Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) I. General 2. Bank’s approval Date of the procurement Plan [Date of General Procurement Notice 3. Period covered by this procurement plan: April 2015 to March 2016 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: PROCUREMENT METHODS, APPLICABILITY & PRIOR REVIEW Expenditure Category Procurement Method Applicability of Procurement Method Prior Review ICB -more than US$ 3.0 million all contracts NCB more than US$ 50,000 and up to US$ 3.0 million first three con Goods, IT Services & NS Up to US$ 50,000 first two cont Non-Consulting Services DC as per paragraph 3.7 of Procurement Guidelines all contracts a Framework as per paragraph 3.6 of Procurement Guidelines First contract Agreements ICB more than US$ 40.0 million all contracts first three contr NCB equal to or over US$ 50,000 (but less than US$ 10,000,000) or over US$ 5, Civil Works NS less than US$ 50,000 first two cont DC as per paragraph 3.7 of Procurement Guidelines all contracts CQS less than US$ 300,000 Consultant first two cont Firms Services QCBS / QBS / FBS / to or over US all LCS July 9, 2010 SSS as per paragraph 3.8 to 3.11 of Consultant Guidelines all contracts Individuals SIC as per paragraph 5.1 to 5.6 of Consultant Guidelines contracts ove 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements: No ICB works packages 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) SSUPSW PROCUREMENT PLAN Ref. Contract Estima Estim Procur Pri Bid Bid / Cont Delive Remar No. Description ted ated ement or Ad Prop ract ry / ks Cost Cost Metho Rev ver osal Sign Comp (INR) (USD d iew t Ope ing letion ) ning Date Date Date GOODS GD-1 Goods for SSUPSW 2,600,0 40,00 NS (var (vari (vari (varies Multipl head office 00 0 ies) es) es) ) e contract s; to be split as necessa ry GD- Outreach & Therapy 285,000 4,384, ICB Yes Ma Apr- May Dec- Re- 2.1 Vans (38 vehicles) ,000 615 r- 2015 - 2015 Adverti 15 2015 sement GD- Response Vans (38 38,000, 584,6 ICB Yes Apr Jun- Dec- Jun- 2.2 vehicles) 000 15 -15 2015 2015 2016 GD-3 Physiotherapy and 30,000, 461,5 NCB Yes Ma May- Jul- Dec- For 38 Medical Equipment 000 38 r- 2015 2015 2015 Buniya 15 d GD-4 Physiotherapy : 17,000, 261,5 NCB Yes Ma May- Jul- Dec- Centers Sports Equipment 000 38 r- 2015 2015 2015 operatin 15 g from GD-5 Equipment for 10,000, 153,8 NCB/N No Ma May- Jul- Dec- GOB Buniyad Centers 000 46 S r- 2015 2015 2015 premise (Misc items like toys, 15 s (Total refrigerator, utensils Budget etc.) of INR 570 Lakhs July 9, 2010 is segrega ted, will be revised if require d for GD 3 - 5 items. Multipl e contract s under GD 5 WORKS CW-1 Renovations of 95,000, 1,461, NCB/N (var May- Aug- Dec- Multipl existing GOB 000 538 S ies) 2015 2015 2015 e premises to serve as contract Buniyad Centers s; to be split as necessa ry CW-2 Construction of 380,000 5,846, NCB Yes Aug- Dec- Dec- Assumi Buniyad Centers ,000 154 2015 2015 2016 ng 18 month work period NON- CONSULTING SERVICES CONSULTANT SERVICES CS- MIS (design, 75,000, 1,153, QCBS Yes No May- Dec- Dec- For 1_SSU development & 000 846 v- 2014 2014 2019 Project PSW management) 13 duratio n CS-1 Technical Design of 40,000, 615,3 QCBS Yes Jan Mar- May Dec- 6 weeks Buniyad Center & 000 85 -15 2015 - 2016 for Construction 2015 design Supervision and 18 months for supervi sion. Budget revised to include constru ction supervi sion July 9, 2010 CS-2 Agency to hire staff 10,000, 153,8 QCBS Yes No Apr- Sep- Aug- complet for Buniyad Centers / 000 46 v- 2014 2014 2017 ed Outreach & Therapy 13 Vans CS-3 Impact Evaluation 30,000, 461,5 QCBS Yes For (development & 000 38 baseline implementation) , midline and end-line surveys and analysis ; for Project duratio n CS-4 Training Strategy & 2,500,0 38,46 QCBS Yes No Apr- Jan- Jul- complet Needs Assessment 00 2 v- 2014 2015 2015 ed (review) 13 CS-5 HR & Performance 5,000,0 76,92 QCBS Yes Assumi Management Systems 00 3 ng 1 (review) year assignm ent CS-6 Communication 5,000,0 76,92 QCBS Yes No Apr- Feb- Dec- complet Strategy & Materials 00 3 v- 2014 2014 2015 ed (design & 13 development) CS-7 External Audit (for 400,000 6,154 LCS No Assumi FY 2013-14 / 2014- ng 15 Project accounts) assignm ent coverin g2 fiscal years (actual contract for 1 year) CS-8 Internal Audit (for 2,000,0 30,76 LCS No Assumi FY 2014-15 / FY 00 9 ng 2015-16 quarterly assignm sample audits at ent district and state) coverin g2 fiscal years (actual contract for 2 years) CS-9 Hiring of Consultant 2,000,0 30,76 SSS/SI Yes Assumi 00 9 C ng 1 year July 9, 2010 assignm ent Totals Estimated 1,029,5 15,83 Costs: 00,000 8,462 INR / 65 USD July 9, 2010 PROCUREMENT India : India: Bihar Integrated Social Protection Strengthening Project PLAN General Information Country: India Banks Approval Date of the Original Procurement Plan: 2016-11-14 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-05-16 Project ID: P118826 GPN Date: Project Name: India: Bihar Integrated Social Protection Strengthening Project Loan / Credit No: IDA / 53490 Executing Agency(ies): BIHAR RURAL DEVELOPMENT SOCIETY, State Society for Ultra Poor and Social Welfare WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CW 2/4 / Construction of Strengthening Outreach and Buniyad centres Arwal Sadar Single Stage - Two IDA / 53490 Social Protection Service Prior Request for Bids Open - National 853,263.00 0.00 Under Review 2016-11-25 2016-11-25 2016-11-25 2016-11-26 2016-12-12 2017-01-05 2018-01-05 District Arwal, Haspura and Envelope Delivery Barun District Aurangabad CW-2/13 / Contruction of Strengthening Outreach and Single Stage - Two Buniyad Centres at Dumraon, IDA / 53490 Social Protection Service Post Request for Bids Open - National 604,338.00 534,235.48 Signed 2017-01-20 2017-01-20 2017-01-20 2017-01-20 2016-11-28 2017-01-20 2017-01-24 2018-01-15 Envelope Buxar Sadar District Buxur Delivery CW-2/1 / Construction of Buniyad Centers at Araia Sadar, Strengthening Outreach and Single Stage - Two Forbisganj Dist Araria IDA / 53490 Social Protection Service Post Request for Bids Open - National 851,202.00 766,740.37 Signed 2017-01-20 2017-01-20 2017-01-20 2017-01-20 2016-12-13 2017-01-20 2016-12-24 2018-01-20 Envelope Kishanganj Sadar District Delivery Kishanganj CW-2/18 / Construction of Strengthening Outreach and Single Stage - Two Bhahadurpur, Benipur District IDA / 53490 Social Protection Service Post Request for Bids Open - National 617,942.00 554,819.79 Signed 2017-02-01 2016-08-25 2017-02-01 2017-02-01 2016-11-30 2017-02-01 2016-12-24 2017-02-01 2016-12-24 2018-01-27 Envelope Darbhanga Delivery CW-2/5 / Construction of Strengthening Outreach and Buniyad Center at Single Stage - Two Pending IDA / 53490 Social Protection Service Post Request for Bids Open - National 896,094.00 0.00 2017-03-02 2017-03-02 2017-03-02 2017-03-02 2017-03-02 2018-02-25 Shergati,Tekari & Neemchak Envelope Implementation Delivery Khijar Sarai Dstrict Gaya. CW-2/26 / Construction of Strengthening Outreach and Single Stage - Two Pending Buniayd centre at Hatua, IDA / 53490 Social Protection Service Post Request for Bids Open - National 913,516.00 0.00 2017-03-02 2017-03-02 2017-03-02 2017-03-02 2017-03-02 2018-02-25 Envelope Implementation Gopalganj District Goplaganj. Delivery CW-2/9 / Construction Of Strengthening Outreach and Buniayd centre at Khaira District Single Stage - Two Under IDA / 53490 Social Protection Service Post Request for Bids Open - National 934,461.00 0.00 2017-03-02 2016-08-25 2017-03-02 2017-03-02 2017-03-02 2017-03-02 2018-02-25 Jamui, Halsi District Lakhisarai, Envelope Implementation Delivery sadar District Sheikpura. CW-2/2 / Construction of Strengthening Outreach and Buniyad Centers at Katihar Single Stage - Two IDA / 53490 Social Protection Service Post Request for Bids Open - National 928,225.00 825,456.05 Signed 2017-03-02 2016-08-25 2017-03-02 2017-03-02 2016-11-22 2017-03-02 2017-03-02 2016-12-24 2018-02-25 Sadar, Manihari , Barsoi District Envelope Delivery Katihar CW-2/22 / Construction of Strengthening Outreach and Single Stage - Two Bunyad Centre at Musahari and IDA / 53490 Social Protection Service Post Request for Bids Open - National 597,227.00 576,028.33 Signed 2017-03-02 2016-08-25 2017-03-02 2017-03-02 2017-03-02 2016-12-24 2017-03-02 2016-12-24 2018-02-25 Envelope khudani District Muzaffarpur Delivery CW-2/6 / Construction of Strengthening Outreach and Single Stage - Two Buniayd Centre at Hisua and IDA / 53490 Social Protection Service Post Request for Bids Open - National 520,468.00 537,086.87 Signed 2017-03-02 2016-08-25 2017-03-02 2017-03-02 2016-11-28 2017-03-02 2016-12-24 2017-03-02 2016-12-24 2018-02-25 Envelope Rajauli District Nawada Delivery CW-2/23 / Construction of Strengthening Outreach and Buniyad Centre at Piprahi District Single Stage - Two IDA / 53490 Social Protection Service Post Request for Bids Open - National 1,262,716.00 1,054,161.85 Signed 2017-03-02 2016-08-25 2017-03-02 2017-04-13 2016-11-28 2017-04-13 2016-12-13 2017-04-13 2016-12-24 2018-04-08 Sheohar, Belsand, Dumra,Pupri Envelope Delivery District Sitamadhi. CW-2/25 / Construction of Strengthening Outreach and Buniayd centre at Bairia, Bagha Single Stage - Two IDA / 53490 Social Protection Service Post Request for Bids Open - National 902,615.00 842,671.65 Signed 2017-03-02 2016-08-25 2017-03-02 2017-03-02 2016-11-28 2017-03-02 2016-12-24 2017-03-02 2016-12-24 2018-02-25 and Gaunaha District West Envelope Delivery Champaran. CW-2/31 / Construction of Strengthening Outreach and Buniyad Centers at Single Stage - Two Pending IDA / 53490 Social Protection Service Post Request for Bids Open - National 1,184,615.00 0.00 2017-03-22 2017-03-22 2017-03-22 2017-03-23 2017-03-23 2018-03-18 BAKHTIYARPUR, MASAUDI, Envelope Implementation Delivery MANER, VIKRAM Dist - PATNA. CW-2/27 / Construction of Strengthening Outreach and Buniyad centre in Saran District Single Stage - Two Pending IDA / 53490 Social Protection Service Post Request for Bids Open - National 913,516.00 0.00 2017-03-22 2017-03-22 2017-03-22 2017-03-22 2017-03-22 2017-09-18 for Marhaura, Saran Sadar and Envelope Implementation Delivery Digwarha Block. GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Social Protection GD-2.1 / MOBILE OUTREACH Systems and Capacity & THERAPY VANS, THERAPY Single Stage - One IDA / 53490 Strengthening Outreach and Prior Request for Bids Open - International N 0.00 4,628,597.60 Signed 2016-02-09 2016-04-25 EQUIPMENT AND ANCILLARY Envelope Social Protection Service GOODS Delivery Strengthening Social Protection NCB GD3 / Physiotherapy, Systems and Capacity Audiological, Optical, Exercise Single Stage - One IDA / 53490 Strengthening Outreach and Prior Request for Bids Open - National N 2,000,000.00 1,165,749.44 Signed 2016-08-12 2016-11-15 Therapy Equipment and Medical Envelope Social Protection Service Consumable - NCB GD3 Delivery Strengthening Social Protection GD-1- SSPMIS / Procurement of Systems and Capacity Non-IT equipment & Request for IDA / 53490 Strengthening Outreach and Prior Open - International N 0.00 57,907.17 Signed 2016-01-13 refurbishment of server room for Quotations Social Protection Service SSPMIS Delivery Page 1 Strengthening Social Protection GD- 5 / Supply and Installation Systems and Capacity Single Stage - One of IT Hardware Software & IDA / 53490 Strengthening Outreach and Prior Request for Bids Open - National N 0.00 1,033,769.40 Signed 2016-03-07 2016-04-04 Envelope Ancillary Goods Social Protection Service Delivery GD-2 / Procurement of Strengthening Outreach and Desktops, Printers, Scanner etc Single Stage - One IDA / 53490 Social Protection Service Prior Request for Bids Open - National 692,308.00 0.00 Under Review 2016-11-23 2016-11-28 2016-11-28 2016-12-07 2017-01-09 2017-01-27 2017-02-08 2017-03-15 2017-09-11 for State, District and Block level Envelope Delivery officials of BRDS GD-3 / Procurement of Tally Strengthening Outreach and Single Stage - One Under Software and related services for IDA / 53490 Social Protection Service Prior Request for Bids Open - National 253,846.00 0.00 2016-11-23 2016-11-28 2016-11-28 2016-12-08 2017-01-09 2017-01-30 2017-02-08 2017-05-02 2017-03-15 2017-07-13 Envelope Implementation BRDS Delivery Strengthening Outreach and GD-1 / Goods for SSUPSW Request for Single Stage - One IDA / 53490 Social Protection Service Post Open - National 2,039.00 971.55 Signed 2016-12-15 2016-12-15 2016-09-09 2016-12-15 head office (Water Purifier) Quotations Envelope Delivery GD-9 / Invitation of Quotation for Strengthening Outreach and Request for Single Stage - One Printing & Supply of IEC Material IDA / 53490 Social Protection Service Post Open - National 9,239.00 0.56 Signed 2016-12-26 2016-12-26 2016-12-23 2017-01-13 Quotations Envelope for Buniyad Centre at SSUPSW. Delivery GD-10 / Invitation of Quotation for Printing, Supply and Strengthening Outreach and Placement of Outdoor Tools Request for Single Stage - One IDA / 53490 Social Protection Service Post Open - National 9,692.00 7,853.16 Signed 2016-12-27 2016-12-27 2016-12-23 2017-01-09 (Hoarding, Glow Sign Board and Quotations Envelope Delivery Standee) for Branding of Buniyad Centre in 14 Districts of Bihar. GD-11 / Invitation of Quotation Strengthening Outreach and Request for Single Stage - One for Printing & Supply of Diary & IDA / 53490 Social Protection Service Post Open - National 13,110.00 1.82 Signed 2016-12-27 2016-12-27 2016-12-14 2017-01-03 Quotations Envelope Calendar' 2017 at SSUPSW Delivery GD-4 / Procurement and Strengthening Social Protection Request for Single Stage - One Under Installation of 50 KVA, Diesel IDA / 53490 Post Open - National 8,333.33 9,861.18 2017-03-05 2017-04-21 2017-10-18 Systems and Capacity Quotations Envelope Implementation generator for BRDS State Office. GD-12 / Invitation of Quotation for supply and Installation of Desktop with UPS and All in One Strengthening Social Protection Request for Single Stage - One IDA / 53490 Post Open - National 49,230.00 0.00 Canceled 2017-01-14 2017-02-17 2017-03-03 printer at Buniyad Centre (a Systems and Capacity Quotations Envelope social care service centre) in 26 districts (DPMU) and SPMU. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NCS- 1 / Engagement of a Strengthening Social Protection Manpower Agency to support Systems and Capacity SSUPSW for the 101 Social Single Stage - One IDA / 53490 Strengthening Outreach and Prior Request for Bids Open - National N 0.00 103,288.79 Signed 2016-10-03 2016-12-19 Care Service Centre (Buniyad) Envelope Social Protection Service and 38 Mobile Outreach & Delivery Therapy Vans NCS-3 / Engagement of security Strengthening Outreach and agency to support SSUPSW for Single Stage - One Under IDA / 53490 Social Protection Service Prior Request for Bids Open - National 923,077.00 0.00 2016-11-23 2016-11-28 2016-11-28 2016-12-07 2017-01-09 2017-02-08 2017-03-15 2017-09-11 Buniyad Centre and Mobile Envelope Implementation Delivery Therapy Van. Strengthening Outreach and NCS-7 / Hiring of Documentarist Request for Single Stage - One IDA / 53490 Social Protection Service Post Open - National 15,385.00 7,699.11 Signed 2016-12-26 2016-12-26 2016-12-21 2017-01-02 or Short Film Maker Quotations Envelope Delivery NCS-8 / Hiring of manpower Strengthening Social Protection Single Stage - One Pending supply agency to provide IDA / 53490 Post Request for Bids Open - National 49,230.00 0.00 2017-03-27 2017-04-01 2017-04-15 2017-05-15 2017-06-01 2018-05-27 Systems and Capacity Envelope Implementation outsource support staff in BISPS. NCS-5 / Hiring of Event Strengthening Outreach and Request for Single Stage - One Pending management Agency for various IDA / 53490 Social Protection Service Post Open - National 49,321.00 0.00 2017-05-06 2017-06-27 2017-08-26 Quotations Envelope Implementation activity . Delivery CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Social Protection FOLDER # 4 / [SSUPSW] -Pkg Systems and Capacity Quality And Cost- NCS-1 : Recruitment Support IDA / 53490 Strengthening Outreach and Prior Open - International N 0.00 192,225.62 Signed 2014-08-26 2014-09-10 Based Selection Agency Social Protection Service Delivery Strengthening Social Protection Systems and Capacity FOLDER # 7 / [BRDS] - CS-1- Quality And Cost- IDA / 53490 Strengthening Outreach and Prior Open - International N 0.00 77,667.19 Signed 2015-01-30 2015-02-02 Recruitment Support Agency Based Selection Social Protection Service Delivery Strengthening Social Protection CS-2-BRDS / Consultancy Systems and Capacity Quality And Cost- Under Services for Training Needs IDA / 53490 Strengthening Outreach and Prior Open - International N 38,462.00 39,395.35 2015-07-27 2015-09-02 Based Selection Implementation Assessment (BRDS) Social Protection Service Delivery Strengthening Social Protection CS-4-BRDS / Communications Systems and Capacity Quality And Cost- Under Strategy and Materials (Design & IDA / 53490 Strengthening Outreach and Prior Open - International N 76,923.00 67,518.83 2015-08-05 2015-09-02 Based Selection Implementation Development) Social Protection Service Delivery Page 2 Strengthening Social Protection CS-5-BRDS / Agency for Systems and Capacity Financial Management Systems Quality And Cost- Under IDA / 53490 Strengthening Outreach and Prior Open - International N 76,923.00 43,068.24 2015-09-07 2016-07-13 (referred as CS-8 in old Based Selection Implementation Social Protection Service procurement plan) Delivery FOLDER # 3 / [SSUPSW]-Pkg CS-1-Design, Development, Strengthening Social Protection Implementation, Operation and Systems and Capacity Quality And Cost- Maintenance of: Transactional IDA / 53490 Strengthening Outreach and Prior Open - International N 0.00 862,601.38 Signed 2015-01-05 2015-01-16 Based Selection Management Information System Social Protection Service for the Social Security Pension Delivery (SSPMIS) Strengthening Social Protection FOLDER # 5 / [SSUPSW]-Pkg Systems and Capacity CS-3 : Training Needs Quality And Cost- IDA / 53490 Strengthening Outreach and Prior Open - International N 0.00 33,742.36 Signed 2015-02-18 2015-02-24 Assessment and Development of Based Selection Social Protection Service Training Strategy Delivery FOLDER # 6 / [SSUPSW] -Pkg Strengthening Social Protection CS-5 : Development of an Systems and Capacity Quality And Cost- Advocacy and Communication IDA / 53490 Strengthening Outreach and Prior Open - International N 0.00 67,996.91 Signed 2014-11-24 2014-12-05 Based Selection Strategy and Design of IEC Social Protection Service Materials Delivery Strengthening Social Protection Folder # 9 / Design Consultancy Systems and Capacity and Supervision Construction Quality And Cost- IDA / 53490 Strengthening Outreach and Prior Open - International N 0.00 422,346.13 Signed 2015-06-24 2015-07-01 Contract for the building of the Based Selection Social Protection Service Buniyad Centres-(BSBCCL) Delivery CS-11 / Roll out of Strengthening Outreach and Quality And Cost- IEC/communication strategy and IDA / 53490 Social Protection Service Prior Open - National 923,077.00 0.00 Under Review 2016-11-29 2016-11-29 2016-11-29 2016-12-01 2016-12-14 2017-01-04 2017-01-24 2017-02-03 2017-08-02 Based Selection Implementation. Delivery CS-12 / Development of Training Strengthening Outreach and Quality And Cost- Under & Learning material and Roll Out IDA / 53490 Social Protection Service Prior Open - National 923,077.00 0.00 2016-12-01 2016-12-20 2016-12-22 2016-12-27 2017-01-20 2017-02-17 2017-03-04 2017-03-21 2017-04-18 2020-04-17 Based Selection Implementation of Training Statergy Delivery INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Social Protection NIL / Hiring of a consultant for Systems and Capacity Individual Consultant social inclusion of persons with IDA / 53490 Strengthening Outreach and Prior Open N 33,333.00 18,840.29 Signed 2015-05-04 2015-06-01 Selection disabilities Social Protection Service Delivery CS -6 / Tally Assessment Test Strengthening Outreach and for co-opting of IAY accountants IDA / 53490 Social Protection Service Prior Direct Selection Direct 46,154.00 22,265.30 Signed 2016-12-19 2016-12-23 2016-12-21 2017-01-02 2017-01-12 2018-01-01 in BRDS. Delivery Page 3