REPUBLIC OF MOZAMBIQUE MINISTRY OF LAND, ENVIRONMENT AND RURAL DEVELOPMENT Agriculture and Natural Resources Landscape Management Project (ANRLMP) Project No: P149620 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: April 2017] 2. Date of General Procurement Notice: July 26, 2016. 3. Period covered by this procurement plan: April 2017 to October 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ All 1,500,000 2. NCB (Goods) and (Non- Above US$ All Consultant Services) 1,500,000 3. ICB (Works) Above US$ All 5,000,000 4. NCB (Works) Above US$ All 5,000,000 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As per paragraphs 3.17 of the Guidelines and Project Procurement Manual. 1 Date: April 19, 2017 4. Reference to (if any) Project Operational/Procurement Manual: Items to be financed under this Credit/Grants will be procured in line with rules in the Operational Manual, Credit/Grants Agreement and Project Procurement Manual. 1 2 3 4 5 6 7 Domesti Estimated Review c Ref. Cost Packag by Bank Commen Description Preferen No. US$ es (Prior / ts ce thousands Post) (yes/no) Summary of the 1 1,791,00 5 No Post NCB (Works) Summary of NCB 2 1,822,60 7 No Post (Goods) Summary of the NCB (Non- 3 775,00 1 No Prior Consulting Services) Summary of the 4 249,6 6 No Post Shopping (Goods) Summary of the Shopping (Non- 5 20,00 1 No Post Consulting Services) 5. Any Other Special Procurement Arrangements: Not Applicable. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods ≥ 200,000 (Firms) 2. Individual ≥ 200,000 2 Date: April 19, 2017 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Estimated Review Description of Ref. No. Cost Package by Bank Comment Assignment US$ s (Prior / s thousands Post) Summary of number of contracts that 17.800,00 6 Prior 1 will be let under QCBS 2 Individuals 495.00 6 Prior 3 Individuals 2.210,8 32 Post 3 Date: April 19, 2017 PROCUREMENT Mozambique : Moz Agriculture and Natural Resources Landscape Management Project PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2016-07-13 2020-11-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149620 GPN Date: 2016-07-28 Project Name: Moz Agriculture and Natural Resources Landscape Management Project Loan / Credit No: IDA / 58550, IDA / Q9900, IDA / D1190, IDA / D5020 M Executing Agency(ies): INISTRY OF LAND, ENVIRONMENT AND RURAL DEVELOPMENT - International Funds Management Unit WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 64/W/ANRLMP/17 / Securing Land Tenure Rights Single Stage - One 2018-04- Rehabilitation of the data IDA / 58550 and Increasing Natural Post Request for Bids Open - National 366,000.00 372,560.56 Signed 2017-06-30 2017-07-17 2017-07-07 2017-08-18 2017-09-18 2017-10-12 2017-10-23 2017-11-16 Envelope 23 center Resources Resilience 01/ARLMP/W/16 / Rural Agriculture and Forest-Based Single Stage - One 2018-04- IDA / 58550 Post Request for Bids Open - National 270,000.00 213,326.94 Signed 2017-06-12 2017-07-10 2017-06-19 2017-07-31 2017-08-08 2017-08-30 2017-08-23 2017-10-04 2017-09-20 Roads Spot Improvements Value Chain Development Envelope 02 02/W/ARLNMP/16 / Rural Agriculture and Forest-Based Single Stage - One 2018-04- IDA / 58550 Post Request for Bids Open - National 300,000.00 205,391.14 Signed 2017-06-15 2017-07-10 2017-06-21 2017-08-02 2017-08-08 2017-09-01 2017-08-25 2017-10-06 2017-09-26 Roads Spot Improvement Value Chain Development Envelope 04 79/W/ANRLMP/17 / Agriculture and Forest-Based Request for Single Stage - One 2018-12- Constructions of PACES IDA / D1190 Post Open - National 70,000.00 0.00 Canceled 2018-04-09 2018-06-06 Value Chain Development Quotations Envelope 03 Warehouses 153/W/ANRLMP/19 / Rural Agriculture and Forest-Based Single Stage - One 2020-04- Roads Spot Improvement - IDA / 58550 Post Request for Bids Open - National 600,000.00 285,080.85 Signed 2019-05-01 2019-04-01 2019-05-06 2019-06-17 2019-05-23 2019-07-17 2019-09-20 2019-08-21 2019-11-28 Value Chain Development Envelope 17 Nampula Province 151/W/ANRLMP/19 / Rural Agriculture and Forest-Based Single Stage - One 2020-04- Roads Spot Improvement - IDA / 58550 Post Request for Bids Open - National 900,000.00 620,429.77 Signed 2019-05-01 2019-04-25 2019-05-06 2019-06-17 2019-05-29 2019-07-17 2019-05-05 2019-08-21 2019-11-28 Value Chain Development Envelope 17 Zambezia Province 156/W/ANRLMP/19 / Rehabilitation of existing Agriculture and Forest-Based Single Stage - One 2020-12- IDA / D1190 Post Request for Bids Open - National 500,000.00 346,261.93 Signed 2019-09-02 2020-01-19 2019-09-09 2019-10-21 2020-03-27 2019-11-20 2019-07-31 2019-12-25 2019-12-31 Irrigation Schemes - Nampula Value Chain Development Envelope 24 Province 157/W/ANRLMP/19 / Under Rehabilitation of existing Agriculture and Forest-Based Single Stage - One 2020-06- IDA / D1190 Post Request for Bids Open - National 500,000.00 0.00 Implementat 2019-09-02 2019-04-25 2019-09-09 2019-10-21 2019-05-23 2019-11-20 2019-12-25 Irrigation Schemes - Value Chain Development Envelope 22 ion Zambezia Province 164/W/ANRLMP/20 / Securing Land Tenure Rights Pending Request for Single Stage - One 2021-06- Rehabilitation of SPGC in IDA / D5020 and Increasing Natural Post Limited 60,000.00 0.00 Implementat 2020-10-19 2020-12-14 Quotations Envelope 12 Nampula Resources Resilience ion 165/W/ANRLMP/2020 / Securing Land Tenure Rights Pending Single Stage - One 2021-08- Rehabilitation of SPGC in IDA / D5020 and Increasing Natural Post Request for Bids Open - National 500,000.00 0.00 Implementat 2020-10-15 2020-10-20 2020-12-01 2020-12-31 2021-02-04 Envelope 03 Zambézia Resources Resilience ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Coordination and Single Stage - One 01/G/ANRLMP/16 / Vehicles IDA / Q9900 Post Request for Bids Open - National 200,000.00 255,031.59 Signed 2016-08-29 2016-08-29 2016-09-03 2016-10-15 2016-10-11 2016-11-14 2016-11-07 2017-03-20 2016-12-30 2017-09-16 Management Envelope Securing Land Tenure Rights 10/G/ANRLMP/16 / Satelite Single Stage - One IDA / 58550 and Increasing Natural Prior Request for Bids Open - National 775,000.00 0.00 Canceled 2016-11-01 2016-11-07 2016-12-20 2017-01-19 2017-02-23 2017-08-22 picture aquisition Envelope Resources Resilience 6/G/ARLNMP/16 / IT Project Coordination and Single Stage - One IDA / 58550 Post Request for Bids Open - National 219,600.00 133,711.91 Signed 2017-03-30 2017-04-04 2017-05-16 2017-10-27 2017-06-15 2017-11-13 2017-10-19 2017-11-30 2018-02-12 Equipament Management Envelope 73/G/ANRLMP/17 / Aquisition for tractors and Agriculture and Forest-Based Single Stage - One IDA / D1190 Post Request for Bids Open - National 1,107,000.00 952,461.70 Signed 2017-05-19 2017-05-23 2017-05-24 2017-07-05 2017-06-22 2017-08-04 2017-08-01 2017-09-08 2017-09-11 2018-03-07 accessories for Small Value Chain Development Envelope Emerging Commercial Farmers 71/G/ANRLMP/17 / IT Project Coordination and Request for Single Stage - One Equipament for Matching IDA / D1190 Post Limited 29,000.00 24,285.55 Signed 2017-06-08 2017-06-12 2017-06-29 2017-06-22 2017-12-26 Management Quotations Envelope Grant Unit Securing Land Tenure Rights 07/G/ARLNMP/16 / Single Stage - One IDA / D1190 and Increasing Natural Post Request for Bids Open - National 78,000.00 51,789.28 Signed 2017-10-02 2017-08-16 2017-10-09 2017-11-21 2017-10-27 2017-12-21 2017-11-17 2018-01-25 2017-11-30 2018-07-24 Motorcycles Envelope Resources Resilience 86/G/ANRLMP/17 / Motorcycle for production Agriculture and Forest-Based Request for Single Stage - One IDA / D1190 Post Open - National 75,000.00 79,226.22 Signed 2017-11-27 2018-01-22 2017-10-23 2018-07-21 officer and market Value Chain Development Quotations Envelope liaison/Zambezia Province 85/G/ANRLMP/17 / Agriculture and Forest-Based Request for Single Stage - One Acquisition of combine IDA / 58550 Post Open - National 75,000.00 67,384.96 Signed 2017-12-13 2018-02-07 2017-11-13 2018-08-06 Value Chain Development Quotations Envelope harvester/tresher 87/G/ANRLMP/17 / Agriculture and Forest-Based Request for Single Stage - One IDA / 58550 Post Open - National 75,000.00 32,256.77 Signed 2017-12-20 2018-02-14 2017-11-03 2018-08-13 Acquisition Irrigation kits Value Chain Development Quotations Envelope 72/G/ANRLMP/17 / IT Project Coordination and Request for Single Stage - One Equipament for Agriculture IDA / D1190 Post Limited 52,500.00 87,160.96 Signed 2018-03-21 2018-05-09 2018-05-16 2018-07-09 2018-11-12 Management Quotations Envelope Hidraulic/Irrigation team Project Coordination and Single Stage - One 08/ARLNMP/G/16 / Vehicles IDA / 58550 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2017-10-31 2017-11-07 2017-12-19 2018-01-18 2018-05-24 2018-11-20 Management Envelope Page 1 94/G/ANRLMP/17 / Office Agriculture and Forest-Based Request for Single Stage - One Furniture for new staff for PIU IDA / D1190 Post Limited 11,000.00 28,910.86 Signed 2018-02-11 2018-04-13 2018-04-19 2018-05-25 2018-10-16 Value Chain Development Quotations Envelope nampula 93/G/ANRLMP/17 / Agriculture and Forest-Based Request for Single Stage - One IDA / D1190 Post Limited 29,000.00 21,506.59 Signed 2018-02-12 2018-05-09 2018-04-09 2018-06-22 2018-10-06 Acquisition IT Equipment Value Chain Development Quotations Envelope 95/G/ANRLMP/17 / Motorcycle for Production Agriculture and Forest-Based Request for Single Stage - One IDA / D1190 Post Open - National 75,000.00 77,990.19 Signed 2018-02-06 2018-04-04 2017-10-23 2018-10-01 officer and market liaison - Value Chain Development Quotations Envelope Nampula Province 113/G/ANRLMP/18 / Acquisition of plants for Agriculture and Forest-Based Request for Single Stage - One IDA / D1190 Post Limited 75,000.00 20,186.61 Signed 2018-03-16 2018-02-27 2018-05-11 2018-02-28 2018-11-09 forest restoration for Nampula Value Chain Development Quotations Envelope Province 111/G/ANRLMP/18 / Acquisition of Plants for Agriculture and Forest-Based Request for Single Stage - One IDA / D1190 Post Limited 75,000.00 30,344.83 Signed 2018-01-30 2018-01-18 2018-03-27 2018-01-31 2018-09-24 Forest Restoration at Value Chain Development Quotations Envelope Zambezia Province 92/G/ANRLMP/17 / Vehicles Agriculture and Forest-Based Single Stage - One for PIU/Nampula and IDA / D1190 Post Request for Bids Open - National 285,000.00 234,333.75 Signed 2018-03-15 2018-04-02 2018-03-26 2018-05-08 2018-05-02 2018-06-07 2018-04-25 2018-07-12 2018-06-06 2019-01-08 Value Chain Development Envelope Zambezia Provinces 114/G/ANRLMP/18 / Aquisition of seedlings for Agriculture and Forest-Based Single Stage - One restoration of degraded areas IDA / D1190 Post Request for Bids Limited 215,000.00 100,693.60 Signed 2018-07-02 2018-07-02 2018-07-18 2018-07-12 2018-09-06 2018-08-09 2018-10-16 2018-08-31 2018-11-20 2018-09-04 2019-11-20 Value Chain Development Envelope in the Provinces of Nampula and Zambezia 128/G/ANRLM/18 / Printing Project Coordination and Request for Single Stage - One of the project Pogress report- IDA / D1190 Post Limited 33,500.00 28,255.62 Signed 2018-11-06 2018-11-08 2019-01-01 2018-11-29 2019-07-01 Management Quotations Envelope First Production cycle report 91/G/ANRLMP/17 / Agriculture and Forest-Based Single Stage - One Acquisition for Trucks for IDA / D1190 Post Request for Bids Open - National 1,345,000.00 0.00 Canceled 2018-10-31 2018-11-12 2018-12-31 2019-01-30 2019-03-06 2019-09-02 Value Chain Development Envelope Emerging Commercial Farmers 89/G/ANRLMP/17 / Acquisition for tractor for Agriculture and Forest-Based Single Stage - One IDA / D1190 Post Request for Bids Open - National 1,245,000.00 0.00 Canceled 2018-10-31 2018-11-08 2018-12-20 2019-01-21 2019-02-25 2019-08-26 Small Emerging Commercial Value Chain Development Envelope Farmers 90/G/ANRLMP/17 / Acquisition of Agricultural Agriculture and Forest-Based Single Stage - One implements and trailers for IDA / D1190 Post Request for Bids Open - National 648,500.00 0.00 Canceled 2018-09-03 2018-09-08 2018-10-22 2018-11-21 2018-12-26 2019-06-24 Value Chain Development Envelope Small Emerging Commercial Farmers 05/G/ARLNMP/16 / IT Project Coordination and Request for Single Stage - One IDA / D1190 Post Open - National 5,000.00 0.00 Canceled 2018-04-09 2018-06-04 2018-12-05 Equipament Management Quotations Envelope 154-1/CER/NCS/ANRLMP/19 / Hiring Service Provider to Contingency Emergency UN Agencies execute the Agricultural and IDA / D1190 Prior Direct 10,000,000.00 10,000,000.00 Signed 2019-05-03 2019-05-08 2019-06-12 2019-05-07 2019-12-09 Response (Direct) Livestock Recovery Plan post cyclone IDAI 167/G/ANRLMP/EMERG/20 / Acquisition of fuel to supply Securing Land Tenure Rights Pending Request for Single Stage - One vehicles and helicopters for IDA / D5020 and Increasing Natural Post Limited 7,000.00 0.00 Implementati 2020-03-25 2020-05-20 2020-11-16 Quotations Envelope the activities of control of the Resources Resilience on red grasshopper 166/G/ANRLMP/EMERG/20 / Acquisition of protective Securing Land Tenure Rights Request for Single Stage - One equipment, spraying and IDA / D5020 and Increasing Natural Post Limited 48,000.00 0.00 Canceled 2020-03-25 2020-05-20 2020-11-16 Quotations Envelope pesticide for activities of Resources Resilience control of the red grasshopper 61/G/ANRLMP/17 / IT Securing Land Tenure Rights Equipment for revitalization of Single Stage - One IDA / 58550 and Increasing Natural Post Request for Bids Open - National 207,000.00 0.00 Canceled 2020-02-27 2020-03-05 2020-04-16 2020-05-17 2020-06-21 2020-12-18 the data center in the field of Envelope Resources Resilience institutional support 62/G/ANRLMP/17 / Office Securing Land Tenure Rights Request for Single Stage - One furniture in the scope of IDA / 58550 and Increasing Natural Post Limited 60,000.00 0.00 Canceled 2020-02-01 2020-03-28 2020-09-24 Quotations Envelope institutional support Resources Resilience 63/G/ANRLMP/17 / Securing Land Tenure Rights Single Stage - One Equipment for datacenter IDA / 58550 and Increasing Natural Post Request for Bids Open - National 182,000.00 0.00 Canceled 2020-03-02 2020-03-09 2020-04-21 2020-05-21 2020-06-25 2020-12-22 Envelope revitalization Resources Resilience 60/G/ANRLMP/2016 / Office Project Coordination and Request for Single Stage - One IDA / Q9900 Post Limited 56,500.00 0.00 Canceled 2016-12-14 2017-02-08 2017-08-07 Suplies Management Quotations Envelope 09/G/ARLNMP/16 / Office Project Coordination and Request for Single Stage - One IDA / D1190 Post Open - National 46,600.00 0.00 Canceled 2017-04-04 2017-05-30 2017-11-26 Supplies Management Quotations Envelope 166/G/ANRLMP/EMERG/20-2 / Acquisition of protective Contingency Emergency equipment, spraying and IDA / D5020 Post Direct Selection Direct 150,000.00 106,869.86 Signed 2020-04-24 2020-04-16 2020-04-29 2020-04-16 2020-06-03 2020-04-27 2020-11-30 Response pesticide for activities of control of the red grasshopper 174/G/ANRLMP/20 / Securing Land Tenure Rights Under Purchase vehicle for PIU - Single Stage - One IDA / D5020 and Increasing Natural Post Request for Bids Open - National 400,000.00 0.00 Implementati 2020-06-30 2020-08-13 2020-07-05 2020-08-16 2020-09-17 2020-09-15 2020-10-20 2021-04-18 Manica, Sofala and Cabo Envelope Resources Resilience on Delgado Province 175/G/ANRLMP/20 / Pending Purchase of motorcycle for PIU Agriculture and Forest-Based Single Stage - One IDA / D5020 Post Request for Bids Open - National 108,000.00 0.00 Implementati 2020-06-30 2020-07-05 2020-08-16 2020-09-15 2020-10-20 2021-04-18 - Manica, Sofala and Cabo Value Chain Development Envelope on Delgado Province Page 2 176/G/ARNLMP/20 / Purchase a Tablets and Agriculture and Forest-Based Request for Single Stage - One Laptops for a PIU - Manica, IDA / D5020 Post Limited 26,280.00 0.00 Canceled 2020-09-05 2020-10-31 2021-04-29 Value Chain Development Quotations Envelope Sofala and Cabo Delgado Province 173/CD/ANRLMP/G/20 / Upgrading the ArcGIS Desktop Securing Land Tenure Rights Standard license to Advanced IDA / 58550 and Increasing Natural Post Direct Selection Direct 10,000.00 8,893.15 Signed 2020-06-30 2020-04-30 2020-07-05 2020-07-06 2020-08-09 2020-07-06 2021-02-05 and purchasing Argis Online Resources Resilience Credits 177/ANRLMP/G/2020 / IT Pending Equipment for the Project Coordination and Request for Single Stage - One IDA / Q9900 Post Limited 35,000.00 0.00 Implementati 2020-08-23 2020-10-18 2021-04-16 management of expressions Management Quotations Envelope on of interest - Baia Produtiva 178/G/ANRLMP/20 / Under Agriculture and Forest-Based Single Stage - One Acquisition of seedlings for IDA / 58550 Post Request for Bids Open - National 250,000.00 0.00 Implementati 2020-08-18 2020-08-13 2020-08-23 2020-09-14 2020-10-04 2020-09-18 2020-11-03 2020-12-08 2021-06-06 Value Chain Development Envelope restoration component on 179/ANRLMP/G/20 / Acquisition of T-shirts, masks and prevention material from Pending Agriculture and Forest-Based Request for Single Stage - One COVID 19 for training IDA / 58550 Post Open - National 100,000.00 0.00 Implementati 2020-10-06 2020-12-07 2021-06-05 Value Chain Development Quotations Envelope extension workers in Sofala, on Manica, Cabo Delgado and Zambézia Provinces. 176-1/G/ANRLMP/20 / Purchase of tablets and Pending Agriculture and Forest-Based Request for Single Stage - One laptops for a PIU - Manica, IDA / D5020 Post Limited 70,000.00 0.00 Implementati 2020-12-06 2021-01-31 2021-07-30 Value Chain Development Quotations Envelope Sofala and Cabo Delgado on Province NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Securing Land Tenure Rights 10/NC/ANRLMP/16 / Satelite Single Stage - One IDA / 58550 and Increasing Natural Prior Request for Bids Open - National 775,000.00 621,474.24 Signed 2016-11-01 2016-10-13 2016-11-04 2016-10-27 2016-12-16 2016-11-15 2017-01-16 2017-01-30 2017-02-20 2017-05-17 2017-08-19 Picture Aquisition Envelope Resources Resilience 21/NC/ANRLMP/16 / Hiring a Project Coordination and Request for Single Stage - One company to create the slogan, IDA / D1190 Post Open - National 20,000.00 0.00 Canceled 2016-10-16 2016-12-11 2017-06-09 Management Quotations Envelope website, logo. 83/NCS/ANRLMP/17 / Project Coordination and Request for Single Stage - One IDA / D1190 Post Open - National 50,000.00 43,882.07 Signed 2017-10-09 2017-12-04 2017-10-24 2018-06-02 Translation Service Management Quotations Envelope 20/NC/ANRLMP/16 / Hiring company to advertise material Project Coordination and Request for Single Stage - One IDA / D1190 Post Open - National 20,000.00 0.00 Canceled 2018-02-28 2018-04-25 2019-04-25 supply (Posters, Printing, Management Quotations Envelope Flyers and other placartes) 123/NC/ANRLMP/18 / Acquisition of Aerial Images Securing Land Tenure Rights Single Stage - One for Systematic Land IDA / 58550 and Increasing Natural Prior Request for Bids Open - International 775,000.00 0.00 Canceled 2018-08-30 2018-09-11 2018-10-23 2018-11-22 2018-12-27 2021-12-11 Envelope Regularization in Zambezia Resources Resilience and Nampula provinces 124/NC/ANRLMP/18 / Acquisition of Aerial Images Securing Land Tenure Rights Single Stage - One for Systematic Land IDA / 58550 and Increasing Natural Post Request for Bids Open - International 775,000.00 0.00 Canceled 2018-08-10 2018-08-13 2018-08-15 2018-09-26 2018-09-12 2018-10-26 2018-10-18 2018-11-30 2019-05-29 Envelope Regularization in Zambezia Resources Resilience and Nampula provinces 154/CER/NCS/ANRLMP/19 / Hiring Service Provider to Contingency Emergency UN Agencies execute the Agricultural and IDA / D1190 Prior Direct 10,000,000.00 0.00 Canceled 2019-04-24 2019-04-29 2019-06-03 2020-01-29 Response (Direct) Livestock Recovery Plan post cyclone IDAI 124/NC/ANRLMP/18-2 / Aerial Images for Systematic Securing Land Tenure Rights Single Stage - One Regularization of Lands in the IDA / 58550 and Increasing Natural Post Request for Bids Open - International 775,000.00 780,000.00 Signed 2019-08-22 2018-08-13 2019-08-27 2019-10-08 2018-09-12 2019-11-07 2018-10-18 2019-12-12 2019-01-31 2020-06-09 Envelope Provinces of Nampula and Resources Resilience Zambézia. 163/NCS/ANRLMP/19 / Project Coordination and Request for Single Stage - One Renovation of project design IDA / D1190 Post Limited 15,000.00 13,136.01 Signed 2020-01-20 2020-01-28 2020-03-16 2020-03-12 2020-09-12 Management Quotations Envelope software licenses CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 18/ARLNMP/C/16 / Design Securing Land Tenure Rights Quality And Cost- and Supervision of Irrigation IDA / 58550 and Increasing Natural Prior Open - International 500,000.00 0.00 Canceled 2016-08-08 2016-12-14 2016-08-29 2016-10-12 2016-11-09 2016-12-09 2017-01-13 2017-02-17 2018-02-17 Based Selection Schemes (Rehabilitation) Resources Resilience 19/CS/ANRLMP/16 / Service Securing Land Tenure Rights Quality And Cost- Provider for Sistematic IDA / 58550 and Increasing Natural Prior Open - International 6,000,000.00 6,310,924.41 Signed 2016-08-26 2016-09-30 2016-09-01 2016-09-27 2017-01-09 2016-10-25 2017-03-14 2016-11-24 2017-04-15 2016-12-29 2017-10-04 2017-02-02 2017-10-06 2018-02-02 Based Selection community land delimitation Resources Resilience Consultant 14-CS/ANRLMP/16 / River Agriculture and Forest-Based IDA / 58550 Prior Qualification Open - International 750,000.00 0.00 Canceled 2016-08-16 2016-09-06 2016-10-20 2016-11-19 2016-12-22 2017-10-30 basin Studies Value Chain Development Selection Consultant 15-CS/ANRLMP/16 / River Agriculture and Forest-Based IDA / 58550 Prior Qualification Open - International 750,000.00 0.00 Canceled 2016-08-16 2016-09-06 2016-10-20 2016-11-21 2016-12-26 2017-06-24 basin studies Value Chain Development Selection Page 3 14/CS/ANRLMP/16 / River Agriculture and Forest-Based Quality And Cost- IDA / D1190 Prior Open - International 750,000.00 788,705.62 Signed 2016-08-29 2016-09-28 2016-09-19 2016-11-02 2016-12-07 2016-11-30 2017-02-16 2016-12-30 2017-04-06 2017-02-03 2017-08-24 2017-03-10 2017-09-06 2018-03-10 Basin Studies Value Chain Development Based Selection 15/CS/ANRLMP/16 / River Agriculture and Forest-Based Quality And Cost- IDA / D1190 Prior Open - International 750,000.00 819,643.12 Signed 2016-08-29 2016-09-29 2016-09-19 2016-11-02 2016-12-07 2016-11-30 2017-02-16 2016-12-30 2017-03-30 2017-02-03 2017-08-24 2017-03-10 2017-09-06 2018-03-10 Basin Studies Value Chain Development Based Selection 18/CS/ANRLMP/16 / Service Securing Land Tenure Rights Consultant Provider for systematic IDA / 58550 and Increasing Natural Prior Qualification Open - International 2,993,980.00 0.00 Canceled 2016-08-16 2016-09-06 2016-10-22 2016-11-21 2016-12-26 2017-06-24 community land delimitation Resources Resilience Selection 32-CS/ANRLMP/16 / Baseline Project Coordination and Quality And Cost- IDA / Q9900 Post Open - National 127,000.00 0.00 Canceled 2016-08-30 2016-08-29 2016-09-20 2016-11-03 2016-12-01 2017-01-01 2017-02-05 2017-03-12 2018-03-12 Survey Management Based Selection 32/CS/ANRLMP/16 / Baseline Project Coordination and Quality And Cost- IDA / Q9900 Prior Open - International 200,000.00 345,948.67 Signed 2016-10-06 2016-09-30 2016-10-27 2016-10-06 2016-12-09 2017-03-20 2017-01-06 2017-04-21 2017-02-06 2017-07-10 2017-03-13 2018-01-29 2017-04-17 2018-03-12 2018-04-17 Sutudy Management Based Selection 21/CS/ANRLMP/16 / Hiring a Consultant Project Coordination and company to create the slogan, IDA / D1190 Post Qualification Open - National 10,000.00 0.00 Canceled 2016-10-10 2016-10-31 2016-12-14 2017-01-14 2017-02-18 2017-08-17 Management website,logo Selection MZ-UGFI-4758-CS-QCBS / Hire service provider to Agriculture and Forest-Based Quality And Cost- IDA / D1190 Prior Open - International 300,000.00 436,412.61 Signed 2017-01-16 2017-01-25 2017-02-06 2017-02-01 2017-03-22 2017-05-09 2017-04-19 2017-06-23 2017-05-19 2017-08-01 2017-06-26 2018-01-29 2017-07-31 2018-03-13 2018-07-31 administer the partial credit Value Chain Development Based Selection guarantee scheme 11/CS/ANRLMP/16 / Service Agriculture and Forest-Based Quality And Cost- Provider for Value Chain IDA / D1190 Prior Open - International 6,000,000.00 0.00 Canceled 2016-08-26 2016-08-31 2016-09-16 2016-10-30 2016-12-27 2016-11-27 2017-03-07 2016-12-27 2017-04-15 2017-01-31 2017-10-13 2017-03-07 2018-03-07 Value Chain Development Based Selection development 97/CS/ANRLMP/17 / Service Agriculture and Forest-Based Quality Based Provider for Quality Control IDA / D1190 Prior Open - International 1,500,000.00 1,811,368.75 Under Review 2017-12-11 2018-02-07 2018-01-08 2018-02-14 2018-02-27 2018-06-15 2018-03-27 2018-07-18 2018-04-26 2018-08-23 2018-05-28 2018-10-26 2018-07-02 2018-10-29 2020-07-01 Value Chain Development Selection and Finance 12/CS/ANRLMP/16 / Service Agriculture and Forest-Based Quality And Cost- Provider-Restauration of IDA / 58550 Prior Open - International 4,000,000.00 0.00 Canceled 2017-01-16 2017-02-06 2017-03-22 2017-04-19 2017-05-19 2017-06-23 2017-07-28 2018-07-28 Value Chain Development Based Selection degraded land 130/CQS/ANRLMP/18 / Provision of service for Consultant Agriculture and Forest-Based training young people in IDA / 58550 Post Qualification Open - National 70,000.00 0.00 Canceled 2019-02-01 2019-02-22 2019-04-08 2019-05-08 2019-06-12 2019-12-09 Value Chain Development sustainable entrepreneurship Selection in agribusiness 153A/CS/ANRLMP/20 / Consultant Supervision for works of rural Agriculture and Forest-Based Under IDA / D5020 Post Qualification Open - National 30,500.00 0.00 2020-05-13 2020-06-03 2020-06-03 2020-06-12 2020-07-17 2020-08-16 2020-09-20 2021-03-19 roads spot improvement in Value Chain Development Implementation Selection Nampula Province 151A/CS/ANRLMP/20 / Consultant Supervision for works of rural Agriculture and Forest-Based Under IDA / D5020 Post Qualification Open - National 73,000.00 0.00 2020-05-29 2020-06-03 2020-06-19 2020-06-12 2020-08-02 2020-09-01 2020-10-06 2021-04-04 roads spot improvement in Value Chain Development Implementation Selection Zambezia Province 157A/CS/ANRLMP/20 / Supervision for works of Consultant Agriculture and Forest-Based Under rehabilitation of existing IDA / D5020 Post Qualification Open - National 50,000.00 0.00 2020-05-29 2020-06-03 2020-06-19 2020-06-12 2020-08-03 2020-09-02 2020-10-07 2021-04-05 Value Chain Development Implementation irrigation schemes - Ninthulo- Selection Zambezia Province 156A/CS/ANRLMP/20 / Supervision for works of Consultant Agriculture and Forest-Based Under rehabilitation of existing IDA / D5020 Post Qualification Open - National 50,000.00 0.00 2020-06-02 2020-06-03 2020-06-23 2020-06-12 2020-08-06 2020-09-07 2020-10-12 2021-04-10 Value Chain Development Implementation irrigation schemes - Micheche Selection in Nampula Province 165A/CS/ANRLMP/2020 / Securing Land Tenure Rights Consultant Supervision of the Pending IDA / D5020 and Increasing Natural Post Qualification Open - National 50,000.00 0.00 2020-10-22 2020-11-12 2020-12-26 2021-01-25 2021-03-01 2021-08-28 Rehabilitation Works of the Implementation Resources Resilience Selection SPGC of Zambézia 182/ANRLMP/DC/20 / Hiring Consultant a firm to prepare the Project Coordination and Pending IDA / D5020 Post Qualification Limited 160,000.00 0.00 2020-11-10 2020-11-24 2020-12-24 2021-01-28 2021-07-27 Environmental and Social Management Implementation Selection Instruments INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual 38/IC/ANRLMP/16 / Project Coordination and IDA / 58550 Post Consultant Open 108,000.00 60,000.00 Signed 2016-10-19 2016-08-29 2016-12-07 2017-01-18 2016-12-28 2017-01-24 2017-02-01 2017-02-01 2017-07-31 Matching Grants Manager Management Selection Individual 41/IC/ANRLMP/16 / Financial Project Coordination and IDA / 58550 Post Consultant Open 54,000.00 36,000.00 Signed 2016-10-19 2017-02-28 2016-12-07 2017-04-18 2016-12-28 2017-04-20 2017-02-01 2017-04-21 2017-07-31 and Admnistrative Officer Management Selection 53/IC/ANRLMP/16 / Individual Project Coordination and Administrative and Financial IDA / Q9900 Post Consultant Open 10,800.00 7,200.00 Signed 2017-12-26 2017-05-19 2018-02-13 2017-08-25 2018-03-06 2017-08-25 2018-04-10 2017-08-30 2018-10-07 Management Assistant Selection Individual 36/IC/ANRLMP/16 / Finance Project Coordination and IDA / Q9900 Prior Consultant Open 72,000.00 0.00 Canceled 2017-02-13 2017-08-28 2017-04-03 2017-04-24 2017-05-29 2018-11-20 Assistant Management Selection 40/IC/ANRLMP/16 / Individual Project Coordination and Technical Advisor for IDA / 58550 Post Consultant Open 72,000.00 48,000.00 Signed 2017-02-14 2017-02-27 2017-04-04 2017-04-18 2017-04-25 2017-04-20 2017-05-30 2017-05-01 2018-11-21 Management Matching Grant Selection 47/IC/ANRLMP/16 / Individual Project Coordination and Administrative and Financial IDA / Q9900 Post Consultant Open 10,800.00 0.00 Canceled 2018-02-14 2018-04-04 2018-04-25 2018-05-30 2019-11-21 Management Assistant Selection Page 4 39/IC/ANRLMP/16 / Individual Project Coordination and Technical Advisor for IDA / 58550 Post Consultant Open 72,000.00 48,000.00 Signed 2017-02-14 2017-02-27 2017-04-04 2017-04-18 2017-04-25 2017-04-20 2017-05-30 2017-04-21 2018-11-21 Management Matching Grant Selection Individual CS23 / Procurement Project Coordination and IDA / Q9900 Prior Consultant Open - National 99,000.00 0.00 Canceled 2016-07-13 2016-07-13 2016-08-31 2016-09-21 2016-10-26 2018-06-30 Specialist Management Selection Individual 74/IC/ANRLMP/17 / Project Project Coordination and IDA / D1190 Post Consultant Open 82,500.00 0.00 Canceled 2017-06-05 2017-06-02 2017-06-19 2017-06-19 2017-07-10 2018-01-06 Coordinator for ANRLMP Management Selection 65/IC/ANRLMP/17 / Senior Individual Project Coordination and Agricultural Hidraulics IDA / D1190 Post Consultant Open 84,000.00 81,000.00 Canceled 2017-04-05 2017-04-25 2017-05-01 2017-07-07 2017-05-08 2017-07-17 2017-06-05 2017-08-15 2017-12-02 Management Specialist Selection Individual 23/IC/ANRLMP/16 / National Project Coordination and IDA / Q9900 Post Consultant Open 129,600.00 0.00 Canceled 2017-05-30 2017-07-18 2017-08-08 2017-09-12 2018-03-11 Coordinator Management Selection 29/IC/ANRLMP/16 / Individual Project Coordination and Environmental/Resilience IDA / Q9900 Post Consultant Open 108,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Management Specialist Selection Individual 26/IC/ANRLMP/16 / Rural Project Coordination and IDA / Q9900 Post Consultant Open 108,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Development Specialist Management Selection Individual 31/IC/ANRLMP/16 / Project Coordination and IDA / Q9900 Prior Consultant Open 90,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Procurement Manager Management Selection Individual 27/IC/ANRLMP/16 / Land Project Coordination and IDA / Q9900 Post Consultant Open 108,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Administration Specialist Management Selection 52/IC/ANRLMP/16 / Natural Individual Project Coordination and Resaurce Specialist Field IDA / Q9900 Post Consultant Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Operator Selection Individual 35/IC/ANRLMP/16 / Project Coordination and IDA / Q9900 Prior Consultant Open 72,000.00 0.00 Canceled 2017-12-29 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Procurement Assistant Management Selection Individual 42/IC/ANRLMP/16 / Project Coordination and IDA / Q9900 Post Consultant Open 90,000.00 0.00 Canceled 2017-08-02 2017-09-20 2017-10-11 2017-11-15 2018-05-14 Provincial Coordinator Management Selection Individual 33/IC/ANRLMP/16 / Project Coordination and IDA / Q9900 Prior Consultant Open 72,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Procurement Assistant Management Selection Individual 37/IC/ANRLMP/16 / M&E Project Coordination and IDA / Q9900 Post Consultant Open 90,000.00 0.00 Canceled 2017-05-02 2017-05-19 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Specialist Management Selection Individual 25/IC/ANRLMP/16 / Value Project Coordination and IDA / Q9900 Post Consultant Open 111,600.00 0.00 Canceled 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 Chain Specialist Management Selection Individual 30/IC/ANRLMP/16 / GIS Project Coordination and IDA / Q9900 Post Consultant Open 72,000.00 0.00 Canceled 2017-07-03 2017-08-21 2017-09-11 2017-10-16 2018-04-14 Specialist Management Selection Individual 28/IC/ANRLMP/16 / Project Coordination and IDA / Q9900 Post Consultant Open 108,000.00 0.00 Canceled 2017-10-04 2017-11-22 2017-12-13 2018-01-17 2018-07-16 Communication Specialist Management Selection Individual 51/IC/ANRLMP/16 / Land Project Coordination and IDA / Q9900 Post Consultant Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Specialist Field Operator Management Selection 50/IC/ANRLMP/16 / Value Individual Project Coordination and Chain Specialist Field IDA / Q9900 Post Consultant Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Operator Selection 49/IC/ANRLMP/16 / Individual Project Coordination and Infraestruture Specialist Field IDA / Q9900 Post Consultant Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Operator Selection 44/IC/ANRLMP/16 / Value Individual Project Coordination and Chain Specialist Field IDA / Q9900 Post Consultant Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Operator Selection Individual 48/IC/ANRLMP / Provincial Project Coordination and IDA / Q9900 Post Consultant Open 90,000.00 0.00 Canceled 2017-08-02 2017-09-20 2017-10-11 2017-11-15 2018-05-14 Coordinator Management Selection 46/IC/ANRLMP/16 / Natural Individual Project Coordination and Resaurce Specialist Field IDA / Q9900 Post Consultant Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Operator Selection Individual 45/IC/ANRLMP/16 / Land Project Coordination and IDA / Q9900 Post Consultant Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Specialist Field Operator Management Selection 35/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Prior Direct Selection Direct 96,000.00 104,000.00 Signed 2017-05-30 2017-06-22 2017-06-09 2018-06-22 2017-08-14 2017-06-01 2019-08-04 Procurement Assistant Management 37/SS/ANRLMP/17 / M&E Project Coordination and IDA / D1190 Post Direct Selection Direct 120,000.00 120,000.00 Signed 2017-05-29 2017-06-01 2017-06-08 2017-05-19 2017-08-12 2017-06-01 2019-08-02 Specialist Management 48/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Post Direct Selection Direct 120,000.00 120,000.00 Signed 2017-06-30 2017-06-22 2017-07-10 2017-08-14 2017-09-13 2017-08-24 2019-09-03 Provincial Coordinator Management Page 5 29/SS/ANRLMP/17 / Project Coordination and Environment and Social IDA / D1190 Post Direct Selection Direct 144,000.00 144,000.00 Signed 2017-05-29 2017-06-01 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 Management Safeguards Specialist 31/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Prior Direct Selection Direct 120,000.00 130,000.00 Signed 2017-05-29 2017-06-05 2017-06-12 2017-06-22 2017-08-16 2017-06-01 2019-08-06 Procurement Manager Management 24/SS/ANRLMP/17 / Natural Project Coordination and resaurces and forestry IDA / D1190 Post Direct Selection Direct 144,000.00 144,000.00 Signed 2017-05-29 2017-06-01 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 Management Specialist 27/SS/ANRLMP/17 / Land Project Coordination and IDA / D1190 Post Direct Selection Direct 144,000.00 144,000.00 Signed 2017-05-29 2017-06-02 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 Administration Specialist Management 28/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Post Direct Selection Direct 144,000.00 144,000.00 Signed 2017-07-05 2017-06-01 2017-07-17 2017-08-31 2017-09-20 2017-09-04 2019-09-10 Communications Specialist Management 26/SS/ANRLMP/17 / Rural Project Coordination and IDA / D1190 Post Direct Selection Direct 144,000.00 144,000.00 Signed 2017-05-29 2017-06-01 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 Development Specialist Management 30/SS/ANRLMP/17 / GIS Project Coordination and IDA / D1190 Post Direct Selection Direct 96,000.00 96,000.00 Signed 2017-07-05 2017-06-05 2017-07-17 2017-09-18 2017-09-20 2017-09-26 2019-09-10 Specialist Management 33/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Prior Direct Selection Direct 96,000.00 96,000.00 Signed 2017-11-15 2018-03-11 2017-11-27 2018-03-15 2018-01-31 2018-02-02 2020-01-21 Procurement Assistant Management 51/SS/ANRLMP/17 / Land Project Coordination and Administration Specialist Field IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2017-06-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2019-04-29 Management Operator 44/SS/ANRLMP/17 / Value Project Coordination and IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2017-05-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Chain Specialist Field Management Operator 49/SS/ANRLMP/17 / Project Coordination and Infraestruture Specialist Field IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2017-05-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Operator 52/SS/ANRLMP/17 / Natural Project Coordination and Resaurces and Forestry IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2017-06-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Specialist Field Operator 45/SS/ANRLMP/17 / Land Project Coordination and Administration Specialist Field IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2017-05-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Operator 46/SS/ANRLMP/17 / Natural Project Coordination and Resaurces and Forestry IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Specialist Field Operator 50/SS/ANRLMP/17 / Value Project Coordination and IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Chain Specialist Field Management Operator 43/SS/ANRLMP/17 / Project Coordination and Infraestruture Specialist Field IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Operator 23/SS/ANRLMP/17 / National Project Coordination and IDA / D1190 Post Direct Selection Direct 172,800.00 190,080.00 Signed 2017-05-29 2017-06-01 2017-06-12 2017-05-26 2017-08-16 2017-06-01 2019-08-06 Coordinator Management 17/IC/ANRLMP/16 / Securing Land Tenure Rights Individual Facilitation of the IDA / 58550 and Increasing Natural Post Consultant Open 30,000.00 0.00 Canceled 2017-03-10 2017-05-01 2017-05-22 2017-06-26 2017-09-24 development of a Common Resources Resilience Selection Landscape Vision Individual 24/IC/ANRLMP/16 / Forest Project Coordination and IDA / Q9900 Post Consultant Open 108,000.00 0.00 Canceled 2017-05-01 2017-06-19 2017-07-10 2017-08-14 2018-02-10 Specialist Management Selection 34/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Post Direct Selection Direct 120,000.00 120,000.00 Signed 2017-07-31 2017-02-27 2017-08-14 2017-03-13 2017-10-18 2017-03-23 2019-08-09 Financial Manager Management 69/IC/ANRLMP/17 / Individual Project Coordination and Environmental and Social IDA / D1190 Post Consultant Open 12,000.00 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 Management Safeguard Specialist Selection Individual 68/IC/ANRLMP/17 / GIS Project Coordination and IDA / D1190 Post Consultant Open 16,000.00 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 Specialist Management Selection Individual 67/IC/ANRLMP/17 / Project Coordination and IDA / D1190 Post Consultant Open 24,000.00 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 Topographer Management Selection 76/IC/ANRLMP/17 / Individual Project Coordination and safeguard social and IDA / D1190 Post Consultant Open 50,400.00 50,400.00 Signed 2017-10-02 2017-09-27 2017-12-04 2017-12-21 2017-12-25 2017-12-21 2018-01-29 2017-12-28 2018-07-28 Management environmental specialist Selection 77/IC/ANRLMP/17 / Individual Agriculture and Forest-Based Agribusiness Expert (Member IDA / D1190 Post Consultant Open 2,400.00 2,400.00 Signed 2017-09-24 2017-11-01 2017-09-26 2017-11-15 2017-09-27 2017-12-20 2017-09-28 2018-06-18 Value Chain Development of Investiment Committee) Selection 78/IC/ANRLMP/17 / Individual Agribusiness Community Agriculture and Forest-Based IDA / D1190 Post Consultant Open 2,400.00 2,400.00 Signed 2017-09-24 2017-09-12 2017-10-30 2017-09-26 2017-11-14 2017-09-27 2017-12-19 2017-09-28 2018-06-17 representative (Member of the Value Chain Development Selection Investiment Committee) 82/CS/ANRLMP/17 / Supervision for works of rural Agriculture and Forest-Based IDA / D1190 Post Direct Selection Direct 30,000.00 69,301.25 Signed 2017-10-20 2017-12-19 2017-10-30 2018-06-06 2018-01-03 2018-03-30 2018-07-02 roads spot Value Chain Development improvement/Zambezia 81/CS/ANRLMP/17 / Supervision for works of Rural Agriculture and Forest-Based IDA / D1190 Post Direct Selection Direct 27,000.00 31,302.14 Signed 2017-10-20 2017-12-19 2017-10-30 2018-01-03 2018-03-30 2018-07-02 roads spot Value Chain Development improvement/Nampula Page 6 96/IC/ANRLMP/17 / Hiring a consultant to support MSME to develop Business Plans for Agriculture and Forest-Based IDA / D1190 Post Direct Selection Direct 60,000.00 98,784.00 Signed 2017-11-29 2017-12-04 2017-12-11 2017-12-14 2018-02-14 2018-02-28 2018-08-13 Non-timber Forest Products in Value Chain Development Nampula and Zambezia Provinces 98/IC/ANRLMP/17 / Individual Agriculture and Forest-Based Specialist in Business IDA / D1190 Post Consultant Open 92,400.00 92,400.00 Signed 2017-11-30 2017-12-04 2018-01-20 2017-12-29 2018-02-12 2018-01-05 2018-03-19 2018-01-19 2020-03-18 Value Chain Development Development Selection Individual 99/IC/ANRLMP/17 / Agriculture and Forest-Based IDA / D1190 Post Consultant Open 92,400.00 92,400.00 Signed 2017-11-30 2017-12-04 2018-01-22 2017-12-29 2018-02-12 2018-01-05 2018-03-19 2018-01-19 2020-03-18 Knowledge transfer Specialist Value Chain Development Selection 101/IC/ANRLMP/17 / Individual Financial Agriculture and Forest-Based IDA / D1190 Post Consultant Open 66,000.00 66,000.00 Signed 2017-11-30 2017-12-04 2018-01-22 2018-01-29 2018-02-12 2018-01-05 2018-03-19 2018-01-19 2020-03-18 administration/Nampula Value Chain Development Selection Province 102/IC/ANRLMP/17 / Individual Financial Agriculture and Forest-Based IDA / D1190 Post Consultant Open 66,000.00 66,000.00 Signed 2017-11-30 2017-12-04 2018-01-22 2017-12-29 2018-02-12 2018-01-15 2018-03-19 2018-01-19 2020-03-18 administration/Zambezia Value Chain Development Selection Province 103/IC/ANRLMP/17 / Individual Accountants (3 for Nampula Agriculture and Forest-Based IDA / D1190 Post Consultant Open 223,200.00 51,921.60 Signed 2017-11-30 2017-12-04 2018-01-22 2018-05-14 2018-02-12 2018-05-17 2018-03-19 2018-05-29 2020-03-18 Province and 3 for Zambezia Value Chain Development Selection Province) 104/IC/ANRLMP/17 / Provincial Assistant of Value Individual Agriculture and Forest-Based Chain IDA / D1190 Post Consultant Open 84,000.00 84,000.00 Signed 2017-12-20 2018-02-07 2017-12-29 2018-02-28 2018-01-05 2018-04-04 2018-01-19 2018-10-01 Value Chain Development Implementation/Nampula Selection Province 105/IC/ANRLMP/17 / Provincial Assistant of Value Individual Agriculture and Forest-Based Chain IDA / D1190 Post Consultant Open 84,000.00 84,000.00 Signed 2017-12-20 2018-02-07 2017-12-29 2018-02-28 2018-01-05 2018-04-04 2018-01-19 2018-10-01 Value Chain Development Implementation/Zambezia Selection Province 80/IC/ANRLMP/17 / Individual Elaboration of the Warehouse Agriculture and Forest-Based IDA / D1190 Post Consultant Open 5,000.00 0.00 Canceled 2018-01-31 2018-03-21 2018-04-11 2018-05-16 2018-11-12 Construction Project for the Value Chain Development Selection PACES Individual 66/IC/ANRLMP/17 / Civil Project Coordination and IDA / D1190 Post Consultant Open 60,000.00 0.00 Canceled 2018-02-01 2018-03-26 2018-04-16 2018-05-21 2020-05-10 Engineer Management Selection 84/IC/ANRLMP/17 / Individual Agriculture and Forest-Based Supervision of Warehouse IDA / D1190 Post Consultant Open 7,000.00 0.00 Canceled 2018-02-01 2018-03-26 2018-04-16 2018-05-21 2018-11-17 Value Chain Development Construction Selection 42/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Post Direct Selection Direct 120,000.00 120,000.00 Signed 2017-06-30 2017-06-22 2017-07-10 2017-08-14 2017-09-13 2017-08-24 2019-09-03 Provincial Coordinator Management Individual 34/IC/ANRLMP/16 / Finance Project Coordination and IDA / Q9900 Prior Consultant Open 90,000.00 0.00 Canceled 2017-03-18 2017-03-23 2017-05-08 2017-05-29 2017-07-03 2017-12-30 Manager Management Selection 65/IC/ ANRLMP/17 / Senior Securing Land Tenure Rights Individual Agricultural hidraulics IDA / D1190 and Increasing Natural Post Consultant Open 84,000.00 0.00 Canceled 2017-06-13 2017-08-01 2017-08-22 2017-09-26 2018-09-26 Specialist Resources Resilience Selection 43/IC/ANRLMP/16 / Individual Project Coordination and Infraestruture Specialist Field IDA / Q9900 Post Consultant Open 63,000.00 0.00 Canceled 2018-04-09 2018-05-28 2018-06-18 2018-07-23 2019-01-19 Management Operator Selection 25/SS/ANRLMP/17 / Value Project Coordination and IDA / D1190 Post Direct Selection Direct 148,800.00 148,800.00 Signed 2017-11-01 2017-11-03 2017-11-13 2017-12-08 2018-01-17 2017-12-22 2020-01-07 Chain Specialist Management 110/SS/ANRLMP/17 / Consultant for the Review of the Business Plans of the Agriculture and Forest-Based IDA / 58550 Post Direct Selection Direct 13,000.00 12,160.00 Signed 2018-01-17 2018-01-26 2018-02-05 2017-12-27 2018-04-11 2018-02-28 2018-10-08 PACES of the Provinces of Value Chain Development Nampula and Zambezia covered by PGIARN 118/SS/ANRLMP/18 / Project Coordination and Administrative and financial IDA / 58550 Post Direct Selection Direct 10,800.00 12,000.00 Signed 2018-06-27 2018-06-27 2018-07-09 2018-01-11 2018-09-12 2018-03-01 2020-09-11 Management assistant - Zambezia 83/IC/ANRLMP/17 / Securing Land Tenure Rights Individual Supervision for works IDA / D1190 and Increasing Natural Post Consultant Open 18,000.00 15,074.38 Signed 2018-08-31 2018-08-17 2018-10-22 2018-07-31 2018-11-12 2018-11-21 2018-12-17 2018-11-21 2019-03-17 rehabilitation of the data Resources Resilience Selection center in Nampula Province 124/IC/ANRLM/18 / Securing Land Tenure Rights Individual Supervision for works IDA / D1190 and Increasing Natural Post Consultant Open 18,000.00 18,375.72 Signed 2018-08-31 2018-08-17 2018-10-22 2018-05-24 2018-11-12 2018-11-16 2018-12-17 2018-11-16 2019-03-17 rehabilitation of the data Resources Resilience Selection center in Zambezia Province 126/SS/ANRLMP/18 / Project Coordination and Advisor for Institutional IDA / 58550 Post Direct Selection Direct 28,800.00 28,800.00 Signed 2018-08-31 2018-09-12 2018-09-11 2018-09-21 2018-09-20 2018-09-28 2019-03-19 Management Relations and Cooperation Individual 127/IC/ANRLMP/18 / Project Coordination and IDA / 58550 Post Consultant Open 120,000.00 120,000.00 Signed 2018-09-20 2018-09-12 2018-11-12 2018-09-26 2018-12-03 2018-09-24 2019-01-07 2018-10-12 2020-12-27 Operational Chief for ANRLMP Management Selection 117/SS/ANRLMP/18 / Project Coordination and Technical Adviser for IDA / 58550 Post Direct Selection Direct 48,000.00 0.00 Canceled 2018-06-27 2018-03-08 2018-07-09 2018-09-12 2019-09-12 Management Matching Grants Unit 116/SS/ANRLMP/18 / Project Coordination and Technical Adviser for IDA / 58550 Post Direct Selection Direct 48,000.00 0.00 Canceled 2018-06-27 2018-05-10 2018-07-09 2018-09-12 2019-09-12 Management Matching Grants Unit Page 7 115/SS/ANRLMP/18 / Project Coordination and IDA / 58550 Post Direct Selection Direct 120,000.00 0.00 Canceled 2018-06-27 2018-07-09 2018-09-12 2019-03-11 Matching Grants Unit Manager Management 122/SS/ANRLMP/18 / Project Coordination and Financial and Administrative IDA / 58550 Post Direct Selection Direct 36,000.00 0.00 Canceled 2018-08-30 2018-09-10 2018-11-14 2019-11-09 Management Officer (MGU) 149/IC/ANRLMP/19 / Individual Project Coordination and Executive Secretary for IDA / 58550 Post Consultant Open 18,000.00 18,000.00 Signed 2019-05-15 2019-03-28 2019-07-03 2019-06-19 2019-07-24 2019-06-19 2019-08-28 2019-07-24 2020-08-27 Management Zambezia Province Selection 150/IC/ANRLMP/19 / Individual Project Coordination and Platform Assistant for IDA / 58550 Post Consultant Open 6,000.00 6,000.00 Signed 2019-05-15 2019-03-28 2019-07-03 2019-07-31 2019-07-24 2019-08-02 2019-08-28 2019-08-02 2020-08-27 Management Zambezia Province Selection 148/IC/ANRLMP/19 / Individual Project Coordination and Platform Assistant for IDA / 58550 Post Consultant Open 6,000.00 89.02 Signed 2019-05-15 2019-03-28 2019-07-03 2019-09-17 2019-07-24 2019-09-19 2019-08-28 2019-09-30 2020-08-27 Management Nampula Province Selection 146/SSS/ANRLMP/19 / Consultancy for the updating of the instruments of Project Coordination and IDA / 58550 Post Direct Selection Direct 15,000.00 16,100.00 Signed 2019-03-15 2019-03-15 2019-03-25 2019-03-19 2019-05-29 2019-05-27 2019-07-28 environmental and social Management safeguards for the ANRLMP- Additional Financing 147/IC/ANRLMP/19 / Individual Project Coordination and Executive Secretary for IDA / 58550 Post Consultant Open 18,000.00 266.47 Signed 2019-05-15 2019-03-28 2019-07-03 2019-09-17 2019-07-24 2019-09-19 2019-08-28 2019-09-24 2020-02-24 Management Nampula Province Selection Individual 155/IC/ANRLMP/19 / Project Coordination and IDA / 58550 Prior Consultant Open 48,000.00 0.00 Canceled 2019-06-21 2019-05-30 2019-08-12 2019-07-31 2019-09-02 2019-10-07 2020-10-06 Procurement specialist Management Selection 160/SSS/ ANRLM/2019 / Project Coordination and IDA / D1190 Prior Direct Selection Direct 120,000.00 120,000.00 Signed 2019-08-06 2019-08-07 2019-08-20 2019-07-19 2019-10-24 2019-08-01 2021-10-13 Procurement Specialist II Management 161/SSS/ANRMP?2019 / Project Coordination and IDA / D1190 Prior Direct Selection Direct 96,000.00 96,000.00 Signed 2019-08-06 2019-08-07 2019-08-16 2019-07-19 2019-10-21 2019-08-01 2021-10-10 Procurement Specialist III Management 119/SS/ANRLMP/18 / Recruitment of consultant to carry out Qualitative Project Coordination and evaluation of the Mid-term IDA / D1190 Post Direct Selection Direct 3,500.00 0.00 Canceled 2018-06-27 2018-07-11 2018-09-14 2018-09-29 Management Review Report of the SUSTAINABILITY Implementation 152/SSS/ANRLMP/19 / Recruitment of consultant to Agriculture and Forest-Based IDA / 58550 Post Direct Selection Direct 45,000.00 0.00 Canceled 2019-05-23 2019-06-04 2019-08-08 2020-03-05 support the implementation Value Chain Development of the Guarantee Fund 161/IC/ANRLMP/19 / Consultant for risk Individual Project Coordination and assessment of gender based IDA / D5020 Post Consultant Open 15,000.00 0.00 Canceled 2019-09-19 2019-09-19 2019-11-08 2019-11-29 2020-01-03 2020-04-01 Management violence at the Project area, Selection Additional Financing Project . 161-2/SSS/ANRLMP/19 / Consultant for risk Agriculture and Forest-Based assessment of gender based IDA / D5020 Post Direct Selection Direct 15,000.00 24,563.00 Signed 2019-11-10 2019-11-10 2019-11-20 2019-11-06 2020-01-24 2019-11-18 2020-07-22 Value Chain Development violence at the Project area, additional financing Project Individual 155/IC/ANRLMP/19-2 / Project Coordination and Under IDA / 58550 Prior Consultant Open 72,000.00 0.00 2019-12-09 2020-01-22 2020-01-30 2020-02-20 2020-03-26 2021-03-26 Procurement Specialist IV Management Implementation Selection 129/IC/ANRLMP/18 / Individual Project Coordination and Financial Administrative IDA / 58550 Post Consultant Open 26,928.00 0.00 Canceled 2018-11-15 2019-01-07 2019-01-28 2019-03-04 2020-03-03 Management Assistant/Zambezia Province Selection 162/SS/ANRLMP/19 / Training of technicians and beneficiaries of the SUSTENTA Securing Land Tenure Rights Individual Project on restoration IDA / D5020 and Increasing Natural Post Consultant Limited 10,000.00 0.00 Canceled 2019-10-31 2019-10-01 2019-11-05 2019-11-28 2019-11-26 2019-12-31 2020-06-28 approach and agroforestry Resources Resilience Selection systems in Nampula and Zambezia landscapes 164A/IC/ANRLMP/2020 / Securing Land Tenure Rights Individual Supervision of the Pending IDA / D5020 and Increasing Natural Post Consultant Limited 6,000.00 0.00 2020-10-21 2020-10-26 2020-11-16 2020-12-21 2021-06-19 Rehabilitation Works of the Implementation Resources Resilience Selection SPGC of Nampula Page 8