PROCUREMENT PLAN Project information: Cambodia- Higher Education Improvement Project (HEIP), IDA Credit No: 6221-KH and Project IDA No: P162971 Project Implementation agency: Mistry of Education Youth and Sport (MoYES) Date of the Procurement Plan: 06 November 2018 Period covered by this Procurement Plan: The procurement period of project covered from year November 2018 to May 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in accordance with the Royal Kingdom of Cambodia’s Updated Procurement Manual for All Externally Financed Projects/Programs (“Procurement Manual”), promulgated through the Sub-decree 74 dated May 22, 2012, which is issued pursuant to Article 3 of the Kingdom of Cambodia’s Law on Public Procurement dated January 14, 2012., such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. i. Procurement shall be open to eligible firms from any country; ii. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights as per attached format; iii. Each Project shall put in place an effective complaints review system that includes review by the implementing agency and subsequent review by another party not involved in the in the procurement process, if not satisfied with the review of the implementing agency. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. PROCUREMENT Cambodia : Cambodia Higher Education Improvement Project PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2018-11-12 2020-09-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162971 GPN Date: 2018-11-06 Project Name: Cambodia Higher Education Improvement Project Loan / Credit No: IDA / 62210 Executing Agency(ies): Ministry of Education Youth and Sport WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Contract Description Component Review Type Method Document Amount Amount qualification Document / Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Completion Type (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MOEYS-HEIP-NS-W-001 / Component 1: Improving Pending Construction of Business Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 200,000.00 0.00 Implementa 2019-12-25 2020-02-05 2020-10-02 Incubation Center for Royal Quotations Envelope Capacity tion University of Agriculture MOEYS-HEIP-NCB-W-001 / Component 1: Improving Pending Construction of Student's Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 1,200,000.00 0.00 Implementa 2019-11-02 2019-11-07 2019-12-19 2020-01-18 2020-02-08 2021-08-01 New Accommodation Envelope Capacity tion Building for ITC MOEYS-HEIP-NCB-W-003 / Component 1: Improving Pending Single Stage - One Construction of Incubation IDA / 62210 Teaching and Learning Post Request for Bids Open - National 600,000.00 0.00 Implementa 2020-03-16 2020-03-21 2020-05-02 2020-06-01 2020-06-22 2021-06-17 Envelope center for RUPP Capacity tion MOEYS-HEIP-NS-W-005 / Component 1: Improving Pending Request for Single Stage - One Renovation of laboratories IDA / 62210 Teaching and Learning Post Open - National 165,000.00 0.00 Implementa 2019-07-13 2019-08-24 2020-02-20 Quotations Envelope for RUPP. Capacity tion MOEYS-HEIP-NS-W-008 / Component 1: Improving Pending Construction for Clean Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 200,000.00 0.00 Implementa 2021-05-07 2021-06-18 2021-12-18 Room infrastructures for Quotations Envelope Capacity tion RUPP. MOEYS-HEIP-NCB-W-004 / Construction of Research building, Student Component 2: Improving Pending Single Stage - One accommodation at Research IDA / 62210 Research in STEM and Post Request for Bids Open - National 900,000.00 0.00 Implementa 2019-12-02 2019-12-07 2020-01-18 2020-02-17 2020-03-09 2020-09-05 Envelope and Training Farm (RTF) Agriculture tion and supportive environment STEM building for UBB MOEYS-HEIP-NS-W-011 / Component 1: Improving Pending Renovation of learning Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 86,000.00 0.00 Implementa 2019-03-23 2019-05-04 2019-10-31 environment facilities for Quotations Envelope Capacity tion UBB. MOEYS-HEIP-ICB-W-001 / Construction of 2 New Component 1: Improving Pending Classroom Buildings for Open - Single Stage - One IDA / 62210 Teaching and Learning Prior Request for Bids 10,285,000.00 0.00 Implementa 2019-09-01 2019-09-06 2019-10-21 2019-11-20 2019-12-11 2021-11-30 SRU & RUA, and 3 International Envelope Capacity tion Student Dormitories Building for RUA & RUPP. MOEYS-HEIP-ICB-W-002 / Construction of new ITC Campus, Foundation work (Pile penetration, Pile Cap and Construction ground Component 1: Improving Pending Open - Single Stage - One floor, 1,2,3,4,5 and roof IDA / 62210 Teaching and Learning Prior Request for Bids 7,800,000.00 0.00 Implementa 2019-11-01 2019-11-06 2019-12-18 2020-01-17 2020-02-07 2022-02-06 International Envelope floors, Finish work Capacity tion (Partition wall, window, door, toilet decoration, MMI- Electric & sanitary, and Landscape). MOEYS-HEIP-NS-W-002 / Component 1: Improving Request for Single Stage - One Renovation Work for IDA / 62210 Teaching and Learning Post Open - National 36,000.00 0.00 Canceled 2020-03-21 2020-05-02 2020-08-30 Quotations Envelope Updating Library at ITC Capacity MOEYS-HEIP-NS-W-012 / Component 2: Improving Under Renovation for Science Labs Single Stage - One IDA / 62210 Research in STEM and Post Request for Bids Open - National 115,000.00 0.00 Implementa 2019-08-20 2020-06-10 2019-08-25 2019-09-29 2020-07-28 2019-10-14 2019-10-30 2020-02-27 at Building A for RUPP for Envelope Agriculture tion 1st Year Page 1 MOEYS-HEIP-NS-W-003 / Component 1: Improving Request for Single Stage - One Renovation Work for IDA / 62210 Teaching and Learning Post Open - National 67,000.00 0.00 Canceled 2019-01-06 2019-02-17 2019-06-17 Quotations Envelope Updating Library at ITC Capacity MOEYS-HEIP-NS-W-034 / Component 2: Improving Renovation of administrative Request for Single Stage - One IDA / 62210 Research in STEM and Post Open - National 107,370.00 94,967.59 Signed 2019-07-05 2019-08-05 2019-12-19 2019-11-03 offices, auditorium, and Quotations Envelope Agriculture research lab MOEYS-HEIP-NS-W-035 / Component 1: Improving Under Lab and office renovation Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 207,000.00 0.00 Implementa 2019-08-06 2019-11-01 2020-03-01 for Faculty of Engineering Quotations Envelope Capacity tion (RUPP) year I MOEYS-HEIP-NS-W-36 / Component 1: Improving Pending Request for Single Stage - One Renovation Laboratory for IDA / 62210 Teaching and Learning Post Open - National 100,000.00 0.00 Implementa 2020-08-17 2020-10-12 2021-04-10 Quotations Envelope ITC Capacity tion MOEYS-HEIP-NS-W-37 / Component 1: Improving Pending Construction entrance Road, Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 197,893.00 0.00 Implementa 2020-08-25 2020-10-20 2021-04-18 Land Fill, Digging ponds Quotations Envelope Capacity tion and stream/creek MOEYS-HEIP-NS-W-38 / Construction Small House Component 1: Improving Pending for Keeping Materials, Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 198,168.00 0.00 Implementa 2020-09-25 2020-11-20 2021-05-19 Office, Lab and Academic Quotations Envelope Capacity tion Building, Irrigation basin andWater Closet for public MOEYS-HEIP-NS-W-39 / Construction Small House Component 1: Improving Pending for Keeping Materials, Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 103,950.00 0.00 Implementa 2020-10-25 2020-12-20 2021-06-18 Office, Lab and Academic Quotations Envelope Capacity tion Building, Irrigation basin andWater Closet for public MOEYS-HEIP-NS-W-004 / Component 1: Improving Pending Construction of incubation Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 60,000.00 0.00 Implementa 2020-02-22 2020-04-04 2020-10-01 center for students to Quotations Envelope Capacity tion startup for SRU. MOEYS-HEIP-NS-W-004(1) Component 1: Improving Pending Single Stage - One / New Workshop Building IDA / 62210 Teaching and Learning Post Request for Bids Open - National 350,000.00 0.00 Implementa 2020-08-20 2020-08-25 2020-09-15 2020-09-29 2020-10-27 2021-02-24 Envelope for M E for SRU Capacity tion MOEYS-HEIP-NS-W-41 / Laboratory Renovation and Component 1: Improving Pending Request for Single Stage - One greenhouse setup for plant IDA / 62210 Teaching and Learning Post Open - National 75,600.00 0.00 Implementa 2020-08-17 2020-10-12 2021-04-10 Quotations Envelope biotech and pesticide residue Capacity tion research project MOEYS-HEIP-NS-W-40 / Installation of drainage Component 1: Improving Pending system, Plastic Houses for Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 93,001.00 0.00 Implementa 2020-10-25 2020-12-20 2021-06-18 farm stations, Plastic Quotations Envelope Capacity tion Houses for farmers and Water meter MOEYS-HEIP-NCB-W-002 / Component 2: Improving Single Stage - One Construction of Agriculture IDA / 62210 Research in STEM and Post Request for Bids Open - National 500,000.00 0.00 Canceled 2019-09-09 2019-09-14 2019-10-26 2019-11-25 2019-12-16 2020-08-12 Envelope Extension Station for SRU. Agriculture MOEYS-HEIP-NS-W-010 / Component 1: Improving Request for Single Stage - One Construction of Science Labs IDA / 62210 Teaching and Learning Post Open - National 115,000.00 0.00 Canceled 2020-05-23 2020-07-04 2020-12-31 Quotations Envelope at Building A for RUPP. Capacity MOEYS-HEIP-NS-W-011 A Component 2: Improving / Lab and office renovation Single Stage - One IDA / 62210 Research in STEM and Post Request for Bids Open - National 123,000.00 0.00 Canceled 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 2021-05-21 for Faculty of Engineering Envelope Agriculture (RUPP) for Year II MOEYS-HEIP-NCB-W-007 / Advance Applied Component 2: Improving Single Stage - One Nonmaterial Research Lab IDA / 62210 Research in STEM and Post Request for Bids Open - National 400,000.00 0.00 Canceled 2020-08-05 2020-08-10 2020-09-21 2020-10-21 2020-11-05 2021-03-05 Envelope with Clean Booth (standard Agriculture Lab) at STEM building MOEYS-HEIP-NS-W-013 / Component 2: Improving Renovation for Science Labs Single Stage - One IDA / 62210 Research in STEM and Post Request for Bids Open - National 115,000.00 0.00 Canceled 2020-08-31 2020-09-05 2020-10-10 2020-10-25 2020-11-06 2021-03-06 at Building A for RUPP for Envelope Agriculture 2nd Year Page 2 MOEYS-HEIP-NS-W-014 / Component 2: Improving Renovate Lab at STEM Request for Single Stage - One IDA / 62210 Research in STEM and Post Open - National 65,000.00 0.00 Canceled 2020-09-05 2020-10-31 2021-03-10 Building (4th-6th floor at Quotations Envelope Agriculture STEM Building) MOEYS-HEIP-NS-W-006 / Component 1: Improving Request for Single Stage - One Renovation of laboratories IDA / 62210 Teaching and Learning Post Open - National 165,000.00 0.00 Canceled 2020-04-27 2020-06-08 2020-12-05 Quotations Envelope for RUPP. Capacity MOEYS-HEIP-NS-W-007 / Component 1: Improving Request for Single Stage - One Construction of Clean Room IDA / 62210 Teaching and Learning Post Open - National 200,000.00 0.00 Canceled 2020-04-27 2020-06-08 2020-12-05 Quotations Envelope infrastructures for RUPP. Capacity MOEYS-HEIP-NS-W-009 / Component 1: Improving Request for Single Stage - One Construction of Science Labs IDA / 62210 Teaching and Learning Post Open - National 115,000.00 0.00 Canceled 2019-07-13 2019-08-24 2020-02-20 Quotations Envelope at Building A for RUPP. Capacity MOEYS-HEIP-W-DS-01 / Component 1: Improving Pending Small renovation works IDA / 62210 Teaching and Learning Post Direct Selection Direct 23,500.00 0.00 Implementa 2020-08-05 2020-08-10 2020-08-29 2020-11-27 (With 4 packages) Capacity tion GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOEYS-HEIP-NCB-G-001 / Component 1: Improving Pending Procurement of Furniture Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 190,000.00 0.00 Implementati 2020-02-21 2020-02-26 2020-03-27 2020-05-11 2020-06-15 2020-10-13 for Student Dormitory for Envelope Capacity on RUA MOEYS-HEIP-NCB-G-002 / Component 1: Improving Pending Single Stage - One Laboratory Furniture for IDA / 62210 Teaching and Learning Post Request for Bids Open - National 300,000.00 0.00 Implementati 2020-02-05 2020-02-10 2020-03-23 2020-04-22 2020-05-13 2020-11-09 Envelope RUA Capacity on MOEYS-HEIP-NS-G-001 / Component 1: Improving Pending Goods for Establish data Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 72,000.00 0.00 Implementati 2021-05-06 2021-06-17 2021-12-14 center,2 Servers (primary Quotations Envelope Capacity on and backup) for ITC MOEYS-HEIP-NCB-G-006 / Component 1: Improving Pending Single Stage - One Computer Lab, Lab facilities IDA / 62210 Teaching and Learning Post Request for Bids Open - National 600,000.00 0.00 Implementati 2021-03-01 2021-03-06 2021-04-17 2021-05-17 2021-06-07 2021-12-04 Envelope for ITC Capacity on MOEYS-HEIP-NS-G-002 / Component 1: Improving Pending Request for Single Stage - One Teaching and Learning IDA / 62210 Teaching and Learning Post Open - National 60,000.00 0.00 Implementati 2021-03-06 2021-04-17 2021-07-16 Quotations Envelope Materials for ITC Capacity on MOEYS-HEIP-NS-G-004 / Component 1: Improving Pending Developing Management Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 100,000.00 0.00 Implementati 2019-07-06 2019-08-17 2019-11-15 Information Systems (MIS) Quotations Envelope Capacity on for RUPP Component 1: Improving Under MOEYS-HEIP-NCB-G-013 / Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 342,000.00 0.00 Implementati 2019-02-01 2020-01-31 2019-02-06 2019-03-20 2020-04-10 2019-04-19 2019-05-10 2019-08-08 Office furniture for RUPP Envelope Capacity on MOEYS-HEIP-NCB-G-014 / Component 1: Improving Pending Single Stage - One Dormitory Furniture for IDA / 62210 Teaching and Learning Post Request for Bids Open - National 436,000.00 0.00 Implementati 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-10 2019-08-08 Envelope RUPP and ITC Capacity on MOEYS-HEIP-NCB-G-015 / Furniture for Student Component 1: Improving Pending accommodation at Research Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 190,000.00 0.00 Implementati 2021-03-01 2021-03-06 2021-04-17 2021-05-17 2021-06-07 2021-09-05 and Training Farm (RTF) Envelope Capacity on and Agribusiness incubator for students for UBB MOEYS-HEIP-NS-G-006 / Component 1: Improving Pending Procurement of 05 Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 10,000.00 0.00 Implementati 2019-01-06 2019-02-17 2019-03-19 Motorcycle for Admin, M&E, Quotations Envelope Capacity on PU, DoF & DoC MOEYS-HEIP-NCB-G-017 / Component 1: Improving Office Equipment & Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 116,700.00 15,900.50 Signed 2018-12-02 2019-02-11 2018-12-07 2019-01-18 2019-03-11 2019-02-17 2019-06-05 2019-03-10 2019-06-20 2019-06-08 2019-08-26 Furniture for PU, DoF, Envelope Capacity PMT, DGHE & DoC Page 3 MOEYS-HEIP-NS-G-007 / Component 1: Improving Pending Supply of 6 packages of Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 72,000.00 0.00 Implementati 2018-12-07 2019-01-18 2019-04-18 Sage 50 Premium Quotations Envelope Capacity on Accounting Component 1: Improving MOEYS-HEIP-NCB-G-007 / Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 730,000.00 511,491.00 Completed 2018-12-02 2019-02-01 2018-12-07 2019-06-18 2019-01-18 2019-08-16 2019-02-17 2019-08-15 2019-03-10 2019-09-10 2019-06-08 2019-10-11 Procurement of 13 Vehicles Envelope Capacity MOEYS-HEIP-NCB-G-003 / Component 1: Improving Equipment for Improve Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 360,000.00 0.00 Canceled 2019-02-05 2019-02-10 2019-03-24 2019-04-23 2019-05-14 2019-11-10 Reading, communication Envelope Capacity facilities for RUA MOEYS-HEIP-NCB-G-005 / Furniture (Lab table, Desk, chair, cabinet, drawer, Component 1: Improving Pending Projector, electric screen, Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 550,000.00 0.00 Implementati 2022-05-25 2022-05-30 2022-06-29 2022-07-17 2022-08-07 2022-11-05 printer, whiteboard, Envelope Capacity on photocopy machine, Desktops computer, air-con etc.) for ITC MOEYS-HEIP-NCB-G-008 / Component 1: Improving Pending Single Stage - One Furniture for new Building IDA / 62210 Teaching and Learning Post Request for Bids Open - National 200,000.00 0.00 Implementati 2021-08-13 2021-08-18 2021-09-17 2021-10-07 2021-10-28 2021-12-28 Envelope in SRU Capacity on MOEYS-HEIP-NCB-G-009 / Component 1: Improving Pending Equipment for Science and Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 150,000.00 0.00 Implementati 2021-07-13 2021-07-18 2021-08-17 2021-09-07 2021-09-28 2021-12-28 Technology and Engineering Envelope Capacity on for SRU MOEYS-HEIP-ICB-G-001 / Lab equipment and material Component 1: Improving Open - Single Stage - One for 3 departments (Bio- IDA / 62210 Teaching and Learning Prior Request for Bids 2,740,000.00 0.00 Canceled 2020-05-21 2020-05-26 2020-07-07 2020-08-06 2020-08-27 2020-11-25 International Envelope engineering, TEED, ITE) in Capacity RUPP MOEYS-HEIP-ICB-G-002 / Component 1: Improving Equipment and material for Open - Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids 1,590,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-07 2020-01-05 13 Labs of Science program International Envelope Capacity for five years. MOEYS-HEIP-NCB-G-016 / Component 1: Improving Procurement of STEM Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 370,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-07 2020-01-05 Research Equipment for Envelope Capacity UBB MOEYS-HEIP-NS-G-005 / Supportive learning Component 1: Improving Pending Request for Single Stage - One environment - Library IDA / 62210 Teaching and Learning Post Open - National 93,000.00 0.00 Implementati 2020-03-07 2020-05-01 2020-07-30 Quotations Envelope Development Textbooks for Capacity on UBB MOEYS-HEIP-NS-G-008 / STEM Research Component 2: Improving Pending Request for Single Stage - One Equipmement for University IDA / 62210 Research in STEM and Post Open - National 87,450.00 0.00 Implementati 2019-07-06 2019-10-02 2020-01-05 Quotations Envelope of Battambang's Students - Agriculture on Year 1 MOEYS-HEIP-NCB-G-018 / Component 2: Improving Pending STEM Research Equipment Single Stage - One IDA / 62210 Research in STEM and Post Request for Bids Open - National 282,550.00 0.00 Implementati 2022-03-01 2022-03-06 2022-04-20 2022-05-30 2022-07-07 2022-10-05 for University of Envelope Agriculture on Battambang-Year 3 (2022) MOEYS-HEIP-NCB-G-019 / IT equipment for office Component 1: Improving rooms, data and e-learning Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 491,573.00 413,341.48 Signed 2019-06-18 2020-01-31 2019-06-23 2019-07-28 2020-04-10 2019-08-27 2020-06-30 2019-09-18 2020-07-08 2019-12-17 center, incubation center, Envelope Capacity LBE lab, Fab-lab, conference room, and smart classroom MOEYS-HEIP-NS-G-009 / Office equipment for office rooms, data and e-learning Component 1: Improving center, incubation center, Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 49,964.00 39,862.90 Signed 2019-06-23 2019-08-14 2019-12-06 2019-10-13 LBE lab, Fab lab, Quotations Envelope Capacity conference room, and smart classroom (Air- Conditioner,Table,Chair.........) MOEYS-HEIP-NS-G-010 / Component 1: Improving Pending Request for Single Stage - One 'Lab equipment for LBE IDA / 62210 Teaching and Learning Post Open - National 16,743.00 0.00 Implementati 2019-06-25 2019-08-10 2019-10-14 Quotations Envelope labs and Fab-lab Capacity on Page 4 MOEYS-HEIP-NS-G-011 / Component 1: Improving Request for Single Stage - One 'Curtain for administrative IDA / 62210 Teaching and Learning Post Open - National 5,570.00 7,225.00 Signed 2019-07-04 2019-08-28 2019-12-06 2019-10-07 Quotations Envelope offices and LBE lab Capacity MOEYS-HEIP-NS-G-012 / Stationary (1-Whiteboard Component 1: Improving Pending Request for Single Stage - One glass for classroom and 2- IDA / 62210 Teaching and Learning Post Open - National 52,600.00 0.00 Implementati 2019-07-04 2019-08-28 2019-10-07 Quotations Envelope 'Books for library and Capacity on graduate school) MOEYS-HEIP-NS-G-013 / Component 1: Improving Pending Equipment for Library at Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 36,000.00 0.00 Implementati 2020-03-21 2020-05-02 2020-08-03 ITC at 3rd year (New Quotations Envelope Capacity on Campus) MOEYS-HEIP-NS-G-014 / Software(1-Software development for accounting system, human resource management system, and Component 1: Improving Pending Request for Single Stage - One fixed asset system and 2- IDA / 62210 Teaching and Learning Post Open - National 47,000.00 0.00 Implementati 2019-07-04 2019-08-09 2019-10-23 Quotations Envelope Software solution architect Capacity on and development of student online interface, online data management system and website) MOEYS-HEIP-NS-G-015 / Component 1: Improving Pending Request for Single Stage - One IT Equipment, Furniture, IDA / 62210 Teaching and Learning Post Open - National 36,000.00 0.00 Implementati 2022-03-29 2022-04-27 2022-07-26 Quotations Envelope Books for library at ITC Capacity on MOEYS-HEIP-NCB-G-020 / RUA-IT facilities and accessories for learning Component 1: Improving facility improvement,LMLA Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 192,250.00 181,214.00 Signed 2019-06-19 2020-01-31 2019-06-22 2019-07-27 2020-04-10 2019-08-06 2020-06-30 2019-08-19 2020-07-08 2019-10-18 lab, Envelope Capacity e-goernance, PMT, and Improving communication in year1 MOEYS-HEIP-NS-G-016 / RUA-IT facilities and Component 1: Improving Pending accessories for learning Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 29,000.00 0.00 Implementati 2021-01-22 2021-03-03 2021-05-21 facility improvement, and Quotations Envelope Capacity on Improving communication in year3 MOEYS-HEIP-NS-G-017 / IT equipment with system Component 1: Improving Pending for RUA accounting software Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 45,000.00 0.00 Implementati 2021-01-22 2021-03-03 2021-08-30 and improving student,staff Quotations Envelope Capacity on and lecturer portals in year3 MOEYS-HEIP-NS-G-018 / 3- RUA-IT equipment with Component 1: Improving Pending Request for Single Stage - One system for tracer study IDA / 62210 Teaching and Learning Post Open - National 49,500.00 0.00 Implementati 2019-09-21 2019-11-02 2020-04-30 Quotations Envelope records and public and Capacity on restricted acess in year1 MOEYS-HEIP-NS-G-020 / Component 1: Improving RUA-Laboratory equipments Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 93,600.00 83,627.59 Signed 2019-07-13 2019-08-22 2019-10-03 2019-12-20 and accessories for VM Lab Quotations Envelope Capacity and FY lab in year1 MOEYS-HEIP-NCB-G-021 / Component 1: Improving Pending RUA-Laboratory equipments Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 118,000.00 0.00 Implementati 2021-02-10 2021-02-15 2021-03-29 2021-04-08 2021-04-26 2021-08-24 and accessories for Agro-in Envelope Capacity on Lab and VM lab in year3 MOEYS-HEIP-NS-G-022 / Component 1: Improving Request for Single Stage - One Electric generator 12KVA IDA / 62210 Teaching and Learning Post Open - National 15,000.00 15,730.00 Signed 2019-11-07 2019-12-09 2020-04-20 2020-02-07 Quotations Envelope for RUA in Year 1 Capacity MOEYS-HEIP-NS-G-023 / Component 1: Improving Pending Request for Single Stage - One Electric generator 500KVA IDA / 62210 Teaching and Learning Post Open - National 100,000.00 0.00 Implementati 2021-01-29 2021-03-13 2021-07-11 Quotations Envelope for RUA in year 3 Capacity on MOEYS-HEIP-NS-G-024 / Component 1: Improving Under Improvement reading Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 20,000.00 19,420.50 Implementati 2019-11-09 2019-12-09 2020-02-07 material (Textbook and Quotations Envelope Capacity on Manual) for RUA in Year 1 Page 5 MOEYS-HEIP-NS-G-025 / Component 1: Improving RUA-Furniture for lerning Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 16,900.00 19,420.50 Signed 2019-06-11 2019-07-22 2020-04-20 2019-08-31 facilities improvement , Quotations Envelope Capacity PMT and LMLA lab in year1 MOEYS-HEIP-NS-G-026 / RUA-Furniture and Component 1: Improving Pending Request for Single Stage - One accessories (for business IDA / 62210 Teaching and Learning Post Open - National 40,000.00 0.00 Implementati 2020-03-22 2020-05-01 2020-06-15 Quotations Envelope incubation center building) Capacity on for RUA at year 3 MOEYS-HEIP-NS-G-027 / Purchase tables and chairs Component 1: Improving Pending to set up small private Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 24,400.00 0.00 Implementati 2019-07-06 2019-09-22 2019-12-30 study area around UBB Quotations Envelope Capacity on pond area and in building for students MOEYS-HEIP-NS-G-028 / Teaching Equipment for Component 1: Improving Pending Request for Single Stage - One teaching and learning (TV IDA / 62210 Teaching and Learning Post Open - National 38,500.00 0.00 Implementati 2019-07-06 2019-08-15 2019-11-13 Quotations Envelope 64 inch for slides, Air Capacity on conditioners in classroom) MOEYS-HEIP-NS-G-029 / Agriculture laboratories Component 1: Improving Pending Request for Single Stage - One equipments(Food processing IDA / 62210 Teaching and Learning Post Open - National 99,000.00 0.00 Implementati 2019-08-06 2019-09-15 2019-12-14 Quotations Envelope Lab,animal scient lab,Micro Capacity on lab, Tissue culture ,103unit) MOEYS-HEIP-NS-G-030 / Component 1: Improving Pending Materials and Equipment Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 50,450.00 0.00 Implementati 2019-07-06 2019-08-30 2019-11-28 for project team (computers, Quotations Envelope Capacity on printer, desk and chairs ) MOEYS-HEIP-NS-G-031 / Component 1: Improving Pending Request for Single Stage - One Research Equipment for Sub- IDA / 62210 Teaching and Learning Post Open - National 15,000.00 0.00 Implementati 2019-08-06 2019-10-01 2019-12-30 Quotations Envelope Project Capacity on MOEYS-HEIP-NS-G-032 / Office Equipment and Software for : Lot1: QA implementation andAccounting and finance office, Component 1: Improving Pending Request for Single Stage - One Lot2: Video conference IDA / 62210 Teaching and Learning Post Open - National 79,000.00 0.00 Implementati 2019-11-15 2019-12-28 2020-03-23 Quotations Envelope system for online training Capacity on and meeting with partners and Equipment the needed hardware for the system, Lot3: Management information Syst MOEYS-HEIP-ICB-G-003 / Lab equipment and material for years 1 (Lab equipment and material for Bio- Component 1: Improving Pending engineering in RUPP for Open - Single Stage - One IDA / 62210 Teaching and Learning Prior Request for Bids 2,765,850.00 0.00 Implementati 2019-10-14 2019-10-19 2019-12-03 2019-12-18 2020-01-10 2020-03-10 years 1, Lab equipment and International Envelope Capacity on material for TEED in RUPP for years 1, Lab equipment and material for ITE in RUPP for years 1 (IT) MOEYS-HEIP-ICB-G-004 / Lab equipment and material (Lab equipment and material for TEED in RUPP for years 3 (Telecom) , Component 1: Improving Pending Open - Single Stage - One Lab Equipment and IDA / 62210 Teaching and Learning Prior Request for Bids 1,587,000.00 0.00 Implementati 2020-07-14 2020-07-19 2020-08-30 2020-09-09 2020-09-29 2020-11-28 International Envelope material for Electrical Capacity on Engineering for Year 3, Lab Equipment and materials for Logistic Engineering for year 3, Lab Equipment and materia MOEYS-HEIP-NCB-G-021 A / Lab equipment and material (Lab equipment and material for TEED in RUPP for years 3 Component 1: Improving Pending (Telecom) , Lab Equipment Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 530,100.00 0.00 Implementati 2020-07-14 2020-07-19 2020-08-30 2020-09-29 2020-10-28 2020-12-27 and material for Electrical Envelope Capacity on Engineering for Year 3, Lab Equipment and materials for Logistic Engineering for year 3, Lab Equipment and materia Page 6 MOEYS-HEIP-ICB-G-005 / Lab Equipment for Advanced (Lab Equipment for Advanced Research Component 1: Improving Pending Open - Single Stage - One (Env.), Lab Equipment for IDA / 62210 Teaching and Learning Prior Request for Bids 1,147,666.00 0.00 Implementati 2019-09-15 2019-09-20 2019-11-01 2019-12-01 2020-01-05 2020-03-05 International Envelope Advanced Research Capacity on (Physics), Lab Equipment for Advanced Research (Chemistry) MOEYS-HEIP-ICB-G-006 / Lab Equipment for Component 1: Improving Pending Advanced( Lab Equipment Open - Single Stage - One IDA / 62210 Teaching and Learning Prior Request for Bids 1,062,950.00 0.00 Implementati 2020-02-22 2020-02-27 2020-03-02 2020-03-22 2020-05-01 2020-06-30 for Advance Research in Y2, International Envelope Capacity on Photonics and applications Equipment MOEYS-HEIP-NCB-G-022 / Lab Furniture (Lab Furniture for Science at Building A of RUPP Y1 (11 Labs), Lab Furniture for Component 1: Improving Under Single Stage - One Science at Building A of IDA / 62210 Teaching and Learning Post Request for Bids Open - National 750,000.00 0.00 Implementati 2019-07-30 2020-07-22 2019-08-04 2019-09-15 2019-10-20 2019-11-24 2020-01-23 Envelope RUPP Y2 (11 Labs), Lab Capacity on Furniture for 4th-6th Floor at STEM Building, Lab Furniture for Faculty of Engineering (RUPP) MOEYS-HEIP-NCB-G-024 / Teaching and Learning Materials (ICT Equipment for teaching and learning (Social Science, Science and Component 1: Improving Pending Single Stage - One Graduate School, Equipment IDA / 62210 Teaching and Learning Post Request for Bids Open - National 133,246.00 0.00 Implementati 2019-10-14 2019-10-19 2019-11-20 2019-12-05 2019-12-18 2020-02-16 Envelope & materials for designing Capacity on and printing Civil Servants' Automation Card(1 Desktop Computer for designing, 1 printing machine, MOEYS-HEIP-NS-G-033 / Component 1: Improving Pending Request for Single Stage - One Buying Microscope 30 units IDA / 62210 Teaching and Learning Post Open - National 45,000.00 0.00 Implementati 2019-11-03 2020-01-06 2020-02-25 Quotations Envelope (Biology) Capacity on MOEYS-HEIP-NCB-G-025 / Component 1: Improving Pending Furniture and Equipment Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 390,000.00 0.00 Implementati 2021-07-03 2021-07-08 2021-08-19 2021-09-18 2021-10-22 2022-01-20 for Incubation center for Envelope Capacity on RUPP MOEYS-HEIP-NS-G-036 / Component 1: Improving Request for Single Stage - One Supply and Delivery fo 01 IDA / 62210 Teaching and Learning Post Open - National 100,000.00 46,000.00 Signed 2019-12-15 2020-01-23 2020-04-27 2020-04-22 Quotations Envelope Bus (with 29 seats) Capacity MOEYS-HEIP-G-037 / IT Component 2: Improving related equipment for data Request for Single Stage - One IDA / 62210 Research in STEM and Post Open - National 31,187.00 28,589.80 Signed 2020-05-15 2020-06-24 2020-07-28 2020-08-23 collection and analysis for 7 Quotations Envelope Agriculture research projects (for RUA) MOEYS-HEIP-G-038 / Laboratory Equipment and Component 2: Improving Request for Single Stage - One consumables for VM and IDA / 62210 Research in STEM and Post Open - National 86,804.00 72,338.38 Signed 2020-05-15 2020-06-24 2020-07-31 2020-08-23 Quotations Envelope LMLA research and food Agriculture processing (for RUA) MOEYS-HEIP-G-039 / Component 2: Improving Request for Single Stage - One Laboratory equipment for IDA / 62210 Research in STEM and Post Open - National 98,820.00 71,321.91 Signed 2020-05-15 2020-06-24 2020-07-31 2020-08-23 Quotations Envelope tissue culture (for RUA) Agriculture MOEYS-HEIP-NS-G-40 / Component 1: Improving Pending "Office Equipment for ACC Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 28,000.00 0.00 Implementati 2020-07-15 2020-09-09 2020-11-08 ($20,000) and for DSR Quotations Envelope Capacity on ($8,000)" Component 1: Improving Pending MOEYS-HEIP-NS-G-41 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 2,000.00 0.00 Implementati 2020-07-15 2020-09-09 2020-11-08 Office Furniture for DSR Quotations Envelope Capacity on MOEYS-HEIP-NCB-G-26 / "Supply and Delivery of 5 Pick-up Track: Component 1: Improving Under Single Stage - One 1 Unit for ITC ($30,000) IDA / 62210 Teaching and Learning Post Request for Bids Open - National 175,000.00 0.00 Implementati 2020-07-10 2020-07-22 2020-07-15 2020-08-26 2020-09-25 2020-10-30 2020-12-29 Envelope 2 Unit for ACC (for 1 Van Capacity on 55,000 and 1 pick-up 30,000) 2 Unit for DSR ($60,000)" Page 7 MOEYS-HEIP-NCB-G-27 / Development and aplication Component 1: Improving Pending of MIS to Store and Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 150,000.00 0.00 Implementati 2020-07-10 2020-07-15 2020-08-26 2020-09-25 2020-10-30 2021-04-28 Manageer Data related to Envelope Capacity on ACC system and accreditation activities MOEYS-HEIP-NS-G-42 / Component 1: Improving Pending Request for Single Stage - One Computer Lap​ for Science IDA / 62210 Teaching and Learning Post Open - National 40,000.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Quotations Envelope and Technology Capacity on MOEYS-HEIP-NS-G-43 / Component 1: Improving Pending Request for Single Stage - One Laptops and printers for IDA / 62210 Teaching and Learning Post Open - National 4,600.00 0.00 Implementati 2020-07-06 2020-08-31 2020-10-30 Quotations Envelope research Capacity on MOEYS-HEIP-NS-G-44 / Component 1: Improving Pending Request for Single Stage - One Pumping machine, and IDA / 62210 Teaching and Learning Post Open - National 2,500.00 0.00 Implementati 2020-07-06 2020-08-31 2020-10-30 Quotations Envelope power tiller Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-45 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 4,500.00 0.00 Implementati 2020-10-25 2020-12-20 2021-02-18 Water Stations and Tester Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-46 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 6,435.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Buying Books Quotations Envelope Capacity on MOEYS-HEIP-NS-G-47 / Component 1: Improving Pending Office Equipment, Software Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 52,122.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 and Refrigerator for Quotations Envelope Capacity on Researcher Component 1: Improving Pending MOEYS-HEIP-NS-G-48 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 73,055.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Lab Acessories Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-49 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 73,055.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Research Equipment Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-50 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 75,315.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Research Comsumable Quotations Envelope Capacity on MOEYS-HEIP-NS-G-51 / Component 1: Improving Pending Request for Single Stage - One Research Connsumble IDA / 62210 Teaching and Learning Post Open - National 35,956.00 0.00 Implementati 2021-04-04 2021-05-30 2021-08-28 Quotations Envelope (Standard) Capacity on MOEYS-HEIP-NCB-G-29 / Component 1: Improving Under IT Facilities and Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 119,830.00 0.00 Implementati 2020-07-01 2020-07-22 2020-07-06 2020-08-17 2020-09-16 2020-10-21 2021-04-19 Accessories/ IT Equipment Envelope Capacity on (Research Project) Component 1: Improving Pending MOEYS-HEIP-NS-G-52 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 3,946.00 0.00 Implementati 2020-07-06 2020-08-31 2020-10-30 Digital Professional Camera Quotations Envelope Capacity on MOEYS-HEIP-NS-G-53 / Component 1: Improving Pending Request for Single Stage - One Analysing and Measurement IDA / 62210 Teaching and Learning Post Open - National 19,600.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Quotations Envelope Equipment Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-54 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 20,400.00 0.00 Implementati 2020-07-15 2020-09-09 2020-12-08 Consumable and Reagents Quotations Envelope Capacity on Component 1: Improving Under MOEYS-HEIP-NCB-G-30 / Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 414,200.00 0.00 Implementati 2020-07-01 2020-07-22 2020-07-06 2020-08-17 2020-09-16 2020-10-21 2020-10-30 Equipment for Rice Products Envelope Capacity on MOEYS-HEIP-NS-G-55 / Component 1: Improving Pending Raw Material for Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 45,950.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Experiment and Lab Quotations Envelope Capacity on Equipments MOEYS-HEIP-NS-G-56 / Component 1: Improving Pending Lab Equipment and Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 94,000.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Materials for Experiment on Quotations Envelope Capacity on Pesticides Page 8 MOEYS-HEIP-NS-G-57 / Component 1: Improving Pending Request for Single Stage - One Experiment Equipment for IDA / 62210 Teaching and Learning Post Open - National 89,900.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Quotations Envelope dry agricultural products Capacity on MOEYS-HEIP-NS-G-58 / Component 1: Improving Pending 3D Printer and Accessories, Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 11,000.00 0.00 Implementati 2020-07-06 2020-08-31 2020-09-06 3D Printer and 3D Printer Quotations Envelope Capacity on Filament MOEYS-HEIP-NCB-G-31 / Component 1: Improving Under Single Stage - One Electronic apparatus and IDA / 62210 Teaching and Learning Post Request for Bids Open - National 245,700.00 0.00 Implementati 2020-08-10 2020-07-22 2020-08-15 2020-09-26 2020-10-26 2020-11-30 2021-02-28 Envelope tools for automation lab Capacity on MOEYS-HEIP-NS-G-59 / Component 1: Improving Pending Request for Single Stage - One Mechanical tools for lab and IDA / 62210 Teaching and Learning Post Open - National 11,000.00 0.00 Implementati 2020-08-15 2020-10-10 2021-01-08 Quotations Envelope experiments Capacity on MOEYS-HEIP-NS-G-60 / Q- Component 1: Improving Pending Request for Single Stage - One Brain System (Quanser) and IDA / 62210 Teaching and Learning Post Open - National 16,800.00 0.00 Implementati 2020-09-04 2020-10-30 2021-01-28 Quotations Envelope Camera (Quanser) Capacity on MOEYS-HEIP-NS-G-61 / Component 1: Improving Pending Request for Single Stage - One Electronic apparatus and IDA / 62210 Teaching and Learning Post Open - National 81,125.00 0.00 Implementati 2020-09-04 2020-10-30 2021-01-28 Quotations Envelope mechanical equipment Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-62 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 7,000.00 0.00 Implementati 2020-07-06 2020-08-31 2020-10-30 Potassium nitrate salt Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-63 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 18,760.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Glass samples Quotations Envelope Capacity on MOEYS-HEIP-NS-G-64 / Component 1: Improving Pending Equipment's and materials Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 28,500.00 0.00 Implementati 2020-08-10 2020-10-05 2021-01-03 for experiment on soy Quotations Envelope Capacity on saucce MOEYS-HEIP-NS-G-65 / Component 1: Improving Pending Request for Single Stage - One Chemical Reagents for IDA / 62210 Teaching and Learning Post Open - National 6,199.00 0.00 Implementati 2020-08-30 2020-10-25 2021-01-23 Quotations Envelope experiments Capacity on MOEYS-HEIP-NS-G-66 / Component 1: Improving Pending Request for Single Stage - One Experimental Equipment for IDA / 62210 Teaching and Learning Post Open - National 96,100.00 0.00 Implementati 2020-08-30 2020-10-25 2021-01-23 Quotations Envelope testing on rubber samples Capacity on MOEYS-HEIP-NCB-G-32 / Component 1: Improving Under Single Stage - One Equipment for production IDA / 62210 Teaching and Learning Post Request for Bids Open - National 154,160.00 0.00 Implementati 2020-08-25 2020-07-22 2020-08-30 2020-10-11 2020-11-10 2020-12-15 2021-06-13 Envelope rubber processing Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-67 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 4,000.00 0.00 Implementati 2020-08-30 2020-10-25 2021-01-23 Auto voltage regulator Quotations Envelope Capacity on MOEYS-HEIP-NS-G-68 / Component 1: Improving Pending Request for Single Stage - One Lab equipment and IDA / 62210 Teaching and Learning Post Open - National 6,600.00 0.00 Implementati 2020-08-30 2020-10-25 2021-01-23 Quotations Envelope materials Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-69 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 42,000.00 0.00 Implementati 2020-07-01 2020-08-26 2020-11-24 Equipment for ceramic Lab Quotations Envelope Capacity on MOEYS-HEIP-NCB-G-33 / Component 1: Improving Under Single Stage - One Universal Testing Machine IDA / 62210 Teaching and Learning Post Request for Bids Open - National 190,000.00 0.00 Implementati 2020-06-26 2020-07-22 2020-07-01 2020-08-12 2020-09-11 2020-10-16 2021-01-14 Envelope (set) Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-70 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 5,500.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Lab Furniture Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-71 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 10,000.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Equipment maintenance Quotations Envelope Capacity on MOEYS-HEIP-NS-G-72 / Component 1: Improving Pending Request for Single Stage - One Make promotion video for IDA / 62210 Teaching and Learning Post Open - National 16,000.00 0.00 Implementati 2020-09-06 2020-11-01 2021-01-30 Quotations Envelope ITC and UIL Capacity on Page 9 MOEYS-HEIP-NS-G-73 / Component 1: Improving Pending Request for Single Stage - One Equipment and Installation IDA / 62210 Teaching and Learning Post Open - National 3,600.00 0.00 Implementati 2020-09-06 2020-11-01 2021-01-30 Quotations Envelope for Practice Language Lab Capacity on MOEYS-HEIP-NS-G-74 / Component 1: Improving Pending Request for Single Stage - One Equipment for prototype IDA / 62210 Teaching and Learning Post Open - National 10,000.00 0.00 Implementati 2020-09-06 2020-11-01 2021-01-30 Quotations Envelope Lab for food processing Capacity on MOEYS-HEIP-NCB-G-004 A / Classroom furniture and Component 1: Improving Pending Single Stage - One office (for Complex building) IDA / 62210 Teaching and Learning Post Request for Bids Open - National 550,000.00 0.00 Implementati 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-07-05 Envelope and business incubation Capacity on centers for ITC MOEYS-HEIP-NCB-G-004 Component 1: Improving Pending B / Classroom furniture and Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 312,000.00 0.00 Implementati 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-07-05 office (for Complex building) Envelope Capacity on ITC MOEYS-HEIP-NS-G-76 / IT Component 1: Improving Pending Equipment for learning Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 83,400.00 0.00 Implementati 2020-07-09 2020-09-03 2020-12-02 facilities and Epidemiology Quotations Envelope Capacity on lab MOEYS-HEIP-NS-G-77 / Component 1: Improving Pending Laboratory for foundation Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 36,000.00 0.00 Implementati 2021-05-06 2021-07-01 2021-09-29 year and veterinary Quotations Envelope Capacity on medicine learning practice MOEYS-HEIP-NS-G-78 / Component 1: Improving Pending Request for Single Stage - One Text book for Library and IDA / 62210 Teaching and Learning Post Open - National 50,000.00 0.00 Implementati 2021-07-06 2021-08-31 2021-11-29 Quotations Envelope faculties Capacity on MOEYS-HEIP-NCB-G-34 / Component 1: Improving Pending Single Stage - One Lab equipment and IDA / 62210 Teaching and Learning Post Request for Bids Open - National 174,670.00 0.00 Implementati 2020-07-01 2020-07-06 2020-08-17 2020-09-16 2020-10-21 2021-04-19 Envelope consumable for food biotec Capacity on MOEYS-HEIP-NS-G-79 / Component 1: Improving Pending Request for Single Stage - One Electronic generator for food IDA / 62210 Teaching and Learning Post Open - National 30,000.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Quotations Envelope biotech research Capacity on MOEYS-HEIP-NS-G-80 / Component 1: Improving Pending Request for Single Stage - One Twin-screw extruder, IDA / 62210 Teaching and Learning Post Open - National 87,250.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Quotations Envelope injection machine, oven Capacity on MOEYS-HEIP-NS-G-81 / Component 1: Improving Pending Laboratory Equipment and Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 81,333.00 0.00 Implementati 2020-07-20 2020-09-14 2020-12-13 cconsumable for tissutre Quotations Envelope Capacity on culture and food biotec Y1 MOEYS-HEIP-NCB-G-35 / Component 1: Improving Pending Lab equipment for pesticide Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 414,500.00 0.00 Implementati 2020-07-01 2020-07-06 2020-08-17 2020-09-16 2020-10-21 2021-01-19 and heavimetal residual in Envelope Capacity on plant products MOEYS-HEIP-NS-G-82 / Laboratory Furniture for Component 1: Improving Pending Request for Single Stage - One research project on tisue IDA / 62210 Teaching and Learning Post Open - National 34,000.00 0.00 Implementati 2020-07-10 2020-09-04 2020-12-03 Quotations Envelope culture, food biotec and Capacity on pesticide residual MOEYS-HEIP-NS-G-83 / Component 1: Improving Pending Laboratory and consumable Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 64,935.00 0.00 Implementati 2020-12-06 2021-01-31 2021-05-01 for bacterial culture and Quotations Envelope Capacity on food processing Year 2 MOEYS-HEIP-NS-G-84 / Laboratory equipment for Component 1: Improving Pending Request for Single Stage - One DNA and PCR and IDA / 62210 Teaching and Learning Post Open - National 85,735.00 0.00 Implementati 2020-12-06 2021-01-31 2021-05-01 Quotations Envelope consumable for DNA and Capacity on pCR MOEYS-HEIP-NS-G-85 / Component 1: Improving Pending consumable for detecting Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 18,300.00 0.00 Implementati 2021-06-06 2021-08-01 2021-10-30 pesticide, heavy metal Quotations Envelope Capacity on residue year 2 MOEYS-HEIP-NS-G-86 / Laboratory Equipment and Component 1: Improving Pending Request for Single Stage - One consumable for tissutre IDA / 62210 Teaching and Learning Post Open - National 51,150.00 0.00 Implementati 2021-06-06 2021-08-01 2021-10-30 Quotations Envelope culture and food biotec, food Capacity on processing Y2 Page 10 MOEYS-HEIP-NS-G-003 / Component 1: Improving Request for Single Stage - One E-learning Lab equipment IDA / 62210 Teaching and Learning Post Open - National 20,000.00 0.00 Canceled 2020-05-06 2020-06-17 2020-09-15 Quotations Envelope for Social Science for RUPP Capacity MOEYS-HEIP-NCB-G-010 / Component 2: Improving Offices equipment at STEM Single Stage - One IDA / 62210 Research in STEM and Post Request for Bids Open - National 420,000.00 0.00 Canceled 2020-05-21 2020-05-26 2020-07-07 2020-08-06 2020-08-27 2020-11-25 Building (21 offices from Envelope Agriculture 4th to 6th floors) for RUPP MOEYS-HEIP-NCB-G-011 / Component 1: Improving Furniture and Equipment Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 390,000.00 0.00 Canceled 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-10 2019-08-08 for Incubation center for Envelope Capacity RUPP Component 1: Improving MOEYS-HEIP-NCB-G-012 / Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 364,000.00 0.00 Canceled 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-10 2019-08-08 Lab furniture for RUPP Envelope Capacity MOEYS-HEIP-NCB-G-013-A / Office Furniture(1-Office Furniture for RUPP and 2- Furniture for office rooms, Component 1: Improving Single Stage - One classroom, data and e- IDA / 62210 Teaching and Learning Post Request for Bids Open - National 655,789.00 0.00 Canceled 2019-10-14 2020-01-31 2019-10-19 2019-11-18 2020-04-10 2019-12-08 2020-01-01 2020-03-31 Envelope learning center, incubation Capacity center, LBE lab, Fab lab, conference room, and smart classroom-ITC) MOEYS-HEIP-NCB-G-023 / Office Furniture( Office Furniture for Faculty of Engineering (RUPP), Office Equipment for Faculty of Component 2: Improving Single Stage - One Engineering (RUPP), Office IDA / 62210 Research in STEM and Post Request for Bids Open - National 762,000.00 0.00 Canceled 2019-08-24 2019-08-29 2019-10-10 2019-10-30 2019-11-28 2020-01-27 Envelope Furniture and equipment for Agriculture Faculty of Engineering (RUPP) for Year II, Office Furniture at STEM Building MOEYS-HEIP-NCB-G-004 / Classroom furniture and Component 1: Improving office (for Complex building) Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 862,000.00 0.00 Canceled 2022-03-25 2022-03-30 2022-05-04 2022-05-18 2022-06-07 2022-09-05 and business incubation Envelope Capacity centers for RUA and ITC at Year 2 MOEYS-HEIP-NS-G-019 / 4- Component 1: Improving IT equipment with system Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 23,000.00 0.00 Canceled 2020-01-28 2020-03-06 2020-08-25 for RUA Journal online Quotations Envelope Capacity management in year2 MOEYS-HEIP-G-DS-01 / Component 1: Improving Pending Office Equipment (With 24 IDA / 62210 Teaching and Learning Post Direct Selection Direct 132,461.00 0.00 Implementati 2020-08-05 2020-08-10 2020-08-29 2020-10-28 items) Capacity on MOEYS-HEIP-G-DS-02 / Component 1: Improving Pending Equipement for Video IDA / 62210 Teaching and Learning Post Direct Selection Direct 54,200.00 0.00 Implementati 2020-08-05 2020-08-10 2020-08-29 2020-10-28 Conference Room (With 5 Capacity on packages) MOEYS-HEIP-G-DS-03 / Component 1: Improving Pending Media Equipment (with 19 IDA / 62210 Teaching and Learning Post Direct Selection Direct 55,204.00 0.00 Implementati 2020-08-05 2020-08-10 2020-08-29 2020-10-28 items) Capacity on MOEYS-HEIP-NCB-G-023A Component 2: Improving Pending Single Stage - One / Office Furniture for IDA / 62210 Research in STEM and Post Request for Bids Open - National 288,938.00 0.00 Implementati 2020-09-03 2020-09-08 2020-10-13 2020-11-17 2020-12-08 2021-02-06 Envelope STEAM Building of RUPP Agriculture on MOEYS-HEIP-NCB-G-023B Component 2: Improving Pending Single Stage - One / Office Equipment for IDA / 62210 Research in STEM and Post Request for Bids Open - National 363,462.00 0.00 Implementati 2020-09-03 2020-09-08 2020-10-13 2020-11-17 2020-12-08 2021-02-06 Envelope STEAM Bulilding of RUPP Agriculture on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 11 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOEYS-HEIP-QCBS-01 / Selection of Consulting Firm for technical design and Component 3: Strengthen Quality And Cost- supervision for construction IDA / 62210 Sectoral Governance and Prior Open - National 1,133,000.00 0.00 Canceled 2019-01-01 2019-02-13 2019-01-22 2019-03-05 2019-03-07 2020-01-01 2019-04-04 2020-02-13 2019-05-04 2019-06-08 2019-07-06 2022-07-05 Based Selection of new buildings at Project Management RUA,SRU, RUPP , ITC and UBB MOEYS-HEIP-QBS-01 / Component 3: Strengthen Quality Based Open - Under Firm to Provide Design and IDA / 62210 Sectoral Governance and Prior 1,605,938.00 0.00 2020-03-23 2020-03-30 2020-04-06 2020-04-21 2020-04-23 2020-07-30 2020-05-21 2020-05-31 2020-06-10 2020-06-27 2022-12-14 Selection International Implementation Supervision Services Project Management MOEYS-HEIP-IC-17 / International Technical Component 1: Improving Consultant Open - Pending Advisor for Promoting IDA / 62210 Teaching and Learning Post Qualification 35,000.00 0.00 2020-04-06 2020-04-27 2020-05-22 2020-06-01 2020-06-13 2020-11-10 International Implementation Research and Development, Capacity Selection Period: 5 months (ITC) MOEYS-HEIP-IC-18 / International Technical Component 1: Improving Consultant Advisor for University- Open - Pending IDA / 62210 Teaching and Learning Post Qualification 15,000.00 0.00 2020-04-06 2020-04-27 2020-05-22 2020-06-01 2020-06-13 2020-09-11 Business Development Plan, International Implementation Capacity Selection Contract Period: 3 months (ITC) MOEYS-HEIP-QBS-02 / An Component 1: Improving Consultant Under Environmental and Social IDA / 62210 Teaching and Learning Post Qualification Open - National 40,000.00 0.00 2020-08-02 2020-08-24 2020-08-23 2020-10-06 2020-11-05 2020-12-10 2021-04-09 Implementation Impact Assessment (ESIA) Capacity Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOEYS-HEIP-IC-04 / Selection of National Component 3: Strengthen Individual Technical Advisor for Project IDA / 62210 Sectoral Governance and Prior Consultant Open 360,000.00 262,647.00 Signed 2018-12-03 2019-01-21 2019-08-08 2019-01-28 2019-08-11 2019-02-18 2019-08-15 2024-04-12 management (National Project Management Selection Individual Consultant) MOEYS-HEIP-IC-08 / Selection of Silk innovation Component 2: Improving Individual Pending specialist for RUPP IDA / 62210 Research in STEM and Post Consultant Open 90,000.00 0.00 2019-01-01 2019-02-19 2019-02-26 2019-03-19 2024-02-21 Implementation (National Individual Agriculture Selection Consultant) MOEYS-HEIP-IC-012 / Selection of International Component 3: Strengthen Individual Technical Advisor for IDA / 62210 Sectoral Governance and Prior Consultant Open 858,000.00 306,979.20 Signed 2018-12-03 2019-01-06 2019-01-21 2019-06-24 2019-01-28 2019-08-07 2019-02-18 2019-08-15 2024-07-21 Support Implementation for Project Management Selection STEM (International Individual Consultant) MOEYS-HEIP-IC-010 / Selection of International Component 3: Strengthen Individual Technical Advisor for Project IDA / 62210 Sectoral Governance and Prior Consultant Open 936,000.00 0.00 Canceled 2018-12-05 2019-01-11 2019-01-23 2019-06-24 2019-01-30 2019-02-20 2024-01-25 management for Project Management Selection (International Individual Consultant) MOEYS-HEIP-IC-02 / Component 1: Improving Individual Recruitment of National IDA / 62210 Teaching and Learning Post Consultant Open 84,000.00 86,690.00 Signed 2018-12-03 2019-01-16 2019-01-21 2019-03-19 2019-01-28 2019-03-19 2019-02-11 2019-04-24 2023-01-21 Procurement Consultant Capacity Selection (Individual Consultant) MOEYS-HEIP-IC-03 / Selection of National Component 1: Improving Individual Under Financial Management IDA / 62210 Teaching and Learning Post Consultant Open 84,000.00 0.00 2018-12-03 2018-08-16 2019-01-21 2019-03-11 2019-01-28 2019-03-19 2019-02-18 2020-06-12 Implementation Consultant (National Capacity Selection Individual Consultant) MOEYS-HEIP-IC-09 / Component 3: Strengthen Individual Selection of National IDA / 62210 Sectoral Governance and Prior Consultant Open 335,000.00 271,790.00 Signed 2019-01-01 2019-02-19 2019-06-24 2019-03-12 2019-08-07 2019-04-02 2019-08-15 2024-03-06 Consultant for Governance Project Management Selection Policy and Planning Page 12 MOEYS-HEIP-IC-011 / Selection of International Technical Advisor for Component 3: Strengthen Individual Pending developing Master Plan for IDA / 62210 Sectoral Governance and Post Consultant Open 143,000.00 0.00 2018-12-03 2019-01-21 2019-01-28 2019-02-18 2020-01-14 Implementation Human resource Project Management Selection (International Individual Consultant) MOEYS-HEIP-IC-14 / National Technical Advisor Component 3: Strengthen Individual to Support Private Higher IDA / 62210 Sectoral Governance and Post Consultant Open 210,000.00 167,520.00 Signed 2019-09-15 2019-08-26 2019-11-03 2019-10-25 2019-11-24 2019-10-25 2019-12-29 2019-10-31 2024-02-06 Education Institution Project Management Selection Program MOEYS-HEIP-IC-15 / International Technical Component 3: Strengthen Individual Advisor to Support Private IDA / 62210 Sectoral Governance and Post Consultant Open 156,000.00 226,700.00 Signed 2019-09-15 2019-08-26 2019-11-03 2019-10-25 2019-11-24 2019-10-25 2019-12-29 2019-11-26 2020-12-28 Higher Education Institution Project Management Selection Program MOEYS-HEIP-IC-16 / NATIONAL CONSULTANT Component 1: Improving Individual ARCHITECT TO DESIGN IDA / 62210 Teaching and Learning Post Consultant Open 30,000.00 31,700.00 Signed 2019-09-02 2019-08-26 2019-10-06 2019-10-25 2019-10-16 2019-10-25 2019-11-04 2019-10-31 2020-10-29 AND SUPERVISE Capacity Selection THE RENOVATION/ CIVIL WORK FOR FIVE HEIs MOEYS-HEIP-IC-010 (1) / International Technical Component 3: Strengthen Individual Advisor for Supporting IDA / 62210 Sectoral Governance and Prior Consultant Open 468,000.00 364,140.00 Signed 2019-12-12 2019-12-19 2020-02-05 2020-04-06 2020-02-26 2020-05-20 2020-03-16 2020-05-22 2023-03-01 Higher Education Project Management Selection Partnership Program and Development MOEYS-HEIP-IC-010 (2) / International Technical Component 3: Strengthen Individual Advisor for Project IDA / 62210 Sectoral Governance and Prior Consultant Open 460,000.00 112,100.00 Signed 2019-12-12 2020-01-06 2020-02-05 2020-04-06 2020-02-26 2020-04-24 2020-03-16 2020-04-27 2023-12-26 Management and Project Management Selection Coordination MOEYS-HEIP-IC-04 (1) / National Technical Advisor Component 3: Strengthen Individual Under for Project management IDA / 62210 Sectoral Governance and Post Consultant Open 260,000.00 0.00 2020-03-25 2020-03-19 2020-04-23 2020-04-30 2020-05-10 2023-04-25 Implementation (National Individual Project Management Selection Consultant) MOEYS-HEIP-IC-16(1) / NATIONAL CONSULTANT Component 1: Improving Individual ARCHITECT TO DESIGN IDA / 62210 Teaching and Learning Post Consultant Open 30,000.00 33,080.00 Signed 2020-03-25 2020-03-18 2020-04-01 2020-03-26 2020-04-11 2020-03-26 2020-04-23 2020-04-01 2021-04-18 AND SUPERVISION THE Capacity Selection RENOVATION/ CIVIL WORK FOR HEIs Component 1: Improving Individual MOEYS-HEIP-IC-02(1) / Pending IDA / 62210 Teaching and Learning Post Consultant Open 43,200.00 0.00 2020-03-25 2020-04-01 2020-04-11 2020-04-25 2022-04-15 Procurement Assistant Implementation Capacity Selection MOEYS-HEIP-IC-19 / National Technical Assistant Component 1: Improving Individual Pending for Project Management and IDA / 62210 Teaching and Learning Post Consultant Open 96,000.00 0.00 2020-04-06 2020-05-12 2020-05-22 2020-06-05 2024-05-15 Implementation Administration, Contract Capacity Selection Period: 48 months (ITC ) MOEYS-HEIP-IC-20 / National Technical Assistant Component 1: Improving Individual Pending for Partnership Management IDA / 62210 Teaching and Learning Post Consultant Open 96,000.00 0.00 2020-04-06 2020-05-12 2020-05-22 2020-06-05 2024-05-15 Implementation and Coordination, Contract Capacity Selection Period: 48 months (ITC) MOEYS-HEIP-IC-21 / National Quality Assurance Component 1: Improving Individual officer for Higher Education Pending IDA / 62210 Teaching and Learning Post Consultant Open 96,000.00 0.00 2020-04-06 2020-05-12 2020-05-22 2020-06-05 2024-05-15 Partnership Programs, Implementation Capacity Selection Contract Period: 48 months (ITC) MOEYS-HEIP-IC-23 / Component 1: Improving Individual National Research Project Pending IDA / 62210 Teaching and Learning Post Consultant Open 96,000.00 0.00 2020-04-06 2020-05-12 2020-05-22 2020-06-05 2024-05-15 Consultant, Contract Period: Implementation Capacity Selection 48 months (ITC) Page 13 MOEYS-HEIP-IC-22 / National Procurement Component 1: Improving Individual Assistant, Contract Period: Pending IDA / 62210 Teaching and Learning Post Consultant Open 48,000.00 0.00 2020-04-06 2020-05-12 2020-05-22 2020-06-05 2022-05-26 24 months with a total Implementation Capacity Selection estimated cost of $ 48,000.00 (ITC) MOEYS-HEIP-IC-24 / Component 1: Improving Individual National Technical for Chief Pending IDA / 62210 Teaching and Learning Post Consultant Open 34,800.00 0.00 2020-07-01 2020-08-19 2020-09-09 2020-10-14 2020-10-17 of Operation (12 months) Implementation Capacity Selection for RUPP MOEYS-HEIP-IC-25 / Component 1: Improving Individual National Technical for Pending IDA / 62210 Teaching and Learning Post Consultant Open 34,800.00 0.00 2020-07-01 2020-08-19 2020-09-09 2020-10-14 2021-10-14 Finance (12 months) for Implementation Capacity Selection RUPP MOEYS-HEIP-IC-05 / Selection of National Technical Advisor for Component 3: Strengthen Individual developing Master Plan for IDA / 62210 Sectoral Governance and Post Consultant Open 55,000.00 0.00 Canceled 2018-12-03 2019-01-21 2019-01-28 2019-02-18 2020-01-14 Human resource for STEM Project Management Selection (National Individual Consultant) MOEYS-HEIP-IC-06 / Selection of National Component 3: Strengthen Individual Technical Advisor for IDA / 62210 Sectoral Governance and Post Consultant Open 60,000.00 0.00 Canceled 2019-08-01 2019-09-19 2019-10-10 2019-10-31 2020-10-30 Developing and conduct Project Management Selection Tracer Study MOEYS-HEIP-IC-07 / Selection of National Component 3: Strengthen Individual Technical Advisor for IDA / 62210 Sectoral Governance and Prior Consultant Open 300,000.00 0.00 Canceled 2019-10-15 2019-12-03 2019-12-10 2019-12-31 2024-12-04 Developing and conduct Project Management Selection Policy Analysis (National individual Consultant) MOEYS-HEIP-IC-13 / Selection of International Component 3: Strengthen Individual Technical Advisor for IDA / 62210 Sectoral Governance and Prior Consultant Open 720,000.00 0.00 Canceled 2018-12-03 2019-01-21 2019-02-11 2019-03-04 2023-02-11 Research (International Project Management Selection Individual Consultant) MOEYS-HEIP-IC-01 / Selection of Project Management Technical Component 1: Improving Individual Assistant for Royal IDA / 62210 Teaching and Learning Post Consultant Open 56,000.00 0.00 Canceled 2019-01-01 2019-06-05 2019-02-19 2019-03-12 2019-04-02 2021-07-20 University of Phnom Penh Capacity Selection (National Individual Consultant) MOEYS-HEIP-IC-DS-01 / Component 1: Improving Pending LMS Administrator for 8 IDA / 62210 Teaching and Learning Post Direct Selection Direct 18,000.00 0.00 2020-08-05 2020-08-15 2020-10-03 2021-01-01 Implementation months For ITC Capacity MOEYS-HEIP-IC-DS-02 / Component 1: Improving Network and system Pending IDA / 62210 Teaching and Learning Post Direct Selection Direct 3,000.00 0.00 2020-08-05 2020-08-15 2020-10-03 2021-01-01 engineer for 4 months for Implementation Capacity ITC MOEYS-HEIP-IC-DS-03 / Component 1: Improving Procurement Assistant to Pending IDA / 62210 Teaching and Learning Post Direct Selection Direct 24,000.00 0.00 2020-08-05 2020-08-15 2020-10-03 2021-01-01 facilitate timely procurement Implementation Capacity of goods works and services Page 14