INTEGRTED FOREST ECOSYSTEM MANAGEMENT PROJECT General Procurement Thresholds and Methods of Procurement: The following methods of procurement shall be used for procurement under the project. It has been agreed that if a invitation for a bid is comprised of several packages, lots or slices, and invited in the same invitation for bid, then the aggregate value of the whole package determines the applicable threshold amount for procurement and also for the review by the Bank. The national competitive bidding (NCB) conditions will be part of the Financing Agreement. Expenditure Contract Procurement Bank Prior Review Category Value (USD) Method >= 5, 000 ICB All ICB contracts 000 < 5, NCB NA Civil Works 000,000 <50 000 Shopping NA NA DC >= 5, 000 000 >= 1, 000 ICB All ICB contracts 000 <1, 000 000 NCB NA Goods <100 000 Shopping NA NA DC >= 1, 500 000 NA QCBS, QBS, FBS, All contracts >= USD Consultant LCS and CQS* 500,000 for firms; all Services NA SSS contracts >= USD NA IC 200,000 for individuals; Notes: ICB – International Competitive Bidding All TORs NCB – National Competitive Bidding DC – Direct Contracting QCBS – Quality and Cost Based Selection QBS – Quality Based Selection FBS – Fixed Budget Selection LCS – Least Cost Selection *CQS – Selection Based on Consultants’ Qualification below $300,000 depending on the nature of assignment SSS – Single (or Sole) Source Selection IC – Individual Consultant selection procedure NA – Not Applicable Summary of the Procurement Packages planned during the first 18 months after July 9, 2010 project effectiveness 1. PROCUREMENT PLAN (July 2015) Date of WB Proc. Contra Review Item № Contract Description Metho ct (Prior/ d Signin Post) g GOODS Component 1. Forest Sector Institutional Reform No goods Component 2. Strategic Investments and Piloting of Sustainable Management Approaches NCB/S 1 Financing the implementation of INRMPs Prior/Post H Investments like afforestation of short NCB/S 2 rotation tree species, natural regeneration Prior/Post H through thinning etc. Component 3. Information and Monitoring and Evaluation National Forest Inventory (NFI) and the 9/1/20 3 Management Forest Inventory (MFI) (Non- ICB Prior 16 consulting services) 6/1/20 4 Office equipment for FMIS NCB Prior 17 Component 4. Project Management, Monitoring and Evaluation 3/1/20 5 Computers for PCU SH Prior 16 3/1/20 6 Furniture for PCU SH Post 16 3/1/20 7 Car for PCU SH Post 16 3/1/20 8 Accounting software for PCU SH Post 16 CONSULTANCY LARGE Date of WB Select. Contra Review Item № Contract Description Metho ct (Prior/ d Signin Post) g Component 1. Forest Sector Institutional Reform July 9, 2010 Support of introduction of new principles 9/1/20 1 QCBS Prior of planning, budgeting and monitoring /a 16 Component 2. Strategic Investments and Piloting of Sustainable Management Approaches Preparation of the Integrated Natural 9/1/20 2 QCBS Prior Resource Management Plans (INRMPs) 16 Component 3. Information and Monitoring and Evaluation The Forest Management Information 1/1/20 3 QCBS Prior System (FMIS) 17 Component 4. Project Management, Monitoring and Evaluation 9/1/20 4 Project Audit LCS Prior 16 July 9, 2010 PROCUREMENT Kyrgyz Republic : Integrated Forest Ecosystem Management PLAN General Information Country: Kyrgyz Republic Bank’s Approval Date of the Original Procurement Plan: 2018-03-26 2021-02-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153721 GPN Date: 2018-04-10 Project Name: Integrated Forest Ecosystem Management Loan / Credit No: TF / A0750 S Executing Agency(ies): tate Agency on Environment Protection and Forestry WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IFEMP-SH-FURNITURE-002- Project Management, Request for Single Stage - One TF / A0750 Post Limited 5,000.00 2,910.86 Completed 2017-06-05 2017-06-15 2017-07-06 2017-07-04 2017-07-25 2017-07-25 2017 / Furniture for PCU Monitoring and Evaluation Quotations Envelope IFEMP-SH-1C-SOFTWARE- Project Management, Request for Single Stage - One 003-2017 / Accounting TF / A0750 Post Limited 5,200.00 5,528.04 Completed 2017-06-05 2017-07-06 2017-07-04 2017-07-26 2017-07-25 Monitoring and Evaluation Quotations Envelope software for PCU IFEMP-SH-PRINTERS-008- Information and Monitoring Request for Single Stage - One 2018 / Printers for 14 pilot TF / A0750 Post Open - National 14,000.00 0.00 Canceled 2018-10-03 2018-10-17 2018-11-01 2018-11-22 and Evaluation Quotations Envelope leshozes KG-IFEMP-SH-PRINTERS-008- Information and Monitoring Request for Single Stage - One 2018 / Printers for 14 pilot TF / A0750 Post Limited 26,000.00 25,272.21 Completed 2018-11-22 2018-10-05 2018-11-29 2018-12-04 2018-12-20 2019-01-15 and Evaluation Quotations Envelope leshozes IFEMP-SH-COMPS-NPL-009- Information and Monitoring Request for Single Stage - One 2019 / Computer equipment TF / A0750 Post Open - National 31,000.00 28,569.94 Completed 2019-07-01 2019-07-19 2019-07-24 2019-08-13 2019-08-07 2019-09-03 and Evaluation Quotations Envelope for 26 for non pilot leskhozes # KG-IFEMP-SH-NFI-010- 2019 / Computer equipment Information and Monitoring Request for Single Stage - One TF / A0750 Post Open - National 84,495.00 75,088.14 Completed 2019-08-30 2019-09-30 2019-11-01 2019-10-31 2019-12-13 for National Forest Inventory and Evaluation Quotations Envelope (NFI) # KG-IFEMP-SH-NFI-012- Information and Monitoring Request for Single Stage - One 2019 / Digital inventory for TF / A0750 Post Open - National 89,510.00 77,841.31 Completed 2019-08-30 2019-09-30 2019-11-01 2019-10-31 2019-12-19 and Evaluation Quotations Envelope National Forest Inventory (NFI) # KG-IFEMP-SH-NFI-011- Information and Monitoring Request for Single Stage - One 2019 / Field instruments for TF / A0750 Post Open - National 64,026.00 64,699.68 Completed 2019-08-30 2019-09-30 2019-11-01 2019-10-31 2019-12-20 and Evaluation Quotations Envelope National Forest Inventory (NFI) KG-IFEMP-SH-NFI-013-2019 Information and Monitoring Request for Single Stage - One / GPS and laboratory for TF / A0750 Post Open - National 40,000.00 12,909.08 Completed 2019-12-27 2019-12-30 2020-01-27 2020-02-12 2020-03-06 2020-03-19 and Evaluation Quotations Envelope National Forest Inventory (NFI) KG-IFEMP-SH-01-2020 / Project Management, Request for Single Stage - One TF / A0750 Post Open - National 3,000.00 2,864.51 Completed 2020-02-08 2020-02-06 2020-02-28 2020-03-11 2020-03-30 2020-05-21 Office furniture for PIU Monitoring and Evaluation Quotations Envelope IFEMP-SH-03-2020 / Development and replication Forest Sector Institutional Request for Single Stage - One TF / A0750 Post Open - National 1,000.00 170.08 Completed 2020-02-11 2020-02-18 2020-03-02 2020-03-12 2020-03-23 2020-05-26 of booklets and barcodes of Reform Quotations Envelope PIU IFEMP-SH-NFI-05-2020 / Information and Monitoring Request for Single Stage - One GPS for National Forest TF / A0750 Post Open - National 27,080.00 24,377.20 Completed 2020-02-15 2020-02-21 2020-03-12 2020-04-17 2020-04-21 2020-08-25 and Evaluation Quotations Envelope Inventory (NFI) IFEMP-COVID-NCB-1-2020 / Strategic Investments and Single Stage - One Special technique for non pilot TF / A0750 Piloting of Sustainable Post Request for Bids Open - National 800,000.00 615,086.64 Signed 2020-07-06 2020-08-13 2020-07-08 2020-08-14 2020-07-22 2020-09-04 2020-07-29 2020-10-14 2020-08-28 2020-11-13 2020-11-30 Envelope leskhozes Management Approaches IFEMP-NCB-FMIS2-2-2020 / Pending Equipment for the Forest Project Management, Single Stage - One TF / A0750 Post Request for Bids Open - National 105,600.00 0.00 Implementati 2020-11-06 2020-11-13 2020-12-04 2020-12-18 2020-12-30 2021-02-26 Management Information Monitoring and Evaluation Envelope on System (FMIS) second phase GEF/IFEMP/G/SH/COVID/1/20 Strategic Investments and Pending 21 / Purchase of planting Request for Single Stage - One TF / A0750 Piloting of Sustainable Post Open - National 38,832.00 0.00 Implementati 2021-02-23 2021-03-12 2021-03-29 materials for vulnerable layers Quotations Envelope Management Approaches on in pilot zone of Talas leskhoz GEF/IFEMP/G/SH/COVID/2/20 21 / Purchase of planting Strategic Investments and Pending Request for Single Stage - One material for vulnerable layers TF / A0750 Piloting of Sustainable Post Open - National 22,938.00 0.00 Implementati 2021-02-20 2021-03-12 2021-03-29 Quotations Envelope in pilot zone of At-Bashy Management Approaches on leskhoz GEF/IFEMP/G/SH/COVID/3/20 Strategic Investments and Pending 21 / Purchase of planting Request for Single Stage - One TF / A0750 Piloting of Sustainable Post Open - National 15,292.00 0.00 Implementati 2021-02-20 2021-03-12 2021-03-29 material for vulnerable layers Quotations Envelope Management Approaches on in pilot zone of Naryn leskhoz GEF/IFEMP/G/SH/COVID/4/20 21 / Purchase of planting Strategic Investments and Pending Request for Single Stage - One material for vulnerable layers TF / A0750 Piloting of Sustainable Post Open - National 22,938.00 0.00 Implementati 2021-02-20 2021-03-12 2021-03-29 Quotations Envelope in pilot zone of Karakol Management Approaches on leskhoz NON CONSULTING SERVICES Page 1 Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-SAEPF-NFI-CS-QCBS- 2018 / Conducting of Kyrgyz Information and Monitoring Quality And Cost- TF / A0750 Prior Open - International 1,000,000.00 1,100,954.81 Signed 2018-03-22 2018-04-10 2018-04-05 2018-04-11 2018-05-17 2018-08-09 2018-06-07 2018-09-20 2018-06-28 2018-11-01 2018-08-02 2019-02-06 2018-09-06 2019-03-20 2021-09-05 National Forest Inventory and and Evaluation Based Selection Capacity Building KG-IFEMP-CQS-SM/INRMP- 02-2018 / Conducting of Social mobilization and Consultant supporting the Integrated Forest Sector Institutional TF / A0750 Post Qualification Open - National 211,000.00 209,912.49 Completed 2018-03-27 2018-03-27 2018-03-27 2018-05-01 2018-06-14 2018-05-15 2018-07-10 2018-06-19 2018-07-13 2018-12-16 2018-12-28 Natural Resource Management Reform Selection Plans (INRMPs) development in Pilot Leskhozes (second batch - 9 pilot leskhozes) KG-IFEMP-CQS-SM-INRMP- 01-2018 / Conducting of Social Mobilization and Consultant Forest Sector Institutional support the Integrated Natural TF / A0750 Post Qualification Open - National 114,518.00 118,325.11 Completed 2018-01-02 2018-01-30 2018-01-09 2018-02-13 2018-04-01 2018-03-15 2018-05-14 2018-04-19 2018-05-31 2018-10-16 2018-12-28 Reform Resource Management Plans Selection development in 5 pilot leskhozes (1 batch) KG-IFEMP-CQS-FMIS-04- 2018 / Selection of consulting Consultant Project Management, firm for establishment of TF / A0750 Post Qualification Open - National 260,000.00 0.00 Canceled 2018-05-22 2018-05-24 2018-07-15 2018-08-14 2018-09-11 2019-09-06 Monitoring and Evaluation centralized database of map Selection and attribute data KG-IFEMP-CQS-FMIS04-2018 / Selection of consulting firm Consultant Project Management, for establishment of TF / A0750 Post Qualification Open - National 259,400.00 183,296.09 Completed 2018-05-20 2018-05-29 2018-06-10 2018-07-27 2018-07-23 2018-10-20 2018-09-03 2018-11-01 2018-09-07 2019-10-01 2019-12-26 Monitoring and Evaluation centralized database of map Selection and attribute data KG-IFEMP-LCS-AUDIT-01- 2018 / FOR THE AUDIT OF Project Management, Least Cost THE INTEGRATED FOREST TF / A0750 Post Open - National 50,000.00 43,120.00 Signed 2018-10-24 2018-11-02 2018-11-07 2018-11-20 2018-12-19 2019-01-25 2018-12-19 2019-02-18 2018-12-31 2019-03-12 2019-01-17 2019-03-20 2019-02-15 2019-03-27 2021-09-30 Monitoring and Evaluation Selection ECOSYSTEM MANAGEMENT PROJECTS IFEMP-CQS-CAPACITY-06- 2019 / Organizing and Consultant Forest Sector Institutional conducting activities of TF / A0750 Post Qualification Open - National 156,000.00 105,038.14 Signed 2019-12-10 2019-12-09 2019-12-31 2019-12-11 2020-01-23 2020-01-22 2020-02-20 2020-01-16 2020-03-02 2020-03-18 2020-09-03 Reform capacity building of forestry Selection staff and forest users IFEMP-CQS-08-2020 / Consultant Forest Sector Institutional Development of PPP models TF / A0750 Post Qualification Open - National 68,000.00 58,460.14 Signed 2020-01-24 2020-01-31 2020-02-14 2020-02-06 2020-03-23 2020-03-10 2020-03-27 2020-06-01 2020-04-01 2020-06-08 2020-07-31 Reform and zoning of SFF Selection IFEMP-CQS-10-2020 / Consultant Service to product a video on Forest Sector Institutional Under TF / A0750 Post Qualification Open - National 4,130.00 0.00 2020-11-06 2020-11-19 2020-11-20 2020-11-25 2020-12-10 2020-12-11 2020-12-14 2021-02-14 results and achievements of Reform Implementation Selection IFEMP IFEMP-QCBS-FMIS2-01-2020 / The Forest Management Information and Monitoring Quality And Cost- Under TF / A0750 Post Open - International 509,448.00 0.00 2020-11-24 2021-02-04 2020-11-27 2021-01-15 2021-02-12 2021-02-19 2021-03-05 2021-03-12 2021-09-12 Information System (FMIS) and Evaluation Based Selection Implementation second phase INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IC-LEGAL-010-2018 / Legal Individual consultant on addressing Forest Sector Institutional TF / A0750 Post Consultant Limited 10,000.00 4,879.82 Completed 2018-06-05 2018-06-07 2018-06-08 2018-06-08 2018-08-13 2018-07-09 2018-08-13 2018-07-13 2019-01-13 2019-12-20 boundary issues in 2 select Reform Selection pilot Leskhozes (lawer) IC- TECH EXPET-LAND ENGENEER-011-2018 / Individual Technical expert (Land Forest Sector Institutional TF / A0750 Post Consultant Limited 5,000.00 3,423.16 Completed 2018-06-05 2018-05-21 2018-06-08 2018-06-08 2018-08-13 2018-07-09 2018-08-13 2018-07-13 2018-11-13 2019-03-29 engeneer) on addressing Reform Selection boundary issues in 2 select pilot Leskhozes IC- BOUNDARY-003/2017 / Individual Forest Sector Institutional Identify boundaries of pilot TF / A0750 Post Consultant Limited 35,000.00 7,616.03 Completed 2018-02-01 2017-09-27 2018-03-08 2017-10-13 2018-03-15 2017-11-17 2018-03-22 2017-11-27 2018-04-20 2018-04-20 Reform leskhozes Selection SSS-02/2018 / Assesment of Strategic Investments and previous experience and TF / A0750 Piloting of Sustainable Post Direct Selection Direct 3,000.00 2,527.08 Completed 2017-06-27 2017-08-14 2017-08-15 2017-07-10 2017-08-18 2017-08-18 2017-10-05 2018-02-15 Development of Mobilization Management Approaches Cuidlines SSS-02-1/2018 / Development of Guideline for Strategic Investments and preparation of Natural TF / A0750 Piloting of Sustainable Post Direct Selection Direct 3,000.00 1,510.79 Completed 2017-12-27 2017-12-27 2017-12-27 2017-12-28 2017-12-28 2018-01-29 2018-08-03 Recources Integrated Management Approaches Mangement Plan SSS-02-2/2018 / Strategic Investments and Development of templates of TF / A0750 Piloting of Sustainable Post Direct Selection Direct 2,000.00 1,870.50 Completed 2017-06-27 2017-12-27 2017-08-15 2017-12-28 2017-12-28 2018-02-02 2018-08-03 subprojects/microprojects Management Approaches and evaluation criteria Page 2 IC-PR-004/2018 / Local PIU Individual Forest Sector Institutional Public Relations and TF / A0750 Post Consultant Open 20,000.00 35,535.09 Signed 2018-10-01 2018-10-10 2018-10-25 2018-11-12 2018-10-26 2018-11-12 2018-11-01 2018-11-15 2019-11-01 Reform Communications Specialist Selection IC-CAPACITY-0114-2018 / Individual Forest Sector Institutional Short-term Consultant on TF / A0750 Post Consultant Open 5,000.00 3,224.65 Completed 2018-10-01 2018-10-10 2018-10-25 2018-11-12 2018-10-26 2018-11-11 2018-11-01 2018-11-14 2019-02-28 2019-09-10 Reform Capacity Building Selection SSS- EVAL BD-012/2018 / Short-term Consultant for Information and Monitoring evaluation of Bidding TF / A0750 Post Direct Selection Direct 600.00 576.54 Completed 2018-06-20 2018-06-22 2018-06-22 2018-06-25 2018-07-10 2018-07-10 2018-08-30 2018-08-30 and Evaluation documents on Interim Solution IC-SSS-015/2018 / TO MAKE Strategic Investments and AMENDMENTS TO THE TF / A0750 Piloting of Sustainable Post Direct Selection Direct 500.00 429.80 Signed 2018-12-17 2018-12-13 2018-12-20 2018-12-28 2018-12-28 2019-01-16 2019-01-15 GUIDELINES ON SUBPROJECTS Management Approaches AND MICRO PROJECTS IC-LEGAL-019/1-2019 / Local Legal Advisor on Individual development of proposals for Forest Sector Institutional TF / A0750 Post Consultant Open 6,000.00 7,500.79 Signed 2019-08-30 2019-09-11 2019-09-22 2019-11-05 2019-09-30 2019-11-07 2019-10-01 2019-11-11 2020-04-01 "Amendments and Additions Reform Selection to the Forest Code of the Kyrgyz Republic" IC-LEGAL-019/2-2019 / Local Legal Advisor on Individual development of proposals for Forest Sector Institutional TF / A0750 Post Consultant Open 6,000.00 5,357.71 Signed 2019-08-30 2019-09-11 2019-09-22 2019-11-06 2019-09-30 2019-11-07 2019-10-01 2019-11-11 2020-04-01 "Amendments and Additions Reform Selection to the Forest Code of the Kyrgyz Republic" IC-FOR.ISS-020-2019 / Local consultant-expert on forest Individual issues on development of Forest Sector Institutional TF / A0750 Post Consultant Open 5,000.00 4,286.17 Completed 2019-08-30 2019-09-11 2019-09-22 2019-11-05 2019-09-30 2019-11-06 2019-10-01 2019-11-11 2020-04-01 2020-12-04 proposals for "Amendments Reform Selection and Additions to the Forest Code of the Kyrgyz Republic" IC-SCIENTIFIC-021-2019 / Local scientific consultant on Individual development of proposals for Forest Sector Institutional TF / A0750 Post Consultant Open 3,000.00 2,143.08 Completed 2019-08-30 2019-09-11 2019-10-23 2019-11-05 2019-11-13 2019-11-11 2019-11-14 2019-11-11 2020-05-15 2020-12-04 "Amendments and Additions Reform Selection to the Forest Code of the Kyrgyz Republic" IC-FINANCIER-022-2019 / Local consultant - expert financier-economist on Individual Forest Sector Institutional development of proposals for TF / A0750 Post Consultant Open 3,000.00 2,143.08 Completed 2019-08-30 2019-09-11 2019-09-22 2019-11-06 2019-09-30 2019-11-06 2019-10-01 2019-11-12 2020-04-01 2020-12-04 Reform "Amendments and Additions Selection to the Forest Code of the Kyrgyz Republic" IC-FMIS2-02-2020 / Short- term consultant on the Individual development of Terms of Information and Monitoring TF / A0750 Post Consultant Open 4,000.00 3,167.99 Signed 2020-02-28 2020-03-10 2020-03-23 2020-04-20 2020-03-25 2020-04-20 2020-04-01 2020-04-21 2020-10-01 Reference for the Forest and Evaluation Selection Management Information System (second phase) IC-LEGAL-03-2020 / Individual Consultant on legal issues on Forest Sector Institutional TF / A0750 Post Consultant Open 5,000.00 6,148.44 Signed 2020-03-05 2020-03-11 2020-03-25 2020-04-20 2020-03-27 2020-04-30 2020-03-31 2020-05-06 2020-09-30 the definition of territorial Reform Selection leskhozes borders IC-LAND ENGENEER-04-2020 Individual / Land surveyor to determine Forest Sector Institutional TF / A0750 Post Consultant Open 3,000.00 4,267.92 Signed 2020-03-05 2020-03-11 2020-03-25 2020-04-20 2020-03-27 2020-04-30 2020-03-31 2020-05-06 2020-07-31 the territorial leskhozes Reform Selection borders IC-DIGITAL-06-2020 / Short- Individual Information and Monitoring term consultant on TF / A0750 Post Consultant Open 4,150.00 3,857.84 Signed 2020-07-08 2020-07-09 2020-07-31 2020-08-17 2020-08-14 2020-08-21 2020-08-20 2020-08-24 2020-12-21 and Evaluation digitalization of cartographic Selection IC-DIGITAL-07-2020 / Short- Individual Information and Monitoring term consultant on TF / A0750 Post Consultant Open 4,150.00 3,857.84 Signed 2020-07-08 2020-07-09 2020-07-31 2020-08-17 2020-08-14 2020-08-21 2020-08-20 2020-08-24 2020-12-21 and Evaluation digitalization of cartographic Selection IC-DIGITAL-08-2020 / Short- Individual Information and Monitoring term consultant on TF / A0750 Post Consultant Open 4,150.00 3,857.84 Signed 2020-07-08 2020-07-09 2020-07-31 2020-08-17 2020-08-14 2020-08-21 2020-08-20 2020-08-24 2020-12-21 and Evaluation digitalization of cartographic Selection SSS-BOUNDARY-01-2021 / Legal Consultant to review draft final reports that Forest Sector Institutional TF / A0750 Post Direct Selection 1,850.00 1,802.61 Signed 2021-01-12 2021-01-12 2021-01-14 2021-01-13 2021-02-17 2021-01-14 2021-05-18 determine/regulate Reform boundaries of At-Bashi and Talas leskhozes Page 3