Procurement Plan – Project Preparation Advance P4760 3rd South West Indian Ocean Project I. General 2. Bank’s approval Date of the procurement Plan: 26th January 2017 3. Date of General Procurement Notice: Pending 4. Period covered by this procurement plan: 28th April 2016 to 31st December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: N/A 4. Reference to (if any) Project Operational/Procurement Manual: Under preparation 5. Any Other Special Procurement Arrangements: N/A 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of the ICB (Works) July 9, 2010 Summary of the ICB (Goods) Summary of the NCB (Works) Summary of the NCB (Goods) Summary of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_100,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N.A 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / Post) Summary of 245,000 2 Post number of contracts that will be let under QCBS Summary of 1,015,000 17 Prior & CQS, IC, number of Post SSS contracts that will be let July 9, 2010 under other methods July 9, 2010 PROCUREMENT Africa : Third South West Indian Ocean Fisheries Governance and Shared Growth Project (SWIOFish3) PLAN General Information Country: Africa Bank’s Approval Date of the Original Procurement Plan: 2017-04-04 2020-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155642 GPN Date: Project Name: Third South West Indian Ocean Fisheries Governance and Shared Growth Project (SWIOFish3) Loan / Credit No: IBRD / P4760, IBRD / 87790 Executing Agency(ies): Ministry of Finance, Trade and the Blue Economy WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Improved Pending GEF23-SWIOFISH3 / FEIU Request for Single Stage - One IBRD / 87790 governance of priority Post Open - National 12,000.00 0.00 Implementati 2020-07-05 2020-08-30 2021-02-26 purchase of data servers Quotations Envelope fisheries on GEF16/G/2020-SWF3 / Component 1: Expansion of Under Single Stage - One THEMIS AIS, Radar IBRD / 87790 sustainable-use marine Post Request for Bids Limited 160,000.00 0.00 Implementati 2020-03-31 2020-04-24 2020-04-05 2020-05-17 2020-06-16 2020-07-21 2021-01-17 Envelope installation and maintenance protected areas on IBRD28/G/2020-SWF3 / Component 3: Sustainable Pending Request for Open - Single Stage - One Equipment for SFA post IBRD / 87790 development of the blue Post 25,000.00 0.00 Implementati 2020-08-19 2020-10-14 2021-04-12 Quotations International Envelope harvest lab economy on GEF43/G/2020-SWF3 / Component 2: Improved Pending Request for Single Stage - One Purchasing Surveillance IBRD / 87790 governance of priority Post Open - National 55,000.00 0.00 Implementati 2020-11-21 2021-01-16 2021-07-15 Quotations Envelope tender vessel. fisheries on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GEF35/NCS/2020-SWF3 / Component 2: Improved Pending Provision of satellite data Open - Single Stage - One IBRD / 87790 governance of priority Post Request for Bids 231,000.00 0.00 Implementati 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2020-12-22 2023-12-22 (AIS, radar, imagery) to International Envelope fisheries on Seychelles Fishing Authority IBRD20/RFB/2020-SWF3 / Component 3: Sustainable Pending GEOTECH SURVEY FOR Single Stage - Two IBRD / 87790 development of the blue Post Request for Bids Open - National 200,000.00 0.00 Implementati 2020-06-01 2020-06-06 2020-07-18 2020-09-30 2020-11-04 2021-05-03 GRAND ANSE Envelope economy on AQUACULTURE HUB CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PA2-SWIOFISH3 / Evaluation of the Component 1: Expansion of Consultant Open - contribution of the extended IBRD / P4760 sustainable-use marine Post Qualification 75,000.00 0.00 Canceled 2018-08-20 2018-09-10 2018-08-21 2018-10-24 2018-11-23 2018-12-28 2019-06-26 International MPA network to the protected areas Selection economy PA3-SWIOFISH3 / Education and awareness Component 2: Improved Consultant Open - program on fisheries IBRD / P4760 governance of priority Post Qualification 50,000.00 0.00 Canceled 2017-05-15 2017-05-15 2018-01-23 2017-05-15 2017-05-15 2017-06-05 2017-12-02 International management plan fisheries Selection implementation IBRD4-SWIOFISH3 / Fisheries sector employment Component 3: Sustainable Consultant Open - survey & identify method for IBRD / 87790 development of the blue Post Qualification 75,000.00 0.00 Canceled 2019-04-15 2019-05-06 2019-06-04 2019-06-19 2019-07-19 2019-08-23 2020-02-19 International routine employment economy Selection monitoring GEF5-SWIOFISH3 / Component 1: Expansion of Consultant Under Drafting of a coral reef IBRD / 87790 sustainable-use marine Post Qualification Open - National 50,000.00 0.00 2019-05-15 2019-08-27 2019-06-05 2019-07-19 2019-11-11 2019-08-18 2019-09-22 2020-03-20 Implementation conservation policy and plan protected areas Selection GEF7-SWIOFISH3 / Perception survey of Component 1: Expansion of Consultant management performance for Under IBRD / 87790 sustainable-use marine Post Qualification Open - National 25,000.00 0.00 2019-04-30 2019-11-29 2019-05-21 2019-07-04 2019-08-03 2019-09-07 2020-03-05 sustainable use area and Implementation protected areas Selection fisheries plans (information for M&E indicator) IBRD17-SWIOFISH3 / Component 3: Sustainable Consultant Open - Under Development of Seychelles IBRD / 87790 development of the blue Post Qualification 80,000.00 0.00 2019-06-30 2020-01-21 2019-07-21 2019-09-03 2019-10-03 2019-11-07 2020-05-05 International Implementation seafood brand economy Selection IBRD1-SWIOFISH3 / Capacity building in project Component 3: Sustainable Consultant Under planning and business IBRD / 87790 development of the blue Post Qualification Open - National 100,000.00 0.00 2019-03-29 2019-03-25 2019-04-19 2019-06-02 2019-07-02 2019-08-06 2020-02-02 Implementation development for small-scale economy Selection fishers IBRD23-SWIOFISH3 / Fisheries sector employment Component 3: Sustainable Quality And Cost- Open - Pending survey and identification of IBRD / 87790 development of the blue Post 75,000.00 0.00 2019-08-22 2019-08-22 2019-08-22 2019-09-13 2019-10-13 2019-11-17 2019-12-22 2020-12-21 Based Selection International Implementation method for routine economy monitoring GEF26-SWIOFISH3A / Communication strategy and Component 2: Improved Consultant Open - Under plan for Mahe Plateau IBRD / 87790 governance of priority Post Qualification 35,000.00 0.00 2019-09-25 2019-11-29 2019-10-16 2019-11-29 2019-12-29 2020-02-02 2020-07-31 International Implementation fisheries management fisheries Selection measures IBRD24-SWIOFISH3 / Development of a Component 3: Sustainable Consultant communication strategy and Under IBRD / 87790 development of the blue Post Qualification Open - National 20,000.00 0.00 2019-10-11 2020-03-13 2019-11-01 2019-12-15 2020-01-14 2020-02-18 2020-08-16 online platform for the Implementation economy Selection Grievance Redress Mechanism IBRD26/CQS/2020-SWF3 / Component 3: Sustainable Consultant Under Communication support for IBRD / 87790 development of the blue Post Qualification Open - National 200,000.00 0.00 2020-01-15 2020-01-21 2020-02-05 2020-03-20 2020-04-19 2020-05-24 2020-11-20 Implementation Blue Finance economy Selection GEF21-SWIOFISH3 / Component 2: Improved Feasibility study on Quality And Cost- Open - IBRD / 87790 governance of priority Post 80,000.00 0.00 Canceled 2019-07-15 2019-08-05 2019-09-18 2019-10-16 2019-11-15 2019-12-20 2020-01-24 2021-01-23 mechanisms for fleet Based Selection International fisheries capacity reduction Page 2 GEF32/CQS/2020-SWF3 / Biological, ecological and Component 1: Expansion of Consultant socioeconomic monitoring of Open - Pending IBRD / 87790 sustainable-use marine Post Qualification 150,000.00 0.00 2020-10-15 2020-11-05 2020-12-19 2021-01-18 2021-02-22 2021-08-21 sustainable-use areas: International Implementation protected areas Selection baseline surveys, indicators and protocols GEF36/CQS/2020-SWF3 / Research on ways to Component 1: Expansion of Consultant mitigate impacts of Open - Pending IBRD / 87790 sustainable-use marine Post Qualification 50,000.00 0.00 2020-07-15 2020-08-05 2020-09-18 2020-10-18 2020-11-22 2021-05-21 industrial fisheries on International Implementation protected areas Selection coastal marine habitats and fisheries GEF40/QCBS/2020-SWF3 / Component 2: Improved Communication and Quality And Cost- Pending IBRD / 87790 governance of priority Post Open - National 150,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-02 2020-11-01 2020-12-06 2021-01-10 2022-01-10 education/awareness activity Based Selection Implementation fisheries support for SFA GEF45/QCBS/2020-SWF3 / Component 2: Improved Preparation of national tuna Quality And Cost- Open - Pending IBRD / 87790 governance of priority Post 100,000.00 0.00 2020-05-01 2020-05-22 2020-07-05 2020-08-02 2020-09-01 2020-10-06 2020-11-10 2021-11-10 fisheries development and Based Selection International Implementation fisheries management plan GEF48/QCBS/2020-SWF3 / Development of a sport and Component 2: Improved Quality And Cost- Open - Pending recreational fishery data IBRD / 87790 governance of priority Post 170,000.00 0.00 2020-07-15 2020-08-05 2020-09-18 2020-10-16 2020-11-15 2020-12-20 2021-01-24 2022-01-24 Based Selection International Implementation collection and monitoring fisheries system IBRD29/QCBS/2020-SWF3 / Feasibility study on Component 3: Sustainable Quality And Cost- Open - Pending invertebrate hatcheries at IBRD / 87790 development of the blue Post 60,000.00 0.00 2020-05-31 2020-06-21 2020-08-04 2020-09-01 2020-10-01 2020-11-05 2020-12-10 2021-12-10 Based Selection International Implementation Grand Anse Aquaculture economy Hub GEF1-SWIOFISH3 / Blue Component 1: Expansion of Consultant carbon assessment for Mahe Open - Pending IBRD / 87790 sustainable-use marine Post Qualification 100,000.00 0.00 2020-04-15 2020-05-06 2020-06-19 2020-07-19 2020-08-23 2021-02-19 Plateau: Mangrove International Implementation protected areas Selection ecosystems GEF3-SWIOFISH3 / Development of a Harvest Component 1: Expansion of Consultant Open - Pending Strategy Policy and IBRD / 87790 sustainable-use marine Post Qualification 75,000.00 0.00 2019-04-15 2019-05-06 2019-06-19 2019-07-19 2019-08-23 2020-02-19 International Implementation Management Standards for protected areas Selection Seychelles Fisheries GEF4-SWIOFISH3 / Component 1: Expansion of Consultant Preparation of management Open - Pending IBRD / 87790 sustainable-use marine Post Qualification 216,000.00 0.00 2020-09-15 2020-10-06 2020-11-19 2020-12-19 2021-01-23 2021-07-22 plans for sustainable use International Implementation protected areas Selection marine protected areas GEF6-SWIOFISH3 / Studies on importance (social, Component 1: Expansion of Consultant economic, value chains) of Open - Pending IBRD / 87790 sustainable-use marine Post Qualification 50,000.00 0.00 2020-06-30 2020-07-21 2020-09-03 2020-10-03 2020-11-07 2021-05-06 charter and sport fishing International Implementation protected areas Selection sector to define MSP impacts IBRD3-SWIOFISH3 / Education & awareness to Component 3: Sustainable Consultant Pending promote tag and release in IBRD / 87790 development of the blue Post Qualification Open - National 105,000.00 0.00 2020-07-15 2020-08-05 2020-09-18 2020-10-18 2020-11-22 2021-05-21 Implementation sport and recreational economy Selection fisheries IBRD10/CQS/2020-SWF3 / Component 3: Sustainable Consultant Human capacity development Open - IBRD / 87790 development of the blue Post Qualification 90,000.00 0.00 Under Review 2020-04-15 2020-05-28 2020-05-06 2020-06-19 2020-07-19 2020-08-23 2021-02-19 plan in support of International economy Selection aquaculture sector Page 3 IBRD22-SWIOFISH3 / Pre- Component 3: Sustainable Consultant assessment of Seychelles Open - Pending IBRD / 87790 development of the blue Post Qualification 35,000.00 0.00 2020-05-15 2020-06-05 2020-07-19 2020-08-18 2020-09-22 2021-03-21 longline fishery against MSC International Implementation economy Selection standard GEF22-SWIOFISH3 / Component 2: Improved Development of the Fisheries Quality And Cost- Open - Pending IBRD / 87790 governance of priority Post 160,000.00 0.00 2020-06-15 2020-07-06 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2021-12-25 Information Management Based Selection International Implementation fisheries System (incl. dashboards) IBRD16-SWIOFISH3 / Component 3: Sustainable Development and piloting of Quality And Cost- Open - Pending IBRD / 87790 development of the blue Post 50,000.00 0.00 2020-04-15 2020-05-06 2020-06-19 2020-07-17 2020-08-16 2020-09-20 2020-10-25 2022-10-25 app to promote post harvest Based Selection International Implementation economy information sharing GEF18/QCBS/2020-SWF3 / Component 2: Improved Quality And Cost- Open - Pending SIH Data Processing and IBRD / 87790 governance of priority Post 80,000.00 0.00 2020-06-15 2020-07-06 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2021-12-25 Based Selection International Implementation Reporting Tools fisheries INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PA5-SWOIFISH3 / Data Component 2: Improved Individual administrator to assist with Under IBRD / P4760 governance of priority Post Consultant Open 25,000.00 0.00 2017-04-30 2017-06-18 2017-07-09 2017-08-13 2018-02-09 adoption of SIH including Implementation fisheries Selection economic data PA12-SWIOFISH3 / Technical Assistance to Component 3: Sustainable Individual Under Fishing Port Development IBRD / P4760 development of the blue Post Consultant Open 15,000.00 0.00 2017-04-28 2017-06-16 2017-07-07 2017-08-11 2018-02-07 Implementation Committee: project economy Selection management system PA18 SWIOFISH3 / Component 4: Project Individual Under Preparation of Project IBRD / P4760 management and Post Consultant Open 30,000.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 Implementation Implementation Manual coordination Selection PA25-SWIOFISH3 / Elaboration of a Component 3: Sustainable Individual Under standardized proposal IBRD / P4760 development of the blue Post Consultant Open 50,000.00 0.00 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 Implementation assessment methology (blue economy Selection bonds onlending) & Training PA14-SWIOFISH3 / Value chain and feasibility study Component 3: Sustainable Individual to guide investment in fish Under IBRD / P4760 development of the blue Post Consultant Open 50,000.00 0.00 2017-08-07 2017-09-25 2017-10-16 2017-11-20 2018-05-19 processing & services sector Implementation economy Selection and assessment of maximum carrying capacity PA34-SWIOFISH3 / Preparatory activities for Component 2: Improved Individual Under Seychelles to conduct first IBRD / P4760 governance of priority Post Consultant Open 20,000.00 0.00 2017-08-21 2017-10-09 2017-10-30 2017-12-04 2018-06-02 Implementation report for the Fisheries fisheries Selection Transparency Initiative PA35-SWIOFISH3 / Development of an Component 2: Improved Individual Pending Institutional Strategic Plan IBRD / P4760 governance of priority Post Consultant Open 25,000.00 0.00 2017-09-25 2017-11-13 2017-12-04 2018-01-08 2018-07-07 Implementation for the Seychelles Fishing fisheries Selection Authority Page 4 PA36-SWIOFISH3 / Draft policy on the management of Component 3: Sustainable Individual Under bycatch landings by IBRD / P4760 development of the blue Post Consultant Open 20,000.00 0.00 2017-10-17 2017-12-05 2017-11-30 2017-12-26 2017-12-18 2018-01-30 2018-07-29 Implementation industrial fishing vessels in economy Selection Seychelles PA16-SWIOFISH3 / Extension of Jan Robinson's contract (Project Manager) for coordination and manage Component 4: Project project preparation and IBRD / P4760 management and Prior Direct Selection Direct 65,820.00 65,820.00 Signed 2017-11-24 2017-11-28 2017-11-24 2017-10-20 2017-11-24 2017-11-26 2018-12-31 implementation activities in coordination accordance to the implementation arrangements set forth in the loan and grant agreements . SWIOFISH3-PA32 / Component 4: Project Individual Environment and Social Under IBRD / 87790 management and Post Consultant Open 90,000.00 0.00 2018-07-11 2018-04-05 2018-08-29 2018-09-19 2018-08-22 2018-10-24 2019-04-22 Specialist to the Project Implementation coordination Selection Implementation Unit GEF12-SWIOFISH3 / Component 2: Improved Individual Liaison officer for Mahe Under IBRD / 87790 governance of priority Post Consultant Open 24,000.00 0.00 2019-04-30 2019-09-13 2019-06-18 2019-07-09 2019-08-13 2020-02-09 Plateau Demersal Fisheries Implementation fisheries Selection Management Plan GEF14-SWIOFISH3 / Component 2: Improved Individual Support to legal framework Under IBRD / 87790 governance of priority Post Consultant Limited 25,000.00 0.00 2019-04-17 2019-04-22 2019-05-13 2019-06-17 2019-12-14 update (revision of Fisheries Implementation fisheries Selection Act and regulations) GEF15-SWIOFISH3 / Evaluation of the Component 1: Expansion of Pending contribution of the extended IBRD / 87790 sustainable-use marine Post Direct Selection Direct 75,000.00 0.00 2019-05-15 2019-05-25 2019-07-29 2020-01-25 Implementation MPA network to the protected areas economy GEF17-SWIOFISH3 / Management strategy Component 2: Improved Pending evaluation and capacity IBRD / 87790 governance of priority Post Direct Selection Direct 30,000.00 0.00 2019-07-01 2019-07-11 2019-09-14 2020-03-12 Implementation building (through CSIRO fisheries cooperation) GEF19-SWIOFISH3 / Data Component 2: Improved capture software for SIH IBRD / 87790 governance of priority Post Direct Selection Direct 96,000.00 0.00 Canceled 2019-05-08 2019-05-08 2019-05-08 2021-06-15 (EIS fees) fisheries GEF26-SWIOFISH3 / Communication strategy and Component 2: Improved Individual plan for Mahe Plateau IBRD / 87790 governance of priority Post Consultant Open 35,000.00 0.00 Canceled 2019-06-15 2019-08-03 2019-08-24 2019-09-28 2020-03-26 fisheries management fisheries Selection measures GEF29-SWIOFISH3 / Stock Component 1: Expansion of discrimination analysis to Under IBRD / 87790 sustainable-use marine Post Direct Selection Direct 135,000.00 0.00 2019-05-30 2019-11-29 2019-06-09 2019-08-13 2020-08-12 inform marine spatial Implementation protected areas planning IBRD19-SWIOFISH3 / Component 4: Project Annual financial audits of Pending IBRD / 87790 management and Post Direct Selection Direct 50,000.00 0.00 2019-06-30 2019-07-10 2019-09-13 2024-09-11 the project by the Office of Implementation coordination the Auditor General IBRD13-SWIOFISH3 / Component 4: Project Individual Monitoring and evaluation Under IBRD / 87790 management and Post Consultant Open 50,000.00 0.00 2019-04-15 2019-08-13 2019-06-03 2019-06-24 2019-07-29 2020-01-25 and communication specialist Implementation coordination Selection - expert support Page 5 IBRD25-SWIOFISH3 / Component 4: Project Individual Under Procurement Assistant to the IBRD / 87790 management and Post Consultant Limited 85,000.00 0.00 2019-10-15 2019-10-24 2019-10-20 2019-12-20 2019-11-10 2020-01-08 2019-12-15 2022-12-14 Implementation Project Implementation Unit coordination Selection GEF31/IC/2020-SWF3 / Development of Strategic Component 1: Expansion of Individual Under Management Framework for IBRD / 87790 sustainable-use marine Post Consultant Open 22,000.00 0.00 2020-02-23 2020-02-25 2020-04-12 2020-05-03 2020-06-07 2020-12-04 Implementation Seychelles Marine Spatial protected areas Selection Plan GEF24-SWIOFISH3 / Component 1: Expansion of Individual Technical assistant to IBRD / 87790 sustainable-use marine Post Consultant Open 5,000.00 0.00 Canceled 2019-05-15 2019-07-03 2019-07-24 2019-08-28 2020-02-24 MEECC for preparing TORs protected areas Selection GEF11-SWIOFISH3 / Education on fisheries Component 2: Improved Individual management: course IBRD / 87790 governance of priority Post Consultant Open 45,000.00 0.00 Canceled 2019-06-30 2019-08-18 2019-09-08 2019-10-13 2020-04-10 development, delivery, local fisheries Selection trainer training GEF20-SWIOFISH3 / Data Component 2: Improved transfer and trouble IBRD / 87790 governance of priority Post Direct Selection Direct 30,000.00 0.00 Canceled 2019-04-15 2019-04-25 2019-06-29 2019-12-26 shootimg for longline logbook fisheries module for Observe (IRD) GEF27-SWIOFISH3 / Component 2: Improved Development of centralised IBRD / 87790 governance of priority Post Direct Selection Direct 30,000.00 0.00 Canceled 2019-09-30 2019-10-10 2019-12-14 2020-04-07 vessel registry for SFA and fisheries SMSA Component 3: Sustainable IBRD18-SWIOFISH3 / Mud IBRD / 87790 development of the blue Post Direct Selection Direct 28,500.00 0.00 Canceled 2019-06-03 2019-06-13 2019-08-17 2020-08-11 crab recuitment study economy GEF39/IC/2020-SWF3 / Component 2: Improved Individual Seychelles' report to the Under IBRD / 87790 governance of priority Post Consultant Open 35,000.00 0.00 2020-04-30 2020-05-15 2020-06-18 2020-07-09 2020-08-13 2021-02-09 Fisheries Transparency Implementation fisheries Selection Initiative GEF41/IC/2020-SWF3 / Training on data analysis, Component 2: Improved Individual Pending risk assessment and asset IBRD / 87790 governance of priority Post Consultant Open 30,000.00 0.00 2020-07-15 2020-09-02 2020-09-23 2020-10-28 2021-04-26 Implementation deployment planning for fisheries Selection MCS GEF44/IC/2020-SWF3 / Scientific design and Component 2: Improved Individual analytical support for a Pending IBRD / 87790 governance of priority Post Consultant Open 45,000.00 0.00 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-04-11 fisheries-independent Implementation fisheries Selection assessment of sea cucumber status GEF47/IC/2020-SWF3 / Component 2: Improved Individual Study on the implications of Pending IBRD / 87790 governance of priority Post Consultant Limited 25,000.00 0.00 2020-10-01 2020-10-06 2020-10-27 2020-12-01 2021-05-30 local bamboo utilisation for Implementation fisheries Selection FADs IBRD27/IC/2020-SWF3 / Component 3: Sustainable Individual Study of post-harvest losses Pending IBRD / 87790 development of the blue Post Consultant Open 30,000.00 0.00 2020-09-01 2020-10-20 2020-11-10 2020-12-15 2021-06-13 and introduction of routine Implementation economy Selection survey methodology GEF42/SSS/2020-SWF3 / Secretary to Implementation Component 2: Improved Individual Pending Co-management Committee IBRD / 87790 governance of priority Post Consultant Direct 48,000.00 0.00 2020-04-15 2020-04-25 2020-05-16 2020-06-20 2020-12-17 Implementation for Mahe Plateau Demersal fisheries Selection Fisheries Management Plan Page 6 IBRD31/SSS/2020-SWF3 / Component 3: Sustainable Fish quality assessment Pending IBRD / 87790 development of the blue Post Direct Selection Direct 48,000.00 0.00 2020-03-31 2020-04-10 2020-06-14 2020-12-11 training - Phase 2 (contract Implementation economy with firm SeaFish UK) IBRD10-SWIOFISH3 / Component 3: Sustainable Individual Human capacity development IBRD / 87790 development of the blue Post Consultant Open 28,500.00 0.00 Canceled 2019-04-30 2019-06-18 2019-07-09 2019-08-13 2020-02-09 plan in support of economy Selection aquaculture sector GEF9-SWIOFISH3 / Implications of sustainable- Component 1: Expansion of Individual Pending use zone allowable activities IBRD / 87790 sustainable-use marine Post Consultant Open 60,000.00 0.00 2020-05-15 2020-07-03 2020-07-24 2020-08-28 2021-02-24 Implementation on purse seine and long-line protected areas Selection fisheries GEF10-SWIOFISH3 / Stock assessment update: CPUE Component 2: Improved Individual Pending standardisation and IBRD / 87790 governance of priority Post Consultant Limited 40,000.00 0.00 2020-04-15 2020-04-20 2020-05-11 2020-06-15 2020-12-12 Implementation production models for fisheries Selection indicator species GEF25-SWIOFISH3 / Component 2: Improved Individual Capacity building for Pending IBRD / 87790 governance of priority Post Consultant Limited 50,000.00 0.00 2020-07-01 2020-07-06 2020-07-27 2020-08-31 2023-08-31 Seychelles' Federation of Implementation fisheries Selection Fisher Associations GEF28-SWIOFISH3 / Development of a social Component 2: Improved Individual accounting matrix and Pending IBRD / 87790 governance of priority Post Consultant Open 40,000.00 0.00 2020-05-15 2020-07-03 2020-07-24 2020-08-28 2021-01-25 artisanal fisheries component Implementation fisheries Selection for the fisheries satellite account GEF13-SWIOFISH3 / Study Component 2: Improved Individual to quantify public sector Pending IBRD / 87790 governance of priority Post Consultant Open 35,000.00 0.00 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 support to the fisheries Implementation fisheries Selection sector IBRD5-SWIOFISH3 / Support to the Development Bank of Seychelles for Component 3: Sustainable Individual Pending Implementation of the Blue IBRD / 87790 development of the blue Post Consultant Open 62,500.00 0.00 2020-05-01 2020-06-19 2020-07-10 2020-08-14 2021-02-10 Implementation Investment Fund: Technical economy Selection assistant to act as fund relationship manager IBRD11-SWIOFISH3 / Component 3: Sustainable Individual FBOA label program Pending IBRD / 87790 development of the blue Post Consultant Open 100,000.00 0.00 2020-04-30 2020-06-18 2020-07-09 2020-08-13 2022-08-13 coordination and Implementation economy Selection management IBRD12-SWIOFISH3 / Component 3: Sustainable Individual Needs assessment study for Pending IBRD / 87790 development of the blue Post Consultant Open 25,000.00 0.00 2020-09-30 2020-11-18 2020-12-09 2021-01-13 2021-07-12 sanitary and phytosanitary Implementation economy Selection monitoring IBRD21-SWIOFISH3 / National standard for Component 3: Sustainable Individual sanitary and phtyosanitary IBRD / 87790 development of the blue Post Consultant Open 40,000.00 0.00 Canceled 2019-10-01 2019-11-19 2019-12-10 2020-01-14 2020-07-12 including implementation economy Selection plan and roadmap GEF18-SWIOFISH3 / SFA Component 2: Improved co-financing of SIH (fees and IBRD / 87790 governance of priority Post Direct Selection Direct 60,000.00 0.00 Canceled 2019-04-15 2019-04-25 2019-06-29 2019-12-26 costs for IFREMER) fisheries Page 7 GEF16-SWIOFISH3 / Component 1: Expansion of THEMIS AIS, Radar IBRD / 87790 sustainable-use marine Post Direct Selection Direct 441,500.00 0.00 Canceled 2019-04-15 2019-08-29 2019-04-25 2019-06-29 2019-12-26 installation maintenance and protected areas subscription costs GEF8-SWIOFISH3 / Drafting of governance Component 1: Expansion of Individual authority establishment act IBRD / 87790 sustainable-use marine Post Consultant Limited 30,000.00 0.00 Canceled 2019-04-30 2020-02-23 2019-05-05 2019-05-26 2019-06-30 2019-12-27 and other MSP regulatory protected areas Selection frameworks GEF30/IC/2020-SWF3 / Component 1: Expansion of Individual Study on the status of ETP Pending IBRD / 87790 sustainable-use marine Post Consultant Open 60,000.00 0.00 2020-05-29 2020-07-17 2020-08-07 2020-09-11 2021-03-10 sharks and rays in MSP Implementation protected areas Selection zones GEF38/IC/2020-SWF3 / Component 2: Improved Individual Socio-economic impact Pending IBRD / 87790 governance of priority Post Consultant Open 40,000.00 0.00 2020-06-01 2020-07-20 2020-08-10 2020-09-14 2021-03-13 assessments for fisheries Implementation fisheries Selection management measures IBRD14-SWIOFISH3 / Component 4: Project Individual Environmental and social IBRD / 87790 management and Post Consultant Limited 40,000.00 0.00 Canceled 2019-04-15 2020-05-05 2019-04-20 2019-05-11 2019-06-15 2020-06-14 specialist - local expert on coordination Selection retainer IBRD14-SWIOFISHA / Component 4: Project Individual Under ENVIRONMENTAL AND IBRD / 87790 management and Post Consultant Open 40,000.00 0.00 2020-05-06 2020-05-05 2020-06-24 2020-07-15 2020-08-19 2021-02-15 Implementation SOCIAL SPECIALIST coordination Selection IBRD33/SSS/2020-SWF3 / Component 4: Project Pending Monitoring and Evaluation IBRD / 87790 management and Post Direct Selection Direct 90,000.00 0.00 2020-05-06 2020-05-16 2020-07-20 2023-07-20 Implementation Specialist for the PIU coordination Page 8