Sample Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan : 19 mai 2015 3. Date of General Procurement Notice: 21 Août 2015 4. Period covered by this procurement plan: 2015-2016 (18 mois) II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditure Category Contract Value Procurement Method Contract Subject to (Threshold) (US$) Prior Review 1. Works ≥5,000,000 ICB All <5,000,000 NCB <500,000 Shopping No threshold Direct Contracting All 2. Goods ≥500,000 ICB All <500,000 NCB <200,000 Shopping No threshold Direct Contracting All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements: 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) July 9, 2010 Annex Table 3.1: Simplified Procurement Plan (With Methods and Time Schedule) a) Goods 1 2 3 4 5 6 7 8 9 10 Expected Estim. Pre- Dom. Prior Ref. Contract Proc. Bid- Start Amount qualific. Pref. Rev. Comments No. (Description Method Opening Date (US$) (yes/no) (yes/no) (yes/no) Date FDG Matériels Feb.2 240,000 AON No No Yes Dec.2015 1 roulants 016 b) Non-consulting Services 1 2 3 4 5 6 7 8 9 10 Expected Estim. Pre- Dom. Prior Ref. Contract Proc. Bid- Start Amount qualific. Pref. Rev. Comments No. (Description Method Opening Date (US$) (yes/no) (yes/no) (yes/no) Date APD Paiement G1 bénéficiaires Quotati Aug. 133,585 No No Yes June 2015 TMC/ACTP on 15 lot1 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Expenditure Category Contract Value Procurement Method Contract Subject to (Threshold) (US$) Prior Review 3. Consulting firms QCBS, QBS, LCS, FBS, ≥200,000 CQS All contracts QCBS, QBS, LCS, FBS, <200,000 CQS Individuals ≥100,000 Comparison of 3 CVs All contracts <100,000 Comparison of 3 CVs Firms and individuals No threshold Single Source All Note: All terms of reference regardless of contract value are subject to prior review. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. July 9, 2010 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref. Description of Estimate Selection Prior Expected Comments No. Assignment d Method Review Proposals Submission Cost (yes/no) Date (US$) Dénombrement- ciblage communautaire CIC1 109,205 QCBS Yes May 2015 TMC/ACTP lot1 Vatomandry Mahanoro Planification PLA3 ACTP Région 70,000 QCBS Yes July 2015 Haute Matsiatra Encadrement ENCA1 97,459 QCBS Yes Dec.2015 ACTP Vague 1 CONS Enquêtes PMT DGTA pour TMC/ACTP 357,750 QCBS Yes June 2015 1 lot1 CONS Enquêtes PMT DGTA pour TMC/ACTP 511,500 QCBS Yes June 2015 2 lot2 CONS Enquêtes PMT DGTA pour TMC/ACTP 255,750 QCBS Yes June 2015 3 lot3 July 9, 2010 PROCUREMENT Madagascar : Social Safety Net Project PLAN General Information Country: Madagascar Banks Approval Date of the Original Procurement Plan: 2017-03-22 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-09-14 Project ID: P149323 GPN Date: Project Name: Social Safety Net Project Loan / Credit No: IDA / D1450, IDA / 57080 Executing Agency(ies): Intervention Funds for Development, Ministry of Population, Community Nutrition National Program Unit WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DRA13TRINF17001 / Travaux de Component 1: Building a safety construction de l' infrastructure Request for Single Stage - One Pending IDA / 57080 net for the poor in selected rural Post Limited 42,419.35 0.00 2017-07-24 2017-07-25 2017-08-04 2017-08-14 2017-08-28 2017-12-06 N°01 dans la région Analanjirofo Proposals Envelope Implementation areas (Toamasina). DRA13TRINF17002 / Travaux de Component 1: Building a safety construction de l'infrastructure Request for Single Stage - One Pending IDA / 57080 net for the poor in selected rural Post Limited 42,419.35 0.00 2017-07-24 2017-07-25 2017-08-04 2017-08-14 2017-08-28 2017-12-06 N°02 dans la région Analanjirofo Proposals Envelope Implementation areas (Toamasina). DRK13MPETR17001 / Component 1: Building a safety TRAVAUX DE REHABILITATION Single Stage - One Pending IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 41,129.03 0.00 2017-07-13 2017-07-20 2017-08-04 2017-08-07 2017-08-21 2017-12-19 DES OUVRAGES Envelope Implementation areas VOHITRINDRY ILAKATRA ARA13TRMPE17003 / Travaux Component 1: Building a safety Single Stage - One Pending de construction infrastructure de IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,164.52 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-09-05 2018-12-21 Envelope Implementation base n°03 post catastrophe areas ARA13TRMPE17004 / Travaux Component 1: Building a safety Single Stage - One Pending de construction infrastructure de IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,164.52 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-09-05 2018-12-21 Envelope Implementation base n°04 post catastrophe areas ARA13TRMPE17005 / Travaux Component 1: Building a safety Single Stage - One Pending de construction infrastructure de IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,164.52 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-09-05 2018-12-21 Envelope Implementation base n°05 areas ARA13TRMPE17006 / Travaux Component 1: Building a safety Single Stage - One Pending de construction infrastructure de IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,164.52 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-09-05 2018-12-21 Envelope Implementation base n°06 areas ARA13TRMPE17007 / Travaux Component 1: Building a safety Single Stage - One Pending de construction infrastructure de IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,164.52 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-09-05 2018-12-21 Envelope Implementation base n°07 post catastrophe areas ARA13TRMPE17008 / Travaux Component 1: Building a safety Single Stage - One Pending de construction infrastructure de IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,164.52 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-09-05 2018-12-21 Envelope Implementation base n°08 post catastrophe areas ARA13TRMPE17009 / Travaux Component 1: Building a safety Single Stage - One Pending de construction infrastructure de IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,164.52 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-08-26 2018-12-11 Envelope Implementation base n°09 post catastrophe areas ARA13TRMPE17010 / Travaux Component 1: Building a safety Single Stage - One Pending de construction infrastructure de IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,164.52 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-09-05 2018-12-21 Envelope Implementation base n°10 post catastrophe areas ARA13TRMPE17011 / Travaux Component 1: Building a safety Single Stage - One Pending de construction infrastructure de IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,164.52 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-09-05 2018-12-21 Envelope Implementation base n°11 post catastrophe areas DRP83TRMPE17007 / Component 1: Building a safety TRAVAUX DE REHABILITATION Request for Single Stage - One IDA / 57080 net for the poor in selected rural Post Limited 42,741.94 0.00 Canceled 2017-07-26 2017-08-01 2017-08-16 2017-08-17 2017-08-31 2018-12-31 EPP POSTENAWO Proposals Envelope areas AMBOVOMBE7 DRP83TRMPE17006 / Component 1: Building a safety TRAVAUX DE REHABILITATION Request for Single Stage - One IDA / 57080 net for the poor in selected rural Post Limited 42,741.94 0.00 Canceled 2017-07-26 2017-08-01 2017-08-16 2017-08-17 2017-08-31 2018-12-31 EPP POSTENAWO Proposals Envelope areas AMBOVOMBE6 DRP83TRMPE17005 / Component 1: Building a safety TRAVAUX DE REHABILITATION Request for Single Stage - One IDA / 57080 net for the poor in selected rural Post Limited 42,741.94 0.00 Canceled 2017-07-26 2017-08-01 2017-08-16 2017-08-17 2017-08-31 2018-12-31 EPP POSTENAWO Proposals Envelope areas AMBOVOMBE5 DRP83TRMPE17003 / Component 1: Building a safety TRAVAUX DE REHABILITATION Request for Single Stage - One IDA / 57080 net for the poor in selected rural Post Limited 42,741.94 0.00 Canceled 2017-07-26 2017-08-01 2017-08-16 2017-08-17 2017-08-31 2018-12-31 EPP POSTENAWO Proposals Envelope areas AMBOVOMBE3 DRP83TRMPE17004 / Component 1: Building a safety TRAVAUX DE REHABILITATION Request for Single Stage - One IDA / 57080 net for the poor in selected rural Post Limited 42,741.94 0.00 Canceled 2017-07-26 2017-08-01 2017-08-16 2017-08-17 2017-08-31 2018-12-31 EPP POSTENAWO Proposals Envelope areas AMBOVOMBE4 DRP83TRMPE17002 / Component 1: Building a safety TRAVAUX DE REHABILITATION Request for Single Stage - One IDA / 57080 net for the poor in selected rural Post Limited 42,741.94 0.00 Canceled 2017-07-26 2017-08-01 2017-08-16 2017-08-17 2017-08-31 2018-12-31 EPP POSTENAWO Proposals Envelope areas AMBOVOMBE2 DRP83TRMPE17001 / Component 1: Building a safety TRAVAUX DE REHABILITATION Request for Single Stage - One IDA / 57080 net for the poor in selected rural Post Limited 42,741.94 0.00 Canceled 2017-07-26 2017-08-01 2017-08-16 2017-08-17 2017-08-31 2018-12-31 EPP POSTENAWO Proposals Envelope areas AMBOVOMBE1 Page 1 DRP13TRMPE17001 / TRAVAUX DE RAHABILITATION Component 1: Building a safety Single Stage - One Pending POST ENAWO EPP IDA / 57080 net for the poor in selected rural Post Request for Bids Open - National 85,483.87 0.00 2017-08-23 2017-08-25 2017-09-24 2017-09-26 2017-10-09 2018-10-09 Envelope Implementation AMBOVOMBE CENTRE areas ET EPP SEVOHIPOTY DRP13TRMPE17002 / Component 1: Building a safety TRAVAUX DE REHABILITATION Single Stage - One Pending IDA / 57080 net for the poor in selected rural Post Request for Bids Open - National 42,741.94 0.00 2017-08-23 2017-08-25 2017-09-24 2017-09-26 2017-10-09 2018-10-09 POST ENAWO EPP Envelope Implementation areas AMPAMATA SUD DRP13TRMPE17003 / TRAVAUX DE REHABILITATION Component 1: Building a safety Single Stage - One Pending POST ENAWO EPP KOROMA IDA / 57080 net for the poor in selected rural Post Request for Bids Open - National 85,483.87 0.00 2017-08-23 2017-08-25 2017-09-24 2017-09-26 2017-10-09 2018-10-09 Envelope Implementation SOALAVA areas ET EPP AMPAHIJOLOKE DRP13TRMPE17004 / TRAVAUX DE REHABILITATION Component 1: Building a safety Single Stage - One Pending POST ENAWO EPP IDA / 57080 net for the poor in selected rural Post Request for Bids Open - National 85,483.87 0.00 2017-08-23 2017-08-25 2017-09-24 2017-09-26 2017-10-09 2018-10-09 Envelope Implementation LAHIMANARA HAUT areas ET EPP ANDANGORO ARA13TRMPE17001 / Travaux Component 1: Building a safety de construction CEG BELAOKA Single Stage - One Pending IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,164.52 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-09-05 2018-12-21 LOKOHO - BELAOKA LOKOHO Envelope Implementation areas - ANDAPA ARA13TRMPE17012 / Travaux Component 1: Building a safety de construction/réhabilitation Single Stage - One Pending IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,216.13 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-09-05 2018-12-21 CSB AMBINANIFAHO - Envelope Implementation areas AMBINANIFAHO - ANTALAHA ARA13TRMPE17002 / Travaux Component 1: Building a safety de construction EPP Single Stage - One Pending IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 42,164.52 0.00 2017-07-28 2017-07-31 2017-08-15 2017-08-18 2017-09-05 2018-12-21 AMPAPAMENA I - Envelope Implementation areas ANDRATAMARINA - SAMBAVA GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Strengthening MG-FID-9596-GO-UN / safety net administration, DGPO127849-1-2 ACQUISITION IDA / D1450 Prior UN Agencies (Direct) Direct 203,654.39 211,043.69 Signed 2017-01-29 2017-03-23 2017-02-12 2017-03-24 2017-03-03 2017-03-03 2017-03-03 monitoring and social 6 VEHICULES PICK UP 4X4 accountability Component 3: Building the A17 / Aquisition of six (06) institutional capacity for vehicles 4X4 and twenty three IDA / D1450 coordination, monitoring and Prior UN Agencies (Direct) Direct 360,000.00 270,310.18 Signed 2017-01-12 2017-01-12 2017-02-06 2017-02-06 2017-02-06 (23) motorcycles evaluation of the social protection syst em Component 3: Building the MG-UPNNC-11684-GO-DIR / institutional capacity for Acquisition de suppléments IDA / D1450 coordination, monitoring and Prior Direct Selection Direct 1,000,000.00 1,238,076.23 Signed 2017-04-11 2017-04-18 2017-06-06 2017-07-27 2018-06-01 nutritionnels (250 tonnes de evaluation of the social Plumpy Sup) protection syst em DG11FRMAC17001 / Marchés Component 1: Building a safety multiples divers divers travaux Request for Single Stage - One Pending IDA / 57080 net for the poor in selected rural Post Limited 5,143.58 0.00 2017-05-06 2017-05-29 2017-06-19 d'impression pour mesures Quotations Envelope Implementation areas d'accompagnement DG11FRMAC17002 / Marchés multiples divers outils pour Component 1: Building a safety Request for Single Stage - One Pending mesures d'accompagnement IDA / 57080 net for the poor in selected rural Post Limited 20,391.54 0.00 2017-05-06 2017-05-29 2017-06-19 Quotations Envelope Implementation ACTP (pins, pochette à areas é argne...) p DG20FRINFO17003 / Marchés Component 1: Building a safety Request for Single Stage - One Pending multiples achats matériels IDA / 57080 net for the poor in selected rural Post Limited 39,275.35 0.00 2017-05-06 2017-05-29 2017-06-19 Quotations Envelope Implementation informatiques areas DG11FRCPS17004 / Marchés Component 1: Building a safety Request for Single Stage - One Pending multiples (Outils de travail et IDA / 57080 net for the poor in selected rural Post Limited 16,212.53 0.00 2017-05-16 2017-06-09 2017-07-09 Quotations Envelope Implementation d'identification des CPS) areas MG-MPPSPF-18168-GO-UN / Component 3: Building the Fournitures et livraison de deux institutional capacity for voitures 4x4 stations wagon,deux IDA / D1450 coordination, monitoring and Prior UN Agencies (Direct) Direct 275,000.00 154,723.45 Signed 2017-06-15 2017-06-22 2017-06-20 2017-06-27 2017-07-20 2017-06-15 2017-11-24 voitures 4x4 pick-up, trente IDA / 57080 evaluation of the social motos pour le fonds initial et pour protection syst em le fonds additionnel NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DRF11CFPAI17001 / Component 1: Building a safety MARCHES MULTIPLES POUR Single Stage - One Pending IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 2,363.33 0.00 2017-04-18 2017-04-21 2017-05-22 2017-05-25 2017-06-02 2019-06-03 LE PAIEMENT DES Envelope Implementation areas É ICIAIRES BÉNF ACTP DRF12CFPAI17002 / Component 1: Building a safety MARCHES MULTIPLES POUR Single Stage - One Pending IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 8,459.93 0.00 2017-06-19 2017-06-21 2017-07-25 2017-07-27 2017-08-10 2019-08-10 LE PAIEMENT DES Envelope Implementation areas É ICIAIRES BÉNF TMDH DRT12CFPAI17001 / Marché Component 1: Building a safety Single Stage - One Pending multiple pour paiement des IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 5,198.00 0.00 2017-05-02 2017-05-08 2017-06-07 2017-06-10 2017-06-17 2019-11-30 Envelope Implementation é iciaires TMDH bénf areas Page 2 DRT12PRPAI17001 / Marché Component 1: Building a safety Single Stage - One Pending multiple pour paiement des IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 13,819.00 0.00 2017-08-30 2017-09-05 2017-09-15 2017-09-30 2017-10-06 2019-11-30 Envelope Implementation é iciaires du TMDH (lot 1) bénf areas DRT12PRPAI17002 / Marché Component 1: Building a safety Single Stage - One Pending multiple pour paiement des IDA / 57080 net for the poor in selected rural Post Request for Bids Limited 10,730.00 0.00 2017-08-30 2017-09-05 2017-09-15 2017-09-30 2017-10-06 2019-11-30 Envelope Implementation é iciaires du TMDH (Lot 2) bénf areas CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DRP83CFAGEX17001 / Component 1: Building a safety Consultant ENCADREMENT ACT POST Pending IDA / D1450 net for the poor in selected rural Post Qualification Open - National 4,375.00 0.00 2017-04-07 2017-04-14 2017-05-01 2017-05-10 2017-05-14 2017-06-13 CATA RANOPISO REGION Implementation areas Selection ANOSY DRP83CFAGEX17002 / Component 1: Building a safety Consultant ENCADREMENT ACT POST Pending IDA / D1450 net for the poor in selected rural Post Qualification Open - National 4,375.00 0.00 2017-04-07 2017-04-14 2017-05-01 2017-05-10 2017-05-14 2017-06-13 CATA ANALAPATSY REGION Implementation areas Selection ANOSY DRF11CFAGEC17001 / Component 1: Building a safety MARCHES MULTIPLES Quality And Cost- Pending IDA / 57080 net for the poor in selected rural Post Open - National 10,117.37 0.00 2017-04-23 2017-04-30 2017-05-18 2017-06-02 2017-07-03 2017-07-06 2017-07-10 2018-07-10 ENCADREMENT DES UTB EN Based Selection Implementation areas ACTP DRA13MOINF17001 / Maitrise Component 1: Building a safety Consultant d'Suvre des infrastructures N°01 Pending IDA / 57080 net for the poor in selected rural Post Qualification Open - National 5,161.29 0.00 2017-05-08 2017-05-15 2017-05-22 2017-06-06 2017-06-13 2018-12-26 et N°02 dans la région d' Implementation areas Selection Analanjirofo (Toamasina). DRK13CFMO17001 / MAITRISE D'RUVRE DES TRAVAUX DE Component 1: Building a safety Pending REHABILITATION DES IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,870.97 0.00 2017-05-10 2017-05-10 2017-05-20 2017-06-04 2017-06-05 2017-06-08 2017-06-15 2017-12-12 Implementation OUVRAGRES VOHITRINDRY areas ILAKATRA DRP83CFBE17001 / MAITRISE Component 1: Building a safety Pending D'OEUVRE EPP POST CATA IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 6,774.19 0.00 2017-05-09 2017-05-10 2017-06-06 2017-06-21 2017-06-21 2017-06-27 2017-07-07 2018-12-31 Implementation ENAWO AMBOVOMBE 1 areas DRP83CFBE17002 / MAITRISE Component 1: Building a safety Pending D'OEUVRE EPP POSTENAWO IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 9,032.26 0.00 2017-05-09 2017-05-09 2017-06-06 2017-06-21 2017-06-21 2017-06-27 2017-07-07 2018-12-31 Implementation AMBOVOMBE2 areas DG11CFAGFDF17001 / Agence chargée de l'élaboration d'un guide pour la formation des formateurs des agences de mise Component 1: Building a safety Consultant en oeuvre en matière d'épargne Pending IDA / 57080 net for the poor in selected rural Post Qualification Open - National 60,000.00 0.00 2017-05-12 2017-05-19 2017-06-11 2017-07-25 2017-08-02 2019-04-30 communautaire et de Implementation areas Selection développement d'affaires dans les activités ACT-P du Projet de Filets Sociaux mis en oeuvre par le FID ARA13CFMO17001 / Prestation de maîtrise d'Suvre des travaux Component 1: Building a safety Pending de construction d'infrastructure IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 Implementation de base n°01 post catastrophe areas ENAWO ARA13CFMO17002 / Prestation de maîtrise d'Suvre travaux de Component 1: Building a safety Pending construction infrastructure de IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 Implementation base n°02 post catastrophe areas ENAWO ARA13CFMO17003 / Prestation de maîtrise d'Suvre travaux de Component 1: Building a safety Pending construction infrastructure de IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 Implementation base n°03 post catastrophe areas ENAWO ARA13CFMO17004 / Prestation de maîtrise d'Suvre travaux de Component 1: Building a safety Pending construction infrastructure de IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 Implementation base n°04 post catastrophe areas ENAWO ARA13CFMO17005 / Prestation de maîtrise d'Suvre travaux de Component 1: Building a safety Pending construction infrastructure de IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 Implementation base n°05 post catastrophe areas ENAWO ARA13CFMO17006 / Prestation de maîtrise d'Suvre travaux de Component 1: Building a safety Pending construction infrastructure de IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 Implementation base n°06 post catastrophe areas ENAWO ARA13CFMO17007 / Prestation de maîtrise d'Suvre travaux de Component 1: Building a safety Pending construction infrastructure de IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 Implementation base n°07 post catastrophe areas ENAWO ARA13CFMO17008 / Prestation de maîtrise d'Suvre de travaux de Component 1: Building a safety Pending construction infrastructure de IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 Implementation base n°08 post catastrophe areas ENAWO Page 3 ARA13CFMO17009 / Prestation Component 1: Building a safety de maîtrise d'Suvre de travaux de Pending IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 construction infrastructure de Implementation areas base n°09 post catastrophe ARA13CFMO17010 / Prestation de maîtrise d'Suvre de travaux de Component 1: Building a safety Pending construction infrastructure de IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 Implementation base n°10 post catastrophe areas ENAWO ARA13CFMO17011 / Prestation Component 1: Building a safety de maîtrise d'Suvre de travaux de Pending IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 construction infrastructure de Implementation areas base n°11 post catastrophe ARA13CFMO17012 / Prestation Component 1: Building a safety de maîtrise d'Suvre de travaux de Pending IDA / 57080 net for the poor in selected rural Post Least Cost Selection Open - National 3,664.52 0.00 2017-05-24 2017-05-24 2017-05-25 2017-06-09 2017-06-10 2017-06-14 2017-06-23 2018-12-21 construction infrastructure Implementation areas sanitaire n°12 post catastrophe Component 2: Strengthening DG23CFFORMSIG17002 / Consultant safety net administration, Pending Formation des personnels du FID IDA / 57080 Post Qualification Open - National 693.75 0.00 2017-06-07 2017-06-14 2017-06-27 2017-07-17 2017-07-21 2017-08-20 monitoring and social Implementation sur l'utilisation des SIG Selection accountability DRT11CFPLAN17001 / Agence de planification chargée du suivi Component 1: Building a safety Consultant Pending et supervision des chantier, suivi IDA / 57080 net for the poor in selected rural Post Qualification Open - National 15,000.00 0.00 2017-07-18 2017-07-19 2017-08-07 2017-08-27 2017-09-03 2019-04-26 Implementation é aluation communautaire, mise v areas Selection à jour des PAMO DRT11CFPLAN17002 / Agence de planification chargée du suivi Component 1: Building a safety Consultant Pending et supervision des chantiers, IDA / 57080 net for the poor in selected rural Post Qualification Open - National 15,000.00 0.00 2017-07-18 2017-07-19 2017-08-07 2017-08-27 2017-09-03 2019-04-26 Implementation é aluation communautaire, suivi v areas Selection mise à jour des PAMO DRT11CFPLAN17003 / Agence de planification chargée du suivi Component 1: Building a safety Consultant Pending et supervision des chantiers, IDA / 57080 net for the poor in selected rural Post Qualification Open - National 15,000.00 0.00 2017-07-18 2017-07-19 2017-08-07 2017-08-27 2017-09-03 2019-04-26 Implementation é aluation communautaire, suivi v areas Selection mise à jour des PAMO DG81CFPLAT1701 / Component 1: Building a safety Consultant FOURNITURE DE SERVICE EN Pending IDA / D1450 net for the poor in selected rural Post Qualification Open - National 30,000.00 0.00 2017-07-26 2017-07-28 2017-08-17 2017-09-11 2017-09-15 2018-12-14 PLATE FORME INTERNET DE Implementation areas Selection COLLECTE DE DONNÉES DRK11CFSECCS1701 / Suivi- Evaluation Communautaire,Mis à Component 1: Building a safety jour PAMO, côntrole et suivi UTB Quality And Cost- Pending IDA / 57080 net for the poor in selected rural Post Open - National 9,677.42 0.00 2017-08-21 2017-08-22 2017-09-10 2017-10-08 2017-10-12 2017-10-19 2017-10-29 2020-04-16 VATANA-MITANTY OUEST- Based Selection Implementation areas VOHIBOATAVO-AMBALAROKA- AMBOHITROVA DRK11CFSECCS1702 / Suivi- É aluation Communautaire, Mis v Component 1: Building a safety Quality And Cost- Pending a jours PAMO, Contrôle et Suivi IDA / 57080 net for the poor in selected rural Post Open - National 7,419.35 0.00 2017-08-21 2017-08-22 2017-09-10 2017-10-08 2017-10-12 2017-10-19 2017-10-29 2020-04-16 Based Selection Implementation UTB ONILAHY - FENOMBY - areas BENIHAONANA DRK11CFSECCS1703 / Suivi- É aluation Communautaire, Mis v a jours PAMO, Contrôle et Suivi Component 1: Building a safety Quality And Cost- Pending UTB VOHILAVA - IDA / 57080 net for the poor in selected rural Post Open - National 9,677.42 0.00 2017-08-21 2017-08-22 2017-09-10 2017-10-08 2017-10-12 2017-10-19 2017-10-29 2020-04-16 Based Selection Implementation AMBOHIMANARIVO MANGAIKA areas - SAHANABOHITRA - AMBORONDRA DRK11CFSECCS1704 / Suivi- É aluation Communautaire, Mis v Component 1: Building a safety Quality And Cost- Pending a jours PAMO, Contrôle et Suivi IDA / 57080 net for the poor in selected rural Post Open - National 7,419.35 0.00 2017-08-21 2017-08-22 2017-09-10 2017-10-08 2017-10-12 2017-10-19 2017-10-29 2020-04-16 Based Selection Implementation UTB MAROFARIHY - MIZILO areas GARA - FENOARIVO DG12CFCIB1701 / Ciblage Component 1: Building a safety Consultant Enquête Enregistrement Pending IDA / 57080 net for the poor in selected rural Post Qualification Open - National 3,135.48 0.00 2017-09-07 2017-09-07 2017-09-23 2017-10-14 2017-10-27 2017-12-26 é iciaires bénf nouvelles Implementation areas Selection communes BETIOKY LOT 1 DG12CFCIB1702 / Ciblage Component 1: Building a safety Consultant Enquête Enregistrement Pending IDA / 57080 net for the poor in selected rural Post Qualification Open - National 2,090.32 0.00 2017-09-07 2017-09-07 2017-09-23 2017-10-14 2017-10-17 2017-12-16 é iciaires bénf nouvelles Implementation areas Selection communes VOHIPENO LOT 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DRU12CICMP17001 / Component 1: Building a safety Individual Consultant Pending Complémentation enregistrement IDA / 57080 net for the poor in selected rural Post Limited 754.72 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 Selection Implementation é iciaires TMDH Betioky CI1 bénf areas DRF12CICMP17001 / COMPLEMENTATION Component 1: Building a safety Individual Consultant Pending ENREGISTREMENT IDA / 57080 net for the poor in selected rural Post Limited 968.56 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 Selection Implementation BENEFICIAIRES TMDH areas AMBOHIMAHASOA DRT12CICMP17001 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 782.16 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 é iciaires TMDH du District de bénf Selection Implementation areas Faratsiho Page 4 DRA12CICMP17001 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 béneficiaire TMDH TOAMASINAII Selection Implementation areas et MAHANORO DRK12CICMP17001 / Component 1: Building a safety COMPLEMENT Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 1,016.04 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 ENREGISTREMENT TMDH Selection Implementation areas VOHIPENO DRA12CICMP17002 / Component 1: Building a safety complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 béneficiaires TMDH TOAMASINA Selection Implementation areas II et MAHANORO DRF12CICMP17002 / COMPLEMENTATION Component 1: Building a safety Individual Consultant Pending ENREGISTREMENT IDA / 57080 net for the poor in selected rural Post Limited 968.56 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 Selection Implementation BENEFICIAIRES TMDH areas AMBOHIMAHASOA DRT12CICMP17002 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 782.16 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 é iciaires TMDH du District de bénf Selection Implementation areas Faratsiho DRF12CICMP17003 / COMPLEMENTATION Component 1: Building a safety Individual Consultant Pending ENREGISTREMENT IDA / 57080 net for the poor in selected rural Post Limited 968.56 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 Selection Implementation BENEFICIAIRES TMDH areas AMBOHIMAHASOA DRK12CICMP17002 / Component 1: Building a safety COMPLEMENTATION Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 1,016.04 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 ENREGISTREMENT TMDH Selection Implementation areas VOHIPENO Component 3: Building the MG-MPPSPF-10539-CS-CDS / institutional capacity for Under C/723/MP33 Appui ciblage IDA / 57080 coordination, monitoring and Prior Direct Selection Direct 16,000.00 0.00 2016-09-16 2016-11-23 2016-11-16 2016-12-23 2017-01-26 Implementation communautaire evaluation of the social protection syst em DRA12CICMP17003 / Component 1: Building a safety complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 béneficiaires TMDH Toamasina II Selection Implementation areas et Mahanoro DRA12CICMP17004 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 béneficiaire TMDH ToamasinaII et Selection Implementation areas Mahanoro DRU12CICMP17002 / Component 1: Building a safety Individual Consultant Pending Complémentation enregistrement IDA / 57080 net for the poor in selected rural Post Limited 754.72 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 Selection Implementation é iciaires TMDH Betioky CI2 bénf areas DRA12CICMP17005 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 béneficiaires TMDH ToamasinaII Selection Implementation areas et Mahanoto DRU12CICMP17004 / Component 1: Building a safety Individual Consultant Pending Complémentation enregistrement IDA / 57080 net for the poor in selected rural Post Limited 754.72 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 Selection Implementation é iciaires TMDH Betioky CI4 bénf areas DRA12CICMP17006 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 béneficiaire TMDH Toamasina II Selection Implementation areas et Mahanoro DRU12CICMP17005 / Component 1: Building a safety Individual Consultant Pending Complémentation enregistrement IDA / 57080 net for the poor in selected rural Post Limited 754.72 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 Selection Implementation é iciaires TMDH Betioky CI5 bénf areas DRA12CICMP17007 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 é iciaire TMDH Toamasina II bénf Selection Implementation areas et Mahanoro DRU12CICMP17003 / Component 1: Building a safety Individual Consultant Pending Complémentation enregistrement IDA / 57080 net for the poor in selected rural Post Limited 754.12 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 Selection Implementation é iciaires TMDH Betioky CI3 bénf areas DRA12CICMP17008 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 é iciaire TMDH Toamasina II bénf Selection Implementation areas et Mahanoro DRA12CICMP17009 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 é iciaire TMDH Toamasina II bénf Selection Implementation areas et Mahanoro DRA12CICMP17010 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 é iciaire TMDH Toamasina II bénf Selection Implementation areas et Mahanoro DRA12CICMP17011 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 é iciaire TMDH Toamasina II bénf Selection Implementation areas et Mahanoro DRA12CICMP17012 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 645.76 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 é iciaire TMDH Toamasina II bénf Selection Implementation areas et Mahanoro Page 5 DRK12CICMP17003 / Component 1: Building a safety COMPLEMENTATION DES Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 1,016.04 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 BENEFICIAIRES TMDH Selection Implementation areas VOHIPENO DRK12CICMP17004 / Component 1: Building a safety COMPLEMENTATION Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 1,016.04 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 ENREGISTREMENT TMDH Selection Implementation areas VOHIPENO DRT12CICMP17003 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 782.16 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 é iciaires TMDH du District de bénf Selection Implementation areas Faratsiho DRT12CICMP17004 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 782.16 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 é iciaires TMDH du District de bénf Selection Implementation areas Faratsiho DRT12CICMP17005 / Component 1: Building a safety Complémentation enregistrement Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 782.16 0.00 2017-04-11 2017-05-03 2017-05-09 2017-05-15 2017-06-29 é iciaires TMDH du District de bénf Selection Implementation areas Faratsiho MG-UPNNC-11703-CS-CDS / Component 3: Building the Appui des Associations/ONG institutional capacity for partenaires dans le Secteur IDA / D1450 coordination, monitoring and Prior Direct Selection Direct 750,000.00 0.00 Under Review 2017-04-12 2017-04-22 2017-06-26 2019-06-16 Nutrition et Santé dans les zones evaluation of the social d'intervention du Projet protection syst em MG-UPNNC-11931-CS-INDV / Component 3: Building the Consultant individuel chargé de institutional capacity for Individual Consultant Under l'élaboration et de la mise à jour IDA / D1450 coordination, monitoring and Post Limited 5,000.00 0.00 2017-04-07 2017-05-16 2017-04-12 2017-04-26 2017-05-17 2017-06-06 Selection Implementation du Manuel des Opérations evaluation of the social (MANOP) protection syst em DRF12CISAI17001 / SAISIE SUR BASE DE DONNÉES LES Component 1: Building a safety Individual Consultant Pending INFORMATIONS SUR LES IDA / 57080 net for the poor in selected rural Post Limited 218.75 0.00 2017-04-18 2017-04-20 2017-05-18 2017-05-24 2017-12-31 Selection Implementation MÉNAGES BENEFICIAIRES EN areas TMDH DRF12CISAI17002 / SAISIE DANS LA BASE DE DONNÉES Component 1: Building a safety Individual Consultant Pending LES INFORMATIONS IDA / 57080 net for the poor in selected rural Post Limited 218.75 0.00 2017-04-18 2017-04-20 2017-05-18 2017-05-24 2017-12-31 Selection Implementation CONCERNANT LES MÉNAGES areas É ICIAIRES BÉNF TMDH DRF12CISAI17003 / SAISIE DANS LA BASE DE DONNÉES Component 1: Building a safety Individual Consultant Pending LES INFORMATIONS IDA / 57080 net for the poor in selected rural Post Limited 218.75 0.00 2017-04-18 2017-04-20 2017-05-18 2017-05-24 2017-12-31 Selection Implementation CONCERNANT LES MÉNAGES areas É ICIAIRES BÉNF TMDH DRF11CISAI17001 / SAISIE DANS LA BASE DE DONNÉES Component 1: Building a safety Individual Consultant Pending LES INFORMATIONS IDA / 57080 net for the poor in selected rural Post Limited 218.75 0.00 2017-04-18 2017-04-20 2017-05-18 2017-05-24 2017-12-31 Selection Implementation CONCERNANT LES MÉNAGES areas É ICIAIRES BÉNF ACTP DRF11CISAI17002 / SAISIE DANS LA BASE DE DONNÉES Component 1: Building a safety Individual Consultant Pending LES INFORMATIONS IDA / 57080 net for the poor in selected rural Post Limited 218.75 0.00 2017-04-18 2017-04-20 2017-05-18 2017-05-24 2017-12-31 Selection Implementation CONCERNANT LES MÉNAGES areas É ICIAIRES BÉNF ACTP DRF11CISAI17003 / SAISIE DANS LA BASE DE DONNÉES Component 1: Building a safety Individual Consultant Pending LES INFORMATIONS IDA / 57080 net for the poor in selected rural Post Limited 218.75 0.00 2017-04-18 2017-04-20 2017-05-18 2017-05-24 2017-12-31 Selection Implementation CONCERNANT LES MÉNAGES areas É ICIAIRES BÉNF ACTP DRK12CISAI17001 / SAISIE DANS LA BASE DE DONNÉES Component 1: Building a safety LES INFORMATIONS Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 2,250.00 0.00 2017-04-25 2017-05-17 2017-05-27 2017-06-05 2017-12-31 CONCERNANT LES MÉNAGES Selection Implementation areas É ICIAIRES BÉNF TMDH VOHIPENO DIRK12CISAI17002 / SAISIE DANS LA BASE DE DONNÉES Component 1: Building a safety LES INFORMATIONS Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 2,250.00 0.00 2017-04-25 2017-05-17 2017-05-27 2017-06-05 2017-06-25 CONCERNANT LES MÉNAGES Selection Implementation areas É ICIAIRES BÉNF TMDH VOHIPENO DIRK11CISAI17001 / SAISIE DANS LA BASE DE DONNÉES Component 1: Building a safety LES INFORMATIONS Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 2,250.00 0.00 2017-04-25 2017-05-17 2017-05-27 2017-06-05 2017-12-31 CONCERNANT LES MÉNAGES Selection Implementation areas É ICIAIRES BÉNF ACTP MANAKARA DIRK11CISAI17002 / SAISIE DANS LA BASE DE DONNÉES Component 1: Building a safety DES INFORMATIONS Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 2,250.00 0.00 2017-04-25 2017-05-17 2017-05-27 2017-06-05 2017-12-31 CONCERNANT LES MÉNAGES Selection Implementation areas É ICIAIRES BÉNF ACTP MANAKARA DRA12CISAI17001 / Saisie des Registres de coresponsabilité et Component 1: Building a safety Individual Consultant Pending Mise à jour des données des IDA / 57080 net for the poor in selected rural Post Limited 1,166.67 0.00 2017-04-28 2017-05-20 2017-05-26 2017-06-01 2018-01-01 Selection Implementation ménages bénfé iciaires sur MIS areas TMDH. DRA12CISAI17002 / Saisie des registres de coresponsabilité et Component 1: Building a safety Individual Consultant Pending mise à jour des données des IDA / 57080 net for the poor in selected rural Post Limited 1,166.67 0.00 2017-04-28 2017-05-20 2017-05-26 2017-06-01 2017-12-31 Selection Implementation ménages bénf é iciaires sur MIS areas TMDH. Page 6 DRA12CISAI17003 / Saisie des registres de coresponsabilité et Component 1: Building a safety Individual Consultant Pending mise à jour des données des IDA / 57080 net for the poor in selected rural Post Limited 1,166.67 0.00 2017-04-28 2017-05-20 2017-05-26 2017-06-01 2017-12-31 Selection Implementation ménages bénf é iciaires sur MIS areas TMDH. DRA12CISAI17004 / Saisie des registres de coresponsabilité et Component 1: Building a safety Individual Consultant Pending mise à jour des données des IDA / 57080 net for the poor in selected rural Post Limited 1,166.67 0.00 2017-04-28 2017-05-20 2017-05-26 2017-06-01 2017-12-31 Selection Implementation ménages bénf é iciaires sur MIS areas TMDH. DRA12CISAI17005 / Saisie des registres de coresponsabilité et Component 1: Building a safety Individual Consultant Pending mise à jour des données des IDA / 57080 net for the poor in selected rural Post Limited 1,166.67 0.00 2017-04-28 2017-05-20 2017-05-26 2017-06-01 2017-12-31 Selection Implementation ménages bénf é iciaires sur MIS areas TMDH. DRA12CISAI17006 / Saisie des registres de coresponsabilité et Component 1: Building a safety Individual Consultant Pending mise à jour des données des IDA / 57080 net for the poor in selected rural Post Limited 1,166.67 0.00 2017-04-28 2017-05-20 2017-05-26 2017-06-01 2017-12-31 Selection Implementation ménages bénf é iciaires sur MIS areas TMDH. DRA12CISAI17007 / Saisie des registres de coresponsabilité et Component 1: Building a safety Individual Consultant Pending mise à jour des données des IDA / 57080 net for the poor in selected rural Post Limited 1,166.67 0.00 2017-04-28 2017-05-20 2017-05-26 2017-06-01 2017-12-31 Selection Implementation ménages bénf é iciaires sur MIS areas TMDH. DRT11CISAI17001 / Opérateur Component 1: Building a safety Individual Consultant Pending de saisie : saisie des fiches de IDA / 57080 net for the poor in selected rural Post Limited 2,250.00 0.00 2017-04-27 2017-05-19 2017-05-30 2017-06-04 2019-05-31 Selection Implementation présence et traitement sur MIS areas DRT11CISAI17002 / Opérateur Component 1: Building a safety Individual Consultant Pending de saisie : saisie des fiches de IDA / 57080 net for the poor in selected rural Post Limited 2,250.00 0.00 2017-04-27 2017-05-19 2017-05-30 2017-06-04 2019-05-31 Selection Implementation présence et traitement sur MIS areas DRT11CISAI17003 / Opérateur Component 1: Building a safety Individual Consultant Pending de saisie : saisie des fiches de IDA / 57080 net for the poor in selected rural Post Limited 2,250.00 0.00 2017-04-27 2017-05-19 2017-05-30 2017-06-04 2019-05-31 Selection Implementation présence et traitement sur MIS areas DRT11CISAI17004 / Opérateur Component 1: Building a safety Individual Consultant Pending de saisie : saisie des fiches de IDA / 57080 net for the poor in selected rural Post Limited 2,250.00 0.00 2017-04-27 2017-05-19 2017-05-30 2017-06-04 2019-05-31 Selection Implementation présence et traitement sur MIS areas DRT11CISAI17005 / Opérateur Component 1: Building a safety Individual Consultant Pending de saisie : saisie des fiches de IDA / 57080 net for the poor in selected rural Post Limited 2,250.00 0.00 2017-04-27 2017-05-19 2017-05-30 2017-06-04 2019-05-31 Selection Implementation présence et traitement sur MIS areas DRT11CISAI17006 / Opérateur Component 1: Building a safety Individual Consultant Pending de saisie : saisie des fiches de IDA / 57080 net for the poor in selected rural Post Limited 2,250.00 0.00 2017-04-27 2017-05-19 2017-05-30 2017-06-04 2019-05-31 Selection Implementation présence et traitement sur MIS areas Component 3: Building the C-723-MP33 / Appui ciblage institutional capacity for Communautaire en vue de IDA / 57080 coordination, monitoring and Prior Direct Selection Direct 16,000.00 25,608.96 Completed 2016-09-16 2017-04-28 2016-11-23 2016-11-16 2016-12-23 2016-12-23 2017-01-26 2017-03-16 l'évaluation d'impacts de l'ACTP evaluation of the social (Cabinet Mitsinjo) protection syst em MG-UPNNC-16399-CS-INDV / Component 3: Building the Consultant Individuel chargé de institutional capacity for Individual Consultant Pending l'élaboration du Manuel IDA / D1450 coordination, monitoring and Post Limited 5,000.00 0.00 2017-06-07 2017-06-21 2017-07-12 2017-08-16 2017-11-14 Selection Implementation d'Exécution du Projet Filets evaluation of the social Sociaux de Sécurité protection syst em Component 3: Building the MG-UPNNC-16432-CS-INDV / institutional capacity for Appui la mise en place Individual Consultant Pending IDA / D1450 coordination, monitoring and Post Open 5,000.00 0.00 2017-06-12 2017-06-19 2017-07-17 2017-08-14 2017-12-12 (conception et formation) du Selection Implementation evaluation of the social système de collecte de données protection syst em DRU12CISAI001 / saisie des Component 1: Building a safety Individual Consultant Pending enregistrement TMDH opérateur IDA / 57080 net for the poor in selected rural Post Limited 900.00 0.00 2017-05-31 2017-06-05 2017-06-27 2017-08-01 2018-01-28 Selection Implementation de saisie areas DRU12CISAI17002 / SAISIE Component 1: Building a safety Individual Consultant Pending DES ENREGISTREMENTS IDA / 57080 net for the poor in selected rural Post Limited 900.00 0.00 2017-05-31 2017-06-05 2017-06-27 2017-08-01 2018-01-28 Selection Implementation TMDH OPERATEUR DE SAISIE areas DRU12CISAI17003 / Saisie des Component 1: Building a safety Individual Consultant Pending enregistrements TMDH opérateur IDA / 57080 net for the poor in selected rural Post Limited 900.00 0.00 2017-05-31 2017-06-05 2017-06-27 2017-08-01 2018-01-28 Selection Implementation de saisie areas DRU12CISAI17004 / Saisie des Component 1: Building a safety Individual Consultant Pending enregistrements TMDH opérateur IDA / 57080 net for the poor in selected rural Post Limited 900.00 0.00 2017-05-31 2017-06-05 2017-06-27 2017-08-01 2018-01-28 Selection Implementation de saisie areas DRT11CFAGEC17001 / Prise de photos pour les cartes des Component 1: Building a safety Pending récepteurs et enregistrement en IDA / 57080 net for the poor in selected rural Post Direct Selection Direct 2,125.40 0.00 2017-07-18 2017-07-26 2017-09-01 2017-10-01 Implementation vue de la complémentation des areas bénfé iciaires DRT11CFAGEC17002 / Prise de photos pour les cartes des Component 1: Building a safety Pending récepteurs et enregistrement en IDA / 57080 net for the poor in selected rural Post Direct Selection Direct 728.23 0.00 2017-07-18 2017-07-26 2017-09-01 2017-10-01 Implementation vue de la complémentation des areas bénfé iciaires (avenant au contrat) DRT11CFAGEC17003 / Prise de photos pour les cartes des Component 1: Building a safety Pending récepteurs et enregistrement en IDA / 57080 net for the poor in selected rural Post Direct Selection Direct 1,035.89 0.00 2017-07-18 2017-07-26 2017-09-01 2017-10-01 Implementation vue de la complémentation des areas bénfé iciaires (avenant au contrat) Page 7 DRT11CFAGEC17004 / Prise de photos pour les cartes des Component 1: Building a safety Pending récepteurs et enregistrement en IDA / 57080 net for the poor in selected rural Post Direct Selection Direct 861.45 0.00 2017-07-18 2017-07-26 2017-09-01 2017-10-01 Implementation vue de la complémentation des areas bénfé iciaires (avenant au contrat) DRT11CFAGEC17005 / Prise de photos pour les cartes des Component 1: Building a safety Pending récepteurs et enregistrement en IDA / 57080 net for the poor in selected rural Post Direct Selection Direct 528.39 0.00 2017-07-18 2017-07-26 2017-09-01 2017-10-01 Implementation vue de la complémentation des areas bénfé iciaires (avenant au contrat) DRT11CFAGEC17006 / Prise de photos pour les cartes des Component 1: Building a safety Pending récepteurs et enregistrement en IDA / 57080 net for the poor in selected rural Post Direct Selection Direct 825.89 0.00 2017-07-18 2017-07-26 2017-09-01 2017-10-01 Implementation vue de la complémentation des areas bénfé iciaires (avenant au contrat) DRT11CFAGEC17007 / Prise de photos pour les cartes des Component 1: Building a safety Pending récepteurs et enregistrement en IDA / 57080 net for the poor in selected rural Post Direct Selection Direct 1,862.34 0.00 2017-07-18 2017-07-26 2017-09-01 2017-10-01 Implementation vue de la complémentation des areas bénfé iciaires (avenant au contrat) DRT11CFAGEC17008 / Prise de photos pour les cartes des Component 1: Building a safety Pending récepteurs et enregistrement en IDA / 57080 net for the poor in selected rural Post Direct Selection Direct 872.18 0.00 2017-07-18 2017-07-26 2017-09-01 2017-10-01 Implementation vue de la complémentation des areas bénfé iciaires (avenant au contrat) DRT11CFAGEC17009 / Prise de photos pour les cartes des Component 1: Building a safety Pending récepteurs et enregistrement en IDA / 57080 net for the poor in selected rural Post Direct Selection Direct 1,067.50 0.00 2017-07-18 2017-07-26 2017-09-01 2017-10-01 Implementation vue de la complémentation des areas bénfé iciaires (avenant au contrat) DRT12CISAI17001 / Opérateur Component 1: Building a safety de saisie : chargé de la saisie Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 3,483.87 0.00 2017-07-18 2017-07-28 2017-08-22 2017-08-25 2019-11-23 des données du TMDH sur MIS Selection Implementation areas (coresponsabilités, mise à jour) DRT12CISAI17002 / Opérateur Component 1: Building a safety de saisie : chargé de la saisie Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 3,483.87 0.00 2017-07-18 2017-07-28 2017-08-22 2017-08-25 2019-11-23 des données du TMDH sur MIS Selection Implementation areas (coresponsabilités, mise à jour) DRT12CISAI17003 / Opérateur Component 1: Building a safety de saisie : chargé de la saisie Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 3,483.87 0.00 2017-07-18 2017-07-28 2017-08-22 2017-08-25 2019-11-23 des données du TMDH sur MIS Selection Implementation areas (coresponsabilités, mise à jour) DRT12CISAI17004 / Opérateur Component 1: Building a safety de saisie : chargé de la saisie Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 3,483.87 0.00 2017-07-18 2017-07-28 2017-08-22 2017-08-25 2019-11-23 des données du TMDH sur MIS Selection Implementation areas (coresponsabilités, mise à jour) DRT12CISAI17005 / Opérateur Component 1: Building a safety de saisie : chargé de la saisie Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 3,483.87 0.00 2017-07-18 2017-07-28 2017-08-22 2017-08-25 2019-11-23 des données du TMDH sur MIS Selection Implementation areas (coresponsabilités, mise à jour) DRT12CISAI17006 / Opérateur Component 1: Building a safety de saisie : chargé de la saisie Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 3,483.87 0.00 2017-07-18 2017-07-28 2017-08-22 2017-08-25 2019-11-23 des données du TMDH sur MIS Selection Implementation areas (coresponsabilités, mise à jour) Component 1: Building a safety DRP81CISAI17001 / CI Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 1,600.00 0.00 2017-07-21 2017-08-06 2017-08-14 2017-08-17 2018-02-13 OPERATEUR DE SAISIE SUD 1 Selection Implementation areas Component 1: Building a safety DRP81CISAI17002 / CI Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 1,600.00 0.00 2017-07-21 2017-08-06 2017-08-14 2017-08-17 2018-02-13 OPERATEUR DE SAISIE SUD 2 Selection Implementation areas Component 1: Building a safety DRP81CISAI17003 / CI Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 1,600.00 0.00 2017-07-21 2017-08-06 2017-08-14 2017-08-17 2018-02-13 OPERATEUR DE SAISIE SUD 3 Selection Implementation areas Component 1: Building a safety DRP81CISAI17004 / CI Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 1,600.00 0.00 2017-07-21 2017-08-06 2017-08-14 2017-08-17 2018-02-13 OPERATEUR DE SAISIE SUD 4 Selection Implementation areas Component 1: Building a safety DRP81CISAI17005 / CI Individual Consultant Pending IDA / 57080 net for the poor in selected rural Post Limited 1,600.00 0.00 2017-07-21 2017-08-06 2017-08-14 2017-08-17 2018-02-13 OPERATEUR DE SAISIE SUD 5 Selection Implementation areas Page 8