & Tabadumra, Block - Rajnagar, JL No - 23, 24 under DPMU, Birbhum. IN-DPMU - M-78915-CW- RFB / Excavation of Komarpur Water Detention Structure (WDS) including construction outlet Pending structure & Laying WTA Request for Single Stage - 2018-09- 2018-09- 2018-11- 2019-01- 2019-02- 2019-08- IBRD / 80900 Prior Open - National 0.00 Implement with procurement of Bids Two Envelope 20 25 06 19 23 22 ation materials at Mouza - Komarpur , J.L.- 273 in Block Habibpur under WBADMI Project in the District of Malda. IN-DPMU - M-78922-CW- RFB / Excavation of Patharbanpur Water Detention Structure (WDS) including construction Pending outlet structure & Laying Request for Single Stage - 2018-09- 2018-09- 2018-11- 2019-01- 2019-02- 2019-08- IBRD / 80900 Post Open - National 0.00 Implement WTA with procurement of Bids Two Envelope 20 25 06 19 23 22 ation materials at Mouza - Patharbanpur , J.L.- 267 in Block Habibpur under WBADMI Project in the District of Malda. IN-DPMU - M-78923-CW- RFB / Excavation of Chechaichandi & Khasharipur WDS including construction outlet structure & Laying Pending Request for Single Stage - 2018-09- 2018-09- 2018-11- 2019-01- 2019-02- 2019-08- WTA with procurement of IBRD / 80900 Prior Open - National 0.00 Implement Bids Two Envelope 20 25 06 19 23 22 materials at Mouza - ation Chechaichandi, J.L.- 244 & Khasharipur, J.L.- 287 in Block Habibpur under WBADMI Project in the District of Malda. IN-DPMU - M-78925-CW- RFB / Excavation of Joteharicharan - I & II Water Detention Structure (WDS) including Pending construction outlet Request for Single Stage - 2018-09- 2018-09- 2018-11- 2019-01- 2019-02- 2019-08- IBRD / 80900 Post Open - National 0.00 Implement structure & Laying WTA Bids Two Envelope 20 25 06 19 23 22 ation with procurement of materials at Mouza - Joteharicharan , J.L.- 43 in Block Bamangola under WBADMI Project in the District of Malda IN-DPMU - M-78927-CW- RFB / Excavation of Perapur - I & II Water Detention Structure (WDS) including construction Pending outlet structure & Laying Request for Single Stage - 2018-09- 2018-09- 2018-11- 2019-01- 2019-02- 2019-08- IBRD / 80900 Post Open - National 0.00 Implement WTA with procurement of Bids Two Envelope 20 25 06 19 23 22 ation materials at Mouza - Perapur, J.L.- 42 in Block Habibpur under WBADMI Project in the District of Malda. IN-DPMU - M-78930-CW- RFB / Excavation of Sankail & Harishchandrapur WDS including construction Pending outlet structure & Laying Request for Single Stage - 2018-09- 2018-09- 2018-11- 2019-01- 2019-02- 2019-08- IBRD / 80900 Post Open - National 0.00 Implement WTA with procurement of Bids Two Envelope 20 25 06 19 23 22 ation materials at Mouza - Sankail, J.L.- 166 & Harishchandrapur, J.L.- 83 in Block Habibpur under WBADMI Project in the District of Malda. IN-DPMU - M-78938-CW- RFB / Excavation of Binodpur & Rajarampur - II WDS including construction outlet Pending structure & Laying WTA Request for Single Stage - 2018-09- 2018-09- 2018-11- 2019-01- 2019-02- 2019-08- IBRD / 80900 Post Open - National 0.00 Implement with procurement of Bids Two Envelope 20 25 06 19 23 22 ation materials at Mouza - Binodpur, J.L.- 44 & Rajarampur, J.L.- 28 in Block Habibpur under WBADMI Project in the District of Malda. IN-DPMU - M-78944-CW- RFB / Excavation of Malancha & Nepalpur WDS including construction outlet structure & Laying Pending WTA with procurement of Request for Single Stage - 2018-09- 2018-09- 2018-11- 2019-01- 2019-02- 2019-08- IBRD / 80900 Post Open - National 0.00 Implement materials at Mouza - Bids Two Envelope 20 25 06 19 23 22 ation Malancha, J.L.- 125 & Nepalpur, J.L.- 127 in Block Bamangola under WBADMI Project in the District of Malda. IN-DPMU - M-78945-CW- RFB / Excavation of Baman Kandar - I & II Water Detention Structure (WDS) including Pending construction outlet Request for Single Stage - 2018-09- 2018-09- 2018-11- 2019-01- 2019-02- 2019-08- IBRD / 80900 Post Open - National 0.00 Implement structure & Laying WTA Bids Two Envelope 20 25 06 19 23 22 ation with procurement of materials at Mouza - Baman Kandar, J.L.- 118 in Block Bamangola under WBADMI Project in the District of Malda. IN-DPMU - M-78947-CW- RFB / Excavation of Mahadebpur & Madhabpur WDS including construction outlet structure & Laying Pending WTA with procurement of Request for Single Stage - 2018-09- 2018-09- 2018-11- 2019-01- 2019-02- 2019-08- IBRD / 80900 Post Open - National 0.00 Implement materials at Mouza - Bids Two Envelope 20 25 06 19 23 22 ation Mahadebpur, J.L.- 119 & Madhabpur, J.L.- 82 in Block Bamangola under WBADMI Project in the District of Malda. GOODS Bid Evaluation Activity Reference Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificati Process Prequalification Bidding Documents Report and Contract No. / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process on (Y/N) Status Evaluation Report as Issued Recommendation Completion (US$) Documents Justification / Invitation Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBR no 14 / procurement of Geophysical IBRD / 80900 Prior Direct Selection Direct 234,600.00 Signed Portable Logger Unit WBR No. 12 [ARC-GIS] / Procurement of ARC-GIS IBRD / 80900 Prior Direct Selection Direct 275,372.90 Signed for SWID WBR No 17 ARC GIS for SPMU / Procurement of IBRD / 80900 Prior Direct Selection Direct 67,820.37 Signed Arc GIS Server for SPMU WBR 18 [ERDAS Imagine] / Procurement of ERDAS Imagine Professional Software IBRD / 80900 Prior Direct Selection Direct 95,981.58 Signed under WBADMIP through Direct Contracting basis in view of strengthening SPMU and SWID WBR 27 / procurement of Arc GIS Software for IDA / 50140 Prior Direct Selection Direct 217,055.73 Signed Directorate of Agriculture under WBADMIP WBR 29 / procurement of Arc GIS Software for IDA / 50140 Prior Direct Selection Direct 169,770.41 Signed SWID under WBADMIP WBR # 30 / procurement of Arc GIS Software for IDA / 50140 Prior Direct Selection Direct 182,431.91 Signed DPMUs under WBADMIP IN-WBADMIP-12964-GO- DIR / Procurement of 2017-04- 2017-04- 2017-05- 2017-11- Autodesk AutoCAD Civil IDA / 50140 Post Direct Selection Direct 15,170.74 Completed 17 18 12 08 3D(Latest Version) by Direct Selection Method IN-WBADMIP-13306-GO- DIR / Training cum Experience Sharing 2017-04- 2017-04- 2017-04- 2017-04- Workshops of WUA's on IDA / 50140 Post Direct Selection Direct 4,593.35 Completed 20 20 25 26 26th April 2017 at Vedic Village Spa Resort for World bank Mission Visit, 2017 IN-WBADMIP-13311-GO- DIR / Training cum Experience Sharing 2017-04- 2017-04- 2017-04- 2017-04- Workshops of WUA's on IDA / 50140 Post Direct Selection Direct 3,824.33 Completed 20 20 26 27 27th April 2017 at Vedic Village Spa Resort for World bank Mission Visit, 2017 IN-DPMU - JALPAIGURI- 15355-GO-RFQ / Procurement of Computer (1 NOS.) & computer Peripherals & Internet Request for Single Stage - 2017-05- 2017-06- 2017-12- IBRD / 80900 Post Open - National 1,598.66 Completed Connection for the Quotations One Envelope 18 05 02 Regional Chemical & Hydro logical Laboratory in Jalpaiguri,SWID under WBADMIP IN-DPMU - HOOGHLY- 16438-GO-RFQ / Supply and Installation of 3 (Three) Numbers of Laptop , 1 (One ) number of Request for Single Stage - 2017-07- 2017-09- 2018-03- IBRD / 80900 Post Open - National 3,789.01 Signed Water Filter cum Purifier Quotations One Envelope 08 02 01 , and 1 (One) number of Water Cooler for the office of DPMU Hooghly , WBADMI Project . Page 16 IN-DPMU - HOOGHLY- 16455-GO-RFQ / Supply of crop wise seeds under Request for Single Stage - 2017-07- 2017-08- 2017-09- "Agricultural programme IBRD / 80900 Post Limited 224.76 Completed Quotations One Envelope 10 15 14 during kharif-2017" for DPMU Hooghly under WBADMI Project. IN-DPMU - DARJEELING-16669-GO- RFQ / Supply of Agricultural input items of Pending Request for Single Stage - 2017-06- 2017-06- 2017-12- Implementation of IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 29 26 Demonstrats centre ation programme under ASS Agriculture & Horticulture during Kharif 2017 under Darjeeling DPMU,WBADMIP IN-DPMU - C-16868-GO- RFQ / Procurement of Pending Seed and fertilizer for Request for Single Stage - 2017-06- 2017-06- 2017-12- IDA / 50140 Post Limited 0.00 Implement Agriculture Purpose in the Quotations One Envelope 06 22 19 ation district of Cooch Behar under WBADMIP. IN-DPMU - PASCHIM- 17236-GO-RFQ / PROCUREMENT OF SUPPLY OF SEEDS, FERTILIZER (N.P.K), MICRO NUTRIENTS DC Pending Request for Single Stage - 2017-06- 2017-07- 2017-12- DISPLAY BOARDS & IDA / 50140 Post Limited 0.00 Implement Quotations One Envelope 12 03 30 CARRYING COST OF DC ation INPUTS FROM DPMU TO WUA LEVEL FOR DEMONSTRATION CENTRE DURING KHARIF 2017-18 UNDER WBADMIP IN-DPMU - PASCHIM- 18042-GO-RFB / PROCUREMENT OF DIFFERENT VEGETABLES SEEDS & Pending Request for Single Stage - 2017-06- 2017-06- 2017-06- 2017-06- 2017-07- 2017-12- FERTILIZER FOR IDA / 50140 Post Limited 0.00 Implement Quotations One Envelope 14 17 28 29 03 30 HORTICULTURE ation DEMONSTRATION CENTRE DURING KHARIF 2017 UNDER WBADMIP, DPMU PASCHIM MEDINIPUR IN-DPMU - PM-18502-GO- DIR / Supply of Fertilizer Pending for conducting horticulture 2017-06- 2017-06- 2017-08- 2018-02- IDA / 50140 Post Direct Selection Direct 0.00 Implement DC in Kharif 2017-18 in 19 27 08 05 ation district Purba Medinipur under WBADMI Project. IN-DPMU - PM-18533-GO- DIR / Supply of fertilizers Pending for conducting Agriculture 2017-06- 2017-06- 2017-07- 2018-01- IDA / 50140 Post Direct Selection Direct 0.00 Implement DC in Kariff 2017 in the 19 24 29 25 ation District Purba Medinipur under WBADMIP. IN-DPMU - PM-18537-GO- RFQ / Supply of seeds for Pending conducting Horticulture DC Request for Single Stage - 2017-06- 2017-08- 2018-02- IDA / 50140 Post Limited 0.00 Implement in Khariff 2017 in the Quotations One Envelope 24 19 15 ation District Purba Medinipur under WBADMIP. IN-DPMU - DARJEELING-18608-GO- RFQ / Supply of Fish fingerlings, Fish feed , other fishery inputs and Pending Request for Single Stage - 2017-06- 2017-08- 2018-02- stationary items for IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 26 21 17 Training field exposure ation visit , for implementation of fishery DC etc. programe under ASS (Fishery) during 2017-18 under DPMU, Darjeeling, WBADMIP. IN-DPMU - DARJEELING-20096-GO- RFQ / Supply of Fishery inputs like Fish Fry, Fish Pending Feed, Medicine etc. Request for Single Stage - 2017-07- 2017-09- 2018-03- IBRD / 80900 Post Limited 0.00 Implement fingerling production Quotations One Envelope 16 10 09 ation through SHG under ASS activities (Fishery) DPMU, Darjeeling ,WBADMI Project during 2017-18. (Rearing fry to fingersings) IN-DPMU - NADIA-23048- GO-RFQ / SUPPLY OF FISH FINGERLINGS, FERTILIZERS, FISH FEED, MEDICINES FOR FISHERIES 01(ONE) NOS D.C. AND 10(TEN) NOS Pending Request for Single Stage - 2017-07- 2017-08- 2017-10- MASS PRODUCTION/ IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 31 18 17 MARKET ORIENTED ation APPROCH OF JAGANNATHPUR MOUZA AT THE DISTRICT OF NADIA UNDER WBADMIP FOR THE YEAR OF 2017-18 IN-DPMU - NADIA-23134- GO-RFQ / SUPPLY OF FISH FINGERLINGS, FERTILIZERS, FISH FEED, MEDICINES FOR FISHERIES 02 (TWO) NOS D.C. AND Pending Request for Single Stage - 2017-07- 2017-08- 2017-10- 03(THREE) NOS MASS IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 31 18 17 PRODUCTION/ MARKET ation ORIENTED APPROACH OF CHANDANPUR AND KARKARIA MOUZA AT THE DISTRICT OF NADIA UNDER WBADMIP FOR THE YEAR OF 2017-18 IN-DPMU - NADIA-23135- GO-RFQ / SUPPLY OF FISH FINGERLINGS, FERTILIZERS, FISH FEED, MEDICINES FOR FISHERIES 02 (TWO) NOS D.C. AND Pending Request for Single Stage - 2017-07- 2017-08- 2017-10- 07(SEVEN) NOS MASS IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 31 18 17 PRODUCTION/ MARKET ation ORIENTED APPROACH OF RUKUNPUR AND TEORKHALI MOUZA AT THE DISTRICT OF NADIA UNDER WBADMIP FOR THE YEAR OF 2017-18 IN-DPMU - NADIA-23139- GO-RFQ / SUPPLY OF FISH DRAGNET FOR 05(FIVE) NOS D.C. OF JAGANNATHPUR, Pending RUKUNPUR, Request for Single Stage - 2017-07- 2017-08- 2017-10- IBRD / 80900 Post Open - National 0.00 Implement CHANDANPUR, Quotations One Envelope 31 18 17 ation TEORKHALI AND KAKKARIA MOUZA AT THE DISTRICT OF NADIA UNDER WBADMIP FOR THE YEAR OF 2017-18 IN-DPMU - JALPAIGURI- 24108-GO-RFQ / Procurement of Instruments and reagents Request for Single Stage - 2017-08- 2017-10- 2018-04- IBRD / 80900 Post Open - National 13,996.53 Completed for Quotations One Envelope 16 11 09 testing for regional chemical and Hydrological Laboratory in jalpaiguri, SWID under WBADMIP IN-DPMU - PASCHIM- 24422-GO-RFQ / Supply of goods for Farmers Field School,Farmers Field Day,exposure visit to be Pending Request for Single Stage - 2017-08- 2017-09- 2018-03- facilitated under ASS-Agri. IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 18 08 31 across the Paschim ation Medinipur District In Unit Package Wise As-On- Demand basis under WBADMI Project IN-DPMU - NADIA-25531- GO-RFQ / SUPPLY OF COMPOSIT FISH CULTURE, FERTILIZERS, FISH FEED, MEDICINES Pending Request for Single Stage - 2017-08- 2017-09- 2017-11- FOR FISHERIES 01 IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 24 12 11 (ONE) NOS D.C. IN ation SEVERAL MOUZA AT THE DISTRICT OF NADIA UNDER WBADMIP FOR THE YEAR OF 2017-18 IN-DPMU - NADIA-25532- GO-RFQ / SUPPLY OF PANGUS MONO CULTURE, FERTILIZERS, FISH FEED, MEDICINES Pending Request for Single Stage - 2017-08- 2017-09- 2017-11- FOR FISHERIES 01 IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 24 12 11 (ONE) NOS D.C. IN ation SEVERAL MOUZA AT THE DISTRICT OF NADIA UNDER WBADMIP FOR THE YEAR OF 2017-18 IN-DPMU - NADIA-25533- GO-RFQ / SUPPLY OF GIANT PRAWN, FERTILIZERS, FISH FEED, MEDICINES FOR Pending Request for Single Stage - 2017-08- 2017-09- 2017-11- FISHERIES 01 (ONE) IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 24 12 11 NOS D.C. IN SEVERAL ation MOUZA AT THE DISTRICT OF NADIA UNDER WBADMIP FOR THE YEAR OF 2017-18 IN-DPMU - NADIA-25534- GO-RFQ / SUPPLY OF GIANT PRAWN, FERTILIZERS, FISH FEED, MEDICINES FOR Pending Request for Single Stage - 2017-08- 2017-09- 2017-11- FISHERIES 01 (ONE) IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 24 12 11 NOS D.C. IN SEVERAL ation MOUZA AT THE DISTRICT OF NADIA UNDER WBADMIP FOR THE YEAR OF 2017-18 Page 17 IN-DPMU - NADIA-25536- GO-RFQ / SUPPLY OF FISH DRAGNET FOR Pending 04(FOUR) NOS D.C. OF Request for Single Stage - 2017-08- 2017-09- 2017-11- IBRD / 80900 Post Open - National 0.00 Implement SEVERAL MOUZA AT Quotations One Envelope 24 12 11 ation THE DISTRICT OF NADIA UNDER WBADMIP FOR THE YEAR OF 2017-18 IN-DPMU - NADIA-25537- GO-RFQ / SUPPLY OF 80(EIGHTY )NOS HORTICULTURE D.C SEEDS, FERTILIZERS,BANNERS, SEED TREATMENT , Pending TRANSPORTATION Request for Single Stage - 2017-08- 2017-09- 2017-11- IBRD / 80900 Post Open - National 0.00 Implement INCLUDING LOADING Quotations One Envelope 24 12 11 ation AND UNLOADING COST FOR RABI SEASON AT VARIOUS WUA LOCATIONS IN THE DISTRICT OF NADIA UNDER WBADMIP FOR THE YEAR OF 2017-18 IN-DPMU - NADIA-25539- GO-RFQ / SUPPLY OF 250( TWO HUNDRED FIFTY) NOS AGRICULTURE D.C SEEDS, FERTILIZERS,BANNERS, SEED TREATMENT , Pending Request for Single Stage - 2017-08- 2017-09- 2017-11- TRANSPORTATION IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 24 12 11 INCLUDING LOADING ation AND UNLOADING COST FOR RABI SEASON AT VARIOUS WUA LOCATIONS IN THE DISTRICT OF NADIA UNDER WBADMIP FOR THE YEAR OF 2017-1 IN-DPMU - NADIA-14420- GO-RFQ / NOTICE INVITING QUOTATIONS FOR THE WORK OF SUPPLY OF DIFFERENT FISHERIES EQUIPMENT, TRAINING MATERIALS, Request for Single Stage - 2017-05- 2017-05- 2017-06- STATIONARY ETC. FOR IDA / 50140 Post Open - National 0.00 Canceled Quotations One Envelope 11 29 28 FISHERIES D.C. AND MARKET BASED INPUT UNDER A.S.S.- FISHERIES COMPONENT UNDER WBADMIP, NADIA DISTRICT FOR THE YEAR OF 2017-2018 IN-WBADMIP-25655-GO- RFB / Supply of 5 ( Five ) numbers of Differential Global Positioning System Request for Single Stage - 2017-08- 2017-09- 2017-10- 2017-11- 2017-12- 2018-06- IBRD / 80900 Post Open - National 121,501.52 Completed (DGPS) Machine for SPMU Bids One Envelope 30 04 16 15 20 18 and 4 PUP Districts DPMUs under WBADMI Project IN-DPMU - PURULIA- 26005-GO-RFQ / Supply of Inputs to the FMPG (Fisheries Mass Production Request for Single Stage - 2017-08- 2017-09- 2017-09- IBRD / 80900 Post Open - National 4,764.88 Signed Group) for the purpose of Quotations One Envelope 30 15 22 fisheries mass production at Bara Bundh Mouza- Swarupdi in manbazar-I Block. IN-DPMU - PURULIA- 26006-GO-RFQ / Supply of Inputs to the FMPG (Fisheries mass production Request for Single Stage - 2017-08- 2017-09- 2017-09- IBRD / 80900 Post Open - National 4,359.52 Signed Group) for the purpose of Quotations One Envelope 30 15 22 fisheries mass production at Durlab Bundh, Block- Barabazar IN-DPMU - PURULIA- 26008-GO-RFQ / Supply of Inputs to the FMPG (Fisheries mass production Request for Single Stage - 2017-08- 2017-09- 2017-09- Group) for the purpose of IBRD / 80900 Post Open - National 4,031.62 Signed Quotations One Envelope 30 15 22 fisheries mass production at Hesaldi Bundh, Nitujara Bundh & Salgambara Bundh, Block- Baghmundi IN-DPMU - PURULIA- 26010-GO-RFQ / Supply of Inputs to the FMPG (Fisheries mass production Request for Single Stage - 2017-08- 2017-09- 2017-09- Group) for the purpose of IBRD / 80900 Post Open - National 3,995.83 Signed Quotations One Envelope 30 15 22 fisheries mass production at Sasandhara Bundh, Bandarjabra Bundh & Jore Bundh, Block- Baghmundi IN-DPMU - PURULIA- 26015-GO-RFQ / Supply of Inputs to the women beneficiaries of FIG Request for Single Stage - 2017-08- 2017-09- 2017-09- IBRD / 80900 Post Open - National 3,388.10 Signed (Fisheries Interest Group) Quotations One Envelope 30 15 22 for the purpose of cage culture activity in project area. IN-DPMU - B-26229-GO- RFQ / Procurement of Water Management Tool Pending Request for Single Stage - 2017-09- 2017-10- 2018-04- set including Evaporimeter IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 04 30 28 for the Water Users ation Association (93 nos.) in Burdwan District IN-DPMU - HOWRAH- 22962-GO-DIR / Supply of Pending Horticulture Inputs and 2017-08- 2017-08- 2017-09- 2018-03- IBRD / 80900 Post Direct Selection Direct 0.00 Implement etc for Kharif 2017 of 18 23 28 27 ation Howrah District under WBADMIP IN-DPMU - HOWRAH- 22963-GO-DIR / Supply of Pending 2017-08- 2017-08- 2017-09- 2018-03- Agriculture Inputs and IBRD / 80900 Post Direct Selection Direct 0.00 Implement 18 23 28 27 etc for Kharif 2017 of ation Howrah District under WBADMIP IN-DPMU - PURULIA- 26000-GO-RFQ / Supply of Inputs to the FMPG (Fisheries Mass Production Request for Single Stage - 2017-08- 2017-09- 2017-09- IBRD / 80900 Post Open - National 1,607.10 Signed Group) for the purpose of Quotations One Envelope 30 15 22 fisheries mass production at Thakur Sayer Bundh in Kashipur Block. IN-SWID-42798-GO-RFB / Installation of Rain Gauge at different existing Under Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-07- locations in lieu of defunct IBRD / 80900 Post Open - National 0.00 Implement Bids Two Envelope 15 20 02 16 20 20 Rain Gauge Station under ation the jurisdiction of EE (AI) , SWID Divn.-II, Burdwan. IN-SWID-42801-GO-RFB / Procurement of 124 nos. DWLRs with Telemetry for Under Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-09- P-Tubes including supply, IBRD / 80900 Post Open - National 0.00 Implement Bids Two Envelope 15 19 02 16 20 18 Installations, testing , ation commissioning cost to SWID under WBADMIP. IN-SWID-42802-GO-RFB / Procurement of 100 nos. DWLRs with Telemetry for Under Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-09- P-Tubes including supply, IBRD / 80900 Post Open - National 0.00 Implement Bids Two Envelope 15 19 02 16 20 18 Installations, testing , ation commissioning cost to SWID under WBADMIP. IN-DPMU - PURULIA- 38232-GO-RFQ / Supply of Request for Single Stage - 2018-02- 2018-03- 2018-04- Computer, Printer, UPS at IBRD / 80900 Post Open - National 3,643.07 Signed Quotations One Envelope 21 29 06 DPMU, Purulia under WBADMI Project. IN-WBADMIP-51951-GO- RFB / Supply of 10 ( Ten ) numbers of Differential Request for Single Stage - 2018-03- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- Global Positioning System IBRD / 80900 Post Open - National 214,561.44 Signed Bids Two Envelope 02 07 18 28 02 29 (DGPS) Machine for Different Districts DPMUs under WBADMI Project. IN-WBADMIP-61950-GO- DIR / Procurement of STAAD Solution (Latest 2018-05- 2018-05- 2018-06- 2018-12- IBRD / 80900 Post Direct Selection Direct 13,983.31 Signed Version ) by Single Source 08 14 19 16 Selection method under WBADMI Project. IN-WBADMIP-61953-GO- DIR / Procurement of ArcGIS Desktop Extension- Under 2018-05- 2018-05- 2018-06- 2018-12- 3D Analyst (Latest Version IBRD / 80900 Post Direct Selection Direct 10,552.20 Implement 08 14 19 16 ) by Single Source ation Selection method under WBADMI Project. IN-SWID-62217-GO-RFQ / Procurement of Chemicals, Field Kits, Glass wares, Instruments and Under Accessories required for Request for Single Stage - 2018-05- 2018-07- 2019-01- IDA / 50140 Post Open - National 0.00 Implement Chemical Analysis of Quotations One Envelope 30 25 21 ation Water Samples at Chemical & Hydrological Laboratory(DCHL), Burdwan, Malda under SWID in connection with WBADMIP IN-WBADMIP-65949-GO- RFB / Supply and Installation of 35 ( thirty five ) numbers of Under Differential Global Request for Single Stage - 2018-06- 2018-06- 2018-07- 2018-10- 2018-11- 2019-05- IBRD / 80900 Post Open - National 0.00 Implement Positioning System (DGPS) Bids Two Envelope 08 13 25 08 12 11 ation Machine for different DPMUs/ Divisions of WRIDD including PUP Districts under WBADMI Project Page 18 IN-WBADMIP-65953-GO- DIR / Engagement of a reputed Nursery for supplying the various plants on waste Pending 2018-06- 2018-06- 2018-07- 2019-01- land/upland development in IBRD / 80900 Post Direct Selection Direct 0.00 Implement 08 13 18 14 the different districts areas ation Bankura, Purulia, Jhargram, Pas. Midnapore, Birbhum etc. of West Bengal as Horticulture activities under WBADMI project on S IN-WBADMIP-67388-GO- DIR / Procurement of Pending 2018-06- 2018-06- 2018-07- 2019-01- Agricultural Implements IBRD / 80900 Post Direct Selection Direct 0.00 Implement 20 25 30 26 during 2018-19 under ation WBADMI Project. IN-WBADMIP-68065-GO- RFQ / Engagement of a reputed Organic Manure Supplier for supplying Vermi-compost and Neem Pending Request for Single Stage - 2018-07- 2018-08- 2019-02- cake for plantation in IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 02 27 25 waste land intervention in ation the Purulia District area as Horticulture activities under WBADMI Project as per lowest quotation basis. IN-WBADMIP-68067-GO- RFQ / Engagement of a reputed Organic Manure Supplier for supplying Vermi-compost and Neem Pending Request for Single Stage - 2018-07- 2018-08- 2019-02- cake for plantation in IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 02 27 25 waste land intervention in ation the Paschim Medinipur District area as Horticulture activities under WBADMI Project as per lowest quotation basis. IN-WBADMIP-68068-GO- RFQ / Engagement of a reputed Organic Manure Supplier for supplying Vermi-compost and Neem Pending Request for Single Stage - 2018-07- 2018-08- 2019-02- cake for plantation in IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 02 27 25 waste land intervention in ation the Birbhum District area as Horticulture activities under WBADMI Project as per lowest quotation basis. IN-WBADMIP-68069-GO- RFQ / Engagement of a reputed Organic Manure Supplier for supplying Vermi-compost and Neem Pending Request for Single Stage - 2018-07- 2018-08- 2019-02- cake for plantation in IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 02 27 25 waste land intervention in ation the Bankura District area as Horticulture activities under WBADMI Project as per lowest quotation basis. IN-WBADMIP-68090-GO- DIR / Engagement of a reputed manufacturer for supplying the Micro- Nutrient Fertilizer (Zinc Pending Plus) for plantation crops 2018-06- 2018-07- 2018-08- 2019-02- IBRD / 80900 Post Direct Selection Direct 0.00 Implement in the different district 27 02 06 04 ation areas of Bankura, Purulia, Paschim Midnapore, Bhirbhum etc of West Bengal under WBADMI Project on SSS basis. IN-DPMU - JALPAIGURI- 69142-GO-RFQ / Supply, Provide Extent Service, Hire Charges etc. for Capacity Building Event Management Activities Pending Request for Single Stage - 2018-07- 2018-08- 2019-03- (Cluster Level & Workshop IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 13 15 13 at DPMU team on ation Particular Theme etc.) under Institutional Development in different WUA in different blocks of DPMU, Jalpaiguri IN-DPMU - JALPAIGURI- 69146-GO-RFQ / Supply, Provide Extent Service, Hire Charges etc. for Capacity Building Event Pending Management Activities Request for Single Stage - 2018-07- 2018-08- 2019-03- IBRD / 80900 Post Open - National 0.00 Implement (Exposure visit within the Quotations One Envelope 13 15 13 ation Jalpaiguri district& Inter District Exposure Visit etc.) under Institutional Development in different WUA in different blocks of IN-DPMU - JALPAIGURI- 69147-GO-RFQ / Supply, Provide Extent Service, Hire Charges etc. for Capacity Building Event Management Activities Pending (WUA Level Training & Request for Single Stage - 2018-07- 2018-08- 2019-03- IBRD / 80900 Post Open - National 0.00 Implement WRDD/DPMU Quotations One Envelope 13 15 13 ation staff/Panchayat Members of Polygon area capacity Building Workshop etc.) under Institutional Development in different WUA i IN-DPMU - JALPAIGURI- 69148-GO-RFQ / Supply of Developing Training & Publicity Materials (IEC) for Capacity Building Pending Request for Single Stage - 2018-07- 2018-08- 2019-03- Management Activities IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 13 15 13 under Institutional ation Development in different WUA in different blocks of DPMU, Jalpaiguri under WBADMI Project IN-DPMU - JALPAIGURI- 69149-GO-RFQ / Supply Provide Extent Service, Hire Charges etc for Exposure Visit within the Pending Jalpaiguri district & colour Request for Single Stage - 2018-07- 2018-08- 2019-03- IBRD / 80900 Post Open - National 0.00 Implement both side printed Leaf Let Quotations One Envelope 13 15 13 ation for ASS Activities under Agriculture Development in different WUA in different blocks of DPMU, Jalpaiguri under WBADMI IN-DPMU - JALPAIGURI- 69151-GO-RFQ / Supply, Provide Extent Service, Hire Charges etc. for ASS Activities Demonstration Pending Related (Workshop within Request for Single Stage - 2018-07- 2018-08- 2019-03- IBRD / 80900 Post Open - National 0.00 Implement Jalpaiguri District & FFS, Quotations One Envelope 13 15 13 ation FFD, Cluster Level Training etc.) under Agriculture Development in different WUA in different blocks of DPMU, Jalpaiguri IN-WBADMIP-69314-GO- RFQ / Engagement of a reputed Organic Manure Supplier for supplying Vermi-compost for Pending Request for Single Stage - 2018-07- 2018-09- 2019-03- plantation in waste land IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 17 11 11 intervention in the Purulia ation District area as Horticulture activities under WBADMI Project as per lowest quotation basis. IN-DPMU - HOOGHLY- 70347-GO-RFQ / Supply and installation of Desktop Pending Request for Single Stage - 2018-07- 2018-09- 2019-03- Monitor, UPS & Pen Drive IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 24 18 18 for the Office of the ation DPMU Hooghly under WBADMI Project. IN-DPMU - PURULIA- 71241-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Gosai Bundh, Natun Bundh & Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 3,309.87 Signed Chaitan Sayer Bundh and Quotations One Envelope 05 21 28 Supply of Inputs to the FIG for fisheries demonstration in Anti Bundh & Choto Ghorer Bundh in Purulia District. IN-DPMU - PURULIA- 71244-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 3,350.14 Signed mass production at Mahato Quotations One Envelope 05 21 28 Bundh, Gora Bundh & Chanda Goria Bundh in Purulia District. IN-DPMU - PURULIA- 71245-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at ation Mudihar Bundh & Bara Pukur Bundh in Purulia District. IN-DPMU - PURULIA- 71248-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at ation Majhpahari Bara Jore Bundh in Purulia District. IN-DPMU - PURULIA- 71250-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 4,604.84 Signed Quotations One Envelope 05 21 28 mass production at Thakur Bundh & Nayan Bundh in Purulia District. IN-DPMU - PURULIA- 71251-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 2,838.84 Signed Quotations One Envelope 05 21 28 mass production at Vanga Bundh & Majhi Bundh in Purulia District. Page 19 IN-DPMU - PURULIA- 71262-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 4,950.52 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Dumur Bundh, in Purulia District. IN-DPMU - PURULIA- 71263-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at Burir ation Bundh, Choin Bundh in Purulia District. IN-DPMU - PURULIA- 71264-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- mass production at IBRD / 80900 Post Open - National 4,788.11 Signed Quotations One Envelope 05 21 28 Matkam Goria , Balichara Bundh,Gur Bundh,Adhar Bundh,Upar Bundh & Tumba Dari in Purulia District. IN-DPMU - PURULIA- 71269-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 6,778.19 Signed Quotations One Envelope 05 21 28 mass production at Hatisura Bundh& Bastardi Bara Bundh in Purulia District. IN-DPMU - PURULIA- 71272-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at Sutabai ation Bara Bundh in Purulia District. IN-DPMU - PURULIA- 71275-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at ation Bhatuikend Bara Bundh, in Purulia District. IN-DPMU - PURULIA- 71278-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at ation Tatultola Bara Bundh in Purulia District. IN-DPMU - PURULIA- 71280-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 3,221.82 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Hir Bundh in Purulia District. IN-DPMU - PURULIA- 71281-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 5,831.32 Signed Ramapada Goria, Kendu Quotations One Envelope 05 21 28 Bundh, Tuyu Bundh, Tudu Bundh, Gokulnagar WDS-1 & Gokulnagar WDS-7 in Purulia District. IN-DPMU - PURULIA- 71285-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- mass production at Uppar IBRD / 80900 Post Open - National 4,597.69 Signed Quotations One Envelope 05 21 28 Bundh, Malidih WDS-2 Bundh, Mahato Bundh & Laya Goria Bundh in Purulia District. IN-DPMU - PURULIA- 71290-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Request for Single Stage - 2018-08- 2018-08- 2018-08- Haludbani pukur Bundh, IBRD / 80900 Post Open - National 6,510.48 Signed Quotations One Envelope 05 21 28 Haridi WDS-3 Bundh, Haridihi WDS-8, Jambediya WDS-1, Jaragora WDS-1, Murgadih WDS-1 & Namo Bundh in Purulia District. IN-DPMU - PURULIA- 71292-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 2,246.93 Signed Purdaha WDS-3 Bundh, Quotations One Envelope 05 21 28 Purdaha WDS-1, Radhamohanpur WDS-3 Bundh & Radhamohanpur WDS-6 Bundh in Purulia District. IN-DPMU - PURULIA- 71295-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 5,884.82 Signed mass production at Quotations One Envelope 05 21 28 Jambediya WDS-2 Bundh & Raghunathpur WDS-1 Bundh in Purulia District. IN-DPMU - PURULIA- 71299-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 5,860.48 Signed Susunia WDS-3 Bundh, Quotations One Envelope 05 21 28 Susunia WDS-1 Bundh, Bhakta Bundh, Natun Bundh, Naran Bundh & Natun Bundh in Purulia District. IN-DPMU - PURULIA- 71302-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- mass production at Lal IBRD / 80900 Post Open - National 5,322.64 Signed Quotations One Envelope 05 21 28 Bundh and Supply of Inputs to the FIG for fisheries demonstration in Pendra Bundh in Purulia District. IN-DPMU - PURULIA- 71305-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Request for Single Stage - 2018-08- 2018-08- 2018-08- Kalfulia, Dhiridadi , IBRD / 80900 Post Open - National 2,087.91 Signed Quotations One Envelope 05 21 28 Karkacha, Turgu Dhara & Bara Kocha Bundh and Supply of Inputs to the FIG for fisheries demonstration in Pakar Bundh in Purulia District. IN-DPMU - PURULIA- 71308-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 1,880.41 Signed Quotations One Envelope 05 21 28 mass production at Shambu Goria Bundh & Sayer Bundh in Purulia District. IN-DPMU - PURULIA- 71310-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Lipsi, Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 6,300.32 Signed Chatra Gorai, Ralidarha, Quotations One Envelope 05 21 28 Surajharna, Adal, Shimul Goria, Darir, Mahalghutu & Bhanga Hir Bundh in Purulia District. IN-DPMU - PURULIA- 71313-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- mass production at IBRD / 80900 Post Open - National 4,100.68 Signed Quotations One Envelope 05 21 28 Aharbera, Jamnala, Dhaniram, Porogora, Shimuljhara & Kud Goria Bundh in Purulia District. IN-DPMU - PURULIA- 71319-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 4,089.51 Signed Quotations One Envelope 05 21 28 mass production at Chagalkandi Bundh in Purulia District. IN-DPMU - PURULIA- 71323-GO-RFQ / Supply of Inputs to the FIG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 4,608.92 Signed fisheries demonstration in Quotations One Envelope 05 21 28 Kamarhir Bundh in Purulia District. IN-DPMU - PURULIA- 71324-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 5,117.74 Signed Quotations One Envelope 05 21 28 mass production at Chaitan Goria Bundh & Diwan Bundh in Purulia District. IN-DPMU - PURULIA- 71326-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Hura Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 3,572.57 Signed Bundh and Supply of Quotations One Envelope 05 21 28 Inputs to the FIG for fisheries demonstration in Bamun Bundh in Purulia District. IN-DPMU - PURULIA- 71329-GO-RFQ / Supply of Pending Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement the purpose of fisheries Quotations One Envelope 05 21 28 ation mass production at Ahar Bundh in Purulia District. IN-DPMU - PURULIA- 71332-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 3,991.43 Signed Quotations One Envelope 05 21 28 mass production at Dumdumi Bundh in Purulia District. Page 20 IN-DPMU - PURULIA- 71334-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at ation Galinda Bundh & Saheb Bundh in Purulia District. IN-DPMU - PURULIA- 71337-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 5,678.93 Signed Quotations One Envelope 05 21 28 mass production at Tubku Bundh & Natun Bundh in Purulia District. IN-DPMU - PURULIA- 71340-GO-RFQ / Supply of Pending Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement the purpose of fisheries Quotations One Envelope 05 21 28 ation mass production at Sayer Bundh in Purulia District. IN-DPMU - PURULIA- 71341-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 5,128.34 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Choika Bundh in Purulia District. IN-DPMU - PURULIA- 71343-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 3,079.84 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Mahul Bundh in Purulia District. IN-DPMU - PURULIA- 71345-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 4,537.52 Signed mass production at Jagat Quotations One Envelope 05 21 28 Goria Bundh, Bhutlaha Bundh & Jamuna Bundh in Purulia District. IN-DPMU - PURULIA- 71348-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 6,766.64 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Bara Bundh in Purulia District. IN-DPMU - PURULIA- 71350-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 6,316.39 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Asur Bundh in Purulia District. IN-DPMU - PURULIA- 71353-GO-RFQ / Supply of Pending Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement the purpose of fisheries Quotations One Envelope 05 21 28 ation mass production at Dubai Bundh in Purulia District. IN-WBADMIP-71375-GO- RFB / Procurement of Under Agriculture Implements for Request for Single Stage - 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-07- IBRD / 80900 Post Open - National 0.00 Implement different districts in the Bids Two Envelope 25 30 10 26 31 01 ation year 2018-19 under WBADMI Project. IN-DPMU - PURULIA- 71380-GO-RFQ / Supply of Inputs to the women members of Self Help Request for Single Stage - 2018-08- 2018-08- 2018-08- Group (SHG)/ Water users IBRD / 80900 Post Open - National 4,646.52 Signed Quotations One Envelope 05 21 28 Association (WUA) for the purpose of spawn to fingerling production in various Districts of Purulia. IN-DPMU - JALPAIGURI- 74071-GO-RFQ / Supply of saplings for implementation of Demonstration Center Pending Request for Single Stage - 2018-08- 2018-10- 2019-04- for"Fruit Tree Plantation IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 21 16 14 Programme" under ation Horticulture Development in Kharif season'2018 of different WUA in Dhupguri block of DPMU, Jalpaiguri under WBADMI Project IN-DPMU - JALPAIGURI- 74072-GO-RFQ / Supply of saplings for implementation of Demonstration Center Pending Request for Single Stage - 2018-08- 2018-09- 2018-10- for"Fruit Tree Plantation IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 21 25 10 Programme" under ation Horticulture Development in Kharif season'2018 of different WUA in Matiali block of DPMU, Jalpaiguri under WBADMI Project IN-DPMU - JALPAIGURI- 74073-GO-RFQ / Supply of saplings for implementation of Demonstration Center for Pending "Fruit Tree Plantation Request for Single Stage - 2018-08- 2018-09- 2018-10- IBRD / 80900 Post Open - National 0.00 Implement Programme" under Quotations One Envelope 21 25 10 ation Horticulture Development in Kharif season'2018 of different WUA in Maynaguri block of DPMU, Jalpaiguri under WBADMI Project IN-DPMU - JALPAIGURI- 74076-GO-RFQ / Supply of saplings for implementation of Demonstration Center Pending Request for Single Stage - 2018-08- 2018-09- 2018-10- for"Fruit Tree Plantation IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 21 25 10 Programme" under ation Horticulture Development in Kharif season'2018 of different WUA in Falakata block of DPMU, Jalpaiguri under WBADMI Project IN-DPMU - JALPAIGURI- 74077-GO-RFQ / Supply of saplings for implementation of Demonstration Center for Pending Request for Single Stage - 2018-08- 2018-09- 2018-10- "Fruit Tree Plantation IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 21 25 10 Programme" under ation Horticulture Development in Kharif season'2018 of different WUA in Mal block of DPMU, Jalpaiguri under WBADMI Project IN-DPMU - NP-74740-GO- RFQ / Capacity building Pending Request for Single Stage - 2018-08- 2018-10- 2019-04- activities under IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 29 24 22 Institutional Development ation for FY:2018-19 for DPMU N 24 PGS IN-DPMU BIRBHUM- 75421-GO-RFQ / Supply for Demonstration on Deshi magur, Singhi, Koi Pending and Tangra and Request for Single Stage - 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Limited 0.00 Implement Demonstration on Monosex Quotations One Envelope 04 30 28 ation Tilapia Culture under fishery component of WBADMI Project Under Birbhum District. IN-DPMU BIRBHUM- 75430-GO-RFQ / Supply for Demonstration on Polyculture- IMC with deshi magur & Pending Request for Single Stage - 2018-09- 2018-10- 2019-04- Demonstration on Bhetki IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 04 30 28 and Chital culture under ation fishery component of WBADMI Project for effective fisheries development activities Under Birbhum District. IN-DPMU BIRBHUM- 76364-GO-RFQ / Pending Agriculture Training Request for Single Stage - 2018-09- 2018-11- 2019-05- IBRD / 80900 Post Limited 0.00 Implement (Farmers Training, FFS, Quotations One Envelope 22 17 16 ation FFD and Expo- Visit within district) in Birbhum District. IN-DPMU BIRBHUM- 76365-GO-RFQ / Pending Horticulture Training Request for Single Stage - 2018-09- 2018-11- 2019-05- IBRD / 80900 Post Limited 0.00 Implement (Farmers Training, FFS, Quotations One Envelope 22 17 16 ation FFD and Expo- Visit within district) in Birbhum District. IN-DPMU BIRBHUM- 76366-GO-RFQ / Workshop at DPMU Level on Team Pending Request for Single Stage - 2018-09- 2018-11- 2019-05- Building & Communication, IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 22 17 16 Register Maintenance and ation Rabi Cultivation in Birbhum District. IN-DPMU BIRBHUM- 76367-GO-RFQ / Training on Institutional Pending Strenghthening, Annual Request for Single Stage - 2018-09- 2018-11- 2019-05- IBRD / 80900 Post Limited 0.00 Implement Action Plan, Budget Quotations One Envelope 22 17 16 ation Preparation, Water Management, Water Distribution, Crop Planning etc in Birbhum District. IN-DPMU BIRBHUM- 76371-GO-RFQ / Demonstration on Fresh water Prawn with selected Pending Indian Major Carp Culture Request for Single Stage - 2018-09- 2018-11- 2019-05- IBRD / 80900 Post Limited 0.00 Implement and Mass Production on Quotations One Envelope 15 10 09 ation Fresh water Giant Prawn with selected Indian Major Carp at Sangri & Talpukur project village in Birbhum District. IN-DPMU BIRBHUM- 76373-GO-RFQ / 2 nos of Demonstration on Pangus Pending Request for Single Stage - 2018-09- 2018-11- 2019-05- (Monoculture) at Raspur & IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 15 10 09 Purana Project Village of ation Mohammad Bazar Block in Birbhum District. Page 21 IN-WBADMIP-77100-GO- DIR / Engagement of a reputed nursery for supplying the various plants in the different Pending districts of Darjeeling, 2018-09- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Direct Selection Direct 0.00 Implement Uttar Dinajpur, Dakshin 06 11 16 14 ation Dinajpur, Malda, Howrah , S24 Pgs, Nadia, Hooghly and Murshidabad as Horticulture activities under WBADMIP on SSS basis . IN-WBADMIP-77102-GO- RFQ / Engagement of a reputed Organic Manure Supplier for supplying Vermi-compost for Pending Request for Single Stage - 2018-09- 2018-11- 2019-05- plantation in waste land IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 11 06 05 intervention in the ation Howrah,Hooghly,Nadia and S24 Pgs district areas as Horticulture activities under WBADMI Project as per lowest quotatation basis. IN-WBADMIP-77140-GO- DIR / Approval for funding11 ( elevan ) numbers of SOLAR Operated Portable Pump - Pending motor Sets (of 1HP/2 2018-09- 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Direct Selection Direct 0.00 Implement HP)on pilot basis by 06 11 16 15 ation SPMU in association with Local Agency (M.Dhara &Brothers) using different Check Dam Sites in Bankura/Purulia/Paschim Medinipur of WBADMIP IN-DPMU - NP-75292-GO- RFQ / Banana Plantation Pending & Papaya Plantation Request for Single Stage - 2018-09- 2018-10- 2019-04- IBRD / 80900 Post Open - National 0.00 Implement under ASS Horticulture for Quotations One Envelope 02 28 26 ation Kharif 2018 -19 for DPMU Barasat North 24 PGS IN-DPMU BIRBHUM- 78625-GO-RFQ / Proactive disclosure through wall Pending Request for Single Stage - 2018-10- 2018-12- 2019-06- painting regarding IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 15 10 08 institutional issues and ation ASS activities under capacity building activities. IN-DPMU BIRBHUM- 78633-GO-RFQ / Village Pending Level Training Programme Request for Single Stage - 2018-10- 2018-12- 2019-06- IBRD / 80900 Post Limited 0.00 Implement under capacity Building Quotations One Envelope 15 10 08 ation Process in respect of WBADMI Project of Birbhum. IN-DPMU BIRBHUM- 78850-GO-RFQ / To provide Fish feed for Mass Production on IMC with Deshimagur at Malkura Pending Request for Single Stage - 2018-10- 2018-12- 2019-06- Project village and IMC IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 15 10 08 fingerling on mass ation production on IMC at Binuria project village of Bolpur Block under fishery compof WBADMI Project of Birbhum District. IN-DPMU BIRBHUM- 78852-GO-RFQ / Supply to distribute fish feed and prophylactics for Mass Production on IMC at Pending Binuria Project village of Request for Single Stage - 2018-10- 2018-12- 2019-06- IBRD / 80900 Post Limited 0.00 Implement Bolpur Block under fishery Quotations One Envelope 15 10 08 ation component of WBADMI Project for effective fisheries Development activities Under Birbhum District. IN-DPMU BIRBHUM- 78854-GO-RFQ / Supply to implement 1 no. of mass production of monosex tilapia at Anandnagar Pending Project village of Request for Single Stage - 2018-10- 2018-12- 2019-06- IBRD / 80900 Post Limited 0.00 Implement Mohammad Bazar Block Quotations One Envelope 15 10 08 ation under fishery component of WBADMI Project for effective fisheries Development activities Under Birbhum District. IN-DPMU BIRBHUM- 78857-GO-RFQ / Supply to implement Mass Production on IMC with Deshimagur at Malkura Project village Pending Request for Single Stage - 2018-10- 2018-12- 2019-06- of Rajnagar, Block under IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 15 10 08 fishery component of ation WBADMI Project for effective fisheries Development activities Under Birbhum District IN-DPMU BIRBHUM- 78859-GO-RFQ / Supply implement 1 no. of mass production of monosex tilapia at Demurtita Pending Request for Single Stage - 2018-10- 2018-12- 2019-06- Project village of IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 15 10 08 Mohammad Bazar Block ation under fishery component of WBADMI Project for effective fisheries development activities Under Birbhum District. IN-DPMU BIRBHUM- 78860-GO-RFQ / Supply to implement 3 nos. of Mass Production on IMC at Perul and Padampur Pending Request for Single Stage - 2018-10- 2018-12- 2019-06- Project village of Rajnagar IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 15 10 08 Block &Raspur Project ation village of Mohammad Bazar Block under fishery component of WBADMI Project of Birbhum District. IN-DPMU BIRBHUM- 78861-GO-RFQ / Supply to implement Mass Production on IMC with Deshimagur at Malkura Project village Pending Request for Single Stage - 2018-10- 2018-12- 2019-06- of Rajnagar, Block under IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 15 10 08 fishery component of ation WBADMI Project for effective fisheries development activities Under Birbhum District. IN-DPMU - DINAJPUR- 78921-GO-RFQ / Procurement of Seed - Pending Mustard ( Hybrid) for Request for Single Stage - 2018-11- 2018-12- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Agriculture Support Quotations One Envelope 05 31 29 ation Services (ASS- Agriculture) under DPMU- Uttar Dinajpur IN-DPMU - DINAJPUR- 78934-GO-RFQ / Procurement of Seed - Pending Request for Single Stage - 2018-11- 2018-12- 2019-06- Maize for Agriculture IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 31 29 Support Services (ASS- ation Agriculture) under DPMU- Uttar Dinajpur IN-DPMU - DINAJPUR- 78936-GO-RFQ / Procurement of Seed - Pending Request for Single Stage - 2018-11- 2018-12- 2019-06- Lentil for Agriculture IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 31 29 Support Services (ASS- ation Agriculture) under DPMU- Uttar Dinajpur IN-DPMU - DINAJPUR- 79398-GO-RFQ / Procurement of Organic Pending Manure (PSB) for Request for Single Stage - 2018-11- 2018-12- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Agriculture Support Quotations One Envelope 05 31 29 ation Services (ASS- Agriculture) under DPMU- Uttar Dinajpur IN-DPMU - DINAJPUR- 79401-GO-RFQ / Procurement of Vermi Pending Request for Single Stage - 2018-11- 2018-12- 2019-06- Compost for Agriculture IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 31 29 Support Services (ASS- ation Agriculture) under DPMU- Uttar Dinajpur IN-DPMU - NP-79409-GO- RFQ / Supplying seeds and bio-inputs for Pending Demonstration programme Request for Single Stage - 2018-10- 2018-11- 2019-05- IBRD / 80900 Post Open - National 0.00 Implement in cluster mode during Quotations One Envelope 01 26 25 ation Rabi under Agriculture for Fy: 2018 -19 for DPMU Barasat North 24 PGS IN-DPMU - DAKSHIN DINAJ-79874-GO-RFQ / Procurement for Mustard Pending Request for Single Stage - 2018-11- 2018-12- 2019-06- Seed for Demonestration IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 05 31 29 Programme in Cluster ation Mode during Rabi 2018-19 Under ASS-Agriculture. IN-DPMU - DAKSHIN DINAJ-79884-GO-RFQ / Procurement for Maize Pending Request for Single Stage - 2018-11- 2018-12- 2019-06- Seed for Demonestration IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 05 31 29 Programme in Cluster ation mode during Rabi 2018-19 Under ASS-Agriculture IN-DPMU - DAKSHIN DINAJ-79885-GO-RFQ / Procurement for Lentil Pending Request for Single Stage - 2018-11- 2018-12- 2019-06- Seed for Demonestration IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 05 31 29 Programme in Cluster ation Mode during Rabi 2018-19 Under ASS-Agriculture. IN-DPMU - DAKSHIN DINAJ-79892-GO-RFQ / Procurement for Vermi Pending Request for Single Stage - 2018-11- 2018-12- 2019-06- Copmpost for IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 05 31 29 Demonstration Programme ation in Cluster Mode during Rabi 2018-19 Under ASS- Agriculture. Page 22 NON CONSULTING SERVICES Bid Evaluation Activity Reference Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificati Process Prequalification Bidding Documents Report and Contract No. / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process on (Y/N) Status Evaluation Report as Issued Recommendation Completion (US$) Documents Justification / Invitation Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-WBADMIP-26365-NC- DIR / Supply and Installation of Internet Pending Connectivity with Video 2017-08- 2017-09- 2017-10- 2019-12- IBRD / 80900 Post Direct Selection Direct 0.00 Implement conferencing System for 28 04 09 30 ation WBADMI Project in SPMU and in 18 Different Districts DPMUs offices under WBADMIP IN-WBADMIP-26953-NC- DIR / Direct contracting for Exhibition expenses and Participation in the Exhibition for "Skoch 2017-09- 2017-09- 2017-09- 2017-09- Award, 2017" & receiving IBRD / 80900 Post Direct Selection Direct 6,891.95 Completed 04 06 07 22 "Skoch Order-of-Merit" Award at Constitution Club of India,Rafi Marg, New Delhi on 8th September to 9th September, 2017. IN-WBADMIP-46047-NC- DIR / Experience sharing workshop with WUAs in presence of World Bank- 2018-01- 2018-01- 2018-02- 2018-08- IBRD / 80900 Post Direct Selection Direct 7,734.50 Completed WBADMIP on 12.02.2018 25 30 13 13 at RAASMANCH in SWABHUMI, The Heritage Plaza , Kolkata. IN-WBADMIP-46049-NC- DIR / Experience sharing workshop with World Bank and Way forward - 2018-01- 2018-01- 2018-02- 2018-08- IBRD / 80900 Post Direct Selection Direct 3,492.10 Completed WBADMIP on 13.02.2018 25 30 13 12 at RAASMANCH in SWABHUMI, The Heritage Plaza , Kolkata. IN-WBADMIP-46050-NC- DIR / Procurement for Mission visit for the "Progress Review workshop 2018-01- 2018-01- 2018-02- 2018-08- with World Bank - IBRD / 80900 Post Direct Selection Direct 2,236.64 Completed 25 30 13 13 WBADMIP on 14.02.2018 at RAASMANCH in SWABHUMI, The Heritage Plaza , Kolkata. IN-WBADMIP-65945-NC- DIR / Direct contracting for Exhibition expenses and Participation in the Exhibition for "Skoch Pending 2018-06- 2018-06- 2018-07- 2019-01- Award, 2018" & receiving IBRD / 80900 Post Direct Selection Direct 0.00 Implement 08 13 18 14 "Skoch Order-of-Merit" ation Award at Constitution Club of India, Rafi Marg, New Delhi on 21st June to 23rd June, 2018. IN-WBADMIP-68198-NC- RFQ / Engagement of a reputed Transport Agency for Transporting different species of plants and Pending organic manures from Request for Single Stage - 2018-07- 2018-08- 2019-02- IBRD / 80900 Post Limited 0.00 Implement Arambagh , Hooghly to Quotations One Envelope 03 28 25 ation different district areas of West Bengal where plantation program has already been taken up under WBADMIP. IN-WBADMIP-69588-NC- RFQ / Consulting Services as Documentation Agency (DA) for Development & Implementation of Communication & Pending Request for Single Stage - 2018-07- 2018-09- 2019-03- Documentation Strategy in IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 18 12 11 Zone -1 (Malda, Uttar ation Dinajpur, Dakhkhin Dinajpur, Jalpaiguri , Darjeeling , Coochbehar DPMUs ) under the WBADMI Project. IN-WBADMIP-69590-NC- RFQ / Consulting Services as Documentation Agency (DA) for Development & Implementation of Pending Request for Single Stage - 2018-07- 2018-09- 2019-03- Communication & IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 18 12 11 Documentation Strategy in ation Zone -2 (Hooghly, Burdwan, Birbhum and Purulia DPMUs ) under WBADMI Project. IN-WBADMIP-69591-NC- RFQ / Consulting Services as Documentation Agency (DA) for Development & Implementation of Pending Request for Single Stage - 2018-07- 2018-09- 2019-03- Communication & IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 18 12 11 Documentation Strategy in ation Zone -3 (Howrah, East Medinipur, West Medinipur, Bankura DPMUs ) under WBADMI Project. IN-WBADMIP-69593-NC- RFQ / Consulting Services as Documentation Agency (DA) for Development & Implementation of Pending Request for Single Stage - 2018-07- 2018-09- 2019-03- Communication & IBRD / 80900 Post Limited 0.00 Implement Quotations One Envelope 18 12 11 Documentation Strategy in ation Zone -1 (North and South 24 Parganas , Nadia, Murshidabad DPMUs ) under the WBADMI Project. IN-WBADMIP-80359-NC- RFQ / Engagement of a reputed Transport Agency for Transporting different species of plants from Pending Arambagh , Hooghly to Request for Single Stage - 2018-10- 2018-12- 2019-06- IBRD / 80900 Post Limited 0.00 Implement different district areas of Quotations One Envelope 09 19 17 ation Hooghly,Malda,Howrah,Nadi a,Murshidabad,S24Pgs where plantation program has already been taken up under WBADMIP. CONSULTING FIRMS Activity Reference Actual Short List and Request for Opening of Combined Loan / Market Contract Type Process Expression of Evaluation of Contract No. / Description Component Review Type Method Amount Terms of Reference Draft Request for Proposals as Technical Proposals Evaluation Report Signed Contract Credit No. Approach Status Interest Notice Technical Proposal Completion (US$) Proposals Issued / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Actual Planned Actual Planned Actual Contract 1/WBADMI/consultancy/201 5-16 / Third party QAQC Quality And of construction works for Open - IBRD / 80900 Prior Cost-Based 1,287,231.85 Signed implementation of surface International Selection water of minor Irrigation under WB ADMI project IN-WBADMIP-25659-CS- CQS / Hiring of Consulting Services for Consultant Development & Pending 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- IBRD / 80900 Post Qualification Open - National 0.00 2017-08-30 Implementation of Implementation 20 01 01 05 04 Selection Communication & Documentation Strategy for the WBADMI Project by CQS Procedure. IN-WBADMIP-35335-CS- QCBS / Consultancy Services for Aerial LiDAR Survey as Pilot-1 in Quality And Pending 2017-11- 2017-12- 2018-01- 2018-02- 2018-03- 2018-04- 2018-10- different Blocks of PUP IBRD / 80900 Post Cost-Based Open - National 0.00 2017-11-03 Implementation 03 18 15 14 21 25 22 Districts under West Selection Bengal Accelerated Development of Minor Irrigation Project (WBADMIP). IN-WBADMIP-60040-CS- QCBS / Consultancy Services for Project Quality And Management for Under 2018-05- 2018-07- 2018-08- 2018-09- 2018-11- 2019-01- 2019-12- IBRD / 80900 Post Cost-Based Open - National 0.00 2018-04-20 construction of WRI&DD Implementation 11 26 23 20 15 03 31 Selection Office Building/(s) at Saltlake Sector -V, Kolkata under WBADMI Project. IN-WBADMIP-60041-CS- QCBS / Consultancy Services for Planning, detailed Drawings and Quality And Under 2018-05- 2018-06- 2018-07- 2018-08- 2018-10- 2018-11- 2019-12- periodical supervision etc. IBRD / 80900 Post Cost-Based Open - National 0.00 2018-04-20 Implementation 04 26 30 31 05 09 31 for construction of Selection WRI&DD Office Building at Saltlake Sector -V, Kolkata under WBADMI Project. INDIVIDUAL CONSULTANTS Page 23