Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Above US$ 1,000,000 All 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 1,500,000 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable July 9, 2010 4. Reference to (if any) Project Operational/Procurement Manual: Project Procurement Manual of CJC Project 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million (yes/n o) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contract (Works) for Prior Review Summary 1.86 4 No Post 1st of the NCB contract (Goods) for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold July 9, 2010 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 200,000 and $300,000 (engineering contracts)_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimate Packages Review Comments of d by Bank Assignment Cost (Prior / US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Ethiopia Competitiveness and Job Creation Project PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2017-03-08 2020-11-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P143302 GPN Date: Project Name: Ethiopia Competitiveness and Job Creation Project Loan / Credit No: IDA / 54510, IDA / 62630 Industrial Parks Development Corporation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-IPDC-9345-CW-RFB / Component 2: Support for Single Stage - One 249,175,403. 245,415,26 2018-03- Construction of Kilinto IDA / 54510 Prior Request for Bids Open - International Signed 2015-05-22 2015-08-07 2015-08-07 2015-05-27 2016-11-16 2016-12-13 2017-03-14 2017-01-20 2017-01-20 Industrial Infrastructure Envelope 27 7.83 19 Industrial Park CJC/NCB/W-02/08 / Component 4: Project Pending Single Stage - One 2017-11- Construction of Kindergarten IDA / 54510 Management and Monitoring Post Request for Bids Open - National 600,000.00 0.00 Implementat 2017-02-02 2017-02-04 2017-03-18 2017-04-17 2017-05-22 Envelope 18 for Bole Lemi PAPs and Evaluation ion IPDC/CJC/NCB/W-02/09 / Construction of Livestock Development - Establishing 1 Component 4: Project Pending Poultry enterprise Single Stage - One 2018-04- IDA / 54510 Management and Monitoring Post Request for Bids Open - National 450,000.00 0.00 Implementat 2017-02-26 2017-07-01 2017-08-12 2017-09-11 2017-10-16 Construction of :1 Poultry Envelope 14 and Evaluation ion shed 3 Fattening sheds and grain mills for Kilinto PAPs ET-IPDC-9347-CW-RFB / Component 2: Support for Single Stage - One 157,758,001. 127,382,45 2018-09- Construction of Bole-Lemi IDA / 54510 Prior Request for Bids Open - International Signed 2015-05-05 2015-07-21 2015-07-21 2015-05-10 2015-07-21 2016-10-30 2018-09-03 2017-01-20 2016-01-26 Industrial Infrastructure Envelope 59 3.78 27 Phase II Industrial Park ET-IPDC-165219-NC-DIR / Under Supply and Installation of Component 2: Support for 20,000,000.0 2020-10- IDA / 62630 Prior Direct Selection Direct 0.00 Implementat 2020-04-01 2020-05-05 2020-04-06 2020-09-16 2020-04-23 Power connection to Bole Lemi Industrial Infrastructure 0 20 ion II and Qilinto IPs GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Pending CJC/SH/G-01/09 / Goods for Component 3: Enhancing IZ Request for Single Stage - One IDA / 54510 Post Limited 150,000.00 0.00 Implementati 2017-06-07 2017-06-07 2017-06-07 skill TrainingCenter linkages to the local economy Quotations Envelope on Component 1: Institutional Pending CJC/SH/G-04/09 / Vehicle Request for Single Stage - One IDA / 54510 and Regulatory Framework Post Limited 200,000.00 0.00 Implementati 2017-05-23 2017-05-23 2017-05-23 for EIC 4WD Quotations Envelope and Capacity Building on Component 4: Project Pending CJC/SH/G-02/09 / Uniform Request for Single Stage - One IDA / 54510 Management and Monitoring Post Limited 5,000.00 0.00 Implementati 2017-06-07 2017-06-07 2017-06-07 for PIU drivers and janitors Quotations Envelope and Evaluation on CJC/SH/G-01/10 / Stationary Component 4: Project Pending items, sanitary materials and Request for Single Stage - One IDA / 54510 Management and Monitoring Post Limited 50,000.00 0.00 Implementati 2017-10-24 2017-12-19 2018-06-17 other miscellaneous goods for Quotations Envelope and Evaluation on PIU CJC/SH/S-01/09 / Printing, Component 4: Project Pending Request for Single Stage - One promotional and branding IDA / 54510 Management and Monitoring Post Limited 75,000.00 0.00 Implementati 2017-10-23 2017-12-18 2018-06-16 Quotations Envelope items for IPDC and CJC-PIU and Evaluation on ET-IPDC-41013-GO-RFQ / Component 4: Project Pending Request for Single Stage - One Procurement of Equipment for IDA / 54510 Management and Monitoring Post Limited 50,000.00 0.00 Implementati 2018-01-03 2018-02-28 2018-08-27 Quotations Envelope Bole Lemi KG and Evaluation on CJC/SH/G-03/09 / Component 4: Project Pending Procurement of Furniture for Request for Single Stage - One IDA / 54510 Management and Monitoring Post Limited 70,000.00 0.00 Implementati 2017-10-17 2017-12-12 2018-06-10 Kindergarten at Bole Lemi Quotations Envelope and Evaluation on PAPs and IPDC ET-IPDC-42523-GO-RFQ / Documentation of different Component 1: Institutional Pending industrial parks (Printing, Request for Single Stage - One IDA / 54510 and Regulatory Framework Post Limited 50,000.00 0.00 Implementati 2018-01-23 2018-03-20 2018-09-16 Binding, Scanning, and CD Quotations Envelope and Capacity Building on burning of documents for 9 industrial parks) ET-IPDC-65788-GO-RFQ / Component 1: Institutional Pending Single Stage - One Procurement of Furniture for IDA / 54510 and Regulatory Framework Post Request for Bids Open - National 150,000.00 0.00 Implementati 2018-06-15 2018-06-20 2018-08-01 2018-08-31 2018-10-05 2019-04-03 Envelope IPDC and Capacity Building on ET-IPDC-40618-GO-RFB / Component 1: Institutional Single Stage - One Procurement of IT equipment IDA / 54510 and Regulatory Framework Post Request for Bids Open - National 150,000.00 0.00 Canceled 2018-06-21 2018-06-26 2018-08-07 2018-09-06 2018-10-11 2019-04-09 Envelope and accessories for IPDC and Capacity Building ET-IPDC-205497-GO-RFQ / Audio- Visual ,IT Equipment Pending Component 3: Enhancing IZ Request for Single Stage - One and related goods for IDA / 62630 Post Limited 15,000.00 0.00 Implementati 2020-11-30 2021-01-04 2021-02-03 linkages to the local economy Quotations Envelope Establishing Sustainable on Training Center at Bole Lemi II NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 ET-IPDC-40700-NC-RFP / Component 4: Project Preparation of Documentary Request for Single Stage - Two IDA / 54510 Management and Monitoring Post Open - National 20,000.00 0.00 Canceled 2018-02-15 2018-02-20 2018-04-03 2018-06-16 2018-07-21 2019-01-17 Film for CJC Project Proposals Envelope and Evaluation achievements. ET-IPDC-153598-NC-RFQ / Production of a video and Component 4: Project Under photograph documentary on Request for Single Stage - One IDA / 62630 Management and Monitoring Post Limited 20,000.00 0.00 Implementati 2020-02-15 2020-04-11 2020-10-08 the achievements registered Quotations Envelope and Evaluation on By competiveness and job creation project office (CJCP) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-IPDC-11323-CS-QCBS / Consultancy Service of Detailed Engineering Design & Tender Document Preparation Component 2: Support for Quality And Cost- IDA / 54510 Prior Open - International 6,000,000.00 0.00 Under Review 2014-07-31 2020-04-01 2014-09-25 2014-11-24 2014-12-09 2014-12-19 2015-01-28 2015-04-01 2016-03-31 (LS) and Supervision & Industrial Infrastructure Based Selection Contract Administration (TB) for Bole-Lemi II and Kilinto Industrial Parks CJC/C-04/09 / Consultancy service for training provision Component 3: Enhancing IZ Quality And Cost- Pending IDA / 54510 Post Open - National 200,000.00 0.00 2017-05-19 2017-05-19 2017-05-19 2017-05-19 2017-05-19 2017-05-19 2017-05-19 2017-05-19 for the skills center at bole linkages to the local economy Based Selection Implementation lemi Industrial Park CJC/C-06/09 / Consultancy Component 1: Institutional Quality And Cost- Service for class one IDA / 54510 and Regulatory Framework Post Open - International 400,000.00 0.00 Canceled 2017-06-27 2017-06-27 2017-06-27 2017-06-27 2017-06-27 2017-06-27 2017-06-27 2017-06-27 Based Selection consulting firm and Capacity Building ET-IPDC-40694-CS-QCBS / Component 4: Project Quality And Cost- Under Studying Baseline Survey For IDA / 54510 Management and Monitoring Post Open - International 100,000.00 0.00 2018-01-29 2018-01-18 2018-02-19 2018-04-04 2018-05-02 2018-06-01 2018-07-06 2018-08-10 2019-08-10 Based Selection Implementation CJC Project and Evaluation CJC/C-18/08 / B2B Linkage Component 3: Enhancing IZ Quality And Cost- Pending IDA / 54510 Post Open - National 150,000.00 0.00 2016-08-11 2016-08-11 2016-08-11 2016-08-11 2016-08-11 2016-08-11 2016-08-11 2016-08-11 MARKETING FIRM linkages to the local economy Based Selection Implementation ET-IPDC-64114-CS-QCBS / Component 1: Institutional Consultancy Service for Quality And Cost- IDA / 54510 and Regulatory Framework Post Open - International 300,000.00 320,000.00 Signed 2018-05-25 2019-08-04 2018-06-15 2019-08-06 2018-07-29 2019-09-30 2018-08-26 2019-11-15 2018-09-25 2019-12-16 2018-10-30 2020-01-02 2018-12-04 2019-12-04 Preparation of Road Map and Based Selection and Capacity Building 10 years Strategic Plan ET-IPDC-40726-CS-QCBS / Consultancy Service for Component 2: Support for Quality And Cost- Under IDA / 54510 Post Open - International 50,000.00 0.00 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 Design of Industrial Parks Industrial Infrastructure Based Selection Implementation Housing Project ET-IPDC-73825-CS-LCS / Component 4: Project Competitiveness and Job Least Cost Pending IDA / 54510 Management and Monitoring Post Open - National 40,000.00 0.00 2018-08-21 2018-09-11 2018-10-25 2018-11-22 2018-12-22 2019-01-26 2019-03-02 2019-08-29 Creation Project Financial Selection Implementation and Evaluation Statement Audit ET-IPDC-93273-CS-QCBS / Consultancy Services for provision of Sourcing, Component 3: Enhancing IZ Quality And Cost- IDA / 54510 Post Open - National 200,000.00 186,871.73 Signed 2018-12-31 2019-01-28 2019-01-21 2019-03-06 2019-05-25 2019-04-03 2019-07-05 2019-05-03 2019-08-02 2019-06-07 2019-08-08 2019-07-12 2019-09-06 2020-07-11 Screening , Training and linkages to the local economy Based Selection allocation for Bole Lemi industrial Park ET-IPDC-97530-CS-CQS / Component 1: Institutional Consultant Procurement of Consulting IDA / 54510 and Regulatory Framework Post Qualification Open - International 200,000.00 0.00 Canceled 2019-01-31 2019-02-21 2019-04-06 2019-05-06 2019-06-10 2019-12-07 firm for Pharmaceutical IP- and Capacity Building Selection Kilinto ET-IPDC-108081-CS-CQS / Consultancy procurement for Transaction Advisory Services- Component 1: Institutional Quality And Cost- PPP for Operations and IDA / 62630 and Regulatory Framework Prior Open - International 500,000.00 0.00 Under Review 2019-04-08 2019-05-21 2019-04-29 2019-06-12 2020-05-29 2019-07-10 2020-07-01 2019-08-09 2020-10-14 2019-09-13 2019-10-18 2020-10-17 Based Selection Management of Bole Lemi and and Capacity Building Kilinto Industrial Parks and affiliated services. CJC/ICB/G-07/08 / Component 1: Institutional Quality And Cost- Development of CRM and ERP IDA / 54510 and Regulatory Framework Prior Open - International 1,000,000.00 0.00 Canceled 2017-09-20 2017-09-20 2017-07-19 2017-09-20 2018-08-03 2017-09-20 2017-09-20 2019-01-17 2017-09-20 2017-09-20 2017-09-20 Based Selection for EIC and IPDC and Capacity Building ET-IPDC-110945-CS-QCBS / Component 1: Institutional Supply, Installation and Quality And Cost- IDA / 54510 and Regulatory Framework Prior Open - International 600,000.00 773,418.70 Signed 2019-05-06 2019-10-22 2019-05-27 2019-11-06 2019-07-10 2020-03-09 2019-08-07 2020-04-28 2019-09-06 2020-07-30 2019-10-11 2020-09-27 2019-11-15 2020-09-28 2020-11-14 Commissioning of ERP system Based Selection and Capacity Building for IPDC ET-IPDC-113651-CS-QCBS / Environmental and Social Component 4: Project Quality And Cost- Audit for Bole Lemi II & IDA / 54510 Management and Monitoring Post Open - National 100,000.00 16,230.74 Signed 2019-05-07 2019-05-19 2019-05-28 2019-07-11 2019-08-30 2019-08-08 2019-10-02 2019-09-07 2019-10-18 2019-10-12 2019-10-28 2019-11-16 2019-11-06 2020-11-15 Based Selection Kilinto IPs and sector specific and Evaluation ESSA for each tenant ET-IPDC-113653-CS-QCBS / Component 4: Project Environmental and Social Quality And Cost- IDA / 54510 Management and Monitoring Post Open - National 50,000.00 31,133.02 Signed 2019-05-07 2019-05-23 2019-05-28 2019-07-11 2019-09-09 2019-08-08 2019-10-10 2019-09-07 2019-10-31 2019-10-12 2019-11-11 2019-11-16 2019-11-19 2020-11-15 Audit for B2B linkage Based Selection and Evaluation beneficiary companies ET-IPDC-161854-CS-QCBS / ASSESSMENT ON PREVENTION Component 1: Institutional Consultant Under AND MANAGEMENT OF IDA / 62630 and Regulatory Framework Post Qualification Open 20,000.00 0.00 2020-03-12 2020-03-18 2020-03-27 2020-04-19 2020-04-16 2020-04-26 2020-05-12 2020-08-10 Implementation GENDER BASED VIOLENCE IN and Capacity Building Selection INDUSTRIAL PARKS (IPs) ET-IPDC-162111-CS-QCBS / Consultancy service for Component 3: Enhancing IZ Quality And Cost- Under "Compliance, nomination, IDA / 62630 Post Open - International 450,000.00 0.00 2020-03-12 2020-03-24 2020-03-27 2020-03-24 2020-04-21 2020-05-19 2020-06-03 2020-06-20 2020-07-12 2020-08-08 linkages to the local economy Based Selection Implementation system development and certification support to SMEs" Page 2 ET-IPDC-162127-CS-QCBS / Consultancy Service to Component 3: Enhancing IZ Quality And Cost- Under "Marketing Support to SMEs to IDA / 62630 Post Open - International 300,000.00 0.00 2020-03-12 2020-03-24 2020-03-27 2020-03-24 2020-04-16 2020-05-27 2020-05-14 2020-07-14 2020-05-24 2020-06-10 2020-06-27 2021-03-24 linkages to the local economy Based Selection Implementation enhance B2B linkages with FDIs" ET-IPDC-162119-CS-QCBS / Consultancy service “Training Component 3: Enhancing IZ Quality And Cost- Under IDA / 62630 Post Open - International 350,000.00 0.00 2020-03-12 2020-03-25 2020-03-27 2020-03-24 2020-04-21 2020-05-19 2020-05-29 2020-06-15 2020-07-13 2021-04-09 and Enhancing Productivity of linkages to the local economy Based Selection Implementation SMEs" ET-IPDC-188725-CS-QCBS / Component 4: Project Quality And Cost- Under Document Management IDA / 62630 Management and Monitoring Post Open - National 250,000.00 0.00 2020-08-14 2020-10-12 2020-08-29 2020-10-22 2020-09-27 2020-10-25 2020-11-04 2020-11-24 2020-12-25 2021-12-25 Based Selection Implementation System (DMS) and Evaluation ET-IPDC-188728-CS-QCBS / Feasibility Study and Develop a Strategy on the Storm Water Component 2: Support for Quality And Cost- Under and Effluent Discharge from IDA / 62630 Post Open - National 50,000.00 0.00 2020-08-14 2020-08-31 2020-09-04 2020-10-03 2020-10-31 2020-11-15 2020-12-05 2020-12-27 2021-12-27 Industrial Infrastructure Based Selection Implementation Waste Water Treatment Plants (WWTP) of KIlinto and Bole Lemi II Industrial Parks INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CJC/C-08/09 / Construction Individual Management Consultant for Component 2: Support for Pending IDA / 54510 Post Consultant Limited 100,000.00 0.00 2017-03-02 2017-03-02 2017-03-02 2017-03-02 2017-03-02 Bole Lemi 2 and Killinto Industrial Infrastructure Implementation Selection Industrial Parks Component 4: Project Individual CJC/H-08/09 / Environment Pending IDA / 54510 Management and Monitoring Post Consultant Open 100,000.00 0.00 2017-02-10 2017-02-10 2017-02-10 2017-02-10 2017-02-10 Specialist Implementation and Evaluation Selection CJC/C-09/09 / Individual Component 4: Project Individual Consultant -Data Analyst- ( Pending IDA / 54510 Management and Monitoring Post Consultant Limited 5,000.00 0.00 2017-04-15 2017-04-15 2017-04-15 2017-04-15 2017-04-15 organizing and documenting Implementation and Evaluation Selection procurement documents). Individual CJC/C-07/09 / Skill Training Component 3: Enhancing IZ Pending IDA / 54510 Post Consultant Limited 50,000.00 0.00 2017-02-24 2017-02-24 2017-02-24 2017-02-24 2017-02-24 Coordinator linkages to the local economy Implementation Selection Component 1: Institutional Individual ET-IPDC-19013-CS-INDV / Under IDA / 54510 and Regulatory Framework Post Consultant Limited 100,000.00 0.00 2017-06-01 2017-06-30 2017-07-21 2017-08-25 2018-08-25 National Financial Consultant Implementation and Capacity Building Selection ET-IPDC-19014-CS-INDV / Component 4: Project Individual Under Recruitment of assistant IDA / 54510 Management and Monitoring Post Consultant Open 25,000.00 0.00 2017-06-24 2017-07-20 2017-08-12 2017-09-02 2017-10-07 2018-10-07 Implementation Project Engineer for Kilinto and Evaluation Selection ET-IPDC-19016-CS-INDV / Component 4: Project Individual Recruitment of assistant Under IDA / 54510 Management and Monitoring Post Consultant Open 25,000.00 0.00 2017-06-24 2017-08-12 2017-09-02 2017-10-07 2018-10-07 Project Engineer for Bole Lemi Implementation and Evaluation Selection II CJC/M-03/07 / Individual Component 4: Project Individual Consultant -Procurement IDA / 54510 Management and Monitoring Prior Consultant Open 100,000.00 0.00 Canceled 2017-04-15 2017-04-15 2017-09-25 2017-04-15 2017-04-15 2017-04-15 Specialist and Evaluation Selection Component 4: Project Individual ET-IPDC-31289-CS-INDV / Under IDA / 54510 Management and Monitoring Prior Consultant Open 100,000.00 0.00 2017-01-12 2017-10-26 2017-03-02 2017-03-23 2017-04-27 2017-10-24 Procurement Specialist Implementation and Evaluation Selection CJC/SSS/C-01/10 / Audit Component 4: Project Services for CJC project Under IDA / 54510 Management and Monitoring Post Direct Selection Direct 20,000.00 0.00 2017-10-27 2017-11-06 2018-01-10 2018-07-09 Account for the year ended Implementation and Evaluation July 8, 2017. ET-IPDC-40708-CS-INDV / Component 1: Institutional Individual National Procurement IDA / 54510 and Regulatory Framework Prior Consultant Open 50,000.00 17,225.54 Under Review 2018-01-10 2018-02-08 2018-02-28 2018-03-21 2018-04-14 2018-04-25 2018-10-17 2018-10-22 Consultant for IPDC and Capacity Building Selection ET-IPDC-40715-CS-INDV / Component 4: Project Individual Under Recruitment of IDA / 54510 Management and Monitoring Post Consultant Open 15,000.00 0.00 2018-01-15 2019-01-30 2018-03-05 2019-01-30 2018-03-26 2018-04-30 2018-10-27 Implementation Communication Specialist and Evaluation Selection ET-IPDC-40737-CS-INDV / Component 1: Institutional Individual National Consultant for the IDA / 54510 and Regulatory Framework Post Consultant Open 100,000.00 0.00 Canceled 2018-02-27 2018-04-17 2018-05-08 2018-06-12 2018-12-09 formulation of SPV at IPDC and Capacity Building Selection ET-IPDC-49425-CS-INDV / Component 4: Project Individual Pending Contract Administration and IDA / 54510 Management and Monitoring Post Consultant Open 50,000.00 0.00 2018-03-15 2018-05-03 2018-05-24 2018-06-28 2019-06-27 Implementation Claim Consultant and Evaluation Selection ET-IPDC-64119-CS-INDV / Component 4: Project Individual Recruitment of Assistant IDA / 54510 Management and Monitoring Prior Consultant Open 20,000.00 1,159.65 Signed 2018-06-15 2018-08-13 2018-08-03 2019-05-06 2018-08-24 2019-11-19 2018-09-28 2019-06-06 2019-03-27 Procurement and Evaluation Selection ET-IPDC-81199-CS-INDV / Component 4: Project Individual Employment of Procurement IDA / 54510 Management and Monitoring Prior Consultant Limited 35,000.00 0.00 Canceled 2018-10-19 2018-11-02 2018-10-24 2018-11-02 2018-11-14 2018-12-19 2019-06-17 Specialist for CJCP and Evaluation Selection ET-IPDC-82663-CS-INDV / Individual Consultant to Support ERP, CRM tasks for Component 1: Institutional Individual Pending Ethiopian Investment IDA / 54510 and Regulatory Framework Post Consultant Direct 100,000.00 0.00 2018-11-02 2018-11-12 2018-12-03 2019-01-07 2019-07-06 Implementation Commission (EIC) and and Capacity Building Selection Industrial Parks Development Corporation (IPDC) ET-IPDC-81199-CS-INDV-2 Component 4: Project Individual Under / Hiring Procurement IDA / 54510 Management and Monitoring Prior Consultant Limited 35,000.00 0.00 2019-01-31 2019-02-05 2019-02-26 2019-04-02 2019-09-29 Implementation Management Specialist and Evaluation Selection Page 3 ET-IPDC-18009-CS-INDV / Component 1: Institutional Individual International Individual IDA / 54510 and Regulatory Framework Prior Consultant Limited 150,000.00 0.00 Canceled 2017-06-01 2017-06-06 2017-06-27 2017-08-01 2018-08-01 Consultant for Pharmaceutical and Capacity Building Selection Industrial Park-- EIC ET-IPDC-98910-CS-INDV / Component 1: Institutional Individual Pending Redesign and Modification of IDA / 54510 and Regulatory Framework Post Consultant Open 30,000.00 0.00 2019-02-28 2019-04-18 2019-05-09 2019-06-13 2019-12-10 Implementation IPDC Website and Capacity Building Selection ET-IPDC-98911-CS-INDV / Component 1: Institutional Individual Under Hiring of Transformational IDA / 54510 and Regulatory Framework Post Consultant Limited 100,000.00 0.00 2019-02-28 2019-03-05 2019-03-26 2019-04-30 2019-10-27 Implementation advisor for IPDC and Capacity Building Selection ET-IPDC-108077-CS-INDV / Component 1: Institutional Individual Hiring of International IDA / 54510 and Regulatory Framework Post Consultant Limited 150,000.00 0.00 Canceled 2019-04-01 2019-04-06 2019-04-27 2019-06-01 2019-11-28 Individual Consultant for and Capacity Building Selection Pharmaceutical IP -Kilinto ET-IPDC-108085-CS-INDV / Hiring of International Individual Component 3: Enhancing IZ Individual Consultant (TA) for IDA / 62630 Post Consultant Open 100,000.00 8,000.00 Signed 2019-04-01 2019-06-17 2019-05-20 2019-09-10 2019-06-10 2019-10-08 2019-07-15 2019-10-10 2020-01-11 linkages to the local economy SME support under B2B Selection linkage ET-IPDC-64132-CS-INDV / Component 4: Project Individual Recruitment of Gender IDA / 54510 Management and Monitoring Post Consultant Open 20,000.00 18,914.03 Signed 2019-05-20 2019-05-31 2019-07-08 2019-07-01 2019-07-29 2019-08-01 2019-09-02 2019-08-01 2020-02-29 Specialist and Evaluation Selection ET-IPDC-113658-CS-INDV / Hiring of individual Individual Component 2: Support for Consultant for handing over IDA / 62630 Post Consultant Open 40,000.00 19,587.70 Signed 2019-10-28 2019-08-21 2019-12-16 2020-02-18 2020-01-06 2019-02-21 2020-02-10 2020-03-01 2020-08-08 Industrial Infrastructure of Bole Lemi II to establish Selection operating procedures ET-IPDC-129680-CS-INDV / Hiring of individual Individual Component 2: Support for Consultant for handing over IDA / 62630 Post Consultant Open 40,000.00 26,410.29 Signed 2019-09-01 2019-08-21 2019-10-20 2020-03-03 2019-11-10 2020-03-10 2019-12-15 2020-03-15 2020-06-12 Industrial Infrastructure of Kilinto IP to establish Selection operating procedures ET-IPDC-153594-CS-INDV / Individual Consultant for Component 1: Institutional Individual assessing the need for Under IDA / 62630 and Regulatory Framework Post Consultant Open 20,000.00 0.00 2020-01-24 2020-02-21 2020-02-23 2020-03-04 2020-03-24 2020-05-23 affordable and accessible Implementation and Capacity Building Selection child care Programs In industrial parks ET-IPDC-158064-CS-INDV / Component 1: Institutional Individual Recruitment of Senior Adviser IDA / 62630 and Regulatory Framework Post Consultant Limited 24,000.00 28,308.82 Signed 2020-02-10 2020-02-24 2020-02-15 2020-02-25 2020-03-07 2020-03-01 2020-04-11 2020-03-01 2020-10-08 to the IPDC CEO as part of and Capacity Building Selection Capacity Building. Component 4: Project Individual ET-IPDC-163913-CS-INDV / Under IDA / 62630 Management and Monitoring Post Consultant Open 20,000.00 0.00 2020-03-16 2020-03-24 2020-04-19 2020-05-04 2020-05-24 2020-11-20 Social Development Specialist Implementation and Evaluation Selection ET-IPDC-180941-CS-QCBS / Component 4: Project Individual Consultancy Services for study Under IDA / 62630 Management and Monitoring Post Consultant Open 10,000.00 0.00 2020-08-14 2020-10-07 2020-09-12 2020-09-19 2020-10-17 2021-04-15 of ESMF for Bole Lemi II & Implementation and Evaluation Selection Kilinto IPs ET-IPDC-197653-CS-INDV / Component 4: Project Individual Under Procurement Management IDA / 62630 Management and Monitoring Prior Consultant Open 24,000.00 0.00 2020-10-08 2020-10-16 2020-11-06 2020-11-13 2020-11-30 2021-06-30 Implementation Specialist and Evaluation Selection Component 1: Institutional Individual ET-IPDC-205548-CS-INDV / Pending IDA / 62630 and Regulatory Framework Post Consultant Limited 35,000.00 0.00 2020-11-29 2020-12-04 2020-12-25 2021-01-29 2021-08-27 Human Resource Advisor Implementation and Capacity Building Selection ET-IPDC-205551-CS-INDV / Component 1: Institutional Individual Communication and Pending IDA / 62630 and Regulatory Framework Post Consultant Limited 35,000.00 0.00 2020-11-29 2020-12-04 2020-12-14 2021-01-14 2021-08-12 Knowledge Management Implementation and Capacity Building Selection Specialist Page 4