Sample Procurement Plan I. General 1. Bank’s approval Date of the Procurement Plan: Original, October 2015. 2. Date of General Procurement Notice: June 26, 2017 3. Period covered by this procurement plan: From September 2017 to September 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB (Works) All All 2. ICB (Goods and Non-Consulting All All Services) 3. NCB (Works) From US$ 15 million All 4. NCB (Goods and Non-Consulting From US$ 4 million All Services) 5. Shopping (Works) None None 6. Shopping (Goods and Non- None None Consulting Services) 7. Direct Contracting (Works) From US$ 15 million All Direct Contracting (Goods and Non- From US$ 4 million All Consulting Services) 2. Prequalification. Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: Not applicable. 4. Reference to (if any) Project Operational/Procurement Manual: The Operations Manual issued by the SEPLAN (Project Implementation Unit) describes the methods and procedures applicable to all procurement of goods, works, non-consulting services and consulting services financed by the Loan Agreement # 8575-BR. 5. Any Other Special Procurement Arrangements: Eligible expenditures under Part 1 of the Project are not subject to the Procurement and Consultant Guidelines. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) July 9, 2010 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior/Post) million nce (yes/no) 1 Summary of 0.24 1 No Prior the ICBs (Goods) 2 Summary of 3.1 16 No Post the NCBs (Goods) 3 Summary of 0.96 11 No Post the NCBs (Non- Consulting Services) 4 Summary of 0.23 5 No Post the Shoppings (Goods) 5 Summary of 0.37 10 No Post the Shoppings (Non- Consulting Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) From US$ 1 million All 2. Single Source Selection (Firms) From US$ 1 million All 3. Individual Consultant From US$ 300,000 All 4 Single Source Selection (Individuals) From US$ 300,000 All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 1,500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank (Prior / Post) July 9, 2010 US$ million 1 Summary of 5.8 19 Prior number of contracts that will be let under QCBS method 2 Summary of 2.2 25 Post SCQ number of contracts that will be let under methods other than QCBS 3 Summary of 2.7 22 Post IC number of contracts that will be let under Individual Consultant method July 9, 2010 PROCUREMENT Brazil : Piaui: Pillars of Growth and Social Inclusion Project PLAN General Information Country: Brazil Banks Approval Date of the Original Procurement Plan: 2017-10-16 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-10-16 Project ID: P129342 GPN Date: 2017-06-26 Project Name: Piaui: Pillars of Growth and Social Inclusion Project Loan / Credit No: IBRD / 85750 Executing Agency(ies): Secretariat of Education of the State of Piauí, General Ombudsman Department of the State of Piauí, Secretariat of Rural Development of the State of Piauí, Secretariat of Health of the State of Piauí, Secretariat of Finance of the State of Piauí, Secretariat of Planning of the State of Piaui, Coordination for Women's Policies of the State of Piauí WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-OGE-PI-1-GO-RFQ / Equipamentos de informatica com objetivo de atender a ã interligaço dos pontos de Component 2: Provision of acesso para que o sistema technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Limited 46,667.00 0.00 2017-05-13 2017-07-08 2018-01-04 informatizado da Ouvidoria esteja strengthen the Borrowers public Quotations Envelope Implementation na Ouvidoria Geral do Estado do management. Piauí, Ouvidorias Setoriais e nos onze territórios do Estado do Piaui BR-OGE-PI-2-GO-RFQ / Equipamentos de infraestrutura Component 2: Provision of de escritorio para melhorar technical assistance to Request for Single Stage - One Pending estrutura fisica da Ouvidoria IBRD / 85750 Post Limited 46,667.00 0.00 2017-06-13 2017-08-08 2018-02-04 strengthen the Borrowers public Quotations Envelope Implementation Geral do Estado, dos gabinetes management. dos ouvidores setoriais e territoriais BR-OGE-PI-3-GO-RFQ / Component 2: Provision of Aparelhos de ar condicionando technical assistance to Request for Single Stage - One Pending tipo SPLIT e tipo janela na sede IBRD / 85750 Post Limited 10,666.00 0.00 2017-06-13 2017-08-08 2018-02-04 strengthen the Borrowers public Quotations Envelope Implementation propria da Ouvidoria Geral do management. Estado do Piaui BR-SEFAZ-PI-1-GO-RFQ / Component 2: Provision of ã Aquisiço de computadores technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Open - National 15,000.00 0.00 2017-10-13 2017-12-08 2018-06-06 sendo cinco computadores e um strengthen the Borrowers public Quotations Envelope Implementation notebook management. BR-SDR-PI-1-GO-RFQ / Component 2: Provision of Equipamentos de comunicacao technical assistance to Request for Single Stage - One Pending dois GPS tres datashow seis IBRD / 85750 Post Open - National 8,451.00 0.00 2017-05-15 2017-07-10 2018-01-06 strengthen the Borrowers public Quotations Envelope Implementation tablets com GPS e uma camera management. fotografica BR-SDR-PI-2-GO-RFQ / Component 2: Provision of Computadores seis por URGP e technical assistance to Request for Single Stage - One Pending dois na UGP e impressoras 4 IBRD / 85750 Post Open - National 16,901.00 0.00 2017-05-15 2017-07-10 2018-01-06 strengthen the Borrowers public Quotations Envelope Implementation multifuncionais e cinco basicas management. para a UGP e as URGP BR-CEPM / PI-29613-GO-RFQ / ã Aquisiço de kits a serem entregues aos Municípios para Component 2: Provision of ã implantaço física dos technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Open - National 29,000.00 0.00 2018-01-13 2018-03-10 2018-09-06 Organismos de Políticas para as strengthen the Borrowers public Quotations Envelope Implementation Mulheres (mesas, cadeiras, management. computadores, impressoras e armários). Component 2: Provision of BR-SEPLAN- PI-30415-GO-RFB technical assistance to Single Stage - One Pending / Compra de veículos IBRD / 85750 Post Request for Bids Open - National 200,000.00 0.00 2017-10-02 2017-10-07 2017-11-18 2017-12-18 2018-01-22 2018-07-21 strengthen the Borrowers public Envelope Implementation automotores para ró gãos management. BR-SEPLAN-PI-4-NC-RFQ / Contrataço ã de serviços de Component 2: Provision of hospedagem para os technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Open - National 58,812.50 0.00 2017-11-27 2018-01-22 2018-07-21 conselheiros da sociedade civil strengthen the Borrowers public Quotations Envelope Implementation participarem das atividades nos management. 12 territórios BR-SEPLAN-PI-9-GO-RFB / ã Aquisiço de 10 computadores, Component 2: Provision of 6 notebooks, 5 tablets, 2 technical assistance to Single Stage - One Pending IBRD / 85750 Post Request for Bids Open - National 18,750.00 0.00 2018-01-01 2018-01-06 2018-02-17 2018-04-23 2018-10-20 maquina fotografica, 1 filmadora, strengthen the Borrowers public Envelope Implementation 1 impressora apara apoiar as management. atividades do SIMO BR-SEPLAN-PI-11-GO-RFB / Component 2: Provision of Aquisiçoã de 2 equipamentos de technical assistance to Single Stage - One Pending IBRD / 85750 Post Request for Bids Open - National 125,000.00 0.00 2018-11-01 2018-11-06 2018-12-18 2019-03-19 2019-09-15 video wal 2x30 para sala de strengthen the Borrowers public Envelope Implementation ã situaço management. BR-SEPLAN- PI-30829-GO-RFQ Component 2: Provision of ã / Aquisiço ã e instalaço de technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Open - National 31,250.00 0.00 2017-11-27 2018-01-22 2018-07-21 equipamentos para strengthen the Borrowers public Quotations Envelope Implementation videoconferência management. BR-SEPLAN-PI-10-GO-RFQ / Component 2: Provision of ã Aquisiço de 02 Kit de technical assistance to Request for Single Stage - One IBRD / 85750 Post Open - National 51,200.00 0.00 Canceled 2018-02-06 2018-04-28 2018-10-25 moderaço ã para apoiar as strengthen the Borrowers public Quotations Envelope atividades do planejamento management. Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-OGE-PI-6-NCS-RFQ / Component 2: Provision of Capacitacoes e treinamentos technical assistance to Request for Single Stage - One Pending dos profissionais que atuarao na IBRD / 85750 Post Limited 42,666.00 0.00 2017-08-13 2017-10-08 2018-04-06 strengthen the Borrowers public Quotations Envelope Implementation area da Ouvidoria Geral do management. Estado BR-SEPLANUGP-PI-03-CS- Component 2: Provision of INDV / Serviços de fornecimento technical assistance to Single Stage - One Pending IBRD / 85750 Post Request for Bids Open - National 115,385.00 0.00 2017-05-01 2017-05-06 2017-06-17 2017-07-17 2017-08-21 2018-02-17 ã e aquisiço de passagens strengthen the Borrowers public Envelope Implementation aéreas management. BR-CEPM / PI-29610-NC-RFQ / Component 2: Provision of ã , publicaço Ediço ã e lançamento technical assistance to Request for Single Stage - One Pending do Plano estadual de Políticas IBRD / 85750 Post Open - National 84,000.00 0.00 2017-11-18 2018-01-13 2018-07-12 strengthen the Borrowers public Quotations Envelope Implementation para as mulheres do Estado do management. Piauí BR-CEPM-PI-1-NC-RQF / Serviços logisticos (coffe break, impressão de materiais...) para a Component 2: Provision of ã realizaço de oficinas envolvendo technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Open - National 20,000.00 0.00 2017-07-06 2017-08-31 2018-02-27 Poder Público Estadual, Poder strengthen the Borrowers public Quotations Envelope Implementation Público Municipal e Sociedade management. Civil nos 12 territórios de desenvolvimento do Estado BR-CEPM / PI-29612-NC-RFQ / Serviços logísticos (coffe Break, impressão de material...) para Component 2: Provision of oficinas de assessoramento e technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Open - National 15,000.00 0.00 2017-11-25 2018-01-20 2018-07-19 acompanhamento da strengthen the Borrowers public Quotations Envelope Implementation implantaçoã e implementaçoã management. dos Organismos Governamentais de Políticas para as Mulheres. BR-SEPLAN-PI-3-NC-RFQ / Component 2: Provision of Serviço de fornecimento de technical assistance to Request for Single Stage - One Pending alimentaçoã e locaçoã de IBRD / 85750 Post Open - National 68,562.50 0.00 2017-07-06 2017-08-31 2018-02-27 strengthen the Borrowers public Quotations Envelope Implementation auditório, sob demanda, para management. evento (12 territorios) BR-SEPLAN-PI-5-NC-RFQ / Contrataçoã de serviços de Component 2: Provision of deslocamento para os technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Limited 41,875.00 0.00 2017-10-07 2017-12-02 2018-05-31 conselheiros da sociedade civil strengthen the Borrowers public Quotations Envelope Implementation participarem das atividades nos management. 12 territorios BR-SEPLAN-PI-16-NC-RFB / Component 2: Provision of ã Contrataço de serviços gráficos technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Open - National 62,500.00 0.00 2017-06-18 2017-08-13 2018-02-09 para impressão das publicaçe õ s strengthen the Borrowers public Quotations Envelope Implementation do SIMO e atividades territoriais management. BR-SEPLANUGP- PI-30311-NC- Component 2: Provision of ã RFQ / Serviço de alimentaço e technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Limited 30,000.00 0.00 2017-10-06 2017-12-01 2018-05-30 aluguel de espaço para strengthen the Borrowers public Quotations Envelope Implementation õ s treinamento em aquisiçe management. Component 2: Provision of BR-SEPLANUGP- PI-30310-NC- technical assistance to Request for Single Stage - One Pending RFB / Empresa de auditoria de IBRD / 85750 Post Limited 80,000.00 0.00 2018-01-07 2018-03-04 2018-08-31 strengthen the Borrowers public Quotations Envelope Implementation DLIs management. BR-SEPLAN- PI-30824-NC-RFQ / Contrataçoã de 01 consultor especializado para serviço de Component 2: Provision of ã diagramaço e art design dos technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Open - National 9,000.00 0.00 2018-01-07 2018-03-04 2019-03-29 materiais produzidos para o strengthen the Borrowers public Quotations Envelope Implementation SIMO e açe õ s territoriais que management. desenvolverá a identidade visual ã da aço BR-SEPLANUGP- PI-30304-NC- Component 2: Provision of RFB / Contrataçoã de firma technical assistance to Request for Single Stage - One Pending independente de auditoria IBRD / 85750 Post Limited 22,500.00 0.00 2018-01-07 2018-03-04 2018-08-31 strengthen the Borrowers public Quotations Envelope Implementation financeira para os anos do management. Projeto BR-SEPLAN-PI-8-NC-RFQ / Aluguel de 2 veiculos, por dois Component 2: Provision of anos, para apoio ao processo de technical assistance to Request for Single Stage - One Pending IBRD / 85750 Post Limited 53,000.00 0.00 2017-07-06 2017-08-31 2019-12-31 monitoramento nos r ó gãos strengthen the Borrowers public Quotations Envelope Implementation setoriais e nos territórios de management. desenvolvimento. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEDUC-PI-13083-CS-QCBS / Consultoria para o processo de Component 2: Provision of ã diagnóstico e elaboraço de technical assistance to Quality And Cost- Pending IBRD / 85750 Post Open - National 108,451.00 0.00 2017-06-12 2017-07-03 2017-08-16 2017-09-13 2017-10-13 2017-11-17 2017-12-22 2018-12-22 ã plano de aço para strengthen the Borrowers public Based Selection Implementation aprimoramento da gestão da management. SEDUC BR-SEDUC-PI-13097-CS-QCBS Component 2: Provision of ã / Elaboraço do Plano de technical assistance to Quality And Cost- Pending IBRD / 85750 Post Open - National 207,042.00 0.00 2017-04-18 2017-05-09 2017-06-22 2017-07-20 2017-08-19 2017-09-23 2017-10-28 2018-10-28 Expansão da Educaço ã Técnica strengthen the Borrowers public Based Selection Implementation de Nível Médio management. Page 2 BR-SEDUC-PI-7-CS-QCBS / Component 2: Provision of Consultoria para diagnóstico e technical assistance to Quality And Cost- Pending ã elaboraço do Plano Estadual de IBRD / 85750 Post Open - National 87,100.00 0.00 2017-05-10 2017-05-31 2017-07-14 2017-08-11 2017-09-10 2017-10-15 2017-11-19 2018-11-19 strengthen the Borrowers public Based Selection Implementation Desenvolvimento Profissional dos management. Professores BR-SEDUC-PI-8-CS-QCBS / Component 2: Provision of ã Consultoria para realizaço da technical assistance to Quality And Cost- Pending IBRD / 85750 Post Open - National 197,183.00 0.00 2017-05-10 2017-05-31 2017-07-14 2017-08-11 2017-09-10 2017-10-15 2017-11-19 2018-11-19 ã avaliaço de impacto do strengthen the Borrowers public Based Selection Implementation Programa Poupança Jovem management. Component 2: Provision of BR-SEDUC-PI-9-CS-QCBS / technical assistance to Quality And Cost- Pending Estudo diagnóstico do ensino IBRD / 85750 Post Open - National 147,887.00 0.00 2017-05-10 2017-05-31 2017-07-14 2017-08-11 2017-09-10 2017-10-15 2017-11-19 2018-11-19 strengthen the Borrowers public Based Selection Implementation médio noturno no Piauí management. BR-SDR-PI-3-CS-QCBS / Component 2: Provision of ã Contrataço de 2 estudos de technical assistance to Quality And Cost- Pending IBRD / 85750 Post Open - National 16,901.00 0.00 2017-05-26 2017-06-16 2017-07-30 2017-08-27 2017-09-26 2017-10-31 2017-12-05 2018-12-05 desempenho físico do strengthen the Borrowers public Based Selection Implementation PROGERE management. BR-SDR-PI-4-CS-QCBS / Component 2: Provision of ã Contrataço de estudo de technical assistance to Quality And Cost- Pending IBRD / 85750 Post Open - National 16,901.00 0.00 2018-01-08 2018-01-29 2018-03-14 2018-04-11 2018-05-11 2018-06-15 2018-07-20 2019-07-20 ã avaliaço de meio termo do strengthen the Borrowers public Based Selection Implementation PROGERE management. Component 2: Provision of BR-SDR-PI-5-CS-CQS / Consultant technical assistance to Pending ã Contrataço ã para customizaço IBRD / 85750 Post Qualification Open - National 45,070.00 0.00 2017-02-06 2017-02-27 2017-04-12 2017-05-12 2017-06-16 2017-12-13 strengthen the Borrowers public Implementation do SIGMA Selection management. Component 2: Provision of BR-SDR-PI-9-CS-QCBS / technical assistance to Quality And Cost- Pending IBRD / 85750 Post Open - National 16,901.00 0.00 2019-01-08 2019-01-29 2019-03-14 2019-04-11 2019-05-11 2019-06-15 2019-07-20 2020-07-19 ã Avaliaço final de impactos strengthen the Borrowers public Based Selection Implementation management. BR-SESAPI-PI-4-CS-QCBS / Consultoria para contratacao Component 2: Provision of para elaboracao dos criterios de technical assistance to Quality And Cost- Pending IBRD / 85750 Post Open - National 180,282.00 0.00 2017-05-10 2017-05-31 2017-07-14 2017-08-11 2017-09-10 2017-10-15 2017-11-19 2018-11-19 acesso as ofertas reguladas e strengthen the Borrowers public Based Selection Implementation governanças do complexo management. regulador - IPF/Ass. Téc BR-SESAPI-PI-5-CS-QCBS / Consultoria para contratacao de Component 2: Provision of capacitacao para implantacao technical assistance to Quality And Cost- Pending dos protocolos na Esf dos IBRD / 85750 Post Open - National 180,282.00 0.00 2017-05-11 2017-06-01 2017-07-15 2017-08-12 2017-09-11 2017-10-16 2017-11-20 2018-11-20 strengthen the Borrowers public Based Selection Implementation municipios integrantes dos management. Territorios de desenvolvimento do 05 CEDCS - IPF/Ass. Téc BR-SEPLAN-PI-1-CS-QCBS / ã Contrataço de consultoria para Component 2: Provision of ã reestruturaço do processo de technical assistance to Quality And Cost- Pending IBRD / 85750 Post Open - National 281,250.00 0.00 2017-09-12 2017-10-03 2017-11-16 2017-12-14 2018-01-13 2018-02-17 2018-04-18 2019-04-18 planejamento, orçamento, strengthen the Borrowers public Based Selection Implementation monitoramento e avaliaçoã do management. Governo do Piaui. BR-SAUDE-PI-30454-CS-QCBS Component 2: Provision of ã / Consultoria para elaboraço de technical assistance to Quality And Cost- Pending inquérito epidemiológico sobre as IBRD / 85750 Post Open - National 225,352.11 0.00 2017-10-16 2017-11-06 2017-12-20 2018-01-17 2018-02-16 2018-03-23 2018-04-27 2019-04-27 strengthen the Borrowers public Based Selection Implementation doenças negligenciadas geo- management. helmintíase e leishmaniose INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEPLANUGP-PI-01-CS- Component 2: Provision of ã INDV / Contrataço de serviços technical assistance to Individual Consultant Under IBRD / 85750 Post Open 72,000.00 0.00 2017-08-10 2017-09-20 2017-09-29 2017-10-02 2018-10-02 õ s de consultoria em aquisiçe strengthen the Borrowers public Selection Implementation (UGP) management. BR-SEPLAN-PI-6-CS-CI / Contrataçoã de consultor especializados para realizar Component 2: Provision of õ s de capacitaço açe ã de technical assistance to Individual Consultant Pending IBRD / 85750 Post Open 6,750.00 0.00 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2018-12-08 conselheiros territoriais nas strengthen the Borrowers public Selection Implementation á eas de planejamento, controle r management. social, agendas territoriais e monitoramento BR-SEPLAN-PI-12-CS-INDV / Component 2: Provision of Contrataço ã de consultor technical assistance to Individual Consultant Pending especializado para serviço de IBRD / 85750 Post Open 18,750.00 0.00 2017-11-27 2018-02-12 2018-03-05 2018-04-09 2019-02-28 strengthen the Borrowers public Selection Implementation elaboraçoã das agendas management. territoriais e atlas dos territórios BR-SEPLAN-PI-15-CS-INDV / ã Contrataço de consultor Component 2: Provision of ã especializado para implantaço technical assistance to Individual Consultant Pending IBRD / 85750 Post Limited 31,250.00 0.00 2017-08-01 2017-08-06 2017-08-27 2017-10-01 2018-03-30 da metodologia do PMBOK strengthen the Borrowers public Selection Implementation (gerenciamento de projetos) para management. o SIMO BR-SEPLAN- PI-30295-CS-INDV ã / Contrataço de consultor especializados para realizar Component 2: Provision of õ s de capacitaço açe ã de technical assistance to Individual Consultant Pending IBRD / 85750 Post Open 6,750.00 0.00 2018-01-02 2018-02-20 2018-03-13 2018-04-17 2018-10-14 conselheiros territoriais nas strengthen the Borrowers public Selection Implementation á eas de planejamento, controle r management. social, agendas territoriais e monitoramento Page 3 BR-SEPLAN- PI-30296-CS-INDV ã / Contrataço de consultor especializados para realizar Component 2: Provision of õ s de capacitaço açe ã de technical assistance to Individual Consultant Pending IBRD / 85750 Post Open 6,750.00 0.00 2018-01-02 2018-02-20 2018-03-13 2018-04-17 2018-10-14 conselheiros territoriais nas strengthen the Borrowers public Selection Implementation á eas de planejamento, controle r management. social, agendas territoriais e monitoramento BR-SEPLAN- PI-30297-CS-INDV ã / Contrataço de consultor especializados para realizar Component 2: Provision of õ s de capacitaço açe ã de technical assistance to Individual Consultant Pending IBRD / 85750 Post Open 6,750.00 0.00 2018-01-02 2018-02-20 2018-03-13 2018-04-17 2018-10-14 conselheiros territoriais nas strengthen the Borrowers public Selection Implementation á eas de planejamento, controle r management. social, agendas territoriais e monitoramento BR-SEPLANUGP- PI-30307-CS- Component 2: Provision of INDV / Consultor especializado technical assistance to Individual Consultant Pending IBRD / 85750 Post Open 51,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 em salvaguardas ambientais e strengthen the Borrowers public Selection Implementation sociais management. BR-SEPLAN-PI-13-CS-INDV / Contrataçoã , por tempo, de 01 consultor especializado para Component 2: Provision of ã serviço de elaboraço de technical assistance to Individual Consultant Pending procedimentos e metodologias IBRD / 85750 Post Open 15,000.00 0.00 2018-01-30 2018-04-04 2018-04-25 2018-06-07 2018-12-04 strengthen the Borrowers public Selection Implementation com aplicaço ã de estatísticas e management. ã tecnologias da informaço para extrair e processar dados do SIMO Page 4