PROCUREMENT PLAN (Textual Part) Project information: Mozambique - P171449 - Maputo Urban Transformation Project Project Implementation agency: Maputo Municipal Council Date of the Procurement Plan: January 2020 Period covered by this Procurement Plan: January – June 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento 5/2016 of March 8, 2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not Applicable PROCUREMENT Mozambique : Maputo Urban Transformation Project PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2020-01-09 2021-08-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171449 GPN Date: 2021-04-08 Project Name: Maputo Urban Transformation Project Loan / Credit No: IDA / V3130, IDA / D7490 M Executing Agency(ies): aputo Municipal Council WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MZ-CMM-187003-CW-RFB / Pending Drainage, sanitation, mobility, Single Stage - One 38,000,000.0 2024-12- IDA / V3130 Informal Settlement Upgrade Prior Request for Bids Open - International 0.00 Implementat 2021-04-23 2021-04-28 2021-06-09 2021-07-09 2021-08-13 public spaces and urban Envelope 0 30 ion equipment works MZ-CMM-186992-CW-RFB / Land demarcation works, Pending Single Stage - One 24,000,000.0 2024-09- Network and Urban IDA / V3130 Sustainable Urban Growth Prior Request for Bids Open - International 0.00 Implementat 2022-06-06 2022-06-11 2022-07-23 2022-08-22 2022-09-26 Envelope 0 20 Infrastructure Systems and ion Basic Urbanization in KaTembe GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-CMM-168529-GO-RFQ / Project Implementation and Request for Single Stage - One IDA / V3130 Post Limited 10,000.00 29,743.59 Signed 2020-05-12 2020-06-10 2020-07-07 2020-10-02 2020-09-05 Supply of Office Furniture Institutional Support Quotations Envelope MZ-CMM-186679-GO-RFB / Project Implementation and Single Stage - One IDA / V3130 Post Request for Bids Open - National 150,000.00 187,062.50 Signed 2020-08-10 2020-09-02 2020-08-15 2020-09-03 2020-09-26 2020-09-22 2020-10-26 2020-10-30 2020-11-30 2020-11-20 2021-05-29 Pickup Double Cab Vehicles Institutional Support Envelope MZ-CMM-167802-GO-RFP / Project Implementation and Request for Single Stage - One Acquisition of office IDA / V3130 Post Limited 40,000.00 0.00 Canceled 2020-05-12 2020-06-10 2020-07-07 2021-01-03 Institutional Support Quotations Envelope equipment MZ-CMM-200807-GO-RFB / Single Stage - One IDA / V3130 Informal Settlement Upgrade Post Request for Bids Open - National 200,000.00 354,971.72 Signed 2020-11-03 2021-02-10 2020-11-08 2021-02-12 2020-12-20 2021-02-25 2021-01-19 2021-04-08 2021-02-23 2021-04-26 2021-08-22 200 Hand Wash Systems Envelope MZ-CMM-194418-GO-RFQ / Project Implementation and Request for Single Stage - One IDA / V3130 Post Limited 40,000.00 0.00 Canceled 2020-09-23 2020-11-09 2021-05-08 IT Equipment Institutional Support Quotations Envelope MZ-CMM-213554-GO-RFB / Project Implementation and Single Stage - One IDA / V3130 Post Request for Bids Open - National 200,000.00 125,354.11 Signed 2021-01-22 2021-01-18 2021-01-27 2021-01-27 2021-03-10 2021-02-25 2021-03-25 2021-06-28 2021-04-22 2021-07-30 2021-10-19 IT Equipment and Software's Institutional Support Envelope MZ-CMM-215207-GO-RFQ / Project Implementation and Request for Single Stage - One Financial management IDA / V3130 Post Limited 50,000.00 57,378.01 Signed 2021-01-30 2021-02-02 2021-03-22 2021-05-21 2021-09-18 Institutional Support Quotations Envelope Software MZ-CMM-200806-GO-RFQ / Request for Single Stage - One Protection Equipment to IDA / V3130 Informal Settlement Upgrade Post Limited 230,000.00 115,076.21 Signed 2020-11-08 2021-02-10 2021-01-03 2021-04-27 2021-07-02 Quotations Envelope Prevent Covid-19 MZ-CMM-218125-GO-RFB / Acquisition of Materials for Contingent Emergency Single Stage - One IDA / V3130 Post Request for Bids Open - National 220,000.00 269,208.49 Signed 2021-02-11 2021-02-10 2021-02-16 2021-02-12 2021-03-18 2021-02-25 2021-04-02 2021-04-08 2021-04-22 2021-04-23 2022-04-22 Production of Cloth Masks to Response Envelope Prevent Cov-19 Pending MZ-CMM-224227-GO-RFQ / Project Implementation and Request for Single Stage - One IDA / V3130 Post Open - National 38,000.00 0.00 Implementati 2021-03-20 2021-05-15 2021-11-11 Videoconference Equipment Institutional Support Quotations Envelope on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-CMM-187000-NC-RFB / Under Single Stage - One Implementation of the Land IDA / V3130 Informal Settlement Upgrade Prior Request for Bids Open - International 2,500,000.00 0.00 Implementati 2021-04-23 2021-04-28 2021-06-09 2021-07-09 2021-08-13 2024-08-22 Envelope Regularization on MZ-CMM-187002-NC-RFB / Implementation of Social Pending Single Stage - One Inclusion Plans and IDA / V3130 Informal Settlement Upgrade Prior Request for Bids Open - International 1,500,000.00 0.00 Implementati 2021-04-23 2021-04-28 2021-06-09 2021-07-09 2021-08-13 2024-05-31 Envelope Combating Gender-based on Violence MZ-CMM-186990-NC-RFB / Pending Implementation of Reform to IDA / V3130 Sustainable Urban Growth Post Request for Bids 500,000.00 0.00 Implementati 2021-02-12 2021-02-17 2021-03-31 2021-07-18 2022-01-14 the construction licenses and on the issuance of DUATs MZ-CMM-186985-NC-RFB / Pending Implementation of Land Value Single Stage - One IDA / V3130 Sustainable Urban Growth Post Request for Bids Open - International 300,000.00 0.00 Implementati 2021-08-20 2021-08-25 2021-10-06 2021-11-05 2021-12-10 2024-09-30 Capture Instruments in Envelope on KaTembe MZ-CMM-186996-NC-RFB / Implementation of the Pending Maputo City Center Single Stage - One Reforms of IPRA, Physical- IDA / V3130 Post Request for Bids Open - International 1,000,000.00 0.00 Implementati 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2024-12-30 Rehabilitation Envelope Fiscal Registry and generic on Values Plant Page 1 MZ-CMM-223242-NC-RFQ / Services for Management of Community Post within the Contingent Emergency Request for Single Stage - One IDA / V3130 Post Limited 75,000.00 166,593.73 Signed 2021-03-17 2021-04-06 2021-05-12 2021-07-30 2022-05-12 Scope of the Control and Response Quotations Envelope Prevention of Covid-19 Maputo City MZ-CMM-186631-NC-RFB / Pending Project Implementation and Single Stage - One Implementation of the Unique IDA / V3130 Post Request for Bids Open - International 300,000.00 0.00 Implementati 2021-12-03 2021-12-08 2022-01-19 2022-02-18 2022-03-25 2025-03-24 Institutional Support Envelope Social Registry on MZ-CMM-218127-NC-RFQ / Integrated care services for Maputo City residents to Contingent Emergency Request for Single Stage - One IDA / V3130 Post Open - National 75,000.00 0.00 Canceled 2021-02-17 2021-02-12 2021-04-14 2022-04-14 reduce the spread of Covid- Response Quotations Envelope 19 and vulnerability to other diseases in 20 neighborhoods MZ-CMM-223215-NC-RFB / Installation of Recycling Equipment, Training and Contingent Emergency Single Stage - One Conducting Awareness IDA / V3130 Post Request for Bids Open - National 308,000.00 0.00 Canceled 2021-03-12 2021-04-06 2021-03-17 2021-04-06 2021-04-16 2021-05-02 2021-06-01 2022-06-01 Response Envelope Campaigns in 20 Neighborhoods in the Maputo City CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-CMM-168538-CS-QCBS / Consulting Services to Quality And Cost- Under prepare studies and projects IDA / V3130 Informal Settlement Upgrade Prior Open - International 1,500,000.00 0.00 2020-07-13 2020-04-24 2020-08-03 2020-05-18 2020-09-16 2020-11-05 2020-10-14 2021-02-08 2020-11-13 2021-06-16 2020-12-18 2021-01-22 2022-09-14 Based Selection Implementation on integrated intervention of informal settlements MZ-CMM-169355-CS-QCBS / Consulting Services Urban Maputo City Center Quality And Cost- IDA / V3130 Prior Open - International 500,000.00 0.00 Canceled 2020-04-27 2020-05-18 2020-07-01 2020-07-29 2020-08-28 2020-10-02 2020-11-06 2021-11-06 mobility studies and project Rehabilitation Based Selection for Baixa da Cidade MZ-CMM-171134-CS-QCBS / Development of Project Project Implementation and Quality And Cost- IDA / V3130 Post Open - International 50,000.00 0.00 Canceled 2020-05-03 2020-05-06 2020-05-24 2020-05-21 2020-07-07 2020-08-04 2020-09-03 2020-10-08 2020-11-12 2021-05-11 Information Management Institutional Support Based Selection System MZ-CMM-186410-CS-QCBS Quality And Cost- Pending / Works Supervision in IDA / V3130 Informal Settlement Upgrade Prior Open - International 1,900,000.00 0.00 2021-04-23 2021-05-14 2021-06-27 2021-07-25 2021-08-24 2021-09-28 2021-11-02 2024-11-01 Based Selection Implementation informal settlements MZ-CMM-186470-CS-QCBS / Development of Technical Maputo City Center Quality And Cost- Under Studies and Projects for IDA / V3130 Prior Open - International 1,000,000.00 0.00 2020-08-17 2020-10-27 2020-09-07 2020-10-28 2020-10-21 2021-06-18 2020-11-18 2020-12-18 2021-01-22 2021-02-26 2022-02-26 Rehabilitation Based Selection Implementation Drainage and Sanitation for the Downtown area MZ-CMM-186501-CS-QCBS Maputo City Center Quality And Cost- Pending IDA / V3130 Prior Open - International 2,250,000.00 0.00 2021-09-28 2021-10-19 2021-12-02 2021-12-30 2022-01-29 2022-03-05 2022-04-09 2024-12-24 / Works Supervision Rehabilitation Based Selection Implementation MZ-CMM-186533-CS-QCBS / Consulting services for Updating the Register, Quality And Cost- Under Revising the Urban IDA / V3130 Sustainable Urban Growth Prior Open - International 500,000.00 0.00 2020-08-12 2021-03-11 2020-09-02 2021-03-15 2020-10-16 2020-11-13 2020-12-13 2021-01-17 2021-02-21 2022-02-21 Based Selection Implementation Management Plan, Preparation of PPs and Safeguards Instruments MZ-CMM-186554-CS-QCBS Quality And Cost- Pending / Works Supervision at IDA / V3130 Sustainable Urban Growth Prior Open - International 720,000.00 0.00 2022-06-06 2022-06-27 2022-08-10 2022-09-07 2022-10-07 2022-11-11 2022-12-16 2023-12-16 Based Selection Implementation KaTembe MZ-CMM-200797-CS-LCS / Project Implementation and Least Cost Under IDA / V3130 Post Open - National 300,000.00 0.00 2020-11-06 2020-10-24 2020-11-27 2020-10-27 2021-01-10 2021-04-14 2021-02-07 2021-03-09 2021-04-13 2021-05-18 2021-11-14 External Auditing Institutional Support Selection Implementation MZ-CMM-200798-CS-QBS / Project Implementation and Quality Based Under IDA / V3130 Post Open - International 150,000.00 0.00 2020-11-06 2020-11-10 2020-11-27 2020-11-16 2021-01-10 2021-02-07 2021-03-09 2021-04-08 2021-05-13 2022-05-13 PBC's Verification Agent Institutional Support Selection Implementation MZ-CMM-213646-CS-QCBS / Consulting Services for Conception, Development and Implementation of an Project Implementation and Quality And Cost- Under IDA / V3130 Post Open - National 100,000.00 0.00 2021-01-18 2021-01-19 2021-01-25 2021-01-27 2021-03-01 2021-05-05 2021-03-29 2021-04-28 2021-06-07 2021-07-12 2022-12-04 Integrated Information Institutional Support Based Selection Implementation Management System for Maputo Urban Transformation Project MZ-CMM-216360-CS-QCBS / Elaboration of Participatory Plans for Social Inclusion, Quality And Cost- Under Gender Equality and for IDA / V3130 Informal Settlement Upgrade Prior Open - International 600,000.00 0.00 2021-01-29 2021-01-28 2021-02-19 2021-01-28 2021-04-04 2021-05-07 2021-05-02 2021-06-01 2021-07-06 2021-08-10 2022-08-10 Based Selection Implementation Combating GBV for the Neighbourhoods in Informal Settlements MZ-CMM-186629-CS-CQS / Consulting Services to support Consultant Project Implementation and Pending the implementation of the IDA / V3130 Post Qualification Open - International 170,000.00 0.00 2021-12-03 2021-12-24 2022-02-06 2022-03-08 2022-04-12 2025-03-24 Institutional Support Implementation Modernization of Selection Administrative Processes MZ-CMM-186481-CS-QCBS / Preparation of technical Maputo City Center Quality And Cost- studies and projects for the IDA / V3130 Prior Open - International 1,000,000.00 0.00 Canceled 2020-08-27 2020-09-17 2020-10-31 2020-11-28 2020-12-28 2021-02-01 2021-03-08 2022-03-08 Rehabilitation Based Selection improvement of public spaces and urban facilities Page 2 MZ-CMM-186540-CS-QCBS / Technical Studies and Quality And Cost- Executive Project for IDA / V3130 Sustainable Urban Growth Prior Open - International 1,000,000.00 0.00 Canceled 2021-07-07 2021-07-28 2021-09-10 2021-10-08 2021-11-07 2021-12-12 2022-01-16 2023-01-16 Based Selection Infrastructures Development in KaTembe MZ-CMM-168539-CS-QCBS / Consultancy Services for Maputo City Center Quality And Cost- IDA / V3130 Prior Open - International 500,000.00 0.00 Canceled 2020-06-10 2020-04-24 2020-07-01 2020-08-14 2020-09-11 2020-10-11 2020-11-15 2020-12-20 2022-08-12 drainage studies and projects Rehabilitation Based Selection for Baixa da Cidade MZ-CMM-168537-CS-QCBS / Consultancy Services to Quality And Cost- prepare studies and projects IDA / V3130 Sustainable Urban Growth Prior Open - International 750,000.00 0.00 Canceled 2020-06-29 2020-07-20 2020-09-02 2020-09-30 2020-10-30 2020-12-04 2021-01-08 2022-01-08 Based Selection for the sustainable development of Katembe MZ-CMM-200796-CS-QCBS / Environmental and Social Quality And Cost- Under IDA / V3130 Informal Settlement Upgrade Post Open - International 500,000.00 0.00 2021-05-14 2021-05-14 2021-06-04 2021-05-17 2021-07-18 2021-08-15 2021-09-14 2021-10-19 2021-11-23 2022-11-23 Impact Assessment for Based Selection Implementation Components 1, 2 and 3 MZ-CMM-168536-CS-QCBS / Consultancy Services for Project Implementation and Quality And Cost- Pending addressing, preparing, IDA / V3130 Prior Open - International 500,000.00 0.00 2021-05-25 2021-06-15 2021-07-29 2021-08-26 2021-09-25 2021-10-30 2021-12-04 2022-12-04 Institutional Support Based Selection Implementation updating and expanding the physical and fiscal registration MZ-CMM-168535-CS-QCBS / Consultancy Services to Project Implementation and Quality And Cost- IDA / V3130 Post Open - International 100,000.00 0.00 Canceled 2020-05-20 2020-08-12 2020-06-10 2020-07-24 2020-08-21 2020-09-20 2020-10-25 2020-11-29 2021-11-29 develop unified social Institutional Support Based Selection Municipal cadaster. MZ-CMM-227454-CS-QCBS Project Implementation and Quality And Cost- Under / Development of Unique IDA / V3130 Post Open - National 100,000.00 0.00 2021-04-09 2021-04-08 2021-04-30 2021-06-13 2021-07-11 2021-08-10 2021-09-14 2021-10-19 2022-10-19 Institutional Support Based Selection Implementation Municipal Social Registry MZ-CMM-169356-CS-QCBS / Consulting services for Maputo City Center Quality And Cost- public spaces and urban IDA / V3130 Prior Open - International 500,000.00 0.00 Canceled 2020-04-27 2020-05-18 2020-07-01 2020-07-29 2020-08-28 2020-10-02 2020-11-06 2021-11-06 Rehabilitation Based Selection equipment studies and project for Baixa da Cidade MZ-CMM-229289-CS-QCBS / Preparation of Studies, Plans and Detailed Project for the Quality And Cost- Under IDA / V3130 Sustainable Urban Growth Prior Open - International 1,500,000.00 0.00 2021-04-25 2021-05-16 2021-06-29 2021-07-27 2021-08-26 2021-09-30 2021-11-04 2022-11-04 Implementation of the Based Selection Implementation KaTembe Landfill and Closure of the Hulene Dump MZ-CMM-237534-CS-CQS / Consultant Project Implementation and Under Project Team Capacity IDA / V3130 Post Qualification Open - National 15,000.00 0.00 2021-06-07 2021-06-02 2021-06-21 2021-06-03 2021-07-19 2021-07-24 2021-08-14 2021-11-12 Institutional Support Implementation Building Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual MZ-CMM-152216-CS-INDV / IDA / V3130 Informal Settlement Upgrade Prior Consultant Open 60,000.00 129,853.86 Signed 2020-01-10 2020-01-16 2020-02-28 2020-06-23 2020-03-20 2020-06-23 2020-04-24 2020-06-24 2021-04-24 Procurement Specialist Selection MZ-CMM-167544-CS-INDV / Individual Project Implementation and Senior Finance Municipal IDA / V3130 Post Consultant Open 60,000.00 152,000.00 Signed 2020-04-16 2020-04-18 2020-06-04 2020-08-20 2020-06-25 2020-10-06 2020-07-30 2020-10-08 2021-07-30 Institutional Support Management Advisor Selection MZ-CMM-168533-CS-QCBS / Consultancy Services for the Individual Project Implementation and Under elaboration of legal and IDA / V3130 Post Consultant Open 100,000.00 0.00 2020-05-27 2020-10-01 2020-07-15 2020-08-05 2020-09-09 2021-03-08 Institutional Support Implementation technical studies for IPRA and Selection LVC revenues maximization MZ-CMM-171140-CS-INDV / Senior Technician in Spatial Individual Project Implementation and Planning and Urban Soil IDA / V3130 Post Consultant Open 60,000.00 75,000.00 Signed 2020-05-05 2020-04-30 2020-06-23 2020-12-11 2020-07-14 2021-02-17 2020-08-18 2021-02-26 2021-02-14 Institutional Support Management to integrate the Selection PTUM Technical Team MZ-CMM-171147-CS-INDV / Individual Project Implementation and Senior Technician in IDA / V3130 Post Consultant Open 60,000.00 67,500.00 Signed 2020-05-05 2020-04-30 2020-06-23 2020-08-28 2020-07-14 2020-09-02 2020-08-18 2020-09-30 2021-02-14 Institutional Support Architecture Selection Individual MZ-CMM-171150-CS-INDV / Project Implementation and IDA / V3130 Post Consultant Open 60,000.00 78,000.00 Signed 2020-05-05 2020-04-30 2020-06-23 2020-11-03 2020-07-14 2020-11-05 2020-08-18 2020-11-13 2021-02-14 Technical Team Leader Institutional Support Selection MZ-CMM-171151-CS-INDV / Individual Project Implementation and Senior Drain Technician of the IDA / V3130 Post Consultant Open 60,000.00 67,500.00 Signed 2020-05-05 2020-04-30 2020-06-23 2020-09-16 2020-07-14 2020-11-05 2020-08-18 2020-11-13 2021-02-14 Institutional Support technical team Selection MZ-CMM-171152-CS-INDV / Senior Technician in Social Individual Project Implementation and Inclusion and Gender to IDA / V3130 Post Consultant Open 60,000.00 60,000.00 Signed 2020-06-02 2020-04-30 2020-07-21 2020-12-15 2020-08-11 2021-01-25 2020-09-15 2021-02-22 2021-03-14 Institutional Support integrate the technical team Selection of PTUM MZ-CMM-172416-CS-INDV / Individual senior water and sanitation Project Implementation and IDA / V3130 Post Consultant Open 60,000.00 63,504.00 Signed 2020-05-08 2020-05-08 2020-06-26 2020-08-25 2020-07-17 2021-05-25 2020-08-21 2021-06-01 2021-02-17 technician of the technical Institutional Support Selection team MZ-CMM-175939-CS-INDV / Individual Project Implementation and Under Senior Advisor for Gender and IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-06-02 2020-09-03 2020-07-21 2020-08-11 2020-09-15 2020-12-14 Institutional Support Implementation Social Inclusion Selection Page 3 MZ-CMM-172422-CS-INDV / Individual Consultant for the Individual definition and implementation Project Implementation and IDA / V3130 Post Consultant Open 60,000.00 0.00 Canceled 2020-05-10 2020-05-08 2020-06-28 2020-07-19 2020-08-23 2021-02-19 of an integrated information Institutional Support Selection management system for the project MZ-CMM-176004-CS-INDV / Individual Project Implementation and Junior Technician in Social IDA / V3130 Post Consultant Open 30,000.00 58,618.26 Signed 2020-06-02 2020-06-04 2020-07-21 2020-09-02 2020-08-11 2020-09-08 2020-09-15 2020-09-21 2020-12-14 Institutional Support Inclusion and Gender Selection MZ-CMM-175981-CS-INDV / Individual Junior Water and Sanitation Project Implementation and IDA / V3130 Post Consultant Open 30,000.00 58,618.26 Signed 2020-06-02 2020-06-04 2020-07-21 2020-08-25 2020-08-11 2020-08-26 2020-09-15 2020-09-11 2020-12-14 Technician of the Project's Institutional Support Selection Technical Team MZ-CMM-176001-CS-INDV / Individual Junior Technician in Spatial Project Implementation and IDA / V3130 Post Consultant Open 30,000.00 35,313.57 Signed 2020-06-02 2020-06-04 2020-07-21 2020-11-03 2020-08-11 2020-11-06 2020-09-15 2020-11-16 2020-12-14 Planning and Urban Soil Institutional Support Selection Management MZ-CMM-175990-CS-INDV / Individual Project Implementation and Junior Technician in IDA / V3130 Post Consultant Open 30,000.00 70,799.99 Signed 2020-06-02 2020-06-04 2020-07-21 2020-09-03 2020-08-11 2020-09-02 2020-09-15 2020-09-16 2020-12-14 Institutional Support Architecture Selection Individual MZ-CMM-175998-CS-INDV / Project Implementation and IDA / V3130 Post Consultant Open 30,000.00 94,395.21 Signed 2020-06-02 2020-06-04 2020-07-21 2020-11-25 2020-08-11 2020-12-03 2020-09-15 2021-01-27 2020-12-14 Junior Drainage Technician Institutional Support Selection Individual MZ-CMM-186605-CS-INDV / Project Implementation and IDA / V3130 Post Consultant Open 120,000.00 93,764.82 Signed 2020-08-18 2020-09-14 2020-10-06 2021-04-28 2020-10-27 2021-06-29 2020-12-01 2021-07-01 2022-11-21 Infrastructure Senior Advisor Institutional Support Selection MZ-CMM-186609-CS-INDV / Individual Senior Technical Advisor on Project Implementation and Under IDA / V3130 Post Consultant Open 120,000.00 0.00 2020-08-18 2020-10-07 2020-10-06 2020-10-27 2020-12-01 2022-11-21 Land Use Planning and Urban Institutional Support Implementation Selection Land Management MZ-CMM-191816-CS-INDV / Individual Consulting services for Project Implementation and Under IDA / V3130 Post Consultant Open 10,000.00 0.00 2020-09-10 2020-09-09 2020-10-13 2020-10-22 2020-11-26 2021-05-25 preparation of Project Institutional Support Implementation Selection Implementation Manual MZ-CMM-200801-CS-INDV / Individual Project Implementation and Under Solid Waste Management IDA / V3130 Post Consultant Open 160,000.00 0.00 2020-11-06 2021-03-06 2020-12-25 2021-08-02 2021-01-15 2021-02-19 2021-08-18 Institutional Support Implementation Advisor Selection MZ-CMM-200803-CS-INDV / Individual Project Implementation and Under Solid Waste Management IDA / V3130 Post Consultant Open 120,000.00 0.00 2020-11-06 2021-04-19 2020-12-25 2021-01-15 2021-02-19 2021-08-18 Institutional Support Implementation Senior Technician Selection MZ-CMM-200805-CS-INDV / Individual Project Implementation and Under Solid Waste Management IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-11-06 2021-04-19 2020-12-25 2021-01-15 2021-02-19 2021-08-18 Institutional Support Implementation Junior Technician Selection MZ-CMM-200799-CS-INDV / Individual Project Implementation and Environmental and Social IDA / V3130 Post Consultant Open 30,000.00 61,959.33 Signed 2020-11-02 2020-11-10 2020-12-21 2021-04-30 2021-01-11 2021-05-11 2021-02-15 2021-05-31 2022-02-15 Institutional Support Safeguards Assistant Selection MZ-CMM-227393-CS-INDV / Individual Project Implementation and Financial Management IDA / V3130 Post Consultant Direct 60,000.00 79,187.75 Signed 2021-03-31 2021-04-08 2021-04-07 2021-04-21 2021-04-09 2021-04-22 2021-04-16 2021-04-23 2022-04-16 Institutional Support Specialist Selection Individual MZ-CMM-227397-CS-INDV / Project Implementation and IDA / V3130 Post Consultant Direct 60,000.00 83,507.08 Signed 2021-03-31 2021-04-08 2021-04-03 2021-04-15 2021-04-05 2021-04-20 2021-04-08 2021-04-23 2022-04-08 Social Safeguards Specialist Institutional Support Selection MZ-CMM-227399-CS-INDV / Individual Project Implementation and Environmental Safeguards IDA / V3130 Post Consultant Direct 60,000.00 83,507.08 Signed 2021-03-31 2021-04-08 2021-04-05 2021-04-15 2021-04-07 2021-04-20 2021-04-12 2021-04-23 2022-04-12 Institutional Support Specialist Selection MZ-CMM-174529-CS-INDV / Individual consultancy for the elaboration of the Individual methodology for updating the IDA / V3130 Sustainable Urban Growth Post Consultant Open 60,000.00 0.00 Canceled 2020-05-25 2020-05-21 2020-07-13 2020-08-03 2020-09-07 2021-03-06 physical tax register, the Selection generic figures map and the IPRA calculation Individual MZ-CMM-186617-CS-INDV / Project Implementation and IDA / V3130 Post Consultant Open 120,000.00 0.00 Canceled 2020-08-19 2020-10-07 2020-10-28 2020-12-02 2022-12-01 Senior Social Inclusion Advisor Institutional Support Selection Individual MZ-CMM-167546-CS-INDV / Project Implementation and IDA / V3130 Post Consultant Open 60,000.00 0.00 Canceled 2020-06-03 2020-07-22 2020-08-12 2020-09-16 2021-09-16 Senior Governance Advisor Institutional Support Selection Individual MZ-CMM-167545-CS-INDV / Project Implementation and IDA / V3130 Post Consultant Open 60,000.00 0.00 Canceled 2020-04-16 2020-04-21 2020-06-04 2020-06-25 2020-07-30 2021-07-30 Senior Urban Planning Advisor Institutional Support Selection MZ-CMM-175992-CS-INDV / Individual Junior Technician of Mobility Project Implementation and IDA / V3130 Post Consultant 30,000.00 0.00 Canceled 2020-06-02 2020-06-04 2020-07-21 2020-08-11 2020-09-15 2020-12-14 and Roads of the project's Institutional Support Selection Technical Team MZ-CMM-200802-CS-INDV / Individual Project Implementation and Under Senior Technician for Urban IDA / V3130 Post Consultant Open 120,000.00 0.00 2021-05-14 2021-04-08 2021-07-02 2021-07-29 2021-07-23 2021-08-27 2022-08-27 Institutional Support Implementation Mobility Selection MZ-CMM-200804-CS-INDV / Individual Project Implementation and Junior Technician for Urban IDA / V3130 Post Consultant Open 60,000.00 30,110.12 Signed 2021-05-21 2021-04-08 2021-07-09 2021-07-30 2021-07-30 2021-08-03 2021-09-03 2021-08-06 2022-09-01 Institutional Support Mobility Selection Individual MZ-CMM-171156-CS-INDV / Project Implementation and IDA / V3130 Post Consultant Open 60,000.00 0.00 Canceled 2020-05-11 2020-04-30 2020-06-29 2020-07-20 2020-08-24 2021-02-20 Urban Mobility Consultant Institutional Support Selection Page 4 MZ-CMM-186611-CS-INDV / Individual Project Implementation and Municipal Governance Senior IDA / V3130 Post Consultant Open 120,000.00 0.00 Canceled 2020-08-19 2020-10-09 2020-10-07 2020-10-28 2020-12-02 2022-11-22 Institutional Support Advisor Selection Individual MZ-CMM-228447-CS-INDV / Project Implementation and Under IDA / V3130 Post Consultant Open 120,000.00 0.00 2021-04-12 2021-04-13 2021-05-31 2021-06-21 2021-07-26 2023-07-26 Municipal Governance Advisor Institutional Support Implementation Selection MZ-CMM-229298-CS-INDV / Individual Project Implementation and Under Communication and Media IDA / V3130 Post Consultant Open 30,000.00 0.00 2021-04-20 2021-04-15 2021-06-08 2021-06-29 2021-08-03 2022-08-03 Institutional Support Implementation Junior Specialist Selection MZ-CMM-229296-CS-INDV / Individual Project Implementation and Under Website Development for IDA / V3130 Post Consultant Open 10,000.00 0.00 2021-04-20 2021-04-15 2021-06-08 2021-06-29 2021-08-03 2022-01-30 Institutional Support Implementation MUTP Selection Individual MZ-CMM-200800-CS-INDV / Project Implementation and IDA / V3130 Post Consultant Open 36,000.00 0.00 Canceled 2020-10-30 2020-10-27 2020-12-18 2021-05-03 2021-01-08 2021-02-12 2021-08-11 Procurement Assistant Institutional Support Selection Individual MZ-CMM-248732-CS-INDV / Project Implementation and IDA / D7490 Prior Consultant Open 84,000.00 0.00 Under Review 2021-08-20 2021-09-15 2021-09-22 2021-10-06 2022-10-01 Procurement Specialist II Institutional Support Selection MZ-CMM-248743-CS-INDV / Individual Project Implementation and Pending Team Leader for the Technical IDA / D7490 Post Consultant Open 84,000.00 0.00 2021-08-31 2021-10-19 2021-11-09 2021-12-14 2022-12-14 Institutional Support Implementation Team Selection MZ-CMM-248739-CS-INDV / Individual Project Implementation and Pending Monitoring & Evaluation IDA / D7490 Post Consultant Limited 84,000.00 0.00 2021-08-20 2021-08-23 2021-08-25 2021-08-30 2022-08-30 Institutional Support Implementation Specialist Selection Page 5