Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Original: August 19, 2016; Updated Procurement Plan, April 2017 2. Date of General Procurement Notice: Dec 24, 2015 3. Period covered by this procurement plan: The procurement period of project covered from August 2016 – December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB Goods and Non-Consulting Above or equal to All Services US$ 2,000,000 2. NCB - Goods and Non-Consulting Below US$ 2,000,000 None Services 3. Shopping - Goods and Non- Below US$ 100,000 None Consulting Services 4. ICB (Works) Above US$ 10 million All 5. NCB (Works) Below US$ 10 million None 6. Shopping – (Works) Below US$ 100,000 None 2. Prequalification. Bidders for shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: N/A at this stage 5. Any Other Special Procurement Arrangements: 5 ICB works packages are eligible to be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 128.1 8 No Prior of the ICB (Works) Summary 1.8 1 No Prior of the ICB (Goods) Summary 19 3 No Post of the NCB (Works) Summary 4.8 1 No Prior of the ICB (Non- Consultant Services) Summary 0.27 1 No Post of the Shopping (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 1,000,000 All QCBS 1. Competitive Methods (Firms) ≥ 300,000 - < None QCBS 1,000,000 1. Competitive Methods (Firms) Below US$ 300,000 None CQS/FBS/LCS 2. Single Source (Firms) All All 3. Individual Above or equal to US$ All 200,000 4. Individual Below US$ 200,000 None 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. 3. Any Other Special Selection Arrangements: 5 QCBS works packages are eligible to be financed under retroactive financing 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 38.1 13 Prior of number of contracts that will be let under QCBS Summary 0.93 3 Prior CQS of number of contracts that will be let under other methods Summary 4.4 7 Prior of number of contracts that will be let under ICS PROCUREMENT Angola : Second Water Sector Institutional Development Project PLAN General Information Country: Angola Bank’s Approval Date of the Original Procurement Plan: 2016-08-10 2021-08-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151224 GPN Date: 2017-08-07 Project Name: Second Water Sector Institutional Development Project Loan / Credit No: IBRD / 87020, / , COFN / C1560 N Executing Agency(ies): ational Directorate of Water WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 1W3/MALANJE/DNA/16 / Rehabilitation and Expansion Design and construction of Single Stage - One 13,800,000.0 8,304,193.5 2021-02- IBRD / 87020 of Water Supply Production Prior Request for Bids Open - International Signed 2016-09-07 2016-11-02 2017-03-04 2016-11-06 2017-05-27 2017-02-21 2017-06-26 2017-04-18 2017-02-27 2017-06-20 network and home Envelope 0 8 25 and Distribution connections in Malanje 2W3/DUNDO/DNA/16 / Rehabilitation and Expansion Design and construction of Single Stage - One 16,050,000.0 12,836,980. Under 2021-05- IBRD / 87020 of Water Supply Production Prior Request for Bids Open - International 2016-09-27 2017-04-14 2016-10-02 2017-04-19 2017-02-27 2017-06-23 2017-03-29 2017-09-26 2017-05-04 2017-10-26 network and home Envelope 0 85 Review 03 and Distribution connections in Dundo 3W3/HUAMBO/DNA/16 / Design and construction of Rehabilitation and Expansion Single Stage - One 23,000,000.0 14,455,883. 2020-12- network and home connection IBRD / 87020 of Water Supply Production Prior Request for Bids Open - International Signed 2016-10-12 2016-12-19 2016-10-23 2017-01-17 2017-02-19 2017-03-22 2017-03-21 2017-09-15 2017-05-10 2017-11-07 Envelope 0 26 10 for peri-urban areas in and Distribution Huambo 4W3/LUENA/DNA/16 / Rehabilitation and Expansion Design and construction of Single Stage - One 17,250,000.0 9,849,128.1 2021-05- IBRD / 87020 of Water Supply Production Prior Request for Bids Open - International Signed 2016-10-15 2017-03-29 2017-05-25 2017-03-30 2017-09-20 2017-06-09 2017-10-20 2017-09-14 2017-05-15 2017-10-30 network and home Envelope 0 9 14 and Distribution connections in Luena 5W3/UIGE/DNA/16 / Design Rehabilitation and Expansion Single Stage - One 11,500,000.0 11,011,372. 2021-05- and construction of network IBRD / 87020 of Water Supply Production Prior Request for Bids Open - International Signed 2016-11-14 2017-04-14 2016-11-19 2017-04-19 2017-03-01 2017-06-16 2017-03-31 2017-10-24 2017-05-19 2017-11-13 Envelope 0 76 18 and home connections in Uige and Distribution 7W3/KUITO/DNA/16 / Rehabilitation and Expansion Design and construction of Single Stage - One 4,071,186.0 2020-06- IBRD / 87020 of Water Supply Production Post Request for Bids Open - National 5,000,000.00 Signed 2017-01-16 2017-06-01 2017-01-21 2017-06-01 2017-03-21 2017-07-19 2017-04-20 2017-10-11 2017-05-31 2017-11-16 network and home Envelope 8 01 and Distribution connections in Kuito 9W3/NDALATANDO/DNA/16 / Design and construction for Rehabilitation and Expansion refurbishment of the WTW, Single Stage - One 10,500,000.0 2020-09- / of Water Supply Production Prior Request for Bids Open - International 0.00 Canceled 2017-05-11 2017-05-16 2017-07-17 2017-08-16 2017-09-28 construction of distribution Envelope 0 28 and Distribution centers and 1.6 km trunk mains for Ndalatando 33W3-B/HUAMBO/DAS/17 / Rehabilitation and Expansion Construction of Network and 5,936,691.6 2019-02- IBRD / 87020 of Water Supply Production Prior Direct Selection Direct 5,757,583.00 Signed 2017-05-19 2017-05-24 2017-06-28 2017-07-12 Home Connections for the 9 18 and Distribution City of Huambo-Lot 2 13W3/KUITO/DNA/17 / Rehabilitation and Expansion Supply and installation of 2018-04- IBRD / 87020 of Water Supply Production Post Direct Selection Direct 400,000.00 0.00 Canceled 2017-09-01 2017-09-06 2017-10-11 valves and fittings for Kuito 09 and Distribution Water Supply System 12W3/NDALATANDO/DNA/17 / Supply and installation of Rehabilitation and Expansion Single Stage - One 2018-07- bulk meters and valves for IBRD / 87020 of Water Supply Production Post Request for Bids Open - National 400,000.00 0.00 Canceled 2017-09-12 2017-09-17 2017-10-29 2017-11-28 2018-01-02 Envelope 01 Ndalatando water supply and Distribution system 6W3-R/DAS/17 / Repairs to Rehabilitation and Expansion the Network and Home Single Stage - One 1,619,865.2 2019-08- IBRD / 87020 of Water Supply Production Post Request for Bids Open - National 770,000.00 Signed 2018-10-22 2018-10-30 2018-10-27 2018-10-30 2018-12-08 2018-12-17 2019-01-07 2018-12-21 2019-02-11 2019-02-15 Connections in the City of Envelope 7 10 and Distribution Ndalatando 8W3/NDALATANDO/DNA/16 / Design and construction of a new water source, WTW, Rehabilitation and Expansion Single Stage - One 30,000,000.0 2023-06- pumping station, raw water IBRD / 87020 of Water Supply Production Prior Request for Bids Open - International 0.00 Canceled 2018-05-28 2018-08-09 2018-08-12 2018-06-15 2018-09-03 2018-10-03 2018-11-26 Envelope 0 26 pipeline, distribution centers and Distribution and trunk mains for Ndalatando 9W3/LUBANGO/DNA/18 / Rehabilitation and Expansion Construction of Water Single Stage - One 1,893,993.0 2019-06- IBRD / 87020 of Water Supply Production Post Request for Bids Open - National 700,000.00 Signed 2018-09-06 2019-03-17 2018-09-11 2019-03-29 2018-10-23 2019-05-14 2018-11-22 2019-06-14 2018-12-27 2019-08-12 Production Boreholes in Envelope 8 25 and Distribution Lubango 8W3A/NDALATANDO/DNA/18 / Design and construction of a new water source, WTW, Rehabilitation and Expansion Request for 50,000,000.0 24,354,312. 2020-11- pumping station, raw water IBRD / 87020 of Water Supply Production Prior Open - International Multi Stage Signed 2018-07-10 2018-09-26 2018-10-05 2019-02-27 2018-10-05 2019-04-02 2018-07-25 2018-09-27 2018-12-24 2019-07-02 2019-04-22 2020-03-19 2019-05-27 2020-04-16 Proposals 0 36 17 pipeline, distribution centers and Distribution and trunk mains for Ndalatando 10W3/LUBANGO/DNA/16 / Rehabilitation and Expansion Single Stage - One 11,121,500.0 4,423,990.0 2021-04- Design and Construction of IBRD / 87020 of Water Supply Production Prior Request for Bids Open - International Signed 2018-12-12 2019-03-21 2018-12-17 2019-03-25 2019-03-07 2019-05-13 2019-04-06 2019-06-18 2019-05-11 2019-08-20 Envelope 0 6 30 reservoirs in Lubango and Distribution 45W3/MALANJE/DNA/18 / Rehabilitation and Expansion Single Stage - One 2020-03- Repair works to connections IBRD / 87020 of Water Supply Production Post Request for Bids Open - National 2,500,000.00 0.00 Canceled 2018-10-31 2018-11-05 2019-01-14 2019-02-13 2019-03-20 Envelope 14 in Malanje and Distribution 46W3/CUITO/DNA/18 / Rehabilitation and Expansion Under Design and Construction of Single Stage - One 2022-04- COFN / C1560 of Water Supply Production Post Request for Bids Open - National 3,500,000.00 0.00 Implementat 2020-06-29 2021-07-08 2020-07-04 2021-07-24 2020-08-15 2020-09-14 2020-10-19 Network and Household Envelope 12 and Distribution ion Connections in Cuito-Phase 2 Page 1 44W3/LUBANGO/DNA/18 / Rehabilitation and Expansion Under Design and Construction of Single Stage - One 5,570,928.3 2022-01- COFN / C1560 of Water Supply Production Post Request for Bids Open - National 3,500,000.00 Implementat 2020-04-16 2020-11-03 2020-04-21 2020-11-03 2020-06-02 2021-06-30 2020-07-02 2021-06-30 2020-08-06 Network and Household Envelope 8 28 and Distribution ion Connections in Lubango 6W3/NAMIBE/DNA/16 / Rehabilitation and Expansion Design and construction of Single Stage - One 3,344,889.8 2023-11- COFN / C1560 of Water Supply Production Post Request for Bids Open - International 9,000,000.00 Signed 2019-05-23 2019-10-31 2019-05-28 2019-10-30 2019-09-10 2020-05-19 2019-10-10 2020-06-30 2019-11-16 2020-08-31 network and home Envelope 3 10 and Distribution connections in Namibe 11W3/LUBANGO/DNA/16 / Rehabilitation and Expansion Pending Single Stage - One 2022-02- Design and construction of COFN / C1560 of Water Supply Production Post Request for Bids Open - National 8,000,000.00 0.00 Implementat 2020-10-30 2020-11-04 2020-12-16 2021-01-15 2021-02-19 Envelope 19 boreholes in Lubango and Distribution ion 74W3/UIGE/19 / Design and construction of a new water Rehabilitation and Expansion Under source, WTW, pumping Request for 35,000,000.0 2023-05- COFN / C1560 of Water Supply Production Prior Open - International Multi Stage 0.00 Implementat 2019-07-25 2019-10-10 2019-10-20 2020-04-28 2019-10-20 2020-06-04 2019-08-09 2019-10-15 2020-01-08 2020-11-12 2020-05-06 2020-06-10 station, raw water pipeline, Proposals 0 26 and Distribution ion distribution centers and trunk mains for Uige 15W3/NDALATANDO/DNA/20 / Design and Construction of Rehabilitation and Expansion Under Single Stage - One 15,500,000.0 2021-03- Network and home COFN / C1560 of Water Supply Production Prior Request for Bids Open - International 0.00 Implementat 2020-05-19 2020-08-12 2020-05-24 2020-08-25 2020-07-05 2020-11-13 2020-08-04 2021-05-25 2020-09-08 Envelope 0 07 connections in Ndalatando and Distribution ion Lot 2 16W3/UIGE/DNA/20 / Design Rehabilitation and Expansion Under Single Stage - One 14,500,000.0 2021-03- and Construction of Network COFN / C1560 of Water Supply Production Prior Request for Bids Open - International 0.00 Implementat 2020-05-25 2020-07-21 2020-05-30 2020-07-27 2020-07-11 2020-11-11 2020-08-10 2021-06-23 2020-09-14 Envelope 0 13 and home connections in Uige and Distribution ion 17W3/HUAMBO/DNA/20 / Rehabilitation and Expansion Pending Single Stage - One 2021-06- Remedial of Water Supply at COFN / C1560 of Water Supply Production Post Request for Bids Open - National 3,000,000.00 0.00 Implementat 2020-08-31 2020-09-05 2020-10-17 2020-11-16 2020-12-21 Envelope 19 Huambo and Distribution ion 18W3/DNA/20 / Remedial of Rehabilitation and Expansion Pending Single Stage - One 2021-07- Water Supply Systems at Uige, COFN / C1560 of Water Supply Production Post Request for Bids Open - National 6,000,000.00 0.00 Implementat 2020-09-14 2020-09-19 2020-10-31 2020-11-30 2021-01-04 Envelope 03 Malange, Lubango and Cuito and Distribution ion 14W3/N’DALATANDO/DNA/2 0 / DESIGN AND CONSTRUCTION OF THE Rehabilitation and Expansion Under EXPANSION AND Single Stage - One 2021-10- COFN / C1560 of Water Supply Production Post Request for Bids Open - International 5,000,000.00 0.00 Implementat 2020-12-31 2021-01-08 2021-01-05 2021-01-08 2021-02-16 2021-04-01 2021-03-18 2021-04-22 REHABILITATION OF THE Envelope 19 and Distribution ion EXISTING MUCARI BULK WATER SUPPLY SYSTEM OF THE CITY OF N’DALATANDO 14W3/NDALATANDO/DNA/20 / Design and Construction of the Expansion and Rehabilitation and Expansion Single Stage - One 2021-03- Rehabilitation of the Existing COFN / C1560 of Water Supply Production Prior Request for Bids Open - International 5,000,000.00 0.00 Canceled 2020-05-25 2020-05-30 2020-07-11 2020-08-10 2020-09-14 Envelope 13 Mucari Bulk Water Supply and Distribution System of the city of Ndalatando 109W3/NDALATANDO/21 / Design and Construction of National distribution network and Rehabilitation and Expansion Procurement Pending Single Stage - One 2022-06- household connections in city IBRD / 87020 of Water Supply Production Post Request for Bids Open - National Document - 1 7,008,000.00 0.00 Implementat 2021-08-15 2021-08-20 2021-10-01 2021-10-31 2021-12-05 Envelope 03 of Lucala and rural and Distribution Envelope process ion communities between Lucala (Non Bank-SPD) and N’Dalatando GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 4G4/DNA/16 / Implementation of a Financial Management and Engineering Request for Single Stage - One / Post Limited 70,000.00 0.00 Canceled 2017-08-08 2017-10-03 2018-04-01 Management System Support Quotations Envelope (Primavera software) 47G1/CITIES/DNA/18 / Water Water Supply Institutional Single Stage - One meters, pipes valves and IBRD / 87020 Strengthening and Capacity Prior Request for Bids Open - National 800,000.00 3,189,329.35 Signed 2018-07-20 2018-10-16 2018-07-25 2018-10-16 2018-09-05 2018-12-04 2018-10-05 2019-02-28 2018-11-09 2019-06-10 2019-05-08 Envelope fittings for six cities Development 53G1/CITIES/DNA/18 / Water Supply Institutional Workstations and printers for Single Stage - One IBRD / 87020 Strengthening and Capacity Post Request for Bids Open - National 300,000.00 370,492.32 Signed 2018-05-30 2018-11-09 2018-06-04 2019-03-18 2018-07-19 2019-04-26 2018-08-18 2019-08-14 2018-09-22 2019-11-18 2019-03-21 Utilities in Huila, Malanje and Envelope Development Cuanza Norte 2G4/DNA/16 / Computers Rehabilitation and Expansion Request for Single Stage - One and IT equipment for the IBRD / 87020 of Water Supply Production Post Limited 100,000.00 97,808.86 Signed 2019-02-17 2018-10-23 2019-04-14 2018-11-26 2019-10-11 Quotations Envelope Project and Distribution 3G4/DNA/16 / Furniture Management and Engineering Request for Single Stage - One IBRD / 87020 Post Limited 100,000.00 63,269.83 Signed 2019-03-05 2018-10-26 2019-04-30 2018-11-28 2019-10-27 shopping Support Quotations Envelope 71G3/UIGE/DNA/18 / Power Rehabilitation and Expansion Pending Request for Single Stage - One Transformer for Uige Water IBRD / 87020 of Water Supply Production Post Limited 50,000.00 0.00 Implementati 2019-01-28 2019-03-25 2019-09-21 Quotations Envelope Supply System and Distribution on 70CS2/INRH/18 / Purchase and installation of 15 remote satellite communication Single Stage - One COFN / C1560 Water Resource Management Post Request for Bids Open - National 750,000.00 0.00 Canceled 2020-05-13 2020-05-18 2020-06-29 2020-07-29 2020-09-02 2021-03-01 equipment and Envelope meteorological sensors for hydrometric stations 1G4/DNA/16 / Education and Water Supply Institutional Single Stage - One laboratory equipment for COFN / C1560 Strengthening and Capacity Post Request for Bids Open - International 1,800,000.00 0.00 Canceled 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2021-01-15 2022-01-15 Envelope Onga Zanga training center Development 48/G1/CITIES/DNA/18 / Water Supply Institutional Single Stage - One Workshop and maintenance IBRD / 87020 Strengthening and Capacity Post Request for Bids Open - National 250,000.00 0.00 Canceled 2018-06-20 2018-06-25 2018-08-06 2018-09-05 2018-10-10 2019-04-08 Envelope equipment Development Page 2 5G4/DNA/20 / Procurement Management and Engineering Request for Single Stage - One of TOMPRO Accounting IBRD / 87020 Post Limited 50,000.00 51,203.21 Signed 2020-02-16 2020-03-10 2020-04-26 2020-05-25 2020-07-26 Support Quotations Envelope Software 6G4/UCP/20 / Procurement Water Supply Institutional of Computers for Young Request for Single Stage - One IBRD / 87020 Strengthening and Capacity Post Limited 100,000.00 49,820.29 Signed 2020-02-14 2020-03-11 2020-04-10 2020-04-15 2020-10-07 Professionals and FCMU Quotations Envelope Development Consultants 54G2/INRH/20 / Under Single Stage - One Procurement of ArGis software COFN / C1560 Water Resource Management Post Request for Bids Open - National 120,000.00 76,393.65 Implementati 2020-03-02 2020-04-28 2020-03-07 2020-04-28 2020-04-18 2020-05-27 2020-05-18 2020-08-14 2020-06-22 2020-12-19 Envelope license and Angola Database on 55G2/INRH/20 / Under Procurement of Hydrometric Single Stage - One COFN / C1560 Water Resource Management Post Request for Bids Open - National 750,000.00 584,755.61 Implementati 2020-03-02 2020-04-15 2020-03-09 2020-04-15 2020-04-20 2020-06-02 2020-05-20 2020-08-13 2020-06-24 2020-12-21 Equipment and Remote Envelope on Connection to the Database 7G1/NDALATANDO/20 / Water Supply Institutional Covid 19 Emergency - COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 5,454.75 4,786.20 Completed 2020-04-09 2020-04-08 2020-04-14 2020-04-07 2020-05-19 2020-04-15 2020-11-15 2020-07-06 Procurement of Motorcycles Development 9G1/NDALATANDO/20 / Water Supply Institutional Covid 19 Emergency - COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 9,273.08 8,263.12 Completed 2020-04-12 2020-06-02 2020-04-17 2020-04-08 2020-05-22 2020-06-11 2020-11-18 2020-09-23 Operation and maintenance Development 10G1/NDALATANDO/20 / Water Supply Institutional Covid 19 Emergency - COFN / C1560 Strengthening and Capacity Post Direct Selection 13,182.32 11,698.34 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-13 2020-05-07 2020-04-15 2020-11-03 2020-04-22 Procurement of pumps, Development reservoirs and accessories 11G1/NDALATANDO/20 / Water Supply Institutional Covid 19 Emergency - COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 7,091.18 6,265.20 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-07 2020-05-22 2020-04-21 2020-11-18 2020-05-21 Procurement of Chemicals Development 12G1/UIGE/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 5,454.75 4,860.66 Signed 2020-04-12 2020-04-21 2020-04-17 2020-04-13 2020-05-22 2020-05-07 2020-11-18 Health and Safety Materials Development 13G1/UIGE/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 2,727.38 2,392.88 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-10 2020-05-22 2020-04-16 2020-11-18 2020-05-25 Health and Safety Materials Development 15G1/UIGE/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 69,376.83 61,599.83 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-10 2020-05-22 2020-04-14 2020-11-18 2020-05-05 Chemicals and laboratory Development reagents 16G1/UIGE/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 16,339.54 10,460.36 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-10 2020-05-22 2020-04-17 2020-11-18 2020-05-27 pumps, reservoirs and Development accessories 17G1/BIE/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 5,454.75 4,786.20 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-10 2020-05-22 2020-04-14 2020-11-18 2020-06-16 motorcycles Development 18G1/BIE/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 2,727.38 2,393.10 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-10 2020-05-22 2020-04-14 2020-11-18 2020-05-25 Health and Safety Materials Development 20G1/BIE/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection 46,342.68 40,662.76 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-10 2020-05-07 2020-04-15 2020-11-03 2020-06-02 Chemicals Development 21G1/BIE/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 54,068.20 47,363.00 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-10 2020-05-22 2020-04-17 2020-11-18 2020-05-21 Pumps Development 22G1/MALANJE/20 / Covid Water Supply Institutional 19 Emergency - Procurement COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 5,454.75 4,778.22 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-13 2020-05-22 2020-04-17 2020-11-18 2020-05-21 of motorcycles Development 23G1/MALANJE/20 / Covid Water Supply Institutional 19 Emergency - Procurement COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 2,727.38 2,515.11 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-13 2020-05-22 2020-04-17 2020-11-18 2020-05-18 of Health and Safety Materials Development 25G1/MALANJE/20 / Covid Water Supply Institutional 19 Emergency - Procurement COFN / C1560 Strengthening and Capacity Post Direct Selection 14,250.54 12,548.89 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-13 2020-05-07 2020-04-20 2020-11-03 2020-06-25 of Chemicals Development 26G1/MALANJE/20 / Covid Water Supply Institutional 19 Emergency - Procurement COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 35,600.66 31,008.69 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-13 2020-05-22 2020-04-17 2020-11-18 2020-09-15 of maintenance materials Development 27G1/HUAMBO/20 / Covid Water Supply Institutional 19 Emergency - Procurement COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 5,454.75 4,804.80 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-30 2020-05-22 2020-05-18 2020-11-18 2020-06-12 of motorcycles Development 32G1/HUILA/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 5,454.75 4,804.80 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-10 2020-05-22 2020-04-15 2020-11-18 2020-05-27 motorcycles Development 28G1/HUAMBO/20 / Covid Water Supply Institutional 19 Emergency - Procurement COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 6,363.88 2,392.39 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-30 2020-05-22 2020-05-14 2020-11-18 2020-06-15 of Health and Safety Materials Development 33G1/HUILA/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 2,727.38 2,400.64 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-10 2020-05-22 2020-05-21 2020-11-18 2020-07-10 Health and Safety Materials Development 30G1/HUAMBO/20 / Covid Water Supply Institutional 19 Emergency - Procurement COFN / C1560 Strengthening and Capacity Post Direct Selection 83,637.74 72,066.19 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-30 2020-05-07 2020-04-14 2020-11-03 2020-05-25 of Chemicals Development Page 3 31G1/HUAMBO/20 / Covid Water Supply Institutional 19 Emergency - Procurement COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 36,115.02 31,811.78 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-30 2020-05-22 2020-05-14 2020-11-18 2020-09-04 of maintenance materials Development 36G1/HUILA/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection 88,821.81 78,372.94 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-10 2020-05-07 2020-04-13 2020-11-03 2020-05-05 pumps and spare parts Development 37G1/HUILA/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection 71,877.65 63,210.84 Completed 2020-04-12 2020-04-08 2020-04-17 2020-04-10 2020-05-07 2020-04-13 2020-11-03 2020-10-26 electrical repair materials Development 56G2/INRH/20 / Pending Procurement of Angola COFN / C1560 Water Resource Management Post Direct Selection Direct 50,000.00 0.00 Implementati 2020-05-04 2020-05-09 2020-06-13 2020-12-10 Database on 57G1/UIGE/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 12,600.00 9,278.99 Signed 2020-05-18 2020-05-14 2020-05-23 2020-06-17 2020-06-27 2020-07-13 2020-12-24 Laboratory Reagents Development 58G1/UIGE/20 / Covid-19 Emergency – Procurement of Water Supply Institutional accessories and materials for COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 63,000.00 52,807.57 Completed 2020-05-18 2020-05-14 2020-05-23 2020-04-07 2020-06-27 2020-06-25 2020-12-24 2020-09-02 the repair of water supply Development network 59G1/HUILA/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 44,000.00 36,913.47 Completed 2020-05-19 2020-05-14 2020-05-24 2020-05-29 2020-06-28 2020-06-23 2020-12-25 2020-09-05 Laboratory Reagents Development 60G1/HUILA/20 / Covid 19 Emergency - Procurement of Water Supply Institutional accessories and materials for COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 80,700.00 67,595.81 Completed 2020-05-20 2020-05-14 2020-05-25 2020-05-29 2020-06-29 2020-07-29 2020-12-26 2020-09-30 the repair of water supply Development network 62G1/NAMIBE/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 87,600.00 73,414.98 Completed 2020-05-19 2020-05-14 2020-05-24 2020-04-18 2020-06-28 2020-06-12 2020-12-25 2020-08-19 Chemicals for water treatment Development 63G1/NAMIBE/20 / Covid 19 Emergency - Procurement of Water Supply Institutional accessories and materials for COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 90,790.00 76,091.19 Completed 2020-05-19 2020-05-14 2020-05-24 2020-04-23 2020-06-28 2020-07-29 2020-12-25 2020-10-16 the repair of water supply Development network 64G1/NAMIBE/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 82,750.00 69,336.37 Completed 2020-05-19 2020-05-14 2020-05-24 2020-04-18 2020-06-28 2020-06-12 2020-12-25 2020-10-16 Laboratory reagents Development 65G1/MOXICO/20 / Covid- Water Supply Institutional 19 Emergency – Procurement COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 2,800.00 2,174.75 Completed 2020-05-20 2020-05-14 2020-05-25 2020-04-22 2020-06-29 2020-06-12 2020-12-26 2020-08-21 of Health and Safety Development equipment 68G1/MOXICO/20 / Covid 19 Emergency - Procurement of Water Supply Institutional accessories and materials for COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 21,850.00 18,156.05 Completed 2020-05-21 2020-05-14 2020-05-26 2020-05-11 2020-06-30 2020-06-25 2020-12-27 2020-09-07 the repair of water supply Development network 69G1/MOXICO/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 24,000.00 19,947.88 Completed 2020-05-21 2020-05-14 2020-05-26 2020-04-22 2020-06-30 2020-06-12 2020-12-27 2020-09-03 an electric generator Development 70G1/MOXICO/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 5,600.00 4,688.73 Completed 2020-05-21 2020-05-14 2020-05-26 2020-05-01 2020-06-30 2020-06-12 2020-12-27 2020-08-28 accessories for the existing Development generator 66G1/MOXICO/20 / Covid- Water Supply Institutional 19 Emergency – Procurement COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 2,800.00 0.00 Canceled 2020-05-20 2020-05-25 2020-06-29 2020-12-26 of Motorcycles Development 67G1/MOXICO/20 / Covid 19 Water Supply Institutional Emergency - Procurement of COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 87,300.00 0.00 Canceled 2020-05-21 2020-05-26 2020-06-30 2020-12-27 chemicals for water treatment Development 8G1/NDALATANDO/20 / Water Supply Institutional Covid 19 Emergency - COFN / C1560 Strengthening and Capacity Post Direct Selection Direct 2,727.38 0.00 Canceled 2020-04-12 2020-04-17 2020-05-22 2020-11-18 Procurement of Health and Development Safety Materials 71G1/COVID EMERGENCY Water Supply Institutional Under /21 / Covid 19 Emergency - Single Stage - One IBRD / 87020 Strengthening and Capacity Post Request for Bids Open - National 625,000.00 0.00 Implementati 2021-03-29 2021-04-15 2021-04-03 2021-04-15 2021-05-15 2021-05-25 2021-06-14 2021-07-19 2022-01-15 Procurement of Chemicals and Envelope Development on reagents 73G1/COVID EMERGENCY/20 / Covid 19 Emergency - Water Supply Institutional Under Single Stage - One Procurement of Office IBRD / 87020 Strengthening and Capacity Post Request for Bids Open - National 360,000.00 0.00 Implementati 2021-03-29 2021-04-22 2021-04-03 2021-04-22 2021-05-15 2021-06-14 2021-07-19 2022-01-15 Envelope supplies and communication Development on equipment 74G1/COVID EMERGENCY/20 Water Supply Institutional Under / Covid 19 Emergency - Single Stage - One IBRD / 87020 Strengthening and Capacity Post Request for Bids Open - National 620,000.00 0.00 Implementati 2021-03-29 2021-04-22 2021-04-03 2021-04-22 2021-05-15 2021-06-14 2021-07-19 2022-01-15 Procurement of Meters, Envelope Development on pumps and network repair materials 75G1/COVID EMERGENCY Water Supply Institutional Pending Request for Single Stage - One /20 / Covid 19 Emergency - IBRD / 87020 Strengthening and Capacity Post Limited 115,000.00 0.00 Implementati 2021-04-03 2021-05-29 2021-11-25 Quotations Envelope Procurement of Motorcycles Development on 72G1/COVID EMERGENCY/20 / Covid 19 Emergency - Procurement of Health and Water Supply Institutional Pending Request for Single Stage - One Protection against Covid IBRD / 87020 Strengthening and Capacity Post Limited 140,000.00 0.00 Implementati 2021-04-03 2021-05-29 2021-11-25 Quotations Envelope (Rubber gloves, Hand Development on sanitizers, face masks, disinfectants etc.) Page 4 78G1/IRSEA/21 / Pending Request for Single Stage - One Procurement of Computers IBRD / 87020 Water Resource Management Post Limited 90,000.00 0.00 Implementati 2021-05-22 2021-07-17 2022-01-13 Quotations Envelope and IT equipment to IRSEA on Pending 67G2/INRH/21 / Purchase of Request for Single Stage - One IBRD / 87020 Water Resource Management Post Limited 20,000.00 0.00 Implementati 2021-05-22 2021-07-17 2022-01-13 Boat and accessories for INRH Quotations Envelope on 91G4/UCP/21 / Procurement Pending Management and Engineering Request for Single Stage - One of 2 Support Vehicles to FCMU- IBRD / 87020 Post Limited 70,000.00 0.00 Implementati 2021-05-22 2021-07-17 2022-01-13 Support Quotations Envelope WB / AFD on 92G4/UCP/21 / Procurement Pending Management and Engineering Request for Single Stage - One of IT Equipment for the IBRD / 87020 Post Limited 50,000.00 0.00 Implementati 2021-05-22 2021-07-17 2022-01-13 Support Quotations Envelope Project on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 56NC1/UIGE/DNA/18 / Water Supply Institutional Single Stage - Two Management Support IBRD / 87020 Strengthening and Capacity Prior Request for Bids Open - International 4,500,000.00 5,681,279.92 Signed 2018-06-01 2018-11-21 2018-08-17 2019-03-29 2018-08-17 2019-05-29 2018-06-06 2018-11-23 2018-10-26 2019-08-20 2019-01-08 2019-12-12 2019-02-12 2020-02-26 2022-02-11 Envelope Services Contract for Uige Development 11CS1/DAS/18 / Operation Water Supply Institutional and Management of Kuito and IBRD / 87020 Strengthening and Capacity Prior Direct Selection Direct 1,135,505.42 1,209,504.20 Signed 2018-06-06 2018-06-12 2018-06-11 2018-07-01 2018-06-29 2018-12-28 Kunje Water Supply System Development 93CS1/DAS/18 / Operation Water Supply Institutional and Management of Huambo IBRD / 87020 Strengthening and Capacity Prior Direct Selection Direct 1,091,728.00 1,470,480.00 Signed 2018-06-06 2018-06-12 2018-06-11 2018-07-01 2018-06-29 2018-12-28 Water Supply System Development 20CS1/DAS/18 / Operation Water Supply Institutional and Management of Malanje IBRD / 87020 Strengthening and Capacity Prior Direct Selection Direct 835,532.08 1,019,169.96 Signed 2018-06-06 2018-06-12 2018-06-11 2018-07-01 2018-06-18 2018-12-28 Water Supply System Development 94CS1/DAS/18 / Operation Water Supply Institutional and Management of Uige IBRD / 87020 Strengthening and Capacity Prior Direct Selection Direct 934,905.00 1,202,407.00 Signed 2018-06-06 2018-06-13 2018-06-11 2018-07-01 2018-06-29 2018-12-28 Water Supply System Development 59CS1/DAS/15 / Operation Water Supply Institutional and Management of Lubango IBRD / 87020 Strengthening and Capacity Prior Direct Selection Direct 2,235,904.99 2,200,875.50 Signed 2018-06-06 2018-06-12 2018-06-11 2018-07-01 2018-06-29 2018-12-28 Water Supply System Development 95CS1/DAS/18 / Operation Water Supply Institutional and Management of IBRD / 87020 Strengthening and Capacity Post Direct Selection Direct 782,000.00 1,180,071.55 Signed 2018-08-20 2018-04-03 2018-08-25 2018-07-23 2018-09-14 2018-08-21 2019-03-13 N´dalatando Water Supply Development System 58NC1/NDALATANDO/DNA/1 Water Supply Institutional 8 / Management Support Single Stage - Two COFN / C1560 Strengthening and Capacity Prior Request for Bids Open - International 6,000,000.00 7,668,596.21 Signed 2019-05-02 2019-07-15 2019-05-07 2019-07-16 2019-06-18 2019-09-25 2019-08-31 2020-03-02 2019-10-05 2020-07-24 2024-09-08 Services Contract for Envelope Development Ndalatando 1NC1/LUENA/DNA/16 / Water Supply Institutional Single Stage - Two Management Contract for COFN / C1560 Strengthening and Capacity Post Request for Bids Open - International 800,000.00 938,762.16 Signed 2019-07-24 2019-06-12 2019-07-29 2019-06-12 2019-09-30 2019-08-12 2019-12-13 2019-09-04 2020-01-17 2019-12-09 2023-02-14 Envelope Luena Development 54NC1/CUITO/DNA/18 / Water Supply Institutional Single Stage - Two Management Support COFN / C1560 Strengthening and Capacity Prior Request for Bids Open - International 6,000,000.00 9,117,817.16 Signed 2019-05-06 2019-08-09 2019-05-11 2019-08-22 2019-06-22 2019-10-02 2019-09-04 2019-12-23 2019-10-09 2020-07-02 2024-09-12 Envelope Services Contract for Cuito Development 55NC1/HUAMBO/DNA/18 / Water Supply Institutional Single Stage - Two Management Support COFN / C1560 Strengthening and Capacity Prior Request for Bids Open - International 6,000,000.00 5,936,554.53 Signed 2019-05-13 2019-07-12 2019-05-18 2019-07-17 2019-06-29 2019-09-18 2019-09-11 2019-12-12 2019-10-16 2020-02-20 2024-09-19 Envelope Services Contract for Huambo Development 57NC1/MALANJE/DNA/18 / Water Supply Institutional Single Stage - Two Management Support COFN / C1560 Strengthening and Capacity Prior Request for Bids Open - International 6,000,000.00 6,718,801.92 Signed 2019-05-17 2019-06-18 2019-05-22 2019-06-19 2019-07-03 2019-09-11 2019-09-15 2019-12-12 2019-10-20 2020-05-28 2020-04-17 Envelope Services Contract for Malanje Development 73NC1/LUBANGO/18 / Water Supply Institutional Single Stage - Two Management Support COFN / C1560 Strengthening and Capacity Prior Request for Bids Open - International 6,000,000.00 0.00 Canceled 2019-06-03 2019-06-08 2019-07-20 2019-10-02 2019-11-06 2024-10-10 Envelope Services Contract for Lubango Development 78NC1/HUILA/19 / Water Supply Institutional Single Stage - Two Management Support COFN / C1560 Strengthening and Capacity Prior Request for Bids Open - International 6,000,000.00 6,599,905.88 Signed 2019-08-05 2019-08-16 2019-08-10 2019-08-22 2019-09-21 2019-10-16 2019-12-04 2020-03-09 2020-01-08 2020-07-30 2024-12-12 Envelope Services Contract for Huíla Development Province Management and Engineering Request for Single Stage - One 103CS1/UCP/20 / Translator COFN / C1560 Post Limited 200,000.00 15,409.23 Signed 2020-05-29 2020-05-12 2020-07-24 2020-06-12 2021-07-04 Support Quotations Envelope 105CS3/NDALATANDO/20 / Rehabilitation and Expansion Demining of the sites for the COFN / C1560 of Water Supply Production Post Direct Selection Direct 106,000.00 89.54 Signed 2020-07-26 2020-07-30 2020-07-31 2020-07-15 2020-09-04 2020-09-03 2021-03-03 new bulk water supply system and Distribution in Ndalatando 56ANC1/UIGE/20 / Water Supply Institutional Management Support Services IBRD / 87020 Strengthening and Capacity Post Direct Selection Direct 204,000.00 347,128.21 Signed 2020-10-30 2020-11-18 2020-11-04 2020-11-19 2020-12-09 2021-02-03 2021-06-07 for Uige Water and Sanitation Development Utility CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1CS3/DNA/16 / Design checking and works Rehabilitation and Expansion Quality And Cost- Supervision of Network and IBRD / 87020 of Water Supply Production Prior Open - International 3,000,000.00 1,948,055.93 Signed 2016-08-16 2016-08-19 2016-09-06 2016-10-20 2016-09-06 2016-11-17 2016-10-20 2016-12-17 2017-01-18 2017-01-21 2017-04-11 2017-02-25 2017-04-17 2020-09-25 Based Selection Home Connections for and Distribution Peirurban areas of Malanje Page 5 2CS3/DNA/16 / Design Rehabilitation and Expansion checking and works Quality And Cost- IBRD / 87020 of Water Supply Production Prior Open - International 3,200,000.00 2,594,875.88 Signed 2016-08-16 2016-08-15 2016-10-03 2016-08-22 2016-11-10 2016-11-08 2017-01-24 2016-12-19 2017-02-23 2017-04-17 2017-03-30 2017-08-02 2017-05-04 2017-08-07 2021-06-04 Supervision of Network and Based Selection and Distribution Home Connections for Dundo 3CS3/DNA/16 / Design checking and works Rehabilitation and Expansion Quality And Cost- Supervision of Network and IBRD / 87020 of Water Supply Production Prior Open - International 3,000,000.00 2,192,328.79 Signed 2016-08-17 2016-08-15 2016-10-04 2016-08-23 2016-11-10 2016-11-08 2017-01-30 2016-12-16 2017-03-01 2017-01-18 2017-04-05 2017-04-18 2017-05-10 2017-04-24 2020-12-10 Based Selection Home Connections for and Distribution Huambo (1st phase) 4CS3/DNA/16 / Design Rehabilitation and Expansion checking and works Quality And Cost- IBRD / 87020 of Water Supply Production Prior Open - International 3,000,000.00 1,815,313.53 Signed 2016-08-18 2016-08-13 2016-10-05 2016-08-22 2016-11-18 2016-11-08 2017-02-02 2016-12-15 2017-03-04 2017-02-08 2017-04-08 2017-05-30 2017-05-13 2017-06-05 2020-12-14 Supervision of Network and Based Selection and Distribution Home Connections for Luena 5CS3/DNA/16 / Design Rehabilitation and Expansion checking and works Quality And Cost- IBRD / 87020 of Water Supply Production Prior Open - International 2,700,000.00 2,304,334.51 Signed 2016-08-19 2016-08-19 2016-10-06 2016-08-23 2016-11-19 2016-11-08 2017-02-08 2016-12-20 2017-03-10 2017-04-11 2017-04-14 2017-07-28 2017-05-19 2017-08-01 2020-12-21 Supervision of Network and Based Selection and Distribution Home Connections for Uige 6CS3/DNA/16 / Design checking and works Rehabilitation and Expansion Quality And Cost- Supervision of Network and IBRD / 87020 of Water Supply Production Prior Open - International 2,900,000.00 2,060,259.00 Signed 2016-08-20 2016-08-19 2016-10-07 2016-08-23 2016-11-20 2016-11-09 2017-02-14 2016-12-22 2017-03-16 2017-07-26 2017-04-20 2018-05-04 2017-05-25 2018-05-21 2020-12-25 Based Selection Home Connections for and Distribution Namibe 7CS3/DNA/16 / Design checking and works Rehabilitation and Expansion Quality And Cost- Supervision of Network and IBRD / 87020 of Water Supply Production Prior Open - International 2,400,000.00 994,220.00 Signed 2016-08-21 2016-08-19 2016-10-08 2016-08-23 2016-11-21 2016-11-08 2017-02-20 2016-12-21 2017-03-22 2017-08-16 2017-04-26 2017-11-07 2017-05-31 2017-11-13 2020-12-28 Based Selection Home Connections for Kuito and Distribution (1st phase) 8CS3/NDALATANDO/DNA/16 / Design checking and works Rehabilitation and Expansion supervision for the Quality And Cost- COFN / C1560 of Water Supply Production Prior Open - International 3,300,000.00 2,795,189.68 Signed 2017-02-01 2018-11-08 2017-02-22 2018-11-13 2017-04-07 2019-06-11 2017-06-05 2019-09-03 2017-07-05 2019-10-23 2017-08-09 2020-01-06 2017-09-13 2020-02-12 2020-09-14 construction of a new water Based Selection and Distribution source and pipeline in Ndalatando 10CS3/LUBANGO/DNA/16 / Rehabilitation and Expansion Design checking and works Quality And Cost- IBRD / 87020 of Water Supply Production Prior Open - International 1,500,000.00 736,287.70 Signed 2017-03-03 2018-05-04 2017-05-18 2018-05-14 2017-07-01 2018-12-12 2017-08-28 2019-02-19 2017-09-27 2019-04-12 2017-11-01 2019-06-10 2017-12-06 2019-06-27 2020-12-07 Supervision of Construction of Based Selection and Distribution reservoirs in Lubango 12CS2/INRH/DNA/16 / TA to develop Integrated Basin Quality And Cost- / Water Resource Management Prior Open - International 2,200,000.00 0.00 Canceled 2017-09-01 2016-10-13 2017-11-03 2016-10-19 2017-12-17 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2019-06-13 Management Plan for River Based Selection Basins in Benguela 13CS2/INRH/DNA/16 / TA to develop Integrated Basin Quality And Cost- / Water Resource Management Prior Open - International 2,200,000.00 0.00 Canceled 2017-02-03 2016-09-06 2017-04-24 2016-10-19 2017-06-07 2017-08-06 2017-09-05 2017-10-10 2017-11-14 2018-11-14 Management Plan for Keve e Based Selection Longa Basins 14CS4/NAMIBE/DNA/16 / Management and Engineering Quality And Cost- Salt water intrusion study at / Post Open - International 500,000.00 0.00 Canceled 2017-06-01 2017-08-01 2017-09-14 2017-11-12 2017-12-12 2018-01-16 2018-09-20 2019-09-20 Support Based Selection Namibe 15CS1/IRSEA/DNA/16 / TA Water Supply Institutional Quality And Cost- Water and Electricity Regulator IBRD / 87020 Strengthening and Capacity Prior Open - International 6,300,000.00 5,051,935.58 Signed 2017-02-08 2018-05-07 2017-04-27 2018-06-15 2017-06-10 2018-12-07 2017-08-09 2019-02-20 2017-09-08 2019-04-02 2017-10-13 2019-05-10 2017-11-17 2019-05-28 2020-12-17 Based Selection (IRSEA) Development 16CS1/DNA/17 / External Management and Engineering Least Cost IBRD / 87020 Post Open - International 130,000.00 64,705.88 Signed 2017-04-17 2017-04-01 2017-05-08 2017-05-10 2017-03-20 2017-06-07 2017-05-22 2017-07-07 2017-10-17 2017-08-11 2017-11-10 2017-09-15 2017-11-29 2021-09-14 Audit Support Selection 35CS4/DNA/17 / Project Management and Engineering Least Cost IBRD / 87020 Post Open - International 250,000.00 171,122.99 Signed 2017-10-18 2017-11-08 2017-11-14 2017-12-22 2017-12-21 2018-01-19 2018-01-31 2018-02-18 2018-03-25 2018-04-09 2018-04-29 2018-06-01 2021-04-13 Internal Audit Support Selection 39CS1/DNA/17 / AUDIT OF FINANCIAL STATEMENTS FOR Water Supply Institutional Least Cost SIX BENEFICIARY WATER IBRD / 87020 Strengthening and Capacity Post Open - International 200,000.00 232,192.51 Signed 2018-01-24 2018-01-25 2018-02-14 2018-01-25 2018-04-06 2018-02-23 2018-05-04 2018-03-27 2018-06-03 2018-04-23 2018-07-08 2018-05-10 2018-08-12 2018-06-08 2021-09-10 Selection SUPPLY AND SANITATION Development UTILITIES 42CS2/TA/INRH/17 / Technical Assistance to INRH Quality And Cost- IBRD / 87020 Water Resource Management Prior Open - International 3,000,000.00 2,028,160.74 Signed 2018-03-30 2018-06-05 2018-04-20 2018-06-13 2018-06-03 2018-11-30 2018-07-01 2019-02-18 2018-07-31 2019-05-30 2018-09-04 2019-08-06 2018-10-09 2019-08-26 2021-10-08 (National Water Resources Based Selection Institute) 49CS3/UIGE/DNA/18 / Rehabilitation and Expansion Environmental and Social Quality And Cost- IBRD / 87020 of Water Supply Production Post Open - National 200,000.00 117,948.37 Signed 2018-07-03 2018-11-20 2018-07-24 2018-12-10 2018-09-06 2019-03-26 2018-10-04 2019-05-23 2018-11-03 2019-05-31 2018-12-08 2019-07-11 2019-01-12 2019-08-26 2020-01-12 Impact Assessment for Uige Based Selection and Distribution Water Supply System 60CS1/DNA/18 / Review of Water Supply Institutional the Legal and Institutional Quality And Cost- IBRD / 87020 Strengthening and Capacity Prior Open - International 663,000.00 568,864.64 Signed 2018-05-16 2018-05-14 2018-06-06 2018-06-14 2018-07-20 2019-01-16 2018-08-17 2019-03-21 2018-09-16 2019-06-18 2018-10-21 2019-08-09 2018-11-25 2019-09-02 2019-08-22 Frameworks of the Angola Based Selection Development Water Sector 65CS1/IRSEA/18 / Water Supply Institutional Quality And Cost- Under Consultancy for beneficiary IBRD / 87020 Strengthening and Capacity Prior Open - International 600,000.00 1,167,745.88 2019-04-25 2020-06-08 2019-05-16 2020-06-13 2019-06-29 2020-10-06 2019-07-27 2020-12-11 2019-08-26 2021-04-26 2019-09-30 2021-07-09 2019-11-04 2020-11-03 Based Selection Implementation assessment Development 67CS2/INRH/18 / Development of National Quality And Cost- IBRD / 87020 Water Resource Management Post Open - National 150,000.00 0.00 Canceled 2019-05-29 2019-06-19 2019-08-02 2019-08-30 2019-09-29 2019-11-03 2019-12-08 2020-06-05 Water Resources Information Based Selection and Use System 9CS3/NDALATANDO/DNA/16 / Design checking and works supervision for the Rehabilitation and Expansion Quality And Cost- refurbishment of the / of Water Supply Production Prior Open - International 2,400,000.00 0.00 Canceled 2017-02-16 2017-03-09 2017-04-22 2017-06-20 2017-07-20 2017-08-24 2017-09-28 2020-09-28 Based Selection treatment plant and and Distribution construction of distribution centers in Ndalatando 72CS4/UCP/18 / Support to Management and Engineering Least Cost the recruitment process of IBRD / 87020 Prior Open - National 50,000.00 503,072.65 Under Review 2018-09-27 2018-11-19 2018-10-18 2018-12-03 2018-12-01 2019-03-26 2018-12-29 2019-05-06 2019-01-28 2019-06-10 2019-03-04 2019-07-07 2019-04-08 2019-08-02 2019-10-05 Support Selection young professionals Page 6 64CS1/IRSEA/18 / Water Supply Institutional Quality And Cost- Consultancy for the baseline IBRD / 87020 Strengthening and Capacity Post Open - National 200,000.00 0.00 Canceled 2019-05-30 2019-06-20 2019-08-03 2019-08-31 2019-09-30 2019-11-04 2019-12-09 2020-06-06 Based Selection for the sector Development 50CS3/LUBANGO/DNA/18 / Design checking and works Rehabilitation and Expansion Quality And Cost- Under Supervision of Network and COFN / C1560 of Water Supply Production Post Open - International 900,000.00 0.00 2020-01-03 2020-09-01 2020-02-02 2020-09-28 2020-03-02 2021-06-22 2020-03-30 2021-08-10 2020-04-29 2020-06-03 2020-07-08 2021-12-30 Based Selection Implementation Home Connections for and Distribution Lubango (1st phase) 52CS3/KUITO/DNA/18 / Design checking and works Rehabilitation and Expansion Quality And Cost- Under Supervision of Network and COFN / C1560 of Water Supply Production Post Open - International 800,000.00 0.00 2020-02-05 2021-06-22 2020-02-26 2021-06-29 2020-04-10 2020-05-08 2020-06-07 2020-07-12 2020-08-16 2021-08-16 Based Selection Implementation Home Connections for Kuito and Distribution (2nd phase) 51CS3/MALANJE/DNA/18 / Design Checking and Rehabilitation and Expansion Quality And Cost- Supervision of Repairs to IBRD / 87020 of Water Supply Production Prior Open - International 1,000,000.00 0.00 Canceled 2018-07-27 2018-08-17 2018-09-30 2018-10-28 2018-11-27 2019-01-01 2019-02-05 2020-02-05 Based Selection Household Connections at and Distribution Malanje 69CS2/INRH/18 / Survey of water users and assessment Quality And Cost- COFN / C1560 Water Resource Management Prior Open - International 1,500,000.00 0.00 Canceled 2020-03-20 2020-04-10 2020-05-24 2020-06-21 2020-07-21 2020-08-25 2020-09-29 2021-09-29 of volume of water demand in Based Selection Cuanza river basin 68CS2/INRH/18 / Quality And Cost- Development and Application COFN / C1560 Water Resource Management Prior Open - International 1,500,000.00 0.00 Canceled 2020-04-23 2020-05-14 2020-06-27 2020-07-25 2020-08-24 2020-09-28 2020-11-02 2021-11-02 Based Selection of Water Rights 75CS3/UIGE/19 / Design checking and works Rehabilitation and Expansion Quality And Cost- Under supervision for the COFN / C1560 of Water Supply Production Prior Open - International 2,400,000.00 0.00 2019-06-26 2019-10-08 2019-07-17 2019-10-09 2019-08-30 2021-03-10 2019-10-28 2020-05-19 2019-11-27 2021-04-15 2020-01-01 2020-02-05 2024-01-15 Based Selection Implementation construction of a new bulk and Distribution water supply system at Uige 59CS3/LUBANGO/DNA/18 / Hydrogeological survey and Management and Engineering Quality And Cost- prospection of new COFN / C1560 Prior Open - International 4,800,000.00 890,368.15 Signed 2018-05-24 2019-08-05 2018-06-14 2019-08-07 2018-07-28 2019-10-03 2018-08-25 2020-01-06 2018-09-24 2020-02-24 2018-10-29 2020-04-07 2018-12-03 2020-04-30 2019-12-03 Support Based Selection production boreholes in Lubango 76CS3/LUBANGO/18 / Consultancy Services for Rehabilitation and Expansion Consultant Environmental and Social COFN / C1560 of Water Supply Production Post Qualification Open - International 200,000.00 180,599.43 Signed 2019-04-22 2019-04-18 2019-05-13 2019-05-03 2019-06-11 2019-06-24 2019-06-25 2019-08-28 2019-07-30 2019-11-04 2020-01-26 Impact Assessment for Water and Distribution Selection Supply Reservoirs at Lubango 79CS1/UCP/19 / Water Supply Institutional Quality And Cost- Independent Verification COFN / C1560 Strengthening and Capacity Prior Open - International 2,000,000.00 2,509,764.71 Signed 2019-08-25 2019-10-17 2019-09-15 2019-10-21 2019-10-29 2020-04-23 2019-11-26 2020-06-16 2019-12-26 2020-07-23 2020-01-30 2020-11-19 2020-03-05 2021-01-25 2025-02-07 Based Selection Agent for the Management Development Contracts 84CS4/EPAL/19 / Management and Engineering Quality And Cost- Under Independent Technical Audit COFN / C1560 Prior Open - International 1,800,000.00 1,687,552.94 2019-08-11 2019-08-16 2019-09-01 2020-04-13 2019-10-15 2020-08-26 2019-11-12 2020-10-26 2019-12-12 2021-02-21 2020-01-16 2021-03-30 2020-02-20 2023-02-19 Support Based Selection Implementation of BITA Project 85CS4/EPAL/19 / Management and Engineering Quality And Cost- Under Independent Safeguards COFN / C1560 Post Open - International 700,000.00 647,757.59 2019-08-11 2019-08-08 2019-09-01 2020-04-10 2019-10-15 2020-07-23 2019-11-12 2020-09-15 2019-12-12 2021-02-03 2020-01-16 2021-03-31 2020-02-20 2023-02-19 Support Based Selection Implementation Auditor of BITA Project 73CS2/INRH/19 / Economic Quality And Cost- and Financial Regime of the COFN / C1560 Water Resource Management Post Open - International 500,000.00 0.00 Canceled 2019-11-29 2019-12-20 2020-02-02 2020-03-01 2020-03-31 2020-05-05 2020-06-09 2020-12-09 Based Selection Use of Water Resources 89CS1/UCP/19 / Technical Water Supply Institutional Quality And Cost- Under Assistance to National Water COFN / C1560 Strengthening and Capacity Prior Open - International 4,000,000.00 0.00 2020-06-30 2020-07-21 2020-09-03 2020-10-01 2020-10-31 2020-12-05 2021-01-09 2021-01-19 Based Selection Implementation Directorate (DNA) Development 90CS1/IRSEA/19 / Analysis of alternatives to subsidise Water Supply Institutional Quality And Cost- Under low income population and COFN / C1560 Strengthening and Capacity Post Open - International 300,000.00 0.00 2020-02-20 2019-11-26 2020-03-12 2020-01-21 2020-04-25 2020-04-22 2020-05-23 2020-06-18 2020-06-22 2020-08-17 2020-07-27 2020-08-31 2021-02-27 Based Selection Implementation identification of potential Development beneficiaries 86CS5/UCP/19 / Sanitation Piloting Small-Scale Master Plans for Cuito, Quality And Cost- Under COFN / C1560 Sanitation Service Delivery in Prior Open - International 1,600,000.00 0.00 2019-10-30 2020-03-25 2019-11-20 2020-04-16 2020-01-03 2020-07-23 2020-01-31 2020-09-30 2020-03-01 2020-11-27 2020-04-05 2021-04-16 2020-05-10 2021-11-01 Dundo, Huambo, Luena Based Selection Implementation Peri-Urban Areas Moçamedes and N´dalatando 80CS1/UCP/19 / PPP Water Supply Institutional Quality And Cost- Under Transaction Advisor for COFN / C1560 Strengthening and Capacity Prior Open - International 1,400,000.00 0.00 2019-12-02 2020-07-15 2019-12-23 2020-07-22 2020-02-20 2020-10-12 2020-03-19 2021-01-18 2020-04-18 2021-04-22 2020-05-23 2021-06-18 2020-06-27 2021-06-27 Based Selection Implementation Cabinda Development 97CS2/INRH/20 / Development of Water Quality And Cost- Under Resources Management Tools COFN / C1560 Water Resource Management Prior Open - International 3,000,000.00 0.00 2020-03-02 2020-04-21 2020-03-23 2020-04-22 2020-05-06 2020-11-17 2020-06-03 2021-02-26 2020-07-03 2020-08-07 2020-09-11 2021-09-11 Based Selection Implementation and Information Management System 98CS2/INRH/20 / Consultant Quality And Cost- Under for Elaboration of the National COFN / C1560 Water Resource Management Prior Open - International 2,500,000.00 0.00 2020-03-02 2020-04-27 2020-03-23 2020-04-29 2020-05-06 2020-11-17 2020-06-03 2021-03-03 2020-07-03 2020-08-07 2020-09-11 2021-09-11 Based Selection Implementation Water Resources Cadaster 99CS2/INRH/20 / Consultant for Implementation of the Quality And Cost- Pending Economic and Financial COFN / C1560 Water Resource Management Prior Open - National 2,000,000.00 0.00 2020-03-02 2020-03-23 2020-05-06 2020-06-03 2020-07-03 2020-08-07 2020-09-11 2021-09-11 Based Selection Implementation Framework for the General Use of Water Resources 100CS3/NDLATANDO/DNA/2 0 / Design Checking and Works Supervision of the Rehabilitation and Expansion Quality And Cost- Under Expansion and Rehabilitation COFN / C1560 of Water Supply Production Prior Open - International 1,330,000.00 0.00 2020-05-10 2020-04-29 2020-05-31 2020-05-04 2020-07-14 2020-07-29 2020-08-11 2020-10-29 2020-09-10 2021-01-07 2020-10-15 2021-05-28 2020-11-19 2021-11-19 Based Selection Implementation of the Existing Mucari Bulk and Distribution Water Supply System of the city of Ndalatando Page 7 101CS3/NDLATANDO/DNA/2 0 / Design Checking and Rehabilitation and Expansion Quality And Cost- Under Works Supervision of the COFN / C1560 of Water Supply Production Prior Open - International 2,000,000.00 0.00 2020-05-11 2020-05-06 2020-06-01 2020-05-07 2020-07-15 2020-07-29 2020-08-12 2020-10-14 2020-09-11 2021-01-05 2020-10-16 2021-06-25 2020-11-20 2021-11-20 Based Selection Implementation Network and home and Distribution connections in Ndalatando 102CS3/UIGE/DNA/20 / Design Checking and Works Rehabilitation and Expansion Quality And Cost- Under Supervision of the Network COFN / C1560 of Water Supply Production Prior Open - International 2,000,000.00 0.00 2020-05-18 2020-05-07 2020-06-08 2020-05-14 2020-07-22 2021-04-02 2020-08-19 2020-10-16 2020-09-18 2021-04-22 2020-10-23 2021-05-18 2020-11-27 2021-11-27 Based Selection Implementation and home connections in Uige and Distribution - Lot 2 104CS3/INRH/20 / Development of Detailed Quality And Cost- Under Inventory of Reservoirs and COFN / C1560 Water Resource Management Prior Open - International 2,500,000.00 0.00 2020-08-10 2020-08-03 2020-08-31 2020-08-07 2020-10-14 2021-04-19 2020-11-11 2021-07-13 2020-12-11 2021-01-15 2021-02-19 2022-02-19 Based Selection Implementation Detailed Dam Safety Assessment of Selected Dams 14ACS4/NAMIBE/19 / Groundwater Potential and Salinity Management in Management and Engineering Quality And Cost- COFN / C1560 Prior Open - International 2,000,000.00 0.00 Under Review 2020-09-28 2020-10-22 2020-11-28 2021-03-16 2021-01-11 2021-03-11 2021-04-10 2021-05-15 2022-01-17 2023-07-19 Moçamedes Well Fields and Support Based Selection associated Namibe Coastal Cities 39ACS1/DNA/20 / External Audit of the Financial Management and Engineering Least Cost Under Statements of Seven (7) IBRD / 87020 Post Open - International 240,000.00 0.00 2020-10-30 2020-11-17 2020-11-20 2020-11-18 2021-01-03 2021-06-18 2021-01-31 2021-08-02 2021-03-02 2021-04-06 2021-05-11 2024-05-10 Support Selection Implementation Beneficiary Water Supply and Sanitation Utilities 16ACS1/DNA/20 / External Management and Engineering Least Cost Under Audit of the Financial IBRD / 87020 Post Open - International 100,000.00 0.00 2020-10-30 2020-11-18 2020-11-20 2020-11-26 2021-01-03 2021-01-31 2021-03-02 2021-04-06 2021-05-11 2024-05-10 Support Selection Implementation Statements of the Project 96CS3/UIGE/20 / Consultancy Services for Rehabilitation and Expansion Consultant Environmental and Social COFN / C1560 of Water Supply Production Post Qualification Open - International 200,000.00 0.00 Canceled 2020-02-28 2020-03-20 2020-04-18 2020-05-02 2020-06-06 2020-12-03 Impact Assessment for and Distribution Selection Ndalatando Bulk Water Supply 106CS3/DNA/20 / Rehabilitation and Expansion Consultant Infrastructure Surveys Water COFN / C1560 of Water Supply Production Post Qualification Open - National 295,000.00 0.00 Canceled 2020-09-06 2020-09-27 2020-11-10 2020-12-10 2021-01-14 2021-07-13 Supply Systems in 6 Provinces and Distribution Selection 87CS4/UCP/21 / Management and Engineering Least Cost IBRD / 87020 Post Open - International 100,000.00 0.00 Canceled 2021-05-31 2021-04-27 2021-06-21 2021-08-04 2021-09-01 2021-10-01 2021-11-05 2021-12-10 2022-06-08 Procurement Auditor Support Selection 107CS4/UCP/21 / Management and Engineering Least Cost Under IBRD / 87020 Prior Open - International 100,000.00 0.00 2021-08-22 2021-06-11 2021-09-12 2021-06-30 2021-10-26 2021-11-23 2021-12-23 2022-01-27 2022-03-03 2022-08-30 Procurement Auditor Support Selection Implementation 108CS3/NDALATANDO/21 / Consultancy services for the Environmental and Social Water Supply Institutional Quality And Cost- Under Impact Assessment (ESIA) of IBRD / 87020 Strengthening and Capacity Post Open - International 800,000.00 0.00 2021-06-28 2021-06-02 2021-07-19 2021-06-08 2021-09-01 2021-09-29 2021-10-29 2021-12-03 2022-01-07 2023-01-07 Based Selection Implementation the existing Mucari water Development supply system in the city of Ndalatando 109CS3/N DALATANDO/21 / Consultant services for Design checking and Work Supervision of distribution Rehabilitation and Expansion Quality And Cost- Pending network and household IBRD / 87020 of Water Supply Production Post Open - International 800,000.00 0.00 2021-08-22 2021-09-12 2021-10-26 2021-11-23 2021-12-23 2022-01-27 2022-03-03 2023-03-03 Based Selection Implementation connections in city of Lucala and Distribution and rural communities between Lucala and N’Dalatando 66CS1/IRSEA/18 / Consultancy for the design Water Supply Institutional Quality And Cost- and implementation of an IBRD / 87020 Strengthening and Capacity Post Open - National 150,000.00 0.00 Canceled 2019-04-17 2018-12-10 2019-05-08 2019-06-21 2019-07-19 2019-08-18 2019-09-22 2019-10-27 2020-04-24 Based Selection information management Development system INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual 11CS4/DNA/16 / Management and Engineering / Prior Consultant Direct 400,000.00 0.00 Canceled 2017-02-23 2018-02-28 2017-03-05 2018-03-01 2017-03-26 2017-04-30 2018-04-30 Hydrogeology specialist Support Selection Water Supply Institutional Individual 17CS4/DNA/17 / Senior IBRD / 87020 Strengthening and Capacity Prior Consultant Open 700,000.00 1,563,268.45 Signed 2017-04-17 2017-05-09 2017-06-03 2017-06-28 2017-06-17 2017-07-25 2017-06-27 2017-07-26 2017-12-24 FCMU Coordinator Development Selection 18CS4/DNA/17 / Senior Water Supply Institutional Individual Financial Management IBRD / 87020 Strengthening and Capacity Prior Consultant Open 700,000.00 809,328.48 Signed 2017-04-24 2017-05-10 2017-06-10 2017-06-28 2017-06-24 2017-07-26 2017-07-04 2017-06-28 2020-07-03 Specialist Development Selection Water Supply Institutional Individual 19CS4/DNA/17 / Financial IBRD / 87020 Strengthening and Capacity Prior Consultant Open 700,000.00 515,059.06 Signed 2017-04-24 2017-05-09 2017-06-10 2017-06-24 2017-09-26 2017-07-04 2017-09-27 2020-07-03 Management Specialist-DNA Development Selection Water Supply Institutional Individual 20CS4/DNA/17 / Senior IBRD / 87020 Strengthening and Capacity Prior Consultant Open 700,000.00 803,171.16 Signed 2017-04-28 2017-05-09 2017-06-14 2017-07-10 2017-06-28 2017-08-10 2017-07-08 2017-08-10 2020-07-07 Procurement Specialist Development Selection Water Supply Institutional Individual 21CS4/DNA/17 / Senior IBRD / 87020 Strengthening and Capacity Prior Consultant Open 500,000.00 645,406.98 Terminated 2017-04-28 2017-05-09 2017-06-14 2017-09-20 2017-06-28 2017-10-30 2017-07-08 2017-11-03 2019-07-08 Procurement Specialist Development Selection Water Supply Institutional Individual 22CS4/DNA/17 / Senior IBRD / 87020 Strengthening and Capacity Prior Consultant Open 700,000.00 405,940.19 Signed 2017-04-28 2017-05-09 2017-06-14 2017-07-12 2017-06-28 2017-08-10 2017-07-08 2017-08-10 2020-07-07 Procurement Specialist-DNA Development Selection Page 8 Water Supply Institutional Individual 23CS4/DNA/17 / Water IBRD / 87020 Strengthening and Capacity Prior Consultant Open 700,000.00 1,291,130.91 Signed 2017-07-21 2017-08-09 2017-09-15 2017-09-27 2017-10-06 2017-10-18 2017-11-10 2017-10-20 2019-05-04 Utility Management Specialist Development Selection Individual 26CS4/DNA/17 / Management and Engineering IBRD / 87020 Prior Consultant Open 250,000.00 435,421.46 Signed 2017-09-15 2017-09-12 2017-11-03 2017-11-24 2018-01-23 2017-12-29 2018-01-26 2020-12-28 Procurement officer (1) Support Selection Individual 27CS4/DNA/17 / Management and Engineering IBRD / 87020 Prior Consultant Open 250,000.00 211,571.46 Signed 2017-09-15 2017-09-12 2017-11-03 2017-11-24 2018-01-25 2017-12-29 2018-01-26 2020-12-28 Procurement Officer (2) Support Selection 28CS4/DNA/17 / Individual Management and Engineering Design/Environmental Expert IBRD / 87020 Prior Consultant Open 385,000.00 592,846.42 Signed 2017-11-01 2017-09-25 2017-12-20 2018-03-07 2018-01-10 2018-05-04 2018-02-14 2018-05-07 2019-08-08 Support to Support DNA/FCMU Selection Individual 24CS4/DNA/17 / Senior Management and Engineering IBRD / 87020 Prior Consultant Open 500,000.00 589,780.01 Signed 2017-09-15 2017-09-11 2017-11-03 2017-11-24 2017-11-07 2017-12-29 2017-11-08 2019-12-29 Design Engineer Support Selection Individual 25CS4/DNA/17 / Senior Management and Engineering IBRD / 87020 Prior Consultant Open 500,000.00 862,744.00 Signed 2017-12-08 2018-05-08 2018-01-26 2018-07-20 2018-02-16 2018-08-06 2018-03-23 2018-08-07 2020-03-22 Environmental Specialist Support Selection 29CS4/DNA/17 / Technical Individual Management and Engineering Assistance to support IBRD / 87020 Prior Consultant Open 350,000.00 574,577.39 Signed 2017-09-28 2017-09-12 2017-11-16 2017-10-23 2017-12-07 2018-02-20 2018-01-11 2018-02-21 2019-07-05 Support DNA/FCMU Selection Individual 30CS4/DNA/17 / Project Management and Engineering IBRD / 87020 Prior Consultant Open 320,000.00 567,269.05 Signed 2017-10-20 2017-10-16 2017-12-08 2017-12-29 2018-08-06 2018-02-02 2018-08-07 2019-07-27 Accountant Support Selection Individual 31CS4/DNA/17 / Financial Management and Engineering IBRD / 87020 Post Consultant Open 170,000.00 283,934.69 Signed 2017-10-20 2017-10-25 2017-12-08 2018-03-07 2017-12-29 2018-03-07 2018-02-02 2018-03-01 2019-07-27 Assistant (1) Support Selection Individual 32CS4/DNA/17 / Financial Management and Engineering IBRD / 87020 Post Consultant Open 170,000.00 139,944.69 Signed 2017-10-20 2017-10-25 2017-12-08 2017-12-29 2018-03-13 2018-02-02 2018-03-01 2019-07-27 Assistant (2) Support Selection 34CS4/DNA/17 / Consultant Individual to Support the Management and Engineering IBRD / 87020 Post Consultant Direct 45,000.00 42,000.00 Signed 2017-11-30 2017-10-12 2017-12-10 2018-04-11 2017-12-31 2018-08-09 2018-02-04 2018-08-10 2018-08-03 Implementation of the Support Selection Primavera Accounting System Rehabilitation and Expansion Individual 36CS4/DNA/17 / Monitoring IBRD / 87020 of Water Supply Production Prior Consultant Open 250,000.00 531,000.00 Signed 2018-05-24 2018-09-04 2018-07-12 2019-02-05 2018-08-02 2019-08-22 2018-09-06 2019-08-28 2019-03-05 Evaluation Specialist and Distribution Selection Rehabilitation and Expansion Individual 37CS4/DNA/17 / Supervision IBRD / 87020 of Water Supply Production Prior Consultant Open 700,000.00 1,199,664.58 Signed 2018-06-03 2018-05-25 2018-07-22 2018-07-11 2018-08-12 2018-08-13 2018-09-16 2018-08-14 2021-08-31 Engineer and Distribution Selection Rehabilitation and Expansion Individual 40CS4/DNA/17 / Stakeholder IBRD / 87020 of Water Supply Production Prior Consultant Open 700,000.00 750,681.66 Signed 2018-04-20 2018-05-16 2018-06-08 2018-08-30 2018-06-29 2018-09-11 2018-08-03 2018-09-13 2020-07-23 Engagement e Social Specialist and Distribution Selection Individual 41CS4/DNA/17 / Information Management and Engineering IBRD / 87020 Prior Consultant Open 200,000.00 341,023.29 Signed 2018-01-08 2018-01-23 2018-02-26 2018-05-07 2018-03-19 2018-06-26 2018-04-23 2018-06-26 2021-04-07 Technology Support Selection 43CS1/IRSEA/18 / SHORT Water Supply Institutional Individual TERM TECHNICAL ASSISTANCE IBRD / 87020 Strengthening and Capacity Post Consultant Open 80,000.00 121,613.80 Signed 2018-03-19 2018-03-15 2018-04-28 2018-05-03 2018-05-08 2018-05-03 2018-05-18 2018-06-18 2018-11-14 TO IRSEA Development Selection Individual 11ACS4/DNA/18 / Management and Engineering IBRD / 87020 Post Consultant Direct 180,000.00 276,428.51 Signed 2018-04-16 2018-06-27 2018-04-26 2018-07-17 2018-05-17 2018-09-10 2018-06-21 2018-09-10 2019-12-13 Hydrogeology specialist Support Selection 61CS4/DNA/18 / Consultant Individual to prepare the TORs for the Management and Engineering IBRD / 87020 Post Consultant Open 80,000.00 0.00 Canceled 2018-07-02 2018-08-20 2018-09-10 2018-10-15 2019-01-13 Updates of the Master Plans in Support Selection 9 Cities 102CS2/DAS/18 / Short Individual Term Technical Assistance to IBRD / 87020 Water Resource Management Post Consultant Direct 100,000.00 104,762.41 Signed 2018-06-11 2018-06-29 2018-06-21 2018-06-13 2018-07-12 2018-07-16 2018-08-16 2018-07-16 2019-02-12 INRH Selection 52CS3/DAS/18 / DESIGN CHECKING AND WORK Rehabilitation and Expansion SUPERVISION OF NETWORK IBRD / 87020 of Water Supply Production Prior Direct Selection Direct 850,000.00 867,067.03 Signed 2018-06-11 2018-06-14 2018-06-13 2018-06-19 2018-07-01 2018-06-29 2018-12-28 AND HOUSE CONNECTIONS IN and Distribution THE CITY OF HUAMBO - LOT 2 Water Supply Institutional Individual 21ACS4/DNA/18 / Senior IBRD / 87020 Strengthening and Capacity Prior Consultant Limited 450,000.00 683,681.52 Signed 2018-06-13 2018-06-27 2018-06-18 2018-07-09 2018-07-09 2018-08-20 2018-08-13 2018-08-21 2020-08-02 Procurement Specialist Development Selection 18ACS4/DNA/18 / SENIOR Water Supply Institutional Individual FINANCIAL MANAGEMENT IBRD / 87020 Strengthening and Capacity Prior Consultant Limited 700,000.00 701,993.30 Signed 2018-07-20 2018-07-19 2018-08-04 2018-08-20 2018-08-09 2018-09-26 2018-08-29 2018-09-27 2021-08-13 SPECIALIST Development Selection Individual 63CS4/UCP/18 / Senior Management and Engineering IBRD / 87020 Prior Consultant Open 450,000.00 0.00 Canceled 2018-08-22 2018-08-14 2018-10-10 2019-03-18 2018-10-31 2018-12-05 2020-12-04 Sanitation Specialist Support Selection Individual 77CS4/UCP/19 / Second Management and Engineering COFN / C1560 Prior Consultant Open 400,000.00 876,851.72 Signed 2019-06-28 2019-06-06 2019-08-16 2019-07-17 2019-09-06 2019-08-05 2019-10-11 2019-08-12 2021-10-10 Senior Works Supervisor Support Selection Individual 82CS4/UCP/19 / Second Management and Engineering COFN / C1560 Prior Consultant Open 400,000.00 446,779.84 Signed 2019-09-16 2019-08-07 2019-11-04 2020-01-16 2019-11-25 2020-02-07 2019-12-30 2020-02-14 2021-12-29 Senior Design Engineer Support Selection 81CS4/UCP/19 / Project Individual Management and Engineering Financial and Administrative COFN / C1560 Prior Consultant Open 400,000.00 260,000.00 Signed 2019-08-30 2019-08-05 2019-10-18 2020-12-15 2019-11-08 2021-01-14 2019-12-13 2021-01-28 2021-12-12 Support Officer Selection Page 9 Rehabilitation and Expansion Individual 83ACS3/UCP/19 / Dispute COFN / C1560 of Water Supply Production Post Consultant Limited 50,000.00 0.00 Canceled 2019-10-30 2019-10-04 2019-11-04 2019-11-25 2019-12-30 2022-12-29 Board Member and Distribution Selection Individual 20ACS4/UCP/19 / Senior Management and Engineering COFN / C1560 Prior Consultant Open 500,000.00 444,203.36 Signed 2019-10-04 2019-10-07 2019-11-20 2020-01-30 2019-12-04 2020-02-24 2019-12-14 2020-02-26 2021-12-13 Procurement Specialist Support Selection Individual 63ACS4/UCP/19 / Sanitation Management and Engineering COFN / C1560 Prior Consultant Open 400,000.00 359,356.32 Signed 2019-10-04 2019-10-07 2019-11-22 2020-01-24 2019-12-13 2020-02-24 2020-01-17 2020-02-14 2022-01-16 Specialist Support Selection Individual 88CS4/UCP/19 / Financial Management and Engineering COFN / C1560 Post Consultant Open 70,000.00 67,200.00 Signed 2019-11-19 2019-10-11 2020-01-07 2020-02-27 2020-01-28 2020-04-22 2020-03-03 2020-04-22 2021-08-25 Assistant (3) Support Selection Water Supply Institutional Individual 22ACS4/DNA/17 / Under IBRD / 87020 Strengthening and Capacity Prior Consultant Open 205,000.00 0.00 2020-01-26 2020-02-11 2020-03-13 2020-04-14 2020-03-27 2020-05-04 2020-04-06 2021-01-31 Procurement Specialist DNA Implementation Development Selection Individual 27ACS4/DNA/20 / Management and Engineering COFN / C1560 Prior Consultant Open 250,000.00 224,400.00 Signed 2020-08-17 2020-08-27 2020-10-05 2021-02-16 2020-10-26 2021-03-02 2020-11-30 2021-03-15 2021-05-29 Procurement Officer Support Selection Individual 33CS4/DNA/17 / MIS Management and Engineering IBRD / 87020 Post Consultant Open 60,000.00 0.00 Canceled 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-06-13 Consultant Support Selection Rehabilitation and Expansion Individual 38CS4/DNA/17 / Senior IBRD / 87020 of Water Supply Production Prior Consultant Open 500,000.00 0.00 Canceled 2018-03-13 2018-05-01 2018-05-22 2018-06-26 2021-06-10 Environmental Specialist and Distribution Selection 58CS1/UCP/20 / Consultant to support Cuanza North Individual Management and Engineering Province Water and Sanitation IBRD / 87020 Post Consultant Limited 72,000.00 0.00 Canceled 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2021-07-29 Support Utility to implement Non- Selection Revenue Water Strategy 78CS1/UCP/20 / Consultant to support Huila Province Individual Management and Engineering Water and Sanitation Utility to IBRD / 87020 Post Consultant Limited 72,000.00 0.00 Canceled 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2021-07-29 Support implement Non-Revenue Selection Water Strategy Rehabilitation and Expansion Individual 83CS3/UCP/19 / Dispute COFN / C1560 of Water Supply Production Post Consultant Limited 50,000.00 0.00 Canceled 2019-09-15 2019-09-20 2019-10-11 2019-11-15 2022-11-14 Board Member and Distribution Selection Rehabilitation and Expansion Individual 112CS4/UCP/21 / IBRD / 87020 of Water Supply Production Prior Consultant Open 400,000.00 0.00 Under Review 2021-10-19 2021-12-07 2021-12-28 2022-02-01 2025-01-31 Environmental Specialist and Distribution Selection 113CS4/UCP/21 / Rehabilitation and Expansion Individual Stakeholder Engagement and IBRD / 87020 of Water Supply Production Prior Consultant Open 400,000.00 0.00 Under Review 2021-09-22 2021-11-10 2021-12-01 2022-01-05 2025-01-04 Social Specialist and Distribution Selection Rehabilitation and Expansion Individual 114CS4/UCP/21 / Pending IBRD / 87020 of Water Supply Production Prior Consultant Open 250,000.00 0.00 2021-10-14 2021-12-02 2021-12-23 2022-01-27 2025-01-26 Procurement Officer Implementation and Distribution Selection Water Supply Institutional Individual 111CS4/UCP/21 / Senior Pending IBRD / 87020 Strengthening and Capacity Prior Consultant Open 600,000.00 0.00 2021-09-16 2021-11-04 2021-11-25 2021-12-30 2024-12-29 Rural Water Supply Engineer Implementation Development Selection Individual 117CS4/EPAL/21 / Senior Management and Engineering Pending IBRD / 87020 Prior Consultant Open 600,000.00 0.00 2021-09-01 2021-10-20 2021-11-10 2021-12-15 2022-06-13 Technical Advisor to EPAL Support Implementation Selection 118CS4/EPAL/21 / Junior Individual Management and Engineering Pending Environmental and Social IBRD / 87020 Post Consultant Open 300,000.00 0.00 2021-09-01 2021-10-20 2021-11-10 2021-12-15 2022-06-13 Support Implementation Specialist Selection 116CS1/UCP/21 / Technical Support to backstop the Water Supply Institutional Individual Pending Provincial Water and IBRD / 87020 Strengthening and Capacity Post Consultant Limited 60,000.00 0.00 2021-11-22 2021-11-27 2021-12-18 2022-01-22 2022-07-21 Implementation Sanitation Utility of Development Selection Ndalatando and Malanje 119CS4/UCP/21 / Consultant Individual for the Preparation of Management and Engineering Pending IBRD / 87020 Post Consultant Limited 60,000.00 0.00 2021-11-08 2021-11-13 2021-12-04 2022-01-08 2022-07-07 Environmental and Social Support Implementation Selection Instruments 120CS4/UCP/21 / Consultant Individual for the Preparation of Management and Engineering Pending IBRD / 87020 Post Consultant Limited 60,000.00 0.00 2021-11-15 2021-11-20 2021-12-11 2022-01-15 2022-07-14 Indigenous People´s Planning Support Implementation Selection Framework Page 10