The World Bank Implementation Status & Results Report BF - Support to the National Biodigester Program (P156413) BF - Support to the National Biodigester Program (P156413) AFRICA WEST | Burkina Faso | Environment, Natural Resources & the Blue Economy Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2017 | Seq No: 2 | ARCHIVED on 25-Nov-2020 | ISR41272 | Implementing Agencies: Ministry of Animal and Fishery Resources, SNV Key Dates Key Project Dates Bank Approval Date: 21-Jan-2017 Effectiveness Date: 30-Dec-2016 Planned Mid Term Review Date: -- Actual Mid-Term Review Date: Original Closing Date: 31-Oct-2025 Revised Closing Date: 31-Oct-2025 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to increase use of biodigesters in rural households of Burkina Faso. The long term objective of this project is to support Burkina Faso s efforts in mitigating climate change through the promotion of the biodigester technology to rural cattle-owning households, which, in addition, provides several benefits for the households, including better access to clean energy and slurry to improve soil fertility. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Low Implementation Status and Key Decisions As of mid-2019, the formal verification process accounted the emission reduction related to the installation of about 9,100 biodigesters. While this is encouraging, this is under the expectations and could lead to a total production of CER about 30% lower than expected if PNB cannot raise the production of biodigesters above 2,000 units per year. The cycle of verification and payments is performing well, with already three payments to SNV accounting for about US$1m. These funds have been instrumental to ensure the sustainability of PNB-BF program after the Dutch funding was terminated in 2019. The lower amount of CERs to be purchased by the World Bank as per the Emission Reduction Purchase Agreement (ERPA) will lead to a restructuring and a reduction of the overall amount of CERs to be purchased by the Bank. 11/25/2020 Page 1 of 4 The World Bank Implementation Status & Results Report BF - Support to the National Biodigester Program (P156413) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Moderate Moderate Macroeconomic -- Low Low Sector Strategies and Policies -- Low Low Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and -- Moderate Moderate Sustainability Fiduciary -- Low Low Environment and Social -- Low Low Stakeholders -- Moderate Moderate Other -- High High Overall -- Moderate Low Results PDO Indicators by Objectives / Outcomes Promoting the biodigester technology to rural cattle-owning households IN00828250 ►Biodigester installed per year (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1,323.00 1,708.00 1,708.00 3,600.00 Date 31-Dec-2015 31-Dec-2018 31-Dec-2018 31-Dec-2026 IN00828247 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 8,000.00 55,158.00 55,158.00 180,000.00 Date 31-Dec-2015 30-Jun-2019 30-Jun-2019 31-Dec-2026 Intermediate Results Indicators by Components Supporting the National Biodigester Program 11/25/2020 Page 2 of 4 The World Bank Implementation Status & Results Report BF - Support to the National Biodigester Program (P156413) IN00828266 ►ERPA amount covered by the installed capacity (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 46.00 46.00 65.00 Date 31-Dec-2015 30-Jun-2019 30-Jun-2019 31-Dec-2026 IN00828248 ►biodigester sector development (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 3.00 Date 31-Dec-2015 13-Apr-2020 13-Apr-2020 31-Dec-2026 IN00828249 ►PNB-BF financing gap18 for phase III covered by the installed capacity of CER production (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 44.00 44.00 65.00 Date 31-Dec-2015 31-Dec-2019 31-Dec-2019 31-Dec-2026 Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P156413 TF-A4117 Effective USD 6.05 6.05 0.00 0.97 5.08 16% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P156413 TF-A4117 Effective 19-Dec-2016 30-Dec-2016 30-Dec-2016 31-Oct-2025 31-Oct-2025 Cumulative Disbursements 11/25/2020 Page 3 of 4 The World Bank Implementation Status & Results Report BF - Support to the National Biodigester Program (P156413) PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 11/25/2020 Page 4 of 4