The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583) Bangladesh Modern Food Storage Facilities Project (P120583) SOUTH ASIA | Bangladesh | Agriculture Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 12 | ARCHIVED on 10-Mar-2019 | ISR35987 | Implementing Agencies: Government of Bangladesh, Directorate General, Ministry of Food Key Dates Key Project Dates Bank Approval Date: 30-Dec-2013 Effectiveness Date: 27-May-2014 Planned Mid Term Review Date: 05-Mar-2018 Actual Mid-Term Review Date: 07-May-2018 Original Closing Date: 30-Jun-2020 Revised Closing Date: 30-Jun-2020 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The overall Project development objective is to increase the grain reserve available to households to meet their post-disaster needs and improve the efficiency of grain storage management. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component A – Construction of Modern Grain Storage Silo Facilities:(Cost $195.00 M) Component B – Support for Food and Market Planning and Monitoring Program:(Cost $25.00 M) Component C - Project management, Construction Supervision, Technical Assistance, Training and Strategic Studies:(Cost $20.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions This is an interim Implementation Status and Results Report (ISR). A full ISR will be prepared after the next implementation support and supervision mission tentatively planned between June-July 2019. Since the last ISR was archived in December 2018, some progress has been recorded: (i) 80 percent of pilling have been completed (against 55 percent in December 2019) for the construction of rice silos in Mymensingh, Madhupur and Ashuganj; (ii) 260,000 household silos (HHS) have been distributed to farmers against 181,000 HHS in December 2018. The Task Team should consider: (i) reassessing the time required to complete all activities to be financed by the project; (ii) extending the project closing date to align with the completion of activities; and (iii) downgrading project performance ratings if more progress is not recorded in procurement of steel silos during the next implementation support mission (tentatively between June-July 2019). 3/10/2019 Page 1 of 5 The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Substantial Substantial Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Substantial Substantial Institutional Capacity for Implementation and Sustainability -- High High Fiduciary -- Substantial Substantial Environment and Social -- Substantial Substantial Stakeholders -- Substantial Substantial Other -- -- Substantial Overall -- Substantial Substantial Results PDO Indicators by Objectives / Outcomes 1. To increase the grain reserve available to households IN00668962 ►P1. Increased grain storage capacity in public and household storage facilities (Metric ton, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 94,000.00 400,000.00 Date 01-Feb-2014 30-Nov-2018 05-Feb-2019 30-Jun-2020 IN00668964 ►P2. Direct Project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 181,000.00 230,000.00 10,000,000.00 Date 01-Feb-2014 30-Nov-2018 05-Feb-2019 30-Jun-2020 IN00674735 Of which female (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target 3/10/2019 Page 2 of 5 The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583) Value 0.00 -- 26.00 50.00 2. To improve the efficiency of grain storage management IN00668965 ►P3. Reduction in grain storage and handling losses in public storage facilities (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 17.00 0.00 50.00 Date 01-Feb-2014 30-Nov-2018 05-Feb-2019 30-Jun-2020 Intermediate Results Indicators by Components Component A – Construction of Modern Grain Storage Silo Facilities IN00668967 ►A1. Site development works completed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 8.00 8.00 Date 01-Feb-2014 30-Nov-2018 05-Feb-2019 30-Jun-2020 IN00668970 ►A2. Public food grain silo consructed and operational (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 181,000.00 0.00 8.00 Date 01-Feb-2014 30-Nov-2018 05-Feb-2019 30-Jun-2020 IN00668975 ►A3. Households provided with safe grain storage containers (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 230,000.00 500,000.00 Date 01-Feb-2014 30-Nov-2018 05-Feb-2019 30-Jun-2020 Component B – Support for Food and Market Planning and Monitoring Program IN00668968 ►B1. CSDs and LSDs connected to a centralized public food storage and distribution management system (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Feb-2014 30-Nov-2018 05-Feb-2019 30-Jun-2020 IN00668971 3/10/2019 Page 3 of 5 The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583) ►B2. Research papers completed and approved by FPMU (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 2.00 15.00 Date 01-Feb-2014 30-Nov-2018 05-Feb-2019 30-Jun-2020 IN00668974 ►B3. Policy notes prepared under the Food Policy Reasearch Program published (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 8.00 Date 01-Feb-2014 30-Nov-2018 05-Feb-2019 30-Jun-2020 Component C - Project management, Construction Supervision, Technical Assistance, Training and Strategic Studies IN00668969 ►C1. Client days of training provided by gender (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 170.00 1,190.00 200,000.00 Date 01-Feb-2014 30-Nov-2018 05-Feb-2019 30-Jun-2020 IN00668973 % of female (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 12.90 12.90 25.00 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P120583 IDA-52650 Effective USD 210.00 210.00 0.00 77.44 114.11 40% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P120583 IDA-52650 Effective 30-Dec-2013 07-Apr-2014 27-May-2014 30-Jun-2020 30-Jun-2020 Cumulative Disbursements 3/10/2019 Page 4 of 5 The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583) Restructuring History Level 2 Approved on 19-Aug-2015 Related Project(s) P168484-Additional Financing For Modern Food Storage Facilities Project 3/10/2019 Page 5 of 5