Procurement Plan I. General 1. Project Information Country: Tanzania Project Name: Second Water Sector Support Project (WSSP II) Project ID: P150361 2. Project Implementation Agency: Ministry of Water and Irrigation Dar es Salaam Water Supply and Sewerage Authority Dar es Salaam Water Supply ans Sewerage Corporation 3. Date of the Procurement Plan: April 2017 4. Period Covered by this Procurement Plan: First 18 Months II. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works and Non-Consulting Services Procurement Approaches and Methods (US$ millions) Prior Review Category (US$ millions) Open International Open Request for National Quotation (RfQ) Works ≥ 10 ≥ 15.0 < 15 ≤ 0.2 Goods, IT, and non- ≥2 ≥5 <5 ≤ 0.1 consulting services B. Consulting Services Category Prior Review Short List of National Consultants (US$ million) (US$ millions) Consulting Services Engineering and Construction Supervision Consultants (Firms) ≥1 ≤ 0.3 ≤ 0.3 Individual Consultants ≥ 0.3 NA. NA. [Overall Project Procurement Risk is SUBSTANTIAL] Notes: Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National News Paper(s) of wide circulation and/or Regional News Paper(s). 1 PROCUREMENT Tanzania : Second Tanzania Water Sector Support Project PLAN General Information Country: Tanzania Banks Approval Date of the Original Procurement Plan: 2017-04-13 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-06-26 Project ID: P150361 GPN Date: Project Name: Second Tanzania Water Sector Support Project Loan / Credit No: IDA / 59490, IDA / 59500, IDA / V0310 Executing Agency(ies): Dar Es Salaam Water Supply and Sewarage Authority, Ministry of Water and Irrigation, Dar es Salaam Water and Sewerage Corporation WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-12669-CW-RFB / Drilling Works for Ground Water IDA / 59490 Component 1: Integrated Water Single Stage - One Pending Monitoring Network in Wami- Post Request for Bids Open - National 1,000,000.00 0.00 2017-09-01 2017-09-06 2017-10-18 2017-11-17 2017-12-22 2018-06-20 IDA / 59500 Resources Management (IWRM) Envelope Implementation Ruvu and Internal Drainage Basins TZ-MOW-12670-CW-RFB / Construction of office and water laboratory buildings for Wami- Ruvu Basin Water Board (BWB) Headquarter at Morogoro and IDA / 59490 Component 1: Integrated Water Single Stage - One Pending Post Request for Bids Open - National 1,000,000.00 0.00 2018-06-04 2018-06-09 2018-07-21 2018-08-20 2018-09-24 2019-03-23 Water Users Association (WUA) IDA / 59500 Resources Management (IWRM) Envelope Implementation Offices at Msowero and rehabilitation and extension of office building for Wami-Ruvu BWB in Dodoma. TZ-MOW-12671-CW-RFB / Civil Works Construction and IDA / 59490 Component 1: Integrated Water Single Stage - One Pending Installation of Water Resources Post Request for Bids Open - National 2,750,000.00 0.00 2018-07-02 2018-07-07 2018-08-18 2018-09-17 2018-10-22 2019-04-20 IDA / 59500 Resources Management (IWRM) Envelope Implementation Monitoring Gauges in all the nine Basins in Tanzania TZ-MOW-12673-CW-RFB / Construction of Office Block for IDA / 59490 Component 1: Integrated Water Single Stage - One Pending the Proposed Water Resources Post Request for Bids Open - National 750,000.00 0.00 2019-03-04 2019-03-09 2019-04-20 2019-05-20 2019-06-24 2019-12-21 IDA / 59500 Resources Management (IWRM) Envelope Implementation Centre of Excellency (COE) in Dar es Salaam TZ-DAWASA-6487-CW-RFB / Construction of water Supply IDA / 59490 Component 2: Dar es Salaam Single Stage - One Distribution Networks Part 1 from Prior Request for Bids Open - International 45,000,000.00 0.00 Canceled 2017-02-28 2017-03-05 2017-05-04 2017-06-18 2017-07-23 2018-01-19 IDA / 59500 Water Supply Improvement Envelope University Reservoir to Bagamoyo TZ-DAWASCO-10088-CW-RFB / Construction of water supply IDA / 59490 Component 2: Dar es Salaam Single Stage - One Prior Request for Bids Open - International 45,000,000.00 0.00 Canceled 2017-04-19 2017-04-24 2017-06-05 2017-07-05 2017-08-09 2019-01-31 distribution network Part 1. (from IDA / 59500 Water Supply Improvement Envelope University reservoir to Bagamoyo) TZ-DAWASCO-25524-CW-RFB / Construction of Water Supply IDA / 59490 Component 2: Dar es Salaam Single Stage - One Under Distribution Network Part I, from Prior Request for Bids Open - International 45,000,000.00 0.00 2017-09-25 2018-05-25 2017-09-30 2018-06-05 2017-11-11 2017-12-11 2018-01-15 2019-07-09 IDA / 59500 Water Supply Improvement Envelope Implementation University Reservoir to Bagamoyo Town TZ-DAWASCO-10084-CW-RFB / Construction of Decentralized Fecal Sludge Management IDA / 59490 Component 2: Dar es Salaam Single Stage - One Pending (FSM) treatment (about 50 Post Request for Bids Open - National 600,000.00 0.00 2018-05-15 2018-05-20 2018-07-01 2018-07-31 2018-09-04 2019-09-04 IDA / 59500 Water Supply Improvement Envelope Implementation units@USD120,000 per unit starting with 10 units first phase)(C2-W04) TZ-DAWASCO-10078-CW-RFB / IDA / 59490 Component 2: Dar es Salaam Single Stage - One Pending Construction of Public toilets in Post Request for Bids Open - National 20,000.00 0.00 2018-06-15 2018-06-20 2018-08-01 2018-08-31 2018-10-05 2019-04-03 IDA / 59500 Water Supply Improvement Envelope Implementation selected areas (C2-W08) TZ-DAWASCO-10079-CW-RFB / Construction of Condominium IDA / 59490 Component 2: Dar es Salaam Single Stage - One Pending Post Request for Bids Open - National 1,500,000.00 0.00 2018-06-20 2018-06-25 2018-08-06 2018-09-05 2018-10-10 2019-10-10 sewerage (about 250 IDA / 59500 Water Supply Improvement Envelope Implementation houses/scheme (C2-W07) TZ-DAWASCO-10081-CW-RFB / Construction of transfer stations IDA / 59490 Component 2: Dar es Salaam Single Stage - One Pending Post Request for Bids Open - National 400,000.00 0.00 2018-06-29 2018-07-04 2018-08-15 2018-09-14 2018-10-19 2019-10-19 (about 30 units@USD40,000 per IDA / 59500 Water Supply Improvement Envelope Implementation unit) first phase (C2-W05) TZ-DAWASCO-10083-CW-RFB / Construction of off-grid water supply small piped schemes to IDA / 59490 Component 2: Dar es Salaam Single Stage - One Pending Post Request for Bids Open - National 2,500,000.00 0.00 2018-06-27 2018-07-02 2018-08-13 2018-09-12 2018-10-17 2020-04-09 serve about 100,000 people @ IDA / 59500 Water Supply Improvement Envelope Implementation USD 50 per capita (several packages-first phase) (C2-W06) TZ-DAWASA-6497-CW-RFB / Construction of Mbezi Beach IDA / 59490 Component 3: Dar es Salaam Single Stage - One Pending Prior Request for Bids Open - International Y 21,800,000.00 0.00 2018-04-20 2018-07-06 2018-07-06 2018-04-25 2018-09-04 2018-10-04 2018-11-08 2020-05-01 Waste Water Treatment Plant IDA / 59500 Sanitation Improvement Envelope Implementation (Design and Build Operation) TZ-DAWASA-55914-CW-RFB / IDA / 59490 Component 3: Dar es Salaam Single Stage - One Under Construction of Pumping station Prior Request for Bids Open - International 41,100,000.00 0.00 2018-04-19 2018-04-24 2018-06-08 2018-07-08 2018-08-12 2019-11-10 IDA / 59500 Sanitation Improvement Envelope Implementation and Sewerage Network TZ-DAWASCO-62380-CW-RFB / Dar es Salaam Performance IDA / 59490 Component 2: Dar es Salaam Single Stage - One Based Water Loss Reduction Prior Request for Bids Open - International Y 20,000,000.00 0.00 Under Review 2018-05-18 2018-08-03 2018-08-03 2018-05-23 2018-10-12 2018-11-11 2018-12-16 2020-06-08 IDA / 59500 Water Supply Improvement Envelope and Management Contract (C2- W02) GOODS Page 1 Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-10924-GO-RFB / Supply of Water Users IDA / 59490 Component 1: Integrated Water Single Stage - One Pending Post Request for Bids Open - National 150,000.00 0.00 2017-05-30 2017-06-04 2017-06-25 2017-07-25 2017-08-29 2017-11-27 Associations Survival Working IDA / 59500 Resources Management (IWRM) Envelope Implementation Kits TZ-MOW-11480-GO-RFB / Supply of eighteen four-Wheel IDA / 59490 Component 1: Integrated Water Single Stage - One Pending Drive Vehicles for the Basin Post Request for Bids Open - National 1,080,000.00 0.00 2017-07-03 2017-07-08 2017-08-07 2017-08-28 2017-10-02 2017-12-31 IDA / 59500 Resources Management (IWRM) Envelope Implementation Water Boards and MoWI's Division of WR. TZ-MOW-12602-GO-RFB / Supply of Motorbikes and IDA / 59490 Component 1: Integrated Water Single Stage - One Pending Post Request for Bids Open - National 350,000.00 0.00 2017-07-03 2017-07-08 2017-08-07 2017-08-21 2017-09-25 2017-11-24 Bicycles (100 of each) to support IDA / 59500 Resources Management (IWRM) Envelope Implementation 100 WUAs TZ-MOW-12667-GO-RFB / Supply of office data IDA / 59490 Component 1: Integrated Water Single Stage - One Pending management tools and Post Request for Bids Open - National 1,250,000.00 0.00 2018-03-01 2018-03-06 2018-04-05 2018-05-05 2018-06-09 2018-09-07 IDA / 59500 Resources Management (IWRM) Envelope Implementation equipment including ICT equipment TZ-MOW-12668-GO-RFB / IDA / 59490 Component 1: Integrated Water Single Stage - One Pending Supply of Communication Post Request for Bids Open - National 500,000.00 0.00 2017-10-02 2017-10-07 2017-11-06 2017-12-06 2018-01-10 2018-04-10 IDA / 59500 Resources Management (IWRM) Envelope Implementation Strategy Materials TZ-MOW-12610-GO-RFP / IDA / 59490 Component 1: Integrated Water Single Stage - One Pending Supply of water quality Post Request for Bids Open - National 300,000.00 0.00 2017-07-01 2017-07-06 2017-08-05 2017-09-04 2017-10-09 2018-04-07 IDA / 59500 Resources Management (IWRM) Envelope Implementation monitoring equipment and tools TZ-MOW-12605-GO-RFB / Supply of surface and groundwater monitoring network IDA / 59490 Component 1: Integrated Water Single Stage - One Pending Prior Request for Bids Open - National 2,900,000.00 0.00 2017-07-03 2017-07-08 2017-08-07 2017-09-06 2017-10-11 2018-04-09 gauges monitoring instruments IDA / 59500 Resources Management (IWRM) Envelope Implementation for large dams and sediment monitoring equipment TZ-DAWASCO-10124-GO-RFB / IDA / 59490 Component 2: Dar es Salaam Single Stage - One Prior Request for Bids Open - National 2,500,000.00 0.00 Canceled 2017-04-20 2017-04-25 2017-06-06 2017-07-06 2017-08-10 2017-11-08 Supply of domestic water meters IDA / 59500 Water Supply Improvement Envelope TZ-DAWASCO-10095-GO-RFB / IDA / 59490 Component 2: Dar es Salaam Single Stage - One Renewal of pipeline (pipes for Post Request for Bids Open - National 500,000.00 0.00 Canceled 2017-04-24 2017-04-27 2017-04-29 2017-06-10 2017-07-10 2017-08-14 2017-10-13 IDA / 59500 Water Supply Improvement Envelope network rehabilitation) TZ-DAWASCO-25523-GO-RFB / Supply of PVC Pipes and IDA / 59490 Component 2: Dar es Salaam Single Stage - One Post Request for Bids Open - National 500,000.00 297,298.91 Signed 2017-09-05 2017-10-06 2017-09-10 2017-10-22 2017-11-21 2018-04-18 2017-12-26 2018-04-30 2018-03-26 Fittings for Network IDA / 59500 Water Supply Improvement Envelope Rehabilitation TZ-DAWASCO-10121-GO-RFB / Supply of Billing equipment (this IDA / 59490 Component 2: Dar es Salaam Single Stage - One Post Request for Bids Open - National 100,000.00 0.00 Canceled 2017-04-18 2017-04-27 2017-04-23 2017-06-04 2017-07-04 2017-08-08 2017-10-07 is specific to hand held meter IDA / 59500 Water Supply Improvement Envelope reading/billing tools) TZ-DAWASCO-15274-GO-RFB / Supply of Domestic Water Meters for Utility Modernization IDA / 59490 Component 2: Dar es Salaam Single Stage - One Prior Request for Bids Open - National 2,500,000.00 0.00 Canceled 2017-05-24 2017-08-14 2017-05-29 2017-08-18 2017-07-10 2017-10-20 2017-08-09 2017-09-13 2018-01-11 and Expansion of Water Supply IDA / 59500 Water Supply Improvement Envelope Distribution System (Packages 2B & 2F) TZ-DAWASCO-53619-GO-RFB / Supply of Domestic Water Meters for Utility Modernization IDA / 59490 Component 2: Dar es Salaam Single Stage - One Under Prior Request for Bids Open - National 2,500,000.00 0.00 2018-03-20 2018-06-20 2018-03-25 2018-06-21 2018-05-06 2018-06-05 2018-07-10 2018-11-07 and Expansion of Water Supply IDA / 59500 Water Supply Improvement Envelope Implementation Distribution System (Packages 2B & 2F) (C2-G01) TZ-DAWASCO-10122-GO-RFB / Supply and installation of SCADA System, i.e. Bulk meters, pressure meters, central IDA / 59490 Component 2: Dar es Salaam Single Stage - One Pending Post Request for Bids Open - National 700,000.00 0.00 2018-05-31 2018-06-05 2018-07-17 2018-08-16 2018-09-20 2019-03-19 station meters, telemetry for IDA / 59500 Water Supply Improvement Envelope Implementation network management and clamp- on and acoustic equipment for leak detection (C2-G02) TZ-DAWASCO-25525-GO-RFB / IDA / 59490 Component 2: Dar es Salaam Single Stage - One Post Request for Bids Open - National 100,000.00 0.00 Canceled 2017-09-05 2018-02-23 2017-09-10 2017-10-22 2017-11-21 2017-12-26 2018-03-26 Supply of Data Loggers IDA / 59500 Water Supply Improvement Envelope TZ-DAWASCO-25525-GO-RFB / IDA / 59490 Component 2: Dar es Salaam Single Stage - One Under Post Request for Bids Open - National 100,000.00 0.00 2018-03-20 2018-03-27 2018-03-20 2018-04-06 2018-04-17 2018-05-17 2018-06-21 2018-09-19 Supply of Data Loggers (C2-G03) IDA / 59500 Water Supply Improvement Envelope Implementation TZ-DAWASCO-54120-GO-RFB / IDA / 59490 Component 2: Dar es Salaam Single Stage - One Under Supply of PVC Pipes for Network Post Request for Bids Open - National 195,000.00 0.00 2018-03-16 2018-04-11 2018-03-21 2018-04-11 2018-05-02 2018-06-01 2018-07-06 2018-10-04 IDA / 59500 Water Supply Improvement Envelope Implementation Rehabilitation (C2-G05) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 TZ-DAWASA-6490-CS-QCBS / Consultant for review of design and construction supervision of IDA / 59490 Component 2: Dar es Salaam Quality And Cost- Prior Open - International 2,000,000.00 0.00 Under Review 2017-02-14 2017-03-07 2017-04-04 2017-05-02 2017-06-01 2017-07-06 2017-08-10 2018-08-10 Mbezi Beach waste water IDA / 59500 Water Supply Improvement Based Selection treatment plant, pumping station and sewerage network TZ-DAWASA-6494-CS-CQS / Consultancy Services for Consultant IDA / 59490 Component 3: Dar es Salaam Under Preparation of ESIA and RAP for Post Qualification Open - National 100,000.00 0.00 2017-02-28 2017-03-02 2017-03-14 2017-04-11 2017-05-02 2017-06-06 2017-12-03 IDA / 59500 Sanitation Improvement Implementation the Mbezi Beach Waste Water Selection Treatment Plant TZ-MOW-10915-CS-QCBS / Consultancy Services for IDA / 59490 Component 1: Integrated Water Quality And Cost- Under Modernizing Hydrological and Prior Open - International 1,750,000.00 0.00 2017-03-30 2017-04-28 2017-06-02 2017-06-30 2017-07-30 2017-08-29 2017-10-03 2019-11-30 IDA / 59500 Resources Management (IWRM) Based Selection Implementation Meteorological Monitoring Systems TZ-MOW-10921-CS-QCBS / Consultancy Services for IDA / 59490 Component 1: Integrated Water Quality And Cost- Under Operational Decision Support Prior Open - International 2,500,000.00 0.00 2017-04-11 2018-01-10 2017-05-12 2018-03-22 2017-06-16 2017-07-14 2017-08-13 2017-09-12 2017-10-17 2018-10-17 IDA / 59500 Resources Management (IWRM) Based Selection Implementation System through Enhanced Hydro- Meteorological Services TZ-MOW-11533-CS-CQS / Technical Assistance for Consultant IDA / 59490 Component 1: Integrated Water Pending strengthening Ground water Post Qualification Open - National 150,000.00 0.00 2017-08-10 2017-08-31 2017-10-14 2017-11-13 2017-12-18 2018-06-16 IDA / 59500 Resources Management (IWRM) Implementation Resources Development and Selection Management in Tanzania TZ-MOW-11545-CS-CQS / Technical Assistance on Consultant IDA / 59490 Component 1: Integrated Water Pending Supporting Implementation of Post Qualification Open - National 100,000.00 0.00 2017-08-30 2017-09-20 2017-11-03 2017-12-03 2018-01-07 2018-07-06 IDA / 59500 Resources Management (IWRM) Implementation IWRMD at National and Basin Selection Levels TZ-MOW-11548-CS-CQS / Consultancy Services for Consultant IDA / 59490 Component 1: Integrated Water Pending Technical Assistance on Post Qualification Open - National 100,000.00 0.00 2017-08-30 2017-09-20 2017-11-03 2017-12-03 2018-01-07 2018-07-06 IDA / 59500 Resources Management (IWRM) Implementation Preparation of Water Resources Selection Use Charges Regulations TZ-MOW-11553-CS-CQS / Consultant Consultancy for Development and IDA / 59490 Component 1: Integrated Water Under Post Qualification Open - National 150,000.00 0.00 2017-09-20 2017-05-18 2017-10-11 2018-03-20 2017-11-24 2017-12-24 2018-01-28 2018-07-27 Implementation of Laboratory IDA / 59500 Resources Management (IWRM) Implementation Selection Information Management System TZ-MOW-11558-CS-CQS / Consultant Consultancy for IDA / 59490 Component 1: Integrated Water Pending Post Qualification Open - National 200,000.00 0.00 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 Conceptualization and strategic IDA / 59500 Resources Management (IWRM) Implementation Selection planning for COE TZ-MOW-11854-CS-QCBS / IDA / 59490 Component 1: Integrated Water Quality And Cost- Under Consultancy services for National Prior Open - International 1,750,000.00 0.00 2017-08-18 2018-01-10 2017-09-08 2018-03-22 2017-10-22 2017-11-19 2017-12-19 2018-01-23 2018-02-27 2019-02-27 IDA / 59500 Resources Management (IWRM) Based Selection Implementation Hydrological Aquifer Mapping TZ-MOW-11857-CS-QCBS / Consultancy Services for IDA / 59490 Component 1: Integrated Water Quality And Cost- Pending Operational Decision Support Prior Open - International 2,500,000.00 0.00 2017-10-05 2017-11-04 2017-12-18 2018-01-15 2018-02-14 2018-03-21 2018-04-25 2019-04-25 IDA / 59500 Resources Management (IWRM) Based Selection Implementation System Through Enhanced Hydro- Meteorological Services TZ-MOW-11864-CS-QCBS / Consultancy Services for IDA / 59490 Component 1: Integrated Water Quality And Cost- Pending Prior Open - International 1,750,000.00 0.00 2017-07-27 2017-08-17 2017-09-30 2017-10-28 2017-11-27 2018-01-01 2018-02-05 2019-02-05 Modernizing Hydrological and IDA / 59500 Resources Management (IWRM) Based Selection Implementation Monitoring Systems TZ-MOW-11875-CS-CQS / Consultancy Services for the Consultant IDA / 59490 Component 1: Integrated Water Pending study of institutional set up for Post Qualification Open - National 50,000.00 0.00 2017-05-25 2017-06-15 2017-07-29 2017-08-28 2017-10-02 2018-03-31 IDA / 59500 Resources Management (IWRM) Implementation water Resources Centre of Selection Excellence TZ-MOW-11878-CS-CQS / Consultant IDA / 59490 Component 1: Integrated Water Pending Design and Supervision for Post Qualification Open - National 250,000.00 0.00 2017-05-25 2017-06-15 2017-07-29 2017-08-28 2017-10-02 2018-03-31 IDA / 59500 Resources Management (IWRM) Implementation Centre of Excellence Building Selection TZ-MOW-11389-CS-QCBS / Consultancy Services for design review and supervision of construction of office and laboratory buildings for Wami- IDA / 59490 Component 1: Integrated Water Quality And Cost- Pending Ruvu Basin Water Boards Post Open - International 600,000.00 0.00 2017-09-05 2017-09-26 2017-10-24 2017-11-21 2017-12-21 2018-01-25 2018-03-01 2019-03-01 IDA / 59500 Resources Management (IWRM) Based Selection Implementation Headquarter Morogoro and Water Users Associations Offices at Msowero and rehabilitation and extension at Dodoma TZ-MOW-10918-CS-QCBS / Consultancy Services for IDA / 59490 Component 1: Integrated Water Quality And Cost- Under Post Open - International 750,000.00 0.00 2017-03-30 2017-04-28 2018-05-22 2017-06-02 2017-06-30 2017-07-30 2017-08-29 2017-10-03 2018-10-03 Catchment Conservation in Wami- IDA / 59500 Resources Management (IWRM) Based Selection Implementation Ruvu Basin TZ-MOW-12527-CS-QCBS / IDA / 59490 Component 1: Integrated Water Quality And Cost- Pending Institutional development support Prior Open - International 1,000,000.00 0.00 2017-10-20 2017-11-10 2017-12-24 2018-01-21 2018-02-20 2018-03-27 2018-05-01 2019-05-01 IDA / 59500 Resources Management (IWRM) Based Selection Implementation technical assistance COE TZ-MOW-12529-CS-CQS / Consultant IDA / 59490 Component 1: Integrated Water Pending Consultancy Services for Prior Qualification Open - International 300,000.00 0.00 2017-07-03 2017-07-24 2017-08-21 2017-09-04 2017-10-09 2018-04-07 IDA / 59500 Resources Management (IWRM) Implementation preparation of future investments Selection TZ-DAWASA-6480-CS-QCBS / Consultancy Services for Construction Supervision of IDA / 59490 Component 2: Dar es Salaam Quality And Cost- Prior Open - International 2,150,000.00 0.00 Canceled 2017-02-14 2017-03-07 2017-04-04 2017-05-04 2017-06-03 2017-07-08 2017-08-12 2018-08-12 Distribution Networks Part 1- IDA / 59500 Water Supply Improvement Based Selection from University Reservoir to Bagamoyo Page 3 TZ-DAWASCO-10055-CS-QCBS / Consultancy for Construction IDA / 59490 Component 2: Dar es Salaam Quality And Cost- supervision of distribution Prior Open - International 2,150,000.00 0.00 Canceled 2017-03-27 2017-04-27 2017-04-17 2017-05-04 2017-05-31 2017-09-08 2017-06-28 2017-07-28 2017-09-01 2017-10-06 2020-03-24 IDA / 59500 Water Supply Improvement Based Selection networks Part 1 - From University Reservoir to Bagamoyo. TZ-DAWASCO-28217-CS-QCBS / Consultancy Services for Supervision of Construction of IDA / 59490 Component 2: Dar es Salaam Quality And Cost- Under Prior Open - International 2,150,000.00 0.00 2017-09-12 2017-09-12 2017-09-12 2017-10-10 2017-11-09 2018-02-20 2017-12-14 2018-06-21 2018-01-18 2020-07-06 Water Supply Distribution IDA / 59500 Water Supply Improvement Based Selection Implementation Network Part 1, from University Reservoir to Bagamoyo Town TZ-MOW-44490-CS-CQS / Consultancy services for Consolidation of Data, Consultant IDA / 59490 Component 1: Integrated Water Information and Models from the Post Qualification Open - National 300,000.00 277,090.70 Signed 2018-01-18 2015-02-19 2018-02-08 2018-03-24 2015-10-06 2018-04-23 2016-12-21 2018-05-28 2016-12-23 2018-11-24 IDA / V0310 Resources Management (IWRM) IWRMD Plans and Preparation of Selection Requirements Specification for WRIS & Web Portal TZ-DAWASCO-10062-CS-QCBS / Provision of Consultancy Services for Preparation of Detailed Engineering Design, IDA / 59490 Component 2: Dar es Salaam Quality And Cost- Post Open - National 400,000.00 0.00 Canceled 2017-10-18 2017-10-11 2017-11-08 2017-12-22 2018-01-19 2018-02-18 2018-03-25 2018-04-29 2019-04-29 Bidding Documents and IDA / 59500 Water Supply Improvement Based Selection Construction Supervision of the Off-Grid Water Supply Works in Dar es Salaam TZ-DAWASCO-53652-CS-QCBS / Provision of Consultancy Services for Preparation of Detailed Engineering Design, IDA / 59490 Component 2: Dar es Salaam Quality And Cost- Post Open - National 400,000.00 0.00 Under Review 2018-03-30 2018-04-20 2018-06-03 2018-07-01 2018-07-31 2018-09-04 2018-10-09 2019-10-09 Bidding Documents and IDA / 59500 Water Supply Improvement Based Selection Construction Supervision of the Off-Grid Water Supply Works in Dar es Salaam (C2-C04) TZ-DAWASCO-10066-CS-QCBS / Provision of Consultancy Services for Preparation of Detailed Engineering Design, IDA / 59490 Component 2: Dar es Salaam Quality And Cost- Prior Open - International 1,500,000.00 0.00 Canceled 2017-09-12 2017-10-03 2017-11-16 2017-12-14 2018-01-13 2018-02-17 2018-03-24 2019-03-24 Bidding Documents and IDA / 59500 Water Supply Improvement Based Selection Construction Supervision of the Off-Grid Sanitation Works in Dar es Salaam TZ-DAWASCO-53675-CS-QCBS / Provision of Consultancy Services for Preparation of Detailed Engineering Design, IDA / 59490 Component 2: Dar es Salaam Quality And Cost- Prior Open - International 1,500,000.00 0.00 Under Review 2018-04-05 2018-04-26 2018-06-09 2018-07-07 2018-08-06 2018-09-10 2018-10-15 2020-10-15 Bidding Documents and IDA / 59500 Water Supply Improvement Based Selection Construction Supervision of the Off-Grid Sanitation Works in Dar es Salaam (C2-C07) TZ-DAWASCO-10065-CS-QCBS / NRW consultancy: asset management, hydraulic model, DMA installation for NRW IDA / 59490 Component 2: Dar es Salaam Quality And Cost- Pending Prior Open - International 1,500,000.00 0.00 2018-08-06 2018-08-27 2018-10-10 2018-11-07 2018-12-07 2019-01-11 2019-02-15 2020-02-15 management, NRW management IDA / 59500 Water Supply Improvement Based Selection Implementation Material Handbook, customer metering and billing (multiple) (C2- C06) TZ-DAWASCO-53747-CS-QCBS / Consultacy servises for ESIA IDA / 59490 Component 2: Dar es Salaam Quality And Cost- Pending Prior Open - International 1,200,000.00 0.00 2018-05-30 2018-06-20 2018-08-03 2018-08-31 2018-09-30 2018-11-04 2018-12-09 2019-12-09 study for the 10 FSM in Dar es IDA / 59500 Water Supply Improvement Based Selection Implementation Salaam (C2-C08) TZ-DAWASCO-53755-CS-QCBS / Consultacy services for ARAP IDA / 59490 Component 2: Dar es Salaam Quality And Cost- Pending Prior Open - International 1,000,000.00 0.00 2018-06-12 2018-07-03 2018-08-16 2018-09-13 2018-10-13 2018-11-17 2018-12-22 2019-12-22 /RAP study 10 FSM in Dar es IDA / 59500 Water Supply Improvement Based Selection Implementation Salaam (C2-C09) TZ-DAWASCO-53757-CS-QBS / Consultancy services for IDA / 59490 Component 2: Dar es Salaam Quality Based Under preparation of specifications for Post Open - National 50,000.00 0.00 2018-04-30 2018-05-21 2018-07-04 2018-08-01 2018-08-31 2018-09-30 2018-11-04 2019-01-03 IDA / 59500 Water Supply Improvement Selection Implementation SCADA system and TOR for NRW consultancy (C2-C10) TZ-MOW-54418-CS-QCBS / Consultancy Services on Water IDA / 59490 Component 1: Integrated Water Quality And Cost- Prior Open - International 414,000.00 385,210.34 Signed 2015-02-03 2015-02-13 2015-09-23 2015-11-13 2016-02-10 2016-07-01 2018-05-30 2018-12-15 2017-08-07 2019-06-13 Resources Management IDA / 59500 Resources Management (IWRM) Based Selection Financing Options TZ-MOW-54421-CS-QCBS / Consultancy Services for IDA / 59490 Component 1: Integrated Water Quality And Cost- Under Preparation of Integrated Water Prior Open - International 533,000.00 0.00 2015-02-03 2015-02-13 2015-09-07 2015-11-12 2016-04-04 2016-12-21 2017-06-01 2017-11-28 IDA / 59500 Resources Management (IWRM) Based Selection Implementation Management and Development Plan for Wami/Ruvu Basin TZ-DAWASCO-28457-CS-QCBS / Performance Improvement IDA / 59490 Component 2: Dar es Salaam Quality And Cost- Pending Prior Open - International 1,500,000.00 0.00 2018-06-20 2018-07-11 2018-08-24 2018-09-21 2018-10-21 2018-11-25 2018-12-30 2019-12-30 Program - PIP Consultancy (C2- IDA / 59500 Water Supply Improvement Based Selection Implementation C05) TZ-MOW-64970-CS-CQS / Component 4: Project Consultant Consultancy Services for Project IDA / 59490 Pending management and Post Qualification Open - National 150,000.00 0.00 2018-06-14 2018-07-05 2018-08-09 2018-09-03 2018-10-08 2019-04-06 Manager Consultancy for Support IDA / V0310 Implementation Implementation Support Selection of WSSP II TZ-MOW-64973-CS-QCBS / Component 4: Project Consultancy Service for Project IDA / 59490 Quality And Cost- Pending management and Prior Open - International 1,200,000.00 0.00 2018-06-20 2018-07-11 2018-08-15 2018-09-12 2018-10-12 2018-11-16 2018-12-21 2019-12-21 Management Firm to Support IDA / V0310 Based Selection Implementation Implementation Support Implementation of WSSP II INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 TZ-MOW-12520-CS-INDV / Individual consultant to support IDA / 59490 Component 1: Integrated Water Individual Consultant Pending the COE core team in providing Prior Open 1,200,000.00 0.00 2017-10-01 2017-11-12 2017-11-19 2017-12-31 2018-06-29 IDA / 59500 Resources Management (IWRM) Selection Implementation multi-sectoral analysis and policy support to different Stakeholders TZ-MOW-12593-CS-INDV / Consultancy Service for updating, Component 4: Project Individual Consultant Under upgrading, refining and IDA / V0310 management and Post Open 30,000.00 0.00 2017-04-20 2017-04-27 2017-05-01 2017-05-03 2017-05-17 Selection Implementation improvement of the PIM, Implementation Support workshops Page 5