PROCUREMENT PLAN (Textual Part) Project information: Dominican Republic DISTRIBUTION GRID MODERNIZATION AND LOSS REDUCTION PROJECT P147277 Project Implementation agency: CDEEE Date of the Procurement Plan: 27-8-18 Period covered by this Procurement Plan:12 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Dominican Republic : Distribution Grid Modernization and Loss Reduction Project PLAN General Information Country: Dominican Republic Bank’s Approval Date of the Original Procurement Plan: 2018-08-27 2021-07-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147277 GPN Date: Project Name: Distribution Grid Modernization and Loss Reduction Project Loan / Credit No: IBRD / 85630 Dominican Corporation of State Power Companies Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Rehabilitation of Selected BO-1-1 / bo.1.1 Proyecto de Distribution Circuits and Rehabilitacion de Circuitos de Upgrading of Metering Solicitud de Single Stage - One 101,208,000. 94,636,401. 2019-09- IBRD / 85630 Previa Open - International Firmado 2017-08-09 2017-08-09 2017-11-09 2017-11-09 2018-05-04 2018-09-10 2018-07-18 2018-08-02 media y baja tension (EDESUR- Systems - Implementation of ofertas Envelope 00 91 21 EDENORTE-EDEESTE) Environmental Manag ement System Rehabilitation of Selected BO-1-3 / bo.1.3 Adecuacion Distribution Circuits and de un sitio actual de acopio Upgrading of Metering Solicitud de Single Stage - One Ejecución 2019-02- IBRD / 85630 Posterior Limited 150,000.00 0.00 2018-11-09 2018-12-10 Residuos (EDESUR-EDENORTE- Systems - Implementation of cotizaciones Envelope pendiente 08 EDEESTE) - PMAA Environmental Manag ement System BO-3-1 / bo.3.1 Adecuacion Oficinas Comerciales Tipo A Commercial Management and en la Zona de Influencia de los Project Management, Circuitos de Edesur) Monitoring and Evaluation of Solicitud de Single Stage - One Ejecución 2018-04- IBRD / 85630 Posterior Limited 308,672.00 0.00 2017-11-20 2018-02-03 (Contempla mobiliario, the Distribution Grid cotizaciones Envelope pendiente 04 sistema de vigilancia, Modernization and Electri cal deteccion de incendio) - Losses Reduction Program Comercial Rehabilitation of Selected BO-1-2 / Distribution Circuits and bo.1.2.Construccion de tres Upgrading of Metering Solicitud de Single Stage - One 2020-01- IBRD / 85630 Previa Open - National 442,100.00 465,645.18 Firmado 2019-08-22 2019-09-17 2019-08-27 2019-09-19 2019-09-26 2019-10-31 2019-10-26 2020-01-16 2019-11-15 2020-02-14 puntos verdes (EDESUR- Systems - Implementation of ofertas Envelope 14 EDENORTE-EDEESTE) - PMAA Environmental Manag ement System Commercial Management and Project Management, BO-3-2 / Adecuación de Monitoring and Evaluation of Solicitud de Single Stage - One 2019-12- Ocho (8) Oficinas Comerciales IBRD / 85630 Posterior Open - National 1,056,619.00 359,481.60 Firmado 2019-05-15 2019-07-25 2019-05-20 2019-07-01 2019-08-29 2019-07-16 2019-10-15 2019-08-14 2019-12-18 the Distribution Grid ofertas Envelope 12 (Edesur (3) y Edenorte (5)) Modernization and Electri cal Losses Reduction Program Commercial Management and BO-3-2-A / Adecuaciones de Project Management, oficinas comerciales de Monitoring and Evaluation of Solicitud de Single Stage - One 2020-04- Edesur (San Cristóbal 1er y IBRD / 85630 Posterior Limited 341,012.00 350,043.16 Firmado 2019-12-26 2020-01-20 2020-02-14 2020-06-09 the Distribution Grid cotizaciones Envelope 14 3er Piso, Patio Colombia y San Modernization and Electri cal Cristóbal Norte) Losses Reduction Program BO.2.1 / Adecuación Terrero para ubicación de furgón para Citizen Engagement and Solicitud de Single Stage - One Ejecución 2020-05- IBRD / 85630 Posterior Limited 4,500.00 0.00 2020-04-16 2020-05-14 almacenamiento temporal de Community Participation cotizaciones Envelope pendiente 29 la UEP/CDEEE. Rehabilitation of Selected BO-1-1-A / Rehabilitación de Distribution Circuits and Redes de los Circuitos Upgrading of Metering Solicitud de Single Stage - One 2022-05- IBRD / 85630 Posterior Open - National 2,721,130.00 0.00 En ejecución 2021-01-22 2021-03-29 2021-02-03 2021-04-06 2021-03-10 2021-05-18 2021-03-30 2021-05-09 MVIE101-EDESUR y HAMO06- Systems - Implementation of ofertas Envelope 09 EDEESTE Environmental Manag ement System GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Rehabilitation of Selected B-1-1 / b.1.1 Adquisición de Distribution Circuits and Kit para Analisis Cualitativo - Upgrading of Metering Solicitud de Single Stage - One Subprograma de manejo y IBRD / 85630 Posterior Limited 24,000.00 0.00 Cancelado 2018-11-03 2018-11-26 2018-12-26 Systems - Implementation of cotizaciones Envelope disposición de aceite con PCB Environmental Manag ement - Calidad Ambiental - PMAA System Rehabilitation of Selected Distribution Circuits and B-1-2 / b.1.2 Equipo de Upgrading of Metering Solicitud de Single Stage - One campo, tabletas, seguridad y IBRD / 85630 Posterior Limited 35,000.00 8,601.49 Firmado 2018-08-17 2019-01-29 2018-09-04 2019-02-28 2018-10-04 2019-05-29 Systems - Implementation of cotizaciones Envelope manejo ambiental - PMAA Environmental Manag ement System Rehabilitation of Selected B-1-3 / b.1.3 Adq. Vehículos Distribution Circuits and utilitarios para las Unidades Upgrading of Metering Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Open - National 115,000.00 0.00 2017-04-03 2017-04-18 2017-05-18 2017-05-28 2017-06-17 2017-08-01 ambientales UEP/CDEEE/EDES Systems - Implementation of ofertas Envelope pendiente - PMAA Environmental Manag ement System B-2-1 / b.2.1 Adquisicion de Carpetas para los Comites de Citizen Engagement and Solicitud de Single Stage - One Seguimiento de las Obras IBRD / 85630 Posterior Limited 23,445.00 14,813.79 Finalizado 2018-07-04 2019-08-29 2018-07-28 2019-10-14 2018-08-27 2019-11-20 Community Participation cotizaciones Envelope (COSE) (EDESUR-EDENORTE- EDEESTE) B-2-5 / b.2.5 Adquisicion Vehiculos para uso de la Citizen Engagement and Solicitud de Single Stage - One Ejecución Gestion Social de las IBRD / 85630 Posterior Open - National 425,000.00 0.00 2017-05-12 2017-05-22 2017-07-03 2017-08-11 2017-09-05 2017-09-30 Community Participation ofertas Envelope pendiente distribuidoras (EDESUR- EDENORTE-EDEESTE) Page 1 B-2-6 / b.2.6 Adquisicion de bombillas de bajo consumo Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Open - National 207,600.00 153,447.20 Firmado 2018-08-06 2019-10-02 2018-08-08 2019-10-09 2018-09-07 2019-11-14 2018-09-17 2019-12-20 2018-09-29 2020-02-25 2018-12-18 para las distribuidoras Community Participation ofertas Envelope (EDESUR-EDENORTE-EDEESTE) B-2-7 / b.2.7 Adqusicion de materiales Impresos (Publicitarios, didacticos y Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 112,307.00 0.00 En ejecución 2018-08-07 2019-09-18 2018-09-01 2018-10-16 brochures) para las Community Participation cotizaciones Envelope distribuidoras (EDESUR- EDENORTE- EDEESTE) Commercial Management and Project Management, B-3-1 / b.3.1. Equipamiento Monitoring and Evaluation of Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Open - International 3,500,000.00 0.00 2019-01-15 2019-01-25 2019-03-08 2019-03-28 2019-04-27 2019-06-26 e Implementacion DataCenter the Distribution Grid ofertas Envelope pendiente Modernization and Electri cal Losses Reduction Program Commercial Management and B-3-2 / b.3.2. Adquisicion de Project Management, vehiculos para realizar visitas Monitoring and Evaluation of Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Open - National 304,000.00 0.00 2017-09-05 2017-09-10 2017-10-22 2017-11-21 2017-12-26 2018-06-24 de supervision tecnica a las the Distribution Grid ofertas Envelope pendiente zonas de las obras (UEP-EDE) Modernization and Electri cal Losses Reduction Program B-3-5-2 / b.3.5.2 Equipos Informaticos para la Commercial Management and Adecuacion de oficina Project Management, comercial tipo A, en la zona Monitoring and Evaluation of Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 56,758.00 0.00 2018-02-06 2018-03-01 2018-03-22 de influencia de los circuitos the Distribution Grid cotizaciones Envelope pendiente de Edesur (Contempla la Modernization and Electri cal adquisicion de mobiliario) - Losses Reduction Program Comercial B-2-8 / Adq. Cámaras para Premiación Concurso Citizen Engagement and Solicitud de Single Stage - One Ejecución Fotografía Uso Racional de IBRD / 85630 Posterior Limited 4,000.00 0.00 2019-01-24 2019-02-18 2019-03-20 Community Participation cotizaciones Envelope pendiente Energía en Circuitos en el Ámbito del Proyecto. B-2-10 / Adq. Placas de Reconocimiento para líderes Citizen Engagement and Solicitud de Single Stage - One Ejecución Comunitarios de los Comités IBRD / 85630 Posterior Limited 3,500.00 0.00 2019-09-04 2019-09-23 2019-10-23 Community Participation cotizaciones Envelope pendiente de Seguimiento de los Circuitos Intervenidos. B-2-9 / Adq. de artículos publicitarios para la campaña Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 30,000.00 12,144.18 Firmado 2018-10-24 2018-10-31 2018-11-12 2018-11-16 2018-12-12 del subcomponente de Community Participation cotizaciones Envelope gestión ambiental Commercial Management and B-3-9 / Adq de 3 Camiones Project Management, Tipo Carga, sin carga - 4 Monitoring and Evaluation of Solicitud de Single Stage - One Furgonetas - 2 Minibuses de IBRD / 85630 Posterior Open - National 429,300.00 406,877.98 Firmado 2019-04-30 2019-05-10 2019-05-05 2019-05-14 2019-06-04 2019-06-18 2019-06-19 2019-07-19 2019-07-11 2019-08-27 2019-08-25 the Distribution Grid ofertas Envelope 15 Pasajeros - y 4 Camionetas Modernization and Electri cal - para Edeeste. Losses Reduction Program B-3-4 / b.3.4. Adquisicion de 4 oficinas comerciales moviles Commercial Management and (1 Edesur - 2 Edenorte - 1 Project Management, Edeeste) (Incluye: Adquisicion Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Posterior Open - National 119,118.00 0.00 En ejecución 2018-09-19 2019-06-13 2018-09-24 2018-11-05 2018-12-05 2019-01-09 2019-03-10 de camion, mobiliario, the Distribution Grid ofertas Envelope equipos de informaticos, Modernization and Electri cal equipo de sonido, Losses Reduction Program senalizacion) - Comercial Commercial Management and Project Management, B-3-10 / Adq de 6 Quioscos Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 49,800.00 24,003.56 En ejecución 2019-05-23 2019-06-12 2019-06-16 2019-07-09 2019-07-31 2019-07-16 de Autopago para Edeeste the Distribution Grid cotizaciones Envelope Modernization and Electri cal Losses Reduction Program Commercial Management and B-3-3-A / Adq. de Licencias Project Management, Adobe Acrobat Professional y Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 7,558.00 3,496.06 Finalizado 2019-05-01 2019-04-26 2019-05-12 2019-05-08 2019-05-27 2019-05-16 Adobe Creative Cloud for the Distribution Grid cotizaciones Envelope Teams para la UEP. Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, B-3-3-B / Adquisición de Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 1,000.00 0.00 En ejecución 2019-05-01 2019-04-25 2019-05-17 2019-06-01 Trituradora para la UEP. the Distribution Grid cotizaciones Envelope Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, B-3-3 / b.3.3. Adquisicion de Monitoring and Evaluation of Solicitud de Single Stage - One Ejecución Equipos Informaticos para la IBRD / 85630 Posterior Limited 36,442.00 0.00 2018-02-10 2018-04-07 2018-06-06 the Distribution Grid cotizaciones Envelope pendiente UEP Modernization and Electri cal Losses Reduction Program B-3-5-1 / b.3.5.1 Commercial Management and Adecuacion de oficinas Project Management, comerciales tipo B, en la zona Monitoring and Evaluation of Solicitud de Single Stage - One de influencia de los circuitos IBRD / 85630 Posterior Open - National 339,650.00 0.00 Cancelado 2018-10-29 2018-11-03 2018-12-03 2018-12-18 2019-01-07 2019-03-08 the Distribution Grid ofertas Envelope de Edenorte y Edesur Modernization and Electri cal (Contempla la adquisicion de Losses Reduction Program mobiliario) - Comercial B-3-7 / b.3.7. Commercial Management and Implementacion Sistema de Project Management, Administracion de Turnos Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 12,000.00 0.00 Cancelado 2018-08-13 2018-09-27 2018-10-27 (Computadoras, Software, the Distribution Grid cotizaciones Envelope Impresoras Pantalla de TV, Modernization and Electri cal Audio) - Comercial Losses Reduction Program Page 2 B-3-6-A / b.3.6. Adquisicion Commercial Management and de materiales para suplir Project Management, Demanda Comercial y Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Previa Open - International 1,551,261.00 968,330.52 Firmado 2019-04-22 2019-09-12 2019-04-27 2019-09-23 2019-06-08 2019-11-15 2019-06-23 2020-02-05 2019-07-22 2020-06-15 2019-11-19 Mantenimiento (Medidores, the Distribution Grid ofertas Envelope acometidas, cajas, etc) - Modernization and Electri cal Comercial Losses Reduction Program Rehabilitation of Selected B-1-2-A / Adq. 5 laptops Distribution Circuits and para los técnicos y Upgrading of Metering Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 6,750.00 7,526.12 Finalizado 2019-08-28 2019-08-29 2019-09-14 2019-09-30 2019-10-14 2019-11-05 coordinadores ambientales de Systems - Implementation of cotizaciones Envelope las EDE. Environmental Manag ement System B-2-11 / Adq. 18 parantes alusivos al Programa de Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 2,250.00 1,192.54 Finalizado 2019-09-15 2019-11-11 2019-10-02 2019-09-26 2019-10-17 2019-10-16 Rehabilitación de Redes Community Participation cotizaciones Envelope Eléctricas B-2-12 / B-2-12 Adq. 651 Collarines alusivos al Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 1,623.00 1,837.75 Finalizado 2019-09-15 2019-09-11 2019-10-14 2019-10-04 2019-10-29 2019-10-31 Programa de Rehabilitación de Community Participation cotizaciones Envelope Redes Eléctricas B-2-13 / B-2-13 Adq. 47,250 cajitas de crayones Citizen Engagement and Solicitud de Single Stage - One para completivo de los libros IBRD / 85630 Posterior Limited 16,029.00 10,318.50 Finalizado 2019-09-15 2019-11-13 2019-10-16 2019-10-10 2019-10-31 2019-11-29 Community Participation cotizaciones Envelope de colorear sobre uso eficiente y seguro de energía. Rehabilitation of Selected Distribution Circuits and B-1-2-B / B-1-2-B Máscaras Upgrading of Metering Solicitud de Single Stage - One y filtros para el personal IBRD / 85630 Posterior Limited 1,800.00 1,515.72 Firmado 2019-11-23 2019-11-21 2019-12-10 2019-12-13 2020-01-09 Systems - Implementation of cotizaciones Envelope Gestión Ambiental de las EDE. Environmental Manag ement System Rehabilitation of Selected Distribution Circuits and B-2-15 / B-2-15 Luminarias Upgrading of Metering Solicitud de Single Stage - One para los Ciruelitos IBRD / 85630 Posterior Limited 700.00 658.37 Finalizado 2019-11-25 2019-11-29 2019-12-19 2019-12-13 2020-01-18 2019-12-17 Systems - Implementation of cotizaciones Envelope (Comunidad Edenorte) Environmental Manag ement System B-2-14 / Adq. 800 agendas 2020 del Programa de Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 10,717.00 7,416.91 Finalizado 2019-12-13 2019-12-13 2020-01-01 2019-12-23 2020-01-31 2020-02-25 Rehabilitación de Redes Community Participation cotizaciones Envelope Eléctricas. Commercial Management and B-3-11 / Adq. Equipos Project Management, técnologicos para oficinas de Monitoring and Evaluation of Solicitud de Single Stage - One Edesur (San Cristóbal 1er y IBRD / 85630 Posterior Open - National 116,127.00 102,428.93 Firmado 2019-12-27 2020-02-03 2020-01-03 2020-02-04 2020-02-02 2020-03-05 2020-02-17 2020-05-14 2020-03-03 2020-06-25 2020-04-17 the Distribution Grid ofertas Envelope 3er Piso, Patio Colombia, San Modernization and Electri cal Cristóbal Norte) Losses Reduction Program Commercial Management and Project Management, B-3-12 / Adq. Kiosco para Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 4,730.00 5,127.09 Firmado 2020-03-08 2020-10-07 2020-04-02 2020-11-10 2020-04-17 oficina Patio Colombia, Edesur the Distribution Grid cotizaciones Envelope Modernization and Electri cal Losses Reduction Program B-3-13 / Adq. de Commercial Management and Señalizaciones de Mercadeo Project Management, para Oficinas de Edesur (San Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 25,198.00 13,575.05 Firmado 2020-03-08 2020-09-10 2020-03-30 2020-10-13 2020-04-29 Cristóbal 1er y 3er piso, Patio the Distribution Grid cotizaciones Envelope Colombia y San Cristóbal Modernization and Electri cal Norte) Losses Reduction Program Commercial Management and B-3-14 / Adq. equipos de Project Management, comunicaciones oficinas de Monitoring and Evaluation of Ejecución Edesur (San Cristóbal 1er y IBRD / 85630 Posterior Adquisición directa Direct 9,985.00 0.00 2020-03-06 2020-03-11 2020-03-23 2020-05-07 the Distribution Grid pendiente 3er piso, Patio Colombia y San Modernization and Electri cal Cristóbal Norte) Losses Reduction Program B-3-15 / Adq. de Licencias Commercial Management and de Software de Turnos Eflow Project Management, para las oficinas de Edesur Monitoring and Evaluation of Ejecución IBRD / 85630 Posterior Adquisición directa Direct 8,510.00 0.00 2020-03-06 2020-03-11 2020-03-23 2020-04-22 (San Cristóbal 1er y 3er piso, the Distribution Grid pendiente Patio Colombia y San Cristóbal Modernization and Electri cal Norte) Losses Reduction Program B-3-16 / Adq. Equipos para Commercial Management and seguridad y vigilancia de las Project Management, oficinas de Edesur (San Monitoring and Evaluation of Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 31,982.00 0.00 2020-03-11 2020-04-08 2020-05-23 Cristóbal 1er y 3er, Patio the Distribution Grid cotizaciones Envelope pendiente Colombia y San Cristóbal Modernization and Electri cal Norte) Losses Reduction Program Commercial Management and Project Management, B-3-8 / b.3.8 Armarios para Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 37,400.00 0.00 Cancelado 2018-11-03 2018-12-25 2019-01-09 area de Archivo - UEP the Distribution Grid cotizaciones Envelope Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, B-3-8-A / Fabricación e Monitoring and Evaluation of Ejecución Instalacion de Archivos para IBRD / 85630 Posterior Adquisición directa Direct 29,628.00 0.00 2019-12-27 2019-12-30 2020-01-11 2020-02-10 the Distribution Grid pendiente UEP Modernization and Electri cal Losses Reduction Program Rehabilitation of Selected B-1-1-A / Adq. de Kit para Distribution Circuits and Análisis Cualitativo - Upgrading of Metering Subprograma de manejo y IBRD / 85630 Posterior Adquisición directa Direct 20,000.00 20,000.00 Finalizado 2019-12-26 2019-12-05 2019-12-31 2019-11-25 2020-01-09 2020-01-21 2020-02-08 2020-02-21 Systems - Implementation of disposición de aceite con PCB Environmental Manag ement . System Page 3 B-2-16 / Adq. de Furgón para almacenamiento Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 5,200.00 0.00 2020-03-27 2020-04-17 2020-06-16 temporal de bienes o Community Participation cotizaciones Envelope pendiente materiales UEP/CDEEE B-2-17 / Adquisición de Citizen Engagement and Solicitud de Single Stage - One Uniformes para personal de IBRD / 85630 Posterior Limited 31,293.00 14,291.52 Firmado 2020-03-27 2020-05-27 2020-04-22 2020-07-27 2020-06-21 Community Participation cotizaciones Envelope gestión social de las EDE. B-3-17 / Adquisición de mobiliario para el salón de Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 9,260.00 6,839.82 Finalizado 2020-03-27 2020-05-05 2020-04-20 2020-07-01 2020-05-20 2020-07-27 reuniones (mesas, sillones y Community Participation cotizaciones Envelope credenza) B-2-18 / Adq. Materiales para prácticas del programa de formación de electricistas Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 11,879.34 12,863.24 Firmado 2020-03-27 2020-11-24 2020-04-23 2021-01-29 2020-05-23 2021-03-02 comunitarios (incluye Community Participation cotizaciones Envelope materiales eléctricos, tubos, plywood para panales) B-2-19 / Adquisición de Kits de herramientas para los Citizen Engagement and Solicitud de Single Stage - One participantes del programa de IBRD / 85630 Posterior Limited 30,125.00 24,733.59 Firmado 2020-03-27 2020-11-24 2020-04-18 2021-01-29 2020-05-03 2021-03-01 Community Participation cotizaciones Envelope formación de electricistas comunitarios B-2-20 / Reproducción de Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 3,150.00 3,371.49 Firmado 2020-03-27 2020-06-18 2020-04-15 2020-08-03 2020-05-15 letreros prepago para las EDE Community Participation cotizaciones Envelope Commercial Management and B-3-18 / Adquisición de Project Management, artículos de protección contra Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 98,000.00 34,059.41 Finalizado 2020-06-06 2020-05-27 2020-07-02 2020-06-29 2020-08-01 2020-07-10 el COVID-19 para personal de the Distribution Grid cotizaciones Envelope la CDEEE y las EDE. Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, B-3-3-C / Adquisición de Monitoring and Evaluation of Solicitud de Single Stage - One una laptop para la IBRD / 85630 Posterior Limited 1,600.00 1,985.91 Finalizado 2020-05-16 2020-06-01 2020-06-06 2020-06-23 2020-06-21 2020-08-04 the Distribution Grid cotizaciones Envelope coordinación de la UEP Modernization and Electri cal Losses Reduction Program B-2-2 / b.2.2. RSC - Adquisición de artículos deportivos para las Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 11,336.00 0.00 2019-04-04 2019-04-28 2019-05-28 comunidades en los circuitos Community Participation cotizaciones Envelope pendiente intervenidos por el Programa en las EDE. B-2-3 / b.2.3. RSC - Adquisición de mesas y sillas para las organizaciones Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 38,606.00 35,215.55 Finalizado 2020-11-04 2020-11-30 2020-11-28 2021-01-29 2020-12-28 2021-03-09 comunitarias en los circuitos Community Participation cotizaciones Envelope intervenidos por el Programa en las EDE. B-2-4 / b.2.4. RSC- Adquisición de Equipos de sonido para las Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 12,056.00 0.00 2020-11-04 2020-11-28 2020-12-28 organizaciones comunitarias Community Participation cotizaciones Envelope pendiente en los circuitos intervenidos por el programa en las EDE. B-2-4-A / RSC- Adquisición de artículos diversos (carpas, lonas, lámparas led, extensiones eléctricas, pala de Citizen Engagement and Solicitud de Single Stage - One Ejecución construcción, picos, regletas, IBRD / 85630 Posterior Limited 4,702.00 0.00 2020-11-05 2020-11-30 2020-12-30 Community Participation cotizaciones Envelope pendiente etc) para las organizaciones comunitarias en los circuitos intervenidos por el programa en las EDE. B-2-4-B / RSC-Adquisición Citizen Engagement and Solicitud de Single Stage - One Ejecución de artículos informáticos IBRD / 85630 Posterior Limited 2,685.00 0.00 2020-11-05 2020-11-30 2020-12-30 Community Participation cotizaciones Envelope pendiente (Computadoras e impresoras) B-2-4-C / RSC - Adquisición de electrodomésticos - Otros Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 5,590.00 0.00 2020-11-05 2020-11-30 2020-12-30 (Abánicos, bebero, termo, Community Participation cotizaciones Envelope pendiente hielera, etc) B-2-14-A / Adq. de 800 agendas 2021 del Programa Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 12,000.00 8,001.39 Finalizado 2020-10-28 2020-11-03 2020-11-20 2020-12-23 2020-12-20 2021-02-16 de Rehabilitación de Redes Community Participation cotizaciones Envelope Eléctricas B-3-11-A / Adq. de 19 Commercial Management and terminales NComputing para Project Management, las oficinas comerciales de Monitoring and Evaluation of Ejecución IBRD / 85630 Posterior Adquisición directa Direct 9,339.00 0.00 2020-10-23 2020-10-24 2020-10-30 2020-11-29 Edesur (San Cristóbal, Patio the Distribution Grid pendiente Colombia y San Cristobal Modernization and Electri cal Norte) Losses Reduction Program Commercial Management and B-3-19 / Uniformes Project Management, corporativos para la Dirección Monitoring and Evaluation of Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 23,000.00 0.00 2021-07-24 2021-08-21 2021-10-20 de Gestión de Proyectos de the Distribution Grid cotizaciones Envelope pendiente Edesur Modernization and Electri cal Losses Reduction Program NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 S-1-1 / S.1.1 Transporte Rehabilitation of Selected para el Movimiento de Distribution Circuits and Transformadores con PCB - Upgrading of Metering Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Open - International 110,000.00 0.00 2018-12-11 2018-12-16 2019-01-27 2019-02-26 2019-04-02 2019-06-01 Tratamiento final Equipo Systems - Implementation of ofertas Envelope pendiente Contaminado - PMAA (EDESUR Environmental Manag ement - EDENORTE - EDEESTE) System S-2-5 / S.2.5. Campaña Digitales en Redes Sociales Citizen Engagement and Solicitud de Single Stage - One Ejecución del Programa de IBRD / 85630 Posterior Limited 60,000.00 0.00 2019-05-30 2019-06-21 2019-10-19 Community Participation cotizaciones Envelope pendiente Rehabilitación de Redes Eléctricas. S-2-6 / Logística para Ceremonia de Premiación Concurso Fotográfico Uso Racional de Energía en Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 7,000.00 0.00 2019-02-06 2019-02-28 2019-03-05 Circuitos en el Ámbito del Community Participation cotizaciones Envelope pendiente Proyecto - EDE (Refrigerios, Luces de ambientación, Truss, Bajantes, etc). S-2-7 / Contratación de servicios para Ruta de Aprendizaje CIclo de Energá Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 8,000.00 0.00 2019-06-07 2019-07-07 2019-08-06 para Lideres Comutarios de Community Participation cotizaciones Envelope pendiente Edesur - Edenorte - Edeeste (Transporte y Refrigerios) S-2-4 / S.2.4 Implementación del Plan de Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 205,974.00 0.00 2019-01-12 2019-02-12 2019-05-13 Comunicación del PRRE Community Participation cotizaciones Envelope pendiente (Publicidad Externa) S-3-1 / S.3.1. Contratación Commercial Management and Servicios de Empresas (15 Project Management, Brigadas) para Gestión Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Posterior Open - National 216,333.00 0.00 Cancelado 2019-03-28 2019-04-02 2019-05-14 2019-06-13 2019-07-08 2020-07-07 Técnico - Comercial y the Distribution Grid ofertas Envelope Disciplinario (EDENORTE), por Modernization and Electri cal - Comercial Losses Reduction Program Commercial Management and S-3-2 / S.3.2. Contratación Project Management, Servicios de Empresas (10 Monitoring and Evaluation of Solicitud de Single Stage - One Brigadas) para Corte y IBRD / 85630 Posterior Open - National 420,000.00 0.00 Cancelado 2019-03-28 2019-04-02 2019-05-14 2019-06-13 2019-07-18 2020-07-17 the Distribution Grid ofertas Envelope Reconexión (EDESUR) - Modernization and Electri cal Comercial Losses Reduction Program S-3-3 / S.3.3. Contratación Commercial Management and Servicios de Empresas (18 Project Management, Brigadas) para Gestión Monitoring and Evaluation of Solicitud de Single Stage - One IBRD / 85630 Previa Open - National 932,200.00 0.00 Cancelado 2018-12-03 2018-12-08 2019-01-19 2019-02-18 2019-03-25 2020-03-24 Técnico - Comercial y the Distribution Grid ofertas Envelope Disciplinario (EDEESTE) - Modernization and Electri cal Comercial Losses Reduction Program Rehabilitation of Selected S-1-2 / Disposición Final de Distribution Circuits and Residuos Peligrosos del Upgrading of Metering Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 45,000.00 0.00 2020-02-01 2020-03-03 2020-05-02 Programa de Rehabilitación de Systems - Implementation of cotizaciones Envelope pendiente Redes Eléctricas Environmental Manag ement System S-2-1 / S.2.1 Edesur: Gastos de Gestión Social, tales como: Actividades de Solidaridad Citizen Engagement and Solicitud de Single Stage - One Social en Comunidades IBRD / 85630 Posterior Limited 6,040.00 0.00 Cancelado 2019-04-06 2019-05-07 2019-11-03 Community Participation cotizaciones Envelope Intervenidas (Refrigerios, Transporte, Alquileres de Carpas, sillas y mesas, etc.) S-2-2 / S.2.2 Edenorte: Gastos de Gestión Social, tales como: Actividades de Solidaridad Social en Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 6,420.00 0.00 Cancelado 2019-04-06 2019-05-07 2019-11-03 Comunidades Intervenidas Community Participation cotizaciones Envelope (Refrigerios, Transporte, Alquileres de Carpas, sillas y mesas, etc.) S-2-3 / S.2.3 Edeeste: Gastos de Gestión Social, tales como: Actividades de Solidaridad Citizen Engagement and Solicitud de Single Stage - One Social en Comunidades IBRD / 85630 Posterior Limited 3,821.00 0.00 Cancelado 2019-05-21 2019-06-21 2019-12-18 Community Participation cotizaciones Envelope Intervenidas (Refrigerios, Transporte, Alquileres de Carpas, sillas y mesas, etc.) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C-2-9-B / c.2.9.b Selección basada Citizen Engagement and Ejecución Realizacion Documental IBRD / 85630 Posterior en calificaciones Open - National 40,000.00 0.00 2018-11-12 2018-12-03 2018-12-25 2019-01-01 2019-01-16 2019-04-16 Community Participation pendiente Proyecto BM de consultores Commercial Management and Project Management, C-3-1 / c.3.1 Auditoria Monitoring and Evaluation of Selección basada IBRD / 85630 Posterior Open - National 150,000.00 0.00 Cancelado 2018-08-20 2018-09-10 2018-10-02 2018-10-30 2018-11-14 2018-12-01 2018-12-21 2019-12-21 Financiera del Proyecto the Distribution Grid en calidad y costo Modernization and Electri cal Losses Reduction Program Commercial Management and C-3-2 / c.3.2 Firma Project Management, verificadora de la Calidad Monitoring and Evaluation of Selección basada IBRD / 85630 Previa Open - International 1,920,000.00 1,271,935.00 Firmado 2018-05-29 2018-06-26 2018-07-24 2018-10-04 2018-08-28 2018-11-22 2018-09-27 2019-01-14 2018-10-25 2019-04-25 2018-11-29 2019-04-25 2020-05-22 Tecnica de las Obras de the Distribution Grid en calidad y costo Rehabilitacion de Redes Modernization and Electri cal Losses Reduction Program Page 5 Commercial Management and Project Management, C-3-3 / c.3.3. Monitoring and Evaluation of Selección basada Ejecución Fortalecimiento Institucional IBRD / 85630 Posterior Open - International 500,000.00 0.00 2018-09-10 2018-10-01 2018-10-23 2018-11-20 2018-12-20 2019-01-24 2019-02-28 2020-02-28 the Distribution Grid en calidad y costo pendiente de las EDE Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, C-3-1-A / Auditoria Monitoring and Evaluation of Selección basada IBRD / 85630 Previa Open - National 150,000.00 0.00 Cancelado 2018-10-02 2018-10-25 2018-10-16 2018-11-07 2018-12-05 2018-12-20 2019-01-06 2019-02-03 2020-02-03 Financiera del Proyecto. the Distribution Grid en calidad y costo Modernization and Electri cal Losses Reduction Program Rehabilitation of Selected C-1-8 / c.1.8 Sistema de Distribution Circuits and Gestion Integral para la Upgrading of Metering Selección basada Ejecución Estandarizacion y Manejo IBRD / 85630 Posterior Open - National 400,000.00 0.00 2018-12-12 2019-01-02 2019-01-24 2019-02-28 2019-03-30 2019-04-20 2019-05-10 2019-11-06 Systems - Implementation of en calidad y costo pendiente Ambiental del Proyecto - Environmental Manag ement PMAA System C-2-9-A / c.2.9.a Produccion de Videos sobre el antes y Selección basada Citizen Engagement and después de las obras y IBRD / 85630 Posterior en calificaciones Open - National 21,100.00 0.00 En ejecución 2018-11-04 2018-12-13 2018-11-25 2019-02-07 2019-01-08 2019-03-28 2019-01-23 2019-02-27 2019-04-28 Community Participation testimonios de los de consultores beneficiarios. C-1-9 / c.1.9 Diagnostico y Rehabilitation of Selected monitoreo del estado actual Distribution Circuits and Selección basada del agua, suelo y aire en los Upgrading of Metering IBRD / 85630 Posterior en calificaciones Open - National 55,000.00 0.00 Cancelado 2018-11-05 2018-11-26 2018-12-25 2019-01-24 2019-02-17 2019-05-18 sitios actuales de acopio, Systems - Implementation of de consultores almacen y sitios a remediar - Environmental Manag ement PMAA System INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Rehabilitation of Selected Distribution Circuits and C-1-1 / c.1.1 Coordinador Upgrading of Metering Selección directa Ejecución IBRD / 85630 Posterior Direct 144,000.00 0.00 2018-07-01 2018-07-11 2018-07-31 2019-07-26 Ambiental para la UEP-PMAA Systems - Implementation of de consultores pendiente Environmental Manag ement System Rehabilitation of Selected C-1-5 / c.1.5 Dos Distribution Circuits and Inspectores Medioambientales Upgrading of Metering Selección directa Ejecución IBRD / 85630 Posterior Direct 135,000.00 0.00 2018-06-04 2018-06-11 2018-06-29 2019-06-29 y de Seguridad Industrial Systems - Implementation of de consultores pendiente (EDESUR) - PMAA Environmental Manag ement System Rehabilitation of Selected C-1-6 / c.1.6 Dos Distribution Circuits and Inspectores Medioambientales Upgrading of Metering Selección directa Ejecución IBRD / 85630 Posterior Direct 135,000.00 0.00 2018-06-04 2018-06-11 2018-07-01 2019-07-01 y de Seguridad Industrial Systems - Implementation of de consultores pendiente (EDENORTE) - PMAA Environmental Manag ement System Rehabilitation of Selected C-1-7 / c.1.7 Dos Distribution Circuits and Inspectores Medioambientales Upgrading of Metering Selección directa Ejecución IBRD / 85630 Posterior Direct 135,000.00 0.00 2018-06-04 2018-06-11 2018-07-01 2019-07-01 y de Seguridad Industrial Systems - Implementation of de consultores pendiente (EDEESTE) - PMAA Environmental Manag ement System Rehabilitation of Selected Distribution Circuits and C-1-11 / c.1.11 Consultor Upgrading of Metering Ejecución para el Diseno de los Puntos IBRD / 85630 Posterior Individual Limited 7,900.00 0.00 2018-07-09 2018-07-16 2018-07-26 2018-08-09 2018-11-07 Systems - Implementation of pendiente Verdes - PMAA Environmental Manag ement System C-2-1 / c.2.1 Contratacion Citizen Engagement and Selección directa IBRD / 85630 Previa Direct 49,392.00 0.00 En ejecución 2018-06-01 2018-06-06 2018-07-01 2019-07-01 Coordinador de Gestion Social Community Participation de consultores C-2-2 / c.2.2 Contratacion Citizen Engagement and Selección directa IBRD / 85630 Previa Direct 33,516.00 0.00 Cancelado 2018-06-04 2018-06-10 2018-08-01 2019-08-01 Analista de Gestion Social Community Participation de consultores C-2-10 / c.2.10 Consultor para el Diseno de la Muestra Citizen Engagement and para el Calculo de Usuarios IBRD / 85630 Posterior Individual Limited 25,000.00 0.00 En ejecución 2018-06-28 2018-10-01 2018-07-10 2018-10-04 2018-08-09 2018-08-31 2018-10-15 Community Participation Servicio Electrico y Capacitacion Personal Commercial Management and Project Management, C-3-4 / c.3.4. Especialista Monitoring and Evaluation of Ejecución Adm Legal Contratos Obras, IBRD / 85630 Posterior Individual Limited 102,000.00 0.00 2018-05-22 2018-05-23 2018-06-06 2018-06-15 2019-06-15 the Distribution Grid pendiente Bienes y Consultorias Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, C-3-5 / c.3.5 Especialista de Monitoring and Evaluation of Selección directa Ejecución IBRD / 85630 Posterior Direct 118,000.00 0.00 2019-03-18 2019-03-23 2019-04-10 2020-04-09 Proyectos UEP the Distribution Grid de consultores pendiente Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, C-3-7 / c.3.7 Analista de Monitoring and Evaluation of Selección directa Ejecución IBRD / 85630 Posterior Direct 48,000.00 0.00 2018-06-04 2018-06-09 2018-07-01 2019-07-01 Adquisiciones - UEP the Distribution Grid de consultores pendiente Modernization and Electri cal Losses Reduction Program Page 6 Commercial Management and Project Management, C-3-8 / c.3.8 Ingeniero Monitoring and Evaluation of Selección directa Ejecución IBRD / 85630 Posterior Direct 64,000.00 0.00 2018-06-06 2018-06-11 2018-07-01 2019-07-01 Supervisor UEP the Distribution Grid de consultores pendiente Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, C-3-9 / c.3.9 Especialista Monitoring and Evaluation of Selección directa Ejecución Monitoreo y Evaluacion del IBRD / 85630 Posterior Direct 96,000.00 0.00 2018-06-06 2018-06-11 2018-07-16 2019-07-16 the Distribution Grid de consultores pendiente Proyecto Modernization and Electri cal Losses Reduction Program C-2-11 / c.2.11 Consultor para el Diseno Grafico de Productos Comunicacionales Citizen Engagement and Ejecución IBRD / 85630 Posterior Individual Limited 38,900.00 0.00 2018-06-01 2018-06-12 2018-07-12 2018-08-01 2019-08-01 del Programa de Community Participation pendiente Rehabilitacion de Redes Electricas C-2-5-1 / C-2-5-1 Citizen Engagement and Contratación Analistas de IBRD / 85630 Posterior Individual Limited 63,520.00 0.00 En ejecución 2018-10-15 2018-10-27 2018-10-22 2018-10-29 2018-10-27 2018-10-31 2019-10-31 Community Participation Datos para Edesur y Edeeste. Commercial Management and Project Management, C-3-1-B / c.3.1 Auditoria Monitoring and Evaluation of Selección directa IBRD / 85630 Previa Direct 112,000.00 30,746.08 Firmado 2018-10-30 2018-11-07 2018-11-07 2019-02-07 2019-03-08 2019-05-17 Financiera del Proyecto the Distribution Grid de consultores Modernization and Electri cal Losses Reduction Program C-2-3-A / C-2-3 Citizen Engagement and Contratación Encargada de IBRD / 85630 Posterior Individual Limited 55,219.00 0.00 En ejecución 2019-04-10 2019-04-10 2019-04-15 2019-04-30 2019-05-10 2020-05-09 Community Participation Comunicaciones de la UEP. C-2-3 / c.2.3 Encargada de Citizen Engagement and Selección directa IBRD / 85630 Previa Direct 55,219.00 0.00 Cancelado 2018-12-10 2018-12-15 2019-01-10 2020-01-10 Comunicaciones de la UEP Community Participation de consultores C-2-5 / c.2.5. Contratacion Citizen Engagement and Selección directa Ejecución Directa Analista de datos IBRD / 85630 Posterior Direct 36,735.00 0.00 2018-05-15 2018-05-25 2018-07-01 2019-07-01 Community Participation de consultores pendiente Edenorte C-2-7 / c.2.7 Contratacion de 12 Gestores Sociales de Citizen Engagement and Selección directa Ejecución Informacion para las EDE ( 4 IBRD / 85630 Posterior Direct 244,754.00 0.00 2018-05-14 2018-05-20 2018-06-16 2019-06-16 Community Participation de consultores pendiente EDESUR - 4 EDENORTE - 4 EDEESTE) C-2-8 / c.2.8 Contratacion de 95 personas para gestion social de las EDE (entre Citizen Engagement and Ejecución IBRD / 85630 Previa Individual Limited 2,032,231.00 0.00 2017-06-06 2017-06-11 2017-07-11 2017-08-31 2018-08-31 gestores y supervisores Community Participation pendiente sociales (36 EDESUR - 37 EDENORTE y 22 EDEESTE) C-3-10 / Contratación Directa de 4 captores Commercial Management and actuales, cuyos contratos Project Management, vencen para aprovechar: la Monitoring and Evaluation of Ejecución compentencia de este IBRD / 85630 Posterior Individual Direct 27,890.46 0.00 2019-06-10 2019-06-14 2019-06-19 2019-06-29 2020-06-28 the Distribution Grid pendiente personal, la inversión Modernization and Electri cal realizada en capacitación, la Losses Reduction Program sinergia del equipo de trabajo, etc. Commercial Management and Project Management, C-3-11 / Contratación de 4 Monitoring and Evaluation of Ejecución captores comerciales para IBRD / 85630 Posterior Individual Limited 27,980.46 0.00 2019-06-10 2019-06-15 2019-06-20 2019-06-27 2020-06-26 the Distribution Grid pendiente Edenorte. Modernization and Electri cal Losses Reduction Program Commercial Management and C-3-12 / Contratación Project Management, Directa de 5 supervisores de Monitoring and Evaluation of Ejecución IBRD / 85630 Posterior Individual Direct 47,065.15 0.00 2019-06-10 2019-06-14 2019-06-19 2019-06-29 2020-06-28 captores comerciales para the Distribution Grid pendiente Edenorte Modernization and Electri cal Losses Reduction Program C-2-4-B / c.2.4-B Contratación Encargada de Citizen Engagement and Ejecución IBRD / 85630 Posterior Individual Limited 18,900.00 0.00 2018-06-25 2019-04-10 2019-05-01 2019-06-10 2020-06-09 Comunicaciones de Edeeste, Community Participation pendiente por un año C-2-4 / c.2.4 Consultores de Citizen Engagement and Selección directa Ejecución Comunicacion y Publicidad de IBRD / 85630 Posterior Direct 91,789.00 0.00 2019-06-07 2019-06-12 2019-07-03 2020-07-02 Community Participation de consultores pendiente las EDE Commercial Management and Project Management, C-3-6 / c.3.6. Especialista en Monitoring and Evaluation of Selección directa IBRD / 85630 Previa Direct 118,000.00 0.00 Cancelado 2018-12-10 2018-12-15 2019-01-02 2020-01-02 Adquisiciones UEP the Distribution Grid de consultores Modernization and Electri cal Losses Reduction Program C-1-9-A / Consultor para la evaluación ambiental y Rehabilitation of Selected propuesta de remediación de Distribution Circuits and sitios para ser utilizados Upgrading of Metering Ejecución IBRD / 85630 Posterior Individual Open 55,000.00 0.00 2019-05-13 2019-06-18 2019-07-09 2019-08-13 2019-11-11 como lugar de Systems - Implementation of pendiente almacenamiento de residuos Environmental Manag ement eléctricos generados por el System Proyecto Rehabilitation of Selected Distribution Circuits and C-1-4 / c.1.4. Coordinador Upgrading of Metering Ambiental y Seguridad IBRD / 85630 Posterior Individual Limited 93,600.00 0.00 Cancelado 2018-07-23 2018-07-28 2018-08-07 2018-09-01 2019-09-01 Systems - Implementation of Industrial (EDEESTE) - PMAA Environmental Manag ement System Page 7 Rehabilitation of Selected Distribution Circuits and C-1-4-A / Coordinador Upgrading of Metering Selección directa Ejecución Ambiental y Seguridad IBRD / 85630 Posterior Direct 93,600.00 0.00 2019-06-25 2019-06-30 2019-07-04 2020-07-03 Systems - Implementation of de consultores pendiente Industrial (EDEESTE) – PMAA Environmental Manag ement System Rehabilitation of Selected Distribution Circuits and C-1-2 / c.1.2. Coordinador Upgrading of Metering Ambiental y Seguridad IBRD / 85630 Posterior Individual Limited 93,600.00 0.00 Cancelado 2018-08-09 2018-08-17 2018-08-22 2018-09-01 2019-08-27 Systems - Implementation of Industrial (EDESUR) - PMAA Environmental Manag ement System Rehabilitation of Selected Distribution Circuits and C-1-3 / c.1.3. Coordinador Upgrading of Metering Ambiental y Seguridad IBRD / 85630 Posterior Individual Limited 93,600.00 0.00 Cancelado 2018-07-23 2018-07-28 2018-08-07 2018-09-01 2019-09-01 Systems - Implementation of Industrial (EDENORTE)- PMAA Environmental Manag ement System Rehabilitation of Selected Distribution Circuits and C-1-2-A / Coordinador Upgrading of Metering Selección directa Ejecución Ambiental y Seguridad IBRD / 85630 Posterior Direct 93,600.00 0.00 2019-06-25 2019-08-26 2019-09-04 2020-09-03 Systems - Implementation of de consultores pendiente Industrial (EDESUR) – PMAA Environmental Manag ement System Rehabilitation of Selected Distribution Circuits and C-1-3-A / Coordinador Upgrading of Metering Selección directa Ejecución Ambiental y Seguridad IBRD / 85630 Posterior Direct 93,600.00 0.00 2019-06-25 2019-08-26 2019-09-04 2020-09-03 Systems - Implementation of de consultores pendiente Industrial (EDENORTE) – PMAA Environmental Manag ement System C-2-2-A / C-2-2-A Citizen Engagement and Ejecución Contratación Analista de IBRD / 85630 Posterior Individual Limited 22,000.00 0.00 2019-09-02 2019-09-07 2019-09-28 2019-11-02 2019-12-02 Community Participation pendiente Gestión Social para la UEP C-2-6 / c.2.6 Contratacion Consultores Asistentes Citizen Engagement and Selección directa Ejecución IBRD / 85630 Posterior Direct 72,554.00 0.00 2018-05-15 2018-05-23 2018-06-16 2019-06-16 Gestión Social de las EDE Community Participation de consultores pendiente (EDENORTE - EDEESTE) C-2-6-A / Contratación Citizen Engagement and Ejecución Asistente Gestión Social de IBRD / 85630 Posterior Individual Limited 13,500.00 0.00 2020-01-26 2020-02-02 2020-02-12 2020-02-27 2020-12-31 Community Participation pendiente Edesur Commercial Management and Project Management, C-3-3-B / Segundo Contrato Monitoring and Evaluation of Selección directa Ejecución Especialista de Proyectos IBRD / 85630 Posterior Direct 88,034.00 0.00 2020-03-12 2020-03-15 2020-04-12 2021-04-12 the Distribution Grid de consultores pendiente UEP/CDEEE Modernization and Electri cal Losses Reduction Program Rehabilitation of Selected Distribution Circuits and C-1-10 / c.1.10 Auditorias Upgrading of Metering de apoyo a la supervision y IBRD / 85630 Posterior Individual Limited 44,000.00 0.00 Cancelado 2020-01-10 2020-01-15 2020-02-04 2020-03-10 2020-04-24 Systems - Implementation of capacitacion - PMAA Environmental Manag ement System C-3-13 / Contratación de un Consultor Individual para la Commercial Management and preparación de planes de Project Management, mejora de la gestión (PMG) de Monitoring and Evaluation of IBRD / 85630 Posterior Individual Limited 100,000.00 0.00 En ejecución 2021-01-23 2021-01-19 2021-01-28 2021-01-22 2021-02-07 2021-03-03 2021-08-30 las empresas eléctricas the Distribution Grid estatales EDENORTE, EDESUR, Modernization and Electri cal EDEESTE, ETED y EGEHID de la Losses Reduction Program República Dominicana C-3-14 / Consultor para el Desarrollo de un Plan de Commercial Management and Arquitectura de Red (PAR) Project Management, para la distribución de energía Monitoring and Evaluation of Selección directa IBRD / 85630 Posterior Direct 66,000.00 0.00 En ejecución 2021-03-15 2021-03-04 2021-03-23 2021-04-16 2021-07-15 eléctrica en la República the Distribution Grid de consultores Dominicana y definición de Modernization and Electri cal unidades constructivas Losses Reduction Program asociadas. C-3-15 / Determinación de Commercial Management and la Metodología de Cálculo y Project Management, Ajuste Periódico de los Monitoring and Evaluation of IBRD / 85630 Posterior Individual Limited 50,000.00 0.00 En ejecución 2021-05-14 2021-05-14 2021-05-19 2021-06-09 2021-07-14 2021-09-12 Ingresos Anuales Permitidos the Distribution Grid (IAP) para las EDE a Nivel Modernization and Electri cal Nacional Losses Reduction Program C-3-16 / Actualización e Implementación del Sistema Commercial Management and Único de Cuentas (SUC) e Project Management, Indicadores de Desempeño Monitoring and Evaluation of Selección directa Ejecución IBRD / 85630 Posterior Direct 83,138.71 0.00 2020-11-10 2020-11-20 2021-01-24 2021-04-24 para Empresas de Distribución the Distribution Grid de consultores pendiente o Comercialización de Modernization and Electri cal Sistemas Aislados y Empresas Losses Reduction Program Propietarias de Redes C-3-17 / Evaluación del Commercial Management and Enfoque Actual de Project Management, Planificación e Monitoring and Evaluation of Ejecución Implementación de la IBRD / 85630 Posterior Individual Limited 50,180.00 0.00 2021-07-29 2021-08-05 2021-08-26 2021-09-10 2021-11-09 the Distribution Grid pendiente Expansión del Sector Eléctrico Modernization and Electri cal de la República Dominicana y Losses Reduction Program Recomendaciones de Mejoras Page 8