INTEGRTED FOREST ECOSYSTEM MANAGEMENT PROJECT General Procurement Thresholds and Methods of Procurement: The following methods of procurement shall be used for procurement under the project. It has been agreed that if a invitation for a bid is comprised of several packages, lots or slices, and invited in the same invitation for bid, then the aggregate value of the whole package determines the applicable threshold amount for procurement and also for the review by the Bank. The national competitive bidding (NCB) conditions will be part of the Financing Agreement. Expenditure Contract Bank Prior Review Procurement Method Category Value (USD) >= 5, 000 000 ICB All ICB contracts < 5, 000,000 NCB NA Civil Works <50 000 Shopping NA NA DC >= 5, 000 000 >= 1, 000 000 ICB All ICB contracts <1, 000 000 NCB NA Goods <100 000 Shopping NA NA DC >= 1, 500 000 NA QCBS, QBS, FBS, All contracts >= USD 500,000 Consultant LCS and CQS* for firms; all contracts >= USD Services NA SSS 200,000 for individuals; All NA IC TORs Notes: ICB – International Competitive Bidding NCB – National Competitive Bidding DC – Direct Contracting QCBS – Quality and Cost Based Selection QBS – Quality Based Selection FBS – Fixed Budget Selection LCS – Least Cost Selection *CQS – Selection Based on Consultants’ Qualification below $300,000 depending on the nature of assignment SSS – Single (or Sole) Source Selection IC – Individual Consultant selection procedure NA – Not Applicable July 9, 2010 Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1. PROCUREMENT PLAN (July 2015) WB Date of Proc. Review Item № Contract Description Contract Method (Prior/ Signing Post) GOODS Component 1. Forest Sector Institutional Reform No goods Component 2. Strategic Investments and Piloting of Sustainable Management Approaches 1 Financing the implementation of INRMPs NCB/SH Prior/Post Investments like afforestation of short rotation tree 2 NCB/SH Prior/Post species, natural regeneration through thinning etc. Component 3. Information and Monitoring and Evaluation National Forest Inventory (NFI) and the 3 Management Forest Inventory (MFI) (Non- ICB Prior 9/1/2016 consulting services) 4 Office equipment for FMIS NCB Prior 6/1/2017 Component 4. Project Management, Monitoring and Evaluation 5 Computers for PCU SH Prior 3/1/2016 6 Furniture for PCU SH Post 3/1/2016 7 Car for PCU SH Post 3/1/2016 8 Accounting software for PCU SH Post 3/1/2016 CONSULTANCY LARGE WB Date of Select. Review Item № Contract Description Contract Method (Prior/ Signing Post) Component 1. Forest Sector Institutional Reform Support of introduction of new principles of 1 QCBS Prior 9/1/2016 planning, budgeting and monitoring /a Component 2. Strategic Investments and Piloting of Sustainable Management Approaches Preparation of the Integrated Natural Resource 2 QCBS Prior 9/1/2016 Management Plans (INRMPs) July 9, 2010 Component 3. Information and Monitoring and Evaluation The Forest Management Information System 3 QCBS Prior 1/1/2017 (FMIS) Component 4. Project Management, Monitoring and Evaluation 4 Project Audit LCS Prior 9/1/2016 July 9, 2010 PROCUREMENT Kyrgyz Republic : Integrated Forest Ecosystem Management PLAN General Information Country: Kyrgyz Republic Bank’s Approval Date of the Original Procurement Plan: 2018-04-04 2020-09-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151102 GPN Date: 2020-09-11 Project Name: Integrated Forest Ecosystem Management Loan / Credit No: IDA / D0950, IDA / 57430 Executing Agency(ies): State Agency on Environment Protection and Forestry WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IFEMP-INVEST-W-SH-10- Strategic Investments and Request for Single Stage - One 2019 / Fencing in Aksu IDA / D0950 Piloting of Sustainable Post Open - National 11,912.00 0.00 Canceled 2019-06-05 2019-07-05 2019-08-05 Quotations Envelope leskhoz 8 hectare Management Approaches IFEMP-INVEST-W-SH-1- 2019 / Installation of fencing and soil preparation for Strategic Investments and planting forest crops, fast- Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 27,696.00 27,058.67 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 growing plantations and Quotations Envelope Management Approaches orchards in Uch-Korgon LH for the current and next years. IFEMP-INVEST-W-SH-2- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 290,772.00 168,911.54 Signed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 Quotations Envelope growing plantations and Management Approaches orchards in Naryn LH in the current and next years. IFEMP-INVEST-W-SH -3- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 80,655.00 70,213.58 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 Quotations Envelope growing plantations and Management Approaches orchards in Batken LH for the current and next years. IFEMP-INVEST-W-SH -4- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 109,980.00 82,803.43 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 Quotations Envelope growing plantations and Management Approaches orchards in Toktogul LH for the current and next years. IFEMP-INVEST-W-SH-5- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 136,138.00 93,094.05 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 Quotations Envelope growing plantations and Management Approaches orchards in Talas LH for the current and next years. IFEMP-INVEST-W-SH -6- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 67,031.00 46,563.62 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 Quotations Envelope growing plantations and Management Approaches orchards in Aksy LH for the current and next years. Page 1 IFEMP-INVEST-W-SH -7- 2019 / Installation of fencing and soil preparation for Strategic Investments and planting forest crops, fast- Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 202,650.00 141,188.34 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 growing plantations and Quotations Envelope Management Approaches orchards in Kara-Kuldzha LH for the current and next years. IFEMP-INVEST-W-SH -8- 2019 / Installation of fencing and soil preparation for Strategic Investments and planting forest crops, fast- Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 128,234.00 78,687.27 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 growing plantations and Quotations Envelope Management Approaches orchards in Toskol-Ata (Kochkor-Ata) LH for the current and next years. IFEMP-INVEST-W-SH-9- 2019 / Installation of fencing and soil preparation for Strategic Investments and planting forest crops, fast- Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 194,000.00 145,193.60 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 growing plantations and Quotations Envelope Management Approaches orchards in Karakol (Aksuu) LH for the current and next years. IFEMP-INVEST-W-SH-11- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 113,259.00 80,647.33 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 Quotations Envelope growing plantations and Management Approaches orchards in At-Bashy LH for the current and next years. IFEMP-INVEST-W-SH-12- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 64,191.00 47,463.04 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 Quotations Envelope growing plantations and Management Approaches orchards in Chui LH for the current and next years. IFEMP-INVEST-W-SH-13- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 72,780.00 37,256.77 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 2019-11-29 Quotations Envelope growing plantations and Management Approaches orchards in Frunze LH for the current and next years. IFEMP-INVEST-W-SH-1/1- 2019 / Installation of fencing and soil preparation for Strategic Investments and planting forest crops, fast - IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 27,696.00 36,983.00 Completed 2019-10-30 2019-10-31 2019-10-31 2019-11-01 2019-11-01 2019-11-04 2020-01-30 growing plantations and Management Approaches orchards in Uch-Korgon LH for the courrent and next years IFEMP-INVEST-W-SH-12/1- 2019 / Installation of fencing and soil preparation for Strategic Investments and planting forest crops, fast - IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 64,191.00 53,197.61 Completed 2019-10-30 2019-10-31 2019-10-31 2019-11-01 2019-11-01 2019-11-04 2020-01-30 growing plantations and Management Approaches orchards in Chui LH for the courrent and next years Page 2 IFEMP-INVEST-W-SH-5/1 - 2019 / Installation of fencing and soil preparation for Strategic Investments and planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 136,138.00 110,482.26 Completed 2019-10-30 2019-11-01 2019-10-31 2019-11-01 2019-11-01 2019-11-04 2020-01-30 growing plantations and Management Approaches orchards in Talas LH for the courent and next years IFEMP/INVEST/W/NCB-1- 2020 / Installation of fences and soil preparation for Strategic Investments and Single Stage - One planting forest crops in IDA / D0950 Piloting of Sustainable Post Request for Bids Open - National 290,714.00 246,772.90 Signed 2020-02-17 2020-02-21 2020-02-19 2020-02-20 2020-03-11 2020-03-13 2020-03-20 2020-04-30 2020-04-20 2020-06-05 2020-07-19 Envelope Chui, Toktogul, Uch-Korgon, Management Approaches Batken, Karakol, Naryn, At- Bashy leskhozes IFEMP/INVEST/W/NCB-4- 2020 / Construction of 10 green houses and 2 concrete Strategic Investments and Under pits in pilot leskhozes Single Stage - One IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 479,145.00 0.00 Implementat 2020-06-12 2020-06-17 2020-06-17 2020-06-19 2020-07-08 2020-07-22 2020-08-21 2021-03-31 (Karakol, At-Bashy, Naryn, Envelope Management Approaches ion Chuy, Talas, Toktogul,Aksy, Toskool-Ata,Uch-Korgon,Kara- Kuldzha) IFEMP/INVEST/W/NCB-2- 2020 / Construction of 21 Strategic Investments and cordon-houses of the Single Stage - One IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 1,272,770.00 1,028,634.56 Signed 2020-06-12 2020-06-17 2020-06-17 2020-06-19 2020-07-08 2020-07-10 2020-07-22 2020-07-17 2020-08-21 2020-09-02 2021-06-30 northern pilot leskhozes Envelope Management Approaches (Talas, Karakol, Naryn, At- Bashy, Ton, Chui, Frunze) IFEMP/INVEST/W/NCB-3- 2020 / Construction of 21 cordon - houses of the Strategic Investments and Under Single Stage - One southern pilot leskhozes IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 1,023,280.00 0.00 Implementat 2020-06-12 2020-06-17 2020-06-17 2020-06-19 2020-07-08 2020-07-22 2020-08-21 2021-06-30 Envelope (Toktogul,Uch Korgon, Management Approaches ion Batken, Aksy, Kara-Kuldzha, Toskool-Ata) IFEMP/INVEST/W/NCB-7- 2020 / Construction of 4 Strategic Investments and Single Stage - One bridges in pilot leskhozes ( IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 198,866.00 180,375.98 Signed 2020-06-23 2020-07-14 2020-07-08 2020-07-15 2020-07-29 2020-08-05 2020-08-10 2020-08-24 2020-08-28 2020-09-07 2021-06-28 Envelope Karakol 1, Toskool Ata 1, Management Approaches Toktogul 1, Batken 1) IFEMP/INVEST/W/NCB-8- 2020 / Construction of Strategic Investments and Under irrigation facilities in pilot Single Stage - One IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 556,957.00 0.00 Implementat 2020-06-23 2020-08-26 2020-07-08 2020-08-28 2020-07-29 2020-08-10 2020-08-28 2021-06-28 leskhozes (Karakol, Frunze, Envelope Management Approaches ion Uch-Korgon, Kara-Kulzha, Toktogul) IFEMP/INVEST/W/NCB-9- 2020 / Construction of power Strategic Investments and Under Single Stage - One lines and installation of TS IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 194,893.00 0.00 Implementat 2020-06-23 2020-08-20 2020-07-08 2020-08-21 2020-07-29 2020-08-11 2020-08-28 2021-06-28 Envelope in pilot leskhozes (Karakol, Management Approaches ion Kara-Kulzha) IFEMP/INVEST/W/NCB-5-20 Strategic Investments and 20 / Сonstruction of irrigatio Single Stage - One IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 359,488.00 0.00 Canceled 2020-06-23 2020-08-06 2020-07-08 2020-08-06 2020-07-29 2020-08-10 2020-08-28 2021-06-28 n canals from trays in pilot Envelope Management Approaches leshozes (Chui, Ton) IFEMP/INVEST/W/NCB-6- 2020 / Drilling and Strategic Investments and Pending Single Stage - One rehabilitation of 7 wells in IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 453,458.00 0.00 Implementat 2020-09-09 2020-09-11 2020-10-02 2020-10-16 2020-11-02 2021-04-30 Envelope pilot leskhozes Karakol 2, Management Approaches ion Ton 4, Batken 1 Page 3 IFEMP/INVEST/W/NCB-5/20 Strategic Investments and Pending 20 / Сonstruction of irrigatio Single Stage - One IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 420,671.00 0.00 Implementat 2020-09-09 2020-09-11 2020-10-02 2020-10-16 2020-11-02 2021-07-02 n canals from trays in pilot Envelope Management Approaches ion leshozes (Chui, Ton) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-IFEMP-SH-COMPS-005- 2018 / Procurement of Computers and office equipment as a support of Forest Sector Institutional Request for Single Stage - One IDA / D0950 Post Limited 22,000.00 20,997.94 Completed 2018-03-19 2018-04-30 2018-05-08 2018-05-30 2018-05-28 Joint Forest Management Reform Quotations Envelope Council (JFMC) and Consultative and Coordination Council (CCC) KG-IFEMP-SH-FURNITURE- 003-2018 / Office furniture as a support of Joint Forest Forest Sector Institutional Request for Single Stage - One IDA / D0950 Post Limited 4,000.00 0.00 Canceled 2018-03-19 2018-04-23 2018-05-23 Management Council (JFMC) Reform Quotations Envelope and Consultative Coordination Council (CCC) IFMP-SH-PRINT-004-2018 / Forest Sector Institutional Request for Single Stage - One Information Board in pilot IDA / D0950 Post Open - National 8,500.00 2,804.09 Completed 2018-08-03 2018-09-12 2018-08-28 2018-10-08 2018-09-24 Reform Quotations Envelope leskhozes IFMP-SH-FURNITURE- Forest Sector Institutional Request for Single Stage - One 005/1-2018 / Support CCC IDA / D0950 Post Open - National 10,080.00 4,024.56 Completed 2018-08-08 2018-08-28 2018-08-28 2018-09-28 2018-09-24 Reform Quotations Envelope and JFMC (office furniture) IFMP-SH-PRINT-005-2018 / Forest Sector Institutional Request for Single Stage - One Information poster in pilot IDA / D0950 Post Open - National 5,000.00 3,708.51 Completed 2018-08-17 2018-09-21 2018-09-10 2018-10-21 2018-10-31 Reform Quotations Envelope leskhozes IFEMP-SH-COMPS-001-2017 Project Management, Request for Single Stage - One IDA / D0950 Post Limited 7,200.00 8,071.60 Completed 2017-06-05 2017-06-15 2017-07-02 2017-07-06 2017-07-27 2017-11-30 / Computers for PCU Monitoring and Evaluation Quotations Envelope IFEMP-SH-VEHICLE-004- Project Management, Request for Single Stage - One IDA / D0950 Post Limited 80,000.00 80,790.33 Completed 2017-06-26 2017-06-30 2017-07-31 2017-08-07 2017-08-30 2017-08-28 2017 / Car for PCU Monitoring and Evaluation Quotations Envelope KG-IFEMP-SH-MNE-005- 2018 / Server for the Project Management, Request for Single Stage - One development of IFEMP IDA / D0950 Post Open - National 2,000.00 3,684.59 Completed 2018-09-24 2018-10-18 2018-09-10 2018-11-18 2018-10-25 Monitoring and Evaluation Quotations Envelope database for MnE and office equipment KG-IFEMP- SH-COMPS - Project Management, Request for Single Stage - One 007-2018 / Computers for IDA / D0950 Post Open - National 10,000.00 5,317.87 Completed 2018-11-23 2018-11-30 2018-12-17 2019-01-11 2019-02-07 2018-12-31 Monitoring and Evaluation Quotations Envelope PIU IFEMP-INVEST-G-SH-5- Strategic Investments and 2019 / Purchase of motor Request for Single Stage - One IDA / 57430 Piloting of Sustainable Post Open - National 18,859.00 33,012.91 Completed 2019-06-05 2019-07-08 2019-07-05 2019-08-29 2019-08-05 2019-10-08 cultivato rwith a plow and Quotations Envelope Management Approaches tree shovels IFEMP-INVEST-G-NCB-2- Strategic Investments and 2019 / Purchase of a car Single Stage - One IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 471,486.00 389,071.31 Completed 2019-06-13 2019-06-28 2019-06-18 2019-07-08 2019-06-27 2019-07-24 2019-07-03 2019-08-01 2019-08-05 2019-09-11 2019-10-07 2019-11-05 with fie-fighting equipment Envelope Management Approaches (MLPK) for pilot leskozes Page 4 IFEMP-INVEST-G-NCB-3- Strategic Investments and 2019 / Purchase of wheeled Single Stage - One IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 537,003.00 523,344.13 Completed 2019-06-11 2019-06-28 2019-06-11 2019-07-08 2019-06-27 2019-07-24 2019-07-03 2019-08-01 2019-08-01 2019-09-11 2019-10-07 2019-11-05 tractors with mounted Envelope Management Approaches equipment IFEMP-INVEST-G-NCB-4- Strategic Investments and 2019 / Purchase of wheeled Single Stage - One IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 124,348.00 87,142.83 Completed 2019-06-13 2019-07-05 2019-06-18 2019-07-08 2019-06-27 2019-07-24 2019-07-03 2019-08-01 2019-08-01 2019-09-11 2019-10-07 2019-11-05 mini tractors with mounted Envelope Management Approaches equipment IFEMP-SH-PRINT-010-2019 / Development and Forest Sector Institutional Request for Single Stage - One IDA / D0950 Post Open - National 1,500.00 616.63 Completed 2019-09-06 2019-08-30 2019-09-13 2019-09-18 2019-09-27 2019-10-01 replication of booklets on Reform Quotations Envelope municipal forests IFEMP-INVEST-G-SH-6- Strategic Investments and 2019 / Purchase of materials Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 21,540.00 0.00 Canceled 2019-06-05 2019-07-08 2019-08-07 for fencing of 4 km in Quotations Envelope Management Approaches Naryn leskhoz KG-IFEMP-SH-02-2020 / Project Management, Request for Single Stage - One IDA / D0950 Post Open - National 4,091.00 2,989.97 Completed 2020-02-07 2020-02-06 2020-02-28 2020-03-11 2020-03-29 2020-05-21 Computer equipment for PIU Monitoring and Evaluation Quotations Envelope IFEMP-SH-03-2020 / Development and replication Forest Sector Institutional Request for Single Stage - One IDA / D0950 Post Open - National 1,000.00 0.00 Canceled 2020-03-06 2020-02-06 2020-04-01 2020-04-24 of booklets and barcodes of Reform Quotations Envelope PIU IFEMP-/INVEST/G/SH-1- Strategic Investments and Request for Single Stage - One 2020 / Beekeeping equipment IDA / D0950 Piloting of Sustainable Post Open - National 40,383.00 35,084.76 Completed 2020-03-04 2020-02-20 2020-04-06 2020-03-16 2020-05-06 2020-06-04 Quotations Envelope for At-Bashi leskhozes Management Approaches IFEMP/INVEST/G/NCB-1- Strategic Investments and Single Stage - One 2020 / Beekeeping equipment IDA / D0950 Piloting of Sustainable Post Request for Bids Open - National 141,345.00 96,904.37 Completed 2020-02-19 2020-02-21 2020-03-04 2020-02-21 2020-03-25 2020-03-13 2020-03-31 2020-04-20 2020-04-29 2020-05-21 2020-05-29 2020-07-10 Envelope for Kara-Kuldzhinsky leskhoz Management Approaches IFEMP-/INVEST/G/SH-2- Strategic Investments and Request for Single Stage - One 2020 / Purchase of planting IDA / D0950 Piloting of Sustainable Post Open - National 26,140.00 7,746.63 Completed 2020-02-21 2020-02-21 2020-03-16 2020-03-16 2020-04-15 2020-03-24 Quotations Envelope materials for Chuy leskhoz Management Approaches IFEMP-/INVEST/G/SH-3- Strategic Investments and Request for Single Stage - One 2020 / Purchase of planting IDA / D0950 Piloting of Sustainable Post Open - National 45,810.00 21,945.12 Signed 2020-02-21 2020-02-21 2020-03-16 2020-03-16 2020-04-15 Quotations Envelope materials for Ton leskhoz Management Approaches IFEMP-/INVEST/G/SH-4- Strategic Investments and 2020 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 6,650.00 1,912.52 Completed 2020-02-21 2020-02-21 2020-03-16 2020-03-16 2020-04-15 2020-03-25 materials for Karakol Quotations Envelope Management Approaches leskhoz IFEMP-/INVEST/G/SH-5- Strategic Investments and Request for Single Stage - One 2020 / Purchase of planting IDA / D0950 Piloting of Sustainable Post Open - National 30,410.00 19,421.43 Signed 2020-02-21 2020-02-21 2020-03-16 2020-03-16 2020-04-15 Quotations Envelope materials for Naryn leskhoz Management Approaches IFEMP-/INVEST/G/SH-6- Strategic Investments and 2020 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 7,730.00 4,937.65 Signed 2020-02-21 2020-02-21 2020-03-16 2020-03-16 2020-04-15 materials for At-Bashi Quotations Envelope Management Approaches leskhoz IFEMP-/INVEST/G/SH-7- Strategic Investments and 2020 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 34,210.00 10,565.21 Signed 2020-02-21 2020-02-21 2020-03-16 2020-03-27 2020-04-15 materials for Toktogul Quotations Envelope Management Approaches leskhoz Page 5 IFEMP/INVEST/LSGB/G/NCB Strategic Investments and Single Stage - One /-1-2020 / Special technique IDA / D0950 Piloting of Sustainable Post Request for Bids Open - National 226,274.00 188,632.49 Signed 2020-05-01 2020-05-12 2020-05-08 2020-05-15 2020-05-29 2020-06-05 2020-06-05 2020-06-26 2020-07-01 2020-07-24 2020-09-01 Envelope for 6 LSGB Management Approaches IFEMP-COVID-SH-1-2020 / Strategic Investments and Under Request for Single Stage - One Purchase of calcium IDA / 57430 Piloting of Sustainable Post Open - National 15,000.00 13,158.04 Implementati 2020-04-27 2020-04-30 2020-05-08 2020-05-18 2020-05-22 2020-05-18 Quotations Envelope hypochlorite (chlorine) Management Approaches on IFEMP-COVID-SH-2-2020 / Strategic Investments and Under Request for Single Stage - One Purchase of individual IDA / 57430 Piloting of Sustainable Post Open - National 85,000.00 0.00 Implementati 2020-05-06 2020-05-15 2020-05-27 2020-06-27 Quotations Envelope protective means Management Approaches on IFEMP/INVEST/M/G/SH/-1- Strategic Investments and 2020 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 55,384.00 0.00 Canceled 2020-03-27 2020-04-21 2020-05-11 materials for Cholpon Ata Quotations Envelope Management Approaches Ail Aimak IFEMP/INVEST/M/G/SH/-2- Strategic Investments and 2020 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 12,637.00 0.00 Canceled 2020-03-27 2020-04-21 2020-05-11 materials for Bel Aldy Ail Quotations Envelope Management Approaches Aimak IFEMP-/INVEST/G/SH-8- Strategic Investments and 2020 / Materials and Request for Single Stage - One IDA / 57430 Piloting of Sustainable Post Open - National 29,200.00 26,462.72 Signed 2020-08-07 2020-08-14 2020-09-01 2020-09-04 2020-10-01 equipment for drip irrigation Quotations Envelope Management Approaches system of Karakol leskhoz IFEMP-/INVEST/G/SH-9- 2020 / Materials and Strategic Investments and Request for Single Stage - One equipment for drip irrigation IDA / 57430 Piloting of Sustainable Post Open - National 96,600.00 80,652.76 Signed 2020-08-07 2020-08-14 2020-09-01 2020-09-04 2020-10-01 Quotations Envelope system of Kara - Kuldzha Management Approaches leskhoz IFEMP-/INVEST/G/SH-10- Strategic Investments and 2020 / Materials and Request for Single Stage - One IDA / 57430 Piloting of Sustainable Post Open - National 12,250.00 11,105.48 Signed 2020-08-07 2020-08-14 2020-09-01 2020-09-04 2020-10-01 equipment for drip irrigation Quotations Envelope Management Approaches system of Aksy leskhoz IFEMP/INVEST/LSGB/G/SH- 1-2020 / Purchase of Strategic Investments and Request for Single Stage - One materials for fencing plots of IDA / D0950 Piloting of Sustainable Post Open - National 56,920.00 45,891.13 Signed 2020-08-14 2020-08-21 2020-09-10 2020-09-09 2020-10-05 Quotations Envelope forest and fruit plantations Management Approaches for Cholpon Ata Aiyl Aymak IFEMP/INVEST/LSGB/G/SH- 2-2020 / Purchase of Strategic Investments and Request for Single Stage - One materials for fencing plots of IDA / D0950 Piloting of Sustainable Post Open - National 27,240.00 23,898.84 Signed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 Quotations Envelope forest and fruit plantations Management Approaches for Zhany Zhol Aiyl Aymak IFEMP/INVEST/LSGB/G/SH- 3-2020 / Purchase of Strategic Investments and materials for fencing plots of Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 28,870.00 26,557.67 Signed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 forest and fruit plantations Quotations Envelope Management Approaches for Onbir Zhylga Aiyl Aymak IFEMP/INVEST/LSGB/G/SH- 4-2020 / Purchase of Strategic Investments and Request for Single Stage - One materials for fencing plots of IDA / D0950 Piloting of Sustainable Post Open - National 36,142.00 25,729.36 Signed 2020-08-14 2020-08-21 2020-09-11 2020-09-07 2020-10-05 Quotations Envelope forest and fruit plantations Management Approaches for Bel Aldy Aiyl Aymak Page 6 IFEMP/INVEST/LSGB/G/SH- 5-2020 / Purchase of Strategic Investments and materials for fencing plots Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 41,247.00 31,688.34 Signed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 for forest and fruit Quotations Envelope Management Approaches plantations for Nichke Sai Aiyl Aymak IFEMP/INVEST/LSGB/G/SH- 6-2020 / Purchase of Strategic Investments and materials for fencing plots Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 37,705.00 29,518.64 Signed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 for forest and fruit Quotations Envelope Management Approaches plantations for Dostuk Aiyl Aymak IFEMP/INVEST/LSGB/G/SH- 7-2020 / Purchase of Strategic Investments and Request for Single Stage - One materials and equipment for IDA / D0950 Piloting of Sustainable Post Open - National 86,468.00 64,203.82 Signed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 Quotations Envelope drip irrigation system for Management Approaches Zhany - Zhol ayil aimak IFEMP/INVEST/LSGB/G/SH- 9-2020 / Purchase of Strategic Investments and Request for Single Stage - One materials and equipment for IDA / D0950 Piloting of Sustainable Post Open - National 47,930.00 38,263.85 Signed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 Quotations Envelope a drip irrigation system for Management Approaches Cholpon-Ata aiyl aimak IFEMP/INVEST/LSGB/G/SH- 10-2020 / Purchase of Strategic Investments and Request for Single Stage - One materials and equipment for IDA / D0950 Piloting of Sustainable Post Open - National 52,954.00 42,411.86 Signed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 Quotations Envelope drip irrigation system for Management Approaches Nichke - Sai aiyl aimak IFEMP/INVEST/LSGB/G/SH- 8-2020 / Purchase of Strategic Investments and Under Request for Single Stage - One materials and equipment for IDA / D0950 Piloting of Sustainable Post Open - National 68,958.00 0.00 Implementati 2020-08-14 2020-08-28 2020-09-11 2020-10-05 Quotations Envelope drip irrigation system for Management Approaches on Onbir - Zhilga ayil aimak IFEMP/INVEST/LSGB/G/SH- 11-2020 / Purchase of Strategic Investments and Under Request for Single Stage - One materials and equipment for IDA / D0950 Piloting of Sustainable Post Open - National 79,258.00 0.00 Implementati 2020-09-04 2020-09-09 2020-09-18 2020-10-08 Quotations Envelope a drip irrigation system for Management Approaches on Bel-Aldy aiyl aimak NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-IFEMP- CQS-DESIGN ESTIMATES -05-2019 / Company for the Strategic Investments and Consultant development of design IDA / D0950 Piloting of Sustainable Post Qualification Open - National 280,000.00 226,378.64 Completed 2019-06-19 2019-06-21 2019-07-10 2019-06-27 2019-07-12 2019-09-16 2019-08-19 2019-10-25 2019-08-23 2019-10-28 2019-11-25 2020-06-19 estimates documetation for Management Approaches Selection bridges,greenhouses, irrigation systems Page 7 KG-IFEMP- CQS-DESIGN ESTIMATES -04-2019 / Company for the Strategic Investments and Consultant development of design IDA / D0950 Piloting of Sustainable Post Qualification Open - National 280,000.00 210,962.72 Completed 2019-06-10 2019-06-28 2019-07-01 2019-07-15 2019-07-12 2019-09-16 2019-08-19 2019-10-25 2019-08-23 2019-10-28 2019-12-23 2020-06-19 estimates documentation for Management Approaches Selection cordons, drying shops and refrigerators KG-IFEMP-CQS- DES.ESTIMATES-06-2019 / Strategic Investments and Consultant Design of construction, IDA / D0950 Piloting of Sustainable Post Qualification Open - National 78,427.00 67,901.60 Signed 2019-11-08 2019-11-14 2019-11-29 2019-11-14 2019-12-13 2019-12-20 2019-12-20 2020-01-27 2019-12-27 2020-01-27 2020-03-06 repair and reconstruction of Management Approaches Selection pilot leshoz facilities KG-IFEMP-CQS- DES.ESTIMATES-07-2020 / Development of design Strategic Investments and Consultant estimate documentation for IDA / D0950 Piloting of Sustainable Post Qualification Open - National 216,000.00 101,138.59 Signed 2020-02-07 2020-02-05 2020-02-28 2020-02-06 2020-03-12 2020-05-17 2020-04-09 2020-05-14 2020-04-15 2020-05-18 2020-07-22 construction, repair and Management Approaches Selection reconstruction of processing shops and cold storage facilities in pilot leskhozes IFEMP-CQS-SUPERVISION- Strategic Investments and Consultant 09-2020 / Company for IDA / D0950 Piloting of Sustainable Post Qualification Open - National 150,000.00 140,943.69 Signed 2020-05-08 2020-06-23 2020-05-15 2020-07-15 2020-06-16 2020-08-17 2020-06-29 2020-09-08 2020-07-01 2020-09-10 2021-07-01 providing technical Management Approaches Selection supervision INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-IFEMP-CS-INT-FA- 01/2018 / Selection of Forest Sector Institutional individual consultant for IDA / D0950 Prior Direct Selection Direct 50,000.00 0.00 Canceled 2018-05-23 2018-05-23 2018-05-24 2018-05-27 2018-12-02 Reform functional and institutional review of Kyrgyz Forestry KG-SAEPF-CS-ENV- SAFEGUARD-INDV / Selection of Individual Individual Information and Monitoring consultant (national) for IDA / 57430 Post Consultant Limited 10,000.00 44,636.68 Signed 2018-05-23 2018-05-31 2018-05-28 2018-06-01 2018-06-18 2018-06-05 2018-07-23 2018-07-06 2019-01-19 and Evaluation providing of consulting Selection services on Environmental Safeguard KG-SAEPF-CS- SOCIALSAFEGUARD-INDV / Individual Selection of Individual Information and Monitoring IDA / 57430 Post Consultant Limited 10,000.00 26,498.92 Signed 2018-05-24 2018-05-31 2018-05-29 2018-06-01 2018-06-19 2018-06-15 2018-07-24 2018-07-23 2019-01-20 consultant (national) for and Evaluation Selection providing of consulting services on Social Safeguard CS-NAT-FA-01-2018 / Selection of national Individual Forest Sector Institutional consultant for Functional IDA / D0950 Post Consultant Limited 10,000.00 5,448.81 Completed 2018-05-25 2018-05-29 2018-05-28 2018-05-30 2018-05-29 2018-06-06 2018-05-31 2018-06-14 2018-11-27 2019-01-30 Reform analyzing of Kyrgyz Forest Selection Sector KG-SAEPF-64439-CS-INDV / Selection of individual Individual consultant for functional and Forest Sector Institutional IDA / D0950 Post Consultant Limited 50,000.00 33,224.00 Completed 2018-05-29 2018-05-31 2018-06-01 2018-04-17 2018-06-04 2018-06-07 2018-06-08 2018-06-12 2018-10-16 2019-01-30 institutional review of the Reform Selection forestry sector of the Kyrgyz Republic Page 8 SSS-PIUDATABASE- 009/2018 / IT specialist on development of database for Project Management, the Integrated Forest IDA / D0950 Post Direct Selection Direct 8,000.00 8,137.84 Completed 2018-07-31 2018-07-26 2018-08-03 2018-08-05 2018-08-24 2019-01-06 2019-04-30 Monitoring and Evaluation Ecosystem Management Project of the Kyrgyz Republic Individual CS- CCC/JFMC-02-1/2018 / Forest Sector Institutional IDA / D0950 Post Consultant Limited 6,750.00 6,589.93 Completed 2018-02-12 2018-01-31 2018-03-17 2018-02-23 2018-04-09 2018-04-20 2018-05-23 2018-05-08 2019-05-08 2019-05-08 PIU Local Focal Point Reform Selection Individual CS- CCC/JFMC-02-2/2018 / Forest Sector Institutional IDA / D0950 Post Consultant Limited 6,750.00 11,748.93 Completed 2018-02-12 2018-01-31 2018-03-17 2018-02-23 2018-04-09 2018-04-20 2018-05-23 2018-05-08 2019-05-08 2019-10-18 PIU Local Focal Point Reform Selection Individual CS- CCC/JFMC-02-3/2018 / Forest Sector Institutional IDA / D0950 Post Consultant Limited 7,100.00 19,413.24 Signed 2018-02-12 2018-01-31 2018-03-17 2018-02-23 2018-04-09 2018-04-20 2018-05-23 2018-05-08 2019-05-08 PIU Local Focal Point Reform Selection Individual CS- CCC/JFMC-02-4/2018 / Forest Sector Institutional IDA / D0950 Post Consultant Limited 7,150.00 21,500.02 Signed 2018-02-12 2018-01-31 2018-03-17 2018-02-23 2018-04-09 2018-04-20 2018-05-23 2018-05-08 2019-05-08 PIU Local Focal Point Reform Selection Individual CS- CCC/JFMC-02-5/2018 / Forest Sector Institutional IDA / D0950 Post Consultant Limited 7,250.00 18,951.32 Signed 2018-02-12 2018-01-31 2018-02-17 2018-05-18 2018-04-09 2018-07-06 2018-05-23 2018-07-13 2019-05-08 PIU Local Focal Point Reform Selection SSS-RTK-03-1/2018 / Development of metodology Forest Sector Institutional IDA / D0950 Post Direct Selection Direct 10,000.00 4,985.34 Completed 2018-04-03 2018-04-04 2018-04-13 2018-04-13 2018-04-25 2018-04-25 2018-10-27 2019-06-15 of Calculation the Cost of Reform foresty works SSS-RTK-03-2/2018 / Development of metodology Forest Sector Institutional IDA / D0950 Post Direct Selection Direct 10,000.00 4,569.65 Completed 2018-04-03 2018-04-04 2018-04-13 2018-04-13 2018-04-25 2018-04-25 2018-10-27 2019-06-28 of Calculation the Cost of Reform foresty works IC-MF-REGULATORY-012- Strategic Investments and Individual 2018 / Expert on regulatory IDA / D0950 Piloting of Sustainable Post Consultant Open 10,000.00 6,466.45 Completed 2018-09-11 2018-09-25 2018-10-12 2018-10-26 2018-10-17 2018-10-26 2018-10-31 2018-10-29 2019-04-30 2019-12-25 status of orphan forests Management Approaches Selection IC-MF-INVENTORY-014- 2018 / Expert on forest Strategic Investments and Individual management inventory IDA / D0950 Piloting of Sustainable Post Consultant Open 3,000.00 2,873.98 Completed 2018-09-11 2018-09-25 2018-10-12 2018-10-26 2018-10-17 2018-10-26 2018-10-31 2018-10-29 2019-01-31 2019-10-30 guidelines for municipal Management Approaches Selection forest IC-MF-FACILITATION-013/1- Strategic Investments and Individual 2018 / Consultants for IDA / D0950 Piloting of Sustainable Post Consultant Open 9,000.00 6,825.69 Completed 2018-09-11 2018-09-25 2018-10-12 2018-10-26 2018-10-17 2018-10-26 2018-10-31 2018-10-29 2019-03-31 2019-10-31 facilitation in municipal Management Approaches Selection forests (3 positoins) IC-MF-FACILITATION-013/2- Strategic Investments and Individual 2018 / Consultants for IDA / D0950 Piloting of Sustainable Post Consultant Open 9,000.00 8,057.07 Completed 2018-09-11 2018-09-25 2018-10-12 2018-10-26 2018-10-17 2018-10-26 2018-10-31 2018-10-29 2019-03-31 2019-10-31 facilitation in municipal Management Approaches Selection forests (3 positoins) IC-MF-FACILITATION-013/3- Strategic Investments and Individual 2018 / Consultants for IDA / D0950 Piloting of Sustainable Post Consultant Open 9,000.00 9,069.78 Completed 2018-09-11 2018-09-25 2018-10-12 2018-10-26 2018-10-17 2018-10-26 2018-10-31 2018-10-29 2019-03-31 2019-10-31 facilitation in municipal Management Approaches Selection forests (3 positoins) IC-FOREST CULTURES- 017/2018 / Consultant on Strategic Investments and Individual devolopment forest IDA / D0950 Piloting of Sustainable Post Consultant Open 10,000.00 8,836.59 Completed 2018-10-05 2018-10-10 2018-11-01 2018-11-16 2018-11-02 2018-11-16 2018-11-09 2018-11-20 2019-03-09 2019-10-10 management investment Management Approaches Selection projects Page 9 IC-TECHNICAL Strategic Investments and Individual ENGENEER-015/2018 / IDA / D0950 Piloting of Sustainable Post Consultant Open 17,518.00 24,314.08 Signed 2018-10-01 2018-10-11 2018-10-26 2018-11-16 2018-10-29 2018-11-22 2018-11-05 2018-11-26 2019-11-05 Technical engeneer for PIU Management Approaches Selection IC-FOREST CULTURES- 017/1/2018 / Short-term Strategic Investments and Individual consultant on development of IDA / D0950 Piloting of Sustainable Post Consultant Open 10,000.00 9,231.94 Completed 2018-10-10 2018-10-11 2018-11-01 2018-11-16 2018-11-02 2018-11-16 2018-11-09 2018-11-20 2019-02-01 2019-10-10 forest management Management Approaches Selection investments IC-FOOD-SAFETY-016-2019 Strategic Investments and Individual / Short-term consultant on IDA / D0950 Piloting of Sustainable Post Consultant Open 10,000.00 4,842.75 Completed 2019-07-03 2019-06-28 2019-07-25 2019-07-24 2019-07-26 2019-07-25 2019-07-31 2019-07-26 2019-11-30 2019-12-19 the organization of Management Approaches Selection processing production IC-CFTI FRUNZE -028/2019 / Short-term consultant on organizing the logistics of Strategic Investments and Individual "Center for Forest IDA / D0950 Piloting of Sustainable Post Consultant Open 3,000.00 2,143.49 Completed 2019-08-30 2019-08-27 2019-09-27 2019-10-29 2019-09-30 2019-10-29 2019-10-01 2019-10-30 2019-10-31 2019-12-25 Technologies and Management Approaches Selection Information" on the basis of the Frunze LH IC-FS.TOURISM-027/2019 / Short-term consultant on the Strategic Investments and Individual development of feasibility IDA / D0950 Piloting of Sustainable Post Consultant Open 10,000.00 5,174.09 Completed 2019-09-06 2019-09-10 2019-10-25 2019-11-01 2019-10-25 2019-11-04 2019-10-31 2019-11-06 2020-02-29 2020-04-27 studies, logistics and Management Approaches Selection organization of tourist facilities IC(NAT)-02-6-2019 / PIU Individual Forest Sector Institutional Local Focal Point in Ysyk- IDA / D0950 Post Consultant Open 9,000.00 8,121.75 Signed 2019-10-25 2019-10-30 2019-11-22 2019-11-26 2019-11-25 2019-11-29 2019-12-01 2019-12-02 2020-12-01 Reform Kul and Naryn oblast Selection IC-LSGB-029/2019 / Short- Strategic Investments and Individual term Consultant 1 for IDA / D0950 Piloting of Sustainable Post Consultant Open 4,000.00 3,650.19 Completed 2019-11-06 2019-10-29 2019-11-29 2019-11-27 2019-12-02 2019-11-29 2019-12-09 2019-12-02 2020-03-09 2020-03-02 development of projects on Management Approaches Selection restoration of LSGB IC-LSGB-030/2019 / Short- term Consultant 2 for Strategic Investments and Individual development of projects on IDA / D0950 Piloting of Sustainable Post Consultant Open 4,000.00 3,470.99 Completed 2019-11-06 2019-10-29 2019-11-29 2019-11-27 2019-12-02 2019-11-29 2019-12-09 2019-12-02 2020-03-09 2020-03-02 restoration of degraded Management Approaches Selection municipal forests IC-MAPPING-01/2020 / Strategic Investments and Individual Consultant on municipal IDA / D0950 Piloting of Sustainable Post Consultant Open 6,000.00 4,800.50 Signed 2020-01-31 2020-02-05 2020-02-26 2020-03-04 2020-02-28 2020-03-10 2020-03-05 2020-03-11 2020-07-05 forests mapping Management Approaches Selection IC-CONST.SUPERVISION- Strategic Investments and Individual 05-2020 / Construction IDA / D0950 Piloting of Sustainable Post Consultant Open 18,000.00 13,792.24 Signed 2020-04-22 2020-04-24 2020-05-12 2020-05-21 2020-05-14 2020-06-01 2020-05-21 2020-06-01 2021-05-21 supervision consultant Management Approaches Selection IC(SSS)-EVAL.SPECIAL Strategic Investments and EQUIP.06-2020 / Technical IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 500.00 777.01 Signed 2020-04-22 2020-05-07 2020-04-30 2020-05-12 2020-05-06 2020-05-15 2020-09-06 expert on special equipment Management Approaches evaluation IC(SSS)-MF-07-2020 / Strategic Investments and Consultant under sub- IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 7,000.00 5,163.27 Signed 2020-06-10 2020-06-17 2020-06-12 2020-06-26 2020-06-15 2020-07-01 2021-06-15 component 2.3 Management Approaches IC-DIS-09-2020 / Technical Supervision Consultant on the installation of a drip Strategic Investments and Individual Under irrigation system, fencing, IDA / D0950 Piloting of Sustainable Post Consultant Open 7,500.00 0.00 2020-08-28 2020-09-01 2020-09-24 2020-09-25 2020-09-29 2021-01-29 Implementation and other projects of the Management Approaches Selection municipality and pilot leskhozes Page 10