Procurement Plan (PP) for Goods for FY 2012 – 2013, Feb 3, 2013 75764 Project Name & ID: Additional Financing for social safety nets projects, Seed Sub-component (SSNP-AF 2/NARC) Executing Agency: DOA Loan/Credit/Grant No: H 424-NP Implementing Agency: NARC Contract Signing Completion date Bid document to Recomm. to WB Description of Procurement at Public Opening procedure GoN BER & Award BER & Award Cost Estimate center/district (NRs Million) Bid invitation WB's NOL to WB's NOL to Procurement Procurement Recommend. Goods S No. of contract Method of Prior/post PP Status Remarks Bid doc Review of Bids or WB WB 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Procurement of Farm Machineries Post P 16.81 NCB PPA 5 Nov 16Nov 18 1 9 Dec 20 Jan 30 Jan 10 Feb 10 May Central 13 and Agricultural tools. 2012 2012 Nov 2012 2013 2013 2013 2013 Office 2012 SSNP-AF/G/NCB/Package-13 Post R Post A Slice 1: Post P 1.89 Rice Transplanter - 3, Power Sprayer -4 Post R SSNP-AF/G/NCB-13.1 Post A Slice 2: Post P 9.90 Combine Multi crops Harvester- 3 Post R SSNP-AF/G/NCB -13.2 Post A Slice 3: Post P 4.26 Tractor not less than 60 HP- 3, Diskc Harrow- 3 Post R Post A SSNP-AF/G/NCB -13.3 Slice 4: Post P .76 Transportation Tailor for Tractor hydraulic - 4 Post R SSNP-AF/G/NCB -13.4 Post A 14 Procurement of Seed Testing Post P 2.8905 NCB PPA 5 Nov 16Nov 18 1 9 Dec 20 Jan 30 Jan 10 Feb 10 May Central Equipment 2012 2012 Nov 2012 2013 2013 2013 2013 Office 2012 SSNP-AF/G/NCB/Package-14 Post R Post A Slice 1: Grain Analyzer Computer Post P .9965 (Moisture Meter) 1 nos., Seed Divider Post R Boerner type -4 , Seed Purity board - 4, Seed Scaner with software - 1 Post A SSNP-AF/G/NCB-14.1 Slice 2: Seed Treating cum Dressing -4, Post P 1.894 Seed Cleaner cum Grader minimum Post R 250 kg/hr - 5 SSNP-AF/G/NCB -14.2 Post A 1 Procurement of Laboratory Post P 4.786 NCB PPA 5 Nov 16Nov 18 1 9 Dec 20 Jan 30 Jan 10 Feb 10 May Central Equipment 2012 2012 Nov 2012 2013 2013 2013 2013 Office 15 2012 SSNP-AF/G/NCB/Package-15 Post R Post A Slice 1: Spectrophotometer - 3, Flame Post P 2.611 Photometer - 4, Trinocular Stereo Zoom Post R Microscope for seed lab -3 Post A SSNP-AF/G/NCB-15.1 Slice 2: Horizontal Laminar flow -1, Post P 2.175 Chlorophyll Meter - 1, Soil pH Meter - Post R 5, Autoclave -4 , Hot air Oven - 5, Leaf Post A Area Meter- 1 SSNP-AF/G/NCB-15.2 Procurement of Office Equipment Post P 1.7135 NCB PPA 5 Nov 16Nov 18 1 9 Dec 20 Jan 30 Jan 10 Feb 10 May 16 2012 2012 Nov 2012 2013 2013 2013 2013 Multimedia Projector-8, GPS-7, Laptop 2012 Computer-8 Post R Post A SSNP-AF/G/NCB/Package -16 Note: 1. Up to Package 12 of Goods were completed in previous Fiscal Years. 2. The date of BER Award Recomm. to WB and WB's NOL of the post review packages are assumed the approval of the authorised officials. 2 Procurement Plan (PP) for Works for FY 2012 – 2013, Feb 3, 2013 Project Name & ID: Additional Financing for social safety nets projects, Seed Sub-component (SSNP-AF 2/NARC) Executing Agency: DOA Loan/Credit/Grant No: H 424-NP Implementing Agency: NARC Contract Signing Completion date Bid document to Recomm. to WB Description of Procurement at Public Opening procedure GoN BER & Award BER & Award Cost Estimate center/district (NRs Million) Bid invitation WB's NOL to WB's NOL to Procurement Procurement Recommend. Works S No. of contract Method of Prior/post PP Status Remarks Bid doc Review of Bids or WB WB 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 7 Nov 16 Nov 19 21 22 Jan 30 Jan 10 Feb 10 Concern 7 Construction, Repair and Maintenance Post P 5.15 NCB PPA 2012 2012 Nov Dec 2013 2013 2013 May Stations Work at RARS, Tarahara and Parwanipur 2012 2012 2013 Post R SSNP-AF/W/NCB/Package-7 Post A Slice 1: Construction of Generator house, Post P 1.5 Repair and Maintenance of Seed storage roof Post R and Thresing Floor at RARS, Tarahara, Sunsari Post A SSNP-AF/W/NCB-7.1 Slice 2: : Construction of Seed Storage Godwn Post P 3.65 and covered threshing floor at RARS, Parwanipur, Bara Post R SSNP-AF/W/NCB-7.2 Post A ____ 7 Nov 16 Nov 19 21 22 Jan 30 Jan 10 Feb 10 Concern Rehabilitation of Electricity System at Post P 2.75 NCB PPA 2012 2012 Nov Dec 2013 2013 2013 May Stations 8 Different Stations: 2012 2012 2013 Post SSNP-AF/W/NCB/Package-8 Post Slice 1: Rehabilitation of Electricity System at Post P .55 RARS, Tarahara Post R SSNP-AF/W/NCB--8.1 Post A Slice 2: Rehabilitation of Electricity System at Post P .55 RARS, Parwanipur Post R SSNP-AF/W/NCB--8.2 Post A Slice 3: Rehabilitation of Electricity System at Post P .55 NMRP, Rampur, Chitwan Post R SSNP-AF/W/NCB--8.3 Post A Slice 4: Rehabilitation of Electricity System at Post P .55 RARS, Nepalgunj Post R SSNP-AF/W/NCB--8.4 Post A Slice 5: Rehabilitation of Electricity System at Post P .55 SSTD, Khumaltar. Post R SSNP-AF/W/NCB--8.5 Post A Note: 1. Up to Package 6 for Works were completed in previous Fiscal Years. 2. The date of BER Award Recomm. to WB and WB's NOL of the post review packages are assumed the approval of the authoriesed officials. 3