Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: May 20, 2017 2. Date of General Procurement Notice: Oct. 10, 2016 3. Period covered by this procurement plan: The whole project period II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) 4 million 2. NCB (Goods) 4 million 3. ICB (Works) 15 million 4. NCB (Works) 15 million 5. (Non-Consultant Services) 4 million [Add other methods if necessary] 2. Prequalification. _Not applicable_. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Not applicable 5. Any Other Special Procurement Arrangements: Advance procurement and retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 0 0 N/A N/A the ICB (Works) Summary of 0 0 N/A N/A July 9, 2010 the ICB (Goods) Summary of 150.47 10 No Prior / Post the NCB (Works) Summary of 50.40 12 No Prior / Post the NCB (Goods) Summary of 0 0 N/A N/A the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) US$2 million 2. Single Source (Firms) US$1 million 3. Individual US$0.4 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 0.51 1 Post number of contracts that will be let under QCBS Summary of 1.82 12 Post number of contracts that will be let under other methods July 9, 2010 PROCUREMENT China : Three Gorges Modern Logistics Center Infrastructure Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2018-05-18 2019-08-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153473 GPN Date: Project Name: Three Gorges Modern Logistics Center Infrastructure Project Loan / Credit No: IBRD / 87660 Executing Agency(ies): Yi Chang PMO WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GK-C1 / Construction Baiyang Port and operations Single Stage - One Works for 8#-11# Berths and IBRD / 87660 Prior Request for Bids Open - National 0.00 12,851,093.41 Signed Area Envelope 7#-11# Land Territories GK-C2 / Road, architectural, port, electric, communication, water supply Under Baiyang Port and operations Single Stage - One & drainage, environmental IBRD / 87660 Prior Request for Bids Open - National 27,220,000.00 0.00 Implementati 2019-04-25 2019-04-30 2019-05-30 2019-06-06 2019-07-04 2020-12-25 Area Envelope protection works and on temporary works in Storage Yard 7#, 12# and 13#. WL-C3 / Intelligent Cargo Distributing Center: 1 Building (21,000m2) and Pending electric, communications, Single Stage - One IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 9,670,000.00 0.00 Implementati 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 2020-03-28 water supply & drainage, Envelope on fire-fighting and environmental protection, etc in Building. DJ-C1 / Roadbed (earthwork & foundation treatment), pavement (carriageway, sidewalk & Pending Transport Connection Single Stage - One auxiliaries), traffic, culverts, IBRD / 87660 Prior Request for Bids Open - National 7,400,000.00 0.00 Implementati 2019-08-16 2019-08-21 2019-10-02 2019-11-01 2019-12-06 2020-06-03 Infrastructure Envelope lighting, integrated pipe on network and drainage in Guihu Road & 2nd Songgang Road. WL-C4 / 1. Containing Devaning & Loading Warehouse: 2 buildings (10,600m2). 2. Foodstuff Warehouse: 3 buildings Pending (19,300m2). 3. Processing Single Stage - One IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 14,940,000.00 0.00 Implementati 2019-08-15 2019-08-20 2019-10-01 2019-10-31 2019-12-05 2020-06-02 Factory: 2 buildings Envelope on (4,600m2). 4. Parking Lot: Road (12,900m2). 5.W1 Container Yard. 6. W1~3# Substation(1800m2). 7.Earthwor GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 WL-G1 / Comprehensive Area: 4 electronic car weighers (150t), 2 tyre cranes (30t), 2 tyre cranes Pending (16t), 1 processing equipment Single Stage - One IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 1,810,000.00 0.00 Implementati 2019-08-16 2019-08-21 2019-10-02 2019-11-01 2019-12-06 2020-06-03 of standard factories, 4 Envelope on bridge cranes (16t-16.5m), 1 electric single-beam crane (5t- 16.5m) and 1 machines maintenance device. WL-G2 / Comprehensive Area: 5 forklifts (5t), 19 forklifts (3t), 20 forklifts (2t), 53 load/unload cab Pending Single Stage - One aprons, 4 motor tractors IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 2,160,000.00 0.00 Implementati 2019-07-16 2019-07-21 2019-09-01 2019-10-01 2019-11-05 2020-05-03 Envelope (Q45), 6 motor tractors on (Q20), 8 flat-bed trailers (PC 40), 12 flat-bed trailers (P20) and 8 vans. GK-G6 / 30 Mobile Belt Conveyors L=15m; 144m Pending Belt Conveyors Baiyang Port and operations Single Stage - One IBRD / 87660 Post Request for Bids Open - National 734,200.00 0.00 Implementati 2019-07-30 2019-08-04 2019-09-03 2019-10-03 2019-11-07 2020-05-05 Area Envelope on B1200, V2.0m/s, 2 electric winches 3T GK-C3 / 1360m windproof Pending Baiyang Port and operations Request for Single Stage - One and dust suppression net, IBRD / 87660 Post Open - National 198,200.00 0.00 Implementati 2019-08-21 2019-10-16 2020-04-13 Area Quotations Envelope 8m high on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NL-S7 / To develop research about "Business Quality And Cost- Open - Under Model & Operation Schedule IBRD / 87660 Capacity Building Prior 538,000.00 0.00 2018-07-19 2018-08-09 2018-08-30 2018-09-06 2018-09-13 2018-09-30 2018-10-28 2020-04-20 Based Selection International Implementation of Baiyang Port & Logistics Park" INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NL-S1 / To provide support about Architectural Individual Pending Engineering to Project Office IBRD / 87660 Capacity Building Post Consultant Open 29,400.00 0.00 2019-06-15 2019-08-03 2019-08-24 2019-09-28 2020-03-26 Implementation during implementation Selection period. Page 2 NL-S2 / To provide support about Port & Harbor Individual Pending Engineering to Project Office IBRD / 87660 Capacity Building Post Consultant Open 22,000.00 0.00 2019-06-15 2019-08-03 2019-08-24 2019-09-28 2020-03-26 Implementation during implementation Selection period. Page 3