Procurement Thresholds. Table 2: Thresholds for Procurement Methods and Prior Review for the Technical Assistance Component, should such activities occur. Contracts Subject N Expenditure Contract Value Procurement to Prior Review oo Category Threshold** (US$) Method (US$ ) 1 Works (NOT C > 5,000,000 ICB All Contracts (But APPLICABLE not envisaged) IN SEPIP for 100,000 < C ≤ 5,000,000 NCB First Contract now) only(But not envisaged) C ≤ 100,000 Shopping None All values Direct All contracts Contracting Goods and C ≥ 750,000 ICB All Contracts Services (other First Contract only 50,000 ≤ C < 750,000 NCB than Consulting 2 Services C< 50,000 Shopping None Direct All values All Contracts Contracting IT Systems, and All Contracts other Non- C ≥ 750,000 ICB 3 consulting Services 50,000 ≤ C < 750,000 NCB First Contract only Consulting C ≥ 200,000 firms All Contracts All Services C < 200,000 All Only TORs 4 C ≥ 50,000 individuals IC All contracts C < 50,000 individuals IC TORs All Values Single Source All Contracts Selection Training, All Values To be based Workshops, on Annual Study Tours Work Plan & 5 Budgets in the TA work plans. Implementation SBMCs SBMCs to None of procurement following activities by Basic SBMCs from the procurement 6 $500,000-$1, procedures 000,000 annual outlined in the grants to schools PIM/Grant acceptable to the Manual. - 91 - Association has been described in the SEPIP PIM and Grant Manual **These thresholds are for the purposes of implementing the TA procurement plan only. The thresholds will be revised periodically based on re-assessment of risks. PROCUREMENT Nigeria : Nigeria - State Education Program Investment Project PLAN General Information Country: Nigeria Banks Approval Date of the Original Procurement Plan: 2018-04-19 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-07-17 Project ID: P122124 GPN Date: Project Name: Nigeria - State Education Program Investment Project Loan / Credit No: IDA / 52200, IDA / 58480 Executing Agency(ies): EKITI SEPIP, YOBE SEPIP, BAUCHI SEPIP, FME SEPIP, BORNO SEPIP WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EK/SEPIP/RFQ/2018/01 / Results-based Component: Request for Single Stage - One Pending Procurement of data capturing IDA / 52200 Support to States' Education Post Limited 20,000.00 0.00 2018-02-03 2018-03-31 2018-09-27 Quotations Envelope Implementation instrument for schools on SEMIS Sector Program EK/SEPIP/RFQ/2018/02 / Procurement and installation of Results-based Component: Request for Single Stage - One Pending office equipments and Solar IDA / 52200 Support to States' Education Post Limited 30,000.00 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation inverter at EMIS in MOE, TSC, Sector Program SUBEB, BTVE & Exams Centre. EK/SEPIP/DIR/2018/01 / Results-based Component: Pending Procurement of Aquaponic IDA / 52200 Support to States' Education Prior Direct Selection Direct 450,000.00 0.00 2018-01-08 2018-01-13 2018-02-17 2018-08-16 Implementation Systems and installation Sector Program EK/SEPIP/RFQ/2018/03 / Procurement of Solar energy for Results-based Component: Request for Single Stage - One Pending Khan Academy schools and IDA / 52200 Support to States' Education Post Limited 100,000.00 0.00 2018-02-03 2018-03-31 2018-09-27 Quotations Envelope Implementation SEMIS offices as alternative Sector Program power source EK/SEPIP/RFQ/2018/04 / Results-based Component: Request for Single Stage - One Pending Procurement of test instruments IDA / 52200 Support to States' Education Post Limited 20,000.00 0.00 2018-01-31 2018-03-28 2018-09-24 Quotations Envelope Implementation on learning assesment Sector Program EK/SEPIP/RFQ/2018/05 / Procurement of Science Results-based Component: Teachers Association of Nigeria Request for Single Stage - One Pending IDA / 52200 Support to States' Education Post Limited 100,000.00 0.00 2018-02-06 2018-04-03 2018-09-30 (STAN) educational resource Quotations Envelope Implementation Sector Program materials for core subject teachers. EK/SEPIP/RFQ/2018/06 / Results-based Component: Request for Single Stage - One Pending Procurement of student laptops IDA / 52200 Support to States' Education Post Limited 100,000.00 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation for full roll-out of Khan Academy Sector Program YBSEPIP-AF/GO/001/2018 / Off/furns, 3 F/proof cabs, 1 Tilt, 3 D/Compt & ac-sories, 20 Lap/Compt, 10 Nwk Printers, 4 Results-based Component: Pending H/Duty Laser P/copiers, 5 Shred IDA / 58480 Support to States' Education Post Direct Selection Direct 99,500.00 0.00 2018-02-04 2018-02-09 2018-03-16 2018-09-12 Implementation mach, 1 S/proof 15kva gen, 1 Sector Program projector, 2 V/cams, 1 Dgt/cam, Solar inv & ac-sories, 5 UPS, 1 Scanner & a S/ binding mach YBSEPIP-AF/GO/002/2018 / Results-based Component: Procurement of 2 No. 4WD Pending IDA / 58480 Support to States' Education Post Direct Selection Direct 100,000.00 0.00 2018-02-15 2018-02-20 2018-03-27 2018-09-23 Double Cabin Hilux Project Implementation Sector Program Vehicle YBSEPIP-AF/GO/003/2018 / Procurement of assorted Office Results-based Component: Pending Furniture for Teachers, Pupils IDA / 58480 Support to States' Education Post Direct Selection Direct 100,000.00 0.00 2018-05-01 2018-05-06 2018-06-10 2018-12-07 Implementation and Students for 30 schools (5 Sector Program Schools per LGA) in 6 LGAs YBSEPIP-AF/GO/004/2018 / Procurement of assorted Text Books (English, Maths, Health Habits, Unit Colour, Drawing Results-based Component: books, Letter words, Primers Pending IDA / 58480 Support to States' Education Post Direct Selection Direct 200,000.00 0.00 2018-09-03 2018-09-08 2018-10-13 2019-04-11 1&2, Creative Arts, Rhymes, Implementation Sector Program Arabic Language and Hausa for 255 ECCDE schools and Computer Studies Books 1,2 & 3 for 173 JSS. Component 3: Improving Access to Quality Education and YBSEPIP-AF/GO/006/2018 / Learning Environment in North Procurement of 210 Nos. East States tracking devices (Handheld Pending IDA / 58480 Post Direct Selection Direct 91,000.00 0.00 2018-11-20 2018-11-25 2018-12-30 2019-06-28 Tablets) embedded with soft ware Component 3.1: Improving Implementation for real time tracking of SEPIP - Access to Quality Education AF activities. Component 3.2: Improving Learning Environment Page 1 Component 3: Improving Access to Quality Education and Learning Environment in North NG-BSEPIP-47353-GO-RFQ / East States Procurement of 6 Laptop Request for Single Stage - One Pending Computers to replace the IDA / 52200 Post Limited 25,000.00 0.00 2018-02-19 2018-04-16 2018-05-16 Component 3.1: Improving Quotations Envelope Implementation unserviceable ones for Project Access to Quality Education management staff Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and NG-BSEPIP-47355-GO-RFQ / Learning Environment in North Procurement of safeguard East States equipments/materials Request for Single Stage - One Pending IDA / 52200 Post Limited 30,000.00 0.00 2018-03-19 2018-05-14 2018-11-10 (handgloves,nose masks,dust Component 3.1: Improving Quotations Envelope Implementation bins,brooms, wheel barrows, Access to Quality Education antiseptics, detergents, etc) Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and Learning Environment in North NG-BSEPIP-47356-GO-RFQ / East States Procurement of STAN Textbooks Request for Single Stage - One Pending IDA / 52200 Post Limited 98,000.00 0.00 2018-04-21 2018-06-16 2018-07-16 (Basic Science, Physics, Component 3.1: Improving Quotations Envelope Implementation Chemistry, Biology in SSS) Access to Quality Education Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and NG-BSEPIP-47354-GO-RFQ / Learning Environment in North Procurement of Students and East States pupils Furniture Students and Request for Single Stage - One Pending IDA / 52200 Post Limited 98,000.00 0.00 2018-06-07 2018-08-02 2018-09-02 Pupils and Student Twin desks Component 3.1: Improving Quotations Envelope Implementation (100 Nos per school) for 30 Access to Quality Education schools in 6 LGAs Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and Learning Environment in North NG-BSEPIP-47352-GO-RFQ / East States Establishment of e-learning Request for Single Stage - One Pending centres (including supply of IDA / 52200 Post Limited 88,000.00 0.00 2018-08-11 2018-10-06 2018-11-06 Component 3.1: Improving Quotations Envelope Implementation equipment, installation, testing Access to Quality Education and commissioning. Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and Learning Environment in North East States BOSEPIP/MNL/18/2 / Request for Single Stage - One Pending Production of 13500 copies of IDA / 58480 Post Open - National 43,000.00 0.00 2018-02-19 2018-04-16 2018-10-13 Component 3.1: Improving Quotations Envelope Implementation pedagogy and psycho-social Access to Quality Education Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and Learning Environment in North East States BOSEPIP/MNL/18/3 / Request for Single Stage - One Pending Production of 3000 copies of IDA / 58480 Post Open - National 35,000.00 0.00 2018-03-17 2018-05-12 2018-11-08 Component 3.1: Improving Quotations Envelope Implementation SBMC Manual Access to Quality Education Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and Learning Environment in North BOSEPIP/MNL/18/4 / East States Translation and production of Request for Single Stage - One Pending IDA / 58480 Post Open - National 35,000.00 0.00 2018-03-19 2018-05-14 2018-11-10 3000 copies of SBMC manual Component 3.1: Improving Quotations Envelope Implementation from English to Hausa language Access to Quality Education Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and Learning Environment in North East States BOSEPIP/EMIS/18/5 / Equiping Request for Single Stage - One Pending EMIS Office (MoE & SUBEB) IDA / 58480 Post Open - National 98,000.00 0.00 2018-04-14 2018-06-09 2018-12-06 Component 3.1: Improving Quotations Envelope Implementation and 27 LGA EMIS Offices Access to Quality Education Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and BOSEPIP/EQP/18/6 / Learning Environment in North Procurement of 15 Nos. tracking East States devices (Handheld Tablets) Request for Single Stage - One Pending IDA / 58480 Post Open - National 20,000.00 0.00 2018-06-09 2018-08-04 2019-01-31 embedded with soft ware for real Component 3.1: Improving Quotations Envelope Implementation time tracking of SEPIP Access to Quality Education activities. Component 3.2: Improving Learning Environment Component 3: Improving Access BOSEPIP/INST/18/8 / to Quality Education and Procurement of assorted Learning Environment in North Instructional Materials (Charts, East States Maps, Globes, Hardcover Request for Single Stage - One Pending Notebooks, School Diaries, IDA / 58480 Post Open - National 100,000.00 0.00 2018-10-20 2018-12-15 2019-06-13 Component 3.1: Improving Quotations Envelope Implementation School Registers, Execise Access to Quality Education Books, Pencils, chalks, Dusters, Standing Blackboards, etc.) for Component 3.2: Improving schools Learning Environment Page 2 Component 3: Improving Access to Quality Education and BOSEPIP/INST/18/9 / Learning Environment in North Procurement of Core Subject East States Textbooks and Teachers Guide Request for Single Stage - One Pending IDA / 58480 Post Open - National 100,000.00 0.00 2018-11-10 2019-01-05 2019-07-04 (Maths, English and Basic Component 3.1: Improving Quotations Envelope Implementation Science/Technology, Social Access to Quality Education Studies) for schools Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and Learning Environment in North East States BOSEPIP/TEXT/18/10 / Printing Request for Single Stage - One Pending of 10,000 Information IDA / 58480 Post Open - National 50,000.00 0.00 2018-12-08 2019-02-02 2019-08-01 Component 3.1: Improving Quotations Envelope Implementation management sytem (IMS) form Access to Quality Education Component 3.2: Improving Learning Environment BOSEPIP/VEH/18/26 / Results-based Component: Procurement of 1 Toyota corolla Request for Single Stage - One Pending IDA / 58480 Support to States' Education Post Open - National 207,179.49 0.00 2018-06-09 2018-08-04 2019-01-31 1.8GLI and 1 Toyota 4Runner Quotations Envelope Implementation Sector Program 4.0L 2017 Models NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EK/SEPIP/CQS/18/02 / Results-based Component: Consultant Institution Capacity building for Pending IDA / 52200 Support to States' Education Post Qualification Open - National 90,000.00 0.00 2018-01-29 2018-02-19 2018-04-04 2018-05-04 2018-06-08 2018-12-05 2,000 teachers for improved Implementation Sector Program Selection learning outcomes EK/SEPIP/CQS/18/03 / Results-based Component: Consultant Consultancy on audit of financial Pending IDA / 52200 Support to States' Education Post Qualification Open - National 3,429.00 0.00 2018-02-01 2018-02-22 2018-04-07 2018-05-07 2018-06-11 2018-12-08 account for the year ended 2016 Implementation Sector Program Selection for Ekiti SEPIP EK/SEPIP/CQS/18/04 / Results-based Component: Consultant Pending Baseline studies for Science IDA / 52200 Support to States' Education Post Qualification Open - National 27,500.00 0.00 2018-02-05 2018-02-26 2018-04-11 2018-05-11 2018-06-15 2018-12-12 Implementation Education in Ekiti State Sector Program Selection EK/SEPIP/CQS/18/05 / Technical support for Results-based Component: Consultant Pending construction and implementation IDA / 52200 Support to States' Education Post Qualification Open - International 153,440.00 0.00 2018-01-29 2018-02-19 2018-04-04 2018-05-04 2018-06-08 2018-12-05 Implementation of TVET Aquaponics Technology Sector Program Selection pilot in Ekiti State.(Phase II) EK/SEPIP/CQS/18/06 / Results-based Component: Consultant Consultancy on Development of Pending IDA / 52200 Support to States' Education Post Qualification Open - International 200,000.00 0.00 2018-04-24 2018-05-15 2018-06-28 2018-07-28 2018-09-01 2019-02-28 STALLAS Learning Assessment Implementation Sector Program Selection Model in Ekiti State EK/SEPIP/CQS/18/07 / Results-based Component: Consultant Capacity building for 2,700 Pending IDA / 52200 Support to States' Education Post Qualification Open - National 57,143.00 0.00 2018-02-01 2018-02-22 2018-04-07 2018-05-07 2018-06-11 2018-12-08 SBMC Officials in primary Implementation Sector Program Selection schools in the State. Component 3: Improving Access to Quality Education and NG-BSEPIP-47357-CS-CQS / Learning Environment in North To access or evaluate Bauchi East States State Educational System via the Consultant Pending performance of IDA / 52200 Post Qualification Open - National 102,000.00 0.00 2018-03-12 2018-04-02 2018-05-16 2018-06-15 2018-07-20 2018-10-22 Component 3.1: Improving Implementation schools/candidate in the annual Selection Access to Quality Education WAEC, NECO and NAPTEB result from 2012 - 2017 Component 3.2: Improving Learning Environment NG-FME SEPIP-51510-CS-INDV / Capacity building for teachers in core subjects in North East Consultant Technical Assistance Pending states on cutting edge skill in IDA / 52200 Post Qualification Open - National 96,000.00 0.00 2018-06-04 2018-06-25 2018-08-08 2018-09-07 2018-10-12 2019-04-10 Component Implementation science teaching in collaboration Selection with the science Teachers Association of Nigeria (STAN) NG-FME SEPIP-51521-CS-CQS Consultant / Workshop on Emergency Technical Assistance Pending IDA / 52200 Post Qualification Open - National 110,000.00 0.00 2018-06-10 2018-07-01 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Response and Management Component Implementation Selection relieve Operation. NG-FME SEPIP-51522-CS-CQS / Project Key Performance Consultant Indicators (KPI) and Fund Technical Assistance Pending IDA / 52200 Post Qualification Open - National 130,000.00 0.00 2018-07-10 2018-07-31 2018-09-13 2018-10-13 2018-11-17 2019-05-16 Distribution Link Indicators Component Implementation Selection Management, Setting , Monitoring and Evaluation NG-FME SEPIP-52383-CS-CQS / Independent Verification of Consultant Technical Assistance Pending Performance Grant Indicators IDA / 52200 Post Qualification Open - National 100,000.00 0.00 2018-04-10 2018-05-01 2018-06-14 2018-07-14 2018-08-18 2019-02-14 Component Implementation (PGIs) 2017 is the Additional Selection Financing (AF) Page 3 BOSEPIP/CON/18/1 / Conduct Component 3: Improving Access of school mapping in 24 LGAs to Quality Education and (Konduga, Biu, Askira/Uba, Learning Environment in North Magumeri, Monguno, Gubio, East States Consultant Mafa, Shani, Hawul, Jere, Marte, Pending IDA / 58480 Prior Qualification Open - National 100,000.00 0.00 2018-02-12 2018-03-05 2018-04-18 2018-05-18 2018-06-22 2018-12-19 Guzalama, Mobbar, Chibok, Component 3.1: Improving Implementation Selection Bama, Dikwa, Ngala, MMC, Access to Quality Education Gwoza, Bayo, Kwaya Kusar,Kaga, Nganzai and Component 3.2: Improving Dambo'a) using GPS equipment Learning Environment INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EK/SEPIP/INDV/18/01 / Results-based Component: Individual Consultant Pending Validation and Verification of IDA / 52200 Support to States' Education Post Direct 30,429.00 0.00 2018-02-05 2018-02-15 2018-03-08 2018-04-12 2018-10-09 Selection Implementation biometric data on SEMIS Sector Program EK/SEPIP/INDV/18/02 / Impact Results-based Component: Individual Consultant Pending Evaluation Study on teachers IDA / 52200 Support to States' Education Post Direct 70,000.00 0.00 2018-03-19 2018-03-29 2018-04-19 2018-05-24 2018-11-20 Selection Implementation deployment in Ekiti State Sector Program YBSEPIP-AF/CS/001/2018 / Development of Psyco-social & Pedagogical Training Manuals for Results-based Component: Teachers and SBMC in Ten (10) Pending IDA / 58480 Support to States' Education Post Direct Selection Direct 140,000.00 0.00 2018-03-15 2018-03-25 2018-05-29 2018-11-25 LGAs: Damaturu, Yunusari, Implementation Sector Program Fune, Potiskum,Gujba, Yusufari, Fika, Geidam, Tarmuwa & Gulani. YBSEPIP-AF/CS/002/2018 / 5- Day training of 231 SBMCs (693 Members) (11 schools in each of Results-based Component: the 6 LGAs: Damaturu, Yunusari, Pending IDA / 58480 Support to States' Education Post Direct Selection Direct 210,000.00 0.00 2018-04-02 2018-04-12 2018-06-16 2018-12-13 Fune, Potiskum, Gujba, Yusufari Implementation Sector Program & 15 schools in each of the other 11 LGAs.) in School Management and Accountability. YBSEPIP-AF/CS/003/2018 / Development and administration Results-based Component: of quantitative supervision Individual Consultant Pending IDA / 58480 Support to States' Education Post Direct 40,000.00 0.00 2018-06-04 2018-06-14 2018-07-05 2018-08-09 2019-02-05 checklist to track performance Selection Implementation Sector Program over time and trouble - shoot problems YBSEPIP-AF/CS/004/2018 / Conduct and Develop Data on SBMCs with /without School Results-based Component: improvement plans in affected Pending IDA / 58480 Support to States' Education Post Direct Selection Direct 90,000.00 0.00 2018-06-11 2018-06-21 2018-08-25 2019-02-21 locations within the 10 LGAs as Implementation Sector Program well as data on teachers, School's populations and locations YBSEPIP-AF/CS/005/2018 / Review of School Educational Results-based Component: Individual Consultant Pending Expenditure against allocations IDA / 58480 Support to States' Education Post Direct 35,000.00 0.00 2018-06-21 2018-07-01 2018-07-22 2018-08-26 2019-02-22 Selection Implementation for prudent school financial Mgt Sector Program and best practices YBSEPIP-AF/CS/006/2018 / Educational Survey on teaching and learning Situation in Results-based Component: Individual Consultant Pending identified Nine (9) LGAs: IDA / 58480 Support to States' Education Post Direct 55,000.00 0.00 2018-07-16 2018-07-26 2018-08-16 2018-09-20 2019-03-19 Selection Implementation Damaturu, Yunusari, Fune, Sector Program Potiskum, Gulani, Yusufari, Fika, Geidam, Tarmuwa & Gujba. YBSEPIP-AF/CS/007/2018 / Mapping of all Primary and Junior Seconday Schools in Ten (10) Results-based Component: Pending LGAs: Damaturu, Yunusari, IDA / 58480 Support to States' Education Post Direct Selection Direct 90,000.00 0.00 2018-08-01 2018-08-11 2018-10-15 2019-04-13 Implementation Fune, Potiskum,Gujba, Yusufari, Sector Program Fika, Geidam, Tarmuwa & Gulani. YBSEPIP-AF/CS/008/2018 / Development of baseline information on CSOs/NGOs Results-based Component: Pending operating within Identified Nine IDA / 58480 Support to States' Education Post Direct Selection Direct 90,000.00 0.00 2018-08-09 2018-08-19 2018-10-23 2019-04-21 Implementation (9) LGAs: Damaturu, Yunusari, Sector Program Fune, Potiskum, Gujba, Yusufari, Fika, Geidam & Gulani. YBSEPIP-AF/CS/009/2018 / Training for 360 (60 Each per subject) Teachers on Maths, Results-based Component: English Language, Biology, Pending IDA / 58480 Support to States' Education Post Direct Selection Direct 140,000.00 0.00 2018-08-20 2018-08-30 2018-11-03 2019-05-02 chemistry, Physics in Senior Implementation Sector Program Secondary School and Integrated science in Junior Secondary schools YBSEPIP-AF/CS/010/2018 / 5 Days Training on Pyschosocial & Results-based Component: Pedagogy for Teachers in 5 Pending IDA / 58480 Support to States' Education Post Direct Selection Direct 220,000.00 0.00 2018-11-12 2018-11-22 2019-01-26 2019-07-25 LGAs: 300 per LGA (Fika, Implementation Sector Program Tarmuwa, Geidam, Gulani and Gujba) NG-FME SEPIP-51504-CS-INDV / Education planning Technical Assistance Individual Consultant Pending management through effective IDA / 52200 Post Limited 8,400.00 0.00 2018-03-30 2018-04-04 2018-04-25 2018-05-30 2018-11-26 Component Selection Implementation management information system (EMIS) Page 4 NG-FME SEPIP-51486-CS-INDV / New approach to information Technical Assistance Individual Consultant Pending IDA / 52200 Post Limited 7,872.00 0.00 2018-08-13 2018-08-18 2018-09-08 2018-10-13 2019-04-11 control, store, record and achieve Component Selection Implementation inventory management NG-FME SEPIP-51519-CS-INDV / Leadership and Good Technical Assistance Individual Consultant Pending IDA / 52200 Post Limited 7,872.00 0.00 2018-05-05 2018-05-10 2018-05-31 2018-07-05 2019-01-01 Governance in Management of Component Selection Implementation Donor Assisted Project NG-FME SEPIP-51523-CS-INDV Technical Assistance Individual Consultant Pending / Procurement training for the IDA / 52200 Post Limited 6,557.00 0.00 2018-05-15 2018-05-20 2018-06-10 2018-07-15 2019-01-11 Component Selection Implementation stakeholders and Project staff. NG-FME SEPIP-51527-CS-INDV Technical Assistance Individual Consultant Pending IDA / 52200 Post Limited 7,872.00 0.00 2018-04-10 2018-04-15 2018-05-06 2018-06-10 2018-12-07 / Capacity building on ICT Component Selection Implementation NG-FME SEPIP-51529-CS-INDV / Advanced Monitoring and Technical Assistance Individual Consultant Pending Evaluation of Project input, IDA / 52200 Post Limited 7,872.00 0.00 2018-05-10 2018-05-15 2018-06-05 2018-07-10 2019-01-06 Component Selection Implementation outputs, impact and outcome for improved performance. NG-FME SEPIP-52384-CS-INDV / Annual Review of Public Technical Assistance Individual Consultant Pending IDA / 52200 Post Limited 65,400.00 0.00 2018-10-10 2018-10-15 2018-11-05 2018-12-10 2019-06-08 Expenditure in the Education Component Selection Implementation Sector NG-FME SEPIP-52391-CS-INDV / Assessment study to determine Technical Assistance Individual Consultant Pending IDA / 52200 Post Limited 57,870.00 0.00 2018-09-20 2018-09-25 2018-10-16 2018-11-20 2019-05-19 the effectiveness in the use of the Component Selection Implementation grants provided to SBMCs NG-FME SEPIP-52393-CS-INDV / Assessment study to examine the impact of the partnerships Technical Assistance Individual Consultant Pending IDA / 52200 Post Limited 67,650.00 0.00 2018-07-20 2018-07-25 2018-08-15 2018-09-19 2019-03-18 between the SEPIP states and Component Selection Implementation the private sectors in the area of technical vocational education. NG-FME SEPIP-52397-CS-INDV / Consultancy on the Result Technical Assistance Individual Consultant Pending IDA / 52200 Post Limited 68,500.00 0.00 2018-08-10 2018-08-15 2018-09-05 2018-10-10 2019-04-08 Driven Monitoring and Evaluation Component Selection Implementation of PGI NG-FME SEPIP-52398-CS-INDV Technical Assistance Individual Consultant Pending / Consultancy on Grievance IDA / 52200 Post Limited 60,000.00 0.00 2018-11-23 2018-11-28 2018-12-19 2019-01-23 2019-07-22 Component Selection Implementation Management and Resolution NG-FME SEPIP-52399-CS-INDV / Consultancy on Beneficiary Technical Assistance Individual Consultant Pending IDA / 52200 Post Limited 70,000.00 0.00 2018-09-16 2018-09-21 2018-10-12 2018-11-16 2019-05-15 Assessment and Review of Component Selection Implementation Additional Financing (AF) states NG-FME SEPIP-52400-CS-INDV / Consultancy on the Evaluation of Teacher's/ SBMCs personnel Technical Assistance Individual Consultant Pending IDA / 52200 Post Limited 51,500.00 0.00 2018-06-18 2018-06-23 2018-07-14 2018-08-18 2019-02-14 trained on Psychosocial and Component Selection Implementation pedagogy in the North East States. Page 5