Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 2. Bank’s approval Date of the procurement Plan 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) 2. NCB (Goods) 3. ICB (Works) 4. NCB (Works) 5. (Non-Consultant Services) [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of the ICB (Works) Summary of the ICB (Goods) Summary of the NCB (Works) Summary of the NCB (Goods) Summary of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) 2. Single Source (Firms) 3. Individual 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] July 9, 2010 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of number of contracts that will be let under QCBS Summary of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Nepal : Earthquake Housing Reconstruction Project PLAN General Information Country: Nepal Bank’s Approval Date of the Original Procurement Plan: 2017-04-28 2019-08-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155969 GPN Date: Project Name: Earthquake Housing Reconstruction Project Loan / Credit No: IDA / 57060, IDA / 61640 Executing Agency(ies): National Reconstruction Authority – CLPIU- Grant Management and Local Infrastructure (GMALI) WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-MOFALD-19176-CW- Project Implementation Request for Single Stage - One RFQ / Partition at CL-PIU IDA / 57060 Post Limited 12,641.00 9,336.58 Signed 2017-06-27 2017-07-01 2017-07-09 Support Quotations Envelope Office NP-MOFALD-27995-CW- Project Implementation Request for Single Stage - One IDA / 57060 Post Limited 1,474.00 0.00 Canceled 2017-10-29 2017-11-04 2017-11-12 RFQ / CL-PIU partition Support Quotations Envelope GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EHRP/DoLIDAR/G/DC-1.1 / Procurement of SUV vehicles, i.e. Toyota Hilux IDA / 57060 Housing Reconstruction Prior Direct Selection Direct 0.00 219,125.56 Signed 4WD Double Cab Pickup - 3 Nos. EHRP/DoLIDAR/G/DC-1.2 / Procurement of SUV vehicles, i.e. Nissan Navara IDA / 57060 Housing Reconstruction Prior Direct Selection Direct 0.00 57,797.52 Signed 4WD Double Cab Luxury (LE) Pick Up NP-MOFALD-19165-GO-RFQ Project Implementation Request for Single Stage - One / Photocopy Machine (1) for IDA / 57060 Post Limited 2,042.00 1,840.91 Signed 2017-06-30 2017-07-03 2017-07-08 Support Quotations Envelope CL-PIU NP-MOFALD-19173-GO-RFQ / Printing and delivery of Project Implementation Request for Single Stage - One directives related to IDA / 57060 Post Limited 972.00 682.47 Signed 2017-06-27 2017-07-04 2017-07-08 Support Quotations Envelope formation of reconstruction community,2073 NP-MOFALD-19175-GO-RFQ Project Implementation Request for Single Stage - One / Printing and delivery of IDA / 57060 Post Limited 680.00 620.25 Signed 2017-06-27 2017-07-03 2017-07-07 Support Quotations Envelope ESMF Brochure NP-MOFALD-27970-GO-RFQ / CL-PIU furniture and Project Implementation Request for Single Stage - One fixtures, Sofa set, Chairs, IDA / 57060 Post Limited 12,038.00 6,779.20 Signed 2017-09-14 2017-09-20 2017-09-26 Support Quotations Envelope Office Table, Hanger, Almira, Carpet, Curtains Page 1 NP-MOFALD-27982-GO-RFQ / CL-PIU IT equipments: Project Implementation Request for Single Stage - One IDA / 57060 Post Limited 8,353.00 6,748.10 Signed 2017-09-14 2017-09-21 2017-10-08 Laptoptop Support Quotations Envelope ,AC,printer,scanner,UPS NP-MOFALD-19154-GO-RFQ / CL-PIU furniture and Project Implementation Request for Single Stage - One fixtures, Meeting Table , IDA / 57060 Post Limited 6,806.69 0.00 Canceled 2017-06-29 2017-07-03 2017-07-09 Support Quotations Envelope carpet, curtains , steel almira , rack NP-MOFALD-19181-GO-RFQ Project Implementation Request for Single Stage - One / Laptop computers for DL- IDA / 57060 Post Limited 9,723.84 0.00 Canceled 2017-06-27 2017-07-02 2017-07-07 Support Quotations Envelope MIS Specialist NP-MOFALD-19189-GO-RFQ / desktop computers Project Implementation Request for Single Stage - One IDA / 57060 Post Limited 4,084.00 0.00 Canceled 2017-06-29 2017-07-04 2017-07-08 (including software) (3), Support Quotations Envelope laptop(3) for CL-PIU NP-MOFALD-38218-GO-RFQ Project Implementation Request for Single Stage - One / Tablets for CL-PIU and IDA / 57060 Post Open - National 5,380.00 4,744.38 Signed 2017-11-27 2017-12-14 2017-12-29 Support Quotations Envelope DL-PIU NP-MOFALD-41940-GO-RFQ / Printing and delivery of Booklet with collection of Project Implementation Request for Single Stage - One Acts, Regulations and IDA / 57060 Post Limited 24,950.00 21,696.23 Signed 2018-01-07 2018-01-16 2018-01-31 Support Quotations Envelope directives related to reconstruction after earthquake and Dairy NP-MOFALD-41941-GO-RFQ / Printing and delivery of Contingency Emergency Request for Single Stage - One housing reconstruction IDA / 57060 Post Limited 16,634.00 12,568.85 Signed 2018-01-08 2018-01-19 2018-02-18 Response Quotations Envelope agreement form and retrofitting form NP-MOFALD-76338-GO-RFQ / 6 numbers of Project Implementation Request for Single Stage - One IDA / 61640 Post Limited 14,000.00 12,176.90 Signed 2018-09-09 2018-10-03 2018-10-18 Motorcycles/scooters for Support Quotations Envelope CLPIU NP-MOFALD-67742-GO-RFQ Project Implementation Request for Single Stage - One / AC -3 nos and Laptops -12 IDA / 57060 Post Limited 15,723.00 0.00 Canceled 2018-06-27 2018-07-03 2018-07-06 Support Quotations Envelope nos for CL-PIU and DL-PIU NP-MOFALD-19168-GO-RFQ / desktop computers (including software) Project Implementation Request for Single Stage - One IDA / 57060 Post Limited 30,630.00 0.00 Canceled 2017-06-29 2017-07-04 2017-07-09 (14),laptop(14), photocopier Support Quotations Envelope (14) ,printer(14) for DL-PIUs of 14 districts NP-MOFALD-27983-GO-RFQ Project Implementation Request for Single Stage - One / Gas heater and other IDA / 57060 Post Limited 1,474.00 0.00 Canceled 2017-11-01 2017-11-07 2017-11-14 Support Quotations Envelope miscelleneous items NP-MOFALD-27971-GO-RFQ / CL-PIU carpet, curtain, Project Implementation Request for Single Stage - One IDA / 57060 Post Limited 6,142.00 0.00 Canceled 2017-11-01 2017-11-08 2017-11-15 and other miscelleneous Support Quotations Envelope items NP-MOFALD-27986-GO-RFQ Project Implementation Request for Single Stage - One IDA / 57060 Post Limited 15,871.00 0.00 Canceled 2017-10-08 2017-10-15 2017-10-25 / Desktop computers Support Quotations Envelope NON CONSULTING SERVICES Page 2 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-MOFALD-27992-NC-RFQ Project Implementation Request for Single Stage - One / Internet services for 12 DL- IDA / 57060 Post Limited 13,758.00 0.00 Canceled 2017-09-14 2017-09-22 2017-10-22 Support Quotations Envelope PIUs under WB and GoN CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Consultant NP-MOFALD-91773-CS-CQS Project Implementation IDA / 61640 Post Qualification Open - National 88,000.00 0.00 Canceled 2018-12-24 2019-01-08 2019-02-14 2019-03-31 2019-04-22 2019-10-19 / PA Digitization Support Selection NP-MOFALD-109527-CS- Consultant Project Implementation Pending CQS / PA digitization of 17 IDA / 57060 Post Qualification Open - National 30,600.00 0.00 2019-05-12 2019-05-27 2019-07-03 2019-07-10 2019-07-24 2020-01-20 Support Implementation districts Selection NP-MOFALD-109525-CS- Consultant Project Implementation Under CQS / PA digitization of 14 IDA / 57060 Post Qualification Open - National 37,400.00 0.00 2019-05-12 2019-05-27 2019-07-03 2019-07-10 2019-07-24 2020-01-20 Support Implementation districts Selection NP-CLPIU-GMALI-127159- Consultant CS-CQS / Consulting service Project Implementation Pending IDA / 61640 Post Qualification Open - National 33,900.00 0.00 2019-08-21 2019-09-05 2019-09-17 2019-09-19 2019-09-28 2020-07-24 for Participation Agreement Support Implementation Selection (PA) compliance verification INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EHRP/DoLIDAR/S/SSS-02 / Procurement Consultant IDA / 57060 Housing Reconstruction Prior Direct Selection Direct 0.00 14,602.83 Signed (Individual) NP-MOFALD-27998-CS- Individual Project Implementation INDV / DL-PIU MIS IDA / 57060 Post Consultant Limited 17,689.00 28,784.09 Signed 2017-09-17 2017-09-24 2017-10-12 2017-10-17 2020-07-31 Support Specialist for Nuwakot Selection NP-MOFALD-38220-CS-CDS / Participation Agreement Project Implementation IDA / 57060 Post Direct Selection Direct 58,472.00 59,433.57 Signed 2017-11-24 2017-11-26 2017-12-20 2018-01-03 (PA) Digitization and upload Support in MIS system EHRP-AF/NRA- Individual CLPIU/GMALI/IC/1/2074-75 / Project Implementation IDA / 61640 Post Consultant Open 44,952.00 25,607.33 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 Financial Specialist for Support Selection okhaldhunga EHRP-AF/NRA- Individual CLPIU/GMALI/IC/2/2074-75 / Project Implementation IDA / 61640 Post Consultant Open 44,952.00 25,607.33 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 Financial Specialist for Support Selection Sindhuli Page 3 EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/3/2074-75 Project Implementation IDA / 61640 Post Consultant Open 44,952.00 27,519.43 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 / Financial Specialist For Support Selection Kavre EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/4/2074-75 Project Implementation IDA / 61640 Post Consultant Open 44,952.00 27,003.87 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 / Financial Specialist for Support Selection Ramechhap EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/5/2074-75 Project Implementation IDA / 61640 Post Consultant Open 44,952.00 25,607.33 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 / Financial Specialist for Support Selection Makawanpur EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/6/2074-75 Project Implementation IDA / 61640 Post Consultant Open 44,952.00 27,519.43 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 / Financial Specialist For Support Selection Bhaktapur EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/7/2074-75 Project Implementation IDA / 61640 Post Consultant Open 44,952.00 26,865.15 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 / Financial Specialist for Support Selection Kathmandu EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/8/2074-75 Project Implementation IDA / 61640 Post Consultant Open 44,952.00 27,519.43 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 / Financial Specialist for Support Selection Lalitpur EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/10/2074- Project Implementation IDA / 61640 Post Consultant Open 44,952.00 27,003.87 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Financial Specialist for Support Selection Gorkha EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/11/2074- Project Implementation IDA / 61640 Post Consultant Open 44,952.00 27,003.87 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Financial Specialist for Support Selection Sindhupalchowk EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/12/2074- Project Implementation IDA / 61640 Post Consultant Open 26,629.00 24,542.22 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Environmental Support Selection Specialist for Okhaldhunga EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/13/2074- Project Implementation IDA / 61640 Post Consultant Open 26,629.00 24,542.22 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Environmental Support Selection Specialist for Kavre EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/14/2074- Project Implementation IDA / 61640 Post Consultant Open 26,629.00 24,542.22 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Environmental Support Selection Specialist for Ramechhap EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/15/2074- Project Implementation IDA / 61640 Post Consultant Open 26,629.00 24,542.22 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Environmental Support Selection Specialist for Makawanpur EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/16/2074- Project Implementation IDA / 61640 Post Consultant Open 26,629.00 24,542.22 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Environmental Support Selection Specialist for Bhaktapur EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/17/2074- Project Implementation IDA / 61640 Post Consultant Open 26,629.00 24,542.22 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Environmental Support Selection Specialist for Kathmandu Page 4 EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/18/2074- Project Implementation IDA / 61640 Post Consultant Open 26,629.00 21,565.01 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Environmental Support Selection Specialist for Lalitpur EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/19/2074- Project Implementation IDA / 61640 Post Consultant Open 26,629.00 23,053.62 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Environmental Support Selection Specialist for Rasuwa EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/20/2074- Project Implementation IDA / 61640 Post Consultant Open 26,629.00 24,542.22 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Environmental Support Selection Specialist for Gorkha EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/21/2074- Project Implementation IDA / 61640 Post Consultant Open 26,629.00 24,542.22 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Environmental Support Selection Specialist for Sindhupalchowk EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/23/2074- Project Implementation IDA / 57060 Post Consultant Open 26,629.00 25,806.88 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Monitoring and Support Selection Evaluation Specialist for Nuwakot EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/24/2074- Project Implementation IDA / 57060 Post Consultant Open 26,629.00 25,806.88 Signed 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Monitoring and Support Selection Evaluation Specialist for Dhading NP-MOFALD-91822-CS- Individual Project Implementation INDV / Social Development IDA / 57060 Post Consultant Open 56,352.00 24,542.22 Signed 2018-12-24 2019-02-14 2019-02-21 2019-03-07 2021-02-24 Support Specialist for CL-PIU Selection EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/9/2074-75 Project Implementation Pending IDA / 61640 Post Consultant Open 44,952.00 0.00 2019-02-25 2019-03-22 2019-03-24 2019-04-02 2020-11-22 / Financial Specialist for Support Implementation Selection Rasuwa EHRP-AF/NRA- Individual CLPIU/GMALI/S/IC/22/2074- Project Implementation Pending IDA / 61640 Post Consultant Open 26,629.00 0.00 2018-05-04 2018-05-29 2018-05-31 2018-06-09 2020-11-25 75 / Social Development Support Implementation Selection Specialist for Sindhuli NP-MOFALD-119164-CS- Individual INDV / DL-PIU Project Implementation Under IDA / 61640 Post Consultant Open 25,542.00 0.00 2019-06-21 2019-07-20 2019-07-22 2019-08-05 2020-06-30 Environmental Specialist at Support Implementation Selection Dhading and Nuwakot NP-MOFALD-119393-CS- Individual INDV / Financial Project Implementation Pending IDA / 61640 Post Consultant Open 13,584.00 0.00 2019-06-21 2019-07-20 2019-07-22 2019-08-05 2020-06-30 Management Specialist at Support Implementation Selection Dolkha NP-MOFALD-119396-CS- Individual Project Implementation Pending INDV / MIS Assistant at IDA / 61640 Post Consultant Open 10,560.00 0.00 2019-06-21 2019-07-20 2019-07-22 2019-08-05 2020-06-30 Support Implementation CL-PIU Selection NP-MOFALD-119401-CS- Individual INDV / Financial Project Implementation Pending IDA / 61640 Post Consultant Open 22,284.00 0.00 2019-06-21 2019-07-20 2019-07-22 2019-08-05 2020-06-30 Management Assistant at CL- Support Implementation Selection PIU NP-MOFALD-121797-CS- Individual INDV / District Level Project Implementation Pending IDA / 61640 Post Consultant Open 13,584.00 0.00 2019-07-11 2019-08-09 2019-08-11 2019-08-25 2020-07-20 Financial Management Support Implementation Selection Specialist at Ramechap Page 5 NP-MOFALD-121800-CS- Individual INDV / District Level Project Implementation Pending IDA / 61640 Post Consultant Open 12,771.00 0.00 2019-07-11 2019-08-09 2019-08-11 2019-08-25 2020-07-20 Environmental Specialist at Support Implementation Selection Rasuwa NP-MOFALD-121801-CS- Individual INDV / District Level Project Implementation Pending IDA / 57060 Post Consultant Open 12,771.00 0.00 2019-07-11 2019-08-17 2019-08-19 2019-09-02 2020-07-28 Monitoring and Evaluation Support Implementation Selection Specialist at Dolkha NP-MOFALD-121814-CS- Individual INDV / Central Level Project Implementation Pending IDA / 61640 Post Consultant Open 30,948.00 0.00 2019-07-11 2019-08-09 2019-08-11 2019-08-25 2020-07-20 Financial Management Support Implementation Selection Specialist Page 6