Procurement Plan PPCR-Building Resilience to Climate Related Hazzard Project – P127508 I. General II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) (>=US$ 1 million) >= US$ 4 million All for Moderate risk 2. NCB (Goods) (= US$ 4 million All for Moderate risk 3. ICB (Works) (>=US$ 5 million) >= US$ 15 million All for Moderate risk 4. NCB (Works) (=US$ 15 million All for Moderate risk 5. (Non-Consultant Services) >= US$ 4 million All for Moderate risk 6. Shopping (Goods) (<=US$ 0.025 NA million) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) >= US$ 2 million All for Moderate risk 2. Individual >= US$ 0.4 million All for Moderate risk 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement)- excluding procurement packages under implementation [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ (yes/no) (Prior / Post) Summary of the ICB - - - - (Works) Summary of the NCB - - - - (Works) Summary of the ICB - - - - (Goods) Summary of the NCB 868,000 3 - Post (Goods) Summary of the RFQ 28,950 2 - Post (Goods) Summary of the DS - - - - (Goods) Summary of the NCB - - - - (Non-Consultant Services) Summary of RFQ (Non- - - - - Consultant Services) III. Selection of Consultants 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ (Prior / million Post) Summary of number of 608,000 1 Prior contracts that will be let under QCBS Summary of number of 266,000 6 Post INDV contracts that will be let under other methods PROCUREMENT Nepal : Building Resilience to Climate Related Hazards PLAN General Information Country: Nepal Bank’s Approval Date of the Original Procurement Plan: 2017-06-07 2019-09-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P127508 GPN Date: Project Name: Building Resilience to Climate Related Hazards Loan / Credit No: TF / 13665, TF / 13557 Executing Agency(ies): Department of Hydrology and Metereology WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPCR/DHM/W/NCB-11 / Construction of infrastructure Modernization of the (approach road, store, water Single Stage - One TF / 13665 Observation Infrastructure Post Request for Bids Open - National 140,835.09 Signed 2017-07-30 2017-08-04 2017-09-15 2017-10-15 2017-11-19 2018-01-18 tank etc) for installation of Envelope and Forecasting RADAR centre in Surkhet (B.1.4) PPCR/DHM/W/NCB-12 / Construction of infrastructure Modernization of the (approach road, store, water Single Stage - One TF / 13557 Observation Infrastructure Post Request for Bids Open - National 0.00 Canceled 2017-06-30 2017-07-05 2017-08-16 2017-09-15 2017-10-20 2018-04-18 tank etc) for installation of Envelope and Forecasting Upper Air Radiosonde in Kirtipur (B1.5) PPCR/DHM/W/SH-15 / Modernization of the Maintenance of Store house Request for Single Stage - One TF / 13665 Observation Infrastructure Post Limited 10,016.90 Signed 2018-05-18 2018-07-13 2018-12-10 at RADAR site Quotations Envelope and Forecasting Surkhet(B.1.4) PPCR/DHM/W/NCB-12-1 / Construction of infrastructure Modernization of the (approach road, store, water Single Stage - One TF / 13665 Observation Infrastructure Post Request for Bids Open - National 50,507.31 Signed 2018-02-08 2018-02-13 2018-03-27 2018-04-26 2018-05-31 2018-07-15 tank etc) for installation of Envelope and Forecasting Upper Air Radiosonde in Kirtipur (B1.5) PPCR/DHM/W/SH-14 / Shifting of electric pole and Modernization of the Request for Single Stage - One electrification to the TF / 13665 Observation Infrastructure Post Limited 13,465.00 Signed 2018-05-23 2018-07-18 2018-11-15 Quotations Envelope Radiosonde site in Kirtipur, and Forecasting Kathmandu (B.1.4) PPCR/DHM/W/ICB-10 / (Re) Modernization of the construction & refurbishment Open - Single Stage - One TF / 13557 Observation Infrastructure Post Request for Bids 3,013,680.96 Signed 2018-09-30 2018-10-05 2018-11-16 2018-12-16 2019-01-20 2019-07-19 of DHM office building (B International Envelope and Forecasting 5.1) PPCR/DHM/W/SH-17 / Modernization of the Pending Improvement of Hydrological Request for Single Stage - One TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-03-05 2019-04-30 2019-07-29 Station of Saptakoshi river Quotations Envelope and Forecasting on at Chatara (B.1.2) PPCR/DHM/W/SH-19 / Improvement of Hydrological Modernization of the Under Request for Single Stage - One stations of East Rapti River TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-03-30 2019-05-25 2019-08-23 Quotations Envelope at Rajaya and Bagmati at and Forecasting on Raigaun and Bhorleni (B.1.2) Page 1 PPCR/DHM/W/SH-20 / Modernization of the Under Improvement of Hydrological Request for Single Stage - One TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-04-15 2019-06-10 2019-09-08 stations of West Rapti Quotations Envelope and Forecasting on River at Kusum (B.1.2) PPCR/DHM/W/SH-21 / Improvement of Hydrological Modernization of the Under Request for Single Stage - One stations of Tamor river, TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-04-15 2019-06-10 2019-09-08 Quotations Envelope Mewa Khola and Kabeli and Forecasting on Khola at Taplejung (B.1.2) PPCR/DHM/W/SH-22 / Improvement of Hydrological stations of Indrawati, Modernization of the Pending Request for Single Stage - One Dolalghat, Sunkoshi TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-04-20 2019-06-15 2019-09-13 Quotations Envelope Tokselghat and Khokhajor and Forecasting on Khola Hariharpur Gadi (B.1.2) PPCR/DHM/W/SH-13 / Construction of Compound Modernization of the Request for Single Stage - One wall, Fencing, Water Tank TF / 13557 Observation Infrastructure Post Limited 19,060.00 Completed 2019-03-15 2019-05-10 2019-11-06 Quotations Envelope etc at RADAR site in and Forecasting Surkhet (B1.5) PPCR/DHM/W/NCB-7 / Improvement of hydrological Modernization of the Pending stations including Single Stage - One TF / 13665 Observation Infrastructure Post Request for Bids Open - National 0.00 Implementati 2019-03-31 2019-04-05 2019-05-17 2019-06-16 2019-07-21 2019-11-18 Establishment of Cable way Envelope and Forecasting on system at selected stations(B.1.2) PPCR/DHM/W/SH-16 / Modernization of the Construction of Protection Request for Single Stage - One TF / 13665 Observation Infrastructure Post Limited 6,797.93 Completed 2019-03-05 2019-04-30 2019-06-29 wall in Approach Road at Quotations Envelope and Forecasting RADAR site Surkhet. (B.1.2) PPCR/DHM/W/SH-24 / Construction of High Quality Modernization of the Pending Request for Single Stage - One Earthing System for TF / 13557 Observation Infrastructure Post Limited 0.00 Implementati 2019-04-15 2019-06-10 2019-08-09 Quotations Envelope Lightning Safety at RADAR and Forecasting on Site (B. 1.2) PPCR/DHM/W/SH-29 / Modernization of the Pending Protection Wall & Request for Single Stage - One TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-08-12 2019-09-30 2019-12-29 Guard/Store Room at Radar Quotations Envelope and Forecasting on Station Surkhet (B.1.4) PPCR/DHM/W/NCB-27 / Store Building & Modernization of the Pending Single Stage - One Infrastructure Development TF / 13665 Observation Infrastructure Post Request for Bids Open - National 0.00 Implementati 2019-08-11 2019-08-14 2019-09-14 2019-09-29 2019-10-27 2019-12-26 Envelope at Radio Sonde Station and Forecasting on Kirtipur (B.1.11) PPCR/DHM/W/NCB-28 / Modernization of the Pending Partition and other civil Single Stage - One TF / 13557 Observation Infrastructure Post Request for Bids Open - National 0.00 Implementati 2019-08-11 2019-08-14 2019-09-14 2019-09-29 2019-10-27 2019-12-26 works at DHM New Envelope and Forecasting on Building (B.5)-(2 Lots) PPCR/DHM/W/SH-30 / Modernization of the Pending Improvement of Met Station Request for Single Stage - One TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-08-25 2019-10-20 2019-12-19 at Katari, Sangha chowk, Quotations Envelope and Forecasting on Amlekhaganj etc.(B.1.2) PPCR/DHM/W/SH-31 / Modernization of the Pending Improvement of Air Quality Request for Single Stage - One TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-09-04 2019-10-30 2019-12-29 site with installation of Quotations Envelope and Forecasting on Transformer (B.1.2) Page 2 PPCR/DHM/W/SH-18 / Improvement of Hydrological Modernization of the Pending stations of Budigandakai at Request for Single Stage - One TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-03-20 2019-05-15 2019-08-13 Arughat, Madi at Sisaghat Quotations Envelope and Forecasting on and Chepe at Garambeshi (B.1.2) PPCR/DHM/W/SH-32 / Modernization of the Pending Improvement of Hydrological Request for Single Stage - One TF / 13557 Observation Infrastructure Post Limited 0.00 Implementati 2019-09-13 2019-11-08 2019-12-08 station of Tamor at Majhitar Quotations Envelope and Forecasting on (B.1.2) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPCR/DHM/G/ICB-25 / Technical Re-equipment of Hydrological Network and Institutional Strengthening, Special Equipment for Capacity Building and Open - Single Stage - One TF / 13557 Prior Request for Bids 1,938,600.54 Signed Hydrological Stations Implementation Support of International Envelope (Supply, Delivery, DHM Installation and Commissioning ) PPCR/DHM/G/ICB-23 / Institutional Strengthening, Surface Meteorological Capacity Building and Open - Single Stage - One Network (Supply, Delivery, TF / 13557 Prior Request for Bids 3,780,599.43 Signed Implementation Support of International Envelope Installation and DHM Commissioning Institutional Strengthening, PPCR/DHM/G/DC-33 / Capacity Building and Procurement of 4WD Double TF / 13557 Prior Direct Selection Direct 125,567.23 Signed Implementation Support of Cab Pickup (4 Pieces) DHM PPCR/DHM/G/ICB-46 / Establishment of Modernization of the Under Open - Single Stage - One Meteorological Instrument TF / 13665 Observation Infrastructure Post Request for Bids 159,653.00 Implementati 2017-08-10 2017-08-15 2017-09-29 2017-10-29 2017-12-03 2018-10-02 International Envelope Calibration Laboratory and Forecasting on (B.1.9) PPCR/DHM/G/ICB-29 / Delivery and installation of Modernization of the Weather Radar for detection Single Stage - One TF / 13557 Observation Infrastructure Prior Request for Bids Open - National 1,560,349.39 Signed 2017-06-21 2017-06-26 2017-08-07 2017-09-06 2017-10-11 2018-10-11 of heavy precipitation and Envelope and Forecasting other meteorological phenomenon (B.1.4) PPCR/DHM/G/ICB-45 / Establishment of Hydro- meteorological work stations Enhancement of the Service Open - Single Stage - One Under TF / 13665 Prior Request for Bids 1,031,728.00 2017-08-10 2017-08-15 2017-09-26 2017-10-26 2017-11-30 2018-11-29 and automated production Delivery System of DHM International Envelope Review system (C.1.1, C.2.2, C.3, C.4.1, C.4.3 ) PPCR/DHM/G/ICB-28 / Modernization of the Highpower Computers for Open - Single Stage - One TF / 13665 Observation Infrastructure Post Request for Bids 327,327.00 Signed 2017-07-19 2017-07-24 2017-09-04 2017-10-04 2017-11-08 2018-10-21 Neumerical Weather International Envelope and Forecasting Prediction(B.3.1) PPCR/DHM/G/NCB-17 / Modernization of the Single Stage - One Remote sensing and GIS TF / 13557 Observation Infrastructure Post Request for Bids Open - National 225,115.27 Signed 2017-11-18 2017-11-23 2018-01-04 2018-02-03 2018-03-10 2018-09-06 Envelope Laboratory(B.2.3) and Forecasting Page 3 PPCR/DHM/G/ICB-34 / Bank Operating Discharge Modernization of the Measurement System at four Single Stage - One TF / 13557 Observation Infrastructure Post Request for Bids Open - National 0.00 Canceled 2017-08-01 2017-08-06 2017-09-17 2017-10-17 2017-11-21 2018-11-16 reivrs (Koshi, Narayani, Envelope and Forecasting West Rapti and Karnali) (B.1.1) PPCR/DHM/G/ICB-43 / Pilot Modernization of the operation of water quality Open - Single Stage - One TF / 13557 Observation Infrastructure Post Request for Bids 0.00 Canceled 2017-12-30 2018-01-04 2018-02-18 2018-03-20 2018-04-24 2018-11-30 and sediment monitoring International Envelope and Forecasting Stations (B.4.1) PPCR/DHM/G/NCB-30 / Communication Equipment Modernization of the Single Stage - One for ICT Infrastructure and TF / 13557 Observation Infrastructure Post Request for Bids Open - National 173,372.85 Signed 2017-12-28 2018-01-02 2018-02-13 2018-03-15 2018-04-19 2018-10-16 Envelope Management System(DHM and Forecasting Networks and Offices) (B.2.1) PPCR/DHM/G/ICB-24 / Modernization of the Open - Single Stage - One lighting detection network TF / 13557 Observation Infrastructure Post Request for Bids 344,277.00 Completed 2017-11-18 2017-11-23 2018-01-04 2018-02-03 2018-03-10 2018-09-06 International Envelope (lightning detectors) (B.1.7) and Forecasting PPCR/DHM/G/SH-39 / Procurement of Modernization of the Request for Single Stage - One Scooter/motorbikes (4 pieces) TF / 13665 Observation Infrastructure Post Limited 7,167.27 Signed 2018-05-19 2018-07-07 2018-08-06 Quotations Envelope to support PMU Operation and Forecasting (B.1.10) PPCR/DHM/G/SH-51 / Institutional Strengthening, Procurement of Heavy duty Capacity Building and Request for Single Stage - One multiple printer (including TF / 13665 Post Limited 0.00 Canceled 2018-05-23 2018-07-18 2018-08-17 Implementation Support of Quotations Envelope software and accessories) (1 DHM pieces) (A.3.2) Institutional Strengthening, PPCR/DHM/G/SH-52 / Pending Capacity Building and Procurement of Furniture TF / 13665 Post Direct Selection Direct 0.00 Implementati 2018-11-15 2018-11-20 2018-12-25 2019-01-24 Implementation Support of and Fixture (A.3.2) on DHM Institutional Strengthening, PPCR/DHM/G/SH-53 / Capacity Building and Request for Single Stage - One Procurement of Monitors for TF / 13665 Post Limited 0.00 Canceled 2018-04-25 2018-06-13 2018-07-13 Implementation Support of Quotations Envelope Desktop Mounting (A.3.2) DHM PPCR/DHM/G/SH-50 / Institutional Strengthening, Procurement of Color printer- Capacity Building and Request for Single Stage - One 1 (including software, other TF / 13665 Post Open - National 0.00 Canceled 2018-02-20 2018-04-17 2018-06-16 Implementation Support of Quotations Envelope equipment and machines etc)- DHM (A.3.2) PPCR/DHM/G/ICB-47 / Modernization of the Establishment of Weather Open - Single Stage - One TF / 13665 Observation Infrastructure Post Request for Bids 314,649.42 Signed 2018-09-10 2018-09-15 2018-10-30 2018-11-29 2019-01-03 2019-10-30 Broadcasting TV Studio International Envelope and Forecasting (C.1.2) PPCR/DHM/G/SH-49 / Institutional Strengthening, Procurement of laptop-8 Pending Capacity Building and Request for Single Stage - One (including software, other TF / 13665 Post Limited 0.00 Implementati 2019-03-05 2019-04-30 2019-08-28 Implementation Support of Quotations Envelope office equipment and on DHM machines)-(A.3.2) PPCR/DHM/G/ICB-48 / Modernization of the Open - Single Stage - One Establishment of Tracer TF / 13665 Observation Infrastructure Post Request for Bids 0.00 Canceled 2018-11-05 2018-11-10 2018-12-25 2019-01-24 2019-02-28 2019-10-26 International Envelope Laboratory (B.1.3) and Forecasting Page 4 PPCR/DHM/G/SH-44 / Procurement of Desktop Modernization of the Pending Request for Single Stage - One Computer for 28 Synoptic TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-07-05 2019-08-30 2019-12-28 Quotations Envelope and Aerosynoptic Stations (B and Forecasting on 1.7) PPCR/DHM/G/ICB-36 / Modernization of the Snow,Glacier and Weather Open - Single Stage - One TF / 13557 Observation Infrastructure Prior Request for Bids 0.00 Canceled 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Monitoring (Equipment and International Envelope and Forecasting pilot survey) (B.1.8) PPCR/DHM/G/ICB-42 / Pilot Modernization of the Open - Single Stage - One operation of air quality TF / 13665 Observation Infrastructure Post Request for Bids 0.00 Canceled 2017-12-31 2018-01-05 2018-02-19 2018-03-21 2018-04-25 2018-10-22 International Envelope monitoring Stations (B.4.1) and Forecasting PPCR/DHM/G/ICB-42-2 / Modernization of the Under Pilot operation of Air Open - Single Stage - One TF / 13665 Observation Infrastructure Post Request for Bids 0.00 Implementati 2019-02-28 2019-03-05 2019-04-19 2019-05-19 2019-06-23 2019-12-20 Quality Monitoring Stations International Envelope and Forecasting on (B.4.1) Institutional Strengthening, PPCR/DHM/G/NCB-56 / Under Capacity Building and Single Stage - One Furniture and Fixture for TF / 13665 Post Request for Bids Open - National 0.00 Implementati 2019-04-25 2019-04-30 2019-06-11 2019-07-11 2019-08-15 2019-11-13 Implementation Support of Envelope DHM new Building (B.5.1) on DHM PPCR/DHM/G/NCB-53 / Modernization of the Under Procurement of Six meter Single Stage - One TF / 13557 Observation Infrastructure Post Request for Bids Open - National 40,635.42 Implementati 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2019-12-03 Mast for AWS installed at Envelope and Forecasting on Airports (B.1.7) PPCR/DHM/G/DC-60 / Modernization of the Pending Procurement of Digital TF / 13557 Observation Infrastructure Post Direct Selection Direct 0.00 Implementati 2019-04-30 2019-05-05 2019-06-09 2019-12-06 Forecast Data from and Forecasting on ECMWF(B.3.1) PPCR/DHM/G/DIR-57 / Modernization of the Procurement of 4WD Double TF / 13665 Observation Infrastructure Post Direct Selection Direct 0.00 Canceled 2019-08-30 2019-09-04 2019-10-09 2019-12-28 Cab Pick-up (3Nos.) for and Forecasting Field Supervision PPCR/DHM/G/NCB-58 / Air Modernization of the Pending Single Stage - One Condition (AC) at DHM New TF / 13665 Observation Infrastructure Post Request for Bids Open - National 0.00 Implementati 2019-08-11 2019-08-16 2019-09-16 2019-10-01 2019-10-29 2019-12-28 Envelope Building (A.3.2) and Forecasting on Institutional Strengthening, PPCR/DHM/G/NCB-62 / Pending Capacity Building and Single Stage - One UPS for New Building at TF / 13665 Post Request for Bids Open - National 0.00 Implementati 2019-08-11 2019-08-14 2019-09-14 2019-09-29 2019-10-27 2019-12-26 Implementation Support of Envelope Babarmahal (A.3.2) on DHM PPCR/DHM/G/NCB-63 / Institutional Strengthening, Pending Audio Video, Security and Capacity Building and Single Stage - One TF / 13665 Post Request for Bids Open - National 0.00 Implementati 2019-08-11 2019-08-14 2019-09-14 2019-09-29 2019-10-27 2019-12-26 Multimedia System at new Implementation Support of Envelope on DHM Building (A.3.2) DHM PPCR/DHM/G/NCB-64 / Modernization of the Pending Single Stage - One Solar System at RADAR TF / 13557 Observation Infrastructure Post Request for Bids Open - National 0.00 Implementati 2019-08-15 2019-08-18 2019-09-18 2019-09-19 2019-10-17 2019-12-26 Envelope Station (B.1.4) and Forecasting on PPCR/DHM/G/NCB-65 / Modernization of the Pending Single Stage - One Solar System at new DHM TF / 13557 Observation Infrastructure Post Request for Bids Open - National 0.00 Implementati 2019-08-11 2019-08-14 2019-09-14 2019-09-29 2019-10-27 2019-12-26 Envelope Building (60 KVA)-(B.5) and Forecasting on PPCR/DHM/G/NCB-67 / Modernization of the Pending Single Stage - One Furniture for DHM Head TF / 13557 Observation Infrastructure Post Request for Bids Open - National 0.00 Implementati 2019-08-11 2019-08-14 2019-09-14 2019-09-29 2019-10-27 2019-12-26 Envelope Office (B.5) and Forecasting on Page 5 PPCR/DHM/G/SH-75 / Institutional Strengthening, Pending Procurement of Laptops (15 Capacity Building and Request for Single Stage - One TF / 13665 Post Limited 0.00 Implementati 2019-08-20 2019-10-15 2019-12-14 Nos.) with its Implementation Support of Quotations Envelope on accessories(A.3.2) DHM PPCR/DHM/G/SH-74 / Modernization of the Pending Request for Single Stage - One Procurement of Deionized TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-08-20 2019-10-15 2019-12-14 Quotations Envelope Water Equipment (B.1.11) and Forecasting on PPCR/DHM/G/SH-73 / Baloon Filling Unit and Modernization of the Pending Request for Single Stage - One spare part of Hydrogen TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-09-05 2019-10-31 2019-12-15 Quotations Envelope generator for and Forecasting on Radiosonde.(B.1.11) PPCR/DHM/G/SH-72 / Modernization of the Pending Request for Single Stage - One Specialized AWS for Radio TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-08-20 2019-10-15 2019-12-14 Quotations Envelope Sonde Center B.1.11) and Forecasting on PPCR/DHM/G/SH-71 / Modernization of the Pending Request for Single Stage - One Transformer for Radar TF / 13665 Observation Infrastructure Post Limited 0.00 Implementati 2019-08-25 2019-10-20 2019-12-19 Quotations Envelope Station (B.1.4) and Forecasting on Institutional Strengthening, PPCR/DHM/G/SH-70 / AWS Pending Capacity Building and Request for Single Stage - One Display system at Airports TF / 13665 Post Limited 0.00 Implementati 2019-08-17 2019-10-05 2019-12-24 Implementation Support of Quotations Envelope 20 Units (A.3.2) on DHM PPCR/DHM/G/SH-69 / Pending Enhancement of the Service Request for Single Stage - One Sound Proofing of Weather TF / 13665 Post Limited 0.00 Implementati 2019-08-20 2019-10-15 2019-12-14 Delivery System of DHM Quotations Envelope TV Studio(C.1.2) on Institutional Strengthening, PPCR/DHM/G/SH-68 / Pending Capacity Building and Request for Single Stage - One CCTV Camera System at TF / 13665 Post Limited 0.00 Implementati 2019-09-04 2019-10-30 2019-12-29 Implementation Support of Quotations Envelope DHM New Building (A.3.2) on DHM PPCR/DHM/G/NCB-66 / Upgrading of OHM Offices, Hydro-logical & Modernization of the Pending Single Stage - One Meteorological Offices TF / 13557 Observation Infrastructure Post Request for Bids Open - National 0.00 Implementati 2019-08-11 2019-08-14 2019-09-14 2019-09-29 2019-10-27 2019-12-26 Envelope (Desktop Computers, and Forecasting on Printers, Scanners & Photocopiers etc)-50 nos.(B.2) PPCR/DHM/G/NCB-57 / Modernization of the Pending Procurement of 4WD Double Single Stage - One TF / 13557 Observation Infrastructure Post Request for Bids Open - National 0.00 Implementati 2019-09-10 2019-09-15 2019-10-20 2019-10-30 2019-11-27 2019-12-27 Cab Pick-up (3Nos.) for Envelope and Forecasting on Field Supervision NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPCR/DHM/NS/SH-5 / Institutional Strengthening, Under Procurement Management Capacity Building and Request for Single Stage - One TF / 13665 Post Limited 0.00 Implementati 2018-11-06 2019-01-01 2019-01-31 Training to BRCH/DHM Implementation Support of Quotations Envelope on Personnel (A 2.1) DHM Institutional Strengthening, PPCR/DHM/NS-6 / Driver Capacity Building and to run the project vehicle at TF / 13665 Post Direct Selection Direct 0.00 Canceled 2017-07-16 2017-07-21 2017-08-25 2018-08-24 Implementation Support of central and field level(A.3.2) DHM Page 6 Institutional Strengthening, PPCR/DHM/NS-7 / Driver Capacity Building and to run the project vehicle at TF / 13665 Post Direct Selection Direct 0.00 Canceled 2017-07-16 2017-07-21 2017-08-25 2018-08-24 Implementation Support of central and field level(A.3.2) DHM PPCR/DHM/NS/SH-2 / Development of Audio Visual Enhancement of the Service Request for Single Stage - One TF / 13665 Post Limited 0.00 Canceled 2019-01-21 2019-03-18 2019-07-16 Documentary of Project Delivery System of DHM Quotations Envelope Activities (C 4.5) PPCR/DHM/NS/IND-10-11 / Institutional Strengthening, Pending Security Guard-2(two) for Capacity Building and TF / 13665 Post Direct Selection Direct 0.00 Implementati 2019-02-28 2019-03-05 2019-04-09 2019-10-06 Upper Air Radio Sonde site Implementation Support of on at Kirtipur, Kathmandu DHM PPCR/DHM/NS/IND-9-10 / Institutional Strengthening, Pending Security Guard-2(two) for Capacity Building and TF / 13665 Post Direct Selection Direct 0.00 Implementati 2019-02-28 2019-03-05 2019-04-09 2019-10-06 RADAR Centre site at Implementation Support of on Surkhet (A.3.2) DHM PPCR/DHM/NS/SH-8 / Institutional Strengthening, Pending Financial Management Capacity Building and Request for Single Stage - One TF / 13665 Post Limited 0.00 Implementati 2019-03-15 2019-05-10 2019-06-09 Training to BRCH/DHM Implementation Support of Quotations Envelope on Personnel (A 2.1) DHM PPCR/DHM/NS/SH-2-2 / Pending Development of Audio Visual Enhancement of the Service Request for Single Stage - One TF / 13665 Post Limited 0.00 Implementati 2019-09-06 2019-11-01 2019-12-01 Documentary of Project Delivery System of DHM Quotations Envelope on Activities (C 4.5) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPCR/DHM/S/FBS-11 / GENERAL CONSULTANT - Institutional Strengthening, SYSTEM INTEGRATOR, Capacity Building and Fixed Budget Open - Consulting Service for TF / 13665 Prior 2,627,441.05 Signed Implementation Support of Selection International Detailed Design of the DHM DHM System, Procurement and Implementation Support PPCR/DHM/S/CQS-13 / Institutional Strengthening, Consultant Development of a legal and Capacity Building and Open - TF / 13557 Prior Qualification 91,048.78 Signed regulatory framework for Implementation Support of International Selection DHM Operations DHM PPCR/DHM/S/CQS-54 / Consultancy service for Consultant Development and Enhancement of the Service TF / 13665 Post Qualification Open - National 0.00 Canceled 2017-10-10 2017-10-31 2017-12-14 2018-01-13 2018-02-17 2018-08-16 Operationalization of Delivery System of DHM Selection Forecast Verification System (C 1.3) PPCR/DHM/S/CQS-56 / Consultancy service for Consultant Enhancement of the Service Development of an TF / 13665 Post Qualification Open - National 32,405.36 Signed 2017-09-01 2017-09-22 2017-11-05 2017-12-05 2018-01-09 2018-07-08 Delivery System of DHM Integrated Web Portal for Selection DHM (C.1.2) PPCR/DHM/S/CQS-40 / Development of Cost Institutional Strengthening, Consultant Recovery System/Business Capacity Building and TF / 13665 Post Qualification Open - National 0.00 Canceled 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-04-27 Model of DHM(specially for Implementation Support of Selection Aeronautical Forecasting DHM Services) (A.1.2) Page 7 PPCR/DHM/S/CQS-26 / Consultancy service for Consultant Enhancement of the Service Development of digital TF / 13665 Post Qualification Open - National 48,200.68 Signed 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-04-27 Delivery System of DHM elevation map for Terai Selection Region (C.2.3) PPCR/DHM/S/CQS-41 / ICT Modernization of the Consultant Infrastructure and Data TF / 13665 Observation Infrastructure Post Qualification Open - National 106,426.74 Signed 2017-07-06 2017-07-09 2017-08-07 2017-08-22 2017-10-03 2018-08-03 Management System for and Forecasting Selection DHM (B 2.2) PPCR/DHM/S/CQS-42 / Implementing and commissioning of High Modernization of the Consultant Resolution Local Area TF / 13665 Observation Infrastructure Post Qualification Open - National 146,230.00 Signed 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-08-28 Numerical Weather and Forecasting Selection Prediction System at DHM (B 2.2) PPCR/DHM/QCBS-34 / Consultancy service for "Establishment of " END-To- END" Flood Early Warning Enhancement of the Service Quality And Cost- Open - System in Koshi & West TF / 13665 Prior 792,788.03 Signed 2017-10-23 2017-11-13 2017-12-27 2018-01-24 2018-02-23 2018-03-30 2018-05-04 2018-11-20 Delivery System of DHM Based Selection International Rapti River Basins to Support & Strengthen Disaster Risk Management" (C2) PPCR/DHM/S/CQS-8 / Institutional Strengthening, Consultancy firm for the Consultant Capacity Building and Under detailed design and TF / 13665 Prior Qualification Open - National 0.00 2017-11-18 2017-12-09 2018-01-22 2018-02-21 2018-03-28 2018-09-24 Implementation Support of Implementation supervision of DHM office Selection DHM building construction (A.3.4) PPCR/DHM/S/CQS-52 / Consultant Development of mobile apps Enhancement of the Service TF / 13665 Post Qualification Open - National 0.00 Canceled 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-02-26 for hydro-meteorological Delivery System of DHM Selection services (C.4.5) PPCR/DHM/S/QCBS-37 / Support to development of Enhancement of the Service Quality And Cost- Open - National Framework for TF / 13557 Post 0.00 Canceled 2017-06-21 2017-07-12 2017-08-25 2017-09-22 2017-10-22 2017-11-26 2017-12-31 2018-09-30 Delivery System of DHM Based Selection International climate services and support to sectoral work groups(C4.2) PPCR/DHM/S/CQS-54-2 / Consultancy service for Consultant Development and Enhancement of the Service Under TF / 13665 Post Qualification Open - National 0.00 2018-10-15 2018-11-05 2018-12-19 2019-01-18 2019-02-22 2019-08-21 Operationalization of Delivery System of DHM Implementation Selection Forecast Verification System (C 1.3) PPCR/DHM/CQS-37 / Support to Development of Consultant National Framework for Enhancement of the Service Open - Under TF / 13665 Post Qualification 0.00 2019-01-31 2019-02-21 2019-04-06 2019-05-06 2019-06-10 2019-11-07 Climate Services and Delivery System of DHM International Implementation Selection Support to Sectoral Workgroup (C 4.2) PPCR/DHM/S/CQS-55 / Institutional Strengthening, Consultant Consultancy service for End Capacity Building and Under TF / 13665 Post Qualification Open - National 83,778.91 2019-03-31 2019-04-21 2019-06-04 2019-07-04 2019-08-08 2019-11-06 Line User's Satisfaction Implementation Support of Implementation Selection Survey (A.3.2) DHM Institutional Strengthening, PPCR/DHM/S/CQS-60 / Consultant Capacity Building and Open - Pending Twinning operation support TF / 13665 Post Qualification 0.00 2019-03-31 2019-04-21 2019-06-04 2019-07-04 2019-08-08 2019-10-07 Implementation Support of International Implementation and capacity building (A.1.3) Selection DHM Page 8 PPCR/DHM/S/CQS-35 / Consultancy service for Consultant development of needs Enhancement of the Service TF / 13557 Post Qualification Open - National 0.00 Canceled 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-04-27 assessment and design of Delivery System of DHM Selection water quality and sediment monitoring networks(A.3.3) PPCR/DHM/S/CQS-92 / Consultancy Service to Consultant Conduct Training Course on Enhancement of the Service Under TF / 13665 Post Qualification Open - National 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-03 2019-09-07 2019-11-06 "Using Modern Weather Delivery System of DHM Implementation Selection Observation System For Nowcasting (A.2.1i) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Institutional Strengthening, PPCR/DHM/S/IND-3 / Individual Capacity Building and Individual Consultant for TF / 13665 Prior Consultant Open 29,292.97 Signed Implementation Support of Project Technical Coordinator Selection DHM Institutional Strengthening, PPCR/DHM/S/IND/SSS-12 / Capacity Building and Individual Consultant- Legal TF / 13665 Prior Direct Selection Direct 2,113.49 Signed Implementation Support of Expert DHM Institutional Strengthening, PPCR/DHM/S/IND-1.1 / Individual Capacity Building and Individual Procurement TF / 13557 Prior Consultant Open 91,058.93 Signed Implementation Support of Consultant Selection DHM Institutional Strengthening, PPCR/DHM/S/IND-3.1 / Individual Capacity Building and Individual Consultant for TF / 13557 Prior Consultant Open 89,617.73 Signed Implementation Support of Project Technical Coordinator Selection DHM Institutional Strengthening, PPCR/DHM/S/IND-44 / Individual Capacity Building and Individual consultant for the TF / 13665 Post Consultant Open 17,726.16 Signed 2017-06-20 2017-08-08 2017-08-29 2017-10-03 2018-09-28 Implementation Support of position of Engineer (A.3.2) Selection DHM PPCR/DHM/S/IND-62-64 / Individual consultant for the Institutional Strengthening, Individual position of Social Safeguard Capacity Building and TF / 13665 Post Consultant Limited 8,168.76 Signed 2017-08-31 2017-09-05 2017-09-26 2017-10-31 2018-04-29 Associate (A.3.2) (3 CV Implementation Support of Selection methods used for selection DHM due to urgency of work.) PPCR/DHM/S/IND- 61-62 / Individual consultant for the Institutional Strengthening, position of Environment Individual Capacity Building and Safeguard Associates (A.3.2) TF / 13665 Post Consultant Open 7,129.50 Signed 2017-08-20 2017-10-08 2017-10-29 2017-12-03 2018-06-01 Implementation Support of (3CV method used for Selection DHM selection due to urgency of work) Institutional Strengthening, PPCR/DHM/S/IND-45 / Individual Capacity Building and Individual consultant for the TF / 13665 Post Consultant Open 37,051.07 Signed 2017-11-18 2018-01-06 2018-01-27 2018-03-03 2018-08-30 Implementation Support of position of Engineer (A.3.2) Selection DHM PPCR/DHM/S/IND-50 / Modernization of the Individual Individual Consultant for the TF / 13665 Observation Infrastructure Post Consultant Open 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-11-14 position of ICT and Forecasting Selection Engineer/consultant (B.2.2) Page 9 PPCR/DHM/S/IND-57 / Institutional Strengthening, Individual Consultant to Individual Capacity Building and develop the SOP of DHM TF / 13665 Post Consultant Open 0.00 Canceled 2017-10-10 2017-11-28 2017-12-19 2018-01-23 2018-04-22 Implementation Support of (A.2.1) (3CV methods used Selection DHM for selection) PPCR/DHM/S/IND-55 / Institutional Strengthening, Individual Individual consultant for the Capacity Building and TF / 13557 Post Consultant Open 0.00 Canceled 2017-06-20 2017-08-08 2017-08-29 2017-10-03 2018-09-28 position of Research Implementation Support of Selection Associate (A.3.2) DHM PPCR/DHM/S/IND-58 / Institutional Strengthening, Individual Consultant for Capacity Building and TF / 13665 Post Direct Selection Direct 0.00 Canceled 2017-10-05 2017-10-15 2017-12-19 2018-02-19 Training Need Assessment Implementation Support of (TNA) of DHM (A.2.1) DHM PPCR/DHM/S/IND-43 / Institutional Strengthening, Individual Individual consultant for the Capacity Building and TF / 13665 Post Consultant Open 0.00 Canceled 2017-06-20 2017-08-08 2017-08-29 2017-10-03 2018-09-28 position of Senior Engineer Implementation Support of Selection (A.3.2) DHM PPCR/DHM/S/IND/SSS-77 / Institutional Strengthening, Individual Individual Consultant for the Capacity Building and TF / 13665 Post Consultant Direct 14,372.87 Signed 2018-04-01 2018-04-11 2018-05-02 2018-05-30 2018-11-26 position of Environment Implementation Support of Selection Safeguard Specialist (A.3.2) DHM PPCR/DHM/S/IND/SSS-78 / Institutional Strengthening, Individual Individual Consultant for the Capacity Building and TF / 13665 Post Consultant Direct 14,320.45 Completed 2018-04-01 2018-04-11 2018-05-02 2018-05-30 2018-11-26 position of Monitoring and Implementation Support of Selection Evaluation Specialist (A.3.2) DHM PPCR/DHM/S/IND/SSS-79 / Institutional Strengthening, Individual Individual Consultant for the Capacity Building and TF / 13665 Prior Consultant Direct 18,309.68 Completed 2018-04-01 2018-04-11 2018-05-02 2018-05-30 2018-11-26 position of Procurement Implementation Support of Selection Consultant (A.3.2) DHM PPCR/DHM/S/IND/SSS-80 / Institutional Strengthening, Individual Individual Consultant for the Capacity Building and TF / 13665 Post Consultant Direct 18,593.65 Completed 2018-05-04 2018-05-14 2018-05-21 2018-06-04 2018-12-01 position of Project Technical Implementation Support of Selection Coordinator (A.3.2) DHM PPCR/DHM/S/IND-65 / Individual Consultant to Design and Establish a Institutional Strengthening, Tracer Laboratory for Individual Capacity Building and Under Measurement of River Flow TF / 13665 Post Consultant Limited 0.00 2018-05-13 2018-05-18 2018-06-08 2018-07-13 2018-11-30 Implementation Support of Implementation by Dilution Gauging Method Selection DHM (3CV method used for selection due to urgency of the work) (B.1.3) PPCR/DHM/S/IND-76 / Individual Consultant as a Institutional Strengthening, Project Secretary to handle Individual Capacity Building and the secretariat work TF / 13665 Post Consultant Limited 2,580.16 Completed 2018-02-28 2018-03-05 2018-03-26 2018-04-30 2018-11-26 Implementation Support of (A.3.2)(3CV method used for Selection DHM selection due to urgency of the work) PPCR/DHM/S/IND-49 / Institutional Strengthening, Individual Individual consultant for the Capacity Building and TF / 13665 Post Consultant Open 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2017-12-04 position of Lead Trainer on Implementation Support of Selection Observer (A.2.1i) DHM PPCR/DHM/S/IND-49-2 / Institutional Strengthening, Individual Individual consultant for the Capacity Building and Under TF / 13665 Post Consultant Open 0.00 2019-01-15 2019-03-05 2019-03-26 2019-04-30 2019-05-20 position of Lead Trainer on Implementation Support of Implementation Selection Observer (A.2.1i) DHM Page 10 PPCR/DHM/S/IND-48 / Institutional Strengthening, Individual Individual consultant for the Capacity Building and TF / 13665 Post Consultant Open 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2017-12-04 position of Lead Trainer on Implementation Support of Selection forecasting (A.2.1i) DHM PPCR/DHM/S/IND-48-2 / Institutional Strengthening, Individual Individual consultant for the Capacity Building and Under TF / 13665 Post Consultant Open 0.00 2019-01-15 2019-03-05 2019-03-26 2019-04-30 2019-05-20 position of Lead Trainer on Implementation Support of Implementation Selection forecasting (A.2.1i) DHM PPCR/DHM/S/IND-69 / Individual Consultant as a Institutional Strengthening, Individual Trainer for Use of Satellites Capacity Building and TF / 13665 Post Consultant Limited 0.00 Canceled 2018-05-13 2018-05-18 2018-06-08 2018-07-13 2018-08-12 in Weather Service Training Implementation Support of Selection (A 2.1) (3CVs method used DHM due to urgency of the work) PPCR/DHM/S/IND-68 / Individual Consultant as a Institutional Strengthening, Individual Trainer for Customer Liaison Capacity Building and TF / 13665 Post Consultant Limited 0.00 Canceled 2018-06-05 2018-06-10 2018-07-01 2018-08-05 2018-09-04 Training (A 201) (3CVs Implementation Support of Selection method used due to urgency DHM of the work) PPCR/DHM/S/IND-67 / Individual Consultant as a Institutional Strengthening, Individual Trainer for Project Capacity Building and TF / 13665 Post Consultant Limited 0.00 Canceled 2018-05-20 2018-05-25 2018-06-15 2018-07-20 2018-08-19 Management Training (A Implementation Support of Selection 2.1) (3CVs method used DHM due to urgency of the work) PPCR/DHM/S/IND-74 / Individual Consultant for Institutional Strengthening, Individual Training on Communication Capacity Building and TF / 13665 Post Consultant Limited 0.00 Canceled 2018-06-30 2018-07-05 2018-07-26 2018-08-30 2018-10-14 for DHM Staff (A.2i) (3CVs Implementation Support of Selection method used due to urgency DHM of the work) PPCR/DHM/S/IND-75 / Individual Consultant for Institutional Strengthening, Individual Training on Leadership for Capacity Building and TF / 13665 Post Consultant Limited 0.00 Canceled 2018-05-30 2018-06-04 2018-06-25 2018-07-30 2018-09-13 DHM Staff (A.2i) (3CVs Implementation Support of Selection method used due to uegency DHM of the work) PPCR/DHM/S/IND/SSS-30 / Individual Structural Engineer to provide valuable Institutional Strengthening, input for DHM Office Individual Capacity Building and Building-1st Phase Civil TF / 13665 Post Consultant Direct 6,444.21 Signed 2018-09-01 2018-09-11 2018-10-02 2018-10-30 2019-04-28 Implementation Support of Works. (A.3.2) Selection DHM Consultant should provide 60 days input spread-over 16 months during Civil Works. PPCR/DHM/S/IND-81 / Institutional Strengthening, Individual Individual Consultant for the Capacity Building and TF / 13665 Post Consultant Open 37,180.73 Signed 2018-10-10 2018-11-28 2018-12-19 2019-01-23 2019-12-30 position of Project Technical Implementation Support of Selection Coordinator (A 3.2) DHM PPCR/DHM/S/IND-82 / Institutional Strengthening, Individual Individual Consultant for the Capacity Building and TF / 13665 Prior Consultant Open 31,436.80 Signed 2018-10-10 2018-11-28 2018-12-19 2019-01-23 2019-12-30 position of Procurement Implementation Support of Selection Consultant (A 3.2) DHM Page 11 PPCR/DHM/S/IND-84 / Institutional Strengthening, Individual Individual Consultant for the Capacity Building and TF / 13665 Post Consultant Open 25,143.09 Signed 2018-10-10 2018-11-28 2018-12-19 2019-01-23 2019-12-30 position of Monitoring and Implementation Support of Selection Evaluation Specialist (A 3.2) DHM PPCR/DHM/S/IND-85 / Institutional Strengthening, Individual Individual Consultant for the Capacity Building and TF / 13665 Post Consultant Open 24,076.88 Signed 2018-10-10 2018-11-28 2018-12-19 2019-01-23 2019-12-30 position of Environment Implementation Support of Selection Safeguard Specialist (A 3.2) DHM PPCR/DHM/S/IND-46 / Institutional Strengthening, Individual Consultant for the Individual Capacity Building and position of Social and TF / 13665 Post Consultant Open 37,720.20 Signed 2018-09-30 2018-11-18 2018-12-09 2019-01-13 2019-12-30 Implementation Support of Communication Specialist (A Selection DHM 3.2) PPCR/DHM/S/IND-83 / Institutional Strengthening, Individual Consultant for the Individual Capacity Building and position of Social and TF / 13665 Post Consultant Open 20,758.89 Signed 2018-10-10 2018-11-28 2018-12-19 2019-01-23 2019-12-30 Implementation Support of Communication Specialist (A Selection DHM 3.2) PPCR/DHM/S/IND-86 / Institutional Strengthening, Individual Consultant for the Individual Capacity Building and position of Financial TF / 13665 Post Consultant Open 23,524.78 Signed 2018-10-10 2018-11-28 2018-12-19 2019-01-23 2019-12-30 Implementation Support of Management Specialist (A Selection DHM 3.2) Institutional Strengthening, PPCR/DHM/S/IND-87 / Individual Capacity Building and Individual Consultant for the TF / 13665 Post Consultant Open 0.00 Canceled 2018-10-10 2018-11-28 2018-12-19 2019-01-23 2019-12-30 Implementation Support of position of Engineer (A 3.2) Selection DHM PPCR/DHM/S/IND-88 / Institutional Strengthening, Individual Individual Consultant for the Capacity Building and TF / 13665 Post Consultant Open 5,539.30 Signed 2018-09-25 2018-11-13 2018-12-04 2019-01-08 2019-12-30 position of Project Secretary Implementation Support of Selection (A 3.2) DHM PPCR/DHM/S/IND-71 / Individual Consultant as a Institutional Strengthening, Trainer for Use of Lightning Individual Capacity Building and Detection Data in Weather TF / 13665 Post Consultant Limited 0.00 Canceled 2019-03-15 2019-03-20 2019-04-10 2019-05-15 2019-06-14 Implementation Support of Service Training (A 2.1) Selection DHM (3CVs method used due to urgency of the work) PPCR/DHM/S/IND-70 / Individual Consultant as a Institutional Strengthening, Trainer for Use of Upper-air Individual Capacity Building and Sounding in Weather Service TF / 13665 Post Consultant Limited 0.00 Canceled 2019-03-15 2019-03-20 2019-04-10 2019-05-15 2019-06-14 Implementation Support of Training (A 2.1) (3CVs Selection DHM method used due to urgency of the work) PPCR/DHM/S/IND-73 / Individual Consultant for Institutional Strengthening, Individual Training on Agro-meteorology Capacity Building and Under TF / 13665 Post Consultant Limited 0.00 2019-03-15 2019-03-20 2019-04-10 2019-05-15 2019-06-29 for DHM staffs (A.2i) (3CVs Implementation Support of Implementation Selection method used due to uegency DHM of the work) PPCR/DHM/S/IND-66 / Individual Consultant as a Institutional Strengthening, Trainer for Quality Individual Capacity Building and Under Management System TF / 13665 Post Consultant Limited 0.00 2019-03-15 2019-03-20 2019-04-10 2019-05-15 2019-07-14 Implementation Support of Implementation Training (A 2.1) (3CVs Selection DHM method used due to urgency of the work) Page 12 PPCR/DHM/S/IND-51 / Individual Development of Audio Visual Enhancement of the Service Pending TF / 13665 Post Consultant Open 0.00 2019-06-10 2019-07-29 2019-08-19 2019-09-23 2019-10-23 Documentary of Project Delivery System of DHM Implementation Selection Activities (C.4.5) PPCR/DHM/S/IND-89-90 / Institutional Strengthening, Individual consultant-2(two) Individual Capacity Building and Pending for the position of Electrical TF / 13665 Post Consultant Limited 0.00 2019-02-28 2019-03-05 2019-03-26 2019-04-30 2019-10-27 Implementation Support of Implementation and Communication Selection DHM Technicians (A.3.2) PPCR/DHM/S/IND-91 / Institutional Strengthening, Individual Consultant as a Individual Capacity Building and Trainer to conduct training TF / 13665 Post Consultant Limited 0.00 Canceled 2019-02-15 2019-02-20 2019-03-13 2019-04-17 2019-05-07 Implementation Support of on Air Quality Mgmt. Selection DHM Training (A.2.1) PPCR/DHM/S/IND-72 / Individual Consultant for Institutional Strengthening, Training for Weather Individual Capacity Building and Forecaster on Uses of TF / 13665 Post Consultant Limited 0.00 Canceled 2019-01-10 2019-01-15 2019-02-05 2019-03-12 2019-04-26 Implementation Support of Weather RADAR (A.2.1.i) Selection DHM (3CVs method used due to urgency of the work) PPCR/DHM/S/IND-28-1 / Institutional Strengthening, Individual Consultant for the Individual Capacity Building and position of Financial TF / 13665 Post Consultant Open 0.00 Canceled 2018-09-30 2018-11-18 2018-12-09 2019-01-13 2019-12-30 Implementation Support of Management Specialist (A Selection DHM 3.2) for 36 months. PPCR/DHM/S/DS-93 / Strategic Planning and Institutional Strengthening, Organization Management, Capacity Building and Pending TF / 13665 Post Direct Selection Direct 0.00 2019-06-16 2019-06-26 2019-08-30 2019-09-22 Leadership, Project Implementation Support of Implementation Management, Communication DHM and Customer Liaison PPCR/DHM/S/IND/DIR-96 / Institutional Strengthening, Individual Consultant as a Capacity Building and Pending TF / 13665 Post Direct Selection Direct 0.00 2019-08-20 2019-08-28 2019-09-14 2019-12-23 Procurement Associate Implementation Support of Implementation (A.3.2) DHM Page 13