Overall Implementation and Procurement Plan for the Vietnam COVID-19 Emergency Response Project Project code: P174389 Prepared by NIHE, July 2020 1. Project information: Country: Viet Nam Borrower/Recipient: Socialist Republic of Viet Nam Project Name: Vietnam COVID-19 Emergency Response Project Project ID No: P174389 Project Implementing Agency: NIHE 2. Bank’s approval date of the Procurement Plan: to be approved in the STEP. 3. Date of General Procurement Notice: to be inserted before project implementation. 4. Period covered by this procurement plan: the whole project implementation period I. Works and Goods and Non-Consultant Services: 1. Prior Review Threshold and Procurement Method Thresholds: The proposed procurement approach for this emergency project prioritizes fast track emergency procurement for the emergency goods and services needed. Key measures to fast track procurement include: (i) use of simple and fast procurement and selection methods fit for an emergency situation including direct contracting, as appropriate, (ii) streamlined competitive procedures with shorter bidding time, (iii) force account, as appropriate, and (iv) unlimited thresholds for Requests For Quotations and national procurement among others, as well as no prior review for emergency procurement.. 2. Prequalification. Not expected for the works/goods packages. 3. Any Other Special Procurement Arrangements: National procurement procedures as specified under paragraph 5.4 of the Procurement Regulations and the conditions specified in Annex 1 to this Procurement Plan 4. Leased assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable. 5. Procurement of second hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not applicable. 1 6. Hands-on Expanded Implementation Support (HEIS) as specified under paragraph 3.10 and 3.11 of the Procurement Regulations: Not Applicable. II. Selection of Consultants 1. Prior Review Threshold and Selection Method Thresholds: Simple and fast method will be used including: (i) Direct Selection, as appropriate, (ii) CQS, and (iii) national procurement among others, as well as no prior review for emergency procurement. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. III. Procurement packages with method and Time Schedule Evaluatio Expected Pack Estimated Selection Comp. WB Market n time for Remarks No. Contract Description price method approach methods Implementati No1 (USD) review on Consulting services IC 7/2020 Open/ Best Hiring consultants National Limited Post qualified 1 TV1 253.238 Competitiv Including: Review candiadat e e Selection/ DS TV1.1 Coordinator 14.847 TV1.2 Finance and procurement consultant 34.560 2 TV1.3 Receiving and equipment management consultant 8.687 TV1.4 Accountant Manager 17.374 TV1.5 Disbursement consultant 17.374 TV1.6 Project monitoring & evaluation consultant 17.374 TV1.7 Communication consultant 11.520 TV1.8 Research Consultant 18.900 TV1.9 Training consultant 23.040 TV1.10 Community research consultant 23.040 TV1.11 Data management and analysing consultant 7.680 Consultant to develop Post Direct 7/2020 standard procedure for 2 TV2 operation and 4.608 National DS maintenance of new equipment Evaluate capacity of Direct 7/2020 testing and biosafety assurance of laboratories Post National at provincial hospitals 3 TV3 and provincial centers for 5.760 DS disease control engaged in surveillance and response to the COVID- 19 pandemic Consultant on developing Direct 7/2020 plans and assessment tools; on collecting Post National 4 TV4 5.760 DS information, entering data, analysing data and writing reports on testing 3 capacity and biosafety of laboratories Consultant on developing Post Direct 7/2020 the protocol to the Institutional Review Board National 5 TV5 (IRB), and adapt the 2.880 DS protocol according to the recommendations of the IRB Review of Viet Nam's Post Direct 7/2020 6 TV6 COVID-19 pandemic risk 4.068 DS communication National Independent financial audit Post 7/2020 7 TV7 21.621 National CQS consultant Goods and Non-consulting services Limited/ 7/2020 Delivery Supply and completely Open time: 06 install the system of National Lowest months Transmission electron 1.398.0 RFB or 1 TB1 Post evaluate from the microscope (TEM) 00 RFQ or DS d cost signing of the contract Supply and completely Limited 8/2020 Delivery install the specialized National time: 04 refrigerator system for Lowest months 2 TB2 microbiological samples 345.300 Post RFQ evaluate from the storage and the d cost signing temperature monitoring of the and control system contract 4 Supply and completely Limited 8/2020 Delivery install the air- National time: 04 conditioning system for RFQ Lowest months 3 TB3 standardized laboratory 165.000 Post evaluate from the animal rearing area for d cost signing testing of new pandemic of the and pandemic agents contract Supply and completely Limited 8/2020 Delivery install 1,000 KVA standby National time: 04 TB4 generators for the entire Lowest months operation of the Biosafety 4 289.000 Post RFQ evaluate from the laboratories systems level d cost signing 2 and 3 of the contract Upgrade and install Direct 8/2020 Delivery completely HVAC control time: 04 TB5 National and monitoring system Lowest months 5 for Level 3 Biosafety 84.500 Post DS evaluate from the laboratory system d cost signing of the contract Limited 8/2020 Delivery National time: 04 Supply and completely Lowest months install equipment of the RFQ 6 TB6 781.040 Post evaluate from the Biosafety laboratories d cost signing systems level 2 and 3 of the contract 5 Limited RFQ 8/2020 Delivery Supply and completely National time: 04 install SARS-CoV-2 virus Lowest months 1.278.1 7 TB7 research equipment Post evaluate from the 60 d cost signing of the contract Limited RFQ 8/2020 Delivery Supply and completely National time: 04 install equipment for Lowest months COVID-19 vaccine 8 TB8 866.000 Post evaluate from the research and production, d cost signing and for COVID-19 test kit of the production contract Limited RFQ 7/2020 Delivery time: 02 Post National Lowest months Consumables, test kit for 9 SPNC1 118.800 evaluate from the ELISA testing d cost signing of the contract Limited RFQ 7/2020 Delivery time: 02 Post National Lowest months 10 SPNC2 99.000 evaluate from the Consumables and d cost signing materials for PRNT testing of the contract Consumables and Post Direct DS 7/2020 Delivery 11 SPDT1 1.000 time: 02 materials for TOT courses National weeks 6 on ELISA testing technique from the for SARS-CoV2 diagnostic signing of the contract Consumables and Post Direct DS 7/2020 Delivery materials for training time: 02 National courses on ELISA testing weeks 12 SPDT 2 technique for SARS-CoV2 2.000 from the diagnostic for laboratory signing staff in provinces and of the hospitals in the North contract Consumables and Post Direct DS 7/2020 Delivery materials for training time: 02 National courses on ELISA testing weeks 13 SPDT3 technique for SARS-CoV2 1.000 from the diagnostic for laboratory signing staff in provinces and of the hospitals in the Central contract Consumables and Post Direct DS 7/2020 Delivery materials for training time: 02 National courses on ELISA testing weeks 14 SPDT4 technique for SARS-CoV2 1.000 from the diagnostic for laboratory signing staff in provinces and of the hospitals in the Highland contract Consumables and Post Direct DS 7/2020 Delivery materials for training time: 02 courses on ELISA testing National weeks 15 SPDT5 technique for SARS-CoV2 1.000 from the diagnostic for laboratory signing staff in provinces and hospitals in the South 7 of the contract Consumables and Post Direct DS 7/2020 Delivery materials for training time: 02 courses on techniques of National weeks sampling, storing and from the transporting of samples signing 16 SPDT6 suspicious to be infected 2.000 of the with SARS-CoV2, on contract biosafety and quality control at biosafety level 2 laboratories in Northern provinces Consumables and Post Direct DS 7/2020 Delivery materials for training time: 02 courses on techniques of National weeks sampling, storing and from the transporting of samples signing 17 SPDT7 suspicious to be infected 1.000 of the with SARS-CoV2, on contract biosafety and quality control at biosafety level 2 laboratories in Central provinces Consumables and Post Direct DS 7/2020 Delivery materials for training time: 02 courses on techniques of National weeks sampling, storing and from the 18 SPDT8 transporting of samples 500 signing suspicious to be infected of the with SARS-CoV2, on contract biosafety and quality control at biosafety level 2 8 laboratories in Highland provinces Consumables and Post Direct DS 7/2020 Delivery materials for training time: 02 courses on techniques of National weeks sampling, storing and from the transporting of samples signing 19 SPDT9 suspicious to be infected 1.000 of the with SARS-CoV2, on contract biosafety and quality control at biosafety level 2 laboratories in Southern provinces Post DS 7/2020 Delivery Direct Supplies, consumables time: 02 and tools for sampling, National weeks 20 VT1 preserving and 5.500 from the transporting samples in signing the North of the contract Post Direct DS 7/2020 Delivery Supplies, consumables time: 02 National and tools for sampling, weeks 21 VT2 preserving and 5.500 from the transporting samples in signing the Central of the contract Supplies, consumables Post Direct DS 7/2020 Delivery and tools for sampling, time: 02 22 VT3 preserving and 5.500 National weeks transporting samples in from the the South signing 9 of the contract Renting classroom for Post Direct DS 8/2020 training courses on ELISA testing technique for National 23 HT1 SARS-CoV2 diagnostic for 4.872 laboratory staff in provinces and hospitals in the North Renting classroom for Post Direct DS 8/2020 training courses on ELISA testing technique for National 24 HT2 SARS-CoV2 diagnostic for 2.184 laboratory staff in provinces and hospitals in the Central Post Limited RFQ 8/2020 Contract time: 04 National Documentary film about months 25 PTL the battle against COVID- 40.000 from the 19 in Vietnam signing of the contract Sample collection for Post Direct FA 8/2020 26 TTM1 community immunity 22.800 study in the north National Sample collection for Post Direct FA 8/2020 27 TTM2 community immunity 24.300 study in the central National Sample collection for Post Direct FA 8/2020 28 TTM3 community immunity 24.300 study in the south National 10 Post Direct FA 8/2020 29 XN Perform serological tests 78.750 National TOTAL 5.954.9 Note: The bidding package price includes all 41 import taxes, VAT and all kinds of expenses. The Procurement Plan shall be updated or adjusted during the project implementation as required to reflect the actual project implementation. CQS: Consultant Qualification Based Selection DS: Direct Selection RFQ: Request for Quotations BFP: Bank Facilitated Procurement FA: Force Account 11 Annex 1 - Additional National Procurement Provisions. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 1. Open Competitive Procurement: When the Recipient uses its own national open competitive procurement arrangements as set forth in (a) Article 20 on Open Bidding of the Recipient’s Law on Procurement No. 43/2013/QH13 dated November 26, 2013 and related provisions necessary to effect the same; and (b) the Recipient’s Decree No. 63/2014/ND-CP dated June 26, 2014 Guiding Implementation of the Law on the Procurement (collectively, “National Procurement Laws”), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (i) No domestic preference over foreign bidders shall be granted to national bidders in bid evaluation, nor shall foreign bidders be asked or required to form joint ventures with or be subcontractors to national bidders in order to submit a bid. (ii) The model bidding documents (harmonized model bidding documents) agreed with the Association shall be used. (iii) No bid shall be eliminated from detailed evaluation on the basis of minor, non-substantive deviations. The evaluation of bidder’s qualifications shall be conducted separately subsequent to the technical and commercial evaluation of the bid. (iv) A bidder shall neither be required nor permitted, as a condition for award, to undertake obligations not specified in the bidding documents or otherwise to modify the bid as originally submitted. (v) No bid shall be rejected on the basis of a comparison with the employer’s estimate and budget ceiling. (vi) The Recipient shall implement an effective mechanism allowing bidders to complaint and have their complaints handled in a timely manner. The complaints mechanism shall allow the submission of anonymous complaints. 12 PROCUREMENT Vietnam : Vietnam COVID-19 Emergency Response Project PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2020-08-12 2020-11-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174389 GPN Date: Project Name: Vietnam COVID-19 Emergency Response Project Loan / Credit No: TF / B3197 National Institute of Hygiene and Epidemiology Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: DCVP / Procure Office Communication, Project Request for Single Stage - One furniture (table, bookshelf, TF / B3197 Post Open - National 3,500.00 3,509.06 Completed 2020-08-17 2020-09-01 2020-09-15 2020-09-15 2020-09-25 management, monitoring and Quotations Envelope chair…) evaluation TBVP / Procure Office Component 3: equipments and supplies Communication, Project Request for Single Stage - One TF / B3197 Post Open - National 15,100.00 0.00 Canceled 2020-08-17 2020-09-05 2020-09-19 (computer, printer, scanner, management, monitoring and Quotations Envelope photocopier…) evaluation TB3 / Supply and completely install the air-conditioning system for standardized Component 1: Strengthening Request for Single Stage - One experimental animal TF / B3197 surveillance and testing Post Open - National 165,000.00 0.00 Canceled 2020-09-04 2020-09-25 2021-01-23 Quotations Envelope laboratory area for testing of capacities emerging and pandemic agents TB2 / Supply and completely install the specialized refrigerator system for Component 1: Strengthening Single Stage - One microbiological samples TF / B3197 surveillance and testing Post Request for Bids Open - National 345,300.00 0.00 Canceled 2020-08-27 2020-09-01 2020-10-01 2020-10-15 2020-10-19 2021-01-17 Envelope storage and the temperature capacities monitoring and control system TB1 / Supply and completely Component 1: Strengthening install the system of Single Stage - One TF / B3197 surveillance and testing Post Request for Bids Open - National 1,389,792.00 0.00 Canceled 2020-08-27 2020-08-30 2020-09-29 2020-10-06 2020-10-14 2021-01-30 Transmission electron Envelope capacities microscope (TEM) TB4 / Supply and completely install 1,000 KVA standby Component 1: Strengthening generators for the entire Single Stage - One TF / B3197 surveillance and testing Post Request for Bids Open - National 289,000.00 0.00 Canceled 2020-08-30 2020-09-02 2020-10-02 2020-10-09 2020-10-15 2021-01-13 operation of the Biosafety Envelope capacities laboratories systems level 2 and 3 TB5 / Upgrade and install Component 1: Strengthening completely HVAC control and TF / B3197 surveillance and testing Post Direct Selection Direct 84,500.00 0.00 Canceled 2020-08-31 2020-09-14 2020-09-23 2021-01-21 monitoring system for Level 3 capacities Biosafety laboratory system TB6 / Supply and completely Component 1: Strengthening install equipment of the Single Stage - One TF / B3197 surveillance and testing Post Request for Bids Open - National 781,210.00 0.00 Canceled 2020-08-31 2020-09-03 2020-10-03 2020-10-17 2020-10-22 2021-01-20 Biosafety laboratories systems Envelope capacities level 2 and 3 TB7 / Supply and completely Component 1: Strengthening Single Stage - One install SARS-CoV-2 virus TF / B3197 surveillance and testing Post Request for Bids Open - National 1,278,160.00 0.00 Canceled 2020-09-06 2020-09-11 2020-10-11 2020-10-25 2020-10-29 2021-01-27 Envelope research equipment capacities TB8 / Supply and completely install equipment for COVID- Component 1: Strengthening Single Stage - One 19 vaccine research and TF / B3197 surveillance and testing Post Request for Bids Open - National 874,000.00 0.00 Canceled 2020-09-06 2020-09-09 2020-10-09 2020-10-23 2020-10-29 2021-01-27 Envelope production, and for COVID-19 capacities test kit production TB 3 / Supply and completely install the air-conditioning Component 1: Strengthening system for standardized Request for Single Stage - One TF / B3197 surveillance and testing Post Open - National 165,000.00 166,144.81 Signed 2020-09-11 2020-10-10 2020-11-02 2021-01-18 laboratory animal rearing area Quotations Envelope capacities for testing of new pandemic and pandemic agents TB 4 / Supply and completely install 1,000 KVA standby Component 2: Strengthening generators for the entire capacities of research of Request for Single Stage - One TF / B3197 Post Open - National 289,000.00 284,712.29 Signed 2020-09-09 2020-10-16 2020-11-02 2021-01-24 operation of the Biosafety COVID-19 vaccines and test Quotations Envelope laboratories systems level 2 kits and 3 TB 5 / Upgrade and install Component 2: Strengthening completely HVAC control and capacities of research of TF / B3197 Post Direct Selection Direct 84,500.00 84,483.78 Signed 2020-09-06 2020-09-21 2020-09-20 2020-10-13 2020-09-26 2020-11-02 2021-01-04 monitoring system for Level 3 COVID-19 vaccines and test Biosafety laboratory system kits TB 1 / Supply and completely Component 1: Strengthening install the system of Request for Single Stage - One TF / B3197 surveillance and testing Post Open - National 1,389,792.00 1,382,669.05 Signed 2020-09-09 2020-10-14 2020-11-02 2021-01-22 Transmission electron Quotations Envelope capacities microscope (TEM) Page 1 TB 2 / Supply and completely install the specialized refrigerator system for Component 1: Strengthening Under Request for Single Stage - One microbiological samples TF / B3197 surveillance and testing Post Open - National 345,300.00 341,904.75 Implementati 2020-09-09 2020-10-16 2021-01-24 Quotations Envelope storage and the temperature capacities on monitoring and control system TB 6 / Supply and completely Component 1: Strengthening install equipment of the Request for Single Stage - One TF / B3197 surveillance and testing Post Open - National 781,210.00 779,080.29 Signed 2020-09-11 2020-10-16 2020-11-02 2021-01-24 Biosafety laboratories systems Quotations Envelope capacities level 2 and 3 TB 7 / Supply and completely Component 1: Strengthening Request for Single Stage - One install SARS-CoV-2 virus TF / B3197 surveillance and testing Post Open - National 1,278,160.00 1,239,862.09 Signed 2020-09-11 2020-10-18 2020-11-02 2021-01-26 Quotations Envelope research equipment capacities TB 8 / Supply and completely install equipment for COVID- Component 1: Strengthening Request for Single Stage - One 19 vaccine research and TF / B3197 surveillance and testing Post Open - National 874,000.00 859,141.40 Signed 2020-09-11 2020-10-18 2020-11-02 2021-01-26 Quotations Envelope production, and for COVID-19 capacities test kit production SP1 / Test Kits for detection Component 1: Strengthening Pending of SARS-CoV-2 anti-body in TF / B3197 surveillance and testing Post Direct Selection Direct 74,172.00 0.00 Implementati 2020-11-04 2020-11-07 2020-11-10 2021-01-09 human serum, human plasma capacities on by ELISA technique. SP2 / Supply reagents, Component 1: Strengthening Under Request for Single Stage - One consumables and chemical for TF / B3197 surveillance and testing Post Open - National 78,946.00 0.00 Implementati 2020-11-05 2020-11-13 2021-01-12 Quotations Envelope research, testing and training. capacities on Component 1: Strengthening Pending VT1 / Supply the Request for Single Stage - One TF / B3197 surveillance and testing Post Limited 69,338.00 0.00 Implementati 2020-11-05 2020-11-15 2021-01-14 Consumables for research. Quotations Envelope capacities on Component 1: Strengthening Under VT2 / Supply the Request for Single Stage - One TF / B3197 surveillance and testing Post Limited 52,331.00 0.00 Implementati 2020-11-05 2020-11-15 2021-01-14 Consumables for training Quotations Envelope capacities on Component 3: Under TBVP1 / Supply the desktop Communication, Project Request for Single Stage - One TF / B3197 Post Limited 4,260.00 0.00 Implementati 2020-11-08 2020-11-15 2020-11-29 and laptop management, monitoring and Quotations Envelope on evaluation MT / Media for sample Component 1: Strengthening Pending Request for Single Stage - One preservation and TF / B3197 surveillance and testing Post Limited 7,860.00 0.00 Implementati 2020-11-07 2020-11-15 2020-11-30 Quotations Envelope transportation capacities on Component 3: Pending TBVP2 / Supply the Communication, Project Request for Single Stage - One TF / B3197 Post Limited 4,313.00 0.00 Implementati 2020-11-28 2020-12-09 2020-12-23 photocopy and scan machine management, monitoring and Quotations Envelope on evaluation NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual XN / Perform serological Component 1: Strengthening Under tests for samples of TF / B3197 surveillance and testing Post Force Account Direct 66,000.00 0.00 Implementati 2020-09-30 2020-10-06 2020-10-05 2020-10-19 2021-01-17 community immunity study capacities on TTM / Implement sample Component 1: Strengthening collection for community TF / B3197 surveillance and testing Post Force Account Direct 20,800.00 20,641.05 Signed 2020-09-30 2020-10-01 2020-10-05 2020-10-05 2020-10-19 2020-10-08 2021-01-17 immunity study capacities Component 3: PTL / Documentary film Pending Communication, Project about the battle against TF / B3197 Post Direct Selection Direct 50,000.00 0.00 Implementati 2020-11-08 2020-11-13 2020-11-16 2021-01-15 management, monitoring and COVID -19 in Vietnam on evaluation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Consultant TV19 / Recruit Independent Communication, Project Pending TF / B3197 Post Qualification Open - National 21,621.00 0.00 2020-08-23 2020-09-06 2020-09-25 2020-10-25 2020-11-04 2021-02-02 financial audit management, monitoring and Implementation Selection evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Individual TV1 / Recruit a project Communication, Project TF / B3197 Post Consultant Direct 14,400.00 14,227.82 Signed 2020-08-12 2020-08-14 2020-08-24 2020-08-25 2020-08-29 2020-08-29 2020-09-01 2020-09-01 2021-01-29 coordinator management, monitoring and Selection evaluation Component 3: Individual TV2 / Recruit a project Communication, Project TF / B3197 Post Consultant Direct 14,400.00 14,227.82 Signed 2020-08-12 2020-08-14 2020-08-24 2020-08-25 2020-08-29 2020-08-29 2020-09-01 2020-09-01 2021-01-29 Planning consultant management, monitoring and Selection evaluation Component 3: Individual TV3 / Recruit a language and Communication, Project TF / B3197 Post Consultant Direct 14,400.00 14,227.82 Signed 2020-08-11 2020-08-18 2020-08-18 2020-08-25 2020-08-25 2020-08-29 2020-08-28 2020-09-01 2021-01-25 interpretation consultant management, monitoring and Selection evaluation Page 2 Component 3: Individual TV4 / Recruit a procurement Communication, Project TF / B3197 Post Consultant Direct 14,400.00 14,227.82 Signed 2020-08-11 2020-08-12 2020-08-18 2020-08-25 2020-08-25 2020-08-29 2020-08-28 2020-09-01 2021-01-25 consultant management, monitoring and Selection evaluation Component 3: Individual TV5 / Recruit Senior Communication, Project TF / B3197 Post Consultant Direct 8,100.00 0.00 Canceled 2020-08-11 2020-08-12 2020-08-18 2020-08-25 2020-08-28 2021-01-25 procurement consultant management, monitoring and Selection evaluation Component 3: Individual TV6 / Recruit equipment Communication, Project TF / B3197 Post Consultant Direct 14,400.00 14,227.82 Signed 2020-08-12 2020-08-12 2020-08-19 2020-08-25 2020-08-26 2020-08-29 2020-08-29 2020-09-01 2021-01-26 management consultant management, monitoring and Selection evaluation Component 3: TV7 / Recruit biosafety and Individual Communication, Project equipment calibration TF / B3197 Post Consultant Direct 14,400.00 14,227.82 Signed 2020-08-12 2020-08-14 2020-08-19 2020-10-02 2020-08-26 2020-10-08 2020-08-29 2020-10-12 2021-01-26 management, monitoring and consultant Selection evaluation Component 3: Individual TV8 / Recruit finance Communication, Project TF / B3197 Post Consultant Direct 14,400.00 14,227.82 Signed 2020-08-12 2020-08-14 2020-08-19 2020-08-25 2020-08-26 2020-08-29 2020-08-29 2020-09-01 2021-01-26 management consultant management, monitoring and Selection evaluation Component 3: Individual TV9 / Recruit disbursement Communication, Project TF / B3197 Post Consultant Direct 8,775.00 8,670.08 Signed 2020-08-12 2020-08-14 2020-08-19 2020-08-25 2020-08-26 2020-08-29 2020-08-29 2020-09-01 2021-01-26 and accountant consultant management, monitoring and Selection evaluation Component 3: TV10 / Recruit project Individual Communication, Project monitoring & evaluation TF / B3197 Post Consultant Direct 10,560.00 10,433.74 Signed 2020-08-23 2020-08-14 2020-09-04 2020-08-25 2020-09-11 2020-09-18 2020-09-01 2021-01-16 management, monitoring and consultant Selection evaluation Component 3: TV11 / Recruit Individual Communication, Project communication and TF / B3197 Post Consultant Direct 10,560.00 10,433.74 Signed 2020-08-23 2020-08-18 2020-09-04 2020-10-02 2020-09-09 2020-10-08 2020-09-16 2020-10-12 2021-01-14 management, monitoring and safeguards consultant Selection evaluation Component 3: TV14.1 / Recruit consultant Individual Communication, Project for training on serological TF / B3197 Post Consultant Direct 12,150.00 12,004.73 Signed 2020-08-16 2020-08-18 2020-08-23 2020-10-02 2020-08-30 2020-09-02 2020-10-12 2020-12-01 management, monitoring and testing and other technique Selection evaluation Component 3: Individual TV15.1 / Recruit consultant Communication, Project TF / B3197 Post Consultant Direct 12,150.00 12,004.73 Signed 2020-08-16 2020-08-16 2020-08-23 2020-10-02 2020-08-30 2020-09-02 2020-10-12 2020-12-31 on epidemiology management, monitoring and Selection evaluation Component 3: TV16.1 / Recruit consultant Individual Communication, Project for quality assurance of TF / B3197 Post Consultant Direct 9,600.00 9,485.22 Signed 2020-08-16 2020-08-16 2020-08-23 2020-10-02 2020-08-30 2020-09-01 2020-10-12 2020-12-30 management, monitoring and sample collection Selection evaluation Component 3: Individual TV17.1 / Recruit consultant Communication, Project TF / B3197 Post Consultant Direct 5,760.00 5,691.13 Signed 2020-08-23 2020-08-18 2020-09-04 2020-10-02 2020-09-09 2020-09-16 2020-10-12 2021-01-14 on data management report management, monitoring and Selection evaluation TV12 / Consultant to develop Component 1: Strengthening Individual standard procedure for TF / B3197 surveillance and testing Post Consultant Direct 4,608.00 4,552.90 Signed 2020-10-01 2020-09-04 2020-10-06 2020-10-02 2020-10-09 2020-10-08 2020-10-12 2020-10-12 2021-01-10 operation and maintenance of capacities Selection new equipment TV13 / Consultant to evaluate capacity of testing and biosafety assurance of laboratories at provincial Component 1: Strengthening Individual hospitals and provincial TF / B3197 surveillance and testing Post Consultant Direct 5,760.00 5,691.13 Signed 2020-08-12 2020-09-04 2020-08-19 2020-10-02 2020-08-26 2020-10-08 2020-08-29 2020-10-12 2020-10-28 centers for disease control capacities Selection engaged in surveillance and response to the COVID-19 pandemic TV18 / Consultant to review Component 1: Strengthening Individual Viet Nam's COVID-19 TF / B3197 surveillance and testing Post Consultant Direct 7,680.00 0.00 Canceled 2020-09-01 2020-09-08 2020-09-15 2020-09-19 2020-11-18 pandemic risk communication capacities Selection TV14.2 / Recruit consultant Component 3: Individual on sample collection, Communication, Project TF / B3197 Post Consultant Direct 12,150.00 12,004.73 Signed 2020-08-16 2020-08-16 2020-08-28 2020-10-02 2020-09-04 2020-10-08 2020-09-07 2020-10-12 2020-12-06 biosafety and quality management, monitoring and Selection management evaluation Component 3: Individual TV15.2 / Recruit consultant Communication, Project TF / B3197 Post Consultant Direct 12,150.00 12,004.73 Signed 2020-08-16 2020-08-16 2020-08-23 2020-10-02 2020-08-30 2020-09-14 2020-10-12 2020-12-13 on medical microbiology management, monitoring and Selection evaluation Component 3: TV16.2 / Recruit a consultant Individual Communication, Project for quality assurance of lab TF / B3197 Post Consultant Direct 9,600.00 0.00 Canceled 2020-08-16 2020-08-16 2020-08-23 2020-08-30 2020-09-04 2021-01-02 management, monitoring and testing Selection evaluation Component 3: Individual TV17.2 / Recruit a consultant Communication, Project TF / B3197 Post Consultant Direct 5,760.00 5,691.13 Signed 2020-08-23 2020-08-18 2020-09-04 2020-10-02 2020-09-09 2020-10-08 2020-09-16 2020-10-12 2021-01-14 on data analysis and report management, monitoring and Selection evaluation Component 3: Individual TV5A / Recruit a Communication, Project TF / B3197 Post Consultant Direct 7,004.00 6,548.03 Signed 2020-09-11 2020-09-11 2020-09-19 2020-10-02 2020-09-26 2020-10-08 2020-10-01 2020-10-12 2021-01-29 procurement consultant management, monitoring and Selection evaluation Page 3