PROCUREMENT PLAN Project information: country: The People’s Republic of China Project name: Zhejiang Qiandao Lake and Xin'an River Basin Water Resources and Ecological Environment Protection Project P-number: P159870 Project Implementation agency: Zhejiang Urban Environment Project Leading Group Office; Chun’an Qiandao Lake Construction Group; Jiande Xinshui Construction Co. Ltd. Date of the Procurement Plan: December 10, 2018 Period covered by this Procurement Plan: [2018-2024] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. A. The Bank’s Standard Procurement Documents (SPDs): The Bank’s SPDs shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. B. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures (Tendering and Bidding Law of the Peoples’ Republic of China, i.e. TBL promulgated by its Order No. 21 dated August 30, 1999 and the Implementation Regulations of the TBL promulgated by its State Council Order No. 613 dated November 30, 2011 and any amendments thereof) may be used with the following conditions to meet the requirements for open competitive procurement of paragraph 5.4 of the Procurement Regulations: a. All procurement notices shall be published in a national newspaper of wide circulation, or on a widely-used website / electronic portal with free access. b. A minimum of twenty (20) business days shall be given to Bidders between the date of such advertisement (or the date of availability of procurement documents, whichever is later and the deadline for the submission of bids). The advertisement and procurement documents shall specify the deadline for the submission of bids. Potential Bidders shall be allowed to inspect and purchase procurement documents at any time prior to the deadline for the submission of bids. c. Any Bidder/Consultant should be eligible to participate in a procurement process and to be awarded a Bank-financed contract as defined in paragraphs 3.21, 3.22 and 3.23 of the Procurement Regulations. d. Bidders/Consultants shall be allowed to submit bids/proposals by mail or in person. Bidders/consultants shall not be mandatory required to be present at the bid/proposal opening session. e. Bidders should not be required to register as a condition for inspecting or purchasing procurement documents, submitting its bid or receiving contract award. A winner Bidder, shall be given reasonable opportunity of registering (if required) before contract signing without any let or hindrance. Bidding shall not be restricted to any class of contractors. f.The winning bidder shall not be required, as a condition of award, to reduce its bid price No contract negotiation shall be permitted unless agreed in the procurement plan. g. No bid may be rejected solely on the basis that the bid price exceeds any cost estimate. Rejection of all bids or re-bidding shall not be allowed solely because the number of bids is less than three (3). Rebidding shall not take place without any sound justification. h. The Bank’s procurement documents for approaching the national market or any procurement document acceptable to the Bank shall be used. All procurement documents must require that bidders/consultants present a signed acceptance at the time of bidding or submitting a proposal, to be incorporated in any resulting contract, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i. The procurement documents shall disclose the newspaper and / or the electronic means in which the information on contract award shall be published. j. The contract award notification shall identify: (a) name and address of the Borrower’s Project Implementing Unit, (b) name and reference number of the contract being awarded and the selection method used (c) names of all Bidders/Consultants that submitted bids/proposals and their prices as read out at the bid opening meeting and as evaluated (d) names of all Bidders/ Consultants whose bids/proposals were rejected either as nonresponsive or as not meeting qualification criteria or were not evaluated, with the reasons therefor and (e) the name of the successful Bidder/Consultant, the final contract price, the contract duration and a summary of its scope. k. The Borrower shall implement an effective complaint mechanism allowing bidders or consultants to complain, and have their complaints handled and responded in a timely manner. Procurement documents should indicate the complaint mechanism procedure and provide the professional title and address of the officials to whom such protests should be sent. l. The Bank shall be allowed to review procurement documentation and activities related to the activities included in the procurement plan. C. Other national procurement arrangements: When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. A. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing is not applicable for those contracts identified in the Procurement Plan tables. B. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations is not applicable. C. Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations: Goods: Domestic Preference is not applicable for those contracts identified in the Procurement Plan tables. Works: Domestic Preference is not applicable. G. Other Relevant Procurement Information: The first batch of Goods, Works and Non-Consulting Services need to be procured: Prior Review Threshold: The thresholds of procurement methods and the requirements for the Bank’s prior review are shown in Table1 according to the Procurement Regulations (dated July 2016, revised November 2017 and August 2018). Table1.Thresholds for Procurement Methods and Prior Review Contract Expenditure Value Prior Review Procurement Method Category Threshold Threshold (US$) (US$) International Open Competitive ≥40,000,000 All contracts Procurement (International + Open) National Open ≥ 500k to Competitive All contracts ≥15 1. Civil works <40,000,000 Procurement million (National + Open) Request for <500,000 N/A Quotations All contracts ≥15 Any value Direct Selection million International Open Competitive ≥10,000,000 All contracts Procurement (International + Open) 2. National Open Goods/Non- ≥ 500k to Competitive All contracts ≥4 consulting <10,000,000 Procurement million services (National + Open) Request for <500,000 N/A Quotations All contracts ≥4 Any value Direct Selection million Currency Unit = Chinese Yuan(CNY) US$1.00 = CNY 6.70 Procurement Packages with Methods and Time Schedule: Estimated Estimate Domestic Review Expected Cost d Cost Procureme Procureme Prequalifi Contrac Preferenc by Bank Bid- Ref. No. Contract Name Description nt nt c-ation t Period Remarks (CNY: 10 (USD: 10 e Opening (yes/no) (Prior / (Month) thousand thousand Category Method Date (yes/no) Post) ) ) Component1: Landscape Management Improvement Chun'an Forest RFB / Forest greening Ecological Open / 2021.0 CLCP21 and renovation of 535.71 79.96 Works No No Post 31 Rehabilitation National 1.08 1531mu Project / C.W. Chun'an Forest RFB / Forest greening Ecological Open / 2021.0 CLCP31 and renovation of 564.12 84.20 Works No No Post 31 Rehabilitation National 1.08 1014mu Project / C.W. Chun'an Forest RFB / Forest greening Ecological Open / 2021.0 CLCP32 and renovation of 567.10 84.64 Works No No Post 31 Rehabilitation National 1.08 1035mu Project / C.W. Component 2: Water Resources Management Improvement The first batch of Consulting Services need to be procured during 2018-2019: Prior Review Threshold: The thresholds of procurement methods and the requirements for the Bank’s prior review are shown in Table2 according to the Procurement Regulations (dated July 2016, revised November 2017 and August 201). Table2.Thresholds for Procurement Methods and Prior Review Contract Expenditure Value Prior Review Procurement Method Category Threshold Threshold (US$) (US$) ≥300,000 QCBS/QBS/LCS/FBS All contracts ≥2 <300,000 FBS, LCS, CQS million Direct Selection for All contracts ≥2 firms million Consultant services Selection of Individual All contracts Consultant ≥400,000 Direct Selection for All contacts ≥ 400,000 individuels Notes: QCBS: Quality- and Cost-Based Selection DS: Direct Selection QBS: Quality-Based Selection IC: Individual Consultant selection FBS: Fixed Budget Selection N/A: Not Applicable LCS: Least Cost Selection CQS: Consultants’ Qualifications-based Selection Currency Unit = Chinese Yuan(CNY) US$1.00 = CNY 6.70 Procurement Packages with Methods and Time Schedule: Estimate Estimated Review Expected d Cost Procureme Procureme Prequalific- Domestic Contrac Cost by Bank Bid- Remar Ref. No. Contract Name Description nt nt ation Preference t Period (USD: 10 Opening ks (CNY: 10 (yes/no) (Prior / (Month) thousand Category Method (yes/no) Date thousand) Post) ) Component 3: Institutional Capacity Building, Monitoring and Project Management PROCUREMENT China : Zhejiang Qiandao Lake and Xin'an River Basin Water Resources and Ecological Environment Protection Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2018-12-17 Revised Plan Date(s): (comma delineated, leave blank if none) 2021-03-28 Project ID: P159870 GPN Date: 2018-09-20 Project Name: Zhejiang Qiandao Lake and Xin'an River Basin Water Resources and Ecological Environment Protection Project Loan / Credit No: IBRD / 88560 Q Executing Agency(ies): iandao Lake PMO WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CLCP1 / No.1 contract section of Chun'an Forest Conpontent 1: Landscape Single Stage - One 2021-10- Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 648,200.00 460,516.56 Signed 2018-12-20 2019-02-01 2018-12-25 2019-02-05 2019-03-06 2019-03-07 2019-04-01 2019-04-11 2019-06-11 Management Improvement Envelope 27 Project:Forest greening and renovation of 3506mu CLCP2 / No.2 contract section of Chun'an Forest Conpontent 1: Landscape Single Stage - One 2021-10- Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 707,500.00 464,781.22 Signed 2018-12-20 2019-02-01 2018-12-25 2019-02-05 2019-03-07 2019-03-07 2019-04-02 2019-04-11 2019-06-11 Management Improvement Envelope 27 Project:Forest greening and renovation of 3561mu CLCP3 / No.3 contract section of Chun'an Forest Conpontent 1: Landscape Single Stage - One 2021-10- Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 786,200.00 533,808.04 Signed 2018-12-20 2019-02-01 2018-12-25 2019-02-05 2019-03-08 2019-03-07 2019-04-01 2019-04-11 2019-06-11 Management Improvement Envelope 27 Project:Forest greening and renovation of 3560mu CLCP4 / No.4 contract section of Chun'an Forest Conpontent 1: Landscape Single Stage - One 2021-10- Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 733,600.00 476,936.78 Signed 2018-12-20 2019-02-01 2018-12-25 2019-02-05 2019-03-12 2019-03-07 2019-04-01 2019-04-11 2019-06-11 Management Improvement Envelope 27 Project:Forest greening and renovation of 2243mu CLCP6 / No.6 contract section of Chun'an Forest Conpontent 1: Landscape Single Stage - One 2021-10- Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 765,800.00 446,281.59 Signed 2018-12-20 2019-02-01 2018-12-25 2019-02-05 2019-03-14 2019-03-07 2019-05-21 2019-04-11 2019-06-11 Management Improvement Envelope 27 Project:Forest greening and renovation of 1127mu CLCP7 / No.7 contract section of Chun'an Forest Conpontent 1: Landscape Request for Single Stage - One 2021-09- Ecological Rehabilitation IBRD / 88560 Post Open - National 458,500.00 276,650.66 Signed 2018-12-25 2019-02-19 2019-06-11 Management Improvement Quotations Envelope 06 Project:Forest greening and renovation of 1798mu CGWB1 / Wangfu Water Component 2: Water Single Stage - One 2020-07- Plant:WTP 2200m3/d and IBRD / 88560 Resources Management Post Request for Bids Open - National 2,913,900.00 0.00 Canceled 2019-01-15 2019-01-20 2019-03-03 2019-04-02 2019-05-07 Envelope 30 water supply pipe Improvement CGFS2 / Fengshuling Water Pl Component 2: Water Single Stage - One 7,088,245.6 2020-07- ant WTP 5000m3/d and wate IBRD / 88560 Resources Management Post Request for Bids Open - National 8,848,100.00 Signed 2019-01-15 2019-06-10 2019-01-20 2019-03-03 2019-07-12 2019-04-02 2019-09-09 2019-05-07 2019-10-18 Envelope 7 30 r supply pipe Improvement CGYJ11 / Yejia Water Plant W Component 2: Water Single Stage - One 1,676,901.9 2020-07- TP 1400m3/d and water suppl IBRD / 88560 Resources Management Post Request for Bids Open - National 1,607,200.00 Signed 2019-01-15 2019-07-01 2019-01-20 2019-03-03 2019-08-09 2019-04-02 2019-10-14 2019-05-07 2019-11-29 Envelope 2 30 y pipe Improvement JSDT4 / Qingtan River in Datong Town (Panshan Component 2: Water Request for Single Stage - One 2019-12- Section): river dredging IBRD / 88560 Resources Management Post Open - National 400,600.00 315,759.74 Signed 2019-01-15 2019-03-12 2019-06-26 Quotations Envelope 07 1.1km, ecological Improvement embankment 2.2km JSHT14 / Wulong River in Hangtou Town (Pengjia Component 2: Water Request for Single Stage - One 2019-12- Section): river dredging IBRD / 88560 Resources Management Post Open - National 471,300.00 329,678.78 Signed 2019-01-15 2019-03-12 2019-06-26 Quotations Envelope 07 1.1km, ecological Improvement embankment 2.2km JSHT15 / Wulong River in Component 2: Water Hangtou Town: new Request for Single Stage - One 2019-12- IBRD / 88560 Resources Management Post Open - National 300,400.00 277,402.44 Signed 2019-01-15 2019-03-12 2019-07-22 construction and Quotations Envelope 07 Improvement rehabilitation of 9 dams JSHT16 / Shimuling River in Component 2: Water Hangtou Town: river dredging Single Stage - One 2020-03- IBRD / 88560 Resources Management Post Request for Bids Open - National 951,600.00 637,750.93 Signed 2019-01-10 2019-04-16 2019-01-15 2019-02-26 2019-05-21 2019-03-28 2019-06-27 2019-05-02 2019-08-06 2.3km, ecological Envelope 27 Improvement embankment 4.6km, 1 dam CGWB1-1 / Wangfu WS: WTP Component 2: Water Single Stage - One 2,221,867.5 2020-10- 2200m3/d and water supply IBRD / 88560 Resources Management Post Request for Bids Open - National 2,647,700.00 Signed 2019-05-15 2019-03-26 2019-05-20 2019-07-01 2019-05-10 2019-07-31 2019-06-16 2019-09-04 2019-08-02 Envelope 3 28 pipe Improvement JSDT5 / Qingtan River in Datong Town (Xikou Section): Component 2: Water Request for Single Stage - One 2019-12- river dredging 0.79km, IBRD / 88560 Resources Management Post Open - National 143,700.00 0.00 Canceled 2019-01-15 2019-03-12 Quotations Envelope 07 ecological embankment Improvement 1.57km JSDT1 / DatongRiver in Component 2: Water Request for Single Stage - One 2019-12- Datong Town: ecological IBRD / 88560 Resources Management Post Open - National 220,700.00 0.00 Canceled 2019-01-15 2019-03-12 Quotations Envelope 07 embankment 9.3km Improvement JSDT1-5 / DatongRiver& Qingtan River(Xikou Section)in Component 2: Water Datong Town: ecological Request for Single Stage - One 2020-07- IBRD / 88560 Resources Management Post Open - National 364,500.00 286,326.47 Signed 2019-08-10 2019-10-05 2019-11-18 embankment 9.3km, river Quotations Envelope 01 Improvement dredging 0.79km, ecological embankment 1.57km Page 1 JLDT1 / No.1contract section of Datong Town Forest Conpontent 1: Landscape Single Stage - One 1,104,134.9 2022-12- Greening and Renovation IBRD / 88560 Post Request for Bids Open - National 1,607,900.00 Signed 2019-08-05 2019-08-29 2019-08-10 2019-09-21 2019-10-12 2019-10-21 2019-10-31 2019-11-25 2019-11-28 Management Improvement Envelope 4 09 Project: forest greening and renovation of 3834 mu JLDT2 / No.2 contract section of Datong Town Forest Conpontent 1: Landscape Single Stage - One 1,077,204.0 2022-12- Greening and Renovation IBRD / 88560 Post Request for Bids Open - National 1,910,800.00 Signed 2019-08-05 2019-08-29 2019-08-10 2019-09-21 2019-10-12 2019-10-21 2019-11-01 2019-11-25 2019-11-28 Management Improvement Envelope 1 09 Project: forest greening and renovation of 4488 mu JLDT3 / No.3 contract section of Datong Town Forest Conpontent 1: Landscape Single Stage - One 1,102,447.0 2022-12- Greening and Renovation IBRD / 88560 Post Request for Bids Open - National 1,490,600.00 Signed 2019-08-05 2019-08-29 2019-08-10 2019-09-21 2019-10-14 2019-10-21 2019-11-06 2019-11-25 2019-12-23 Management Improvement Envelope 1 09 Project: forest greening and renovation of 2920 mu JLSC4 / Shouchang Town Forest Greening and Conpontent 1: Landscape Request for Single Stage - One 2022-10- Renovation Project: forest IBRD / 88560 Post Open - National 432,900.00 342,283.69 Signed 2019-08-10 2019-10-05 2019-11-21 Management Improvement Quotations Envelope 19 greening and renovation of 1671 mu JLHT5 / Hangtou Town Forest Greening and Conpontent 1: Landscape Single Stage - One 2022-12- Renovation Project: forest IBRD / 88560 Post Request for Bids Open - National 1,511,500.00 983,362.36 Signed 2019-08-05 2019-08-29 2019-08-10 2019-09-21 2019-09-29 2019-10-21 2019-10-23 2019-11-25 2019-11-21 Management Improvement Envelope 09 greening and renovation of 5839 mu JLLC6 / Shouchang Forest Farm & Xin’anjiang Forest Farm Forest Greening and Renovation Project: Conpontent 1: Landscape Single Stage - One 1,121,777.2 2022-12- shouchang forest farm:forest IBRD / 88560 Post Request for Bids Open - National 1,076,300.00 Signed 2019-08-05 2019-08-29 2019-08-10 2019-09-21 2019-10-15 2019-10-21 2019-12-11 2019-11-25 2020-01-14 Management Improvement Envelope 2 09 greening and renovation of 3382 mu;Xin’anjiang forest farm:forest greening and renovation of 1801 mu CLCP8 / CLCP8: Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 800,000.00 486,499.33 Signed 2019-08-05 2019-08-14 2019-08-10 2019-09-21 2019-09-16 2019-10-21 2019-11-13 2019-11-25 2019-12-24 Management Improvement Envelope 23 greening and renovation of 3376 mu CLCP9 / CLCP9:Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 680,000.00 441,230.91 Signed 2019-08-05 2019-08-14 2019-08-10 2019-09-21 2019-09-16 2019-10-21 2019-11-13 2019-11-25 2019-12-24 Management Improvement Envelope 23 greening and renovation of 2464 mu CLCP10 / CLCP10:Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 650,000.00 403,362.30 Signed 2019-08-05 2019-08-14 2019-08-10 2019-09-21 2019-09-17 2019-10-21 2019-12-13 2019-11-25 2019-12-24 Management Improvement Envelope 23 greening and renovation of 2251 mu CLCP11 / CLCP11:Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 790,000.00 495,355.48 Signed 2019-08-05 2019-08-14 2019-08-10 2019-09-21 2019-09-17 2019-10-21 2019-11-13 2019-11-25 2019-12-24 Management Improvement Envelope 23 greening and renovation of 4106 mu CLCP12 / CLCP12: Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 780,000.00 478,471.53 Signed 2019-08-05 2019-08-14 2019-08-10 2019-09-21 2019-09-18 2019-10-21 2019-11-13 2019-11-25 2019-12-24 Management Improvement Envelope 23 greening and renovation of 3453 mu CLCP13 / CLCP13:Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 780,000.00 476,424.74 Signed 2019-08-05 2019-08-14 2019-08-10 2019-09-21 2019-09-18 2019-10-21 2019-11-13 2019-11-25 2019-12-24 Management Improvement Envelope 23 greening and renovation of 2048 mu CLCP14 / CLCP14:Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 810,000.00 493,997.41 Signed 2019-08-05 2019-08-15 2019-08-10 2019-09-21 2019-09-23 2019-10-21 2019-09-23 2019-11-25 2019-12-24 Management Improvement Envelope 23 greening and renovation of 1297 mu CLCP15 / CLCP15:Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 790,000.00 486,566.57 Signed 2019-08-05 2019-08-15 2019-08-10 2019-09-21 2019-09-23 2019-10-21 2019-11-13 2019-11-25 2019-12-24 Management Improvement Envelope 23 greening and renovation of 1172 mu CLCP16 / CLCP16:Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 730,000.00 411,140.65 Signed 2019-08-05 2019-08-15 2019-08-10 2019-09-21 2019-09-24 2019-10-21 2019-11-13 2019-11-25 2019-12-24 Management Improvement Envelope 23 greening and renovation of 2218 mu CLCP17 / CLCP17:Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 730,000.00 460,355.12 Signed 2019-08-05 2019-08-15 2019-08-10 2019-09-21 2019-09-24 2019-10-21 2019-12-10 2019-11-25 2020-01-09 Management Improvement Envelope 23 greening and renovation of 2258 mu CLCP18 / CLCP18:Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 790,000.00 441,234.49 Signed 2019-08-05 2019-08-15 2019-08-10 2019-09-21 2019-09-25 2019-10-21 2019-11-13 2019-11-25 2019-12-24 Management Improvement Envelope 23 greening and renovation of 2709 mu CLCP19 / CLCP19:Chun'an Forest Ecological Conpontent 1: Landscape Single Stage - One 2020-05- Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 820,000.00 471,887.60 Signed 2019-08-05 2019-08-15 2019-08-10 2019-09-21 2019-09-25 2019-10-21 2019-11-13 2019-11-25 2019-12-24 Management Improvement Envelope 23 greening and renovation of 3393 mu Page 2 CLCP5 / No.5 contract section of Chun'an Forest Conpontent 1: Landscape Single Stage - One 2022-06- Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 640,800.00 423,598.19 Signed 2019-08-02 2019-03-01 2019-08-07 2019-09-18 2019-03-13 2019-10-18 2019-04-01 2019-11-22 2019-06-11 Management Improvement Envelope 09 Project:Forest greening and renovation of 1237mu JSHT12 / Hangchuan section of Shouchang River in Component 2: Water Single Stage - One 2020-10- Hangtou Town: river dredging IBRD / 88560 Resources Management Post Request for Bids Open - National 1,258,200.00 893,255.41 Signed 2019-08-02 2019-05-16 2019-08-07 2019-09-18 2019-06-24 2019-10-18 2019-06-28 2019-11-22 2019-07-25 Envelope 17 3.3km, ecological Improvement embankment 3.5km, 3 dams CGLC12 / Langchuan Water S Component 2: Water upply Extention Networks wa Single Stage - One 2021-03- IBRD / 88560 Resources Management Post Request for Bids Open - National 831,343.28 556,508.26 Signed 2019-08-20 2019-08-29 2019-08-25 2019-10-17 2019-10-06 2019-10-09 2019-11-05 2019-10-15 2019-12-10 2019-11-28 ter supply pipe and related fac Envelope 04 Improvement ilities CGPM3 / Chuan'an Rural Component 2: Water Water Supply: Pingmen WS: Single Stage - One 2,372,373.5 2021-10- IBRD / 88560 Resources Management Post Request for Bids Open - National 2,923,253.73 Signed 2020-04-15 2020-05-19 2020-04-20 2020-06-01 2020-06-19 2020-07-01 2020-06-28 2020-08-05 2020-08-12 WTP 800m3/d and water Envelope 2 29 Improvement supply pipe CGPS4 / Chuan'an Rural Component 2: Water Water Supply:Pingshan WS: Single Stage - One 2,186,429.0 2021-10- IBRD / 88560 Resources Management Post Request for Bids Open - National 3,613,029.85 Signed 2020-04-15 2020-03-29 2020-04-19 2020-05-31 2020-04-29 2020-06-30 2020-05-12 2020-08-04 2020-07-09 water supply pipe and related Envelope 2 28 Improvement facilities CGQB6 / Chuan'an Rural Component 2: Water Water Supply:Qiaobei WS: 2021-10- IBRD / 88560 Resources Management Post Request for Bids 846,925.37 579,918.97 Signed 2020-04-15 2020-03-29 2020-04-20 2020-06-01 2020-04-29 2020-07-01 2020-05-12 2020-08-05 2020-06-20 water supply pipe and related 29 Improvement facilities CGLQ8 / Chuan'an Rural Component 2: Water Water Supply:Linqi WS: water Single Stage - One 1,372,880.4 2021-10- IBRD / 88560 Resources Management Post Request for Bids Open - National 2,380,537.31 Signed 2020-04-15 2020-04-10 2020-04-20 2020-06-01 2020-05-11 2020-07-01 2020-06-10 2020-08-05 2020-07-24 supply pipe and related Envelope 4 29 Improvement facilities CGJS9 / Chuan'an Rural Water Component 2: Water Supply:Jieshou WS: water Single Stage - One 1,103,378.7 2021-10- IBRD / 88560 Resources Management Post Request for Bids Open - National 2,234,805.97 Signed 2020-04-15 2020-04-23 2020-04-20 2020-06-01 2020-05-26 2020-07-01 2020-06-15 2020-08-05 2020-07-22 supply pipe and related Envelope 1 29 Improvement facilities CGQD10 / Chuan'an Rural Water Supply: Component 2: Water Single Stage - One 1,040,943.1 2021-10- IBRD / 88560 Resources Management Post Request for Bids Open - National 1,552,925.37 Signed 2020-04-15 2020-03-29 2020-04-20 2020-06-01 2020-04-30 2020-07-01 2020-05-15 2020-08-05 2020-06-19 Envelope 7 29 Qiandaohu WS: water supply Improvement pipe and related facilities CGXS13 / Chuan'an Rural Water Supply: Component 2: Water Single Stage - One 2,116,260.7 2021-10- IBRD / 88560 Resources Management Post Request for Bids Open - National 3,224,686.57 Signed 2020-04-15 2020-05-19 2020-04-20 2020-06-01 2020-06-19 2020-07-01 2020-06-30 2020-08-05 2020-08-12 Envelope 0 29 Xiashan WS: WTP 2100m3/d Improvement and water supply pipe CGJJ15 / Chuan'an Rural Water Supply: Component 2: Water Single Stage - One 1,772,685.3 2021-10- IBRD / 88560 Resources Management Post Request for Bids Open - National 3,040,477.61 Signed 2020-04-15 2020-04-23 2020-04-20 2020-06-01 2020-05-26 2020-07-01 2020-06-15 2020-08-05 2020-07-22 Envelope 1 29 Jiangjia WS: water supply pipe Improvement and related facilities JUHT3 / Forest emgerency Conpontent 1: Landscape Single Stage - One 2021-02- road of 9km in Hangtou IBRD / 88560 Post Request for Bids Open - National 667,230.00 467,646.65 Signed 2020-02-09 2020-03-29 2020-02-14 2020-03-27 2020-06-04 2020-04-26 2020-06-08 2020-05-31 2020-07-14 Management Improvement Envelope 25 Town, width 2.5m JUXA4 / Forest emgerency road of 13.13km in Conpontent 1: Landscape Single Stage - One 1,897,384.3 2021-08- IBRD / 88560 Post Request for Bids Open - National 3,638,773.00 Signed 2020-02-09 2020-03-30 2020-02-14 2020-03-27 2020-05-18 2020-04-26 2020-06-02 2020-05-31 2020-07-03 Xin'anjiang Street Office, Management Improvement Envelope 3 24 width 4.0m JUHT2 / Construction of Conpontent 1: Landscape Single Stage - One 2021-09- wetland in Hangtou Town: IBRD / 88560 Post Request for Bids Open - National 735,007.00 503,107.59 Signed 2020-06-05 2020-06-11 2020-06-10 2020-07-22 2020-07-14 2020-08-21 2020-07-17 2020-09-25 2020-08-20 Management Improvement Envelope 20 16247.2m2 JSDT3 / Zhenyuan River in Datong Town:Zhenyuan Section:river dredging 8.14km, ecological embankment 3.57km;Futang Section:river dredging Component 2: Water Single Stage - One 1,563,015.6 2022-03- 0.8km,ecological IBRD / 88560 Resources Management Post Request for Bids Open - National 1,934,578.21 Signed 2020-06-09 2020-06-24 2020-06-14 2020-07-26 2020-07-28 2020-08-25 2020-08-19 2020-09-29 2020-09-21 Envelope 6 23 embankment 1.6km;Songxi Improvement Section:river dredging 0.93km, ecological embankment 1.4km;rehabilitation of 10 dams JSDT6 / Fengjia River in Component 2: Water Datong Town: river dredging Single Stage - One 2021-09- IBRD / 88560 Resources Management Post Request for Bids Open - National 857,074.33 683,147.42 Signed 2020-06-09 2020-06-24 2020-06-14 2020-07-26 2020-07-28 2020-08-25 2020-08-19 2020-09-29 2020-09-21 3.04km, ecological Envelope 24 Improvement embankment 5.04km JSDT2 / Qingtan River in Datong Town:Chanyang Section:river dredging 4.7km, ecological embankment Component 2: Water Single Stage - One 1,725,333.7 2022-03- 8.0km;Qingtan Section: river IBRD / 88560 Resources Management Post Request for Bids Open - National 2,264,355.53 Signed 2020-06-09 2020-06-24 2020-06-14 2020-07-26 2020-07-27 2020-08-25 2020-08-19 2020-09-29 2020-09-21 Envelope 8 23 dredging 1.55km, ecological Improvement embankment 3.1km;new construction and rehabilitation of 13 dams CLCP20 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 660,040.45 500,629.37 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-09 2020-11-06 2020-10-14 2020-12-11 2020-11-03 Management Improvement Envelope 11 Forest greening and renovation of 1990 mu Page 3 CLCP22 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 929,354.93 705,160.88 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-09 2020-11-06 2020-10-14 2020-12-11 2020-11-03 Management Improvement Envelope 11 Forest greening and renovation of 2074 mu CLCP23 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 858,844.33 656,958.04 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-10 2020-11-06 2020-10-21 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 2180 mu CLCP24 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 820,368.81 585,371.37 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-10 2020-11-06 2020-10-19 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 3552 mu CLCP25 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 918,081.04 631,126.56 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-12 2020-11-06 2020-10-14 2020-12-11 2020-11-03 Management Improvement Envelope 11 Forest greening and renovation of 4420 mu CLCP26 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 822,906.72 576,451.72 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-13 2020-11-06 2020-10-20 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 2395 mu CLCP27 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 899,270.15 617,461.79 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-13 2020-11-06 2020-10-20 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 1409 mu CLCP28 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 827,330.45 565,139.95 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-14 2020-11-06 2020-10-20 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 898 mu CLCP29 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 877,186.57 584,524.79 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-15 2020-11-06 2020-10-21 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 1032 mu CLCP30 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 848,068.51 547,782.53 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-15 2020-11-06 2020-10-21 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 983 mu CLCP33 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 848,462.39 548,053.98 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-16 2020-11-06 2020-10-19 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 953mu CLCP34 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 750,528.06 489,913.52 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-15 2020-11-06 2020-10-21 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 3098 mu CLCP35 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 756,140.15 486,065.32 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-19 2020-11-06 2020-10-20 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 1748 mu CLCP37 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 800,711.34 519,513.88 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-20 2020-11-06 2020-10-27 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 3591mu CLCP36 / Chun'an Forest Ecological Rehabilitation Project: Conpontent 1: Landscape Single Stage - One 2021-12- IBRD / 88560 Post Request for Bids Open - National 695,193.73 446,225.56 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-20 2020-11-06 2020-10-27 2020-12-11 2020-11-23 Management Improvement Envelope 11 Forest greening and renovation of 4001 mu CGWP5 / Chuan'an Rural Component 2: Water Water Supply:Weiping WS: Single Stage - One 3,841,703.8 2022-03- IBRD / 88560 Resources Management Post Request for Bids Open - National 4,876,131.04 Signed 2020-09-04 2020-09-25 2020-09-09 2020-10-21 2020-10-27 2020-11-20 2020-12-07 2020-12-25 2021-01-14 water supply pipe and related Envelope 3 20 Improvement facilities CGFK14 / Chuan'an Rural Component 2: Water Water Supply:Fenkou WS: Single Stage - One 5,418,540.6 2022-03- IBRD / 88560 Resources Management Post Request for Bids Open - National 5,347,981.79 Signed 2020-09-04 2020-09-25 2020-09-09 2020-10-21 2020-10-27 2020-11-20 2020-12-07 2020-12-25 2021-01-15 water supply pipe and related Envelope 5 20 Improvement facilities JUDT1 / Bridge rehabilitation in Datong Town: 12 bridges Component 2: Water along Qingtan River and Single Stage - One 2021-06- IBRD / 88560 Resources Management Post Request for Bids Open - National 906,241.00 0.00 Canceled 2020-02-16 2020-02-21 2020-04-03 2020-05-03 2020-06-07 Zhenyuan River, with Envelope 02 Improvement rehabilitation area of 1237.5m2 Page 4 JUDT1-1 / Bridge rehabilitation in Datong Town: Component 2: Water Under 12 bridges along Qingtan Single Stage - One 2022-04- IBRD / 88560 Resources Management Post Request for Bids Open - National 906,241.00 0.00 Implementat 2020-12-27 2021-01-15 2021-01-01 2021-02-12 2021-03-02 2021-03-14 2021-04-18 River and Zhenyuan River, Envelope 13 Improvement ion with rehabilitation area of 1237.5m2 JLFH8 / Forest fire Conpontent 1: Landscape Request for Single Stage - One 2020-04- pool:building 20 forest fire IBRD / 88560 Post Open - National 166,900.00 0.00 Canceled 2019-08-10 2019-10-05 Management Improvement Quotations Envelope 02 pools in project area CLCP21 / Chun'an Forest Ecological Rehabilitation Under Project: Conpontent 1: Landscape Single Stage - One 2023-10- IBRD / 88560 Post Request for Bids Open - National 799,567.16 572,649.23 Implementat 2021-01-08 2021-01-06 2021-01-13 2021-02-24 2021-02-04 2021-03-26 2021-02-19 2021-04-30 Management Improvement Envelope 31 ion Forest greening and renovation of 1531 mu CLCP31 / Chun'an Forest Ecological Rehabilitation Under Project: Conpontent 1: Landscape Single Stage - One 2023-10- IBRD / 88560 Post Request for Bids Open - National 841,970.15 542,314.76 Implementat 2021-01-08 2021-01-06 2021-01-13 2021-02-24 2021-02-05 2021-03-26 2021-02-19 2021-04-30 Management Improvement Envelope 31 ion Forest greening and renovation of 1014 mu CLCP32 / Chun'an Forest Ecological Rehabilitation Under Project: Conpontent 1: Landscape Single Stage - One 2023-10- IBRD / 88560 Post Request for Bids Open - National 846,417.91 522,625.83 Implementat 2021-01-08 2021-01-06 2021-01-13 2021-02-24 2021-02-05 2021-03-26 2021-02-19 2021-04-30 Management Improvement Envelope 31 ion Forest greening and renovation of 1035 mu GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JNZZ1 / Surface pollution control for planting industry Conpontent 1: Landscape Single Stage - One (equipments including solar IBRD / 88560 Post Request for Bids Open - National 647,500.00 423,659.47 Signed 2019-01-10 2019-03-20 2019-01-15 2019-02-26 2019-04-26 2019-03-28 2020-05-22 2019-05-02 2020-09-27 2024-04-05 Management Improvement Envelope insecticidal light and insect sticky board) JLFH7 / Procuring of forest fire prenvention GIS Conpontent 1: Landscape Single Stage - One IBRD / 88560 Post Request for Bids Open - National 579,300.00 0.00 Canceled 2019-01-10 2019-11-27 2019-01-15 2019-02-26 2019-03-28 2019-05-02 2019-10-29 monitoring and early warning Management Improvement Envelope system and other equipments JLFH7 / Procuring of forest fire prenvention GIS Conpontent 1: Landscape Request for Single Stage - One IBRD / 88560 Post Open - National 382,300.00 399,449.64 Signed 2019-08-10 2019-10-05 2020-03-25 2020-04-02 monitoring and early warning Management Improvement Quotations Envelope system and other equipments CNSB1 / PROCUMENT OF AGR ICULTURAL DEVEICES, LIKE Fie Conpontent 1: Landscape Request for Single Stage - One IBRD / 88560 Post Open - National 5,970.15 5,691.64 Completed 2020-04-15 2020-06-10 2020-08-13 2020-12-07 2020-09-11 ldsArea Measure device filin Management Improvement Quotations Envelope g cabinet etc NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CAJY2 / Chun'an County: Exte rnal Environment Monitoring Component 3: Institutional Consultant External environment monitori IBRD / 88560 Capcity Buildting, Monitory Post Qualification Open - National 144,700.00 129,490.81 Signed 2018-12-20 2019-08-18 2019-01-10 2019-02-23 2019-11-04 2019-03-25 2019-12-20 2019-04-29 2019-12-24 2024-06-21 ng, preparation of environmen and Project Management Selection t monitoring report JDJY2 / Jiande City: External E nvironment Monitoring Exter Component 3: Institutional Consultant nal environment monitoring, p IBRD / 88560 Capcity Buildting, Monitory Post Qualification Open - National 35,800.00 33,811.49 Signed 2018-12-20 2019-08-19 2019-01-10 2019-02-23 2020-01-08 2019-03-25 2020-03-23 2019-04-29 2020-03-23 2024-06-21 reparation of environment mo and Project Management Selection nitoring report ZJJY1-6 / Project Management Consulting Services:project management (support for bidding and deal Component 3: Institutional Quality And Cost- with the complaint, contract IBRD / 88560 Capcity Buildting, Monitory Post Open - International 500,000.00 504,000.00 Signed 2018-12-30 2019-03-18 2019-01-20 2019-04-29 2019-03-05 2019-08-26 2019-04-02 2019-10-15 2019-05-02 2019-10-15 2019-06-06 2019-12-04 2019-07-11 2020-01-15 2024-06-30 Based Selection variation management, and Project Management construction management and payment review). preparation of the Progress Report for WB. CHJC2 / Chun'an and Jiande E nvironment Monitoring Project (Result monitoring) Result m Component 3: Institutional Quality And Cost- onitoring for water conservan IBRD / 88560 Capcity Buildting, Monitory Post Open - International 840,000.00 694,061.44 Signed 2019-06-30 2019-11-22 2019-07-21 2019-08-18 2020-01-14 2019-09-15 2020-04-08 2019-09-22 2020-04-10 2019-10-13 2020-05-06 2019-11-17 2020-06-09 2024-07-13 Based Selection cy project, forest project and and Project Management agriculture project of Chun'an County and Jiande City Component 3: Institutional Consultant JLJY1 / Study on Three Under IBRD / 88560 Capcity Buildting, Monitory Post Qualification Open - National 238,224.00 189,176.93 2020-02-09 2020-03-03 2020-03-01 2020-04-14 2020-12-22 2020-05-14 2021-01-28 2020-06-18 2023-12-31 Forestry Issues Implementation and Project Management Selection Page 5 CHJC1-1 / Chun'an Environment Monitoring Project- Monitioring top-level Component 3: Institutional Quality And Cost- design, modelling, data IBRD / 88560 Capcity Buildting, Monitory Post Open - International 373,134.33 0.00 Under Review 2020-12-10 2021-02-23 2020-12-31 2021-02-04 2021-03-06 2021-03-13 2021-04-03 2021-05-08 2024-06-30 Based Selection management, evaluation and and Project Management consultation service in Shangwuxi watershed. CLJY1 / Chun'an Forest Ecological Rehabilitation Project:Study on Effect of Component 3: Institutional Consultant Under Forest Ecosystem Restoration, IBRD / 88560 Capcity Buildting, Monitory Post Qualification Open - National 49,253.73 0.00 2021-01-30 2021-03-01 2021-02-20 2021-04-05 2021-05-05 2021-06-09 2023-12-31 Implementation Study on Ecological and Project Management Selection Afforestation Techniques in Manm Mountain JHJC1-1 / Shouchang River Basin Water Ecological Component 3: Institutional Consultant Pending Monitoring System Overall IBRD / 88560 Capcity Buildting, Monitory Post Qualification Open - National 268,656.72 0.00 2021-03-30 2021-04-20 2021-06-03 2021-07-03 2021-08-07 2024-06-30 Implementation Design and Whole Process and Project Management Selection Consultation Service INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CAJY1 / Chun'an County: Exte rnal Resettlement Monitoring Component 3: Institutional Individual External resettlement and la IBRD / 88560 Capcity Buildting, Monitory Post Consultant Limited 143,300.00 80,130.50 Signed 2018-12-20 2019-08-27 2018-12-25 2019-12-04 2019-01-15 2020-01-06 2019-02-19 2020-01-06 2024-06-22 nd acquisition monitoring, pre and Project Management Selection paration of resettlement repor t JDJY1 / Jiande City: External R esettlement Monitoring Exter Component 3: Institutional Individual nal resettlement and land acq IBRD / 88560 Capcity Buildting, Monitory Post Consultant Limited 35,800.00 60,091.00 Signed 2018-12-20 2019-05-06 2018-12-25 2019-12-20 2019-01-15 2020-01-14 2019-02-19 2020-01-14 2024-06-22 uisition monitoring, preparati and Project Management Selection on of resettlement report Page 6