Procurement Plan (Jal Marg Vikas Project) I. General 1. Project information: [Country: India, Borrower: Ministry of Shipping, Government of India, Project Name: Capacity Augmentation of National Waterway – 1 (Jal Marg Vikas Project), Loan No.:……..; Project ID: P-149460, Project Implementing Agency (PIA): Inland Waterways Authority of India (IWAI), Ministry of Shipping] 2. Bank’s approval Date of the procurement Plan : March 15, 2017 3. Date of General Procurement Notice: 15-September-2014 4. Period covered by this procurement plan: First 18 months of the project, including retroactive financing. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Categor Threshold (US$ Method of Procurement y Equivalent) Works International Competitive Bidding > 40,000,000 (ICB) National Competitive Bidding Up to 40,000,000 (with NCB (NCB) conditions) Shopping Up to 100,000 As per paragraph 3.7 of Direct Contracting (DC) Guidelines Public-Private Partnership (PPP) As per paragraph 3.14 of for Works Guidelines As per paragraph 3.9 of Force Account Guidelines As per paragraph 3.6 of Framework Agreement (FA) Guidelines Goods International Competitive Bidding > 3,000,000 and non- (ICB) consulta Limited International Bidding (LIB) wherever agreed by Bank nt National Competitive Bidding Up to 3,000,000 (with NCB services (NCB) conditions) (NCS) Shopping Up to 100,000 Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) As per paragraph 3.14 of Services Guidelines Force Account (only for NCS) As per paragraph 3.9 of Guidelines Framework Agreement (FA)1 As per paragraph 3.6 of Guidelines Procurement from United Nations As per paragraph 3.10 of (UN) Agencies Guidelines World Bank review of procurement: The World Bank will prior review (thresholds are based on “Substantial” risk rating, which may be modified if risk rating is changed after assessment by Bank during implementation of the project) the following contracts: a) Works (Including turnkey, supply & installation of plant and equipment and PPP) : All contracts more than US$ 10 million equivalent b) Goods, Information Technology and non-consulting services : All contracts more than US$ 2 million equivalent First contract issued by implementing agency [IA] will be subject to prior review irrespective of their value. In addition, the justifications for all contracts to be issued on the basis of LIB, single-source or direct contracting, will be subject to prior review. The above thresholds are for the initial 18 month implementation period; based on the procurement performance of the project these thresholds may be subsequently modified. Even for Post Review cases, the inputs of Bank on Technical Specifications will be obtained by project. The procurement plan will be updated annually (or at any other time if required) and will reflect any change in prior review thresholds. The World Bank will carry out an annual ex-post procurement review of the procurement falling below the prior review thresholds provided above. To avoid any doubts, the Bank may conduct at any time Independent Procurement Reviews (IPRs) of all the contracts financed under the grant. 1 DGS&D rate contracts may be used as framework agreement (FA) provided: • Use of DGS&D rate contracts as FA must be reflected on the procurement plan agreed by the Bank for particular goods. • Before issuing the purchasing order, the implementing agency will carry out a price analysis on the specific good that is intended to be purchased. If after this due diligence the implementing agency concludes (and Bank agrees) that the DGS&D rate contracts are more advantageous, DGS&D rate contracts may be used as FA. • To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders (in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders). On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned. 2. Prequalification. Bidders for Least Available Depth tender for the first contract and any other contract, as per requirement, shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: N/A 5. Any Other Special Procurement Arrangements: Retroactive Financing as per Legal Agreement. 6. Procurement Packages with Methods and Time Schedule 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurem Prequalificat Domesti Review Expected Commen No. (Description) Cost ent ion (yes/no) c by Bank Bid- ts (Rs. Method Preferen (Prior / Opening Million) ce Post) Date (yes/no) CANW- Interior Works for 7.9 Shopping No No Post 24-Apr-15 The 1/IWAI/ Office of the value of JMV/4A Project contract Management Unit was of Jal Marg Vikas increase Project d to Rs. 9.1 Million CANW- Furniture and 6.6 Shopping No No Post 24-Apr-15 The 1/IWAI/ other equipment value of JMV/4B for Office of the contract Project was Management Unit increase of Jal Marg Vikas d to Rs. Project 7.4 Million CANW- Office Interiors 2 2.5 Shopping No No Post 24-Apr-15 1/IWAI/ for PMU JMV/4C CANW- Laptops (6 Nos.) 0.46 Shopping No No Post 26-Sept- 1/IWAI/ 14 JMV/5 CANW- Self Propelled 600 ICB No No Prior May-16 1/IWAI/ Cutter Suction JMV/7 Dredger (2 Nos.) CANW- Inspection cum 100 ICB No Yes Prior 22-Jan-15 The 1/IWAI/ Survey Vessel (2 contract JMV/8 Nos.) is awarded at Rs. 139.94 Million CANW- Performance 2,034.9 ICB Yes No Prior 15-Feb-16 Contract 1/IWAI/ based or JMV/9 Maintenance finalized, contract for Contract Navigation on Part to be of National signed Waterway – 1 for Rs. (Farakka – 1589.1 Bhagalpur) Million CANW- Procurement of 2,018 ICB No No Prior 28-Sept- Contract 1/IWAI/ EPC Contract for 15 or JMV/10 Construction of finalized, Terminal at Contract Varanasi signed for Rs. 1695.9 Million CANW- Procurement of 2,921 ICB No No Prior 14-Mar-16 Contract 1/IWAI/ EPC Contract for or JMV/11 Construction of finalized, IWT Terminal at Contract Sahibganj, signed Jharkhand for Rs. 2809 Million CANW- Procurement of 4,650 ICB No No Prior 18-Apr-16 Contract 1/IWAI/ EPC Contract for or JMV/15 Construction of finalized, Multimodal IWT Contract Terminal at to be Haldia, signed West Bengal for Rs. 5173.62 Million CANW- Procurement of 3,520 ICB No No Prior May-16 Contract 1/IWAI/ EPC Contract for or JMV/16 Construction of finalized, Navigation Lock at Contract Farakka, signed West Bengal for Rs. 3591.9 Million CANW- Laptop (1 No.) 0.16 Shopping No No Post 03-Dec-15 Through 1/IWAI/ (Apple) DGS&D JMV/17 Rate Contract CANW- B&W Printer (1 0.27 Shopping No No Post 03-Dec-15 Through 1/IWAI/ No.) DGS&D JMV/18 Rate Contract CANW- Color Printer (1 0.19 Shopping No No Post 03-Dec-15 Through 1/IWAI/ No.) DGS&D JMV/19 Rate Contract CANW- Desktop (8 Nos.) 0.37 Shopping No No Post 03-Dec-15 Through 1/IWAI/ DGS&D JMV/20 Rate Contract CANW- Laptop (10 Nos.) 0.62 Shopping No No Post 03-Dec-15 Through 1/IWAI/ DGS&D JMV/21 Rate Contract CANW- UPS (10 Nos.) 0.24 Shopping No No Post 03-Dec-15 Through 1/IWAI/ DGS&D JMV/22 Rate Contract CANW- Performance 6,925 ICB Yes No Prior 15-Apr-17 1/IWAI/ based JMV/28 Maintenance contract for Navigation on Part of National Waterway – 1 (Barh – Ghazipur) CANW- Performance 2,346.6 ICB Yes No Prior 15-Apr-17 1/IWAI/ based JMV/29 Maintenance contract for Navigation on Part of National Waterway – 1 (Ghazipur – Varanasi) CANW- Procurement of 600 ICB No No Prior 18-Mar-17 1/IWAI/ EPC Contract for JMV/30 Construction of IWT Terminal at third Location CANW- Procurement of 800 ICB No No Prior 18-Feb-18 1/IWAI/ EPC Contract for JMV/31 Construction of IWT Terminal at Kalughat, Bihar CANW- Procurement of 600 ICB No No Prior 18-Jan-17 1/IWAI/ EPC Contract for JMV/32 Construction of IWT Terminal at Ghazipur, Uttar Pradesh CANW- Procurement of 375 ICB No No Prior 18-Jul-17 1/IWAI/ EPC Contract for JMV/33 Construction of Vessel Repair and Maintenance Facility, Site 1 CANW- Procurement of 375 ICB No No Prior 18-Aug-17 1/IWAI/ EPC Contract for JMV/34 Construction of Vessel Repair and Maintenance Facility, Site 2 Total 2,7857.8 Rs. 1 15,015. 96 Million worth of contract awarde d III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Threshold (US$ Category Method of Procurement Equivalent) Consultants’ Selection Based on Consultants’ Up to 300,000 Services Qualifications (CQS)/Least-Cost Selection (LCS) Single-Source Selection (SSS) As per paragraphs 3.9- 3.11 of Guidelines Individuals As per Section V of Guidelines Particular Types of Consultants As per paragraphs 3.15- 3.21 of Guidelines Quality- and Cost-Based for all other cases Selection (QCBS)/ Quality-Based Selection (QBS)/ Selection under a Fixed Budget (FBS) (i) International shortlist > 800,000 (ii) Shortlist may comprise Up to 800,000 national consultants only a) Consulting Services (firms) : All contracts more than US$ 1 million equivalent; b) Individual Consultants : All contracts above US$ 300,000. First Consultancy contract issued by implementing agency [IA] will be subject to prior review irrespective of their value. In addition, the justifications for all contracts to be issued on the basis of single-source, will be subject to prior review. The above thresholds are for the initial 18 month implementation period; based on the procurement performance of the project these thresholds may be subsequently modified. Even for Post Review cases, the inputs of Bank on TORs will be obtained by project. The procurement plan will be updated annually (or at any other time if required) and will reflect any change in prior review thresholds. The World Bank will carry out an annual ex-post procurement review of the procurement falling below the prior review thresholds provided above. To avoid any doubts, the Bank may conduct at any time Independent Procurement Reviews (IPRs) of all the contracts financed under the grant. NCB Condition: National competition for the procurement of goods and works according to the established thresholds will be conducted in accordance with paragraphs 3.3 & 3.4 of Section III of the Guidelines and the following provisions: a) Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding; b) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; c) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State; d) Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; e) Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/Employer); f) Re-bidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; g) Rate contracts entered into by Directorate General of Supplies and Disposals (DGS&D) will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however for any procurement under the Shopping procedures; h) Two or three envelope system will not be used (except when using e- procurement system assessed and agreed by the Bank). 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Retroactive Financing as per Legal Agreement 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref. No. Description of Estimated Selection Review Expected Comments Assignment Cost Method by Bank Proposals (Rs. Million) (Prior / Submission Post) Date CANW- Detailed 454.34 QCBS Prior 22-Apr-15 Contract 1/IWAI/JMV/1 Feasibility awarded at Study for Rs. 188.1 Capacity Million + GBP Augmentation 0.74 Million of National (excluding Waterway-1 applicable and Detailed taxes) Engineering for its Ancillary Works and processes CANW- Consultancy for 57.57 QCBS Prior 30-Jan-15 Contract 1/JMV/IWAI/2 Environmental awarded at and Social Rs. 28.61 Impact Million Assessment (excluding (ESIA), applicable Environmental taxes) Management Plan (EMP) and Resettlement Action Plan (RAP) for Capacity Augmentation of National Waterway-1 (Jal Marg Vikas) CANW- Consultant for 66.79 QCBS Prior 13-Mar-15 Contract 1/JMV/IWAI/4 IWT Sector awarded at Development Euro 0.84 Strategy and Million + Rs. Market 0.62 Million Development (excluding all Study for applicable Capacity taxes) Augmentation of National Waterway-1 CANW- Supporting 23.84 QCBS Prior 04-Apr-16 Contract 1/JMV/IWAI/12 Services for awarded at Design of Inland Euro 0.28 Vessels for Million Capacity (excluding all Augmentation applicable of National taxes) Waterway – 1 (Jal Marg Vikas Project) CANW- Consultancy for 6.5 QCBS Post 21-Mar-16 Contract 1/JMV/IWAI/13 Communication awarded at s Needs Rs. 2.16 Assessment, Million Development (excluding all and applicable Implementation taxes) of Communication s Strategy and Strategic Communication s Support for ‘Capacity augmentation of navigational infrastructure of National Waterway-1’ between Haldia to Allahabad (Jal Marg Vikas Project) CANW- Implementation 3.34 QCBS Post 04-Apr-16 1/JMV/IWAI/14 of Resettlement Action Plan (RAP) for Jal Marg Vikas Project for the Capacity Augmentation of Navigation on National Waterway -1 CANW- Consultancy for 42.49 QCBS Post May-16 1/JMV/IWAI/23 Inland Waterways Transport Institutional Strengthening and Capacity Building CANW- Technical 97.22 QCBS Prior Jun-16 1/JMV/IWAI/24 Support Services Consultancy – Cluster 1 for MMT at Varanasi and Sahibganj (located at Patna) CANW- Technical 117.96 QCBS Prior Jun-16 1/JMV/IWAI/25 Support Services Consultancy – Cluster 2 for MMT at Haldia and Navigation Lock at Farakka (located at Kolkata) CANW- Consultancy 37.41 QCBS Prior Jun-16 Contract 1/JMV/IWAI/26 Services for awarded at Project Rs. 14.31 Preparatory and Million + USD Definition Study 0.47 Million for (excluding all Development of applicable Ferry services taxes) on NW-1 CANW- Consultancy 34.42 QCBS Prior Jun-16 Contract 1/JMV/IWAI/27 Services for awarded at Plan and Euro 0.5 Implementation Million support for (excluding all commercializati applicable on of NW-1 taxes) Total 941.88 Rs. 233.8 Million + GBP 0.74 Million + Euro 1.62 Million + USD 0.47 Million worth of contract awarded PROCUREMENT India : Capacity Augmentation of the National Waterway- 1 (JAL MARG VIKAS) Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-06-10 2021-09-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148775 GPN Date: Project Name: Capacity Augmentation of the National Waterway- 1 (JAL MARG VIKAS) Project Loan / Credit No: IBRD / P4740, IBRD / 87520 Inland Waterways Authority of India Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Folder # 6 / Construction of Single Stage - One 25,949,781. Multimodal IWT Terminal at IBRD / P4740 Prior Request for Bids Open - International 0.00 Signed 2015-10-30 2016-05-13 Envelope 17 Varanasi, Uttar Pradesh CANW-1/IWAI/JMV/15 / Procurement of EPC Contract Component A: Improving the Single Stage - One 71,538,461.5 75,683,207. 2019-05- for Construction of IBRD / P4740 navigability of NW-1 (Haldia Prior Request for Bids Open - International Signed 2016-09-20 2017-01-12 2016-09-20 2017-01-12 2016-09-20 2017-01-12 2016-10-20 2017-01-12 2016-11-24 2017-06-30 Envelope 4 68 06 Multimodal IWT Terminal at to Varanasi) Haldia, West Bengal CANW-1-IWAI-JMV-11 / Engineering Procurement and Component A: Improving the Single Stage - One 44,938,461.5 40,963,712. 2019-04- Construction (EPC) for IBRD / P4740 navigability of NW-1 (Haldia Prior Request for Bids Open - International Signed 2016-09-20 2016-09-23 2016-09-20 2016-09-20 2017-01-12 2016-09-20 2017-01-12 2016-11-09 2017-01-12 Envelope 4 56 21 Construction of IWT Terminal to Varanasi) at Sahibganj, Jharkhand CANW-1/IWAI/JMV/16 / Procurement of EPC Contract Component A: Improving the Single Stage - One 54,153,846.1 52,544,647. 2019-05- for Construction of Navigation IBRD / P4740 navigability of NW-1 (Haldia Prior Request for Bids Open - International Signed 2016-09-20 2017-01-12 2016-09-20 2017-01-12 2016-09-20 2017-01-12 2016-10-20 2017-01-12 2016-11-24 2017-01-01 Envelope 5 94 06 Lock at Farakka, to Varanasi) West Bengal CANW-1/IWAI/JMV/9 / Performance based Component A: Improving the Under Maintenance contract for Single Stage - One 31,306,153.8 24,652,781. 2019-07- IBRD / P4740 navigability of NW-1 (Haldia Prior Request for Bids Open - International Implementat 2017-06-23 2017-09-08 2017-06-28 2017-09-08 2017-06-28 2017-06-28 2017-11-17 2017-06-28 2017-12-17 2017-06-28 2018-01-21 Navigation on Part of National Envelope 4 86 15 to Varanasi) ion Waterway - 1 (Farakka - Bhagalpur) IN-IWAI-26080-CW-RFB / Sultanganj - Mahendrapur - Component A: Improving the Performance based assured Single Stage - Two 36,430,769.2 2018-07- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - International 0.00 Canceled 2017-08-24 2018-02-16 2017-08-29 2017-10-10 2017-12-23 2018-01-27 depth dredging between Envelope 3 26 to Varanasi) Sultanganj - Mahendrapur stretch of NW-1 IN-IWAI-26081-CW-RFB / Mahendrapur-Barh - Component A: Improving the Performance based Assured Single Stage - Two 36,107,692.3 2018-07- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - International 0.00 Canceled 2017-08-24 2018-02-16 2017-08-29 2017-10-10 2017-12-23 2018-01-27 depth dredging between Envelope 0 26 to Varanasi) Mahendrapur - Barh stretch of NW-1 CANW-1/ IWAI / JMV /9 / Procurement for Providing Assured Least Available Depth of 3.0 m by Dredging / Component A: Improving the Single Stage - One 2019-02- Bandalling as well as Erection IBRD / P4740 navigability of NW-1 (Haldia Prior Request for Bids Open - International 25.69 0.00 Canceled 2017-01-12 2017-03-30 2017-01-13 2017-03-30 2017-01-13 2017-01-17 2017-06-08 2017-01-13 2017-07-08 2017-01-13 2017-08-12 Envelope 03 and Maintenance of to Varanasi) Navigational Aids in Farakka - Kahalgaon Stretch of National Waterway -1 (River Ganga) IN-IWAI-46606-CW-RFP / Component A: Improving the Ghazipur - EPC contract for Request for Single Stage - Two 19,230,770.0 2020-11- IBRD / 87520 navigability of NW-1 (Haldia Prior Open - National 0.00 Canceled 2018-01-31 2018-02-10 2018-03-10 2018-04-29 2018-05-27 construction of IWT Inter Proposals Envelope 0 12 to Varanasi) Modal Terminal at Ghazipur CANW-1/IWAI/JMV/9A / Performance based Component A: Improving the maintenance contract for Single Stage - One 31,306,153.8 23,084,025. 2023-04- IBRD / P4740 navigability of NW-1 (Haldia Prior Request for Bids Open - International Signed 2018-03-09 2018-05-25 2018-05-25 2018-03-14 2018-08-03 2018-09-02 2018-03-14 2018-10-07 2018-04-09 navigation on part of National Envelope 4 00 30 to Varanasi) Waterway - 1 (Farakka - Kahalgaon) IN-IWAI-46606A-CW-RFB / Component A: Improving the Ghazipur - EPC Contract for Single Stage - Two 19,230,770.0 2020-12- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - National 0.00 Canceled 2018-03-09 2018-03-26 2018-03-19 2018-03-28 2018-04-16 2018-06-05 2018-07-03 construction of IWT Inter Envelope 0 19 to Varanasi) Modal Terminal at Ghazipur IN-IWAI-65611-CW-RFB / Procurement of EPC Contract Component A: Improving the Under Single Stage - Two 14,940,000.0 2020-11- for Construction of IWT IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - National 0.00 Implementat 2018-06-15 2018-08-14 2018-06-20 2018-08-01 2018-10-14 2018-11-18 Envelope 0 17 Terminal at Ghazipur, Uttar to Varanasi) ion Pradesh IN-IWAI-68538-CW-RFB / Procurement of Contractor for Providing Assured Least Component A: Improving the Available Depth of 2.5 /3.0 m Single Stage - Two 36,430,766.2 2023-12- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - International 0.00 Canceled 2018-07-06 2018-07-12 2018-07-11 2018-09-07 2018-08-22 2018-09-24 2018-11-04 2018-12-09 by Performance Based Envelope 3 09 to Varanasi) Dredging & Bandalling in Sultanganj - Mahendrapur (74 km) of National Waterway - 1 IN-IWAI-68539-CW-RFB / Procurement of Contractor for Providing Assured Least Component A: Improving the Available Depth of 2.5 /3.0 m Single Stage - Two 36,107,692.3 2023-12- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - International 0.00 Canceled 2018-07-06 2018-07-26 2018-07-11 2018-08-22 2018-09-24 2018-11-04 2018-12-09 by Performance Based Envelope 0 09 to Varanasi) Dredging & Bandalling in Mahendrapur - Barh (71 km) of National Waterway - 1 Page 1 IN-IWAI-77998-NC-RFB / Component A: Improving the Paving the Back up area of Single Stage - Two 2018-11- IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 290,000.00 0.00 Canceled 2018-09-20 2018-09-25 2018-10-11 2018-10-22 2018-10-30 Varanasi Multi Modal Terminal Envelope 29 to Varanasi) with Paver Blocks IN-IWAI-96065-CW-RFB / Bend Correction - Re- engineering of River Bends in Component A: Improving the Under Approach Channel Up Stream Single Stage - Two 16,000,000.0 2020-01- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - National 0.00 Implementat 2019-01-31 2019-04-05 2019-02-05 2019-03-19 2019-06-01 2019-07-06 of Farakka Navigational Lock Envelope 0 02 to Varanasi) ion through LAD Dredging / dry excavation or combination there of. IN-IWAI-103402-CW-RFB / Component A: Improving the Pending Procurement of EPC Contract Single Stage - Two 10,152,857.0 2021-08- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - National 0.00 Implementat 2019-02-28 2019-03-05 2019-04-16 2019-06-29 2019-08-03 for Bank Protection Work in Envelope 0 02 to Varanasi) ion Feeder Canal IN-IWAI-68538-CW-RFB-A / Procurement of Contractor for Providing Assured Least Component A: Improving the Available Depth of 2.5 /3.0 m Single Stage - Two 36,430,766.2 22,421,443. 2024-08- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - International Signed 2019-03-29 2019-04-03 2019-05-15 2019-07-28 2019-09-18 2019-09-01 2019-04-12 by Performance Based Envelope 3 14 31 to Varanasi) Dredging & Bandalling in Sultanganj - Mahendrapur (74 km) of National Waterway - 1 IN-IWAI-68539-CW-RFB-A / Procurement of Contractor for Providing Assured Least Component A: Improving the Available Depth of 2.5 /3.0 m Single Stage - Two 36,107,692.3 26,368,711. 2024-08- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - International Signed 2019-03-29 2019-04-03 2019-05-15 2019-07-28 2019-06-12 2019-09-01 2019-04-12 by Performance Based Envelope 0 29 31 to Varanasi) Dredging & Bandalling in Mahendrapur - Barh (71 km) of National Waterway - 1 IN-IWAI-68629-CW-RFB / LAD - Ghazipur Varanasi Stretch ( 133km) - Component A: Improving the Procurement of dredging Single Stage - Two 62,307,700.0 2023-12- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - International 0.00 Canceled 2018-07-13 2018-07-18 2018-08-29 2018-11-11 2018-12-16 Works & services for Providing Envelope 0 16 to Varanasi) Assured Least Available Depth of 2.2m by performance Based Dredging & Bandalling. IN-IWAI-136395-CW-RFB / Barh- Majuhua - Contract for Quantity Based Dredging Contract & Providing Target Component A: Improving the Pending Least Available depth LAD of Single Stage - Two 2020-09- IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 5,653,846.00 0.00 Implementat 2019-10-15 2019-10-20 2019-12-01 2020-02-13 2020-03-19 2.50m and Channel Width of Envelope 15 to Varanasi) ion 30 m during 1st & 2nd year and 35 m during 3rd year onwards , On O&M Contract ( using IWAI Dredgers) IN-IWAI-133241-CW-RFB / Ghazipur-Varanasi Stretch - Procurement of contract for Quantity Based Dredging Component A: Improving the Contract & Providing Target Single Stage - Two 2020-08- IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 6,468,000.00 0.00 Canceled 2019-09-16 2019-09-21 2019-11-02 2020-01-15 2020-02-19 LAD ( Least Available Depth) Envelope 17 to Varanasi) of 2.20m and Channel Width of 30m during 1st & 2nd year and 35m during 3rd year onwards. IN-IWAI-133235-CW-RFB / Majhaua-Ghazipur stretch - Procurement of Contract foe Quantity Based Dredging Component A: Improving the Contract & providing Target Single Stage - Two 13,908,461.0 2020-08- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - National 0.00 Canceled 2019-09-16 2019-09-21 2019-11-02 2020-01-15 2020-02-19 LAD I Least Available Depth) Envelope 0 17 to Varanasi) of 2.5 m & channel Width of 30 m during 1st & 2nd year and 35 m during 3rd year onwards. IN-IWAI-144901-CW-RFB / Barh-Digha (69km) - Procurement of Contract for providing Assured LAD - Component A: Improving the Least available Depth of 2.5 m Single Stage - Two 27,857,145.0 2020-10- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - National 0.00 Canceled 2019-11-25 2020-01-09 2019-12-05 2020-04-01 2020-01-15 2020-03-29 2020-05-03 by performance Based Envelope 0 30 to Varanasi) Dredging / Bandalling as well as Erection Maintenance of Navigational Aids in Barh - Digha Stretch of NW-1 IN-IWAI-144903-CW-RFB / Digha-Majhaua (98 Km) - Procurement of contractor for providing Assured LAD- Least Component A: Improving the Available Depth of 2.5M by Single Stage - Two 39,480,000.0 2020-10- IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - National 0.00 Canceled 2019-11-26 2020-01-07 2019-12-06 2020-04-01 2020-01-15 2020-03-29 2020-05-03 Performance Based Dredging Envelope 0 30 to Varanasi) / Bandalling as well as Erection Maintenance of Navigational Aids in Digha - Majhaua ( 98 Km) in NW-1 IN-IWAI-185377-CW-RFB / Kalughat IWT - Construction Component A: Improving the Under Single Stage - Two 13,214,285.0 2023-03- of Inter-Modal IWT Terminal IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - National 0.00 Implementat 2020-08-17 2020-12-11 2020-08-24 2021-06-13 2020-10-23 2021-03-30 2021-01-05 2021-08-29 2021-02-09 Envelope 0 01 on EPC Contract at Kalughat - to Varanasi) ion Bihar IN-IWAI-189283-CW-RFB / Majhaua-Ghazipur 121km - Contract for Quantity Based Dredging for providing LAD Component A: Improving the Under Single Stage - Two 12,915,000.0 2023-12- (Least Available Depth) of IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - National 0.00 Implementat 2020-11-30 2021-09-21 2020-12-07 2021-01-18 2021-04-02 2021-05-07 Envelope 0 31 2.0m /2.25m/2.5m. and to Varanasi) ion Width of 30 m in Majhaua – Ghazipur 121 km of National Waterway – 1 Page 2 IN-IWAI-189285-CW-RFB / (Ghazipur - Varanasi 133 km) Contract for Quantity Based Dredging for providing LAD Component A: Improving the Pending Single Stage - Two 2023-12- (Least Available Depth) of IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 7,577,428.00 0.00 Implementat 2020-12-10 2020-12-17 2021-01-28 2021-04-12 2021-05-17 Envelope 31 2.0m /2.25m/2.5m. and to Varanasi) ion Width of 30 m in Ghazipur - Varanasi 133 km of National Waterway – 1 IN-IWAI-213010-CW-RFB / Barh-Digha-Majhaua 167km - Contract for Quantity Based Dredging for providing LAD Component A: Improving the Pending (Least Available Depth) of Single Stage - Two 2023-12- IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 4,864,286.00 0.00 Implementat 2021-01-20 2021-01-25 2021-03-08 2021-05-21 2021-06-25 2.0m /2.25m/2.5m. and Envelope 30 to Varanasi) ion Width of 30 m in Barh-Digha- Majhaua 167Km on O&M contract using IWAI Dredgers on National Waterway – 1 IN-IWAI-228846-CW-RFB / Component A: Improving the Pending Construction of 03 pairs of RO Single Stage - Two 2022-02- IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 1,464,000.00 0.00 Implementat 2021-05-03 2021-05-08 2021-06-19 2021-09-17 2021-10-22 RO Terminals in the State of Envelope 19 to Varanasi) ion Bihar IN-IWAI-176289-CW-RFB / Tribeni - Farakka - Procurement of ADMEASUREMENT CONTRACTS for Quantity Component A: Improving the Single Stage - Two 2021-07- Based Dredging Contract with IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 9,210,527.00 0.00 Canceled 2020-08-16 2020-11-17 2020-08-21 2020-11-19 2020-10-02 2021-03-04 2020-12-15 2021-01-19 Envelope 18 for 3m LAD and Channel to Varanasi) Width of 36 m in Triveni – Farakka stretch round the year for 5 years Between Farraka – Tribeni Stretch (351KMs) IN-IWAI-240376-CW-RFB / Tribeni - Farakka (351kms) - Procurement of Request for Bids - ADMEASUREMENT Component A: Improving the Under Single Stage - Two Works (without 2023-12- CONTRACTS for Quantity IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 6,762,000.00 0.00 Implementat 2021-07-08 2021-08-17 2021-07-13 2021-08-17 2021-08-10 2021-10-03 2021-11-07 Envelope prequalification) 31 Based Dredging Contract for to Varanasi) ion SPD 3m LAD and Channel Width of 36 m for 3 years in Triveni – Farakka stretch IN-IWAI-242322-CW-RFB / ADMEASUREMENT Request for Bids - CONTRACTS FOR SERVICES Component A: Improving the Under Single Stage - Two Works (without 2023-12- FOR WATER LEVEL AND IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 1,200,000.00 0.00 Implementat 2021-07-12 2021-07-22 2021-07-17 2021-07-22 2021-08-28 2021-11-10 2021-12-15 Envelope prequalification) 31 DISCHARGE MONITORING to Varanasi) ion SPD STATIONS ON NATIONAL WATERWAY No. 1 GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWAI-64317-GO-RFB / Component A: Improving the SPCSD - Self Propelled Cutter Single Stage - Two IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - International 9,230,770.00 0.00 Canceled 2018-05-28 2018-06-14 2018-06-02 2018-08-27 2018-07-14 2018-09-17 2018-09-26 2018-10-31 2019-04-29 Suction Dredgers for JMVP- Envelope to Varanasi) NW-1 ( 2 Nos) IN-IWAI-29583-GO-RFB / Component A: Improving the SPCSD - Self Propelled Cutter Single Stage - Two IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - International 12,307,700.00 0.00 Canceled 2017-10-10 2017-12-18 2017-10-25 2017-12-24 2018-04-07 2018-05-21 2019-05-21 Suction Dredgers for JMVP - Envelope to Varanasi) NW-1( 2nos) IN-IWAI-52298-GO-RFB / VOIP- Voice Over Internet Component A: Improving the Protocol systems to be Single Stage - Two IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 67,700.00 0.00 Canceled 2018-03-12 2018-05-01 2018-03-17 2018-05-16 2018-04-28 2018-06-08 2018-07-11 2018-08-15 2019-02-11 installed at NOIDA, Varanasi, Envelope to Varanasi) Patna, Sahibganj, Kolkatta & Faraka. IN-IWAI-79679-GO-RFB / Component B: Institutional Procurement of Equipment for Strengthening and improving Single Stage - Two Solid & Liquid waste: IBRD / 87520 the investment climate, Post Request for Bids Open - National 318,461.54 0.00 Canceled 2018-09-26 2018-09-27 2018-10-01 2018-11-12 2018-10-12 2019-01-25 2018-11-02 2019-03-01 2020-02-29 Envelope Collection & Transportation at vessel design and MMT Varanasi construction framework IN-IWAI-96103-GO-RFQ / Component B: Institutional Supply and Installation of Strengthening and improving Request for Single Stage - One CCTV Surveillance system at IBRD / 87520 the investment climate, Post Open - National 57,292.31 48,530.97 Signed 2019-01-28 2019-03-25 2019-01-02 2019-05-09 Quotations Envelope Sahibganj Terminal, Farakka vessel design and Lock and Haldia Terminal construction framework IN-IWAI-121793-GO-RFB / Procurement of Waste Component B: Institutional Reception facility including Strengthening and improving Pending collection, storage, treatment Single Stage - Two IBRD / 87520 the investment climate, Post Request for Bids Open - National 987,652.43 0.00 Implementati 2019-07-15 2019-07-20 2019-08-31 2019-11-13 2019-12-18 2020-12-17 and disposal of solid and Envelope vessel design and on liquid waste at MMT Varanasi, construction framework MMT Sahibganj and MMT Haldia IN-IWAI-104973-GO-RFB / Component A: Improving the Single Stage - Two Floating Debris Collector Work IBRD / 87520 navigability of NW-1 (Haldia Prior Request for Bids Open - International 3,321,428.57 0.00 Canceled 2019-03-08 2019-05-03 2019-03-13 2019-05-24 2019-04-24 2019-07-07 2019-08-11 2020-08-10 Envelope Boat and Twin Skipper Barge to Varanasi) IN-IWAI-228578-GO-RFB / Component B: Institutional Procurement of FRP (12 Nos.) Strengthening and improving Pending Single Stage - Two and VIP (04 Nos.) boats on NW- IBRD / 87520 the investment climate, Post Request for Bids Open - National 653,333.33 0.00 Implementati 2021-05-03 2021-05-08 2021-06-19 2021-09-01 2021-10-06 2022-04-04 Envelope 1 under JMVP Phase-II (Arth vessel design and on Ganga) construction framework NON CONSULTING SERVICES Page 3 Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWAI-55644-NC-RFB / Geo-technical Investigation at Component A: Improving the Single Stage - One various locations in NW-1 for IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 125,262.00 0.00 Canceled 2018-04-20 2018-05-30 2018-04-25 2018-06-04 2018-06-06 2018-06-29 2018-07-06 2018-08-10 2019-02-06 Envelope Bank Protection, RO-RO and to Varanasi) Ship repair complex IN-IWAI-55630-NC-RFB / Component B: Institutional Procurement of Cargo Vessels Strengthening and improving Single Stage - Two on leasing cum Time charter IBRD / 87520 the investment climate, Prior Request for Bids Open - National 2,067,695.00 0.00 Canceled 2018-05-24 2018-05-29 2018-07-10 2018-09-22 2018-10-27 2019-04-25 Envelope basis for capacity vessel design and augmentation of NW-1 construction framework IN-IWAI-55630A-NC-RFB / Procurement of Non- Component B: Institutional consulting Services for Cargo Strengthening and improving Under Single Stage - Two and Ro-Ro Vessel Hiring for IBRD / 87520 the investment climate, Prior Request for Bids Open - National 2,171,077.00 0.00 Implementati 2018-08-31 2019-01-13 2018-09-05 2019-01-14 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope Capacity Augmentation of vessel design and on National waterways-1 ( River construction framework Ganga) IN-IWAI-215436-NC-RFB / Component A: Improving the CAMC AND O&M OF RIS Single Stage - Two IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 537,517.37 0.00 Canceled 2021-01-27 2021-01-25 2021-02-01 2021-02-11 2021-03-15 2021-06-30 2021-05-28 2021-07-02 2024-07-02 STATIONS OF PHASE-I AND Envelope to Varanasi) CAMC OF SHIP STATIONS IN-IWAI-243301-NC-RFB / RIS : CAMC and O&M of RIS Component A: Improving the Under Stations – Phase -1 (Haldia – Single Stage - Two IBRD / 87520 navigability of NW-1 (Haldia Post Request for Bids Open - National 537,517.37 0.00 Implementati 2021-07-14 2021-07-14 2021-07-19 2021-07-16 2021-07-22 2021-10-04 2021-11-08 2022-05-07 Farakka of NW-1) and CAMC Envelope to Varanasi) on of Ship Stations on National Waterway No. 1 (River Ganga) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWAI-188-CS-QCBS / Consultancy Services for Project Preparatory and Definition Study for Development of Ferry services Component A: Improving the Quality And Cost- on NW-1. The scope of work IBRD / P4740 navigability of NW-1 (Haldia Post Open - International 575,587.04 864,232.68 Signed 2016-09-20 2017-01-01 2016-09-20 2016-09-20 2017-01-13 2016-10-07 2017-01-13 2016-11-06 2017-01-13 2016-12-21 2016-11-04 2017-01-25 2016-12-21 2018-04-25 Based Selection includes a detailed strategic to Varanasi) planning, design, and techno- economic feasibility study that sets out a broad planning framework.. CANW-1/IWAI/JMV/24 / Technical Support Services Component B: Institutional Consultant, Cluster 1 for Strengthening and improving Capacity augmentation of Quality And Cost- IBRD / P4740 the investment climate, Prior Open - International 2,907,692.32 0.00 Canceled 2017-01-12 2017-01-13 2017-02-02 2017-01-13 2017-03-18 2017-04-11 2017-04-15 2017-05-19 2017-05-15 2017-06-29 2017-06-19 2017-07-24 2018-07-24 navigational infrastructure of Based Selection vessel design and National Waterway-1 between construction framework Haldia to Allahabad (Jal Marg Vikas Project) CANW-1/IWAI/JMV/25 / Technical Support Services Consultant, Cluster 2 for Component A: Improving the Capacity augmentation of Quality And Cost- IBRD / P4740 navigability of NW-1 (Haldia Prior Open - International 1,927,692.30 2,828,322.71 Signed 2017-01-12 2017-01-13 2017-02-02 2017-01-13 2017-03-18 2017-06-28 2017-04-15 2017-05-19 2017-05-15 2017-06-29 2017-06-19 2017-11-02 2017-07-24 2017-11-08 2018-07-24 navigational infrastructure of Based Selection to Varanasi) National Waterway-1 between Haldia to Allahabad (Jal Marg Vikas Project) IWAI/WB/NW- 1/11/3/8/2016 / Consultancy Component A: Improving the for Communication Needs Quality And Cost- IBRD / P4740 navigability of NW-1 (Haldia Post Open - National 30,525.00 36,531.36 Signed 2017-01-16 2017-02-06 2017-03-22 2017-10-24 2017-04-19 2017-11-15 2017-05-19 2016-12-01 2017-06-23 2016-12-06 2017-07-28 2017-01-05 2018-07-28 Assessment Study for Based Selection to Varanasi) Capacity Augmentation of National Waterways -I CANW-1/JMV/IWAI/4 / Consultant for IWT Sector Component A: Improving the Development Strategy and Quality And Cost- IBRD / P4740 navigability of NW-1 (Haldia Prior Open - International 1,027,490.00 1,023,147.66 Signed 2017-03-21 2017-04-10 2017-04-11 2017-05-25 2017-06-01 2017-06-22 2015-03-13 2017-07-22 2017-06-22 2017-08-26 2017-06-30 2017-09-30 2015-04-24 2018-09-30 Market Development Study for Based Selection to Varanasi) Capacity Augmentation of National Waterway-1 CANW-1/JMV/IWAI/36 / Consultancy Services for Risk Component A: Improving the Quality And Cost- Assessment and Disaster IBRD / P4740 navigability of NW-1 (Haldia Post Open - International 384,838.06 102,190.58 Signed 2017-04-11 2017-04-07 2017-04-26 2017-08-16 2017-06-09 2017-11-14 2017-07-07 2017-12-12 2017-08-06 2018-02-09 2017-09-10 2018-02-27 2017-10-15 2018-04-04 2018-04-13 Based Selection Management Plan for National to Varanasi) Waterway-1 CANW-1/JMV/IWAI/37 / Consultancy for Asset Component A: Improving the Quality And Cost- Management Framework IBRD / P4740 navigability of NW-1 (Haldia Post Open - International 469,676.11 0.00 Canceled 2017-04-11 2017-06-07 2017-05-02 2017-06-15 2017-07-13 2017-08-12 2017-09-16 2017-10-21 2018-06-30 Based Selection Development for National to Varanasi) Waterway-1 IN-IWAI-26064-CS-LCS / Ship Model testing - Consultancy for Supporting Component A: Improving the Services for Ship Model Least Cost IBRD / 87520 navigability of NW-1 (Haldia Post Open - National 237,000.00 592,711.37 Signed 2017-08-24 2017-08-25 2017-09-14 2017-10-28 2017-11-25 2017-10-25 2017-12-25 2017-11-08 2018-01-29 2017-11-10 2018-03-05 2017-11-28 2018-09-01 Testing of Design of Inland Selection to Varanasi) Vessels for Capacity Augmentation of National Waterways-1 IN-IWAI-27893-CS-QCBS / Component A: Improving the Quality And Cost- Varanasi -Sahibganj - TSSC-I IBRD / P4740 navigability of NW-1 (Haldia Prior Open - International 1,456,840.00 1,289,831.05 Signed 2017-09-08 2017-09-29 2017-11-12 2017-11-10 2017-12-10 2017-12-13 2018-01-09 2018-01-08 2018-02-13 2018-01-19 2018-03-20 2018-01-22 2019-03-20 Based Selection Technical support services. to Varanasi) Page 4 IN-IWAI-28980-CS-QCBS / Smartphone Based Geo- Component A: Improving the spatial Technology Tool for Quality And Cost- IBRD / 87520 navigability of NW-1 (Haldia Post Open - International 100,000.00 100,000.00 Signed 2017-09-18 2017-04-07 2017-10-09 2017-11-22 2017-09-26 2017-12-20 2017-11-30 2018-01-19 2018-01-15 2018-02-23 2018-02-07 2018-03-30 2018-02-23 2019-03-30 Enhancing Monitoring & Based Selection to Varanasi) Execution capability of JMVP for NW-1 IN-IWAI-29587-CS-QCBS / Component A: Improving the Quality And Cost- ESIA,EMP,RAP for additional IBRD / 87520 navigability of NW-1 (Haldia Post Open - International 737,450.00 0.00 Canceled 2017-10-04 2017-10-09 2017-10-25 2017-11-03 2017-12-08 2018-03-06 2018-01-05 2018-05-02 2018-02-04 2018-06-05 2018-03-11 2018-04-15 2019-04-15 Based Selection interventions of JMVP to Varanasi) IN-IWAI-31158-CS-QCBS / Component A: Improving the Asset Management & Quality And Cost- Under IBRD / 87520 navigability of NW-1 (Haldia Prior Open - International 1,953,788.00 0.00 2017-10-05 2017-10-05 2017-10-05 2017-10-06 2017-11-04 2017-11-27 2017-11-06 2018-01-18 2017-11-07 2017-11-10 2018-11-10 operational frame work Based Selection Implementation to Varanasi) development for NW-1 IN-IWAI-25121-CS-QCBS / Asset Management - Component A: Improving the Consultancy Services foe Quality And Cost- IBRD / 87520 navigability of NW-1 (Haldia Post Open - International 608,624.00 0.00 Canceled 2017-08-24 2017-08-25 2017-09-14 2017-08-28 2017-10-28 2017-09-05 2017-11-25 2017-12-25 2018-01-29 2018-03-05 2019-03-05 Asset Management & Based Selection to Varanasi) Operational Framework development for NW-1 IWAI/TEST/06102017 / Test Component A: Improving the Quality And Cost- - Consultancy services for IBRD / 87520 navigability of NW-1 (Haldia Prior Open - International 1,000,000.00 0.00 Canceled 2017-10-06 2017-10-20 2017-12-19 2018-01-16 2018-02-15 2018-03-22 2018-04-26 2019-04-26 Based Selection IWAI to Varanasi) CANW-1/JMV/IWAI/35 / Component B: Institutional Consultancy Services for Study Strengthening and improving Quality And Cost- on the effect of navigational IBRD / P4740 the investment climate, Post Open - International 227,570.85 0.00 Canceled 2017-04-07 2017-03-06 2017-04-18 2017-06-01 2017-06-29 2017-07-29 2017-09-02 2017-10-07 2018-10-07 Based Selection activities on Dolphin in the vessel design and National Waterway - 1 construction framework Component B: Institutional CANW-1/JMV/IWAI/27 / Plan Strengthening and improving and Implementation support Quality And Cost- Pending IBRD / 87520 the investment climate, Post Open - International 529,578.95 0.00 2018-03-28 2018-04-18 2018-06-01 2018-06-29 2018-07-29 2018-09-02 2018-10-07 2019-10-07 for Commercialization of NW- Based Selection Implementation vessel design and 1 construction framework IN-IWAI-67912-CS-QCBS / Procurement of Consultancy Component A: Improving the Quality And Cost- Services for ESIA, EMP and RAP IBRD / 87520 navigability of NW-1 (Haldia Post Open - International 737,450.00 193,080.66 Signed 2018-06-29 2018-07-31 2018-07-20 2018-08-23 2018-09-02 2018-10-05 2018-09-30 2018-11-05 2018-10-30 2018-12-12 2018-12-04 2019-02-15 2019-01-08 2019-02-27 2019-07-07 Based Selection for additional Interventions on to Varanasi) NW-1 IN-IWAI-29231-CS-QCBS / RAP- Sahibganj - Resettlement Action Plan for Component A: Improving the the Multi Modal Terminal at Quality And Cost- IBRD / 87520 navigability of NW-1 (Haldia Post Open - National 54,500.00 0.00 Canceled 2017-09-20 2017-11-07 2017-10-11 2018-05-24 2017-11-24 2018-05-24 2017-12-22 2018-01-21 2018-02-25 2018-04-01 2019-04-01 Sahibganj for Jal Marg Vikas Based Selection to Varanasi) Project for the Capacity Augmentation of navigation on National Waterway -1 IN-IWAI-64340-CS-QCBS / TSSC-3 , Technical Component A: Improving the Quality And Cost- Supervisory Support IBRD / 87520 navigability of NW-1 (Haldia Prior Open - International 3,847,700.00 0.00 Canceled 2018-07-19 2018-08-09 2018-09-22 2018-10-20 2018-11-19 2018-12-24 2019-01-28 2020-01-28 Based Selection Consultancy for Dredging to Varanasi) Contracts IN-IWAI-55634-CS-QCBS / Component B: Institutional Setting up of Digital Control Strengthening and improving Centre (War Room) for Real Quality And Cost- IBRD / 87520 the investment climate, Post Open - National 36,881.17 0.00 Canceled 2018-03-28 2018-04-12 2018-04-18 2018-06-04 2018-06-01 2018-06-29 2018-07-29 2018-09-02 2018-10-07 2019-10-07 Time monitoring for Project Based Selection vessel design and under Capacity Augmentation construction framework of NW-1 IN-IWAI-71540-CS-QCBS / Component B: Institutional NINI - Framing of Guidelines Strengthening and improving to Develop National Inland Quality And Cost- IBRD / 87520 the investment climate, Post Open - International 109,891.62 0.00 Canceled 2018-08-01 2018-08-10 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2019-06-10 Navigation Institute (NINI) to Based Selection vessel design and be Centre of Excellence in IWT construction framework Sector IN-IWAI-64340A -CS-QCBS / TSSC-3, Technical Support Services Consultant Cum Project Management Consultant for Managing and Component A: Improving the Quality And Cost- Supervision of Contract on IBRD / 87520 navigability of NW-1 (Haldia Prior Open - International 7,883,361.00 8,650,936.89 Signed 2018-09-26 2018-09-27 2018-10-17 2018-11-02 2018-11-20 2019-02-19 2018-12-18 2019-05-31 2019-01-17 2019-07-09 2019-02-21 2019-12-12 2019-03-28 2020-01-06 2024-03-26 Based Selection Assured LAD by Dredging / to Varanasi) Bandalling as well as Erection and Maintenance of Navigation Aids in NW-1 ( River Ganga) IN-IWAI-31158A-CS-QCBS / Component A: Improving the Development Asset Quality And Cost- IBRD / 87520 navigability of NW-1 (Haldia Prior Open - International 1,953,788.00 1,655,220.83 Signed 2018-10-16 2018-10-16 2018-10-16 2018-11-15 2018-11-17 2018-11-18 2018-10-16 2018-11-21 2018-02-13 2019-06-30 Management Consultancy - Based Selection to Varanasi) operational frame work IN-IWAI-68596-CS-QCBS / Component A: Improving the Quality And Cost- Implementation of RAP for IBRD / 87520 navigability of NW-1 (Haldia Post Open - National 54,356.23 0.00 Canceled 2018-07-09 2018-07-30 2018-07-30 2018-08-23 2018-09-12 2018-10-10 2018-11-09 2018-12-14 2019-01-18 2019-07-17 Based Selection MMT at Sahibganj to Varanasi) IN-IWAI-68596-CS-QCBS-2 / Hiring of NGO for Implementation of Resettlement Action Plan Component A: Improving the Quality And Cost- (RAP) for the Multimodal IBRD / 87520 navigability of NW-1 (Haldia Post Open - National 71,898.00 45,390.23 Signed 2019-07-10 2019-08-07 2019-07-31 2019-08-13 2019-09-13 2019-10-01 2019-10-11 2019-11-18 2019-11-10 2019-11-29 2019-12-15 2019-12-09 2020-01-19 2019-12-16 2021-01-18 Based Selection Terminal at Sahibganj for Jal to Varanasi) Marg Vikas Project for the Capacity Augmentation of National Waterway -1 IN-IWAI-88532-CS-QCBS / Digitization- designing an Component A: Improving the End to End Digital Solution to Quality And Cost- IBRD / 87520 navigability of NW-1 (Haldia Post Open - International 670,293.00 0.00 Canceled 2018-11-30 2019-01-08 2018-12-21 2019-01-10 2019-02-07 2019-03-09 2019-04-13 2019-05-18 2019-11-14 enable Seamless and efficient Based Selection to Varanasi) trade through National Waterway-1. Page 5 Component B: Institutional IN-IWAI-205136-CS-QCBS / Strengthening and improving Project Management Quality And Cost- IBRD / 87520 the investment climate, Prior Open - International 1,415,000.00 0.00 Under Review 2020-11-24 2020-12-04 2020-12-15 2020-12-22 2021-01-28 2021-05-19 2021-02-25 2021-03-27 2021-05-01 2021-06-05 2024-06-04 Consultancy Services for JMVP Based Selection vessel design and including Arth Ganga Program construction framework IN-IWAI-211551-CS-QCBS / Comprehensive Consultancy Services for preparation of Component B: Institutional Detailed Project Report (DPR) Strengthening and improving Quality And Cost- for IWT sector development IBRD / 87520 the investment climate, Post Open - International 338,666.67 0.00 Canceled 2021-01-07 2021-01-18 2021-01-28 2021-02-11 2021-03-13 2021-06-08 2021-04-10 2021-07-09 2021-05-10 2021-07-09 2021-06-14 2021-07-19 2022-03-19 Based Selection for enhancement of socio- vessel design and economic activities in and construction framework around Ganga-Bhagirathi- Hooghly river system (NW-1) IN-IWAI-215458-CS-QCBS / Consultancy Service for preparation of Detailed Component A: Improving the Quality And Cost- Under Project Report (DPR) for the IBRD / 87520 navigability of NW-1 (Haldia Post Open - National 344,000.00 0.00 2021-01-27 2021-01-27 2021-02-17 2021-02-24 2021-04-02 2021-05-04 2021-04-30 2021-06-18 2021-05-30 2021-07-28 2021-07-04 2021-09-16 2021-08-08 2022-04-05 Based Selection Implementation work of renovation / to Varanasi) modernization of existing navigation lock at Farakka IN-IWAI-227401-CS-QCBS / Component B: Institutional Consultancy Service for Strengthening and improving Institutional Strengthening Quality And Cost- Under IBRD / 87520 the investment climate, Post Open - International 706,719.30 0.00 2021-04-12 2021-04-09 2021-05-03 2021-06-16 2021-07-31 2021-08-30 2021-10-04 2021-11-08 2023-11-08 and Capacity Building of Based Selection Implementation vessel design and Inland Waterways Transport construction framework Sector in India IN-IWAI-235475-CS-QCBS / Engagement of an Organization for providing Component B: Institutional Consultancy Services for Strengthening and improving Quality And Cost- Under Stakeholder Engagement, IBRD / 87520 the investment climate, Post Open - National 709,333.33 0.00 2021-06-01 2021-06-14 2021-06-22 2021-07-22 2021-08-05 2021-09-02 2021-10-02 2021-11-06 2021-12-11 2022-12-11 Based Selection Implementation Livelihood Support and vessel design and Communication for IWT construction framework Promotion on NW-1 under the Arth Ganga Program of JMVP IN-IWAI-246165-CS-QCBS / Engagement of a professional Component B: Institutional Communications Agency to Strengthening and improving Quality And Cost- Under develop and implement a IBRD / 87520 the investment climate, Post Open - National 313,268.56 0.00 2021-08-02 2021-08-09 2021-08-23 2021-10-06 2021-11-03 2021-12-03 2022-01-07 2022-02-11 2023-02-11 Based Selection Implementation strategic communications vessel design and approach for the Jal Marg construction framework Vikas Projects IN-IWAI-246888-CS-QCBS / Direct RFP - Comprehensive Consultancy Services for preparation of Detailed Component A: Improving the Project Report (DPR) for IWT Quality And Cost- Under IBRD / 87520 navigability of NW-1 (Haldia Post Open - National 640,000.00 0.00 2021-08-09 2021-08-13 2021-08-30 2021-09-08 2021-10-13 2021-11-10 2021-12-10 2022-01-14 2022-02-18 2023-02-18 Sector Development for Based Selection Implementation to Varanasi) enhancement of Socio- economic activities in and around Ganga – Bhagirathi - Hoogly river system (NW-1) IN-IWAI-255177-CS-QCBS / Direct RFP - TSSC cum PMC for managing and supervising Component A: Improving the Quality And Cost- Pending the EPC Contract for IMT IBRD / 87520 navigability of NW-1 (Haldia Post Open - National 740,568.00 0.00 2021-09-27 2021-10-18 2021-12-01 2021-12-29 2022-01-28 2022-03-04 2022-04-08 2023-04-08 Based Selection Implementation Kalughat for Capacity to Varanasi) Augmentation of National Waterway-1 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWAI-37888-CS-CDS / Selection of consultant for Component A: Improving the study on the effect of IBRD / 87520 navigability of NW-1 (Haldia Post Direct Selection Direct 74,310.00 75,439.29 Signed 2017-11-29 2017-11-29 2017-12-10 2017-12-01 2018-02-13 2017-12-20 2018-09-30 navigational activities on to Varanasi) Dolphin in National Waterway- 1 IN-IWAI-68596-CS-CDS / Component A: Improving the Implementation of RAP for IBRD / 87520 navigability of NW-1 (Haldia Post Direct Selection Direct 54,356.23 0.00 Canceled 2019-03-29 2019-04-08 2019-06-12 2019-12-09 MMT at Sahibganj to Varanasi) Component B: Institutional IN-IWAI-158167-CS-CDS / Strengthening and improving Consultancy Services for IBRD / 87520 the investment climate, Post Direct Selection Direct 5,000.00 4,631.21 Signed 2020-02-26 2020-02-02 2020-03-07 2020-02-07 2020-05-11 2020-03-03 2020-11-07 Messaging Workshop for IWAI vessel design and officers construction framework IN-IWAI-162537-CS-CDS / Independent Quality Component B: Institutional Inspection for the works of Strengthening and improving New Navigation lock at IBRD / 87520 the investment climate, Post Direct Selection Direct 28,571.73 27,406.90 Signed 2020-03-11 2020-01-03 2020-03-21 2020-01-10 2020-05-25 2020-07-13 2020-11-21 Farakka, MMT haldia, MMT vessel design and Varanasi & MMT Sahibganj by construction framework NTCPWC Component B: Institutional IN-IWAI-208579-CS-CDS / Strengthening and improving Engagement of M/s PwC for IBRD / 87520 the investment climate, Post Direct Selection Direct 24,000.00 14,697.87 Signed 2020-12-14 2020-12-02 2020-12-24 2020-12-03 2021-02-27 2021-01-20 2021-03-31 one resource person vessel design and construction framework IN-IWAI-230396-CS-CDS / Study/consultancy for implementation of self- propelled pontoon technique Component A: Improving the in floating pontoon bridges Under IBRD / 87520 navigability of NW-1 (Haldia Post Direct Selection Direct 20,000.00 0.00 2021-04-26 2021-07-08 2021-05-06 2021-08-06 2021-07-10 2022-01-06 installed across river Ganga in Implementation to Varanasi) NW-1 for smooth passage of inland vessels on a pilot project basis as a replacement to the conventional kulfi system. Page 6 IN-IWAI-245524-CS-CDS / EIA Study and preparation of Component A: Improving the Under EMP for carrying out Channel IBRD / 87520 navigability of NW-1 (Haldia Post Direct Selection Direct 27,953.33 0.00 2021-08-10 2021-07-29 2021-08-20 2021-08-09 2021-10-24 2022-04-22 Implementation Stabilization Works at 07 to Varanasi) locations on NW-1 IN-IWAI-248582-CS-CDS / Technical Assistance for Channel stabilization Works Component A: Improving the for development of IBRD / 87520 navigability of NW-1 (Haldia Post Direct Selection Direct 680,000.00 0.00 Under Review 2021-09-07 2021-09-24 2021-09-17 2021-11-21 2022-05-20 Navigational Channel with Eco- to Varanasi) friendly techniques at 17 Locations on NW-1 Page 7