Sample Procurement Plan I. General 1. Bank’s approval Date of the Procurement Plan: Original, October 2011; Revision 1, October 2013. 2. Date of General Procurement Notice: October 2011 3. Period covered by this procurement plan: From January 2018 to January 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB (Works) All All 2. ICB (Goods and Non-Consulting All All Services) 3. NCB (Works) From US$ 10 million All 4. NCB (Goods and Non-Consulting From US$ 2 million All Services) 5. Shopping (Works) None None 6. Shopping (Goods and Non- None None Consulting Services) 7. Direct Contracting (Works) From US$ 10 million All Direct Contracting (Goods and Non- From US$ 2 million All Consulting Services) 2. Prequalification. Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: Not applicable. 4. Reference to (if any) Project Operational/Procurement Manual: The Project Operations Manual describes the methods and procedures applicable to all procurement of goods, works, non-consulting services and consulting services financed by the Loan Agreement # 8113-BR. 5. Any Other Special Procurement Arrangements: Not applicable. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) July 9, 2010 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior/Post) million nce (yes/no) 1 Summary of 0.7 2 No Post the NCBs (Goods) 2 Summary of 6.3 10 No Prior/Post 1 package the NCBs subjects to (Non- prior Consulting review Services) 3 Summary of 6.3 4 No Post the NCBs (Works) 4 Summary of 0.07 1 No Post the Shoppings (Goods) 5 Summary of 0.09 5 No Post the Shoppings (Non- Consulting Services) 6 Summary of 0.15 2 No Post the Shoppings (Works) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) From US$ 1 million All 2. Single Source Selection (Firms) From US$ 1 million All 3. Individual Consultant From US$ 300,000 All 4 Single Source Selection (Individuals) From US$ 300,000 All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 1,500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Estimated Packages Review Comments July 9, 2010 Description of Cost by Bank Assignment US$ (Prior / Post) million 1 Summary of 2.0 10 Post number of contracts that will be let under QCBS method 2 Summary of 0.5 3 Post LCS number of contracts that will be let under methods other than QCBS 3 Summary of 0.85 6 Prior/Post 2 number of Package contracts that subject to will be let prior under review Individual Consultant method July 9, 2010 PROCUREMENT Brazil : BR Sergipe Water PLAN General Information Country: Brazil Bank’s Approval Date of the Original Procurement Plan: 2017-10-06 2019-10-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P112074 GPN Date: Project Name: BR Sergipe Water Loan / Credit No: IBRD / 81130 Executing Agency(ies): Secretariat of Environment and Water Resources of the State of Sergipe WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 12123A / Recuperação da Estrutura Fisica das Barragens dos Reservatorios Component 2: Water for Solicitação de Single Stage - One IBRD / 81130 Posterior Open - National 0.00 Cancelado 2017-10-15 2017-10-20 2017-12-01 2017-12-31 2018-02-04 2018-08-03 Jacarecica I, Jacarecica II, Irrigation Propostas Envelope Governador Joao Alves Filho, Jaime Umbelino de Souza. 21123C / Reforma da estrutura fisica dos escritórios dos perímetros Em fase de irrigados Jacarecica I, Component 2: Water for Solicitação de Single Stage - One IBRD / 81130 Posterior Open - National 0.00 Implementaçã 2017-10-30 2017-11-04 2017-12-16 2018-01-15 2018-02-19 2018-08-18 Jacarecica II, Gov Joao Irrigation Propostas Envelope o Alves Filho (Ribeira) e das Diretorias Tecnicas na sede da COHIDRO 21230 / Implantacao de novo sistema de irrigacao localizada, com fornecimento de equipamentos e materiais, Component 2: Water for Solicitação de Single Stage - One Implementaçã nos perimetros irrigados IBRD / 81130 Posterior Open - National 0.00 2017-07-20 2017-07-25 2018-01-09 2018-02-08 2018-03-15 2018-10-11 Irrigation Propostas Envelope o Pendente Jacarecica I e Poção da Ribeira (Barragem Governador Joao Alves Filho). 21280 / Implantacao de Projetos de Irrigação Localizada com fornecimento Em fase de Component 2: Water for Solicitação de Single Stage - One de Material e Capacitcaão IBRD / 81130 Posterior Open - National 0.00 Implementaçã 2017-11-30 2017-12-05 2018-01-16 2018-02-15 2018-03-22 2018-09-18 Irrigation Propostas Envelope dos Agricultores Familiares o beneficiarios na sub bacia do Rio Jacarecica. 21122C / Instalar Descarga de Fundo nas Barragens Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2018-09-01 2018-09-06 2018-10-06 2018-10-16 2018-11-05 2019-05-04 Jacarecica II e Governador Irrigation Propostas Envelope o Pendente João Alves Filho 21122D / Implantação de Component 2: Water for Solicitação de Single Stage - One Implementaçã stop-log na barragem do IBRD / 81130 Posterior Open - National 0.00 2018-09-01 2018-09-06 2018-10-18 2018-11-17 2018-12-22 2019-04-21 Irrigation Propostas Envelope o Pendente reservatório Jacarecica II 21242 / Implantação da modernização e automação dos sistemas de Component 3: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2019-03-11 2019-03-16 2019-04-27 2019-05-27 2019-07-01 2020-04-16 bombeamento para irrigação Cities Propostas Envelope o Pendente nos perímetros Jacarecica I e Gov. João Alves Filho Page 1 22372 / Contratacao de empresa para execucao de servicos de reforma e montagem de estufas, viveiros telados, bancadas Component 2: Water for Solicitação de Single Stage - One IBRD / 81130 Posterior Open - National 0.00 Cancelado 2017-12-15 2018-02-09 2018-08-08 para producao de mudas e Irrigation Cotações Envelope sistema de irrigacao, com fornecimento de materiais e equipamentos, para o Horto da EMDAGRO 23342B / Contratação de empresa para execução das obras de reforma do Component 2: Water for Solicitação de Single Stage - One Implementaçã Escritório Local da IBRD / 81130 Posterior Open - National 0.00 2019-08-26 2019-08-31 2019-09-25 2019-10-10 2019-10-29 2020-04-26 Irrigation Propostas Envelope o Pendente EMDAGRO em Itabaiana, na Bacia Hidrográfica do rio Sergipe 23342A / Contratação de empresa para execução das obras de construção do Component 2: Water for Solicitação de Single Stage - One Implementaçã Escritório Local da IBRD / 81130 Posterior Open - National 0.00 2019-08-26 2019-08-31 2019-09-20 2019-10-10 2019-10-30 2020-04-27 Irrigation Propostas Envelope o Pendente EMDAGRO em Ribeirópolis, na Bacia Hidrográfica do rio Sergipe. 23342C / Contratação de empresa para execução das Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2019-08-26 2019-08-31 2019-09-25 2019-10-10 2019-11-01 2020-04-29 obras de reforma da Sede Irrigation Propostas Envelope o Pendente da EMDAGRO em Aracaju 22322 / Contratação de empresa especializada para execução de obras de instalação de Unidade Demonstrativa Piloto de Component 2: Water for Solicitação de Single Stage - One IBRD / 81130 Posterior Open - National 0.00 Cancelado 2018-08-15 2018-08-20 2018-09-19 2018-09-29 2018-10-30 2019-04-28 Conservação de Água e Solo Irrigation Propostas Envelope no Campo de Difusão de Tecnologias da EMDAGRO, em Itabaiana, na sub bacia do rio Jacarecica, na BHRS. 22371 / Execucao das obras civis para construcao de cisterna, servcços de Component 2: Water for Solicitação de Single Stage - One nivelamento e de IBRD / 81130 Posterior Open - National 0.00 Cancelado 2017-09-20 2017-11-15 2018-05-14 Irrigation Cotações Envelope pavimentacao de estruturas teladas para ampliacao do Horto da EMDAGRO 22322A / Execução de obras de reforma e construção de instalações rurais para implantação de Em fase de Unidade Demonstrativa Component 2: Water for Solicitação de Single Stage - One IBRD / 81130 Posterior Open - National 0.00 Implementaçã 2019-09-09 2019-09-14 2019-10-14 2019-11-03 2019-12-08 2020-04-08 Piloto de Conservação de Irrigation Propostas Envelope o Água e Solo em Itabaiana, na sub bacia do rio Jacarecica, bacia hidrográfica do rio Sergipe. 21123D / Realização de serviços de recuperação da estrutura física das Component 2: Water for Solicitação de Single Stage - One Implementaçã barragens dos reservatórios IBRD / 81130 Posterior Open - National 0.00 2019-07-26 2019-07-31 2019-09-11 2019-10-11 2019-11-15 2020-04-23 Irrigation Propostas Envelope o Pendente Jacarecica I, Jacarecica II, Governador João Alves Filho, Jaime Umbelino de Souza Page 2 11220 / Execução de Obra Component 1: Integrated de construção e reforma do Water Resource Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2019-10-28 2019-11-12 2019-12-12 2019-12-22 2020-01-11 2020-04-30 atual prédio da SERHMA Management and Propostas Envelope o Pendente para abrigar a SEDURBS. Institutional Development 11250 / Reforma da SEDURBS compreendendo reforma de salas, auditório, Component 1: Integrated almoxarifado, depósito, Water Resource Solicitação de Single Stage - One banheiros, revisão de IBRD / 81130 Posterior Open - National 0.00 Cancelado 2019-08-26 2019-08-31 2019-10-12 2019-11-11 2019-12-16 2020-04-14 Management and Propostas Envelope cobertura, pinturas externas Institutional Development dos blocos e dos muros e recuperação dos portões para acolher a extinta SEMARH. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 22331 / Aquisição de equipamentos eletroeletrônicos para estruturação do centro de Component 2: Water for Solicitação de Single Stage - One IBRD / 81130 Posterior Open - National 0.00 Cancelado 2017-12-20 2018-02-14 2018-08-13 capacitação e difusão da Irrigation Cotações Envelope agroecologia de Itabaiana e escritórios locais da EMDAGRO 22332 / Aquisição de mobiliário e equipamentos de escritório para estruturação Component 2: Water for Solicitação de Single Stage - One Implementaçã do Centro de Capacitação e IBRD / 81130 Posterior Open - National 0.00 2017-12-21 2018-02-15 2018-08-14 Irrigation Cotações Envelope o Pendente Difusão da Agroecologia de Itabaiana e escritórios locais da EMDAGRO 22333 / Aquisição de mobiliário e quipamentos e utensílios de copa e cozinha para a estruturação do Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2017-12-22 2018-02-16 2018-08-15 centro de capacitação e Irrigation Cotações Envelope o Pendente difusão da agroecologia de Itabaiana e escritórios locais da EMDAGRO 22334 / Aquisição de máquinas, equipamentos e materiais agrícolas para a Component 2: Water for Solicitação de Single Stage - One Implementaçã etruturação do Centro de IBRD / 81130 Posterior Open - National 0.00 2017-12-23 2018-02-17 2018-08-16 Irrigation Cotações Envelope o Pendente Capacitação e Difusão da Agroecologia de Itabaiana da EMDAGRO 35110 / Aquisicao de materiais e equipamentos para o Programa de Reducao Component 3: Water for Solicitação de Single Stage - One IBRD / 81130 Prévia Open - National 0.00 Cancelado 2017-10-17 2017-10-22 2017-12-03 2018-01-02 2018-02-06 2018-08-05 e Controle de Perdas (PRCP) Cities Propostas Envelope para o SIA Aracaju e SAA Itabaiana 11230 / Aquisição de Component 1: Integrated Mobiliários, equipamentos de Water Resource Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2018-04-09 2018-04-14 2018-05-26 2018-06-25 2018-07-30 2019-01-26 comunicação e informática Management and Propostas Envelope o Pendente para a SEMARH. Institutional Development Page 3 14210 / Aquisição de Component 1: Integrated equipamentos de informática Water Resource Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2018-04-10 2018-04-10 2018-04-10 2018-04-10 2018-05-30 2018-07-29 para o funcionamento da Management and Propostas Envelope o Pendente AGRESE Institutional Development 23111 / Aquisição de veículos de pequeno porte - Component 2: Water for Solicitação de Single Stage - One Implementaçã camionetes cabine dupla - IBRD / 81130 Posterior Open - National 0.00 2018-04-10 2018-04-10 2018-04-10 2018-04-10 2018-06-09 2018-09-07 Irrigation Propostas Envelope o Pendente para a EMDAGRO e para a COHIDRO 23120 / Aquisição de equipamento de informática e multimídia para Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2018-04-09 2018-04-14 2018-05-26 2018-06-25 2018-07-30 2019-01-26 desenvolvimento institucional Irrigation Propostas Envelope o Pendente da EMDAGRO e da COHIDRO 23320 / Aquisição de veículos, equipamentos e Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2018-04-10 2018-04-15 2018-05-27 2018-06-26 2018-07-31 2019-01-27 trator como fortalecimento Irrigation Propostas Envelope o Pendente institucional da EMDAGRO 211210B / Implantar Component 2: Water for Solicitação de Single Stage - One Implementaçã instrumentação geotécnica na IBRD / 81130 Posterior Open - National 0.00 2018-09-01 2018-09-06 2018-10-06 2018-10-20 2018-11-04 2019-05-03 Irrigation Propostas Envelope o Pendente Barragem Jacarecica I 23321 / Aquisição de Trator Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 2018-11-20 para o CDT da EMDAGRO Irrigation Propostas Envelope o Pendente 23111A / Aquisição de Component 2: Water for Solicitação de Single Stage - One Implementaçã camionetes cabine dupla IBRD / 81130 Posterior Open - National 0.00 2018-07-20 2018-07-25 2018-09-05 2018-10-05 2018-11-09 2019-02-17 Irrigation Propostas Envelope o Pendente para a Emdagro 23230 / Aquisição de equipamentos de apoio a Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2018-07-10 2018-07-15 2018-08-26 2018-09-25 2018-10-30 2019-04-28 perfuração de poços, veículos Irrigation Propostas Envelope o Pendente e barcos 23380 / Aquisição de diversos equipamentos para Component 2: Water for Solicitação de Single Stage - One Implementaçã dotar o ITPS de laboratório IBRD / 81130 Posterior Open - National 0.00 2019-08-09 2019-08-14 2019-09-25 2019-10-25 2019-11-29 2020-04-27 Irrigation Propostas Envelope o Pendente de análise de agrotóxicos nos alimentos 22331A / Aquisição de tendas articuladas para a Em fase de estruturação do Centro de Component 3: Water for Solicitação de Single Stage - One IBRD / 81130 Posterior Open - National 0.00 Implementaçã 2019-09-09 2019-09-14 2019-10-03 2019-11-07 2020-03-06 Capacitação e Difusão da Cities Cotações Envelope o Agroecologia de Itabaiana e escritórios locais da Emdagro 22332A / Aquisição de um 01 (um) triturador de galhos com motor elétrico, 02 (duas) motosserras e 02 lavadoras Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2019-09-13 2019-11-08 2020-03-07 de alta pressão para Irrigation Cotações Envelope o Pendente estruturação do Centro de Capacitação e Difusão da Agroecologia de Itabaiana. Page 4 22333A / Aquisição de equipamentos eletroeletrônicos para estruturação do Centro de Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2019-09-14 2019-11-09 2020-03-08 Pesquisa e Difusão da Irrigation Cotações Envelope o Pendente Agroecologia de Itabaiana e escritórios locais da EMDAGRO 22334A / Aquisição de Mobiliário para estruturação do Centro de Pesquisa e Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2019-09-14 2019-11-09 2020-03-08 Difusão da Agroecologia de Irrigation Cotações Envelope o Pendente Itabaiana e escritórios locais da EMDAGRO 211211 / Implantar instrumentação e realizar monitoramento nas Component 2: Water for Solicitação de Single Stage - One IBRD / 81130 Posterior Open - National 0.00 Cancelado 2018-01-25 2018-01-30 2018-03-13 2018-04-12 2018-05-17 2019-03-13 barragens Jacarecica II, Irrigation Propostas Envelope Governador João Alves Filho e Jaime Umbelino Souza 11232 / Aquisição de Component 1: Integrated Equipamentos de Informática Water Resource Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2019-10-27 2019-11-01 2019-11-16 2019-12-16 2020-01-20 2020-03-20 para a SERHMA e Management and Propostas Envelope o Pendente SEDURBS Institutional Development NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SEMARH 04/2015 / Revisao Component 1: Integrated e Atualizacao do Manual Water Resource IBRD / 81130 Prévia Aquisição Direta Direct 29,648.39 Assinado Operacional do Programa Management and Aguas de Sergipe Institutional Development PAS 16180 / Contratacao Component 1: Integrated de consultor individual para Water Resource IBRD / 81130 Prévia Aquisição Direta Direct 22,405.10 Cancelado exercer a funcao de Management and Engenheiro da UAPAS Institutional Development Component 1: Integrated 16200 / Realização de Water Resource Implementaçã auditoria independente - IBRD / 81130 Posterior Aquisição Direta Direct 0.00 2018-01-30 2018-02-04 2018-03-11 2018-05-10 Management and o Pendente 2018 e 2019 Institutional Development 21126 / Recuperar e substituir equipamentos da tomada d'água da Barragem Jacarecica II e recuperar o Em fase de Component 2: Water for Solicitação de Single Stage - One stop log e a grade de IBRD / 81130 Posterior Open - National 0.00 Implementaçã 2018-02-20 2018-02-25 2018-04-08 2018-05-08 2018-06-12 2018-10-10 Irrigation Propostas Envelope proteção da adução do o reservatório Governador João Alves Filho (Poção da Ribeira). 21128 / Realizar amostragens e ensaios para verificar a agresssividade ao Em fase de concreto da água dos Component 2: Water for Solicitação de Single Stage - One IBRD / 81130 Posterior Open - National 0.00 Implementaçã 2018-01-30 2018-03-27 2018-09-23 reservatórios Jacarecica I, Irrigation Cotações Envelope o Jacarecica II, Governador João Alves Filho e Jaime Umbelino Souza Page 5 23360 / Implantação de rede em fibra óptica, Em fase de interligando a Emdagro à Component 2: Water for Solicitação de Single Stage - One IBRD / 81130 Posterior Open - National 0.00 Implementaçã 2017-07-30 2017-08-04 2018-01-15 2018-02-14 2018-03-21 2018-07-19 Rede de Fibra Óptica Irrigation Propostas Envelope o Estadual, com fornecimento de material e equipamentos 21190 / Georreferenciamento das bacias hidráulicas das barragens Jacarecica I, Jacarecica II e Gov João Alves Filho e levantamento Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2017-08-15 2017-08-20 2017-10-01 2017-10-31 2018-01-11 2018-05-11 cartográfico dos imóveis Irrigation Propostas Envelope o Pendente desapropriados pelo Governo do Estado de Sergipe, para implantação das respectivas barragens e perímetros. 35200 / Constratacao de servcços para acoes de Component 3: Water for Solicitação de Single Stage - One controle de perdas nos IBRD / 81130 Posterior Open - National 0.00 Cancelado 2017-10-04 2017-10-09 2017-11-20 2017-12-20 2018-01-24 2019-01-19 Cities Propostas Envelope municipios de Aracaju de Itabaiana 22250 / Contratação de serviços especializados para capacitação no uso adequado de agrotóxicos para Component 1: Integrated irrigantes, agricultores Em fase de Water Resource Solicitação de Single Stage - One familiares e técnicos IBRD / 81130 Posterior Open - National 0.00 Implementaçã 2018-01-15 2018-01-20 2018-03-03 2018-04-02 2018-05-07 2018-11-03 Management and Propostas Envelope colaboradores dos perímetros o Institutional Development irrigados Poção da Ribeira, Jac I e II e comunidades do entorno e para agentes de endem 13100 / Contratação dos serviços de cercamento, Component 1: Integrated reflorestamento e revegetação Water Resource Solicitação de Single Stage - One para atender aos projetos de IBRD / 81130 Posterior Open - National 4,171,144.39 Assinado 2017-04-30 2017-05-05 2017-06-16 2017-07-16 2017-08-20 2019-04-12 Management and Propostas Envelope preservação, conservação e Institutional Development recuperação de mananciais, na região da BHRS Component 1: Integrated 15100 / Divulgação do Water Resource Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2018-07-10 2018-07-15 2018-08-14 2018-08-24 2018-09-13 2019-04-21 Programa Águas de Sergipe Management and Propostas Envelope o Pendente Institutional Development 21129B / Recuperar a Component 2: Water for Solicitação de Single Stage - One Implementaçã ombreira direita à jusante IBRD / 81130 Posterior Open - National 0.00 2018-09-01 2018-09-06 2018-10-06 2018-10-16 2018-11-05 2019-05-04 Irrigation Propostas Envelope o Pendente da barragem Jacarecica I 23250 / Implantação de rede em fibra óptica, Em fase de interligando a COHIDRO à Component 2: Water for Solicitação de Single Stage - One IBRD / 81130 Posterior Open - National 0.00 Implementaçã 2018-08-15 2018-08-20 2018-10-01 2018-10-31 2018-12-05 2019-02-03 Rede de Fibra óptica Irrigation Propostas Envelope o Estadual, com fornecimento de material e equipamentos. 23390 / Contratação de serviços especializados para reestruturação da Rede Lógica de Dados, reestruturação do Quadro Component 2: Water for Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2019-08-26 2019-08-31 2019-09-20 2019-10-10 2019-10-30 2020-04-27 Geral de Energia e Irrigation Propostas Envelope o Pendente instalação de uma Rede de Monitoramento com Circuito Fechado de Televisão com fornecimento de materiais Page 6 22373 / Contratação de serviços especializados de montagem de estufas agrícolas, bancadas para produção de mudas e Component 2: Water for Solicitação de Single Stage - One Implementaçã sistema de irrigação, com IBRD / 81130 Posterior Open - National 0.00 2019-08-26 2019-08-31 2019-09-30 2019-10-20 2019-11-09 2020-04-27 Irrigation Propostas Envelope o Pendente fornecimento de materiais e equipamentos no Centro de Capacitação e Difusão da Agroecologia de Itabaiana (SE) 211211A / Serviços de implantação e monitoramento da instrumentação geotécnica, com fornecimento de equipamentos e materiais, Em fase de Component 2: Water for Solicitação de Single Stage - One nas barragens dos IBRD / 81130 Posterior Open - National 0.00 Implementaçã 2019-08-28 2019-09-02 2019-10-14 2019-11-13 2019-12-18 2020-04-16 Irrigation Propostas Envelope reservatórios dos Perímetros o Irrigados Jacarecica II, Governador João Alves Filho (Poção da Ribeira) e Jaime Umbelino de 16500 / Contratação de Serviços de digitalização dos processos administrativos, Component 1: Integrated incluindo preparação, Water Resource Solicitação de Single Stage - One Implementaçã IBRD / 81130 Posterior Open - National 0.00 2019-10-06 2019-12-01 2020-03-30 organização, indexação, Management and Cotações Envelope o Pendente digitalização e consulta, Institutional Development oriundos do Programa Águas de Sergipe. 21127A / Especificação técnica para contratação de serviços de Coleta de Amostras e entrega em laboratório destinada a Component 2: Water for Solicitação de Single Stage - One Implementaçã realização de ensaios para IBRD / 81130 Posterior Open - National 0.00 2019-11-04 2019-11-09 2019-12-09 2019-12-29 2020-01-27 2020-04-26 Irrigation Propostas Envelope o Pendente agressividade ao concreto das barragens pela água dos reservatórios e a reatividade álcali-agregado nas barragens Jaca 21127 / Realizar amostragens e ensaios para verificar a reatividade álcali- Component 2: Water for Solicitação de Single Stage - One agregado das barragens IBRD / 81130 Posterior Open - National 0.00 Cancelado 2018-01-25 2018-01-30 2018-03-13 2018-04-12 2018-05-17 2018-09-14 Irrigation Propostas Envelope Jacarecica I, Jacarecica II, Governador João Alves Filho e Jaime Umbelino Souza CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Integrated SMC 01/2014 / SERVICOS Water Resource Seleção Baseada Open - DE CONSULTORIA DE IBRD / 81130 Prévia 3,703.37 Rescindido Management and no Menor Custo International AUDITORIA EXTERNA Institutional Development Page 7 12300 / Implantação do sistema integrado de licenciamento ambiental e de outorga do uso da água contratação de empresa de Seleção Baseada Component 2: Water for Em fase de consultoria para integração IBRD / 81130 Posterior na Qualidade e Open - National 0.00 2017-05-15 2017-06-05 2017-07-19 2017-08-16 2017-09-15 2017-10-20 2018-04-20 2019-04-20 Irrigation Implementação dos processos de Custo licenciamento ambiental e de outorgas do direito de uso de recursos hídricos no estado de 21122A / Estudos e Projetos Executivos visando a implantação da descarga Seleção Baseada de fundo nas barragens dos Component 2: Water for Em fase de IBRD / 81130 Posterior na Qualidade e Open - National 0.00 2017-10-30 2017-11-20 2018-01-03 2018-01-31 2018-03-02 2018-04-06 2018-05-11 2019-04-06 reservatórios Jacarecica II e Irrigation Implementação Custo Gov. João Alves Filho e Stop Log na barragem do reservatório Jacarecica II. 21124 / Elaboração do Plano de Segurança dos Reservatórios das Barragens Seleção Baseada Component 2: Water for Em fase de Jacarecica I, Jacarecica II, IBRD / 81130 Posterior na Qualidade e Open - National 0.00 2018-02-01 2018-02-22 2018-04-07 2018-05-05 2018-06-04 2018-07-09 2018-08-13 2019-01-10 Irrigation Implementação Governador João Alves Filho Custo (Poção da Ribeira), Jaime Umbelino Souza (Poxim) 21125 / Realizar estudo Seleção Baseada hidrológico das barragens Component 2: Water for Em fase de IBRD / 81130 Posterior na Qualidade e Open - National 0.00 2017-07-15 2017-08-05 2017-09-18 2017-10-16 2017-11-15 2017-12-20 2018-01-24 2019-01-24 Jacarecica I, Jacarecica II e Irrigation Implementação Custo Governador João Alves Filho 21129A / Elaboração de projeto executivo para Seleção Baseada recuperação e contenção dos Component 2: Water for IBRD / 81130 Posterior na Qualidade e Open - National 62,879.47 Assinado 2017-07-15 2017-08-05 2017-09-18 2017-10-16 2017-11-15 2017-12-20 2018-01-24 2019-01-24 taludes da ombreira direita Irrigation Custo à jusante da barragem Jacarecica I 211210A / Estudo visando Seleção Baseada a implantação da Component 2: Water for Em fase de IBRD / 81130 Posterior na Qualidade e Open - National 0.00 2017-11-24 2017-12-15 2018-01-28 2018-02-25 2018-03-27 2018-05-01 2018-06-05 2019-04-21 instrumentação geotécnica na Irrigation Implementação Custo barragem Jacarecica I 21241 / Elaboração de projetos executivos de modernização e automação Component 2: Water for Seleção Baseada Em fase de dos sistemas de IBRD / 81130 Posterior Open - National 0.00 2017-06-15 2017-07-06 2017-08-19 2017-09-16 2017-10-16 2017-11-20 2017-12-25 2018-06-23 Irrigation no Menor Custo Implementação bombeamento para irrigação nos perímetros Jacarecica I e Gov. João Alves Filho 22321 / Contratação de serviços técnicos especializados para identificação, mapeamento, Component 1: Integrated elaboração de diagnóstico Water Resource Seleção Baseada Implementação físico (ambiental) e IBRD / 81130 Posterior Open - National 0.00 2017-04-15 2017-05-06 2017-06-19 2017-07-17 2017-08-16 2017-09-20 2018-03-02 2019-02-25 Management and no Menor Custo Pendente elaboração de projetos Institutional Development padrões para recuperação e conservação da vegetação nativa das nascentes e olhos d'água ... 23330 / Capacitação de colaboradores e agricultores Component 2: Water for Seleção Baseada Implementação IBRD / 81130 Posterior Open - National 0.00 2017-09-30 2017-10-21 2017-12-04 2018-01-01 2018-01-31 2018-03-07 2018-04-11 2018-10-08 familiares na gestão de Irrigation no Menor Custo Pendente recursos naturais Page 8 23370 / Contratação de empresa de consultoria especializada em TI para Seleção Baseada desenvolvimento de software Component 2: Water for Open - Em fase de IBRD / 81130 Posterior na Qualidade e 0.00 2018-04-10 2018-05-01 2018-06-14 2018-07-12 2018-08-01 2018-09-05 2018-10-10 2019-04-28 para o ratreamento e Irrigation International Implementação Custo controle do comércio e uso de agrotóximos no Estado de Sergipe 23341 / Elaboração dos Projetos Executivos para a construção, reforma e Component 2: Water for Seleção Baseada Implementação IBRD / 81130 Posterior Open - National 0.00 2017-07-01 2017-07-22 2017-09-04 2017-10-02 2017-11-01 2017-12-06 2018-01-10 2018-07-09 ampliação dos escritórios Irrigation no Menor Custo Pendente municipais e escritório sede da EMDAGRO. 14100 / Prestação de serviços de consultoria para elaboração dos estudos Component 1: Integrated locacionais e projetos dos Seleção Baseada Water Resource Open - aterros de pequeno porte na IBRD / 81130 Posterior na Qualidade e 0.00 Cancelado 2018-04-05 2018-04-05 2018-04-05 2018-04-05 2018-04-05 2018-04-05 2018-04-20 2019-04-20 Management and International Região do Agreste Central Custo Institutional Development Sergipano e elaboração do EIA-RIMA de aterro de médio porte. 11120 / Elaboração dos projetos básico e executivo, incluindo todos os projetos Component 2: Water for Seleção Baseada IBRD / 81130 Posterior Open - National 0.00 Cancelado 2018-04-10 2018-05-10 2018-05-25 2018-06-22 2018-06-27 2018-07-17 2018-07-29 2018-09-12 complementares, para Irrigation no Menor Custo instalação física da SEMARH. 23350 / Desenvolvimento de Seleção Baseada Software de gestão para Component 2: Water for IBRD / 81130 Posterior na Qualidade e Open - National 0.00 Cancelado 2017-06-30 2017-07-21 2017-09-03 2017-10-01 2017-10-31 2017-12-05 2018-01-09 2019-01-04 fortalecimento institucional Irrigation Custo da EMDAGRO. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Integrated SEMARH n 01/2015 / CI - Water Resource IBRD / 81130 Prévia Individual Open 17,626.90 Assinado TRADUTOR UAPAS Management and Institutional Development 16140 / Contratação de Consultor Individual para Component 1: Integrated auxiliar a UAPAS na Water Resource Implementação elaboração dos documentos IBRD / 81130 Posterior Individual Open 0.00 2016-03-10 2016-04-28 2016-05-19 2016-06-12 2016-12-09 Management and Pendente necessários para os diversos Institutional Development processos licitatórios do programa. 16180 / Contratação de consultor individual para Component 1: Integrated auxiliar a UAPAS nos Water Resource Implementação controles de pagamentos e IBRD / 81130 Posterior Individual Open 0.00 2015-05-05 2015-06-23 2015-07-14 2017-06-11 2018-06-11 Management and Pendente realização dos demonstrativos Institutional Development financeiros (IFR) exigidos pelo Programa. Page 9 161100 / Contratação de Consultor Individual para auxiliar a UAPAS na Component 1: Integrated elaboração e conferência dos Water Resource Implementação IBRD / 81130 Posterior Individual Open 0.00 2015-09-21 2015-11-09 2015-11-30 2017-10-12 2018-10-12 documentos técnicos dos Management and Pendente diversos processos previstos Institutional Development para os Componentes 1 e 2 do programa. 22341 / Elaboração dos Projetos Executivos para a construção, reforma e Component 2: Water for Implementação IBRD / 81130 Posterior Individual Open 0.00 2017-06-30 2017-08-18 2017-09-08 2017-10-13 2018-04-11 ampliação dos escritórios Irrigation Pendente municipais e escritório sede da EMDAGRO. 21235 / Contratação de Consultor Individual na área de Agronomia para atuar na supervisão da implantação do novo sistema de irrigação Component 2: Water for IBRD / 81130 Posterior Individual Open 0.00 Cancelado 2018-04-19 2018-05-04 2018-05-09 2018-05-19 2019-04-14 localizada, com fornecimento Irrigation de equipamentos e materiais, nos perímetros irrigados Jacarecia I e Poção da Ribeira 11240 / Contratação de um consultor individual para prestação de assessoria ao Component 1: Integrated processo de fortalecimento do Water Resource Em fase de Comitê da BHRS - Plano de IBRD / 81130 Posterior Individual Open 0.00 2018-07-25 2018-09-12 2018-10-03 2018-11-07 2019-04-26 Management and Implementação ação para promover e Institutional Development acompanhar a execução dos planos de bacias, cobrança e enquadramento. Page 10