The World Bank Implementation Status & Results Report Locust Emergency and Food Security Project (P174314) Locust Emergency and Food Security Project (P174314) SOUTH ASIA | Pakistan | Agriculture and Food Global Practice | IBRD/IDA | Investment Project Financing | FY 2021 | Seq No: 1 | ARCHIVED on 23-Nov-2020 | ISR44157 | Implementing Agencies: Agricultural, Supply & Prices Department, Govt. of Sindh, Ministry of National Food Security and Research, Agriculture Department, Govt. of the Punjab, Islamic Republic of Pakistan, Department of Agriculture, Govt. of Khyber Pakhtunkhwa, Agriculture and Cooperatives Department, Govt of Balochistan Key Dates Key Project Dates Bank Approval Date: 31-Jul-2020 Effectiveness Date: -- Planned Mid Term Review Date: 04-Apr-2022 Actual Mid-Term Review Date: Original Closing Date: 30-Jun-2023 Revised Closing Date: 30-Jun-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To control the locust outbreak, restore livelihoods in locust-affected areas, and strengthen Pakistan’s national food security monitoring and management system. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1 Surveillance and Control Measures:(Cost $104.00 M) Component 2: Livelihood Protection and Rehabilitation:(Cost $50.00 M) Component 3: Early Warning System and Food Security:(Cost $26.00 M) Component 4: Project Management, Monitoring and Evaluation:(Cost $20.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Satisfactory Overall Implementation Progress (IP) -- Satisfactory Overall Risk Rating -- Substantial Implementation Status and Key Decisions The project was approved by the board on July 31, 2020. At the end of September, the project was approved by the Executive Committee of the National Economic Council (ECNEC) subject to revision of the government’s internal project document (PC-1). Clarifications related to: (i) capacity building of the Departments of Plant Protection; (ii) asset attribution; (iii) role of provinces and operations and maintenance arrangements to maintain assets after project closure; (iv) research activities at provincial level; and (v) review and finalization of project management and technical assistance costs. The PC-I has now been revised in close consultation with all relevant stakeholders and is expected to be considered in the third week of November. 11/23/2020 Page 1 of 9 The World Bank Implementation Status & Results Report Locust Emergency and Food Security Project (P174314) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial -- Substantial Macroeconomic Substantial -- Substantial Sector Strategies and Policies Moderate -- Moderate Technical Design of Project or Program Moderate -- Moderate Institutional Capacity for Implementation and Substantial -- Substantial Sustainability Fiduciary Substantial -- Substantial Environment and Social High -- High Stakeholders Moderate -- Moderate Other -- -- -- Overall Substantial -- Substantial Results PDO Indicators by Objectives / Outcomes Control of desert locust outbreak implemented IN00914463 ►Affected agricultural land area restored to productivity (percentage) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 90.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Percentage of affected agricultural land area restored to productivity IN00914465 ►Affected pasture/rangeland restored to productivity (percentage) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 90.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 11/23/2020 Page 2 of 9 The World Bank Implementation Status & Results Report Locust Emergency and Food Security Project (P174314) Comments: Percentage of affected pasture/rangeland restored to productivity IN00914503 ►Early warning system developed, functioning and sustainable (Yes/No) (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Early warning system developed, functioning and sustainable. IN00914505 ►Regional coordination on locust surveillance and control strengthened (Yes/No) (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Regional coordination on locust surveillance and control strengthened. Livelihoods in locust-affected areas restored IN00914464 ►Affected households supported with cash- or inputs-based assistance (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 96,000.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Number of households receiving cash or inputs based assistance to mitigate the effects of locust damage. IN00914502 Females as direct recipients of cash- or inputs-based assistance (Number) (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 20,000.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 IN00914504 ►Share of locust-affected farmers (incl. livestock owners) report renewed agricultural activity (percentage) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 90.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Share of locust-affected farmers (including crop farmers, livestock owners) who have restarted (and Comments: reporting) agricultural activity within one year of having been affected by the locust outbreak. 11/23/2020 Page 3 of 9 The World Bank Implementation Status & Results Report Locust Emergency and Food Security Project (P174314) IN00914506 Share of locust-affected female farmers report renewed agricultural activity (percentage) (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 90.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 National food security system strengthened IN00914501 ►National food security and nutrition information system strengthened and functioning (Yes/No) (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: National food security and nutrition information system strengthened and functioning Overall Comments PDO Project implementation not yet started. Intermediate Results Indicators by Components Surveillance and Control Measures IN00914507 ►Land area sprayed with pesticide for locust control (Hectare (Ha)) (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 2,500,000.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Total land area in ha sprayed with pesticides for locust control (annually). IN00914511 ►Area of locust-affected land surveyed (Hectare (Ha)) (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 4,000,000.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Area of locust-affected land surveyed (annually). IN00914514 11/23/2020 Page 4 of 9 The World Bank Implementation Status & Results Report Locust Emergency and Food Security Project (P174314) ►Locust monitoring system operational (Yes/No) (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Assessment of whether country-level locust monitoring systems are operational. IN00914517 ►Pesticide inventory stored in accordance with appropriate international safety standards (Yes/No) (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: National and provincial level assessment of safety of storage of locust pesticide inventory IN00914519 ►Number of locust control teams trained (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1,000.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Number of locust control teams trained IN00914522 ►Women engaged in ground surveys for pest surveillance (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 4,000.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Number of women engaged in ground surveys for pest surveillance. Livelihood Protection and Rehabilitation IN00914508 ►Community-based infrastructure improved (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 40.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Number of community-based infrastructure improved 11/23/2020 Page 5 of 9 The World Bank Implementation Status & Results Report Locust Emergency and Food Security Project (P174314) IN00914524 ►Person work-days generated by emergency cash-for-work schemes (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 460,000.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Number of person work-days generated for affected populations though emergency cash-for-work Comments: schemes IN00914525 ►Farmer Field School participants adopting CSA technologies and practices (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 15,000.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Number of farmer field school participants adopting CSA technologies and practices IN00914526 ►Agriculture Disaster & Climate Risk Management Operational Plans with Implementation Guidelines developed (district) (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 36.00 Date 01-Jun-2020 -- 06-Nov-2020 30-Aug-2023 Number of Agriculture Disaster & Climate Risk Management Operational Plans with Implementation Comments: Guidelines developed (district) Early Warning Preparedness and Food Security IN00914509 ►National locust outbreak early warning and preparedness plan tested (Yes/No) (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Assessment of readiness to launch locust early warning and preparedness plan. IN00914512 ►Desert locust control centers fully operational (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 19.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 11/23/2020 Page 6 of 9 The World Bank Implementation Status & Results Report Locust Emergency and Food Security Project (P174314) Number of Desert Locust Control Centers (DLCC) in the network, rehabilitated and/or newly established Comments: and fully operational. IN00914515 ►Strategy for the National Food Strategic Reserve updated (Yes/No) (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Strategy for the National Food Strategic Reserve updated IN00914520 ►Capacity of Crop Reporting Services (CRS) of provincial agriculture departments strengthened (Yes/No) (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Capacity of Crop Reporting Services (CRS) of provincial agriculture departments in using the standard Comments: data collection techniques including GIS for data collection, crop yield forecasting strengthened. IN00914523 ►A mechanism to collect information on prices, stocks, supplies and demand of essential food items and agriculture inputs from district level developed (Yes/No) (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 A mechanism to collect information on prices, stocks, supplies and demand of essential food items and Comments: agriculture inputs from district level developed Project Management, and Monitoring and Evaluation IN00914510 ►Awareness raising campaigns conducted (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 15.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Comments: Number of awareness raising communications campaigns conducted. IN00914513 Awareness campaigns targeted to women (Number) (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 10.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 11/23/2020 Page 7 of 9 The World Bank Implementation Status & Results Report Locust Emergency and Food Security Project (P174314) IN00914516 ►Citizen Engagement: Beneficiaries that feel project investments reflect their needs and provide feedback (percentage) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 75.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 Citizen Engagement: Percentage of beneficiaries that feel project investments reflect their needs and Comments: provide feedback IN00914518 Women beneficiaries that feel project investments meet their needs and provide feedback (percentage) (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 75.00 Date 01-Jun-2020 -- 06-Nov-2020 31-Aug-2023 IN00914521 ►Minimum 30 percent project staff should be women (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 30.00 Date 31-Aug-2020 -- 06-Nov-2020 31-Aug-2023 Comments: 30 percent of staff engaged in project implementation should be women. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed Not P174314 IDA-67630 USD 200.00 200.00 0.00 0.00 205.46 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P174314 IDA-67630 31-Jul-2020 -- -- 30-Jun-2023 30-Jun-2023 Effective Cumulative Disbursements 11/23/2020 Page 8 of 9 The World Bank Implementation Status & Results Report Locust Emergency and Food Security Project (P174314) PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 11/23/2020 Page 9 of 9