PROCUREMENT PLAN (Textual Part) Project Information: Ghana Energy Sector Transformation Initiative Project (P163984) Project Implementation agency: Ministry of Energy (MoEn) Date of Procurement Plan: April 2019 Period covered by this Procurement Plan: March 2019 – September 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Ghana Public Procurement Act 2003 (Act 663) and the Ghana Public Procurement (Amendment) Act 2016 (Act 914), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable. Works: Not Applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information. None. PROCUREMENT Ghana : Ghana Energy Sector Transformation Initiative Project PLAN General Information Country: Ghana Bank’s Approval Date of the Original Procurement Plan: 2019-04-24 2021-06-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163984 GPN Date: Project Name: Ghana Energy Sector Transformation Initiative Project Loan / Credit No: IDA / 63030 Ministry of Energy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOEN-115968-GO-RFB Component 1: Management Single Stage - One / 2No. 4WD Cross Country IDA / 63030 of energy sector financial Post Request for Bids Open - National 140,000.00 134,923.23 Completed 2019-06-10 2019-06-28 2019-06-15 2019-07-27 2019-07-31 2019-08-26 2019-10-30 2019-09-30 2019-12-19 2020-01-28 2020-01-29 Envelope Vehicles flows GH-MOEN-114744-GO-RFB Component 1: Management Pending Single Stage - One / Office equipment and IDA / 63030 of energy sector financial Post Request for Bids Open - National 160,000.00 0.00 Implementati 2020-02-14 2020-02-19 2020-03-11 2020-04-10 2020-05-22 2020-08-20 Envelope furniture flows on GH-MOEN-114755-GO-RFB Component 1: Management Single Stage - One / E-Billing/E-Payment IDA / 63030 of energy sector financial Post Request for Bids Open - International 600,000.00 0.00 Canceled 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 2021-07-20 Envelope Software and Hardware flows Equipment GH-MOEN-114753-GO-RFB Pending Component 2: Sector Single Stage - One / E-Billing/E-Payment IDA / 63030 Post Request for Bids Open - International 150,000.00 0.00 Implementati 2019-08-12 2019-08-17 2019-09-28 2019-10-28 2019-12-02 2020-05-30 Planning and coordination Envelope Software and Hardware on Equipment GH-MOEN-167989-GO-DIR / Under COVID-19 Emergency Component 5: Project IDA / 63030 Prior Direct Selection Direct 10,000.00 0.00 Implementati 2020-04-13 2020-04-18 2020-05-03 2020-05-18 Response Computer management on Equipment and Accessories GH-MOEN-222040-GO-DIR / Pending Upgrade of GRIDCo’s SCADA Component 2: Sector IDA / 63030 Prior Direct Selection Direct 2,600,000.00 0.00 Implementati 2021-06-30 2021-07-14 2021-10-06 2022-10-06 Network Management System Planning and coordination on and Telecommunications NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOEN-114762-CS-CQS Component 1: Management Consultant / Street-lighting Tariff IDA / 63030 of energy sector financial Post Qualification Open - National 50,000.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-09-13 2019-10-18 2020-01-16 Analysis flows Selection GH-MOEN-114763-CS-LCS / Component 2: Sector Least Cost Gas and Power Sector IDA / 63030 Post Open - International 100,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-13 2020-01-17 2020-05-16 Planning and coordination Selection Coordination Study GH-MOEN-114850-CS-QCBS Component 1: Management Quality And Cost- / Technical Audit of Power IDA / 63030 of energy sector financial Post Open - International 200,000.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-09-11 2019-10-11 2019-11-15 2019-12-20 2020-04-18 Based Selection Plants flows GH-MOEN-114851-CS-QCBS / Satellite and Field Survey Quality And Cost- IDA / 63030 Component 3: Energy access Post Open - International 250,000.00 198,880.00 Signed 2019-06-10 2019-09-17 2019-07-01 2019-10-10 2019-08-14 2020-03-13 2019-09-11 2020-05-11 2019-10-11 2020-09-30 2019-11-15 2020-12-18 2019-12-20 2021-01-18 2020-04-18 Analysis and Upgrade of Based Selection Existing Geospatial Software GH-MOEN-114855-CS-QCBS / eGIS for NEDCo Techiman Quality And Cost- IDA / 63030 Component 3: Energy access Prior Open - International 1,750,000.00 1,561,500.00 Signed 2019-06-10 2019-12-05 2019-07-01 2020-01-31 2019-08-14 2020-05-27 2019-09-11 2020-07-24 2019-10-11 2020-08-25 2019-11-15 2020-11-23 2019-12-20 2020-12-10 2021-06-12 and Parts of Sunyani Based Selection Operational Areas GH-MOEN-114869-CS-QCBS Quality And Cost- / Feasibility study to improve IDA / 63030 Component 4: Natural gas Post Open - International 300,000.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-09-11 2019-10-11 2019-11-15 2019-12-20 2020-04-18 Based Selection efficiency of GNGC plants GH-MOEN-114871-CS-QCBS / Study to optimize LNG to Quality And Cost- incorporate bulk-breaking IDA / 63030 Component 4: Natural gas Post Open - International 300,000.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-09-11 2019-10-11 2019-11-15 2019-12-20 2020-04-18 Based Selection capabilities and possibility of extracting LPG GH-MOEN-114873-CS-QCBS / Strategy for Competitive Quality And Cost- IDA / 63030 Component 4: Natural gas Post Open - International 150,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-13 2020-01-17 2020-06-25 Tendering of Gas/LNG Based Selection Volumes Page 1 GH-MOEN-114876-CS-QCBS / Study on deregulation of Quality And Cost- transportation in the IDA / 63030 Component 4: Natural gas Post Open - International 250,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-13 2020-01-17 2020-05-16 Based Selection petroleum downstream industry GH-MOEN-114880-CS-QCBS / Control of Major Accident Quality And Cost- IDA / 63030 Component 4: Natural gas Post Open - International 270,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-13 2020-01-17 2020-05-16 Hazards (COMAH) Regulations Based Selection Study GH-MOEN-114882-CS-QCBS / Control of Major Accident Quality And Cost- IDA / 63030 Component 4: Natural gas Post Open - International 270,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-13 2020-01-17 2020-05-16 Hazards (COMAH) Regulations Based Selection Study GH-MOEN-114885-CS-QCBS Component 1: Management / Management of Quality And Cost- IDA / 63030 of energy sector financial Post Open - International 400,000.00 0.00 Canceled 2019-08-12 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2020-08-19 Implementation of Approved Based Selection flows VRA Restructuring GH-MOEN-114886-CS-QCBS Component 2: Sector Quality And Cost- / Gas Regulatory Framework IDA / 63030 Post Open - International 500,000.00 0.00 Canceled 2019-08-12 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2020-06-20 Planning and coordination Based Selection and Institutional Setup studies GH-MOEN-114887-CS-QCBS / Electricity Regulatory Component 2: Sector Quality And Cost- IDA / 63030 Post Open - International 500,000.00 0.00 Canceled 2019-08-12 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2020-06-20 Framework and Institutional Planning and coordination Based Selection Setup studies GH-MOEN-114888-CS-QCBS Component 2: Sector Quality And Cost- IDA / 63030 Post Open - International 200,000.00 0.00 Canceled 2019-08-12 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2020-06-20 / Fuel Procurement Strategy Planning and coordination Based Selection GH-MOEN-114889-CS-QCBS Quality And Cost- / Distribution Master Plan IDA / 63030 Component 3: Energy access Post Open - International 500,000.00 467,573.40 Signed 2019-08-12 2019-06-10 2019-09-02 2019-08-21 2019-10-16 2020-03-13 2019-11-13 2020-05-07 2019-12-13 2020-08-14 2020-01-17 2020-09-22 2020-02-21 2020-11-16 2020-08-19 Based Selection Studies GH-MOEN-114890-CS-QCBS / Update of Distribution and Quality And Cost- IDA / 63030 Component 3: Energy access Post Open - International 170,000.00 414,250.00 Signed 2019-08-12 2019-08-21 2019-09-02 2019-10-10 2019-10-16 2020-03-13 2019-11-13 2020-05-06 2019-12-13 2020-08-14 2020-01-17 2020-10-12 2020-02-21 2020-11-16 2020-08-19 Construction Standards Based Selection Studies GH-MOEN-114891-CS-QCBS Quality And Cost- / Gas market review and IDA / 63030 Component 4: Natural gas Post Open - International 320,000.00 0.00 Canceled 2019-08-12 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2020-08-19 Based Selection market development study GH-MOEN-114893-CS-QCBS Quality And Cost- Pending / Cost-Reflective Gas Tariff IDA / 63030 Component 4: Natural gas Post Open - International 150,000.00 0.00 2020-02-24 2020-03-16 2020-04-29 2020-05-27 2020-06-26 2020-07-31 2020-09-04 2021-01-02 Based Selection Implementation Methodology Study GH-MOEN-114879-CS-QCBS Quality And Cost- Under / Development of Natural Gas IDA / 63030 Component 4: Natural gas Post Open - International 300,000.00 0.00 2020-03-02 2020-04-03 2020-03-23 2020-04-18 2020-05-06 2020-08-26 2020-06-03 2020-09-29 2020-07-03 2020-10-11 2020-08-07 2020-09-11 2021-01-09 Based Selection Implementation Distribution franchise in Tema GH-MOEN-114874-CS-QCBS / Strategy for Balancing Quality And Cost- Under IDA / 63030 Component 4: Natural gas Post Open - International 250,000.00 0.00 2020-03-02 2020-04-03 2020-03-23 2020-04-18 2020-05-06 2020-08-20 2020-06-03 2020-09-28 2020-07-03 2020-10-11 2020-08-07 2020-09-11 2021-03-10 Natural Gas Demand and Based Selection Implementation Supply GH-MOEN-114872-CS-QCBS Component 2: Sector Quality And Cost- Pending / Grid Resilience and IDA / 63030 Post Open - International 400,000.00 0.00 2020-10-05 2020-10-26 2020-12-09 2021-01-06 2021-02-05 2021-03-12 2021-04-16 2021-10-13 Planning and coordination Based Selection Implementation Reinforcement Study GH-MOEN-114854-CS-QCBS / Consumer and Market Assessment Study and Quality And Cost- IDA / 63030 Component 3: Energy access Post Open - International 180,000.00 163,770.00 Signed 2020-03-03 2020-02-08 2020-03-24 2020-02-19 2020-05-07 2020-06-15 2020-06-04 2020-07-22 2020-07-04 2020-09-02 2020-08-08 2020-10-22 2020-09-12 2020-11-20 2021-01-10 Development of National Based Selection Clean Cooking Strategy for Ghana GH-MOEN-114852-CS-QCBS Quality And Cost- Pending / Feasibility and Investment IDA / 63030 Component 3: Energy access Post Open - International 250,000.00 0.00 2020-07-06 2020-07-27 2020-09-09 2020-10-07 2020-11-06 2020-12-11 2021-01-15 2021-05-15 Based Selection Implementation Planning Studies GH-MOEN-156217-CS-QCBS Component 1: Management / Legal and Financial Review Quality And Cost- Pending IDA / 63030 of energy sector financial Post Open - International 150,000.00 0.00 2020-03-02 2020-03-23 2020-05-06 2020-06-03 2020-07-03 2020-08-07 2020-09-11 2021-01-09 of Backlog of Power Purchase Based Selection Implementation flows Agreements GH-MOEN-156224-CS-QCBS Component 1: Management Quality And Cost- Under / Audit and Review of the IDA / 63030 of energy sector financial Post Open - International 300,000.00 0.00 2020-03-02 2020-10-14 2020-03-23 2020-11-17 2020-05-06 2020-06-03 2020-07-03 2020-08-07 2020-09-11 2021-01-09 Based Selection Implementation Legacy Debt flows GH-MOEN-156226-CS-LCS / Component 1: Management Independent Assessment and Least Cost Pending IDA / 63030 of energy sector financial Post Open - International 80,000.00 0.00 2020-04-06 2020-04-27 2020-06-10 2020-07-08 2020-08-07 2020-09-11 2020-10-16 2021-01-14 Drafting of all Required Selection Implementation flows Changes in PURC Act GH-MOEN-156229-CS-QCBS / Integration of PURC Component 2: Sector Quality And Cost- IDA / 63030 Post Open - International 300,000.00 0.00 Canceled 2020-03-02 2020-05-27 2020-03-23 2020-10-14 2020-05-06 2020-06-03 2020-07-03 2020-08-07 2020-09-11 2021-01-09 Database with Utility Providers Planning and coordination Based Selection to get Real-time Data GH-MOEN-156230-CS-QCBS Component 2: Sector Quality And Cost- Under / Review of Ghana Petroleum IDA / 63030 Post Open - International 300,000.00 0.00 2020-03-02 2020-04-03 2020-03-23 2020-04-18 2020-05-06 2020-08-20 2020-06-03 2020-09-29 2020-07-03 2020-10-11 2020-08-07 2020-09-11 2021-01-09 Planning and coordination Based Selection Implementation Products Price Build-Up GH-MOEN-156234-CS-QCBS Component 2: Sector Quality And Cost- Pending / Gap and Regional Market IDA / 63030 Post Open - International 110,000.00 0.00 2020-10-05 2020-10-26 2020-12-09 2021-01-06 2021-02-05 2021-03-12 2021-04-16 2021-10-13 Planning and coordination Based Selection Implementation Analysis GH-MOEN-167986-CS-QCBS / Cash Water-Fall Mechanism Component 1: Management Quality And Cost- Pending Real-Time IT Platform IDA / 63030 of energy sector financial Post Open - International 100,000.00 0.00 2020-04-20 2020-05-11 2020-06-24 2020-07-22 2020-08-21 2020-09-25 2020-10-30 2021-04-28 Based Selection Implementation Development and flows Implementation Page 2 Component 1: Management GH-MOEN-167993-CS-LCS / Least Cost Pending IDA / 63030 of energy sector financial Post Open - International 60,000.00 0.00 2020-05-10 2020-05-31 2020-07-21 2020-08-18 2020-09-17 2020-10-22 2020-11-26 2021-03-06 Streetlighting Tariff Analysis Selection Implementation flows GH-MOEN-189339-CS-QCBS Component 1: Management Quality And Cost- Under / Consultancy for Assessment IDA / 63030 of energy sector financial Post Open - International 300,000.00 0.00 2020-08-20 2020-08-25 2020-09-03 2020-09-16 2020-10-15 2020-11-12 2020-12-10 2021-01-07 2021-02-11 2021-12-08 Based Selection Implementation of Street-lighting In Ghana flows GH-MOEN-189356-CS-QCBS Component 1: Management / Consultancy Services for Quality And Cost- Under IDA / 63030 of energy sector financial Post Open - International 500,000.00 0.00 2020-08-21 2020-08-25 2020-09-11 2020-11-17 2020-10-25 2020-11-22 2020-12-22 2021-01-26 2021-03-02 2021-12-27 Technical Audit of Power Based Selection Implementation flows Plants GH-MOEN-220368-CS-QCBS Quality And Cost- Under / Network Protection and IDA / 63030 Component 3: Energy access Post Open - International 500,000.00 0.00 2021-03-07 2021-04-12 2021-04-04 2021-04-28 2021-05-18 2021-06-15 2021-07-15 2021-08-19 2021-09-23 2022-03-22 Based Selection Implementation Coordination Study for NEDCo GH-MOEN-222022-CS-QCBS / Development of Component 1: Management Quality And Cost- Pending Methodologies for IDA / 63030 of energy sector financial Post Open - International 500,000.00 0.00 2021-03-15 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2022-03-30 Based Selection Implementation Competitive Selection for ECG flows Governance Structure GH-MOEN-222023-CS-QCBS / Technical and Legal Support Quality And Cost- Pending IDA / 63030 Component 4: Natural gas Post Open - International 300,000.00 0.00 2021-05-24 2021-06-21 2021-08-04 2021-09-01 2021-10-01 2021-11-05 2021-12-10 2022-06-08 for Implementation of Gas Based Selection Implementation Aggregator Role GH-MOEN-222025-CS-QCBS / Update of Tariff Component 1: Management Quality And Cost- Pending Methodology, Design and IDA / 63030 of energy sector financial Post Open - International 250,000.00 0.00 2021-03-15 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2022-03-30 Based Selection Implementation Implementation of Customer flows Satisfaction Index (CSI) GH-MOEN-222026-CS-QCBS / Development of CRM Component 2: Sector Quality And Cost- Pending IDA / 63030 Post Open - International 250,000.00 0.00 2021-03-15 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2021-12-30 Communication and Public Planning and coordination Based Selection Implementation Relations Implementation Plan GH-MOEN-222027-CS-QCBS / Development of COMAH and Quality And Cost- IDA / 63030 Component 4: Natural gas Post Open - International 250,000.00 0.00 Under Review 2021-05-24 2021-06-17 2021-06-21 2021-08-04 2021-09-01 2021-10-01 2021-11-05 2021-12-10 2022-04-09 Natural Gas Distribution Based Selection Regulations GH-MOEN-222028-CS-QCBS / Review of Natural Gas Quality And Cost- Transmission and Distribution IDA / 63030 Component 4: Natural gas Post Open - International 300,000.00 0.00 Under Review 2021-03-15 2021-06-17 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2021-12-30 Based Selection Infrastructure Development Plan of Ghana GH-MOEN-222030-CS-QCBS / Estimation of the Value of Component 2: Sector Quality And Cost- IDA / 63030 Post Open - International 250,000.00 0.00 Under Review 2021-03-15 2021-06-17 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2021-10-15 Lost Load (VoLL) of Electricity Planning and coordination Based Selection Supply in Ghana GH-MOEN-222032-CS-QCBS Component 1: Management / Development of Fuel Quality And Cost- Pending IDA / 63030 of energy sector financial Post Open - International 200,000.00 0.00 2021-05-17 2021-06-14 2021-07-28 2021-08-25 2021-09-24 2021-10-29 2021-12-03 2022-03-03 Procurement Strategy for Based Selection Implementation flows Ghana GH-MOEN-222034-CS-QCBS / Development of CRM Component 2: Sector Quality And Cost- Monitoring and Evaluation IDA / 63030 Post Open - International 200,000.00 0.00 Under Review 2021-03-15 2021-06-17 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2021-12-30 Planning and coordination Based Selection Framework and CRM Baseline Study for NPA GH-MOEN-222036-CS-QCBS Quality And Cost- Pending / Analysis of Gas Value Chain IDA / 63030 Component 4: Natural gas Post Open - International 300,000.00 0.00 2021-04-05 2021-05-03 2021-06-16 2021-07-14 2021-08-13 2021-09-17 2021-10-22 2022-04-20 Based Selection Implementation Costs GH-MOEN-240109-CS-QCBS / Consultancy Services To Component 2: Sector Quality And Cost- Pending Develop Of LPG Behavioural IDA / 63030 Post Open - International 300,000.00 0.00 2021-06-23 2021-07-14 2021-08-27 2021-09-24 2021-10-24 2021-11-28 2022-01-02 2022-07-31 Planning and coordination Based Selection Implementation Change And Public Awareness Strategy INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOEN-110263-CS-CDS / Component 5: Project IDA / 63030 Prior Direct Selection Direct 102,924.00 137,232.00 Signed 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 Power Sector Specialist management GH-MOEN-110277-CS-CDS / Component 5: Project IDA / 63030 Prior Direct Selection Direct 56,700.00 75,600.00 Signed 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 Social & Gender Specialist management GH-MOEN-110279-CS-CDS / Component 5: Project IDA / 63030 Prior Direct Selection Direct 40,080.00 40,080.00 Signed 2019-05-27 2019-08-28 2019-06-10 2019-09-12 2019-09-23 2019-09-27 2020-09-30 Renewable Electricity Expert management GH-MOEN-113272-CS-CDS / Component 5: Project IDA / 63030 Prior Direct Selection Direct 162,162.00 0.00 Canceled 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2021-12-31 Project Manager management GH-MOEN-113274-CS-CDS / Component 5: Project Financial Management IDA / 63030 Prior Direct Selection Direct 130,977.00 174,636.00 Signed 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 management Specialist GH-MOEN-113275-CS-CDS / Component 5: Project IDA / 63030 Prior Direct Selection Direct 109,161.00 145,548.00 Signed 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 Procurement Specialist management GH-MOEN-113276-CS-CDS / Component 5: Project Monitoring & Evaluation IDA / 63030 Prior Direct Selection Direct 85,779.00 114,372.00 Signed 2019-05-27 2019-08-28 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 management Specialist GH-MOEN-113277-CS-CDS / Component 5: Project IDA / 63030 Prior Direct Selection Direct 67,500.00 90,000.00 Signed 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 Communication Specialist management Page 3 Individual GH-MOEN-113280-CS-INDV Component 5: Project IDA / 63030 Prior Consultant Open 110,200.00 133,200.00 Signed 2019-05-20 2019-06-18 2019-07-01 2019-09-16 2019-07-08 2019-09-20 2019-07-29 2019-09-30 2021-12-31 / Gas Sector Specialist management Selection Component 1: Management Individual GH-MOEN-150645-CS-INDV IDA / 63030 of energy sector financial Post Consultant Limited 216,000.00 144,000.00 Signed 2019-12-24 2019-12-22 2019-12-29 2020-01-13 2020-01-08 2020-01-27 2020-01-22 2020-02-28 2023-01-21 / Technical Coordinator flows Selection Component 1: Management Individual GH-MOEN-151138-CS-INDV IDA / 63030 of energy sector financial Post Consultant Limited 108,000.00 96,000.00 Signed 2019-12-24 2019-12-22 2019-12-29 2020-01-13 2020-01-08 2020-01-27 2020-01-22 2020-04-23 2023-01-21 / Policy Advisor flows Selection GH-MOEN-151141-CS-INDV / Consultancy Services for the Component 1: Management Individual Preparation of Procedures and IDA / 63030 of energy sector financial Post Consultant Limited 10,000.00 22,000.00 Signed 2019-12-24 2019-12-22 2019-12-29 2020-01-13 2020-01-08 2020-01-27 2020-01-22 2020-02-28 2020-02-21 Operational Document for flows Selection Implementation of Cash Water- Fall Mechanism GH-MOEN-167982-CS-INDV Component 1: Management Individual / Cash Water-Fall Mechanism IDA / 63030 of energy sector financial Post Consultant Limited 144,000.00 144,000.00 Signed 2020-04-20 2020-06-15 2020-04-30 2020-06-22 2020-05-21 2020-07-23 2020-06-25 2020-07-29 2022-06-15 Independent Accountant flows Selection GH-MOEN-167984-CS-INDV Component 1: Management Individual / Cash Water-Fall Mechanism IDA / 63030 of energy sector financial Post Consultant Limited 60,000.00 600,000.00 Signed 2020-04-20 2020-06-15 2020-04-30 2020-06-22 2020-05-21 2020-07-23 2020-06-25 2020-07-29 2022-06-15 Financial Analyst flows Selection GH-MOEN-174618-CS-INDV / Consultancy Services To Support NEDCo In The Component 1: Management Individual Definition Of An Action Plan IDA / 63030 of energy sector financial Post Consultant 50,000.00 0.00 Canceled 2020-05-25 2020-05-30 2020-06-20 2020-07-14 2020-10-12 For Improvement Of Revenue flows Selection Cycle And Prepayment Operations GH-MOEN-175924-CS-INDV / Consultancy Services To Support NEDCo In The Component 1: Management Individual Under Definition Of An Action Plan IDA / 63030 of energy sector financial Post Consultant Limited 50,000.00 0.00 2020-06-02 2020-08-18 2020-06-07 2020-06-28 2020-07-26 2020-10-24 Implementation For Improvement Of Revenue flows Selection Cycle And Prepayment Operations GH-MOEN-202785-CS-INDV / CONSULTANCY SERVICES Individual FOR LEGAL REVIEW OF THE IDA / 63030 Component 4: Natural gas Post Consultant Limited 150,000.00 68,181.82 Signed 2020-11-06 2020-11-05 2020-11-11 2020-11-11 2020-11-20 2020-12-03 2020-11-27 2020-12-09 2021-01-29 TAKORADI GAS SALES Selection AGREEMENT BETWEEN N-GAS AND VRA GH-MOEN-202793-CS-INDV / CONSULTANCY SERVICES Individual FOR COMMERCIAL REVIEW OF IDA / 63030 Component 4: Natural gas Post Consultant Limited 75,000.00 33,792.60 Signed 2020-11-06 2020-11-05 2020-11-11 2020-11-10 2020-11-20 2020-12-03 2020-11-27 2020-12-09 2021-01-29 THE TAKORADI GAS SALES Selection AGREEMENT BETWEEN N-GAS AND VRA GH-MOEN-204420-CS-INDV / Technical Assistance for Capacity Development and Component 1: Management Individual Under Tooling For Regulatory IDA / 63030 of energy sector financial Post Consultant Limited 60,000.00 0.00 2020-11-16 2020-11-12 2020-11-21 2020-12-11 2020-12-21 2021-03-21 Implementation Appraisal and Monitoring of flows Selection Performance Improvement Projects GH-MOEN-206473-CS-INDV / INTEGRATION OF PURC Individual Component 2: Sector Under DATABASE WITH UTILITY IDA / 63030 Post Consultant Limited 70,000.00 0.00 2020-11-27 2021-01-08 2020-12-02 2020-12-23 2021-01-27 2021-03-28 Planning and coordination Implementation PROVIDERS TO GET REAL- Selection TIME DATA IN GHANA GH-MOEN-240091-CS-INDV / PREPARATION OF Individual ENVIRONMENTAL AND SOCIAL Component 2: Sector Pending IDA / 63030 Post Consultant Limited 70,000.00 0.00 2021-06-24 2021-07-04 2021-07-25 2021-08-14 2021-11-12 MANAGEMENT FRAMEWORK Planning and coordination Implementation Selection (ESMF) FOR ELECTRICITY COMPANY OF GHANA (ECG) Page 4