Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 10, 2017 (Original procurement plan). 2. Date of General Procurement Notice: NA 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. Goods Above US$ 4 million All 2. Works Above US$ 15 million All 3. Non-Consultant Services Above US$ 4 million All 2. Prequalification. NA. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: The Project Implementation Manual (PIM) makes reference to all applicable procurement guidelines and manuals including the Commune/Sangkat Fund PIM for small-scale infrastructure activities carried out by the sub-national levels (Commune/Sangkat), has been developed for this project. 4. Any Other Special Procurement Arrangements: 5 packages (goods) would be financed under retroactive financing 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness. 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comments No. on ed stic by Bank Cost Prefe (Prior / US$ rence Post) million (yes/ no) Communi 5.48 60 No Post procured by ty Communes/ June 12, 2017 infrastruc Sangkats tures individually for the whole life of the project Procure 0.92 8 No Post will be ment of procured vehicles, centrally at office the beginning of equipme project nt, office implementa furniture, tion motorcyc (shopping les, etc. method) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Selection of Consulting firms Above US$ 2 million All 2. Selection of Individual Above US$ All Consultant 400,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 11 individual consultants would be financed through retroactive financing. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 6 7 Ref. Description Estimate Pac Review Comments No. d kag by Bank Cost es (Prior / US$ Post) million Producer Group 0.34 1 Post QCBS method Mobilization for June 12, 2017 Siem Reap (NGO package) Self-help Group 0.27 1 Post QCBS method Mobilization for SRP (NGO) Human Resources 0.92 2 Post QBS method Development Services Provider (HRDSP) for Siem Reap (NGO/Firm) Consulting firms for 0.175 1 Post CQS method baseline survey, impact survey, and final impact survey, and External financial auditing Individual 2.93 126 Post Selection of consultants for individual supporting the consultant. national level and sub-national level project entities (finance, procurement, infrastructure, community development, micro-finance experts, livelihood specialists, etc.) June 12, 2017 PROCUREMENT Cambodia : KH - Livelihood Enhancement and Association of the Poor Project (LEAP) PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2017-06-12 2021-08-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153591 GPN Date: Project Name: KH - Livelihood Enhancement and Association of the Poor Project (LEAP) Loan / Credit No: IDA / 59600 Ministry of Interior Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Pending KH-MOI-99874-CW-RFQ / Component 3: Project Request for Single Stage - One 2019-05- IDA / 59600 Post Open - National 30,000.00 0.00 Implementat 2019-03-06 2019-04-17 Office Renovation at PCO-MOI Management Quotations Envelope 17 ion KH-MOI-99875-CW-CDD / The rehabilitation laterite road Component 1: Improving Pending (Length 2400m, Width 4.00m, Community Driven 2019-09- IDA / 59600 Livelihoods for Rural Poor Post Open - National 28,341.00 0.00 Implementat 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 0.15m thick) and Single Pipe Development 09 and Vulnerable Households ion Culvert Ø 1.0m (2 units) for Anlong Samnar, Chi Kraeng. KH-MOI-99886-CW-CDD / The rehabilitation laterite road ( Length 1500m, Width Component 1: Improving Pending Community Driven 2019-08- 4.00m, 0.15m Thick) and IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,208.00 0.00 Implementat 2019-03-01 2019-03-08 2019-04-30 2019-05-07 2019-05-21 Development 19 Construction of Box Culver and Vulnerable Households ion heigth 2m with Stop Log (1 unit) for Doun Kaev, Puok. KH-MOI-99878-CW-CDD / The rehabilitation laterite road Component 1: Improving Pending Community Driven 2019-07- (Length 2419m, Width 3.50m, IDA / 59600 Livelihoods for Rural Poor Post Open - National 25,921.00 0.00 Implementat 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 Development 11 0.15m thick) for Chi Kraeng, and Vulnerable Households ion Chi Kraeng. KH-MOI-99880-CW-CDD / The rehabilitation laterite road (Length 2090m, Width 4.00m, 0.15m thick) and Construction Component 1: Improving Pending Community Driven 2019-07- of Single Pipe Culvert Ø 0.6m IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,721.00 0.00 Implementat 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 Development 11 (1 unit), Single Pipe Culvert Ø and Vulnerable Households ion 0.8m (1 unit) and Single Pipe Culvert Ø 1.0m (1unit) for Dan Run, Soutr Nikom. KH-MOI-99881-CW-CDD / The rehabilitation laterite road (Length 1550m, Width 4.00m, Component 1: Improving Pending 0.15m thick), Single Pipe Community Driven 2019-09- IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,965.00 0.00 Implementat 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 Culvert Ø 1.0m (1unit) and Development 19 and Vulnerable Households ion Construction of Double Pipe Culvert Ø 0.8m (5units), for Ballangk, Prasat Bakong. KH-MOI-99887-CW-CDD / Construction of Box Culvert heigth 2m with stop Log (1unit), Box Culvert heigth Component 1: Improving Pending Community Driven 2019-09- 1.5m with stop Log (1unit) IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,896.00 0.00 Implementat 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 Development 09 Pipe Culver Ø 0.8m with Stop and Vulnerable Households ion Log (1unit) and Single Pipe Culvert Ø 0.8m (4 unit) for Sasar Sdam, Puok. KH-MOI-99888-CW-CDD / Construction of Reinforced Component 1: Improving Pending Concrete Road (Lengh 260m, Community Driven 2019-09- IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,417.00 0.00 Implementat 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 width 5.00m, 0.15m thick) for Development 09 and Vulnerable Households ion Kampong Thkov, Kralanh. Total: 0.260 km KH-MOI-99890-CW-CDD / The rehabilitation ponds size (60mx30mx5m), Component 1: Improving Pending (30mx25mx5m), Community Driven 2019-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,949.00 0.00 Implementat 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 (40mx20mx5m), Development 11 and Vulnerable Households ion (50mx50mx5m) for Slaeng Spean, Srei Snam. Total:4 Places KH-MOI-99891-CW-CDD / The rehabilitation laterite road Component 1: Improving Pending Community Driven 2019-09- (1.450km) and Single Pipe IDA / 59600 Livelihoods for Rural Poor Post Open - National 32,660.00 0.00 Implementat 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 Development 09 Culvert Ø 1.0m (3 units) for and Vulnerable Households ion Svay Chek, Angkor Thum. KH-MOI-99892-CW-CDD / The rehabilitation laterite road ( Length 2520m, Width Component 1: Improving Pending Community Driven 2019-09- 4.00m, 0.15 Thick) and IDA / 59600 Livelihoods for Rural Poor Post Open - National 34,064.00 0.00 Implementat 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 Development 09 Construction of Single Pipe and Vulnerable Households ion Culvert Ø 1.0m (2 unit) for Leang Dai, Angkor Thum. KH-MOI-99893-CW-CDD / The rehabilitation laterite road (Length 1080m, Width 4.00m, Component 1: Improving Pending 0.15m thick) and Construction Community Driven 2019-08- IDA / 59600 Livelihoods for Rural Poor Post Open - National 27,869.20 0.00 Implementat 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-05-07 of Single Pipe Culvert Ø 0.8m Development 05 and Vulnerable Households ion (1 unit) and Triple Pipe Culvert, Ø 1.0m (3 unit) for Ta Siem, Svay Leu. KH-MOI-99894-CW-CDD / Construction of Reinforced Component 1: Improving Pending Community Driven 2019-09- Concrete Road (Length 445m, IDA / 59600 Livelihoods for Rural Poor Post Open - National 48,510.00 0.00 Implementat 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 Development 09 Width 3.50m, 0.15m thick) and Vulnerable Households ion for khnang Phnum, Svay Leu. Page 1 KH-MOI-99889-CW-CDD / The rehabilitation laterite road Component 1: Improving Pending Community Driven 2019-09- (Length 2600m, Width 5.00m, IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,932.00 0.00 Implementat 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 Development 09 0.15m thick) for Klang Hay, and Vulnerable Households ion Srei Snam. Total: 2.600 km KH-MOI-110153-CW-CDD / Construction:1- Reinforcement concrete road:(L353m, W 4m, T0.15m) Component 1: Improving Pending Community Driven 2019-09- and drainage system (L353m, IDA / 59600 Livelihoods for Rural Poor Post Open - National 89,712.00 0.00 Implementat 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 Development 09 0.6m ) and 2-Reinforcement and Vulnerable Households ion concrete road (L357m, W 4m, T 0.15m) in Sangkat Dangkao, Khan Dangkao KH-MOI-110154-CW-CDD / Construction of Reinforcement concrete road and Drainage System: 1- Road Component 1: Improving Pending (100m) , 2-Road (171m ), 3- Community Driven 2019-09- IDA / 59600 Livelihoods for Rural Poor Post Open - National 98,080.00 0.00 Implementat 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 Road (52m), 4- Road(88m) ,5- Development 24 and Vulnerable Households ion Road (90m), 6- Road (93m) and 7-Road (L128m) in Sangkat Prey Veaeng, Khan Dangkao KH-MOI-110159-CW-CDD / Construction of reinforcement concrete road:(466m, width 5m, thickness 0.15m ), 2- Component 1: Improving Pending Community Driven 2019-09- Road:(312m, width 4m, IDA / 59600 Livelihoods for Rural Poor Post Open - National 105,204.00 0.00 Implementat 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 Development 24 thickness 0.15m ) and and Vulnerable Households ion drainage system:(312m,cross section 0.6m) in Sangkat Kork Roka, Khan Preak Pnov KH-MOI-110165-CW-CDD / Construction of reinforcement concrete road and and drainage system in Prey Spueu Component 1: Improving Pending & Prey Sandaek, Sangkat Community Driven 2019-10- IDA / 59600 Livelihoods for Rural Poor Post Open - National 84,579.00 0.00 Implementat 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 Chaom Chau 2, Khan Por Sen Development 09 and Vulnerable Households ion Chey (663m) and drainage system (523m) in Sangkat Chaom Chau 2, Khan Por Sen Chey KH-MOI-110174-CW-CDD / Construction of reinforcement concrete: 1- Road(124m), 2- Road (137m). 3- Road (117m Component 1: Improving Pending Community Driven 2019-10- ). 4-Installation of Sola street IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,250.00 0.00 Implementat 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 Development 09 lighting and poles (117m), and Vulnerable Households ion and (139m ) in Sangkat Chbar Ampov Ti Pir, Khan Chbar Ampov KH-MOI-110155-CW-CDD / Construction of reinforcement concrete: 1- Road (99m) ,1- Road(101m), 2-Road(60m), 3- Drainage system:(9m), 4- Component 1: Improving Pending Community Driven 2019-12- Installation of Sola street IDA / 59600 Livelihoods for Rural Poor Post Open - National 28,703.49 0.00 Implementat 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 Development 25 lighting and poles and Vulnerable Households ion (120m),(439m),(439m) and (98m) in Sangkat Chrang Chamreas Ti Muoy,Khan Russey Keo KH-MOI-110151-CW-CDD / Construction: 1- Reinforcement concrete road (340m) and drainage system:(448m), 2-Road Component 1: Improving Pending (L130m) and drainage system Community Driven 2019-12- IDA / 59600 Livelihoods for Rural Poor Post Open - National 171,670.08 0.00 Implementat 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 (130m), 3-Road (120m) and Development 25 and Vulnerable Households ion drainage system:(250m), 4- Road (238m) and drainage system (238m) in Sangkat Trapeang Krasang, Khan Por Sen Chey KH-MOI-110147-CW-CDD / Construction:1-Reinforcement concrete road, Drainage (L171m),Installation of Sola street lighting and Component 1: Improving Pending poles(171m), 2- Community Driven 2019-12- IDA / 59600 Livelihoods for Rural Poor Post Open - National 43,476.23 0.00 Implementat 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 Reinforcement concrete Development 25 and Vulnerable Households ion road(147m),drainage(48m), Installation of Sola street lighting and poles (147m) in Sangkat Khmuonh, Khan Saen Sokh KH-MOI-110144-CW-CDD / Construction: 1- Reinforcement concrete road:(L262m, w 2.6m, T 0.12m) ,Drainage Component 1: Improving Pending system:(262m,0.6m), 2- Community Driven 2019-12- IDA / 59600 Livelihoods for Rural Poor Post Open - National 71,818.97 0.00 Implementat 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 Installation:(18 Sola street Development 25 and Vulnerable Households ion lighting and poles for 262m) and 3-Concrete bridge: (L206m, width1.50m, T0.07m) in Sangkat Srah Chak, Khan Daun Penh KH-MOI-110162-CW-CDD / Construction of reinforcement concrete:1- road:(L102m, width 2.5m, thickness 0.12m) Component 1: Improving Pending and drainage system:(114m).2- Community Driven 2019-12- IDA / 59600 Livelihoods for Rural Poor Post Open - National 37,878.83 0.00 Implementat 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 road:(169m, width 3.5m, Development 25 and Vulnerable Households ion thickness 0.15m) and drainage system:(169m) in Sangkat Boeng Kak 1, Khan Tuol Kork Page 2 KH-MOI-110173-CW-CDD / Construction of reinforcement concrete: 1- Road(110m, Component 1: Improving Pending width 4m, thickness 0.15m), 2- Community Driven 2019-12- IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,281.06 0.00 Implementat 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 Road(100m),2-Installation of Development 25 and Vulnerable Households ion Sola street lighting and poles (250m) in Khtor,Sangkat Preak Leap, Khan Chroy Changvar KH-MOI-110168-CW-CDD / Construction of reinforcement concrete:1- road(158m) and drainage (138m), 2-Road and drainage system (77m),3- Component 1: Improving Pending Community Driven 2019-10- road(261m) and drainage IDA / 59600 Livelihoods for Rural Poor Post Open - National 73,334.73 0.00 Implementat 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 Development 09 (207m),4-Installation of Sola and Vulnerable Households ion street lighting and poles(158m), (77m)and (261m) in Sangkat Chak Angrae Leu, Khan Mean Chey KH-MOI-140916-CW-CDD / Repair Dike 78 for Sangkat Component 1: Improving Pending Krabei Riel, Siem Reap Community Driven 2020-02- IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,005.00 0.00 Implementat 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 Municipality ( Size 2.95Km Development 27 and Vulnerable Households ion length, 4.00m width, 2.00m height) KH-MOI-140917-CW-CDD / Construction of Reinforced Concrete Road for Kampong Component 1: Improving Pending Community Driven 2020-02- Khleang Commune, Sotr IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,248.00 0.00 Implementat 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 Development 27 Nikom District ( Size 0.25Km and Vulnerable Households ion length, 5.00m width, 0.15m thick) KH-MOI-140918-CW-CDD / Upgrade Earth Road to Laterite Pavement for Sangkat Chong Khneas, Siem Reap Component 1: Improving Pending Community Driven 2020-02- Municipality ( Size 0.80Km IDA / 59600 Livelihoods for Rural Poor Post Open - National 27,191.00 0.00 Implementat 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 Development 27 length, 4.00m width, 0.15m and Vulnerable Households ion thick), including 1 unit of culvert construction, 0.60m Diameter, 16.00m length. KH-MOI-146743-CW-CDD / Digging Community Pond one place (size 100mx75mx6.00m) including fence construction and Earth Component 1: Improving Pending Community Driven 2020-04- Dam with laterite pavement IDA / 59600 Livelihoods for Rural Poor Post Open - National 45,730.00 0.00 Implementat 2019-12-06 2019-12-13 2019-12-27 2020-01-03 2020-01-17 Development 16 4.00 meter width, 2.00 meter and Vulnerable Households ion heigh surrounding the pond and 2 reinforced concrete stairs, access laterite road 170m length, 4.00m wid KH-MOI-146745-CW-CDD / Unlined Earth Canal Rehabilitation with 1500m Length, 2m bed, 1.60m Depth including the Construction of Component 1: Improving Pending Community Driven 2020-04- Cented Causeway with pipe IDA / 59600 Livelihoods for Rural Poor Post Open - National 41,288.00 0.00 Implementat 2019-12-06 2019-12-13 2019-12-27 2020-01-03 2020-01-17 Development 16 0.80m diameter, 8m length, and Vulnerable Households ion 4m width 5 places and Construction of Trapezoidal Section Lined Concrete canal with 16m length, 2 KH-MOI-162028-CW-CDD / Earth Road Repair and Laterite Pavement 2 lines for Sangkat Svay Dangkum, Siem Reap Component 1: Improving Pending Municipality (For line 1: 0.87 Community Driven 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 22,511.00 0.00 Implementat 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 Km length, 4.00 m width, Development 20 and Vulnerable Households ion 0.15m thick including 1 unit of single culvert construction, 1.00m Diameter, 7.00m length ( For line 2: 0.60 Km le KH-MOI-162399-CW-CDD / Reinforced Concrete Road for Component 1: Improving Pending Kampong Thkov Commune, Community Driven 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,950.00 0.00 Implementat 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 Kralanh District ( 0.26 Km Development 20 and Vulnerable Households ion length,4.50m Width, 0.15 thick). KH-MOI-162400-CW-CDD / Earth Road Repair and Laterite Pavement for Svay Leu Commune, Svay Leu District ( Component 1: Improving Pending Community Driven 2020-07- 3.70 Km length, 4.00 m IDA / 59600 Livelihoods for Rural Poor Post Open - National 55,881.00 0.00 Implementat 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 Development 20 width, 0.15m thick), including and Vulnerable Households ion 2 units of double culvert construction, 1.00 m Diameter, 6.00 m length. KH-MOI-162401-CW-CDD / Earth Road Repair and Laterite Pavement for Ta Siem Commune, Svay Leu District ( Component 1: Improving Pending Community Driven 2020-07- 2.335 Km length, 4.50 m IDA / 59600 Livelihoods for Rural Poor Post Open - National 35,980.00 0.00 Implementat 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 Development 20 width, 0.15m thick), including and Vulnerable Households ion 1 unit of single culvert construction, 1.00m Diameter, 6.00 m length. KH-MOI-162402-CW-CDD / Earth Road Repair and Laterite Pavement for Boeng Mealea Commune, Svay Leu District ( Component 1: Improving Pending Community Driven 2020-07- 2.80 Km length, 5.00 m IDA / 59600 Livelihoods for Rural Poor Post Open - National 44,027.00 0.00 Implementat 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 Development 20 width, 0.15m thick), including and Vulnerable Households ion 2 units of single culvert construction, 0.60m&0.80 Diameter, 6.00 m length. Page 3 KH-MOI-162403-CW-CDD / Earth Road Repair and Laterite Pavement 3 lines for Peak Snaeng Commune, Angkor Thom District ( For Line1: Component 1: Improving Pending Community Driven 2020-07- 1.95 Km length, 4.00 m IDA / 59600 Livelihoods for Rural Poor Post Open - National 54,983.00 0.00 Implementat 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 Development 20 width, 0.15m thick including and Vulnerable Households ion 2 units of single culvert construction, 1.00 m Diameter, 5.00 m length & 1 unit of single culver KH-MOI-162406-CW-CDD / Earth Road Repair and Laterite Pavement 5 lines for Kampong Kdei Commune, Chi kraeng Component 1: Improving Pending Community Driven 2020-07- District, ( Total length 3190m, IDA / 59600 Livelihoods for Rural Poor Post Open - National 59,812.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 Development 30 4.00m width, 0.15 thick and Vulnerable Households ion including 1 unit of Double box culvert 2.00m heigh, 6.00m length) KH-MOI-162407-CW-CDD / Earth Road Repair and Literate Pavement 3 lines for Chi kraeng Commune, Chi kraeng District, ( Total length 1680m, Component 1: Improving Pending Community Driven 2020-07- 4.00m, 0.15 thick width IDA / 59600 Livelihoods for Rural Poor Post Open - National 39,802.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 Development 30 including 2 units of single and Vulnerable Households ion pipe culvert 0.60m diameter, 6.00m length and 3 units of single pipe culvert 1.00m diam KH-MOI-162408-CW-CDD / Reinforced Concrete Bridge Component 1: Improving Pending Construction for Tram Sasar Community Driven 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,100.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 Commune, Srei Snam District ( Development 30 and Vulnerable Households ion 4.00m Heigh, 11.00m length, 4.00m width). KH-MOI-162409-CW-CDD / Earth Road Repair and Laterite Pavement for Mean Chey Commune, Brasat Bakong Component 1: Improving Pending Community Driven 2020-07- District ( Length 1800m, IDA / 59600 Livelihoods for Rural Poor Post Open - National 31,649.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 Development 30 4.00m width, 0.15 thick and 1 and Vulnerable Households ion unit of single box culvert with water gate, 2.50m heigh, 5.90m length ) KH-MOI-162410-CW-CDD / Earth Road Repair and Laterite Pavement for Roluos Commune, Brasat Bakong District, ( Length 4625m, Component 1: Improving Pending Community Driven 2020-07- 4.00m width, 0.15 thick IDA / 59600 Livelihoods for Rural Poor Post Open - National 49,078.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 Development 30 including 1 units of single and Vulnerable Households ion pipe culvert 0.60m diameter, 6.00m length and 2 units of single pipe culvert 0.80m diameter, 6.00m len KH-MOI-162412-CW-CDD / Earth Road Repair and Laterite Pavement 2 lines for Kantreang Commune, Brasat Component 1: Improving Pending Community Driven 2020-07- Bakong District, ( Total length IDA / 59600 Livelihoods for Rural Poor Post Open - National 19,225.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 Development 30 1500m, 4.00m width, 0.15 and Vulnerable Households ion thick including 1 unit of single pipe culvert 0.80m diameter, 5.00m length) KH-MOI-162414-CW-CDD / Earth Road Repair and Laterite Pavement for Ballangk Commune, Brasat Bakong Component 1: Improving Pending Community Driven 2020-07- District, ( Length 985m, IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,670.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 Development 30 4.00m width, 0.15 thick and Vulnerable Households ion including 3 units of single pipe culvert 0.60m diameter, 5.00m length) KH-MOI-162415-CW-CDD / Earth Road Repair and Laterite Component 1: Improving Pending Pavement for Dan Run Community Driven 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 26,913.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 Commune, Sotr Nikom Development 30 and Vulnerable Households ion District, ( Length 2600m, 4.00m width, 0.15m thick ) KH-MOI-162416-CW-CDD / Laterite Road Construction for Prey Chruk Commune, Pouk District ( 3614 m length, Component 1: Improving Pending 4.00m width, 0.15 thick Community Driven 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 62,129.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 including 5 units of single Development 30 and Vulnerable Households ion pipe culvert, 0.60m Diameter, length 6.00m and 1 unit of single pipe culvert 0.80m diameter, length 6.00m ) KH-MOI-162417-CW-CDD / Laterite Road Construction for Doun Kaev Commune, Pouk District ( 2500 m length, Component 1: Improving Pending 4.00m width, 0.15 thick Community Driven 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 49,293.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 including 1 unit of single pipe Development 30 and Vulnerable Households ion culvert,0.80m Diameter length 6.00m and 1 unit of single pipe culvert 1.00m diameter, length 6.00m ) KH-MOI-162418-CW-CDD / Digging Community Pond 2 places for Kdei Run Component 1: Improving Pending Commune, Pouk District Community Driven 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 34,396.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 including fence construction Development 30 and Vulnerable Households ion surrounding the pond and 2 doors ( Size: 60mx33mx5m and 60mx24mx5m) Page 4 KH-MOI-162419-CW-CDD / Reinforced Concrete Road Construction for Khnat Commune, Pouk District ( Component 1: Improving Pending 400m length, 5.00m width, Community Driven 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 57,625.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 0.15m thick including 1 unit Development 30 and Vulnerable Households ion of single pipe culvert 0.60 diameter, 6.00m length and 1 unit of single pipe culvert 0.80 diameter, 6.00m length KH-MOI-162420-CW-CDD / Laterite Road Construction for Sasar Sdam Commune, Pouk Component 1: Improving Pending District ( 1500m length, Community Driven 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 39,060.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 5.00m width, 0.15 thick Development 30 and Vulnerable Households ion including 2 units of single pipe culvert,0.80m Diameter length 6.00m) KH-MOI-162421-CW-CDD / Laterite Road Construction for Lvea Commune, Pouk District Component 1: Improving Pending Community Driven 2020-07- ( 2200m length, 4.00m width, IDA / 59600 Livelihoods for Rural Poor Post Open - National 38,419.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 Development 30 0.15 thick including 3 units of and Vulnerable Households ion single pipe culvert,0.60m Diameter length 6.00m) KH-MOI-162422-CW-CDD / Unlined Earth Canal Rehabilitation for Spean Tnoat Component 1: Improving Pending Commune, Chi Kraeng District Community Driven 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 33,487.00 0.00 Implementat 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 ( 2100m length, 1.20m bed, Development 30 and Vulnerable Households ion 1.20 Depth including of 6 units of single pipe culvert with water gate) KH-MOI-162423-CW-CDD / Reinforced Concrete Bridge upgrade in Phum 2, Sangkat Srah Chak, Khan Daun Pend ( Total length 73m, 1.20m Component 2: Improving Pending Community Driven 2020-08- width, 1.50 heigh, 0.07m IDA / 59600 Livelihoods for Urban Poor Post Open - National 65,309.00 0.00 Implementat 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 Development 09 thickness), Reinforced and Vulnerable Households ion Concrete Road in Phum 20, Sangkat Srah Chak, Khan Daun Penh ( Total length 60m, 2.40m widt, 0.15m thi KH-MOI-162424-CW-CDD / Reinforced Concrete Road in Phum 3, Sangkat Boeung Kak 1, Khan Toul Kork( Total length 46m, 2m width, 0.15m Component 2: Improving Pending Community Driven 2020-08- thickness) and Drainage IDA / 59600 Livelihoods for Urban Poor Post Open - National 9,333.00 0.00 Implementat 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 Development 09 system (Total length 34m, and Vulnerable Households ion 0.6m diameter). Reinforced concrete road in Phum 4, Sangkat Boeung Kak 1, Khan Toul kork(Total le KH-MOI-162425-CW-CDD / Reinforced Concrete Road in Talei Village, Sangkat Dangkao, Khan Dangkao( Total length 149m, 3.5m Component 2: Improving Pending Community Driven 2020-08- width, 0.15m thickness) and IDA / 59600 Livelihoods for Urban Poor Post Open - National 50,729.00 0.00 Implementat 2020-04-06 2020-04-13 2020-04-27 2020-05-04 2020-05-18 Development 16 Drainage system (Total length and Vulnerable Households ion 67m, 0.6m diameter). Reinforced concrete road in Khva Village, Sangkat Dangkao, Khan Dangkao(Total KH-MOI-162426-CW-CDD / Reinforced Concrete Road in Component 2: Improving Pending Toap Boss Village, Sangkat Community Driven 2020-08- IDA / 59600 Livelihoods for Urban Poor Post Open - National 40,542.00 0.00 Implementat 2020-04-06 2020-04-13 2020-04-27 2020-05-04 2020-05-18 Prey Veang, Khan Dangkao( Development 16 and Vulnerable Households ion Total length 310m, 4m width, 0.15m thickness) KH-MOI-162428-CW-CDD / Reinforced Concrete Road in Preak Leap Village, Sangkat Component 2: Improving Pending Preak Leap, Khan Chroy Community Driven 2020-08- IDA / 59600 Livelihoods for Urban Poor Post Open - National 55,323.00 0.00 Implementat 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 Changvar( Total length 287m, Development 09 and Vulnerable Households ion 3.5m width, 0.15m thickness) and drainage system (Total length 287m, 0.6m diameter) KH-MOI-162429-CW-CDD / Reinforced Concrete Road in Sen Sok Ty Mouy Village, Component 2: Improving Pending Sangkat Khmounh, Khan Sen Community Driven 2020-08- IDA / 59600 Livelihoods for Urban Poor Post Open - National 111,552.00 0.00 Implementat 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 Sok( Total length 547m, 4m Development 13 and Vulnerable Households ion width, 0.15m thickness) and drainage system (Total length 550m, 0.6m diameter) KH-MOI-162430-CW-CDD / Reinforced Concrete Road in Samaki 5 Village, Sangkat Trapeang Krasang, Khan Pou Sen Chey( Total length 196m, Component 2: Improving Pending Community Driven 2020-08- 6m width, 0.15m thickness) IDA / 59600 Livelihoods for Urban Poor Post Open - National 64,039.00 0.00 Implementat 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 Development 13 Reinforced Concrete Road in and Vulnerable Households ion Samaki 6 Village, Sangkat Trapeang Krasang, Khan Pou Sen Chey( Total length 121m, 4m & 5m Page 5 KH-MOI-162432-CW-CDD / Reinforced Concrete Road in Chrey Koang Village, Sangkat Choam Chau 2, Khan Pou Sen Chey( Total length 287m, 5m Component 2: Improving Pending Community Driven 2020-08- width, 0.15m thickness) and IDA / 59600 Livelihoods for Urban Poor Post Open - National 177,610.00 0.00 Implementat 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 Development 13 Drainage System(Total Length and Vulnerable Households ion 287, 0.6m diameter) , Reinforced Concrete Road in Prey Lvea Village, Sangkat Choam Ch KH-MOI-162433-CW-CDD / Reinforced Concrete Road in Andong 1 & Andong 2 Villages, Sangkat Kork Roka, Component 2: Improving Pending Community Driven 2020-08- Khan Peeak Phnov( Total IDA / 59600 Livelihoods for Urban Poor Post Open - National 42,245.00 0.00 Implementat 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 Development 13 length 211m, 4m width, and Vulnerable Households ion 0.15m thickness) and Drainage System(Total Length 211m, 0.6m diameter) KH-MOI-162435-CW-CDD / Reinforced Concrete Road in Component 2: Improving Pending Daeum Sleng Village, Sangkat Community Driven 2020-08- IDA / 59600 Livelihoods for Urban Poor Post Open - National 28,928.00 0.00 Implementat 2020-04-10 2020-04-17 2020-05-01 2020-05-08 2020-05-22 Chbar Ampov 2, Khan Chbar Development 20 and Vulnerable Households ion Ampov ( Total length 234m, 3.4m width, 0.15m thickness) KH-MOI-169345-CW-CDD / Solar LED Power Street lighting in Phum 2, Sangkat Srah Chak, Khan Daun Pend ( Component 2: Improving Pending Total sets 22 sets), Solar LED Community Driven 2020-09- IDA / 59600 Livelihoods for Urban Poor Post Open - National 13,469.00 0.00 Implementat 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 Power Street lighting in Phum Development 14 and Vulnerable Households ion 22, Sangkat Srah Chak, Khan Daun Pend ( Total sets 11 sets), Solar LED Power Street lighting in Phum 24, Sangkat KH-MOI-169346-CW-CDD / Solar LED Power street Component 2: Improving Pending Community Driven 2020-09- lighting in Phum 8, Sangkat IDA / 59600 Livelihoods for Urban Poor Post Open - National 3,613.00 0.00 Implementat 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 Development 14 Boeung Kak 1, Khan Toul and Vulnerable Households ion Kork( Total sets 11 sets) KH-MOI-169347-CW-CDD / Solar LED Power street lighting in Khva Village, Sangkat Dangkao, Khan Component 2: Improving Pending Community Driven 2020-09- Dangkao( Total sets 26 sets), IDA / 59600 Livelihoods for Urban Poor Post Open - National 15,774.00 0.00 Implementat 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 Development 14 Solar LED Power street and Vulnerable Households ion lighting in Mol Village, Sangkat Dangkao, Khan Dangkao(Total sets 23 sets) KH-MOI-169348-CW-CDD / Solar LED Power street Component 2: Improving Pending Community Driven 2020-09- lighting in Phum 3, Sangkat IDA / 59600 Livelihoods for Urban Poor Post Open - National 5,495.00 0.00 Implementat 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 Development 14 Chrang Chamreas Ty Mouy, and Vulnerable Households ion Khan Russei Kao( Total sets 17 sets) KH-MOI-169349-CW-CDD / Solar LED Power street Component 2: Improving Pending Community Driven 2020-09- lighting in Khtor Village, IDA / 59600 Livelihoods for Urban Poor Post Open - National 9,674.00 0.00 Implementat 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 Development 15 Sangkat Preak Leap, Khan and Vulnerable Households ion Chroy Chang Var( Total sets 30 sets) KH-MOI-169350-CW-CDD / Solar LED Power street lighting in Svay Ckek Thmei Component 2: Improving Pending Community Driven 2020-09- Village, Dandong 1&2 IDA / 59600 Livelihoods for Urban Poor Post Open - National 15,064.00 0.00 Implementat 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 Development 15 Villages, Sangkat Kork Roka, and Vulnerable Households ion Khan Preak Phnov( Total sets 47 sets) KH-MOI-169351-CW-CDD / Solar LED Power street lighting in Daeum Sleng, Component 2: Improving Pending Community Driven 2020-09- Daeum Sleng I, Daeum Chan I IDA / 59600 Livelihoods for Urban Poor Post Open - National 21,978.00 0.00 Implementat 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 Development 15 Villages, Sangkat Chbar and Vulnerable Households ion Ampov 2, Khan Chbar Ampov( Total sets 69 sets) KH-MOI-191867-CW-CDD / Reinforced Concrete Road Construction for Khnang Component 1: Improving Pending Community Driven 2020-12- Phnum Commune,Svay Leu IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,181.00 0.00 Implementat 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 Development 26 District, Siem Reap Province ( and Vulnerable Households ion Length: 0.18 Km, Width 5.00 m, 0.15m thick) KH-MOI-191856-CW-CDD / Earth Road Repair and Laterite Pavement for Anlong Samnar, Component 1: Improving Pending Siem Reap Province ( Length Community Driven 2021-08- IDA / 59600 Livelihoods for Rural Poor Post Open - National 27,338.00 0.00 Implementat 2021-04-15 2021-04-22 2021-05-06 2021-05-13 2021-05-27 1.80 Km, Width 4.00 m, Development 25 and Vulnerable Households ion 0.15m thick including 2 units of single culvert construction, Ø0.80m, length 6.00m) KH-MOI-191857-CW-CDD / Earth Road Repair and Laterite Pavement two lines for Sangkat Krabei Riel, Siem Reap Municipality, Siem Reap Component 1: Improving Pending Community Driven 2021-07- Province ( For line1: Length: IDA / 59600 Livelihoods for Rural Poor Post Open - National 45,396.00 0.00 Implementat 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 Development 25 1.868 Km, Width 5.00m, 0.15 and Vulnerable Households ion thick including 2 units of single culverts, Ø 0.80m, length 7.00m and Ø1.00m, length 7.0 Page 6 KH-MOI-191859-CW-CDD / Earth Road Repair and Laterite Pavement for Sangkat Tuek Vil ,Siem Reap Municipality, Siem Component 1: Improving Pending Reap Province ( Length: 2.325 Community Driven 2021-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 64,903.00 0.00 Implementat 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 Km , Width: 5.00 m, 0.15m Development 25 and Vulnerable Households ion thick), including 5 units of single culvert construction, 1 Unit Ø1.00 m, length 6.00 m, 4 units Ø1.00 m, l KH-MOI-191860-CW-CDD / Reinforced Concrete Road Construction for Kampong Component 1: Improving Pending Community Driven 2021-06- Khleang Commune, Sotr IDA / 59600 Livelihoods for Rural Poor Post Open - National 33,774.00 0.00 Implementat 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 Development 25 Nikom District, Siem Reap and Vulnerable Households ion Province ( Length 0.25 Km, Width 5.00 m, 0.15m thick) KH-MOI-162413-CW-CDD / Earth Road Repair and Laterite Pavement for Bakong Commune, Brasat Bakong Component 1: Improving Pending Community Driven 2021-07- District, ( Length 1.60 Km, IDA / 59600 Livelihoods for Rural Poor Post Open - National 42,032.00 0.00 Implementat 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 Development 25 4.00m width, 0.15 thick and Vulnerable Households ion including 3 units of double pipe culvert 1.00m diameter, 5.00m length) KH-MOI-191861-CW-CDD / Reinforced Concrete Road Construction for Kampong Component 1: Improving Pending Community Driven 2021-06- Phluk Commune, Brasat IDA / 59600 Livelihoods for Rural Poor Post Open - National 39,635.00 0.00 Implementat 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 Development 25 Bakong District, Siem Reap and Vulnerable Households ion Province ( Length 0.23 Km, Width 6.00 m, 0.15m thick) KH-MOI-191862-CW-CDD / Earth Road Repair and Laterite Pavement 2 lines for Trapeang Thum Commune ,Brasat Component 1: Improving Pending Community Driven 2021-07- Bakong District, Siem Reap IDA / 59600 Livelihoods for Rural Poor Post Open - National 36,380.00 0.00 Implementat 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 Development 25 Province ( For line1: Length and Vulnerable Households ion 0.50 Km, Width 4.00m, 0.15 thick , For line 2: Length 3.05 Km, Width 4.00m, 0.15 thick) KH-MOI-191863-CW-CDD / Laterite Road Construction 2 lines for Reul Commune ,Pouk Component 1: Improving Pending District, Siem Reap Province Community Driven 2021-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 31,787.00 0.00 Implementat 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 (For line Length 2.09 Km, Development 25 and Vulnerable Households ion Width 4.00m, 0.15 thick , For line 2: Length 0.75 Km, Width 4.00m, 0.15 thick) KH-MOI-191865-CW-CDD / Drilled wells Construction Component 1: Improving Pending Community Driven 2021-06- with Afridev Pump for Yeang IDA / 59600 Livelihoods for Rural Poor Post Open - National 11,429.00 0.00 Implementat 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 Development 25 Commune ,Pouk District, Siem and Vulnerable Households ion Reap Province for 5 places KH-MOI-191864-CW-CDD / Laterite Road Construction 2 lines for Trei Nhoar Commune ,Pouk District, Siem Reap Component 1: Improving Pending Province ( For line 1: Length Community Driven 2021-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 35,805.00 0.00 Implementat 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 1.20 Km, Width 4.00m, 0.15 Development 25 and Vulnerable Households ion thick , For line 2: Length 1.45 Km, Width 4.00m, 0.15 thick including 1 unit of double culvert Ø0.60m, length 6.0 KH-MOI-191866-CW-CDD / Drilled wells with solar Pump and Water Distributed Component 1: Improving Pending Community Driven 2021-07- Connection 4 places for IDA / 59600 Livelihoods for Rural Poor Post Open - National 47,530.00 0.00 Implementat 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 Development 25 Chrouy Neang and Vulnerable Households ion NguonCommune ,Srei Snam District, Siem Reap Province KH-MOI-162411-CW-CDD / Construction of Community Shelter for Ampil Commune, Brasat Bakong District ( Size: 8mx12m, with steel frame, Component 1: Improving Pending Community Driven 2021-09- reinforced concrete slab IDA / 59600 Livelihoods for Rural Poor Post Open - National 15,377.00 0.00 Implementat 2021-05-14 2021-05-21 2021-06-04 2021-06-11 2021-06-25 Development 23 0.10m thick and zinc roof ) and Vulnerable Households ion including one latrine construction with 4 separated rooms and installation of one unit of wa KH-MOI-251230-CW-RFQ / Laterite Road Construction for Mukh Paen Commune, Pouk District, Siem Reap Province ( Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2 lines, for line1: Length= IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 26,739.00 0.00 Implementat 2021-09-11 2021-10-16 Quotations Envelope 14 1.20 Km, Width= 5.00m, and Vulnerable Households Bank-SPD) ion Thick=0.15m , For line 2: Length= 0.85 Km, Width= 4.00m, Thick=0.15m) KH-MOI-251231-CW-RFQ / Laterite Road Construction for Samraong Yea Commune, Pouk District, Siem Reap Component 1: Improving Request for Pending Province (04 Lines, Total Request for Single Stage - One 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 36,214.00 0.00 Implementat 2021-09-11 2021-10-16 Length= 3.16 Km, Width= Quotations Envelope 14 and Vulnerable Households Bank-SPD) ion 4.00m, Thick=0.15m including 1 unit of double culvert construction, Ø0.60 m, length 6.00m) GOODS Page 7 Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-14029-GO-RFQ / Pending Component 3: Project Request for Single Stage - One Office Furniture for National IDA / 59600 Post Open - National 27,380.00 0.00 Implementati 2017-07-14 2017-09-03 2017-10-18 Management Quotations Envelope Level and Sub National Level on KH-MOI-14017-GO-RFQ / Pending Component 3: Project Request for Single Stage - One Softwares ( Accounting) for IDA / 59600 Post Open - National 10,000.00 0.00 Implementati 2017-07-31 2017-09-20 2017-11-19 Management Quotations Envelope PCO-MOI 1 unit on KH-MOI-26199-GO-RFB / Component 1: Improving Pending Motorcycles plus helmets for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 226,100.00 0.00 Implementati 2017-10-02 2017-10-16 2017-11-15 2017-12-06 2018-01-03 2018-03-04 National level and Sub- Envelope and Vulnerable Households on National (Total 133 Units) KH-MOI-26827-GO-RFB / Lot1: Develop Management Information System (MIS) Pending Component 3: Project Single Stage - One System Lot2: Server, IDA / 59600 Post Request for Bids Open - National 140,000.00 0.00 Implementati 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 Management Envelope Network, Tablet, website, etc.) on Lot 3:MIS webside maintenance for PCO-MOI KH-MOI-33988-GO-RFQ / 4 Pending Component 3: Project Request for Single Stage - One Laptop Computers for IDA / 59600 Post Open - National 9,200.00 0.00 Implementati 2017-11-05 2017-12-05 2017-12-20 Management Quotations Envelope Management on KH-MOI-34259-GO-RFB / Under Component 3: Project Single Stage - One Office Equipment for National IDA / 59600 Post Request for Bids Open - National 132,200.00 0.00 Implementati 2017-11-08 2019-01-10 2017-11-13 2017-12-15 2019-02-15 2018-01-14 2018-02-18 2018-04-19 Management Envelope and Sub National Leve on KH-MOI-36613-GO-UN / Lot1:Vehicles (Station Wagon) 3 units for -PCO-MOI and 1 units for MEF, Component 1: Improving Pending UN Agencies Lot2:Vehicles (Pick up Cars) IDA / 59600 Livelihoods for Rural Poor Post Direct 330,000.00 0.00 Implementati 2017-11-17 2017-11-22 2017-12-25 2018-02-23 (Direct) for 1units for GDA-MAFF, 3 and Vulnerable Households on units for Siem Reap and 2 units for PPM. The total Vehicles: 10 Units KH-MOI-34266-GO-UN / Vehicles (Station Wagon) 3 Component 1: Improving UN Agencies units for -PCO-MOI and 1 IDA / 59600 Livelihoods for Rural Poor Post Direct 132,000.00 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-02-23 (Direct) units for MEF, Total Vehicles: and Vulnerable Households 4 Units KH-MOI-11051-GO-RFB / Vehicles (Pick up Cars) for Component 1: Improving Single Stage - One 1units for GDA-MAFF, 3 units IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 198,000.00 0.00 Canceled 2017-10-02 2017-10-16 2017-11-15 2017-12-15 2018-01-07 2018-05-07 Envelope for Siem Reap and 2 units for and Vulnerable Households PPM. Total Vehicles: 6 Units KH-MOI-99858-GO-RFQ / Pending Component 3: Project Request for Single Stage - One Total 7 Air Conditioners for IDA / 59600 Post Open - National 4,900.00 0.00 Implementati 2019-03-06 2019-04-03 2019-04-17 Management Quotations Envelope PCO and MAFF on Pending KH-MOI-99860-GO-RFQ / Component 3: Project Request for Single Stage - One IDA / 59600 Post Open - National 20,000.00 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 Office Furniture for MOI-PCO Management Quotations Envelope on KH-MOI-99861-GO-RFQ / Printing Material and Component 1: Improving Pending Thumbprint pad for Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 22,644.00 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 SHG/producer Quotations Envelope and Vulnerable Households on group/commune federation for 2019 KH-MOI-99863-GO-RFQ / Material for SHG/producer Component 1: Improving Pending Request for Single Stage - One group/commune federation IDA / 59600 Livelihoods for Rural Poor Post Open - National 31,250.00 0.00 Implementati 2019-03-06 2019-04-24 2019-05-24 Quotations Envelope (Boxes for keeping documents and Vulnerable Households on and cash) KH-MOI-99865-GO-RFQ / Equipment for Component 1: Improving Pending Request for Single Stage - One Commune/Sangkat IDA / 59600 Livelihoods for Rural Poor Post Open - National 10,000.00 0.00 Implementati 2019-03-06 2019-04-03 2019-04-18 Quotations Envelope Investment Projects (SRP and and Vulnerable Households on PPCH) KH-MOI-99868-GO-RFQ / Component 1: Improving Pending 72 Tablets for MIS (3 MoI, 3 Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 24,840.00 0.00 Implementati 2019-04-06 2019-05-04 2019-06-03 GDA, 3 PPCH, 3 Pro. S_Reap, Quotations Envelope and Vulnerable Households on 47 commune, 13 Sangkat) KH-MOI-99869-GO-RFQ / Printing Materials (Logos, Component 1: Improving Pending Request for Single Stage - One Printed Folder, Factsheets, IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,250.00 0.00 Implementati 2019-05-06 2019-06-03 2019-06-24 Quotations Envelope Newsletters, Brochures, and Vulnerable Households on Posters and Standing Poster) KH-MOI-99871-GO-RFQ / Printing Materials for Component 1: Improving Under Request for Single Stage - One SHG/producer IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,145.00 0.00 Implementati 2019-12-06 2020-01-04 2020-02-03 Quotations Envelope group/commune federation and Vulnerable Households on for 2020 KH-MOI-26829-GO-RFB / Material for SHG/Poducer group/commune Component 1: Improving federation(books keeping, Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 126,250.70 0.00 Canceled 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 cash book, pay and loan Envelope and Vulnerable Households record book, SHG box for keeping docs. And Thumprint pad) for SRP KH-MOI-121052-GO-RFQ / Pending Component 3: Project Request for Single Stage - One Procurement of supply Server IDA / 59600 Post Open - National 20,000.00 0.00 Implementati 2019-07-10 2019-08-04 2019-09-03 Management Quotations Envelope and network for LEAP Project on Page 8 KH-MOI-136652-GO-RFQ / Component 1: Improving Pending Request for Single Stage - One Office Furniture for Skill IDA / 59600 Livelihoods for Rural Poor Post Open - National 4,400.00 0.00 Implementati 2019-10-16 2019-11-11 2019-11-25 Quotations Envelope Development Activities and Vulnerable Households on KH-MOI-136666-GO-RFQ / Component 1: Improving Pending Motorcycles for Skill Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 17,500.00 0.00 Implementati 2019-10-16 2019-11-11 2019-11-25 Development Activities (10 Quotations Envelope and Vulnerable Households on Units) KH-MOI-168855-GO-RFQ / Component 1: Improving Pending Vehicles (VAN) 1 units for - Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open 30,000.00 0.00 Implementati 2020-04-29 2020-06-05 2020-07-05 PCO-MOI ( Import tax will be Quotations Envelope and Vulnerable Households on exempted) KH-MOI-168856-GO-RFQ / Component 1: Improving Pending Request for Single Stage - One Office Furniture for Sub IDA / 59600 Livelihoods for Rural Poor Post Open - National 16,915.00 0.00 Implementati 2020-05-02 2020-05-28 2020-06-27 Quotations Envelope National Level (PCO, SRP ) and Vulnerable Households on KH-MOI-168859-GO-RFQ / Study Equipment (Hummer Component 1: Improving Pending Test, DCP Test, Autormatic Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 11,000.00 0.00 Implementati 2020-05-06 2020-05-29 2020-06-13 Level, GPS…2sets) for Quotations Envelope and Vulnerable Households on Commnune/Sangkat Investment Projects (SRP) KH-MOI-168860-GO-RFQ / Printing Communication Component 1: Improving Pending Materials (LEAP Newsletters Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 12,000.00 0.00 Implementati 2020-06-20 2020-07-18 2020-08-08 semi-annual (2time/years) in Quotations Envelope and Vulnerable Households on Khmer and English 2time/year) KH-MOI-168861-GO-RFQ / Component 1: Improving Pending Printing Communication Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 4,000.00 0.00 Implementati 2020-09-06 2020-10-04 2020-10-25 Materials ( Success Story 4 Quotations Envelope and Vulnerable Households on time/year) KH-MOI-168862-GO-RFQ / Component 1: Improving Pending Request for Single Stage - One Video Production of project IDA / 59600 Livelihoods for Rural Poor Post Open - National 7,000.00 0.00 Implementati 2020-09-06 2020-09-29 2020-10-29 Quotations Envelope achievement (15 Minute) and Vulnerable Households on KH-MOI-226724-GO-RFB / Component 1: Improving Under Vehicles (VAN) 1 units for - Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 130,000.00 0.00 Implementati 2021-04-18 2021-04-23 2021-04-23 2021-04-27 2021-05-23 2021-06-22 2021-07-27 2021-08-02 PCO-MOI, Vehicles (Pick up Envelope and Vulnerable Households on Cars) 2 units for Siem Reap KH-MOI-226726-GO-UN / Component 2: Improving Pending SUV Vehicles 1 units for UN Agencies IDA / 59600 Livelihoods for Urban Poor Post Direct 40,000.00 0.00 Implementati 2021-04-18 2021-04-21 2021-06-02 2021-08-31 PPCH( Import tax will be (Direct) and Vulnerable Households on exempted) KH-MOI-226728-GO-RFQ / Component 1: Improving Under Request for Single Stage - One Motorcycles( 12 Units for SRP IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,000.00 0.00 Implementati 2021-04-19 2021-04-27 2021-05-29 2021-06-28 Quotations Envelope and 3 Units for MAFFs) and Vulnerable Households on KH-MOI-226744-GO-RFQ / Office Equipment: (4 Laptops for PCO, 2 Laptops for PPCH Under Component 3: Project Request for Single Stage - One ,5 Laptops for MAFF , 4 Note IDA / 59600 Post Open - National 33,032.00 0.00 Implementati 2021-04-26 2021-05-21 2021-06-23 2021-07-23 Management Quotations Envelope Book for SC, 2 Desktops for on PPCH, 1 Printer for MAFF, and 15 Tablets for New CF-SRP) KH-MOI-226750-GO-RFQ / Procurement of 1 unit Stability Camera Stand ,1 unit Zoom- Pending Len Camera ,1 Unit Drone Component 3: Project Request for Single Stage - One IDA / 59600 Post Open - National 7,400.00 0.00 Implementati 2021-05-02 2021-06-15 2021-07-15 Camera for SRP and 1Unit Management Quotations Envelope on Zoom-Len Camera,1set Equipment of video conference for PPCH KH-MOI-226753-GO-RFQ / Pending Installation Microphone Component 3: Project Request for Single Stage - One IDA / 59600 Post Open - National 20,000.00 0.00 Implementati 2021-06-02 2021-07-16 2021-08-15 System for PCO-LEAP meeting Management Quotations Envelope on room KH-MOI-226767-GO-RFQ / Materials for SHG/producer group (14000 Cash book for SHGs member, 1200 SHGs Component 1: Improving Under Request for Single Stage - One Saving, Loan & Repayment IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,400.00 0.00 Implementati 2021-04-26 2021-04-27 2021-06-23 2021-07-23 Quotations Envelope Books,1200 SHG minute and Vulnerable Households on books, 4000 SHG minute books and 1200 Thumbprint pad for SHG 2021 KH-MOI-226770-GO-RFQ / Purchase 25 Booth for PGs to Component 1: Improving Pending Request for Single Stage - One promote agriculture products IDA / 59600 Livelihoods for Rural Poor Post Open - National 6,875.00 0.00 Implementati 2021-05-04 2021-06-10 2021-07-10 Quotations Envelope for weekend Market for SMT- and Vulnerable Households on SRP KH-MOI-226776-GO-RFQ / Printing Communication Component 1: Improving Pending Materials (LEAP Newsletters Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 8,500.00 0.00 Implementati 2021-05-08 2021-06-05 2021-12-02 semi-annual (2time/years) in Quotations Envelope and Vulnerable Households on Khmer and English 2time/year) 2021 KH-MOI-226782-GO-RFQ / Printing 140 Produce PCV Component 1: Improving Pending Request for Single Stage - One Banner and 11200 leaflets on IDA / 59600 Livelihoods for Rural Poor Post Open - National 9,400.00 0.00 Implementati 2021-04-19 2021-05-25 2021-06-15 Quotations Envelope Skills Development and Vulnerable Households on information for SRP and PPCH Page 9 KH-MOI-226783-GO-RFQ / Printing Tools to Provide technical training for CAHEWs in Q1 and Q2 on (Chicken Eggs Incubator Making), (how Component 1: Improving Pending Request for Single Stage - One to use vaccination kits), 50 IDA / 59600 Livelihoods for Rural Poor Post Open - National 52,500.00 0.00 Implementati 2021-05-04 2021-06-30 2021-12-27 Quotations Envelope Sets ( chicken raising ) (Pig and Vulnerable Households on Raising) and 50 Sets PCV Banner Training Tools (Fish (rice and vegetable production) KH-MOI-226784-GO-RFQ / Component 1: Improving Pending Design and print out banner Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 3,000.00 0.00 Implementati 2021-05-04 2021-06-09 2021-06-30 to mainstream information on Quotations Envelope and Vulnerable Households on gender to target beneficiaries NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-99864-NC-RFQ / Under Component 3: Project Request for Single Stage - One Develop Website for LEAP IDA / 59600 Post Open - National 5,600.00 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 Management Quotations Envelope Projec on Component 1: Improving Pending KH-MOI-99870-NC-RFQ / Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,000.00 0.00 Implementati 2019-07-06 2019-08-17 2019-10-16 Four (4) Video Spots Quotations Envelope and Vulnerable Households on KH-MOI-226780-NC-RFQ / Pending Component 3: Project Request for Single Stage - One Video Production of project IDA / 59600 Post Open - National 7,000.00 0.00 Implementati 2021-07-06 2021-08-17 2021-10-16 Management Quotations Envelope achievement 2021 on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-39863-CS-CQS / Consultant Impact Survey (3nd year of the Component 3: Project Pending IDA / 59600 Post Qualification Open - National 30,000.00 0.00 2020-01-02 2020-01-23 2020-03-07 2020-04-06 2020-05-11 2020-11-07 project/Mid-term review) Management Implementation Selection (Local Firm) at PCO-MOI KH-MOI-39867-CS-CQS / Final Impact Survey ( (5th year Consultant Component 3: Project Pending of Project evaluation and IDA / 59600 Post Qualification Open - National 40,000.00 0.00 2022-01-03 2022-01-24 2022-03-09 2022-04-08 2022-05-13 2022-11-09 Management Implementation completion report) (Local Selection Firm) at PCO-MOI KH-MOI-82848-CS-CQS / Development of Community Component 1: Improving Consultant Institutions of the Poor for 4 Under IDA / 59600 Livelihoods for Rural Poor Post Qualification Open - National 280,000.00 0.00 2018-10-22 2019-01-18 2018-11-12 2019-01-11 2019-02-10 2019-03-17 2022-11-30 Districts​​  (Angkor Thum, Implementation and Vulnerable Households Selection Kralanh, Pouk and Srei Snam District) KH-MOI-82083-CS-CQS / Development of Community Component 1: Improving Consultant Institutions of the Poor for 5 Under IDA / 59600 Livelihoods for Rural Poor Post Qualification Open - National 290,000.00 0.00 2018-10-22 2018-12-21 2018-11-12 2019-01-11 2019-03-22 2019-02-10 2019-03-17 2022-12-05 Districts ( Chi Kraeng, Prasat Implementation and Vulnerable Households Selection Bakong, Siem Reap, Soutr Nikom and Svay Leu District) KH-MOI-70310-CS-QCBS / Component 1: Improving Human Resource Quality And Cost- IDA / 59600 Livelihoods for Rural Poor Prior Open - International 784,000.00 0.00 Canceled 2018-12-14 2019-01-13 2019-01-16 2019-02-26 2019-05-10 2019-04-12 2019-05-12 2019-06-16 2019-07-21 2023-06-30 Development Service Provider Based Selection and Vulnerable Households (HRDSP) for SRP and PPCH KH-MOI-39858-CS-QCBS / Human Resources Component 2: Improving Quality And Cost- Development Services IDA / 59600 Livelihoods for Urban Poor Post Open - International 367,932.00 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 Based Selection Provider(HRDSP) for PPM and Vulnerable Households (NGO/Firm) KH-MOI-39860-CS-CQS / Consultant Component 3: Project Baseline Survey (1st IDA / 59600 Post Qualification Open - National 30,000.00 0.00 Canceled 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-11-21 Management year)(Local Firm) at PCO-MOI Selection KH-MOI-39857-CS-QCBS / Human Resources Component 1: Improving Quality And Cost- Development Services IDA / 59600 Livelihoods for Rural Poor Post Open - International 545,936.00 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 Based Selection Provider(HRDSP) for SRP and Vulnerable Households (NGO/Firm) KH-MOI-187154-CS-CQS / Tracer Study Consultant for Component 1: Improving Consultant Under 24 months (one firm IDA / 59600 Livelihoods for Rural Poor Post Qualification Open - National 45,000.00 0.00 2020-08-10 2020-08-07 2020-08-31 2020-08-23 2020-10-14 2020-11-13 2020-12-18 2022-12-08 Implementation consultant will be hired for and Vulnerable Households Selection both SRP and PPCH) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-13893-CS-INDV / Component 1: Improving Individual Under Provincial Operation and M&E IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 120,000.00 0.00 2017-06-26 2017-12-07 2017-08-23 2018-04-30 2017-09-06 2018-04-30 2017-10-11 2022-10-10 Implementation Specialist for SRP (60 Months) and Vulnerable Households Selection KH-MOI-13901-CS-INDV / Individual Component 3: Project Pending Project Assistant for PCO-MOI IDA / 59600 Post Consultant Open 18,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2020-10-24 Management Implementation (60 Months) Selection Page 10 KH-MOI-13903-CS-INDV / Component 2: Improving Individual Pending National Operation and M&E IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 150,000.00 0.00 2017-06-26 2017-08-23 2017-09-06 2017-10-11 2022-10-10 Implementation Specialist for PPM (60 Months) and Vulnerable Households Selection KH-MOI-13905-CS-INDV / Component 1: Improving Individual Provincial Finance Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-06-26 2017-08-23 2017-09-06 2017-10-11 2020-10-10 Management Specialist for SRP Implementation and Vulnerable Households Selection (36 Months) KH-MOI-13907-CS-INDV / Component 1: Improving Individual Pending Project Assistant for SRP (60 IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 15,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2022-10-24 Implementation Months) and Vulnerable Households Selection KH-MOI-13910-CS-INDV / Component 2: Improving Individual Pending Project Assistant for PPM (60 IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 15,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2022-10-24 Implementation Months) and Vulnerable Households Selection KH-MOI-13913-CS-INDV / Component 2: Improving Individual Pending 01 PPM Infrastructure IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 72,000.00 0.00 2017-07-17 2017-09-13 2017-09-27 2017-11-01 2020-10-31 Implementation Specialist at PPM (36 Months) and Vulnerable Households Selection KH-MOI-11055-CS-INDV / Individual National Project Management Component 3: Project Pending IDA / 59600 Post Consultant Open 180,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2022-11-30 and M&E consultant at PCO- Management Implementation Selection MOI KH-MOI-11263-CS-INDV / Component 1: Improving Individual National Finance Management Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2020-11-30 Specialist for MOI/PPM(36 Implementation and Vulnerable Households Selection Months) KH-MOI-13886-CS-INDV / Component 2: Improving Individual Pending National procurement IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 90,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2020-11-30 Implementation Specialist based at PCO and Vulnerable Households Selection KH-MOI-30826-CS-INDV / Component 1: Improving Individual Provincial Infrastructure Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 Specialist (P M & E Engineer) Implementation and Vulnerable Households Selection at SRP (36 Months) KH-MOI-30834-CS-INDV / Provincial Infrastructure Component 1: Improving Individual Pending Specialist (Building IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 Implementation Construction Engineer) at SRP and Vulnerable Households Selection (36 Months) KH-MOI-30840-CS-INDV / Provincial Infrastructure Component 1: Improving Individual Pending Specialist (Rural Road IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 Implementation Construction Engineer) at SRP and Vulnerable Households Selection (36 Months) KH-MOI-39794-CS-INDV / Individual Component 3: Project Pending International Micro-Finance IDA / 59600 Post Consultant Open 60,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-07-16 Management Implementation Expert at PCO-MOI(60 days) Selection KH-MOI-39797-CS-INDV / Individual National Communication Component 3: Project Pending IDA / 59600 Post Consultant Open 90,000.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-14 Specialist at PCO-MOI (36 Management Implementation Selection Months) KH-MOI-39798-CS-INDV / Individual Component 3: Project Pending National MIS Specialist at PCO- IDA / 59600 Post Consultant Open 60,000.00 0.00 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2020-04-02 Management Implementation MOI (24 Months) Selection KH-MOI-39800-CS-INDV / Component 1: Improving Individual National Agriculture Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-14 Likelihood Specialist for GDA- Implementation and Vulnerable Households Selection MAFF (36 Months) KH-MOI-39817-CS-INDV / Component 1: Improving Individual Pending National HR Development IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 48,000.00 0.00 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2020-04-02 Implementation Specialist for SRP (24 Months) and Vulnerable Households Selection KH-MOI-39821-CS-INDV / Component 2: Improving Individual National HR Development Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 48,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2020-05-06 Specialist for PPM ( 24 Implementation and Vulnerable Households Selection Months) KH-MOI-39888-CS-INDV / 7 Component 1: Improving Individual Pending District Facilitators (7 DF x 55 IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 336,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 Implementation Months) at Siem Reap and Vulnerable Households Selection KH-MOI-40438-CS-INDV / Component 1: Improving Individual Pending Provincial Micro-Finance IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2021-05-01 Implementation Specialist for SRP ( 36 Months) and Vulnerable Households Selection KH-MOI-40440-CS-INDV / Component 1: Improving Individual Senior Livelihood/business Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2021-05-01 development Specialist for Implementation and Vulnerable Households Selection SRP (36 Months) KH-MOI-40447-CS-INDV / Component 1: Improving Individual Pending 47 Commune Facilitators IDA / 59600 Livelihoods for Rural Poor Prior Consultant Open 564,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 Implementation (47CFs x55 Months) for SRP and Vulnerable Households Selection KH-MOI-40449-CS-INDV / Component 1: Improving Individual 47 Commune Animal Health & Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 338,400.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 Extension Workers (47 CAHEW Implementation and Vulnerable Households Selection x 55 Months) for SRP KH-MOI-40453-CS-INDV / 4 Component 2: Improving Individual Local Coordinator for urban Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 96,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 poor(4CLUPs x 55 Months) for Implementation and Vulnerable Households Selection PPM Individual KH-MOI-99872-CS-INDV / Component 3: Project Pending IDA / 59600 Post Consultant Open 15,000.00 0.00 2019-03-01 2019-04-21 2019-05-05 2019-06-09 2022-06-08 Project Assistant for MAFF Management Implementation Selection Page 11 KH-MOI-99873-CS-INDV / Component 1: Improving Individual Tracer Study Consultant (60 IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 18,000.00 0.00 Canceled 2019-06-03 2019-07-22 2019-07-29 2019-08-12 2019-10-11 Working Days) and Vulnerable Households Selection KH-MOI-136635-CS-INDV / International Skill Component 1: Improving Individual Development Advisor (120 Under IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 112,800.00 0.00 2019-10-04 2019-10-18 2019-11-10 2019-11-15 2019-11-28 2020-03-27 days x 1 pax) for (20day- Implementation and Vulnerable Households Selection 2019, 80 days-2020 and 20 days-2021) KH-MOI-136641-CS-INDV / Component 2: Improving Individual National Skills Development Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 85,000.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 Specialist (34 monthsx1pax) Implementation and Vulnerable Households Selection for PCO-LEAP KH-MOI-136643-CS-INDV / Component 2: Improving Individual Human Resource Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 190,400.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 Development Facilitators for Implementation and Vulnerable Households Selection SRP (34month x 7 paxes) KH-MOI-136648-CS-INDV / Component 1: Improving Individual Human Resource Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 81,600.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 Development Facilitators for Implementation and Vulnerable Households Selection PPCH (34month x 3 paxes) KH-MOI-168864-CS-INDV / National Consultant for Component 1: Improving Individual Pending Market Linkage Study IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 56,000.00 0.00 2020-05-24 2020-07-12 2020-08-02 2020-09-06 2022-09-06 Implementation (Intermittent) for 3 year (2020- and Vulnerable Households Selection 2022) KH-MOI-168866-CS-INDV / National Consultant for Sturdy Component 1: Improving Individual Pending research promote Linkage IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 31,200.00 0.00 2020-05-01 2020-06-19 2020-07-10 2020-08-14 2022-08-14 Implementation with formal Financial sector and Vulnerable Households Selection for 3 year (2020-20220) KH-MOI-220888-CS-INDV / Component 1: Improving Individual Procure to replacement of Ms. Under IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 33,360.00 0.00 2021-03-01 2021-02-23 2021-04-03 2021-04-08 2021-04-22 2022-04-22 Teng Ratana Resigned on 22 Implementation and Vulnerable Households Selection July 2020 KH-MOI-226811-CS-INDV / One National procurement Component 2: Improving Individual Specialist based at PCO (12 Under IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 30,000.00 0.00 2021-04-08 2021-04-23 2021-06-05 2021-06-19 2021-07-24 2022-07-24 months) to replacement Mr. Implementation and Vulnerable Households Selection Chay Ponlork Resigned on 01 Oct 2019 KH-MOI-226812-CS-INDV / Individual One National Independent Component 3: Project Pending IDA / 59600 Post Consultant Open 6,000.00 0.00 2021-05-03 2021-06-21 2021-07-12 2021-08-16 2021-10-15 auditor for Infrastructure with Management Implementation Selection (2 month 2021) Based in PCO KH-MOI-226814-CS-INDV / Component 1: Improving Individual One National Agriculture Under IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 30,000.00 0.00 2021-04-08 2021-04-23 2021-05-27 2021-06-17 2021-07-22 2022-07-22 Likelihood Specialist for GDA- Implementation and Vulnerable Households Selection MAFF (12 Months) KH-MOI-226815-CS-INDV / Provincial Infrastructure Specialist (Rural Road Component 1: Improving Individual Under Construction Engineer) at SRP IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 24,000.00 0.00 2021-04-08 2021-04-23 2021-05-27 2021-06-17 2021-07-22 2022-07-22 Implementation (12 Months) to replacement and Vulnerable Households Selection Mr Set Chamroeun Resigned on 31 Jan 21 KH-MOI-226816-CS-INDV / Individual One Junior Finance/Admin Component 3: Project IDA / 59600 Post Consultant Open 9,600.00 0.00 Under Review 2021-05-03 2021-05-21 2021-06-23 2021-07-07 2021-08-11 2022-08-11 Officer Based in PCO (12 Management Selection Months) KH-MOI-226817-CS-INDV / Component 2: Improving Individual One Junior Finance/Admin IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 9,600.00 0.00 Under Review 2021-05-03 2021-05-21 2021-06-23 2021-07-07 2021-08-11 2022-08-11 Officer Based in SMT-PPCH and Vulnerable Households Selection (12 Months) KH-MOI-226818-CS-INDV / Component 1: Improving Individual One Junior Finance/Admin IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 9,600.00 0.00 Under Review 2021-05-03 2021-05-21 2021-06-23 2021-07-07 2021-08-11 2022-08-11 Officer Based in SMT- SRP (12 and Vulnerable Households Selection Months) KH-MOI-226819-CS-INDV / Component 1: Improving Individual One Promote finance linkage Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 9,600.00 0.00 2021-05-03 2021-06-09 2021-06-23 2021-07-26 2022-07-26 facilitators Base in SMT-SRP Implementation and Vulnerable Households Selection (1pax x12 Months) Page 12