Procurement Plan General 1. Bank’s approval Date of the procurement Plan October 2, 2018 2. Date of General Procurement Notice: October 15, 2018 3. Period covered by this procurement plan: October 2018 to April, 2020 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: No. Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) All ≥3,000,000 2. NCB (Goods) All <3,000,000 3. ICB (Works) ≥15,000,000 All 4. NCB (Works) <15,000,000 All 5. (Non-Consultant Services) ≥1,500,000 All 2. Prequalification. Bidders when applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project GHANA PRODUCTIVE SAFETY NETS PROJECT 02/10/2018 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Estimated Domestic Review Ref. Description Cost Packages Preference by Bank Comments No. US$ million (yes/no) (Prior / Post) Summary of the NCB 1 (Goods) 900 2 None None Summary of the ICB 2 (Non-Consultant - None None None Services) Summary of the NCB 755 3 (Non-Consultant 2 None None Services) 4 Summary of the ICS 1926.6 18 None None (services) 5 Summary of the 153 2 None None SHOPPING (Goods) 6 Summary of the 268 3 None None SHOPPING (Non- consulting services) 7 Summary of LCS 660 9 None None (services) 8 Summary of the 400 1 None None QCBS(Works) 9 Summary of the 405 2 None None CQS(Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comment 1. Competitive Methods (Firms) ≥$500 2. Single Source (Firms) ≥$100 3. Individual ≥$200 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Assignment Estimated Review No. Cost Packages by Bank Comments US$ million (Prior / Post) Summary of number of 1 contracts that will be let 400 1 under QCBS Summary of number of 2 contracts that will be let 12,617 68 under other methods PROCUREMENT Ghana : Ghana Productive Safety Net Project PLAN General Information Country: Ghana Bank’s Approval Date of the Original Procurement Plan: 2018-10-05 2020-01-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164603 GPN Date: 2019-01-25 Project Name: Ghana Productive Safety Net Project Loan / Credit No: IDA / 63370, / Executing Agency(ies): Ministry of Local Government and Rural Development WORKS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-SAFETY NETS-141510-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Sabiye IDA / 63370 Intensive Public Works Post Open - National 34,945.00 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Junction-Wewa Feeder Road Program ion (5.0km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141511-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 120,665.61 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Widnaba GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141512-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 54,851.25 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Popolipo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141517-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 75,667.79 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Wasipe GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141518-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 59,985.50 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Zamwengo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141519-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 72,199.69 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Zamsa GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141520-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 108,730.59 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Bachonsa GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141528-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 82,054.66 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Kenkelle GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141530-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 78,848.22 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Touri GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141531-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 163,634.70 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Pialugu GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141533-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 80,873.92 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Duuri No. 1 GH-MLGRD-SAFETY NETS-141535-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 111,418.58 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Earth Dam at Mankuri- Program ion Kontwiri GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141536-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 157,419.56 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Berwong GH-MLGRD-SAFETY NETS-141537-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 119,719.04 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Earth Dam at Eremon Program ion Yagra GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141539-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 49,966.00 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Dabozesi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141541-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 95,332.89 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Katagri GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141542-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 40,046.38 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Kulsalboug GH-MLGRD-SAFETY NETS-141543-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 43,399.88 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Earth Dam at Soliga Program ion (Phase 2) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141544-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 137,274.20 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Loho GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141545-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 93,202.73 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Payani Page 1 GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141548-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 80,514.88 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Ketuo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141553-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 72,727.27 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Zeng GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141554-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 50,546.08 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Wulensi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141556-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 105,304.11 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilition of Small Earth Quotations Envelope Program ion Dam at Lingbinsi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141557-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 87,100.13 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Singa GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141563-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 99,420.20 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Nakpala GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141565-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 34,421.20 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Nakwabi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141566-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 94,187.67 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Gbeogo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141567-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 29,539.78 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Tindongo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141569-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 64,982.94 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Kunyabin GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141571-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 45,942.77 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Tousal GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141572-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 96,383.27 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Bosoyiri GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141573-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 36,837.91 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Meteo GH-MLGRD-SAFETY NETS-141575-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Ujoja- IDA / 63370 Intensive Public Works Post Open - National 52,178.67 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Ochadindo Feeder Road Program ion (3.1km) GH-MLGRD-SAFETY NETS-141577-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Bulingin- IDA / 63370 Intensive Public Works Post Open - National 58,037.06 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Kangba Feeder Road Program ion (4.0Km) GH-MLGRD-SAFETY NETS-141578-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Tampiem- IDA / 63370 Intensive Public Works Post Open - National 66,192.29 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Dandafuro Feeder Road Program ion (4.8Km) GH-MLGRD-SAFETY NETS-141579-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Dupari- IDA / 63370 Intensive Public Works Post Open - National 65,206.43 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Goripie Feeder Road Program ion (4.5Km) GH-MLGRD-SAFETY NETS-141582-CW-RFB / Component 2: Labor Pending Rehabilitation of Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 26,266.79 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Woramponho Junction - Quotations Envelope Program ion Woramponho Feeder Road (1.8Km) GH-MLGRD-SAFETY NETS-141584-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Hani - IDA / 63370 Intensive Public Works Post Open - National 39,253.92 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Storage Facility Site Feeder Program ion Road (3.5Km) GH-MLGRD-SAFETY NETS-141586-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Sawia- IDA / 63370 Intensive Public Works Post Open - National 64,370.81 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Mempekasa Feeder Road Program ion (3.7Km) GH-MLGRD-SAFETY NETS-141588-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Mpentease IDA / 63370 Intensive Public Works Post Open - National 15,812.00 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope - Akyease Feeder Road Program ion (1.0Km) GH-MLGRD-SAFETY NETS-141589-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Jelinkon - IDA / 63370 Intensive Public Works Post Open - National 90,479.20 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Yoliyiri Feeder Road Program ion (6.3Km) GH-MLGRD-SAFETY NETS-141590-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Saboba - IDA / 63370 Intensive Public Works Post Open - National 32,333.68 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Boagbaln Feeder Program ion Road(2.5km) Page 2 GH-MLGRD-SAFETY NETS-141591-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Ziape - IDA / 63370 Intensive Public Works Post Open - National 44,113.54 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Kikayili Feeder Road Program ion (3.5Km) GH-MLGRD-SAFETY NETS-141592-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Srenoso IDA / 63370 Intensive Public Works Post Open - National 51,784.21 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope No. 1 - Bosomponso Feeder Program ion Road (4.2Km) GH-MLGRD-SAFETY NETS-141593-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Nyankoma IDA / 63370 Intensive Public Works Post Open - National 26,903.96 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Junction -Sawia Feeder Program ion Road (2.1Km) GH-MLGRD-SAFETY NETS-141594-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Mama IDA / 63370 Intensive Public Works Post Open - National 56,692.16 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Kura-Hundokope Feeder Program ion Road (4.0Km) GH-MLGRD-SAFETY NETS-141595-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Nyankpani- IDA / 63370 Intensive Public Works Post Open - National 43,395.27 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Wumbdoja Feeder Road Program ion (3.5Km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141600-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 65,124.02 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Goziiri-Na- Quotations Envelope Program ion Ewini Feeder Road (4.0Km) GH-MLGRD-SAFETY NETS-141601-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Kaleo- IDA / 63370 Intensive Public Works Post Open - National 28,341.37 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Buoduori Feeder Road Program ion (1.2Km) GH-MLGRD-SAFETY NETS-141603-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Bareki - IDA / 63370 Intensive Public Works Post Open - National 70,025.00 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Gundork - Zanlerigu Feeder Program ion road (4.7km) GH-MLGRD-SAFETY NETS-141604-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Kikaayiri- IDA / 63370 Intensive Public Works Post Open - National 57,025.10 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Kpatorigu Feeder Program ion Road(3.8km) GH-MLGRD-SAFETY NETS-141606-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Nalogn- IDA / 63370 Intensive Public Works Post Open - National 49,257.92 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Nanpoado Feeder Road Program ion (3.5km) GH-MLGRD-SAFETY NETS-141607-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 40,641.08 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Kunyokuong-Metorbuo Program ion Feeder Road (3.0Km) GH-MLGRD-SAFETY NETS-141609-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Nkwanta IDA / 63370 Intensive Public Works Post Open - National 71,573.62 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Farm Jnc-Hiawoanwu Program ion Feeder Road (4.2km) GH-MLGRD-SAFETY NETS-141610-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Ziseri Jnc- IDA / 63370 Intensive Public Works Post Open - National 65,457.63 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Kumasung-Zari Market Program ion Feeder Road (5.0km) GH-MLGRD-SAFETY NETS-141611-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Kpatinga - IDA / 63370 Intensive Public Works Post Open - National 24,946.23 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Bugnaayilii Feeder Road Program ion (1.5km) GH-MLGRD-SAFETY NETS-141612-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Ul-Kpong- IDA / 63370 Intensive Public Works Post Open - National 68,952.78 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Deriyiiri Feeder Road Program ion (5.2Km) GH-MLGRD-SAFETY NETS-141614-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Monkrate IDA / 63370 Intensive Public Works Post Open - National 65,171.07 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Jnc-Monkrate Feeder Road Program ion (3.6Km) GH-MLGRD-SAFETY NETS-141615-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 73,919.68 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Ahiamankyene-Sabaja Program ion Feeder Road (3.5Km) GH-MLGRD-SAFETY NETS-141616-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Dika- IDA / 63370 Intensive Public Works Post Open - National 53,782.99 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Ahumansu Feeder Road Program ion (4.0Km) GH-MLGRD-SAFETY NETS-141619-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Boya- IDA / 63370 Intensive Public Works Post Open - National 65,369.07 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Adonsi-Adagbira Feeder Program ion Road (4.0km) GH-MLGRD-SAFETY NETS-141621-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Dole - IDA / 63370 Intensive Public Works Post Open - National 50,925.07 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Nokoyiiri Feeder Road Program ion (3.8Km) GH-MLGRD-SAFETY NETS-141622-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Sanabiisi - IDA / 63370 Intensive Public Works Post Open - National 81,019.55 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Kabre- Akulyor Feeder road Program ion (5.6km) Page 3 GH-MLGRD-SAFETY NETS-141623-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Pintengsa- IDA / 63370 Intensive Public Works Post Open - National 57,483.53 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Bachiesa Feeder Road Program ion (4.0km) GH-MLGRD-SAFETY NETS-141624-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Kpemale- IDA / 63370 Intensive Public Works Post Open - National 54,185.28 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Bandimsugru Feeder Program ion Road(3.5km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141625-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 41,304.39 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Sheri- Quotations Envelope Program ion Kaliito Feeder Road(3.0km) GH-MLGRD-SAFETY NETS-141627-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Takyie - IDA / 63370 Intensive Public Works Post Open - National 67,000.95 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Toyempare Feeder Road Program ion (4.8Km) GH-MLGRD-SAFETY NETS-141628-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Kukua - IDA / 63370 Intensive Public Works Post Open - National 48,664.76 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Mabung Feeder Road Program ion (3.2Km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141859-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 153,400.00 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Nayorku GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141860-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 50,500.35 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Karimenga GH-MLGRD-SAFETY NETS-141861-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Walewale- IDA / 63370 Intensive Public Works Post Open - National 62,297.82 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Bugya Kura Feeder Road Program ion (4.4km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141862-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 140,965.24 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Nagbo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141864-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 154,203.63 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Sakogu GH-MLGRD-SAFETY NETS-141865-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Langbinsi- IDA / 63370 Intensive Public Works Post Open - National 55,623.62 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Bumboazio Feeder Road Program ion (3.5km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141867-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 119,719.04 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Lam-Buu GH-MLGRD-SAFETY NETS-142616-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Kpemale- IDA / 63370 Intensive Public Works Post Open - National 54,185.27 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Bandimsugru Feeder Road Program ion (3.5km) GH-MLGRD-SAFETY Component 2: Labor Under NETS-142683-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 94,057.27 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Pobikwaa- Quotations Envelope Program ion Annan Feeder Road (4.9km) GH-MLGRD-SAFETY NETS-142686-CW-RFB / Component 2: Labor Under Request for Single Stage - One Rehabilitation of Yehuno IDA / 63370 Intensive Public Works Post Open - National 68,148.53 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Junction-Yehuno Feeder Program ion Road (4.1km)68 GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142689-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 111,954.00 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Wenchiki GH-MLGRD-SAFETY NETS-142698-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Sangbana IDA / 63370 Intensive Public Works Post Open - National 45,081.54 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Jnc-Sangbana Feeder Road Program ion (2.0km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142699-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 95,285.04 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Namongo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142701-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 116,579.99 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Mangor GH-MLGRD-SAFETY NETS-142702-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Naghan- IDA / 63370 Intensive Public Works Post Open - National 54,931.55 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Sangbani Feeder Road Program ion (3.6km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142710-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 30,574.81 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Dingoni Quotations Envelope Program ion Feeder Road (1.5Km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142711-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 5,371,596.00 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Nakpayili GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142713-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 77,212.79 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Banda Page 4 GH-MLGRD-SAFETY NETS-142716-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 51,368.34 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Abrewankor-Konkonbaline Program ion Feeder Road (3.6Km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142718-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 88,215.31 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Arizeem GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142720-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 70,119.89 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Yakin GH-MLGRD-SAFETY NETS-142722-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Mognori - IDA / 63370 Intensive Public Works Post Open - National 73,589.93 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Tampizua -Bador-Gomoluka Program ion Feeder Road (5.1km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142724-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 89,489.37 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Earth Quotations Envelope Program ion Dams at Kumpalgunga GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142727-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 126,600.27 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Earth Quotations Envelope Program ion Dams at Narango GH-MLGRD-SAFETY NETS-142735-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Ayumsey- IDA / 63370 Intensive Public Works Post Open - National 136,810.72 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Tabiugu Feeder Road Program ion (3.7KM) GH-MLGRD-SAFETY NETS-142738-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 136,810.72 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Earth Dam at Kadema- Program ion Kpikpaluk (Agbanlong) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142739-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 108,730.58 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Bachonsa GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142742-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 94,010.68 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Yariga GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142745-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 79,393.11 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Votukom GH-MLGRD-SAFETY NETS-142749-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Sianongo- IDA / 63370 Intensive Public Works Post Open - National 56,272.72 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Tesnatinga Feeder Road Program ion (3.56km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142751-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 96,587.89 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Bugpiigu GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142752-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 90,797.60 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Kugasheigu GH-MLGRD-SAFETY NETS-142757-CW-RFB / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Gagbiri IDA / 63370 Intensive Public Works Post Open - National 69,016.71 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Market -Central Mosque Program ion Feeder Road (5.0km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142758-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 85,691.72 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Nabaala- Quotations Envelope Program ion Billaw Feeder Road (4.5Km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142760-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 150,741.49 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Nankpawie GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142762-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 76,578.39 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Nmanduanu GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142766-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 178,516.42 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Kunkorgu GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142768-CW-RFB / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 82,096.24 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Rehabilitation of Gbaal-Kuni Quotations Envelope Program ion Feeder Road (4.8Km) GH-MLGRD-SAFETY NETS-142769-CW-RFB / Component 2: Labor Under Request for Single Stage - One Rehabilitation of Logba- IDA / 63370 Intensive Public Works Post Open - National 31,485.81 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Akusane-Horglikope Feeder Program ion Road (5.0km) GH-MLGRD-SAFETY NETS-142776-CW-RFB / Component 2: Labor Under Request for Single Stage - One Rehabilitation of Tsrinorni- IDA / 63370 Intensive Public Works Post Open - National 69,701.77 0.00 Implementat 2019-10-31 2019-11-05 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Quotations Envelope Kesenyemito Feeder Road Program ion (4.2km) GH-MLGRD-SAFETY NETS-146719-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha IDA / 63370 Intensive Public Works Post Driven Direct 73,702.36 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Nindowala Page 5 GH-MLGRD-SAFETY NETS-146726-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 60,000.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Nanyili GH-MLGRD-SAFETY NETS-146889-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 74,163.96 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Mamakora GH-MLGRD-SAFETY NETS-146894-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 61,456.55 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Sabare GH-MLGRD-SAFETY NETS-146895-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha IDA / 63370 Intensive Public Works Post Driven Direct 77,191.82 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees including nursery at Sheini GH-MLGRD-SAFETY NETS-146716-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 97,742.36 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Saamanpo GH-MLGRD-SAFETY NETS-146725-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees including nursery at Kaleo GH-MLGRD-SAFETY NETS-146729-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Kokoligu Gbantakuuri GH-MLGRD-SAFETY NETS-146736-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 55,951.45 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Kokoligu Bekyiinteng GH-MLGRD-SAFETY NETS-146722-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha IDA / 63370 Intensive Public Works Post Driven Direct 77,742.36 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees including nursery at Sentu GH-MLGRD-SAFETY NETS-146750-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Wellembelle GH-MLGRD-SAFETY NETS-146754-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 50,951.45 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Sorbelle GH-MLGRD-SAFETY NETS-146783-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Pending degraded community land IDA / 63370 Intensive Public Works Post Driven Direct 65,112.15 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Soe- Ayelbia GH-MLGRD-SAFETY NETS-146749-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees including nursery at Saru GH-MLGRD-SAFETY NETS-146748-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 54,878.73 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Yipala GH-MLGRD-SAFETY NETS-146759-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 65,524.18 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Nyandema GH-MLGRD-SAFETY NETS-146763-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 80,636.18 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees including nursery at Busa GH-MLGRD-SAFETY NETS-146764-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 55,951.45 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Nakore GH-MLGRD-SAFETY NETS-146765-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 80,636.18 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees including nursery at Ga Page 6 GH-MLGRD-SAFETY NETS-146768-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 55,951.45 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Bankpama GH-MLGRD-SAFETY NETS-146724-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Kumasaal GH-MLGRD-SAFETY NETS-146760-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 97,742.36 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Buffiama GH-MLGRD-SAFETY NETS-146789-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 8ha IDA / 63370 Intensive Public Works Post Driven Direct 45,112.15 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Chuchuliga-Awenaguuk GH-MLGRD-SAFETY NETS-146793-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 77,164.91 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Naadema GH-MLGRD-SAFETY NETS-146810-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 86,120.18 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Nayorku GH-MLGRD-SAFETY NETS-146862-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 71,318.18 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Yishielanyili GH-MLGRD-SAFETY NETS-146799-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 5ha IDA / 63370 Intensive Public Works Post Driven Direct 52,373.45 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees including nursery at Jakpa GH-MLGRD-SAFETY NETS-146816-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 50,767.73 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Yahyayilli GH-MLGRD-SAFETY NETS-146761-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha IDA / 63370 Intensive Public Works Post Driven Direct 73,702.36 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Katua GH-MLGRD-SAFETY NETS-146811-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 70,969.27 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Tamaklan GH-MLGRD-SAFETY NETS-146813-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 60,969.27 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Fufulso GH-MLGRD-SAFETY NETS-146856-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 72,112.15 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Yikurugu GH-MLGRD-SAFETY NETS-146863-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 58,258.18 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Kutung GH-MLGRD-SAFETY NETS-146867-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 72,586.18 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Mango fruit trees at Ayirafie GH-MLGRD-SAFETY NETS-146869-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 72,552.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Monkrate GH-MLGRD-SAFETY NETS-146871-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 73,643.09 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion incluing nursery at Ahiamankyene Page 7 GH-MLGRD-SAFETY NETS-146874-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 75,369.64 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Bejamse GH-MLGRD-SAFETY NETS-146875-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 55,353.27 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Beposo GH-MLGRD-SAFETY NETS-146880-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 55,353.27 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Grubi GH-MLGRD-SAFETY NETS-146885-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 77,361.73 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Nakpayili GH-MLGRD-SAFETY NETS-146886-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 55,484.09 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Tampoaya GH-MLGRD-SAFETY NETS-146887-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 20ha IDA / 63370 Intensive Public Works Post Driven Direct 95,597.82 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees including nursery at Pabila GH-MLGRD-SAFETY NETS-146888-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 20ha IDA / 63370 Intensive Public Works Post Driven Direct 68,278.12 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Teak woodlot trees at Damanko & Abunyanya GH-MLGRD-SAFETY NETS-146746-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Sinsina GH-MLGRD-SAFETY NETS-146751-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha IDA / 63370 Intensive Public Works Post Driven Direct 97,742.36 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees including nursery at Bullu GH-MLGRD-SAFETY NETS-146769-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 70,951.45 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Kuka- Zuli GH-MLGRD-SAFETY NETS-146773-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 8ha IDA / 63370 Intensive Public Works Post Driven Direct 43,746.33 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Kamega GH-MLGRD-SAFETY NETS-146782-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 8ha IDA / 63370 Intensive Public Works Post Driven Direct 43,746.33 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Feo - Asebre GH-MLGRD-SAFETY NETS-146779-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 65,112.15 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Yikurugu GH-MLGRD-SAFETY NETS-146873-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 51,530.18 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Coconut fruit trees at Kadentwe & Nkatinkon GH-MLGRD-SAFETY NETS-146893-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 73,994.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Mogneigu GH-MLGRD-SAFETY NETS-146792-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 65,112.15 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Sandema -Kori GH-MLGRD-SAFETY NETS-146806-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 8 degraded IDA / 63370 Intensive Public Works Post Driven Direct 75,112.15 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 communal land using Program Development ion Cashew fruit trees including nursery at Gbeogo Page 8 GH-MLGRD-SAFETY NETS-146794-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 55,524.18 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Nyandema GH-MLGRD-SAFETY NETS-146795-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 8ha IDA / 63370 Intensive Public Works Post Driven Direct 43,746.33 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Kpemale GH-MLGRD-SAFETY NETS-146796-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 65,112.15 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Kpentaung GH-MLGRD-SAFETY NETS-146798-CW-FCA / Rehabilitation of 5ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 52,373.45 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Nansoni GH-MLGRD-SAFETY NETS-146802-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 77,164.91 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Kubugu GH-MLGRD-SAFETY NETS-146809-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha IDA / 63370 Intensive Public Works Post Driven Direct 83,940.55 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Bulbia GH-MLGRD-SAFETY NETS-146866-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 74,283.64 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded land using Program Development ion Mango fruit trees at Atsigode GH-MLGRD-SAFETY NETS-146882-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 85,426.91 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Ahiamansu GH-MLGRD-SAFETY NETS-146890-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 51,815.05 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Wui GH-MLGRD-SAFETY NETS-146897-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 60,850.73 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Mbowura GH-MLGRD-SAFETY NETS-146803-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 55,524.18 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Loagri GH-MLGRD-SAFETY NETS-146814-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 75,767.73 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Mbawupe GH-MLGRD-SAFETY NETS-146864-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 61,318.18 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded land using Program Development ion Cashew fruit trees at Salaa GH-MLGRD-SAFETY NETS-146884-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 76,869.64 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Tampion GH-MLGRD-SAFETY NETS-146896-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 65,850.73 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Malando GH-MLGRD-SAFETY NETS-146704-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Sornyo GH-MLGRD-SAFETY NETS-146711-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 60,000.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Kojokpere Page 9 GH-MLGRD-SAFETY NETS-146717-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 97,742.36 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Balanta GH-MLGRD-SAFETY NETS-146723-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha IDA / 63370 Intensive Public Works Post Driven Direct 73,702.36 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Billow GH-MLGRD-SAFETY NETS-146891-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha IDA / 63370 Intensive Public Works Post Driven Direct 79,749.45 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees including nursery at Kunjuli GH-MLGRD-SAFETY NETS-146892-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha IDA / 63370 Intensive Public Works Post Driven Direct 77,393.09 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Sobiba GH-MLGRD-SAFETY NETS-146800-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 84,369.64 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Wundua GH-MLGRD-SAFETY NETS-146808-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 72,437.82 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Mango fruit trees Program Development ion including nursery at Benwoko GH-MLGRD-SAFETY NETS-146801-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 81,634.36 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Teak woodlot trees Program Development ion including nursery at Namangu GH-MLGRD-SAFETY NETS-146804-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Pending degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 65,112.15 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 using Cashew fruit trees Program Development ion including nursery at Dasabligo GH-MLGRD-SAFETY NETS-146805-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 8ha IDA / 63370 Intensive Public Works Post Driven Direct 53,746.33 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Kparikpii GH-MLGRD-SAFETY NETS-146707-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 60,000.00 0.00 Implementat 2019-12-24 2019-12-29 2020-02-02 2022-12-31 degraded communal land Program Development ion using Cashew fruit trees at Kakiase GH-MLGRD-SAFETY NETS-152499-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 96,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Earth Dam at Adaklu Program ion Torda GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152500-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 93,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Sofa GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152501-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 103,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Vakpo Korda GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152502-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 104,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Deve GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152503-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 106,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Bawakope GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152504-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 105,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Akorsu GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152505-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 51,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Nyantang GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152506-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 175,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Gbirigi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152507-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 64,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of 1No. Small Quotations Envelope Program ion Earth Dam at Bau GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152508-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 130,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Bambuli Page 10 GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152512-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 170,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Sia-Kura GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152513-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 104,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Salankpan GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152514-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 72,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Tijo GH-MLGRD-SAFETY NETS-152515-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 120,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Earth Dam at Nanton- Program ion Kurugu GH-MLGRD-SAFETY NETS-152516-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 135,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Earth Dam at Nayili Program ion Sachedo GH-MLGRD-SAFETY NETS-152518-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 85,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope earth dam at Nakpali Program ion Tindang GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152519-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 145,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Nahoyili GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152520-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 86,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Nakpaboari GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152521-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 58,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Kabrono GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152522-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 116,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Chokosi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152523-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 105,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Yabraso GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152524-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 120,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Degedege GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152525-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 61,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Mansin GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152526-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 106,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Small Quotations Envelope Program ion Earth Dam at Nsesreso GH-MLGRD-SAFETY NETS-152527-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Dzolopuita- IDA / 63370 Intensive Public Works Post Open - National 110,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Gbedome Feeder Road Program ion (6.5km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152528-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 80,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Hehekpoe- Quotations Envelope Program ion Waya Feeder Road (4.0km) GH-MLGRD-SAFETY NETS-152529-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Kwame IDA / 63370 Intensive Public Works Post Open - National 87,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Ntow-Apenteng Feeder Road Program ion (4.5km) GH-MLGRD-SAFETY NETS-152530-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Dukuma IDA / 63370 Intensive Public Works Post Open - National 60,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Tsrukpe-Zanuta Feeder Program ion Road (4.6km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152531-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 80,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Adwofo- Quotations Envelope Program ion Gyateh Feeder Road (4.1km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152532-CW-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Post Open - National 48,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Rehabilitation of Eyisam- Quotations Envelope Program ion Engow Feeder Road (3.1km) GH-MLGRD-SAFETY NETS-152534-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Mota Jnc- IDA / 63370 Intensive Public Works Post Open - National 71,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Mota Sasu Feeder Road Program ion (4.0km) GH-MLGRD-SAFETY NETS-152535-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Ayiwata- IDA / 63370 Intensive Public Works Post Open - National 75,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Ayawa-Wuxor Feeder Road Program ion (3.5km) GH-MLGRD-SAFETY NETS-152536-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Doffor Jnc.- IDA / 63370 Intensive Public Works Post Open - National 53,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Doffor & Others Feeder Program ion Road (3.5km) Page 11 GH-MLGRD-SAFETY NETS-152537-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Trawa- IDA / 63370 Intensive Public Works Post Open - National 60,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Trawa Junc. Feeder Road Program ion (4.0km) GH-MLGRD-SAFETY NETS-152538-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of Nadigu- IDA / 63370 Intensive Public Works Post Open - National 64,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Digu-Zali-Dubilagbini Feeder Program ion Road (5.0Km) GH-MLGRD-SAFETY NETS-152539-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 38,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Kyeremasu-Kofibour Feeder Program ion Road (3.4Km) GH-MLGRD-SAFETY NETS-152540-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 32,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Sunurososo-Okyerekrom Program ion Feeder Road (1.9Km) GH-MLGRD-SAFETY NETS-152543-CW-RFQ / Component 2: Labor Pending Request for Single Stage - One Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 58,000.00 0.00 Implementat 2020-01-10 2020-01-15 2020-02-14 2020-03-15 2020-04-19 2022-12-31 Quotations Envelope Asempanaye-Yawben Feeder Program ion Road (4.0km) GOODS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-SAFETY NETS-80531-GO-RFB / Component 5: Project Under Single Stage - One Procurement of 8 No. 4X4 IDA / 63370 Management, Coordination, Post Request for Bids Open - National 360,000.00 0.00 Implementat 2019-10-04 2019-10-09 2019-11-20 2019-12-20 2020-01-24 2020-05-23 Envelope Vehicles for LIPW and PI and Capacity Building ion monitoring activities GH-MLGRD-SAFETY NETS-80528-GO-RFB / Under Supply of 170No. all-terrain Component 1: Productive Single Stage - One IDA / 63370 Post Request for Bids Open - National 216,363.64 0.00 Implementat 2019-10-04 2019-10-09 2019-11-20 2019-12-20 2020-01-24 2020-04-23 Motorbikes for LIPW and Inclusion Envelope ion PI Monitoring and Supervision activities GH-MLGRD-SAFETY NETS-80524-GO-RFQ / Component 5: Project Under Request for Single Stage - One Procurement of 35No. IDA / 63370 Management, Coordination, Post Open - National 26,000.00 0.00 Implementat 2019-10-09 2019-12-04 2020-01-18 Quotations Envelope Laptops and 10No. Desktops and Capacity Building ion +UPS GH-MLGRD-SAFETY NETS-80525-GO-RFQ / Procurement of 5No. Component 5: Project Pending Photocopiers, 4No. projectors Request for Single Stage - One IDA / 63370 Management, Coordination, Post Limited 7,864.00 0.00 Implementat 2019-12-11 2020-02-05 2020-03-21 with screen, 5No. Digital Quotations Envelope and Capacity Building ion and Video Camera & LCD and 2 No. Drones for RDCU and Zonal Offices. GH-MLGRD-SAFETY NETS-80535-GO-RFB / Component 2: Labor Under Procurement of 100 Tablets Single Stage - One IDA / 63370 Intensive Public Works Post Request for Bids Open - National 25,090.91 0.00 Implementat 2019-10-04 2019-10-09 2019-11-20 2019-12-20 2020-01-24 2020-04-23 and Biometric Scanners for Envelope Program ion capturing LIPW Daily Work Attendance GH-MLGRD-SAFETY NETS-146899-GO-RFQ / Component 2: Labor Pending Procurement of 460 Tablets Request for Single Stage - One IDA / 63370 Intensive Public Works Post Limited 190,000.00 0.00 Implementat 2019-12-25 2020-02-19 2020-04-15 with Biometric Scanners for Quotations Envelope Program ion capturing LIPW Daily Work Attendance GH-MLGRD-SAFETY NETS-146900-GO-RFQ / Pending Procurement of 1 No. HP Component 1: Productive Request for Single Stage - One IDA / 63370 Post Limited 12,000.00 0.00 Implementat 2019-12-25 2020-02-19 2020-04-15 Server to Host GMISPro, E- Inclusion Quotations Envelope ion Dash, PI System application software and database GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152541-GO-RFQ / Request for Single Stage - One IDA / 63370 Intensive Public Works Prior Limited 82,000.00 0.00 Implementat 2020-01-15 2020-03-11 2020-06-09 Supply of Poly Pots for Quotations Envelope Program ion Cashew Seedlings Production. GH-MLGRD-SAFETY Component 2: Labor Pending Request for Single Stage - One NETS-152542-GO-RFQ / IDA / 63370 Intensive Public Works Prior Limited 50,000.00 0.00 Implementat 2020-01-15 2020-03-11 2020-06-09 Quotations Envelope Supply of Poly Sheets and Program ion Shade Nets NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-SAFETY NETS-80514-NC-DIR / Component 5: Project Pending Procurement of Service IDA / 63370 Management, Coordination, Post Direct Selection Direct 10,000.00 0.00 Implementat 2019-10-15 2019-10-20 2019-11-24 2020-02-24 Provider to migrate from and Capacity Building ion ACCPAC to GIFMIS GH-MLGRD-SAFETY Pending NETS-80518-NC-DIR / Component 1: Productive IDA / 63370 Post Direct Selection Direct 30,000.00 0.00 Implementat 2019-10-15 2019-10-20 2019-11-24 2020-02-22 Service Provider for Inclusion ion Upgrading & Maintenance of GMIS-Pro GH-MLGRD-SAFETY NETS-80521-NC-DIR / Service Provider to upgrade Component 2: Labor Pending and integrate Electronic IDA / 63370 Intensive Public Works Post Direct Selection Direct 15,000.00 0.00 Implementat 2019-10-15 2019-10-20 2019-11-24 2020-02-22 Work Attendance Program ion Management System ( e- DASH) into GMIS Pro Page 12 GH-MLGRD-SAFETY Component 5: Project Pending NETS-80522-NC-DIR / IDA / 63370 Management, Coordination, Post Direct Selection Direct 15,000.00 0.00 Implementat 2019-10-18 2019-10-23 2019-11-27 2021-05-14 Sharepoint Server and Capacity Building ion configuration Email hosting with NITA GH-MLGRD-SAFETY Pending NETS-80517-NC-RFB / Component 1: Productive Request for Single Stage - One IDA / 63370 Post Limited 72,000.00 0.00 Implementat 2019-10-09 2019-12-04 2021-05-27 Selection of Service Provider Inclusion Quotations Envelope ion for LIPW and PI E- Payment Services GH-MLGRD-SAFETY NETS-146208-NC-DIR / Pending Component 1: Productive Selection of Service Provider IDA / 63370 Prior Direct Selection Direct 72,000.00 0.00 Implementat 2019-11-29 2019-12-04 2020-01-08 2020-07-06 Inclusion for LIPW and PI E- ion Payment Services CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Process Expression of Request for Opening of Technical Evaluation of / Description Component Review Type Method Amount Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Status Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal (US$) Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Status Contract (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-SAFETY Component 5: Project Individual NETS-80479-CS-INDV / IDA / 63370 Management, Coordination, Prior Consultant Open 90,000.00 48,000.00 Signed 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2020-09-08 Procurement of National and Capacity Building Selection Coordinator for RDCU GH-MLGRD-SAFETY Component 5: Project Individual NETS-80487-CS-INDV / Under / Management, Coordination, Prior Consultant Open 57,600.00 36,000.00 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2020-09-08 Procurement of National Implementation and Capacity Building Selection Engineer at RDCU GH-MLGRD-SAFETY NETS-80490-CS-INDV / Component 5: Project Individual Under Procurement of Institutional / Management, Coordination, Prior Consultant Open 57,600.00 36,000.00 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2020-09-08 Implementation & Capacity Development and Capacity Building Selection Specialist at RDCU GH-MLGRD-SAFETY NETS-80491-CS-INDV / Component 5: Project Individual Under Procurement of Productive / Management, Coordination, Prior Consultant Open 57,600.00 0.00 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2020-09-08 Implementation Inclusion Specialist for and Capacity Building Selection RDCU GH-MLGRD-SAFETY NETS-80494-CS-INDV / Component 5: Project Individual Under Procurement of Monitoring / Management, Coordination, Prior Consultant Open 57,600.00 0.00 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2020-09-08 Implementation and Evaluation Officer for and Capacity Building Selection RDCU GH-MLGRD-SAFETY Component 5: Project Individual NETS-80504-CS-INDV / Under / Management, Coordination, Prior Consultant Open 32,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Procurement of 1No. Implementation and Capacity Building Selection Engineer for Zonal Office 1 GH-MLGRD-SAFETY NETS-80507-CS-INDV / Component 5: Project Individual Under Procurement of 1No. / Management, Coordination, Prior Consultant Open 32,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Implementation Accountant for Zonal Office and Capacity Building Selection 1 GH-MLGRD-SAFETY NETS-80510-CS-INDV / Component 5: Project Individual Procurement of 1No. / Management, Coordination, Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Community Animator for and Capacity Building Selection Zonal Office 1 GH-MLGRD-SAFETY NETS-80742-CS-INDV / Component 5: Project Individual Procurement of 1No. / Management, Coordination, Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Community Animator for and Capacity Building Selection Zonal Office 2 GH-MLGRD-SAFETY NETS-80744-CS-INDV / Component 5: Project Individual Procurement of 1No. / Management, Coordination, Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Community Animator for and Capacity Building Selection Zonal Office 3 GH-MLGRD-SAFETY NETS-80746-CS-INDV / Component 5: Project Individual Procurement of 1No. / Management, Coordination, Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Community Animator for and Capacity Building Selection Zonal Office 4 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80749-CS-INDV / Under / Management, Coordination, Prior Consultant Open 32,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Procurement of 1No. Implementation and Capacity Building Selection Engineer for Zonal Office 2 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80750-CS-INDV / Under / Management, Coordination, Prior Consultant Open 32,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Procurement of 1No. Implementation and Capacity Building Selection Engineer for Zonal Office 3 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80751-CS-INDV / Under / Management, Coordination, Prior Consultant Open 32,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Procurement of 1No. Implementation and Capacity Building Selection Engineer for Zonal Office 4 GH-MLGRD-SAFETY NETS-80754-CS-INDV / Component 5: Project Individual Under Procurement of 1No. / Management, Coordination, Prior Consultant Open 32,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Implementation Accountant for Zonal Office and Capacity Building Selection 2 GH-MLGRD-SAFETY NETS-80755-CS-INDV / Component 5: Project Individual Under Procurement of 1No. / Management, Coordination, Prior Consultant Open 32,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Implementation Accountant for Zonal Office and Capacity Building Selection 3 Page 13 GH-MLGRD-SAFETY NETS-80756-CS-INDV / Component 5: Project Individual Under Procurement of 1No. / Management, Coordination, Prior Consultant Open 32,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Implementation Accountant for Zonal Office and Capacity Building Selection 4 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80758-CS-INDV / Under / Management, Coordination, Prior Consultant Open 32,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Procurement of 1No. PI Implementation and Capacity Building Selection Officer for Zonal Office 2 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80761-CS-INDV / Under / Management, Coordination, Prior Consultant Open 32,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Procurement of 1No. PI Implementation and Capacity Building Selection Officer for Zonal Office 3 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80763-CS-INDV / Under / Management, Coordination, Prior Consultant Open 32,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Procurement of 1No. PI Implementation and Capacity Building Selection Officer for Zonal Office 4 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80765-CS-INDV / / Management, Coordination, Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Procurement of 1No. PI and Capacity Building Selection Officer for RDCU GH-MLGRD-SAFETY NETS-80499-CS-INDV / Component 5: Project Individual Under Procurement of 1No. Zonal IDA / 63370 Management, Coordination, Prior Consultant Open 50,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Implementation Coordinator for Zonal Office and Capacity Building Selection 1 GH-MLGRD-SAFETY NETS-87845-CS-INDV / Component 5: Project Individual Procurement of 1No. IDA / 63370 Management, Coordination, Prior Consultant Open 27,000.00 30,000.00 Signed 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2020-09-02 Safeguards and Case and Capacity Building Selection Management Officer at RDCU GH-MLGRD-SAFETY Component 5: Project Individual NETS-87846-CS-INDV / IDA / 63370 Management, Coordination, Prior Consultant Open 27,000.00 36,000.00 Signed 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2020-09-02 Procurement of 1No. and Capacity Building Selection Procurement Officer GH-MLGRD-SAFETY NETS-80741-CS-INDV / Component 5: Project Individual Under Procurement of 1No. Zonal IDA / 63370 Management, Coordination, Prior Consultant Open 50,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Implementation Coordinator for Zonal Office and Capacity Building Selection 4 GH-MLGRD-SAFETY NETS-80739-CS-INDV / Component 5: Project Individual Under Procurement of 1No. Zonal IDA / 63370 Management, Coordination, Prior Consultant Open 50,400.00 31,200.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Implementation Coordinator for Zonal Office and Capacity Building Selection 2 GH-MLGRD-SAFETY NETS-80740-CS-INDV / Component 5: Project Individual Under Procurement of 1No. Zonal IDA / 63370 Management, Coordination, Prior Consultant Open 50,400.00 0.00 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Implementation Coordinator for Zonal Office and Capacity Building Selection 3 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80483-CS-INDV / IDA / 63370 Management, Coordination, Prior Consultant Open 57,600.00 36,000.00 Signed 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2020-09-08 Procurement of Project and Capacity Building Selection Accountant at RDCU GH-MLGRD-SAFETY NETS-91546-CS-INDV / Component 5: Project Individual Procurement of 1No. Under IDA / 63370 Management, Coordination, Prior Consultant Open 45,000.00 0.00 2018-12-14 2019-02-01 2019-02-22 2019-03-29 2020-09-13 Management Information Implementation and Capacity Building Selection Systems Specialist for RDCU GH-MLGRD-SAFETY Component 5: Project Individual NETS-80508-CS-INDV / / Management, Coordination, Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2020-09-15 Procurement of 1No. PI and Capacity Building Selection Officer for Zonal Office 1 Page 14