Procurement Plan Project: Rwanda Stunting Prevention and Reduction Project: P 164845. Project Implementation agency: Rwanda Biomedical Centre (RBC) Date of General Procurement Notice : {Kindly Mention the Date, if published} Date of the Procurement Plan: Sep 2017 Period covered by this Procurement Plan: Nov 2017 to April 2019 (For the first 18 months). Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP, constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. All Consultancy Services shall be procured following Procurement Regulations and Bank’s SPDs. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law of Rwanda, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information:- (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: (The table below depicts the Thresholds and Procurement Methods to be used under the Rwanda Pilot Program for Climate Resilience project): Thresholds*, Procurement Methods, and Prior Review Goods, Works, and Non-Consulting Services Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 2 million Open National ( Goods) – Open Tender < $2 million and > $ 2,500 as per Ministerial Order 2014 RFQ (Goods) Less than $ 2,500 or as stipulated in Rwanda Procurement Regulations Open International (Works) Equal to or more than 10 million Open National (Works) - Open Tender as Less than 10 million per Ministerial Order 2014 Method of Procurement Thresholds for Method (US$ equivalent) RFQ (works) Less than $ 2,500 or as stipulated in Rwanda Procurement Regulations Open International (Non-consulting Equal to or More than 2 million Services) Open National (Non-consulting Services) Less than 2 million - Open Tender as per Ministerial Order 2014 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Framework Agreements All procurement that meet the requirements as per Para 6.57 to 6.59 of Procurement Regulations., and with prior agreement in PP with the Bank. First FA and All other FAs above USD 2 million are subject to prior review by Bank It is not expected that there will need for prequalification in the procurement arrangements under Rwanda Stunting Prevention and Reduction Project Selection of Consultants Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based Selection As per requirements of para 7.3 of the Regulations (QCBS) Quality Based Selection (QBS) As per requirements of para 7.8 to 7.10 of the Regulations Selection based on a Fixed Budget As per requirements of para 7.4 and 7.5 of the (FBS) Regulations Selection Based on Least Cost Basis As per requirements of para 7.6 and 7.7 of the (LCS) Regulations Selection based on Consultant’s As per requirements of para 7.11 and 7.12 of the Qualification (CQ) Regulations Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 per contract. Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive Selection As per requirements of para 7.36 and 7.37 of the Regulations Limited Competitive Selection As per requirements of para 7.38 of the Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “Moderate”): (a) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 4 million; (b) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 15 million; (c) Consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million; and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. PROCUREMENT Rwanda : Rwanda Stunting Prevention and Reduction Project PLAN General Information Country: Rwanda Bank’s Approval Date of the Original Procurement Plan: 2018-06-27 2020-08-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164845 GPN Date: 2018-11-02 Project Name: Rwanda Stunting Prevention and Reduction Project Loan / Credit No: IDA / 61870, TF / A6567 Executing Agency(ies): Rwanda Biomedical Center - Ministry of Health WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned RW-RBC-146096-CW-DIR / Complete set up and equipping POEs with Pending infrastructure such as IDA / 61870 CERC Post Direct Selection Direct 1,264,946.00 0.00 Implementat 2019-11-22 2019-11-27 2020-01-01 2020-06-29 temporary screening and ion holding areas, hand washing facilities, toilets and necessary furniture RW-RBC-146094-CW-DIR / Pending Water supply to 58 health IDA / 61870 CERC Post Direct Selection Direct 2,218,649.00 0.00 Implementat 2019-11-22 2019-11-27 2020-01-01 2020-06-29 centres without water ion GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-RBC-67187-GO-RFB / Component 1: Prevention of Pending Procure pregnancy testing Single Stage - One IDA / 61870 Stunting at Community and Post Request for Bids Open - National 345,554.52 0.00 Implementati 2018-09-10 2018-09-15 2018-10-26 2018-11-16 2018-12-07 2019-04-06 equipment (Urine test kit Envelope Household Levels on for pregnancy testing) RW-RBC-67178-GO-RFB / Procure Basic equipment Component 1: Prevention of Pending Single Stage - One (Register book, Picture IDA / 61870 Stunting at Community and Post Request for Bids Open - National 100,593.00 0.00 Implementati 2018-07-06 2018-07-09 2018-08-13 2018-09-03 2018-09-24 2019-01-22 Envelope books, Mats, Towel and Household Levels on Toilet paper) RW-RBC-67107-GO-RFB / Procure Hygienic Materials for Home-ECD and Sanitation and clean water for Ubudehe 1 households Component 1: Prevention of Pending Single Stage - One (Hygienic plastic slabs, Tippy IDA / 61870 Stunting at Community and Post Request for Bids Open - National 815,047.00 0.00 Implementati 2018-08-20 2018-08-25 2018-09-29 2018-10-20 2018-11-10 2019-03-10 Envelope tap for hand washing, Water Household Levels on filter and storage container, Water tank for rain water collection + installation and Water pipel RW-RBC-67143-GO-RFB / Component 1: Prevention of Pending Procure Home Utensils and Single Stage - One IDA / 61870 Stunting at Community and Post Request for Bids Open - National 90,353.00 0.00 Implementati 2018-08-16 2018-08-21 2018-09-28 2018-10-19 2018-11-09 2019-02-07 crockery (Cookware, Plate Envelope Household Levels on ware and Utensils) Page 1 RW-RBC-67103-GO-RFB / Procure construction materials for Home Based Component 1: Prevention of Pending ECD and improved Single Stage - One IDA / 61870 Stunting at Community and Post Request for Bids Open - National 1,282,079.00 0.00 Implementati 2018-07-13 2018-07-18 2018-08-31 2018-09-21 2018-10-12 2019-02-09 sanitation and clean water Envelope Household Levels on in Ubudehe 1 Households (Iron sheets and doors for latrines) RW-RBC-68610-GO-RFB / Component 2: High-impact Pending Single Stage - One Procure Nutrition IDA / 61870 Health and Nutrition Post Request for Bids Open - National 873,832.00 0.00 Implementati 2018-08-22 2018-08-27 2018-09-28 2018-10-19 2018-11-09 2019-03-09 Envelope commodities and drugs Services on RW-RBC-68611-GO-RFB / Procure basic tools for waste Component 2: High-impact management(Procurement of Single Stage - One IDA / 61870 Health and Nutrition Post Request for Bids Open - National 1,269,913.00 0.00 Canceled 2018-08-24 2018-08-27 2018-09-28 2018-10-19 2018-11-09 2019-03-09 water testing kits, Safe Envelope Services disposal boxes and equipment) RW-RBC-88629-GO-APA / Component 2: High-impact Alternative Single Stage - One Procure Nutrition IDA / 61870 Health and Nutrition Post Procurement Open - National 873,832.00 0.00 Canceled 2018-12-14 2018-12-19 2019-01-09 2019-01-16 2019-02-06 2019-08-05 Envelope commodities and drugs Services Arrangement RW-RBC-88631-GO-APA / Component 1: Prevention of Alternative Procure pregnancy testing Single Stage - One IDA / 61870 Stunting at Community and Post Procurement Open - National 345,554.52 0.00 Canceled 2018-12-14 2018-12-19 2019-01-09 2019-01-16 2019-02-06 2019-08-05 equipment (Urine test kit Envelope Household Levels Arrangement for pregnancy testing) RW-RBC-89364-GO-APA / Component 1: Prevention of Alternative Single Stage - One Production of Posters and IDA / 61870 Stunting at Community and Post Procurement Open - National 42,442.00 0.00 Canceled 2018-12-14 2018-12-19 2019-01-09 2019-01-16 2019-02-06 2019-08-05 Envelope other print media Household Levels Arrangement Component 1: Prevention of Alternative RW-RBC-89365-GO-APA / Single Stage - One IDA / 61870 Stunting at Community and Post Procurement Open - National 1,665.88 0.00 Canceled 2018-12-17 2018-12-22 2019-01-12 2019-01-19 2019-02-09 2020-02-04 Production of Short videos Envelope Household Levels Arrangement RW-RBC-67197-GO-RFB / Procure CHW equipment Component 1: Prevention of Pending (Weighing scales, Cupboard, Single Stage - One IDA / 61870 Stunting at Community and Post Request for Bids Open - National 2,857,443.00 0.00 Implementati 2019-02-15 2019-02-18 2019-03-21 2019-04-11 2019-05-02 2019-07-31 timer, thermometer, apron, Envelope Household Levels on badges, boots, umbrellas, bags, T-shirts and ibitenge) RW-RBC-112073-GO-RFB / Component 1: Prevention of Pending Single Stage - One Procurement of water testing IDA / 61870 Stunting at Community and Post Request for Bids Open - National 340,252.00 0.00 Implementati 2019-04-28 2019-05-01 2019-06-01 2019-06-22 2019-07-14 2019-10-12 Envelope kits Household Levels on RW-RBC-112075-GO-RFB / Component 1: Prevention of Pending Single Stage - One Procurement of basic waste IDA / 61870 Stunting at Community and Post Request for Bids Open - National 884,004.00 0.00 Implementati 2019-04-28 2019-05-01 2019-06-02 2019-06-23 2019-07-14 2019-11-11 Envelope management tools Household Levels on RW-RBC-146098-GO-RFB / Acquire 2 operational vehicle Pending Single Stage - One for sample transportation, IDA / 61870 CERC Post Request for Bids Open - National 110,960.00 0.00 Implementati 2020-01-10 2020-01-15 2020-02-19 2020-03-11 2020-04-01 2020-08-29 Envelope emergency travels, outreach on and rapid response activities Component 2: High-impact Pending RW-RBC-146089-GO-RFB / TF / A6567 Health and Nutrition Prior Direct Selection Direct 8,000,000.00 0.00 Implementati 2019-11-20 2019-11-25 2019-12-30 2020-12-29 Supply of FBF Services on RW-RBC-146097-GO-DIR / Pending Establish and equip isolation IDA / 61870 CERC Post Direct Selection Direct 1,413,189.00 0.00 Implementati 2019-11-24 2019-11-29 2020-01-03 2020-07-01 facility in hospitals on Page 2 RW-RBC-165459-GO-RFB / Component 1: Prevention of Pending Single Stage - One Acquisition of motorbikes TF / A6567 Stunting at Community and Post Request for Bids Open - National 126,217.00 0.00 Implementati 2020-03-20 2020-03-21 2020-04-21 2020-05-12 2020-05-27 2020-09-24 Envelope for 13 Districts Household Levels on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Prevention of Pending RW-RBC-67204-NC-RFB / Single Stage - One IDA / 61870 Stunting at Community and Post Request for Bids Open - National 65,882.35 0.00 Implementati 2018-09-21 2018-09-21 2018-09-21 2018-09-21 2018-09-26 2018-10-26 Radio series Envelope Household Levels on Component 1: Prevention of Pending RW-RBC-67201-NC-RFB / Request for Single Stage - One IDA / 61870 Stunting at Community and Post Limited 1,665.88 0.00 Implementati 2018-10-14 2018-12-09 2019-02-07 Production of Short videos Quotations Envelope Household Levels on RW-RBC-67206-NC-RFB / Component 1: Prevention of Pending Single Stage - One Production of Posters and IDA / 61870 Stunting at Community and Post Request for Bids Open - National 42,442.00 0.00 Implementati 2018-08-31 2018-08-31 2018-08-31 2018-08-31 2018-09-05 2018-10-05 Envelope other print media Household Levels on RW-RBC-80801-NC-RFQ / Component 1: Prevention of Request for Single Stage - One Advertisement in IDA / 61870 Stunting at Community and Post Limited 10,000.00 0.00 Canceled 2018-10-12 2018-10-24 2019-10-19 Quotations Envelope Newspapers Household Levels CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-RBC-68594-CS-QCBS / Assessment of the integration of new Component 1: Prevention of nutritional features, develop Quality And Cost- Pending IDA / 61870 Stunting at Community and Post Open - National 53,328.00 0.00 2018-10-01 2018-10-22 2018-11-05 2018-11-26 2018-12-26 2019-01-30 2019-03-06 2019-05-05 system requirement analysis, Based Selection Implementation Household Levels design and development based on existing reporting systems RW-RBC-68585-CS-QCBS / Conduct a KAP study on Component 1: Prevention of nutrition, hygiene, early Quality And Cost- Pending IDA / 61870 Stunting at Community and Post Open - National 116,177.00 0.00 2018-12-04 2018-12-19 2019-01-10 2019-01-31 2019-03-02 2019-04-06 2019-05-11 2019-11-07 learning, parenting and child Based Selection Implementation Household Levels protection among families with children under 5 years RW-RBC-89369-CS-CAPA / Revamping Rapid SMS to Component 1: Prevention of Alternative accommodate two way IDA / 61870 Stunting at Community and Post Procurement Open - National 28,000.00 0.00 Canceled 2018-12-17 2019-01-07 2019-02-20 2019-03-20 2019-04-19 2019-05-24 2019-06-14 2020-06-13 communication between Household Levels Arrangement health centers and CHWs RW-RBC-68586-CS-QCBS / Conduct Optifood Analysis to identify gaps in current diets consumption, and Component 1: Prevention of suggests locally available Quality And Cost- IDA / 61870 Stunting at Community and Post Open - National 47,625.00 0.00 Canceled 2018-08-24 2018-09-14 2018-09-28 2018-10-19 2018-11-18 2018-12-23 2019-01-27 2019-03-28 foods to fill them. At low Based Selection Household Levels cost ,and develop food based recommendations and likely reduction in prevalence of stunting Page 3 RW-RBC-95230-CS-CDS / Conduct food Analysis to identify gaps in current diets consumption, and Component 2: High-impact suggests locally available Quality And Cost- Open - IDA / 61870 Health and Nutrition Post 47,625.00 0.00 Canceled 2019-02-15 2019-03-08 2019-03-22 2019-03-24 2019-04-14 2019-04-23 2019-05-21 2019-08-19 foods to fill them. At low Based Selection International Services cost ,and develop food based recommendations and likely reduction in prevalence of stunting. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Monitoring Individual RW-RBC-67130-CS-INDV / Under IDA / 61870 and Evaluation, and Post Consultant Open 75,621.00 0.00 2018-06-29 2018-08-16 2018-07-22 2018-07-29 2018-08-08 2019-08-08 Internal Auditor (1) Implementation Program Management Selection Component 3: Monitoring Individual RW-RBC-67133-CS-INDV / Under IDA / 61870 and Evaluation, and Post Consultant Open 111,803.72 0.00 2018-06-29 2018-08-28 2018-07-22 2018-07-27 2018-08-08 2019-08-08 M&E Specialist (1) Implementation Program Management Selection Component 3: Monitoring Individual RW-RBC-67134-CS-INDV / Under IDA / 61870 and Evaluation, and Post Consultant Open 111,803.72 0.00 2018-06-29 2018-08-31 2018-07-22 2018-07-27 2018-08-08 2019-08-08 Communication Specialist (1) Implementation Program Management Selection RW-RBC-67212-CS-INDV / Component 2: High-impact Individual Technical Assistance to IDA / 61870 Health and Nutrition Post Consultant Open 28,088.00 0.00 Canceled 2018-11-14 2018-12-24 2019-01-14 2019-02-04 2019-04-05 design repository of key Services Selection messages (local consultant) RW-RBC-68579-CS-INDV / TA to review status of application of positive deviance' ("maman lumiere") Component 1: Prevention of Individual Pending methodology in currently IDA / 61870 Stunting at Community and Post Consultant Open 15,750.00 0.00 2018-08-24 2018-10-10 2018-10-17 2018-11-07 2019-01-06 Implementation existing pilots within the Household Levels Selection country (implementation and challenges) and develop a national strategy RW-RBC-68580-CS-INDV / Component 1: Prevention of Individual Create a national ECD Pending IDA / 61870 Stunting at Community and Post Consultant Open 10,000.00 0.00 2018-09-06 2018-10-26 2018-11-02 2018-11-23 2019-01-22 program website and its Implementation Household Levels Selection related social media channels RW-RBC-68583-CS-INDV / Revamping Rapid SMS to Component 1: Prevention of Individual Pending accommodate two way IDA / 61870 Stunting at Community and Post Consultant Open 28,000.00 0.00 2019-01-08 2019-03-01 2019-03-08 2019-03-29 2019-05-28 Implementation communication between Household Levels Selection health centers and CHWs Component 3: Monitoring Individual RW-RBC-67127-CS-INDV / Under IDA / 61870 and Evaluation, and Prior Consultant Open 223,607.44 0.00 2018-07-11 2018-08-16 2018-08-09 2018-08-16 2018-08-24 2019-08-24 Financial Specialists (2) Implementation Program Management Selection Component 3: Monitoring Individual RW-RBC-67120-CS-INDV / Under IDA / 61870 and Evaluation, and Prior Consultant Open 157,448.12 0.00 2018-07-20 2018-07-20 2018-08-16 2018-08-23 2018-08-31 2019-08-31 Program Manager (1) Implementation Program Management Selection Page 4 RW-RBC-95238-CS-INDV / TA to develop strategy to Component 2: High-impact Individual reach adolescent girls with Pending IDA / 61870 Health and Nutrition Post Consultant Open 20,250.00 0.00 2019-01-31 2019-02-26 2019-03-05 2019-03-17 2019-06-15 nutrition counseling and Implementation Services Selection weekly iron folic acid supplementation RW-RBC-68584-CS-INDV / Assessment of WASH needs ( Hygienic plastic slabs, Tippy tap for hand washing, Component 1: Prevention of Individual Water filter and storage IDA / 61870 Stunting at Community and Post Consultant Open 21,783.00 0.00 Canceled 2018-08-24 2018-10-19 2018-10-26 2018-11-16 2019-01-15 container, Water tank for Household Levels Selection rain water collection + installation and Water pipelines) for identified households Component 1: Prevention of Individual RW-RBC-68578-CS-INDV / IDA / 61870 Stunting at Community and Post Consultant Open 54,000.00 0.00 Canceled 2018-08-17 2018-10-05 2018-10-26 2018-11-16 2019-01-15 Develop new CHWs strategy Household Levels Selection RW-RBC-68582-CS-INDV / Development and validation of BCC messages and design Component 1: Prevention of Individual of communication tools and IDA / 61870 Stunting at Community and Post Consultant Open 13,500.00 0.00 Canceled 2019-01-23 2019-03-14 2019-03-21 2019-04-11 2019-06-10 guidelines for Household Levels Selection implementation, nutrition, hygiene, parenting and child development RW-RBC-67219-CS-INDV / Technical Assistance to review repository of Component 2: High-impact Individual messages and build capacity IDA / 61870 Health and Nutrition Post Consultant Open 27,058.82 0.00 Canceled 2018-11-14 2018-12-24 2018-12-29 2019-01-19 2019-03-20 among social cluster Services Selection technical working group (local consultant) RW-RBC-67211-CS-INDV / Technical Assistance to Component 2: High-impact Individual develop social cluster IDA / 61870 Health and Nutrition Post Consultant Open 78,204.00 0.00 Canceled 2018-11-14 2018-12-24 2018-12-31 2019-01-28 2019-03-29 communication strategy Services Selection (international consultant) RW-RBC-95226-CS-CDS / Component 1: Prevention of Individual Pending Develop new Community IDA / 61870 Stunting at Community and Post Consultant Open 54,000.00 0.00 2019-02-15 2019-03-13 2019-03-27 2019-04-17 2019-05-17 Implementation Health Workers strategy Household Levels Selection RW-RBC-177287-CS-CDS / Control and supervision of Pending construction works for IDA / 61870 CERC Post Direct Selection Direct 70,000.00 0.00 2020-06-08 2020-06-11 2020-06-19 2020-09-17 Implementation Isolation facilities in Hospitals RW-RBC-177288-CS-CDS / Control and supervision of Pending IDA / 61870 CERC Post Direct Selection Direct 43,235.00 0.00 2020-06-08 2020-06-11 2020-06-16 2020-12-13 construction works of points Implementation of entries (PoEs) RW-RBC-189272-CS-CDS / Process evaluation and coverage survey of FBF Component 1: Prevention of Pending under the stunting IDA / 61870 Stunting at Community and Prior Direct Selection Direct 52,372.00 0.00 2020-09-20 2020-09-27 2020-10-26 2021-04-24 Implementation prevention and reduction Household Levels project (SPRP) targeted districts. Page 5