Public Disclosure Copy The World Bank Implementation Status & Results Report Enhanced Road Access Project (P145545) Enhanced Road Access Project (P145545) EAST ASIA AND PACIFIC | Samoa | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 3 | ARCHIVED on 16-Mar-2015 | ISR18212 | Implementing Agencies: Land Transport Authority Key Dates Key Project Dates Board Approval date:17-Oct-2013 Effectiveness Date:20-Feb-2014 Planned Mid Term Review Date:30-Jun-2016 Actual Mid-Term Review Date:-- Original Closing Date:30-Apr-2019 Revised Closing Date:30-Apr-2019 Project Development Objectives Project Development Objective (from Project Appraisal Document) To restore key road sector assets damaged by extreme weather events and enhance the climate resilience of critical roads and bridges in Samoa. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Road and Bridge Reconstruction:(Cost $28.60 M) Technical Assistance:(Cost $2.00 M) Project Management:(Cost $1.40 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  --  Moderate Implementation Status and Key Decisions 3/16/2015 Page 1 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Enhanced Road Access Project (P145545) LTA’s new Project Support Division, comprising one Manager and two Engineers is expected to take over project management on behalf of the implementing agency by the end of February 2015. A primary concern is not losing the progress that has been made over the past few months to accelerate implementation while the new PSD is set up. A good period of overlap the current members of the PMU and the PSD will be necessary to ensure a smooth transition. In addition, extensive training and continuous support will be required to familiarize the new team with World Bank policies and the projects Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  --  Low Macroeconomic  --  --  Moderate Sector Strategies and Policies  --  --  Low Technical Design of Project or Program  --  --  Moderate Institutional Capacity for Implementation and Sustainability  --  --  Moderate Fiduciary  --  --  Substantial Environment and Social  --  --  Moderate Stakeholders  --  --  Low Other  --  --  -- 3/16/2015 Page 2 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Enhanced Road Access Project (P145545) Overall  --  --  Moderate Results Project Development Objective Indicators PHINDPDOTBL  Roads rehabilitated, Non-rural (Kilometers, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 17-Oct-2013 23-Jun-2014 29-Jan-2015 30-Apr-2019 PHINDPDOTBL  2. Bridges rehabilitated to improved standards. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 7.00 Date 17-Oct-2013 23-Jun-2014 29-Jan-2015 30-Apr-2019 PHINDPDOTBL  3. Reduction in disruptions in traffic flows at targeted locations. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4.00 4.00 4.00 0.00 Date 17-Oct-2013 23-Jun-2014 29-Jan-2015 30-Apr-2019 PHINDPDOTBL  4. Instances when project designs are informed by access audits. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 7.00 Date 17-Oct-2013 23-Jun-2014 29-Jan-2015 30-Apr-2019 3/16/2015 Page 3 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Enhanced Road Access Project (P145545) Overall Comments Intermediate Results Indicators PHINDIRITBL  Agreement on key roads for reconstruction. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 2.00 5.00 Date 17-Oct-2013 23-Jun-2014 29-Jan-2015 30-Apr-2019 Comments It has been agreed that Vaitele Street will be widened and the Cross Island Road improved under ERAP. PHINDIRITBL  Identification of specific bridges to be improved. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.00 2.00 6.00 Date 17-Oct-2013 23-Jun-2014 29-Jan-2015 30-Apr-2019 Comments In addition to the Leone Bridge, a new bridge will be built at Ma'lio'lio on the island of Savai'i. Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P145545 IDA-H8840 Effective USD 20.00 20.00 0.00 1.10 17.87 6% P145545 TF-17563 Effective USD 6.35 6.35 0.00 0.00 6.35 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P145545 IDA-H8840 Effective 17-Oct-2013 01-Nov-2013 20-Feb-2014 30-Apr-2019 30-Apr-2019 3/16/2015 Page 4 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Enhanced Road Access Project (P145545) P145545 TF-17563 Effective 08-Oct-2014 08-Oct-2014 08-Oct-2014 30-Apr-2019 30-Apr-2019 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 3/16/2015 Page 5 of 5 Public Disclosure Copy