The World Bank Report No: ISR2081 Implementation Status & Results Mauritania Public Disclosure Copy MR - Business Environment Enhancement Project (P102031) Operation Name: MR - Business Environment Enhancement Project (P102031) Project Stage: Implementation Seq.No: 6 Status: ARCHIVED Last Modified Date: 08-Mar-2011 Country: Mauritania Approval FY: 2008 Product Line: IBRD/IDA Region: AFRICA Lending Instrument: Specific Investment Loan Implementing Agency(ies): CPI former DGPIP Key Dates Board Approval Date 22-May-2008 Original Closing Date 30-Nov-2013 Planned Mid Term Review Date 28-Jun-2011 Last Archived ISR Date 29-Jun-2010 Effectiveness Date 28-Dec-2009 Revised Closing Date 30-Nov-2013 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) The overall project development objective (PDO) is to enhance the business climate through improvements in the financial, legal and judiciary sectors, and regulatory environment for business. This would facilitate private-sector led growth/investment in the economy and improve the services of the public enterprises that directly impact private sector growth and development. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost 1. Improving the Business Climate to Foster Private Sector Development 3.00 2. Building Public-Private Partnerships and Productivity Enhancement 1.50 3. Support for Project Implementation 0.50 Public Disclosure Copy Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Unsatisfactory Overall Implementation Progress (IP) Satisfactory Moderately Unsatisfactory Overall Risk Rating High Implementation Status Overview Official use only. Not for public disclosure. Results Page 1 of 5 The World Bank Report No: ISR2081 Project Development Objective Indicators Public Disclosure Copy Indicator Baseline Current End Target Indicator Name Value Value Value Non performing loans (NPLs) at commercial banks improve 20% 28% 15% Date Date Date 01-Jan-2008 30-Jun-2010 30-Nov-2013 Type Unit of Measure Comment Comment Comment Custom Indicator Text Central Bank (BCM) latest available data Indicator Baseline Current End Target Indicator Name Value Value Value Number of procedures required to establish a business is reduced 11 9 5 Date Date Date 01-Jan-2008 30-Jun-2010 30-Nov-2013 Type Unit of Measure Comment Comment Comment Custom Indicator Text Doing Business 2011 data Indicator Baseline Current End Target Indicator Name Value Value Value Percent of Commercial and financial court decisions that are published 0% 0 80% on the GRIM website increases Date Date Date 01-Jan-2008 31-Dec-2010 30-Nov-2013 Type Unit of Measure Comment Comment Comment Custom Indicator Text No output yet. Intermediate Results Indicators Public Disclosure Copy Indicator Baseline Current End Target Indicator Name Value Value Value Cost to start up a business (as a percent of GNI per capita) decreases 56% 33.6 35% Date Date Date 01-Jan-2008 30-Jun-2010 30-Nov-2013 Type Unit of Measure Comment Comment Comment Custom Indicator Text Doing Business 2011 data Page 2 of 5 The World Bank Report No: ISR2081 Indicator Baseline Current End Target Public Disclosure Copy Indicator Name Value Value Value Number of days required to start a business decreases 65 19 30 Date Date Date 01-Jan-2008 30-Jun-2010 30-Nov-2013 Type Unit of Measure Comment Comment Comment Custom Indicator Text Doing Business 2011 data Indicator Baseline Current End Target Indicator Name Value Value Value Percentage of tax on gross revenue decreases 107 68.4 60 Date Date Date 01-Jan-2008 30-Jun-2010 30-Nov-2013 Type Unit of Measure Comment Comment Comment Custom Indicator Text Doing Business 2011 data Indicator Baseline Current End Target Indicator Name Value Value Value Number of tax payments per year decreases 38 38 20 Date Date Date 01-Jan-2008 30-Jun-2010 30-Nov-2013 Type Unit of Measure Comment Comment Comment Custom Indicator Text Doing Business 2010 data Indicator Baseline Current End Target Indicator Name Value Value Value Number of performance contracts signed for key public enterprises 0 0 5 Public Disclosure Copy (Somelec, Somagaz, SNDE, Mauripost & Port of Nouakchott) Date Date Date increases 01-Jan-2008 31-Dec-2010 30-Nov-2013 Type Unit of Measure Comment Comment Comment Custom Indicator Text Work started but no output yet Page 3 of 5 The World Bank Report No: ISR2081 Indicator Baseline Current End Target Public Disclosure Copy Indicator Name Value Value Value Investment plan for electricity sector is completed No investment plan exists 0 Plan is completed and adopted Date Date Date 01-Jan-2008 31-Dec-2010 30-Nov-2013 Type Unit of Measure Comment Comment Comment Custom Indicator Text Consultant has been hired, work is on-going but not completed yet Indicator Baseline Current End Target Indicator Name Value Value Value Volume of Bank Support: Enabling Environment - Microfinance 0.00 1000000.00 Date Date Date 30-Jun-2010 30-Nov-2013 Type Unit of Measure Comment Comment Comment Core Indicator Amount(USD) No input yet Indicator Baseline Current End Target Indicator Name Value Value Value Volume of Bank Support: Enabling Environment - SME 0.00 100000.00 1000000.00 Date Date Date 01-Jan-2008 30-Jun-2010 30-Nov-2013 Type Unit of Measure Comment Comment Comment Core Indicator Amount(USD) Studies, workshop and training Data on Financial Performance (as of 13-Jan-2011) Financial Agreement(s) Key Dates Public Disclosure Copy Project Loan No. Status Approval Date Signing Date Effectiveness Date Closing Date P102031 IDA-44480 Effective 22-May-2008 01-Jul-2008 28-Dec-2009 30-Nov-2013 Disbursements (in Millions) Project Loan No. Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P102031 IDA-44480 Effective XDR 3.20 3.20 0.00 0.60 2.60 19.00 Disbursement Graph Page 4 of 5 The World Bank Report No: ISR2081 Public Disclosure Copy Key Decisions Regarding Implementation Official use only. Not for public disclosure. Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Public Disclosure Copy Page 5 of 5