PROCUREMENT PLAN (Textual Part) Project information: [Congo, Republic of] [Statistics Capacity Building Project] [P133731] Project Implementation agency: [Statistics Capacity Building Project] Date of the Procurement Plan: [28 Avril 2017] Period covered by this Procurement Plan: [November 29, 2016 – 31 December 2017] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in not applicable, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable Works: [is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. PROCUREMENT Congo, Republic of : CG-Statistics Capacity Building Project PLAN General Information Country: Congo, Republic of Bank’s Approval Date of the Original Procurement Plan: 2017-06-06 2020-08-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133731 GPN Date: Project Name: CG-Statistics Capacity Building Project Loan / Credit No: IDA / 55000, IDA / V0870, IBRD / 88510, IDA / V1720 Executing Agency(ies): CG-Statistics Capacity Building Project WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Contract Description Component Review Type Method Document Amount Amount qualification Document / Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Completion Type (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Institutional PSTAT-045-T-AON-20 / Development, Human Single Stage - One En attente Travaux de construction du IBRD / 88510 A priori Appel d'offres Open - National 5,172,414.00 0.00 2020-03-20 2020-03-25 2020-05-06 2020-06-05 2020-07-10 2021-01-06 Resources and Envelope d'exécution complexe INS -CASP Organizational Structure GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PSTAT-014-F-ED-17 / Component 1: Institutional Acquisition du logiciel Passation de Development, Human PHOENIX pour les prix ( IDA / 55000 A priori marché de gré à Direct 30,000.00 39,054.64 Signé 2017-07-30 2017-08-04 2017-09-08 2017-08-11 2018-03-07 Resources and AFRISTAT)_ Regularisation, gré Organizational Structure contrat déjà signé PSTAT-030-F-ED-17 / Component 1: Institutional Acquisition des tablettes et Passation de Development, Human de leurs accessoires IDA / 55000 A priori marché de gré à Direct 999,129.00 999,129.00 Signé 2017-12-01 2017-12-06 2018-01-10 2017-12-15 2018-07-09 Resources and (Solution solaire, Micro SD gré Organizational Structure Card et Clé )_ UNOPS PSTAT-012-F-AOI-17 / Acquisition des tablettes Component 1: Institutional pour le Recensement Development, Human Open - Single Stage - One IDA / 55000 A priori Appel d'offres 1,000,000.00 0.00 Annulé 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Général de la Population et Resources and International Envelope de l'Habitation ( RGPH) et Organizational Structure des enquêtes de l'INS. PSTAT-013-F-AON-17 / Équipements de matériels informatiques pour les sectoriels, DD statistique, Component 1: Institutional l'Assistance technique de Development, Human Single Stage - One l'INS , gestion de ressources IDA / 55000 A priori Appel d'offres Open - National 700,000.00 0.00 Annulé 2017-10-20 2017-10-25 2017-12-06 2018-01-05 2018-02-09 2018-08-08 Resources and Envelope des humaines de l'INS, Prix Organizational Structure et de l'UCP , et les équipements pour le système d'archivage de l'INS et du PSTAT PSTAT-030-F-DIR-18 / Acquisition de 45 téléphones Component 2: Data Passation de satellitaires et de 45 cartes IDA / V0870 production, Dissemination A posteriori marché de gré à Direct 81,000.00 72,151.56 Achevé 2018-07-24 2018-06-12 2018-07-29 2018-06-01 2018-09-02 2018-06-13 2019-03-01 2018-07-06 SIM pour les enquêtes de and the use of Statistics gré l'INS PSTAT-27-F-CF-18 / Component 2: Data Acquisition de mobilier de Single Stage - One IDA / V1720 production, Dissemination A posteriori Demande de prix Limited 73,000.00 60,674.66 Achevé 2018-12-29 2018-10-31 2019-02-23 2018-11-15 2019-08-22 2018-12-21 bureau pour les bureaux de Envelope and the use of Statistics l'INS et du BCR PSTAT-19-F-DC-18 / Component 2: Data Acquisition de matériels et Single Stage - One IDA / V0870 production, Dissemination A posteriori Demande de prix Limited 50,000.00 0.00 Annulé 2019-01-02 2019-02-27 2019-08-26 équipement informatique Envelope and the use of Statistics pour le RGPH et le REGEC Page 1 PSTAT-057-SASC-18 / Acquisition de 15 groupes Component 2: Data électrogènes et accessoires Single Stage - One IDA / V0870 production, Dissemination A posteriori Demande de prix Limited 7,500.00 0.00 Annulé 2018-12-29 2019-02-23 2019-08-22 d'installation pour le Envelope and the use of Statistics dénombrement pilote (RGPH) et REGEC PSTAT-020-CF-F-19 / Acquisition de 100 GPS Component 1: Institutional pour les enquêtes de Development, Human Single Stage - One IBRD / 88510 A posteriori Demande de prix Limited 72,727.00 47,166.94 Signé 2019-09-04 2019-07-11 2019-10-30 2019-07-29 2020-04-27 l'Institut National de la Resources and Envelope Statistique ( REGEC, Organizational Structure RGPH) PSTAT-024-CF-F-19 / Acquisition de fourniture de Component 3: Project Single Stage - One IBRD / 88510 A posteriori Demande de prix Limited 18,181.00 0.00 Annulé 2019-10-05 2019-11-30 2020-05-28 bureau et de consommables Management Envelope informatique pour l'UCP PSTAT-021-CF-F-19 / Acquisition de matériels Component 1: Institutional informatiques pour les Development, Human Single Stage - One IBRD / 88510 A posteriori Demande de prix Limited 99,000.00 68,552.06 Signé 2019-10-05 2019-11-08 2019-11-30 2019-11-06 2020-05-28 services statistiques Resources and Envelope sectoriels et personnels Organizational Structure additionnels PSTAT-034-F-AON-19 / Acquisition matériel et Component 2: Data équipement informatiques Single Stage - One En cours IBRD / 88510 production, Dissemination A posteriori Appel d'offres Open - National 200,000.00 0.00 2019-12-20 2020-02-05 2019-12-25 2020-02-17 2020-02-05 2020-03-10 2020-03-06 2020-04-10 2020-10-07 pour les directions Envelope d'exécution and the use of Statistics départementales de la statistique ( DDS) PSTAT-036F-DC-20 / Component 1: Institutional Acquisition et installation Development, Human Single Stage - One IBRD / 88510 A posteriori Demande de prix Limited 50,000.00 38,382.12 Signé 2020-01-11 2020-01-09 2020-03-07 2020-01-27 2020-09-03 groupe électrogène du Resources and Envelope nouveau site de l'INS Organizational Structure PSTAT-037F-DC-20 / Component 2: Data Acquisition matériels Single Stage - One IBRD / 88510 production, Dissemination A posteriori Demande de prix Open - National 10,000.00 11,903.81 Signé 2020-01-19 2020-03-15 2020-02-03 2020-09-11 aratoires pour la Envelope and the use of Statistics cartographie PSTAT-038F-DC-20 / Component 2: Data Single Stage - One Acquisition de 90 gilets de IBRD / 88510 production, Dissemination A posteriori Demande de prix Open - National 12,000.00 4,004.95 Signé 2020-01-19 2020-03-15 2020-02-03 2020-09-11 Envelope sauvetage/ cartographie and the use of Statistics PSTAT-039F-DC-20 / Component 2: Data Single Stage - One Acquisition de 320 matelas IBRD / 88510 production, Dissemination A posteriori Demande de prix Open - National 5,300.00 7,767.18 Signé 2020-01-19 2020-03-15 2020-02-03 2020-09-11 Envelope / cartographie and the use of Statistics PSTAT-040F-DC-20 / Component 2: Data Acquisition de 80 petits Single Stage - One IBRD / 88510 production, Dissemination A posteriori Demande de prix Open - National 16,000.00 30,085.58 Signé 2020-01-19 2020-03-15 2020-02-12 2020-09-11 groupes électrogènes et Envelope and the use of Statistics convertisseur chargeur PSTAT-041F-DC-20 / Component 2: Data Single Stage - One Acquisitionde 320 kit IBRD / 88510 production, Dissemination A posteriori Demande de prix Open - National 17,200.00 6,580.87 Signé 2020-01-19 2020-03-15 2020-02-03 2020-09-11 Envelope camping house and the use of Statistics PSTAT-042F-DC-20 / Component 2: Data Acquisition materiel et Single Stage - One En cours IBRD / 88510 production, Dissemination A posteriori Demande de prix Open - National 35,000.00 0.00 2020-01-19 2020-03-15 2020-09-11 fourniture de bureau / Envelope d'exécution and the use of Statistics cartographie PSTAT-052-F-DC-20 / Component 3: Project Single Stage - One En attente IBRD / 88510 A posteriori Demande de prix Limited 43,000.00 0.00 2020-05-20 2020-07-15 2021-01-11 mobilier de bureau Management Envelope d'exécution PSTAT-053-F-DC-20 / Component 3: Project Single Stage - One En attente Fourniture de bureau pour IBRD / 88510 A posteriori Demande de prix Limited 34,000.00 0.00 2020-04-15 2020-06-10 2020-12-07 Management Envelope d'exécution UCP Component 1: Institutional PSTAT-048-F-DC-20 / Development, Human Single Stage - One En attente acquisition de 120 motos IBRD / 88510 A posteriori Demande de prix Limited 176,000.00 0.00 2020-04-14 2020-06-09 2020-12-06 Resources and Envelope d'exécution pour le REGEC Organizational Structure Page 2 Component 1: Institutional PSTAT-063-F-DC-20 / Development, Human Single Stage - One En attente Materiel pour enquête unité IBRD / 88510 A posteriori Demande de prix Limited 25,000.00 0.00 2020-03-25 2020-05-20 2020-11-16 Resources and Envelope d'exécution standards Organizational Structure NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PSTAT-003-F-ED-17 / Contrat maintenance et entretien matériel Passation de Component 3: Project informatique_ IDA / 55000 A priori marché de gré à Direct 7,200.00 0.00 Annulé 2017-06-18 2017-06-23 2017-07-28 2018-01-24 Management Renouvellement du contrat ( gré MAGES D'ALLIANCES TAMA) PSTAT-004-F-ED-17 / Contrat de connexion internet. Recrutement d'une Passation de société chargée de la Component 3: Project IDA / 55000 A priori marché de gré à Direct 60,000.00 0.00 Annulé 2017-06-25 2017-06-30 2017-08-04 2018-01-31 connexion internet et de la Management gré fourniture de l'accès internet par fibre optique pour l'UCP et le BCR PSTAT-001 BIS- SASC- ED-17 / Renouvellement du contrat de service de Passation de gardiennage ( SUBLIME Component 3: Project IDA / 55000 A priori marché de gré à Direct 34,243.00 32,136.39 Achevé 2017-01-09 2018-03-19 2017-01-14 2017-02-18 2017-01-13 2017-08-17 2017-12-29 Congo) - Régularisation Management gré dans STEP de l'ANO réçu depuis 11 janvier 2017_ contrat signé hors STEP PSTAT-006 BIS- SASC-ED- 17 / Contrat du notaire pour la rédaction des Component 1: Institutional contrats des bourses des Passation de Development, Human étudiants ( Maître IDA / 55000 A priori marché de gré à Direct 13,025.00 10,912.92 Achevé 2017-03-07 2017-03-12 2017-04-16 2017-04-04 2017-10-13 2017-05-05 Resources and MOKOKO) _ Régularisation gré Organizational Structure dans STEP de l'ANO réçu depuis mars 2017 hors STEP PSTAT-002-BIS-SASC-ED- 17 / Renouvellement du contrat d'entretien des Passation de Component 3: Project locaux de l'UCP ( Service IDA / 55000 A priori marché de gré à Direct 9,600.00 8,418.00 Achevé 2017-01-08 2017-09-14 2017-01-13 2018-03-15 2017-02-17 2017-01-13 2017-08-16 2017-12-30 Management ALAN) _ Régularisation gré dans STEP de l'ANO réçu depuis le 11 janvier 2017 hors STEP PSTAT-002-F-ED-17 / Contrat entretien des Passation de locaux_ Renouvellement du Component 3: Project IDA / 55000 A priori marché de gré à Direct 9,600.00 0.00 Annulé 2017-06-25 2017-06-30 2017-08-04 2018-01-31 contrat d'entretien des Management gré locaux de l'UCP ( SERVICE ALAN) PSTAT-001-F-ED-17 / Contrat de gardiennage- Passation de Component 3: Project Renouvellement du contrat IDA / 55000 A priori marché de gré à Direct 34,243.00 0.00 Annulé 2017-06-25 2017-06-25 2017-06-25 2017-06-25 Management de gardiennage pour l'UCP gré et le BCR ( Sublime Congo) PSTAT-006-F-ED-17 / Contrat Notaire_ Passation de Recrutement d'un notaire Component 3: Project IDA / 55000 A priori marché de gré à Direct 13,025.00 0.00 Annulé 2017-06-25 2017-06-30 2017-08-04 2018-01-31 pour la rédaction des Management gré contrats des bourses des étudiants PSTAT-003-BIS-F-ED-17 / Renouvellement du contrat Passation de Component 3: Project de la maintenance - IDA / 55000 A priori marché de gré à Direct 7,200.00 0.00 Annulé 2016-01-04 2016-01-04 2016-01-04 2016-01-04 2016-01-04 2016-01-04 Management entretien du materiel gré informatique Page 3 PSTAT-004-BIS- F-ED-17 / Recrutement d'une société Passation de Component 3: Project (CONGO TELECOM) pour IDA / 55000 A priori marché de gré à Direct 35,373.00 0.00 Annulé 2017-01-11 2017-01-11 Management la connexion internet de gré l'UCP et le le BCR PSTAT-017BIS-SASC-17 / Recrutement d'une société Component 3: Project Single Stage - One IDA / 55000 A posteriori Demande de prix Limited 14,400.00 14,054.20 Achevé 2018-01-02 2017-02-15 2018-02-27 2017-05-03 2018-08-26 2017-09-11 pour l'entretien du groupe Management Envelope électrogène et split PSTAT-007-F-CF-17 / Component 2: Data Single Stage - One Impression de l'annuaire IDA / 55000 production, Dissemination A posteriori Demande de prix Limited 20,000.00 14,054.20 Achevé 2018-01-03 2017-02-15 2018-02-28 2017-05-03 2018-08-27 2017-09-11 Envelope statistique 2014 du Congo and the use of Statistics PSTAT-017-F-17 / Recrutement d'une société Component 3: Project Single Stage - One pour l'entretien du groupe IDA / 55000 A posteriori Demande de prix Limited 14,400.00 5,189.24 Achevé 2018-01-03 2017-05-11 2018-02-28 2017-07-06 2018-08-27 2018-07-05 Management Envelope électrogène et des split de l'UCP PSTAT-01-ASC-ED-18 / Acquisition du logiciel Passation de TOM2PRO version multi- Component 3: Project IDA / V0870 A posteriori marché de gré à Direct 31,000.00 28,881.02 Achevé 2018-03-28 2018-03-14 2018-04-02 2017-09-11 2018-05-07 2018-03-11 2018-11-03 2018-04-25 projets et Mise en réseau Management gré sur 3 ordinateurs ( TOMATE) PSTAT-032-SASC-DIR-18 / Component 1: Institutional Renouvellement de la police Passation de Development, Human assurance de 16 véhicules ( IDA / V0870 A posteriori marché de gré à Direct 73,044.00 64,237.48 Signé 2018-07-04 2018-07-06 2018-07-09 2018-08-13 2018-07-10 2019-02-09 Resources and INS et UCP) ( ALLIANZ gré Organizational Structure CONGO) PSTAT-033-SASC-DIR-18 / Recrutement d'une société Component 1: Institutional pour l'Entretien des locaux Development, Human Single Stage - One IBRD / 88510 A posteriori Demande de prix Limited 27,000.00 0.00 Annulé 2018-08-05 2018-08-30 2018-09-30 2019-03-29 loués par le PSTAT pour Resources and Envelope l'Institut National de la Organizational Structure Statistique PSTAT-034-SASC-DIR-18 / Recrutement d'une entreprise pour services Component 1: Institutional d'Entretien des split et le Development, Human Single Stage - One IBRD / 88510 A posteriori Demande de prix Limited 12,000.00 0.00 Annulé 2019-01-02 2019-02-27 2019-08-26 groupe électrogène des Resources and Envelope bureaux loués par le Organizational Structure PSTAT pour l'Institut National de la Statistique PSTAT-056-SASC-DIR-18 / Component 1: Institutional Renouvellement du contrat Passation de Development, Human de services de gardiennage IBRD / 88510 A posteriori marché de gré à Direct 42,164.00 15,080.71 Signé 2019-02-27 2018-12-31 2019-03-04 2018-12-31 2019-04-08 2019-01-02 2019-10-05 Resources and des locaux du PSTAT et gré Organizational Structure des deux sites de l'INS PSTAT-058-SASC-DIR-18 / Renouvellement du contrat Passation de Component 3: Project pour l'entretien et IBRD / 88510 A posteriori marché de gré à Direct 7,200.00 2,588.48 Signé 2019-01-28 2018-12-31 2019-02-02 2018-12-31 2019-03-09 2019-01-04 2019-09-05 Management maintenance du parc gré informatique du PSTAT PSTAT-059-SASC-DIR-18 / Passation de Renouvellement du contrat Component 3: Project IBRD / 88510 A posteriori marché de gré à Direct 9,600.00 3,026.40 Signé 2019-01-28 2018-12-31 2019-02-02 2018-12-31 2019-03-09 2019-01-02 2019-09-05 de l'entretien des locaux du Management gré PSTAT PSTAT-010-CF- SASC-19 / Component 1: Institutional Contrat d'assurance des Development, Human Single Stage - One véhicules de l'UCP et des IBRD / 88510 A posteriori Demande de prix Limited 9,000.00 0.00 Annulé 2019-07-05 2019-08-30 2020-02-26 Resources and Envelope véhicules affectés à l'INS Organizational Structure pour les enquêtes PSTAT-010-ED- SASC-19 / Component 1: Institutional Contrat d'assurance Passation de Development, Human véhicules pour les de l'UCP IBRD / 88510 A posteriori marché de gré à Direct 9,000.00 5,100.73 Signé 2019-04-30 2019-04-01 2019-05-05 2019-04-01 2019-06-09 2019-04-24 2019-12-06 Resources and et les véhicules affectés à gré Organizational Structure l'INS Page 4 PSTAT-018-ED-SASC- 19 / Passation de Renouvellement du contrat Component 3: Project IBRD / 88510 A posteriori marché de gré à Direct 4,500.00 4,232.64 Signé 2019-06-30 2019-05-31 2019-07-05 2019-05-31 2019-08-09 2019-05-31 2020-02-05 de services d'entretien des Management gré locaux de l'UCP PSTAT PSTAT-019-ED-SASC- 19 / Passation de Renouvellement du contrat Component 3: Project IBRD / 88510 A posteriori marché de gré à Direct 7,000.00 7,003.16 Signé 2019-06-30 2019-05-31 2019-07-05 2019-05-31 2019-08-09 2019-05-31 2020-02-05 de service de gardiennage Management gré de l'UCP PSTAT PSTAT-020-ED-SASC- 19 / Renouvellement du contrat Passation de Component 3: Project de prestation de service IBRD / 88510 A posteriori marché de gré à Direct 3,600.00 3,532.31 Signé 2019-06-30 2019-05-31 2019-07-05 2019-05-31 2019-08-09 2019-05-31 2020-02-05 Management d'entretien et maintenance gré informatique PSTAT-022-CF-SASC-19 / Impression des manuels de Component 2: Data Single Stage - One productions et diffusions IBRD / 88510 production, Dissemination A posteriori Demande de prix Limited 63,636.00 53,132.96 Signé 2019-09-04 2019-06-21 2019-10-30 2019-07-10 2020-04-27 Envelope statistiques et des rapports and the use of Statistics d'études PSTAT-018-ED-SASC BIS- Passation de 19 / Renouvellement du Component 3: Project IBRD / 88510 A posteriori marché de gré à Direct 4,500.00 0.00 Annulé 2019-06-28 2019-07-03 2019-08-07 2020-02-03 contrat de services Management gré d'entretien des locaux de l'UCP PSTAT PSTAT-043SASC-DC-20 / Component 2: Data Single Stage - One En attente Location de 28 véhicules IBRD / 88510 production, Dissemination A posteriori Demande de prix Open - National 45,000.00 0.00 2020-01-19 2020-03-15 2020-09-11 Envelope d'exécution pour la cartographie and the use of Statistics CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PSTAT-015-C-QC-17 / Recrutement d'une agence de communication pour la Sélection fondée Component 2: Data vulgarisation des activités et sur les IDA / 55000 production, Dissemination A posteriori Open - National 180,000.00 205,084.49 Signé 2017-07-16 2017-06-23 2017-08-06 2017-09-19 2017-11-30 2017-10-19 2018-05-30 2017-11-23 2018-06-05 2018-05-22 produits du SSN et l'appui qualifications des and the use of Statistics à la mise en œuvre du consultants plan de communication du PSTAT PSTAT-17-C-SQC-18 / Sélection fondée Sélection d'une firme Component 2: Data sur les chargée de constituer la IDA / V0870 production, Dissemination A posteriori Open - National 75,000.00 0.00 Annulé 2018-05-31 2018-04-11 2018-06-21 2018-05-24 2018-08-04 2018-09-03 2018-10-08 2019-04-06 qualifications des table de composition des and the use of Statistics consultants aliments PSTAT-18-C-SQC-18 / Sélection fondée SÉLECTION D'UNE FIRME Component 2: Data sur les CHARGÉE D'ASSURER LE IDA / V0870 production, Dissemination A posteriori Open - National 100,000.00 77,224.53 Signé 2018-06-29 2018-04-17 2018-07-20 2018-05-24 2018-09-02 2019-10-02 2018-10-02 2019-11-02 2018-11-06 2019-09-30 2019-05-05 qualifications des PAIEMENT DES AGENTS and the use of Statistics consultants DE TERRAIN PSTAT-24-C-SQC-18 / Component 1: Institutional Sélection fondée Sélection d'un Bureau Development, Human sur les En cours d'étude d'architecture et de IDA / V0870 A posteriori Open - National 250,000.00 303,012.13 2018-06-29 2019-04-16 2018-07-20 2019-05-03 2018-09-02 2019-06-25 2018-10-02 2019-09-25 2018-11-06 2019-10-10 2019-05-05 Resources and qualifications des d'exécution vérification et de suivi des Organizational Structure consultants travaux de construction PSTAT-029-C- SFQC-18 / Recrutement d'un cabinet Sélection fondée Component 3: Project Open - En cours charge de l'audit externe du IBRD / 88510 A posteriori sur la qualité et 60,000.00 0.00 2018-07-31 2018-06-14 2018-08-21 2018-07-16 2018-10-04 2018-10-15 2018-11-01 2018-12-01 2019-01-05 2019-02-09 2020-02-09 Management International d'exécution PSTAT exercice 2017 (PPA) le coût -2018, 2019 et 2020. PSTAT-24-C-SFQC-18 / Sélection fondée Sélection d'une firme Component 2: Data sur les Open - chargée du monitoring IBRD / 88510 production, Dissemination A priori 1,000,000.00 0.00 Annulé 2018-08-27 2018-09-17 2018-10-31 2018-11-30 2019-01-04 2019-07-03 qualifications des International externe de la sous and the use of Statistics consultants composante FBR du PSTAT Component 1: Institutional Sélection fondée PSTAT-047-C-QC-20 / Development, Human sur les Open - En cours Contrôleur technique des IBRD / 88510 A posteriori 135,000.00 0.00 2020-03-20 2020-05-18 2020-04-10 2020-05-29 2020-05-24 2020-06-23 2020-07-28 2021-01-24 Resources and qualifications des International d'exécution travaux Organizational Structure consultants Page 5 Sélection fondée PSTAT-051-C-SFQC-20 / Component 3: Project Open - En attente IBRD / 88510 A posteriori sur la qualité et 25,000.00 0.00 2020-04-21 2020-05-12 2020-06-25 2020-07-23 2020-08-22 2020-09-26 2020-10-31 2021-10-31 Audit externe 2020 et 2021 Management International d'exécution le coût INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PSTAT-020-C-CI-17 / Component 1: Institutional Recrutement d'un consultant Development, Human IDA / 55000 A priori Individuel Open 43,200.00 0.00 Annulé 2017-06-25 2017-09-14 2017-08-13 2017-09-03 2017-10-08 2018-04-06 individuel, spécialiste en Resources and ressources humaines Organizational Structure PSTAT-005-C-ED-17 / Contrat du spécialiste en communication_ Sélection de Component 3: Project Renouvellement du contrat IDA / 55000 A priori consultants par Direct 110,376.00 0.00 Annulé 2017-06-18 2017-06-28 2017-09-01 2018-02-28 Management du spécialiste en entente directe communication de l'UCP sur une période de 24 mois. PSTAT-018-C-ED-17 / Recrutement d'un Component 2: Data consultant_ assistance IDA / 55000 production, Dissemination A priori Individuel Direct 134,000.00 0.00 Annulé 2017-06-18 2017-06-18 2017-06-18 2017-07-09 2018-01-05 technique permanent pour and the use of Statistics le RGPH Component 3: Project PSTAT-016-C-CI-17 / Recr IDA / 55000 A priori Individuel Open 43,200.00 0.00 Annulé 2017-06-25 2017-08-13 2017-09-03 2017-10-08 2018-04-06 Management PSTAT-005- BIS-C-ED-17 / Renouvellement du contrat du spécialiste en Component 3: Project IDA / 55000 A priori Individuel Direct 41,680.00 44,904.86 Achevé 2017-02-28 2017-02-28 2017-02-28 2017-09-14 2017-02-28 2017-04-04 2017-02-28 2018-04-03 communication de l'UCP Management pour une periode de 12 mois PSTAT-008-C-ED-17 / Recrutement d'un consultant Component 2: Data Sélection de individuel en cartographie IDA / 55000 production, Dissemination A priori consultants par Direct 35,400.00 0.00 Annulé 2017-06-25 2017-07-05 2017-09-08 2018-03-07 censitaire pour le RGPH and the use of Statistics entente directe 2017 (Consultant JAMAGNE) PSTAT-021-C-ED-17 / Recrutement du Coordonnateur de l'UCP ( Sélection de Dominique KIMPOUNI) - Component 3: Project IDA / 55000 A priori consultants par Direct 144,000.00 150,006.81 Signé 2017-08-14 2017-08-24 2017-10-28 2017-05-02 2018-04-26 Régularisation dans STEP Management entente directe de l'ANO reçu depuis le 28 avril 2017_ contrat signé hors STEP PSTAT-022-C-CI-17 / Consultant international Component 1: Institutional principal pour l'élaboration Development, Human de la deuxième édition du IDA / 55000 A priori Individuel Limited 125,000.00 208,000.00 Signé 2017-07-10 2017-07-15 2017-08-05 2017-09-14 2017-09-09 2016-08-22 2018-03-08 Resources and Plan National de Organizational Structure Développement du Congo PND-2 : 2017-2021. PSTAT-025-C-CI-17 / consultant international programmation sectoriel et Component 1: Institutional suivi évaluation pour Development, Human IDA / 55000 A priori Individuel Limited 75,000.00 74,150.00 Signé 2016-08-15 2016-08-20 2016-09-10 2018-03-15 2016-10-15 2016-08-22 2017-04-13 L'élaboration de la deuxième Resources and édition du Plan National de Organizational Structure Développement du Congo PND-2 : 2017-2021. PSTAT-024-C-CI-17 / Consultant international en Component 1: Institutional informatique, pour Development, Human l'élaboration de la deuxième IDA / 55000 A priori Individuel Limited 75,000.00 138,600.00 Signé 2016-08-15 2016-08-20 2016-09-10 2017-09-14 2016-10-15 2016-08-22 2017-04-13 Resources and édition du Plan National de Organizational Structure Développement du Congo PND-2 : 2017-2021. Page 6 PSTAT-023-C-CI-17 / Consultant international Component 1: Institutional macro budgétaire Development, Human l'élaboration de la deuxième IDA / 55000 A priori Individuel Limited 75,000.00 74,150.00 Signé 2016-08-15 2016-08-20 2016-09-10 2017-09-14 2016-10-15 2016-08-29 2017-04-13 Resources and édition du Plan National de Organizational Structure Développement du Congo PND-2 : 2017-2021. PSTAT-026-C-CI-17 / consultant international Component 1: Institutional suivi évaluation pour Development, Human L'élaboration de la deuxième IDA / 55000 A priori Individuel Limited 75,000.00 74,150.00 Signé 2016-08-15 2016-08-20 2016-09-10 2018-03-15 2016-10-15 2016-08-22 2017-04-13 Resources and édition du Plan National de Organizational Structure Développement du Congo PND-2 : 2017-2021. PSTAT-019 BIS- C-CI-17 / Component 2: Data Recrutement d'un consultant IDA / 55000 production, Dissemination A posteriori Individuel Open 12,000.00 10,310.84 Signé 2017-10-31 2017-12-19 2017-08-29 2018-01-09 2017-11-08 2018-02-13 2017-11-08 2018-08-12 individuel pour le création and the use of Statistics du site web du PSTAT PSTAT-011-C-ED-17 / Renouvellement des contrats des ingénieurs statisticiens et démographes de haut Component 1: Institutional niveau non employés, pour Sélection de Development, Human l'appui aux projets IDA / 55000 A priori consultants par Direct 38,400.00 0.00 Annulé 2017-02-17 2017-02-27 2017-05-03 2017-10-30 Resources and d'enquêtes et aux services entente directe Organizational Structure statistiques de l'INS dans le cadre de la fidélisation et motivation (6 contrats ): Balossa Sivan PSTAT-018-BIS-C-ED-17 / Component 2: Data Renouvellement du contrat IDA / 55000 production, Dissemination A priori Individuel Direct 110,833.00 0.00 Annulé 2017-05-02 2017-05-02 de l Assistant technique and the use of Statistics RGPH PSTAT-019-C-CI-17 / Recrutement d'un consultant Component 3: Project individuel en vue de la IDA / 55000 A posteriori Individuel Open 12,000.00 0.00 Annulé 2017-06-25 2017-08-13 2017-09-03 2017-10-08 2018-04-06 Management réalisation du site web du PSTAT PSTAT-031-C-CI-17 / Component 1: Institutional Consultant chargé de Development, Human l'élaboration du cadre de IDA / V0870 A posteriori Individuel Open 20,000.00 0.00 Annulé 2017-10-20 2017-10-20 2017-10-31 2017-10-31 2017-11-02 2017-11-03 Resources and gestion environnementale et Organizational Structure sociale dans STEP PSTAT-033-C-CI-17 / Component 2: Data Consultant individuel IDA / V0870 production, Dissemination A posteriori Individuel Open 55,000.00 15,573.04 Achevé 2018-02-28 2018-04-18 2018-03-08 2018-05-09 2018-03-29 2018-06-13 2018-03-30 2018-12-10 2018-06-06 international spécialiste en and the use of Statistics sondage PSTAT-034-C-CI-17 / consultant individuel un Component 2: Data Expert "Développeur, IDA / V0870 production, Dissemination A posteriori Individuel Open 50,000.00 12,032.00 Achevé 2018-02-28 2017-12-26 2018-04-18 2018-03-16 2018-05-09 2018-03-28 2018-06-13 2018-03-30 2018-12-10 2018-06-29 Collecte et Traitement de and the use of Statistics données d'enquêtes CAPI" PSTAT-027-C-CI-17 / Recrutement du Statisticien d'appui, Responsable de la Component 3: Project En cours Composante 2 "Production IDA / V0870 A posteriori Individuel Open 45,000.00 0.00 2018-03-12 2017-09-07 2018-04-30 2018-03-19 2018-05-21 2018-06-25 2018-12-22 Management d'examen de données, diffusion et utilisation des statistiques" du PSTAT PSTAT-016-BIS-C-CI-17 / Component 3: Project Recrutement d un Auditeur IDA / V0870 A posteriori Individuel Open 45,000.00 0.00 Annulé 2018-03-12 2018-03-12 Management interne au sein de l UCP PSTAT-028-C-CI-17 / Recrutement d'un (e) Component 3: Project En cours IDA / V0870 A posteriori Individuel Open 30,000.00 0.00 2018-03-12 2018-03-22 2018-04-30 2018-05-21 2018-06-25 2018-12-22 Trésorière ou trésorier au Management d'examen sein du PSTAT PSTAT-029-C-CI-17 / Recrutement d'un assistant Component 3: Project IDA / V0870 A posteriori Individuel Open 30,000.00 16,666.46 Signé 2018-03-12 2018-03-26 2018-04-30 2018-04-17 2018-05-21 2018-04-23 2018-06-25 2018-04-23 2018-12-22 administratif au sein du Management PSTAT Page 7 PSTAT-009-C-ED-17 / Component 1: Institutional Recrutement d'une firme Sélection de Development, Human pour la préparation des IDA / V0870 A posteriori consultants par Direct 40,000.00 0.00 Annulé 2018-07-20 2018-07-30 2018-10-03 2019-04-01 Resources and étudiants candidats aux entente directe Organizational Structure concours statistique (CASP) PSTAT-010-C-ED-17 / Recruter un consultant individuel pour appuyer le CASP dans la préparation des candidats aux concours Component 1: Institutional Sélection de et pour la revue du Development, Human En cours IDA / V0870 A posteriori consultants par Direct 70,000.00 20,068.56 2018-01-30 2017-10-25 2018-02-09 2017-12-08 2018-04-15 2018-01-23 2018-10-12 programme de formation Resources and d'examen entente directe statistique et développement Organizational Structure de programmes d'études appropriés du CASP ( Consultant GRUN REHOMME) PSTAT-035-C-ED-17 / Recrutement de GRUN REHOMME formateur (CAPESA) pour appuyer Component 1: Institutional l'INS et le CASP dans la Sélection de Development, Human sensibilisation, le IDA / V0870 A priori consultants par Direct 26,500.00 0.00 Annulé 2017-12-13 2017-12-23 2018-02-26 2018-08-25 Resources and recrutement et la entente directe Organizational Structure préparation des candidats aux concours d'entrée dans les écoles africaines de statistique PSTAT-032-C-C-17 / Appui technique à la réalisation Component 2: Data Sélection de de l'Enquête Démographique IDA / V0870 production, Dissemination A posteriori consultants par Direct 24,000.00 24,000.00 Achevé 2017-09-03 2017-10-22 2017-11-21 2017-11-21 2018-01-31 2018-04-13 et de Santé (SIDA, and the use of Statistics entente directe Paludisme) ICF MACRO International PSTAT-036-C-ED-17 / Recrutement de Olga Vasyechko formatrice (CAPESA) pour appuyer Component 1: Institutional l'INS et le CASP dans la Sélection de Development, Human sensibilisation, le IDA / V0870 A posteriori consultants par Direct 8,449.00 8,553.90 Achevé 2017-12-13 2017-12-13 2017-12-23 2017-12-08 2018-02-26 2018-01-18 2018-08-25 2018-03-22 Resources and recrutement et la entente directe Organizational Structure préparation des candidats aux concours d'entrée dans les écoles africaines de statistique PSTAT-037-C-ED-17 / Recrutement de Jeannot Ngban formateur (ISSEA) pour appuyer l'INS et le Component 1: Institutional Sélection de CASP dans la Development, Human IDA / V0870 A priori consultants par Direct 13,591.00 0.00 Annulé 2017-12-13 2017-12-23 2018-02-26 2018-08-25 sensibilisation, le Resources and entente directe recrutement et la Organizational Structure préparation des candidats aux concours d'entrée dans les écoles africaines de statistique PSTAT-038-C-ED-17 / Recrutement de Justin Tchangam formateur (ISSEA) pour appuyer l'INS Component 1: Institutional et le CASP dans la Sélection de Development, Human sensibilisation, le IDA / V0870 A priori consultants par Direct 11,020.00 0.00 Annulé 2017-12-13 2017-12-23 2018-02-26 2018-08-25 Resources and recrutement et la entente directe Organizational Structure préparation des candidats aux concours d'entrée dans les écoles africaines de statistique PSTAT-06-C-ED-18 / Component 1: Institutional Sélection de Contrat de fidélisation des Development, Human IDA / V0870 A posteriori consultants par Direct 7,200.00 0.00 Annulé 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2019-02-10 statisticien: ONKA Resources and entente directe MOUANDA Vivien Organizational Structure PSTAT-07-C-ED-18 / Component 1: Institutional Fidélisation des ingénieurs Sélection de Development, Human statisticiens et IDA / V0870 A posteriori consultants par Direct 7,200.00 6,378.62 Signé 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 Resources and démographes: OSSOUNA entente directe Organizational Structure Dukken Gaphi Page 8 PSTAT-08-C-ED-18 / Component 1: Institutional Sélection de Fidélisation et motivation Development, Human IDA / V0870 A posteriori consultants par Direct 7,200.00 4,278.22 Signé 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 des ingénieurs statisticiens : Resources and entente directe MITOUMOUENI Antoine Organizational Structure PSTAT-09-C-ED-18 / Component 1: Institutional Sélection de Fidélisation et motivation Development, Human IDA / V0870 A posteriori consultants par Direct 7,200.00 4,252.42 Signé 2018-05-31 2018-06-11 2018-06-10 2018-08-14 2018-07-03 2019-02-10 des ingénieurs statisticiens: Resources and entente directe OKANIANGA Murphy Organizational Structure PSTAT-10-C-ED-18 / Component 1: Institutional Fidélisation et motivation Sélection de Development, Human des ingénieurs statisticiens IDA / V0870 A posteriori consultants par Direct 7,200.00 4,252.42 Signé 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 Resources and et démographes: GASSAI entente directe Organizational Structure OSSEBI PSTAT-11-C-ED-18 / Component 1: Institutional Fidélisation et motivation Sélection de Development, Human des ingénieurs statisticiens IDA / V0870 A posteriori consultants par Direct 7,200.00 6,378.62 Signé 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 Resources and et démographes: BALOSSA entente directe Organizational Structure Chriss Sivananda PSTAT-12-C-ED-18 / Component 1: Institutional Fidélisation et motivation Sélection de Development, Human des ingénieurs statisticiens IDA / V0870 A posteriori consultants par Direct 7,200.00 4,278.22 Signé 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 Resources and et démographes_ entente directe Organizational Structure MOKOMPONI Morlond PSTAT-13-C-ED-18 / Fidélisation et motivation Component 1: Institutional Sélection de des ingénieurs statisticiens Development, Human IDA / V0870 A posteriori consultants par Direct 7,200.00 6,417.32 Signé 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 et démographes_ IPANDZA Resources and entente directe LONDA NGANGA Chriss Organizational Structure Nawa PSTAT-15-C-ED-18 / Fidélisation et motivation Component 1: Institutional Sélection de des ingénieurs statisticiens Development, Human IDA / V0870 A posteriori consultants par Direct 7,200.00 6,378.62 Signé 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 et démographes_ KAMBO Resources and entente directe GUERE KOMONZO Claude Organizational Structure Christian PSTAT-16-C-ED-18 / Fidélisation et motivation Component 1: Institutional Sélection de des ingénieurs statisticiens Development, Human IDA / V0870 A posteriori consultants par Direct 7,200.00 4,252.42 Signé 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 et démographes_ Resources and entente directe MALONGA Philitchev Organizational Structure Audrokiev Component 1: Institutional PSTAT-21-C-CI-18 / Development, Human Recrutement d'un Ingénieur IDA / V0870 A posteriori Individuel Open 48,000.00 47,305.53 Signé 2018-05-31 2018-04-23 2018-07-19 2018-10-29 2018-08-09 2019-06-25 2018-09-13 2019-07-08 2019-03-12 Resources and en Bâtiment national Organizational Structure Component 1: Institutional PSTAT-22-C-CI-18 / Development, Human Recrutement d'un Spécialiste IDA / V0870 A posteriori Individuel Open 93,000.00 42,696.50 Signé 2018-05-31 2018-04-23 2018-07-19 2018-09-19 2018-08-09 2019-06-04 2018-09-13 2019-07-08 2019-03-12 Resources and en développement social Organizational Structure Component 1: Institutional PSTAT-23-C-CI-18 / Development, Human Recrutement d'un Spécialiste IDA / V0870 A posteriori Individuel Open 93,000.00 43,666.24 Signé 2018-05-31 2018-04-23 2018-07-19 2018-09-19 2018-08-09 2019-06-25 2018-09-13 2019-07-08 2019-03-12 Resources and en environnement Organizational Structure PSTAT-25-C-CI-18 / Recrutement d'une équipe de deux consultants Component 2: Data individuels pour la revue à IDA / V0870 production, Dissemination A posteriori Individuel Limited 50,000.00 32,937.00 Achevé 2018-06-18 2018-05-07 2018-06-23 2018-07-06 2018-07-14 2018-08-21 2018-08-18 2018-08-22 2019-02-14 2019-03-20 mi-parcours du projet de and the use of Statistics renforcement des capacités en statistiques_ Chef de mission PSTAT-26-C-CI-18 / Recrutement d'un Spécialiste en Component 2: Data accompagnement des IDA / V0870 production, Dissemination A posteriori Individuel Limited 25,000.00 29,337.00 Achevé 2018-06-18 2018-05-07 2018-06-23 2018-07-06 2018-07-14 2018-08-21 2018-08-18 2018-08-22 2019-02-14 2019-03-20 systèmes statistiques and the use of Statistics nationaux pour la revue à mi-parcours Page 9 PSTAT-27-C-CI-18 / Component 2: Data Recrutement d'un consultant IDA / V0870 production, Dissemination A posteriori Individuel Open 25,000.00 0.00 Annulé 2018-05-31 2018-05-22 2018-07-19 2018-08-09 2018-09-13 2019-03-12 individuel international de and the use of Statistics la gestion des plaintes PSTAT-02-C-ED-18 / Sélection de Renouvellement du contrat Component 3: Project IDA / V0870 A posteriori consultants par Direct 50,000.00 11,517.46 Achevé 2018-05-31 2018-06-12 2018-06-10 2018-08-14 2018-07-02 2019-02-10 2018-10-01 du spécialiste en Management entente directe communication du PSTAT PSTAT-28-C-CI-18 / Component 2: Data Renouvellement du contrat IDA / V0870 production, Dissemination A posteriori Individuel Direct 66,000.00 58,922.48 Achevé 2018-05-31 2018-06-13 2018-06-10 2018-06-25 2018-07-01 2018-06-25 2018-08-05 2018-07-02 2019-02-01 2018-12-31 du Conseiller Technique and the use of Statistics permanent du RGPH PSTAT-031-CI-DIR-18 / Consultant individuel Component 2: Data international pour la IDA / V0870 production, Dissemination A posteriori Individuel Direct 40,000.00 32,380.00 Signé 2018-07-30 2018-06-12 2018-08-09 2018-06-20 2018-08-30 2018-06-21 2018-10-04 2018-06-22 2019-04-02 mission d'assistance and the use of Statistics technique n°2 du consultant spécialiste CAPI PSTAT-035-SASC-DIR-18 / Component 1: Institutional Recrutement d'un consultant Development, Human individuel pour la mise en IDA / V0870 A posteriori Individuel Open 15,000.00 0.00 Annulé 2018-08-20 2018-10-08 2018-10-29 2018-12-03 2019-06-01 Resources and place du site web de Organizational Structure l'Institut National PSTAT-036-CI-DIR-18 / Renouvellement du contrat Sélection de Component 3: Project de l'Assistante de Direction IBRD / 88510 A posteriori consultants par Direct 30,000.00 27,768.08 Signé 2018-08-31 2018-08-30 2018-09-10 2018-11-14 2018-08-31 2019-05-13 Management de l'Unité de Coordination entente directe du PSTAT PSTAT-037-C-CI-18 / Recrutement d'un Assistant Component 3: Project IBRD / 88510 A posteriori Individuel Open 28,800.00 0.00 Annulé 2018-08-31 2018-09-19 2018-10-19 2018-11-09 2018-12-14 2019-06-12 en Passation des marchés Management au sein de l'UCP PSTAT PSTAT-038-CI-DIR-18 / Sélection de Component 3: Project Renouvellement du contrat IBRD / 88510 A posteriori consultants par Direct 109,206.00 100,765.31 Signé 2018-10-29 2018-09-18 2018-11-08 2018-10-24 2019-01-12 2018-10-29 2019-07-11 Management du RAFC du PSTAT entente directe PSTAT-039-CI-DIR-18 / Sélection de Component 3: Project Renouvellement du contrat IBRD / 88510 A priori consultants par Direct 205,000.00 0.00 Annulé 2018-10-29 2018-09-28 2018-11-08 2018-12-26 2019-01-12 2019-07-11 Management du SSE du PSTAT entente directe PSTAT-040-CI-DIR-18 / Sélection de Component 3: Project Renouvellement du contrat IBRD / 88510 A priori consultants par Direct 205,000.00 0.00 Annulé 2018-10-29 2018-09-28 2018-11-08 2018-12-26 2019-01-12 2019-07-11 Management du SPM du PSTAT entente directe PSTAT-041-CI-DIR-18 / Sélection de Renouvellement du contrat Component 3: Project IBRD / 88510 A posteriori consultants par Direct 144,000.00 0.00 Annulé 2019-04-29 2019-05-09 2019-07-13 2020-01-09 du Coordonnateur du Management entente directe PSTAT PSTAT-042-CI-DIR-18 / Sélection de Component 3: Project Renouvellement du contrat IBRD / 88510 A posteriori consultants par Direct 76,800.00 62,229.71 Signé 2019-04-30 2019-03-08 2019-05-10 2019-07-14 2019-05-10 2020-01-10 Management du Comptable du PSTAT entente directe PSTAT-043-CI-C-18 / Component 1: Institutional Recrutement d'un Development, Human IBRD / 88510 A posteriori Individuel Open 43,200.00 0.00 Annulé 2018-11-29 2018-09-19 2019-01-17 2019-02-07 2019-03-14 2019-09-10 responsable de la Resources and composante 1 Organizational Structure PSTAT-044-CI-C-18 / Sélection de Renouvellement du contrat Component 3: Project IBRD / 88510 A posteriori consultants par Direct 41,856.00 34,678.43 Signé 2019-03-29 2019-03-08 2019-04-08 2019-06-12 2019-04-23 2019-12-09 de l'Assistant Administratif Management entente directe du PSTAT PSTAT-045-CI-C-18 / Sélection de Component 3: Project Renouvellement du contrat IBRD / 88510 A posteriori consultants par Direct 41,856.00 8,256.77 Signé 2019-03-29 2019-03-14 2019-04-08 2019-06-12 2019-04-23 2019-12-09 Management du trésorier entente directe PSTAT-046-CI-DIR-18 / Sélection de Component 3: Project En cours Renouvellement du contrat IBRD / 88510 A posteriori consultants par Direct 11,008.00 0.00 2019-02-28 2019-03-08 2019-03-10 2019-03-14 2019-05-14 2019-11-10 Management d'exécution du Planton entente directe Page 10 PSTAT-047-CI-DIR-18 / Renouvellement du contrat Component 2: Data Sélection de En cours du Statisticien d'appui _ IBRD / 88510 production, Dissemination A posteriori consultants par Direct 94,176.00 0.00 2019-03-29 2019-04-02 2019-04-08 2019-04-25 2019-06-12 2019-12-09 d'exécution Responsable de la and the use of Statistics entente directe composante 2 PSTAT-048-C-DIR-18 / Component 1: Institutional Contra IFORD _Ecole pour Sélection de Development, Human la formation des IDA / V1720 A posteriori consultants par Direct 42,000.00 62,208.36 Signé 2018-12-24 2018-10-17 2019-01-03 2019-03-09 2018-11-19 2019-09-05 Resources and Démographes pour le Congo entente directe Organizational Structure Brazzaville PSTAT-049-C-DIR-18 / Contrat avec ENSAE Component 1: Institutional Sélection de (Dakar) pour la formation Development, Human IDA / V1720 A posteriori consultants par Direct 25,000.00 17,617.84 Signé 2018-12-24 2018-10-08 2019-01-03 2019-03-09 2018-11-19 2019-09-05 des ingénieurs des travaux Resources and entente directe statistiques pour le Congo Organizational Structure Brazzaville PSTAT-050-C-DIR-18 / Contrat avec ISSEA Component 1: Institutional Sélection de (Cameroun) pour la Development, Human IDA / V1720 A posteriori consultants par Direct 102,000.00 0.00 Annulé 2018-12-24 2018-10-08 2019-01-03 2019-03-09 2019-09-05 formation des ingénieurs Resources and entente directe des travaux statistiques Organizational Structure pour le Congo Brazzaville PSTAT-051-C-DIR-18 / Contrat avec ENSEA Component 1: Institutional Sélection de (Abidjan) pour la formation Development, Human IDA / V1720 A posteriori consultants par Direct 11,000.00 16,679.62 Signé 2018-12-24 2018-10-17 2019-01-03 2019-03-09 2018-11-19 2019-09-05 des ingénieurs des travaux Resources and entente directe statistiques pour le Congo Organizational Structure Brazzaville PSTAT-052-CI-18 / Component 1: Institutional Recrutement d'un consultant Development, Human pour l'élaboration du PGES IDA / V1720 A posteriori Individuel Open 30,000.00 0.00 Annulé 2018-12-24 2018-10-31 2019-02-11 2019-03-04 2019-04-08 2019-10-05 Resources and ( plan de gestion Organizational Structure environnemental et social PSTAT-053-CI-DIR-18 / Sélection de Renouvellement du contrat Component 3: Project IBRD / 88510 A posteriori consultants par Direct 113,510.00 22,621.76 Achevé 2018-12-24 2018-09-18 2019-01-03 2018-12-27 2019-03-09 2018-12-27 2019-09-05 2019-03-01 du Spécialiste en Management entente directe Communication du PSTAT PSTAT-054-CI-DIR-18 / Component 1: Institutional Renouvellement du contrat Sélection de Development, Human du chauffeur de la Direction IBRD / 88510 A posteriori consultants par Direct 14,400.00 0.00 Annulé 2019-04-30 2019-05-10 2019-07-14 2020-01-10 Resources and Générale de l'INS_ entente directe Organizational Structure M'BOYAS PSTAT-055-CI-DIR-18 / Recrutement d'un consultant Component 3: Project IDA / V1720 A posteriori Individuel Open 20,000.00 0.00 Annulé 2019-03-26 2019-02-26 2019-05-14 2019-06-04 2019-07-09 2020-01-05 pour l'élaboration du Management manuel d'exécution du PSTAT PSTAT-059-CI-18 / Component 1: Institutional Recrutement d'un assistant Development, Human IBRD / 88510 A posteriori Individuel Open 12,000.00 0.00 Annulé 2019-02-26 2019-04-16 2019-05-07 2019-06-11 2019-12-08 et administratif et logistique Resources and pour appuyer l'INS Organizational Structure PSTAT-005-C-CI-19 / Component 2: Data Recrutement d'un consultant IBRD / 88510 production, Dissemination A posteriori Individuel Open 50,000.00 37,849.72 Signé 2019-06-30 2019-08-31 2019-08-18 2019-12-03 2019-09-08 2019-12-07 2019-10-13 2019-12-17 2020-04-10 individuel chargé de la mise and the use of Statistics en place du FBR PSTAT-007-C-ED-19 / Sélection de Component 3: Project Renouvèlement du contrat IBRD / 88510 A posteriori consultants par Direct 16,176.00 13,050.81 Signé 2019-07-31 2019-05-07 2019-08-10 2019-06-06 2019-10-14 2019-06-12 2020-04-11 Management du chauffeur_ MIANTAMA entente directe PSTAT-006-CI-ED-19 / Sélection de Component 3: Project Renouvèlement du contrat IBRD / 88510 A posteriori consultants par Direct 16,176.00 13,050.81 Signé 2019-07-31 2019-05-07 2019-08-10 2019-10-14 2019-06-12 2020-04-11 Management du chauffeur_DZALAMOU entente directe PSTAT-008-CI-ED-19 / Sélection de Component 3: Project Renouvèlement du contrat IBRD / 88510 A posteriori consultants par Direct 16,617.00 13,050.81 Signé 2019-07-31 2019-05-07 2019-08-10 2019-10-14 2019-06-12 2020-04-11 Management du chauffeur_ BATHEAS entente directe Page 11 PSTAT-009-CI-ED-19 / Sélection de renouvèlement du contrat de Component 3: Project IBRD / 88510 A posteriori consultants par Direct 8,089.00 6,180.23 Signé 2019-04-30 2019-05-07 2019-05-10 2019-05-09 2019-07-14 2019-05-10 2020-01-10 Monsieur YOMES M'NOYAS Management entente directe chaffeur affecté à l'INS PSTAT-012- C-CI-19 / Régularisation _recrutement Component 2: Data Consultants individuel IBRD / 88510 production, Dissemination A posteriori Individuel Open 40,000.00 36,417.65 Signé 2016-01-10 2016-02-28 2016-03-20 2016-03-15 2016-04-24 2016-03-30 2016-10-21 charge de l'élaboration des and the use of Statistics documents techniques du (REGEC) PSTAT-013-C- DIR- 19 / Sélection de Régularisation Component 3: Project IDA / V0870 A posteriori consultants par Direct 51,000.00 70,973.75 Signé 2018-12-30 2019-01-09 2019-03-15 2018-12-27 2019-09-11 _renouvèlement du contrat Management entente directe du SPM. PSTAT-014-C- DIR -19 / Sélection de Régularisation Component 3: Project IDA / V0870 A posteriori consultants par Direct 51,000.00 44,831.02 Signé 2018-12-30 2019-01-09 2019-03-15 2018-12-27 2019-09-11 _renouvèlement du contrat Management entente directe du SSE. PSTAT-015-CI-ED-19 / Component 1: Institutional Fidélisation et motivation Sélection de Development, Human En cours des ingénieurs statisticiens IBRD / 88510 A posteriori consultants par Direct 7,200.00 0.00 2019-06-28 2019-04-04 2019-07-08 2019-04-25 2019-09-11 2020-03-09 Resources and d'exécution et démographes _ IBARA entente directe Organizational Structure Ngokaba (ISE) PSTAT-011-DIR-C-19 / Assistance et contrôle Component 2: Data Sélection de techniques du Recensement IBRD / 88510 production, Dissemination A posteriori consultants par Direct 367,600.00 327,600.00 Signé 2016-04-29 2016-05-09 2016-07-13 2016-04-29 2017-01-09 Général de la Population et and the use of Statistics entente directe de l'Habitation du Congo PSTAT-001-C-CI-19 / Recrutement du spécialiste Component 3: Project En cours IBRD / 88510 A priori Individuel Open 210,000.00 0.00 2019-07-30 2019-05-15 2019-09-17 2019-10-02 2019-10-08 2019-11-12 2020-05-10 en passation des marchés Management d'examen de l'UCP PSTAT PSTAT-002-C-CI-19 / Recrutement du spécialiste Component 3: Project En cours IBRD / 88510 A priori Individuel Open 210,000.00 0.00 2019-07-31 2019-05-15 2019-09-18 2019-10-02 2019-10-09 2019-11-13 2020-05-11 en Suivi-Evaluation de Management d'examen l'UCP PSTAT PSTAT-003-C-CI-19 / Recrutement du Spécialiste Component 3: Project En cours IBRD / 88510 A priori Individuel Open 210,000.00 0.00 2019-07-31 2019-05-15 2019-09-18 2019-10-02 2019-10-09 2019-11-13 2020-05-11 en Communication de l'UCP Management d'examen PSTAT PSTAT-004-C-CI-19 / Recrutement du Component 3: Project En cours IBRD / 88510 A priori Individuel Open 210,000.00 0.00 2019-07-31 2019-05-15 2019-09-18 2019-10-02 2019-10-09 2019-11-13 2020-05-11 Coordonnateur de l'UCP Management d'examen PSTAT PSTAT-016-C-CI-19 / Spécialiste en évaluation Component 1: Institutional institutionnelle, Development, Human IBRD / 88510 A posteriori Individuel Open 50,000.00 0.00 Annulé 2019-07-31 2019-05-24 2019-09-18 2019-10-09 2019-11-13 2020-05-11 organisationnelle et Resources and fonctionnelle - Reforme Organizational Structure CASP PSTAT-017-C-CI-19 / Component 1: Institutional Spécialiste en Réformes des Development, Human IBRD / 88510 A posteriori Individuel Open 50,000.00 83,815.59 Signé 2019-07-31 2019-05-24 2019-09-18 2019-12-03 2019-10-09 2020-02-11 2019-11-13 2020-02-17 2020-05-11 programmes de formation_ Resources and Reforme CASP Organizational Structure PSTAT-023-CI-ED-19 / Sélection de Component 3: Project Renouvèlement du contrat IBRD / 88510 A posteriori consultants par Direct 30,545.00 0.00 Annulé 2019-08-30 2019-08-30 2019-09-09 2019-11-13 2020-05-11 Management de la trésorière de l'UCP entente directe PSTAT-025-C-CI-19 / Component 1: Institutional Consultant élaboration Development, Human En cours IBRD / 88510 A posteriori Individuel Open 30,000.00 0.00 2019-10-10 2019-10-24 2019-11-28 2019-12-19 2020-01-23 2020-07-21 NIES( notice d'impact Resources and d'examen environnemental et social) Organizational Structure Component 1: Institutional PSTAT-027-C-CI-19 / Development, Human Elaboration plan de IBRD / 88510 A posteriori Individuel Open 50,000.00 24,184.88 Signé 2019-10-08 2019-10-07 2019-11-26 2019-12-03 2019-12-17 2019-12-12 2020-01-21 2019-12-15 2020-07-19 Resources and formation INS Organizational Structure Page 12 PSTAT-028-C-END- Component 1: Institutional CABINET LA BOUSSOLE- Sélection de Development, Human 19 / Cabinet études IBRD / 88510 A posteriori consultants par Direct 50,000.00 37,930.80 Signé 2019-10-30 2019-10-14 2019-11-09 2019-10-25 2020-01-13 2019-11-06 2020-07-11 Resources and topographiques travaux entente directe Organizational Structure complexe INS-CASP PSTAT-029-C-ED-BCBTP-19 Component 1: Institutional Sélection de / Laboratoire études Development, Human IBRD / 88510 A posteriori consultants par Direct 100,000.00 65,909.49 Signé 2019-10-30 2019-10-14 2019-11-09 2019-10-25 2020-01-13 2019-11-06 2020-07-11 géotechniques site complexe Resources and entente directe CASP-INS Organizational Structure Component 1: Institutional PSTAT -026-C-CI-19 / Development, Human Consultant PSR ( plan IBRD / 88510 A posteriori Individuel Open 30,000.00 0.00 Annulé 2019-10-09 2019-11-27 2019-12-18 2020-01-22 2020-07-20 Resources and succinct de réinstallation) Organizational Structure PSTAT-033-C-ED-MBEP FOMEKONG -19 / Component 2: Data Sélection de Renouvellement contrat En cours IBRD / 88510 production, Dissemination A posteriori consultants par Direct 40,000.00 0.00 2019-12-13 2019-11-19 2019-12-23 2020-02-26 2020-08-24 consultant du système d'examen and the use of Statistics entente directe d'interview assisté par ordinateur ( CAPI) PSTAT-032-C-ED-JANVIER METAGNO-19 / Component 2: Data Sélection de En cours Renouvellement contrat IBRD / 88510 production, Dissemination A posteriori consultants par Direct 40,000.00 0.00 2019-12-13 2019-11-20 2019-12-23 2020-02-26 2020-08-24 d'exécution expert en statistique and the use of Statistics entente directe d'entreprise PSTAT-30-C-ED-INS-19 / Component 2: Data Sélection de Protocole d'accord entre En cours IBRD / 88510 production, Dissemination A priori consultants par Direct 750,000.00 0.00 2019-12-12 2019-11-21 2019-12-22 2019-11-14 2020-02-25 2020-08-23 PSTAT -INS pour le d'exécution and the use of Statistics entente directe recrutement des enquêteurs. PSTAT-031- C-ED- UNFA- Component 2: Data Sélection de 19 / Assistance et contrôle IBRD / 88510 production, Dissemination A posteriori consultants par Direct 380,000.00 375,578.00 Signé 2019-12-05 2019-11-26 2019-12-15 2019-12-02 2020-02-18 2019-12-03 2020-08-16 technique du RGPH du and the use of Statistics entente directe Congo PSTAT-035C-CI-19 / Analyse approfondies des Component 2: Data En attente données de l' enquête par IBRD / 88510 production, Dissemination A posteriori Individuel Open 7,000.00 0.00 2020-01-15 2020-03-04 2020-03-25 2020-04-29 2020-10-26 d'exécution grappes à indicateurs and the use of Statistics multiples (MICS) 2015 Component 1: Institutional PSTAT-044-C-CI-20 / Development, Human En attente Recrut consultant enquête IBRD / 88510 A posteriori Individuel Open 25,000.00 0.00 2020-05-08 2020-06-26 2020-07-17 2020-08-21 2021-02-17 Resources and d'exécution des ménages Organizational Structure PSTAT-046-C-CI-20 / Component 1: Institutional Consultant etude Development, Human En cours diagnostique stat sectorielles IBRD / 88510 A posteriori Individuel Open 40,000.00 0.00 2020-06-10 2020-05-13 2020-07-29 2020-08-19 2020-09-23 2021-03-22 Resources and d'exécution ( forêt, mines ,gaz et Organizational Structure pétrole) PSTAT-049-C-CI-20 / Component 3: Project En attente assistant chargé de la IBRD / 88510 A posteriori Individuel Open 21,000.00 0.00 2020-04-24 2020-06-12 2020-07-03 2020-08-07 2021-02-03 Management d'exécution logistique PSTAT-048-C-ED- Component 1: Institutional Sélection de YAMEOGO EOUAYA -20 / Development, Human IBRD / 88510 A posteriori consultants par Direct 25,000.00 21,913.95 Signé 2020-04-15 2020-03-01 2020-04-25 2020-03-05 2020-06-29 2020-03-09 2020-12-26 Consultant enquête unités Resources and entente directe non standards Organizational Structure PSTAT-054-C-CI-20 / Component 3: Project En attente Consultant national pour IBRD / 88510 A posteriori Individuel Open 20,000.00 0.00 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 Management d'exécution évaluation finale du PSTAT PSTAT-050-C-CI-20 / consultant international Component 3: Project En attente IBRD / 88510 A posteriori Individuel Open 35,000.00 0.00 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 pour evaluation final du Management d'exécution projet PSTAT-055-C-CI-20 / Component 1: Institutional Recrutement cslt formation Development, Human En cours IBRD / 88510 A posteriori Individuel Open 15,000.00 0.00 2020-05-08 2020-06-24 2020-06-26 2020-07-17 2020-08-21 2021-02-17 cadre stat commerce Resources and d'exécution extérieur Organizational Structure Page 13 PSTAT-056-C-END-EWEK Component 1: Institutional ASSOUNGA-20 / Sélection de Development, Human Fidélisation et motivation IBRD / 88510 A posteriori consultants par Direct 10,000.00 6,045.23 Signé 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-03-13 2020-11-30 Resources and des ingénieurs statisticiens entente directe Organizational Structure et démographes/ EWEK ASSOUNGA PSTAT-057-C-END-GANGA ANGELUS-20 / Fidélisation Component 1: Institutional et motivation des ingénieurs Sélection de Development, Human statisticiens et démographes IBRD / 88510 A posteriori consultants par Direct 10,000.00 6,127.81 Signé 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-03-13 2020-11-30 Resources and de haut niveau non entente directe Organizational Structure employés aux projets pour l'appui aux projets de l'INS PSTAT-058-C-END-GONBA ONDOUMA-20 / Fidélisation Component 1: Institutional et motivation des ingénieurs Sélection de Development, Human statisticiens et démographes IBRD / 88510 A posteriori consultants par Direct 10,000.00 4,082.83 Signé 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-03-13 2020-11-30 Resources and de haut niveau non entente directe Organizational Structure employés aux projets pour l'appui aux projets de l'INS PSTAT-059-C-END-IBARA TSIBA-20 / Fidélisation et Component 1: Institutional motivation des ingénieurs Sélection de Development, Human statisticiens et démographes IBRD / 88510 A posteriori consultants par Direct 10,000.00 4,085.21 Signé 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-01-02 2020-11-30 Resources and de haut niveau non entente directe Organizational Structure employés aux projets pour l'appui aux projets de l'INS PSTAT-060-C-END- MBOUKOU PIERRICK-20 / Fidélisation et motivation Component 1: Institutional Sélection de des ingénieurs statisticiens Development, Human IBRD / 88510 A posteriori consultants par Direct 10,000.00 4,085.21 Signé 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-01-02 2020-11-30 et démographes de haut Resources and entente directe niveau non employés aux Organizational Structure projets pour l'appui aux projets de l'INS PSTAT-061-C-END-SITA BANZOUZI-20 / Fidélisation Component 1: Institutional et motivation des ingénieurs Sélection de Development, Human statisticiens et démographes IBRD / 88510 A posteriori consultants par Direct 10,000.00 6,127.81 Signé 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-03-13 2020-11-30 Resources and de haut niveau non entente directe Organizational Structure employés aux projets pour l'appui aux projets de l'INS PSTAT-062-C-CI-20 / Component 1: Institutional Consultant formation Development, Human En attente IBRD / 88510 A posteriori Individuel Open 17,000.00 0.00 2020-05-14 2020-07-02 2020-07-23 2020-08-27 2021-02-23 personnel en charge des Resources and d'exécution comptes nationaux Organizational Structure PSTAT-064-C-CI-20 / Component 1: Institutional Consultant statistique du Development, Human En attente secteur rural et IBRD / 88510 A posteriori Individuel Open 10,000.00 0.00 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 Resources and d'exécution environnement / Elaboration Organizational Structure SNDS II PSTAT-065-C-CI-20 / Consultant statistiques du Component 1: Institutional devlpt institutionnel Development, Human En attente IBRD / 88510 A posteriori Individuel Open 10,000.00 0.00 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 ressources humaines et Resources and d'exécution finances/ Elaboration SNDS Organizational Structure II PSTAT-066-C-ED- Sélection de BOUNKAZI JEAN Component 3: Project En attente IBRD / 88510 A posteriori consultants par Direct 5,000.00 0.00 2020-08-20 2020-08-30 2020-11-03 2021-05-02 HONORE- 20 / Recrutement Management d'exécution entente directe d'un chauffeur Page 14