PE Support to the Subnational Transport Program Project (P132515) Procurement Plan Country: Peru Region: LATIN AMERICA AND CARIBBEAN Approval Date: 11-Dec-2015 General Procurement Notice published on: 30-Nov-2016 July 9, 2010 PROCUREMENT Peru : Support to the Subnational Transport Program Project PLAN General Information Country: Peru Banks Approval Date of the Original Procurement Plan: 2016-12-22 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-08-14 Project ID: P132515 GPN Date: 2016-11-30 Project Name: Support to the Subnational Transport Program Project Loan / Credit No: IBRD / 85620 Executing Agency(ies): Descentralized Provias WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PROVIAS-9711-CW-RFB / Rehabilitacion y Mejoramiento del Camino Vecinal de Talavera- Infrastructure for Integration and Single Stage - One Pending Mulacancha-Taramba-Nueva IBRD / 85620 Post Request for Bids Open - National 1,354,815.84 0.00 2017-07-03 2017-07-08 2017-08-19 2017-09-18 2017-10-23 2018-03-22 Social Inclusion Envelope Implementation Esperanza -Ap-510 , Long. 14.28 km Prov. Andahuaylas, APURIMAC PE-PROVIAS-9712-CW-RFB / Mejoramiento de Camino Vecinal Pacobamba-Huironay- Infrastructure for Integration and Single Stage - One Pending IBRD / 85620 Post Request for Bids Open - National 5,456,251.32 0.00 2017-07-03 2017-07-08 2017-08-19 2017-09-18 2017-10-23 2018-05-21 Ccerabamba-Abra Cusqueña, Social Inclusion Envelope Implementation Long. 28.83 km Prov. Andahuaylas,APURIMAC PE-PROVIAS-4678-CW-RFB / Infrastructure for Integration and Single Stage - One Chuchin - Esccana - Rumi Rumi IBRD / 85620 Post Request for Bids Open - National 3,023,521.00 0.00 Canceled 2017-07-03 2017-07-17 2017-08-16 2017-08-30 2017-09-13 2018-11-07 Social Inclusion Envelope -Huinche - Moyorcco PE-PROVIAS-4679-CW-RFB / Paquete N° 1 obras de Rural Road Infrastructure Single Stage - One IBRD / 85620 Post Request for Bids Open - National 1,348,397.00 0.00 Canceled 2017-06-05 2017-06-19 2017-07-19 2017-08-02 2017-08-16 2018-05-13 mantenimiento periodico en 40 Maintenance Envelope km PE-PROVIAS-11812-CW-RFB / Servicio de gestión y conservación vial por niveles de Rural Road Infrastructure Single Stage - One Pending IBRD / 85620 Prior Request for Bids Open - International 15,042,761.00 0.00 2018-08-13 2018-09-10 2018-10-26 2018-11-02 2018-12-11 2022-01-09 servicio de los caminos vecinales Maintenance Envelope Implementation de la provincia de Chanchamayo - Junín. GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PROVIAS-9697-CS-QCBS / Estudio definitivo del camino vecinal Emp. Ruta 16 - Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - National 87,962.42 0.00 2017-04-03 2017-04-17 2017-05-06 2017-06-03 2017-06-08 2017-06-29 2017-07-13 2018-09-06 Inkacancha Social Inclusion Based Selection Implementation Long. 10.70 km Prov. Paucartambo, CUSCO PE-PROVIAS-9700-CS-QCBS / Estudio definitivo del camino vecinal Puente Checca - Puente Asunción - Chitibamba - Emp. Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - National 240,869.05 0.00 2017-04-03 2017-04-17 2017-05-06 2017-06-03 2017-06-08 2017-06-29 2017-07-13 2018-09-06 CU-126 (Comunidad Huinchiri - Social Inclusion Based Selection Implementation Quehue), Long. 29.30 km Prov. Canas, CUSCO PE-PROVIAS-9702-CS-QCBS / Estudio definitivo del camino vecinal Emp. CU-129 (Chapina) - Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - National 184,145.63 0.00 2017-04-03 2017-04-17 2017-05-06 2017-06-03 2017-06-08 2017-06-29 2017-07-13 2018-09-06 Quille, Social Inclusion Based Selection Implementation Long. 22.40 km Prov. Paruro, CUSCO PE-PROVIAS-9704-CS-QCBS / Estudio definitivo del camino Infrastructure for Integration and Quality And Cost- Pending vecinal Puente Quesccañuma - IBRD / 85620 Post Open - National 246,376.98 0.00 2017-04-21 2017-05-05 2017-05-24 2017-06-21 2017-06-26 2017-07-17 2017-07-31 2018-09-24 Social Inclusion Based Selection Implementation Huaynahuarco - Ccarapampa - Huisala PE-PROVIAS-4909-CS-QCBS / Estudio definitivo del camino vecinal Puente Angasmayo Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - National 200,341.00 0.00 2017-04-03 2017-04-17 2017-05-06 2017-06-03 2017-06-08 2017-06-29 2017-07-13 2018-09-06 Millpo Dv Huariperja - Huariperja, Social Inclusion Based Selection Implementation Long. 24.40 km Prov. Huamanga, AYACUCHO Page 1 PE-PROVIAS-4914-CS-QCBS / Estudio definitivo del camino vecinal Vinchos-Paccha- Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - National 186,612.00 0.00 2017-04-03 2017-04-17 2017-05-06 2017-06-03 2017-06-08 2017-06-29 2017-07-13 2018-09-06 Andabamba, Social Inclusion Based Selection Implementation Long. 22.70 km Prov. Huamanga, AYACUCHO PE-PROVIAS-11172-CS-QCBS / Supervision de la obra Infrastructure for Integration and Quality And Cost- Under IBRD / 85620 Post Open - National 545,625.00 0.00 2017-04-03 2017-04-24 2018-03-06 2017-06-07 2017-07-05 2017-08-04 2017-09-08 2017-10-13 2018-06-10 Pacobamba - Huironay - Social Inclusion Based Selection Implementation Ccerabamba - Abra Cusqueña PE-PROVIAS-11174-CS-QCBS / Supervision de la obra Talavera Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - National 135,482.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-05 2017-08-04 2017-09-08 2017-10-13 2018-04-11 - Mulacancha - Taramba - Nueva Social Inclusion Based Selection Implementation Esperanza - AP-510 PE-PROVIAS-4917-CS-QCBS / Elaboracion de Plan Vial Decentralized Road Quality And Cost- Pending IBRD / 85620 Post Open - National 322,959.48 0.00 2017-04-03 2017-04-17 2017-05-06 2017-06-03 2017-06-08 2017-06-29 2017-07-13 2017-12-10 Provincial Participativo de 10 Management Based Selection Implementation GLP PE-PROVIAS-4690-CS-QCBS / Quality And Cost- Pending IBRD / 85620 Project Management Post Open - National 694,245.00 0.00 2017-09-04 2017-09-18 2017-10-07 2017-10-28 2017-11-02 2017-11-23 2017-12-07 2021-11-16 Auditoria financiera Based Selection Implementation PE-PROVIAS-4915-CS-QCBS / Implementación del plan de Decentralized Road Quality And Cost- IBRD / 85620 Post Open - National 293,600.00 0.00 Canceled 2017-04-03 2017-04-17 2017-05-06 2017-06-03 2017-06-08 2017-06-29 2017-07-13 2018-07-13 acción de VDL en 4 provincias . Management Based Selection Region de Cusco y Puno PE-PROVIAS-4691-CS-FBS / Consultant Paquete N° 2 de 10 Estudios Infrastructure for Integration and IBRD / 85620 Post Qualification Open - National 1,644,157.00 0.00 Canceled 2017-06-05 2017-06-19 2017-07-08 2017-07-22 2017-08-05 2018-09-29 definitivos de camino vecinales Social Inclusion Selection en 200 km PE-PROVIAS-4916-CS-QCBS / Implementación del plan de Decentralized Road Quality And Cost- acción de VDL en 4 provincias . IBRD / 85620 Post Open - National 293,600.00 0.00 Canceled 2017-04-03 2017-04-17 2017-05-06 2017-06-03 2017-06-08 2017-06-29 2017-07-13 2018-07-13 Management Based Selection Region de Cajamarca y Amazonas PE-PROVIAS-4918-CS-QCBS / Paquete N° 2 de Estudio Infrastructure for Integration and Quality And Cost- IBRD / 85620 Post Open - National 2,466,236.00 0.00 Canceled 2017-04-03 2017-04-17 2017-05-06 2017-06-03 2017-06-08 2017-06-29 2017-07-13 2018-09-06 definitivo en 5 corredores Social Inclusion Based Selection logisticos PE-PROVIAS-4689-CS-QCBS / Sistema de Informacion , Decentralized Road Quality And Cost- Pending monitoreo y evaluación diseñado IBRD / 85620 Post Open - International 293,599.53 0.00 2017-05-24 2017-06-07 2017-06-26 2017-07-24 2017-07-29 2017-08-19 2017-09-02 2017-12-31 Management Based Selection Implementation e implementado, mantenido y de acceso libre PE-PROVIAS-63578-CS-QCBS / PAQ.ANCASH: Perfil y est def rehab y mejoramiento CV Tr1:Emp.PE-1N-Dv.Fundo Pto Viejo-Pto. Santa, Tr2:Emp.PE- Infrastructure for Integration and Quality And Cost- Under 1N-Emp.PE-1N Q,Emp.PE-1NQ- IBRD / 85620 Post Open - International 444,794.14 0.00 2018-06-14 2018-06-28 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-03-22 Social Inclusion Based Selection Implementation Emp.AN-924,Emp.AN-921 (Nepeña)-Dv.AN-925,Dv.San José(Nepeña)-San José-Emp.AN- 104(Morteros),Tr3: Emp. An101(Alto Pusha PE-PROVIAS-63580-CS-QCBS / PAQ.APURIMAC:Perfil y est def rehab y mejoramiento CV Tr1:AP-855-Emp.PE-109 (Ccoriray)-Vito,Tr2:Emp.PE3SF- Pta. Infrastructure for Integration and Quality And Cost- Under IBRD / 85620 Post Open - International 432,486.73 0.00 2018-06-14 2018-06-28 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-03-22 Carretera(Casanacocha),Tr3:Dv Social Inclusion Based Selection Implementation Puca Puca-Molinopata-Trujipata- Emp.AP 103,Tr4:Emp. PE03A(Puente Huayquipa)- Huayquipa,Tr5: Emp.AP- 768(Dv.Chalhuan PE-PROVIAS-63587-CS-QCBS / PAQ.LA LIBERTAD:Perfil y est def rehab y mejoramiento CV Tr1:Emp.LI-111- Lucma-La Represita-Penintay-Huachacual- Samamuy,Emp.LI-713- Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - International 433,134.49 0.00 2018-06-14 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-03-22 Recuaycito,Tr2: Quiruvilca- Social Inclusion Based Selection Implementation Emp.LI-931,Emp.LI-931- Huacampalda- Dv.Bado,Tr3:Emp.LI- 528(Pacanga)- Martín Sanches- Emp.LI-512 PE-PROVIAS-63588-CS-QCBS / PAQ.LAMBAYEQUE: Perfil y est. def. rehab. y mejoramiento CV Tr1:Emp.PE-1N- Manco Capac 1-Emp.PE-1N,Emp.PE- Infrastructure for Integration and Quality And Cost- Under 1N-Manco Capac 2-Emp.PE- IBRD / 85620 Post Open - International 344,391.58 0.00 2018-06-14 2018-06-28 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-03-22 Social Inclusion Based Selection Implementation 1N,Tr2:Emp.PE-06-El Higo- Emp.LA-109,Tr3:Emp.LA-112- Emp.LA-111,Emp.LA-112- Pta.Carretera,Tr4:Emp.PE- 1NJ(El Puente)-Inverna PE-PROVIAS-63581-CS-QCBS / PAQ. AYACUCHO:Perfil y estudio definitivo rehabilitación y mejoramiento de los CV Tr 1: Infrastructure for Integration and Quality And Cost- Under IBRD / 85620 Post Open - International 428,816.10 0.00 2018-06-14 2018-06-28 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-03-22 Emp. AY - 103 - Allpaspina - Social Inclusion Based Selection Implementation Putacca - Raymina - Pitec, Tr 2: Huambo - Alcamenca - Emp. PE - 32A Page 2 PE-PROVIAS-63591-CS-QCBS / PAQ.PUNO: Perfil y est. def.rehab. y mejoramiento CV Tr1:Emp. PE-3SG(Llalli)-Emp.PU- 125,Tr2:Emp.PU-123-Dv.PU-1005- Infrastructure for Integration and Quality And Cost- Pending Dv.PU-1006-Dv. Huayta Pata, IBRD / 85620 Post Open - International 621,157.18 0.00 2018-06-14 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-03-22 Social Inclusion Based Selection Implementation Emp.PU-1004-Huayta Pata-Coa Chico,Tr3:Emp.PE-3S-Marcuyo- Emp.PU-1198(Río Zapatilla),Emp:PU-1198(Río Zapatilla PE-PROVIAS-63592-CS-QCBS / PAQ.TUMBES: Perfil y estudio definitivo rehabilitación y mejoramiento de los CV Tr 1: Emp. TU-101 (La Coja) - Emp. Infrastructure for Integration and Quality And Cost- Under IBRD / 85620 Post Open - International 392,325.71 0.00 2018-06-14 2018-06-28 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-03-22 TU-516, Dv La Coja - Emp. TU- Social Inclusion Based Selection Implementation 524 (Dv el Tutumo), Tr 2: Dv. Salado Grando - Plateritos - Emp.TU-516, Dv. Plateritos - Emp.TU-105 PE-PROVIAS-63590-CS-QCBS / PAQ.LORETO: Perfil y estudio definitivo rehabilitación y mejoramiento C.V. Emp. LO-103 Infrastructure for Integration and Quality And Cost- Pending (Nuevo San Juan) - Dv. San Juan IBRD / 85620 Post Open - National 176,751.69 0.00 2018-06-14 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-03-22 Social Inclusion Based Selection Implementation de Puritana - Villa Puerto Cruz, Emp. Via No Clasificada - Nuevo Mundo - San Juan - San Juan de Puritana PE-PROVIAS-63589-CS-QCBS / PAQ.LIMA: Perfil y estudio definitivo rehabilitación y mejoramiento CV Tr I: Emp. PE- Infrastructure for Integration and Quality And Cost- Pending 1S-Emp. LM-835 (DV. La Huaca) IBRD / 85620 Post Open - National 235,481.79 0.00 2018-06-14 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-03-22 Social Inclusion Based Selection Implementation - San Antonio, Tr II: Emp. PE-1S - San Antonio, Tr 2: Emp. PE-1S - Huayhuanco - Emp. LM-878 (Roldan) PE-PROVIAS-63593-CS-QCBS / PAQ.UCAYALI: Perfil y estudio definitivo rehabilitación y Infrastructure for Integration and Quality And Cost- Pending mejoramiento del camino vecinal IBRD / 85620 Post Open - National 233,754.44 0.00 2018-06-14 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-03-22 Social Inclusion Based Selection Implementation Emp UC 105 (Bolognesi) - Pta Carretera (A chambiral)-CC NN Sta Clara PE-PROVIAS-66683-CS-QCBS / Elaboración de Planes Viales Provinciales Participativos de: Decentralized Road Quality And Cost- Huaraz, Antonio Raymondi, IBRD / 85620 Post Open - National 244,397.43 0.00 Under Review 2018-06-14 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-01-21 Management Based Selection Huari, Huarmey, Huaylas, Ocros, Pomabamba, Santa, Sihuas y Yungay PE-PROVIAS-66684-CS-QCBS / Elaboración de Planes Viales Provinciales Participativos de: Decentralized Road Quality And Cost- IBRD / 85620 Post Open - National 195,235.76 0.00 Under Review 2018-06-14 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-01-21 Huamanga, Cangallo, Huanta, La Management Based Selection Mar, Lucanas, Paucar del Sara Sara y Víctor Fajardo PE-PROVIAS-66685-CS-QCBS / Elaboración de Planes Viales Provinciales Participativos de: Decentralized Road Quality And Cost- Abancay, Andahuaylas, IBRD / 85620 Post Open - National 290,334.35 0.00 Under Review 2018-06-14 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-01-21 Management Based Selection Cotabambas, Grau, Caraveli, Castilla, Nazca, Pisco, Barranca, Huaral y Yauyos PE-PROVIAS-66703-CS-QCBS / Elaboración de Planes Viales Provinciales Participativos de: Cajamarca, Cajabamba, Chota, Decentralized Road Quality And Cost- IBRD / 85620 Post Open - International 313,447.03 0.00 Under Review 2018-06-14 2018-06-28 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-01-21 Contumazá, Cutervo, Hualgayoc, Management Based Selection San Ignacio, San Marcos, San Pablo, Bellavista, Huallaga y Picota PE-PROVIAS-66709-CS-QCBS / Elaboración de Planes Viales Decentralized Road Quality And Cost- Provinciales Participativos IBRD / 85620 Post Open - National 108,683.10 0.00 Under Review 2018-06-14 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-01-21 Management Based Selection de:Chanchamayo, Jauja, Oxapampa, Atalaya PE-PROVIAS-66712-CS-QCBS / Elaboración de Planes Viales Provinciales Participativos de: Chiclayo, Ferreñafe, Lambayeque, Ascope, Bolivar, Decentralized Road Quality And Cost- IBRD / 85620 Post Open - International 361,532.15 0.00 Under Review 2018-06-14 2018-06-28 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-01-21 Chepén, Julcán, Otuzco, Management Based Selection Pacasmayo, Pataz, Sánchez Carrión, Santiago de Chuco, Gran Chimu, Virú y Contralmirante Villar PE-PROVIAS-66714-CS-QCBS / Elaboración de Planes Viales Provinciales Participativos de: Decentralized Road Quality And Cost- Carabaya, Chucuito, El Collao, IBRD / 85620 Post Open - National 221,424.37 0.00 Under Review 2018-06-14 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-01-21 Management Based Selection Lampa, Moho, San Antonio de Putina, Tambopata, Manu y Tacna PE-PROVIAS-66717-CS-QCBS / Elaboración de Planes Viales Decentralized Road Quality And Cost- IBRD / 85620 Post Open - National 47,132.58 0.00 Under Review 2018-06-14 2018-06-28 2018-07-17 2018-08-14 2018-08-19 2018-09-09 2018-09-23 2019-01-21 Provinciales Participativos de: Management Based Selection Maynas y Ucayali. Page 3 PE-PROVIAS-73704-CS-QCBS / PQT APURIMAC:Perfil y estudio definitivo rehabilitación y mejoramiento CV Tr1 Emp PE- 3S(Pte San Martin)- Infrastructure for Integration and Quality And Cost- Pending Huancamarca-Chaccobamba- IBRD / 85620 Post Open - International 424,462.65 0.00 2018-08-13 2018-08-27 2018-09-15 2018-10-13 2018-10-18 2018-11-08 2018-11-22 2019-11-22 Social Inclusion Based Selection Implementation Casabamba-Cayara-Morochuco- Orccorbamba-Emp AP-549 (Lte Dist),Tr2 Emp AP-108- Pachaconas, Tr3 Emp AP-108- Huancaray, Tr4 Emp PE-PROVIAS-73705-CS-QCBS / PQT LA LIBERTAD I:Perfil y estudio definitivo rehabilitación y mejoramiento CV Tr1 Emp PE- 1N(Manuel Guarniz)-Faclo Chico Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - International 459,693.98 0.00 2018-08-13 2018-08-27 2018-09-15 2018-10-13 2018-10-18 2018-11-08 2018-11-22 2019-11-22 -Nueva Esperanza-Faclo Grande Social Inclusion Based Selection Implementation -El Ingenio-La Compuerta- Algodonal-Hda Flaco Grande Vieja-Cruz de Guayabo-La Barranca, Tr 2 Emp PE PE-PROVIAS-73706-CS-QCBS / PQT LA LIBERTAD II: Perfil y estudio definitivo rehabilitación y mejoramiento CV Tr1 Emp PE- 1N-Calunga, Emp PE-1N- Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - International 464,018.96 0.00 2018-08-13 2018-08-27 2018-09-15 2018-10-13 2018-10-18 2018-11-08 2018-11-22 2019-11-22 Chanquin Bajo-Emp LI-119, Emp Social Inclusion Based Selection Implementation S/C-Puente La Alameda, Tr2 Dv. Susanga(Huacapongo)- Condornada-Caray, Tr3 Emp PE- 10A-Ayangay-Chugurpampa- C PE-PROVIAS-73707-CS-QCBS / PQT LA LIBERTAD III: Perfil y estudio definitivo rehabilitación y mejoramiento CV Tr1 Santa Rosa-El Alto San Idelfonso-Nvo. Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - International 385,356.14 0.00 2018-08-13 2018-08-27 2018-09-15 2018-10-13 2018-10-18 2018-11-08 2018-11-22 2019-11-22 Horizonte-Lomas de Prieto, Tr2 Social Inclusion Based Selection Implementation Emp PE-1NH-Nvo Paraiso-Pta Carretera, Tr3 Quiruvilca-Emp LI- 931,Emp LI-931-Huacampalda- Dv. Bado PE-PROVIAS-73708-CS-QCBS / PQT MADRE DE DIOS: Perfil y estudio definitivo rehabilitación y mejoramiento CV Tr1 Emp PE- Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - International 432,662.82 0.00 2018-08-13 2018-08-27 2018-09-15 2018-10-13 2018-10-18 2018-11-08 2018-11-22 2019-11-22 30C (Dv. Piñal) - Piñal - Nuevo Social Inclusion Based Selection Implementation San Juan, Tr2 Emp MD-101 (Boca Colorado) - Emp MD-518 (Nuevo San Juan Grande) PE-PROVIAS-73709-CS-QCBS / PQT PASCO: Perfil y estudio definitivo rehabilitación y mejoramiento CV Tr I: Emp PE- Infrastructure for Integration and Quality And Cost- Pending 5N (Dv. Villa Rica) - Cedro IBRD / 85620 Post Open - National 254,655.10 0.00 2018-08-13 2018-09-03 2018-10-17 2018-11-14 2018-12-14 2019-01-18 2019-02-22 2020-02-22 Social Inclusion Based Selection Implementation Pampa - Purus - Pte. Paucartambo - Emp PE-5N, Emp PA-691 - El Oconal - Puente Oconal - Emp. PA-691 PE-PROVIAS-73710-CS-QCBS / PQT PUNO I: Perfil y estudio definitivo rehabilitación y mejoramiento CV Tr1 Emp PE- 3S-Culuyo-Chancachi-Aripa Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - International 457,315.24 0.00 2018-08-13 2018-09-03 2018-10-17 2018-11-14 2018-12-14 2019-01-18 2019-02-22 2020-02-22 Ccoca Ruma-Thunuhuaya-Emp Social Inclusion Based Selection Implementation PU-1130, Tr2 Emp PE-3S(Pueblo Libre)-Emp PU-130, Emp PE- 3S(Crucero)-Ticaraya-Emp PU- 130, Emp PE-3S(Crucero)-Tuquin PE-PROVIAS-73711-CS-QCBS / PQT SAN MARTIN II: Perfil y estudio definitivo rehabilitación y mejoramiento CV Tr1 Emp SM- 113 (Yantalo) - Pto Los Angeles Infrastructure for Integration and Quality And Cost- Pending IBRD / 85620 Post Open - International 395,736.10 0.00 2018-08-13 2018-09-03 2018-10-17 2018-11-14 2018-12-14 2019-01-18 2019-02-22 2020-02-22 (Rio Mayo), Tr2 Emp PE-5N - Social Inclusion Based Selection Implementation Purus - Rioja, Emp PE-5N - Sector Winba, Tr3 Emp SM-116 - Dv. CCNN El Naranjal - Dv. Lamas - Chirap INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PROVIAS-4694-CS-INDV / Paquete N° 3 de 25 expedientes Rural Road Infrastructure Individual Consultant IBRD / 85620 Post Open 694,245.00 0.00 Canceled 2017-06-05 2017-07-03 2017-07-17 2017-07-31 2017-11-28 de mantenimiento periodico de Maintenance Selection caminos vecinales por 500 km PE-PROVIAS-4693-CS-INDV / Elaboracion de Plan Vial Decentralized Road Individual Consultant IBRD / 85620 Post Open 17,616.00 0.00 Canceled 2017-01-16 2017-02-13 2017-02-27 2017-03-13 2017-10-09 Departamental Participativo Management Selection paquete 2 PE-PROVIAS-12057-CS-INDV / Consultoría para los Decentralized Road Individual Consultant Pending procedimiento de certificación IBRD / 85620 Post Open 8,807.99 0.00 2017-05-02 2017-05-07 2017-05-07 2017-05-19 2017-08-17 Management Selection Implementation ocupacional para el mantenimiento de caminos PE-PROVIAS-12307-CS-INDV / Consultoría para el seguimiento y Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 16,441.57 0.00 2017-05-02 2017-05-16 2017-05-16 2017-05-28 2017-12-24 evaluación del Plan de Acción de Management Selection Implementation la VDL PE-PROVIAS-28360-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 28,677.15 0.00 2017-09-29 2017-10-06 2017-10-06 2017-10-27 2018-02-24 Management Selection Implementation Provincial Participativo de ICA Page 4 PE-PROVIAS-28370-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 28,677.15 0.00 2017-09-29 2017-10-06 2017-10-06 2017-10-27 2018-02-24 Provincial Participativo de Management Selection Implementation General Sánchez Cerro PE-PROVIAS-28372-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 24,822.70 0.00 2017-09-29 2017-10-06 2017-10-06 2017-10-27 2018-02-24 Provincial Participativo de Daniel Management Selection Implementation Alcides Carrión PE-PROVIAS-28374-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 24,822.70 0.00 2017-09-29 2017-10-06 2017-10-06 2017-10-27 2018-02-24 Provincial Participativo de Management Selection Implementation Candarave PE-PROVIAS-39281-CS-INDV / Consultor individual senior en Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 25,901.94 0.00 2017-12-04 2017-12-11 2017-12-11 2017-12-26 2018-12-21 fortalecimiento de la gestión vial Management Selection Implementation de gobiernos regionales PE-PROVIAS-39284-CS-INDV / Consultor individual senior en Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 22,201.67 0.00 2017-12-04 2017-12-11 2017-12-11 2017-12-26 2018-12-21 fortalecimiento de la gestión vial Management Selection Implementation de gobiernos locales PE-PROVIAS-39747-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 25,593.59 0.00 2017-12-11 2017-12-15 2017-12-15 2017-12-22 2018-04-06 Management Selection Implementation Provincial Participativo - Chupaca PE-PROVIAS-39752-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 20,968.24 0.00 2017-12-11 2017-12-15 2017-12-15 2017-12-22 2018-03-22 Provincial Participativo - Management Selection Implementation Cajatambo PE-PROVIAS-39753-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 23,435.09 0.00 2017-12-11 2017-12-15 2017-12-15 2017-12-22 2018-03-22 Provincial Participativo - Management Selection Implementation Tahuamanu PE-PROVIAS-39754-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 20,968.24 0.00 2017-12-11 2017-12-15 2017-12-15 2017-12-22 2018-03-22 Management Selection Implementation Provincial Participativo -Ilo PE-PROVIAS-39756-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 23,126.73 0.00 2017-12-11 2017-12-15 2017-12-15 2017-12-22 2018-04-06 Provincial Participativo - Management Selection Implementation Huancané PE-PROVIAS-39757-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 28,060.44 0.00 2017-12-11 2017-12-15 2017-12-15 2017-12-22 2018-04-06 Management Selection Implementation Provincial Participativo - Melgar PE-PROVIAS-39759-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 23,126.73 0.00 2017-12-11 2017-12-15 2017-12-15 2017-12-22 2018-04-06 Management Selection Implementation Provincial Participativo - Sandia PE-PROVIAS-39771-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 25,593.59 0.00 2017-12-11 2017-12-15 2017-12-15 2017-12-22 2018-04-06 Management Selection Implementation Provincial Participativo - Rioja PE-PROVIAS-39772-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 24,360.16 0.00 2017-12-11 2017-12-15 2017-12-15 2017-12-22 2018-04-06 Provincial Participativo - San Management Selection Implementation Martín PE-PROVIAS-39773-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 23,435.09 0.00 2017-12-11 2017-12-15 2017-12-15 2017-12-22 2018-03-22 Management Selection Implementation Provincial Participativo - Tocache PE-PROVIAS-39774-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 23,126.73 0.00 2017-12-11 2017-12-15 2017-12-15 2017-12-22 2018-04-06 Management Selection Implementation Provincial Participativo - Tarata PE-PROVIAS-62410-CS-INDV / Expediente tecnico para el mantenimiento periodico de los Rural Road Infrastructure Individual Consultant Pending caminos vecinales de los tramos: IBRD / 85620 Post Open 58,967.72 0.00 2018-05-11 2018-05-18 2018-05-18 2018-06-01 2018-07-31 Maintenance Selection Implementation 1) San Luis - Cardon - Canchabamba y 2) Tarica - Parihuanca - Aco PE-PROVIAS-62413-CS-INDV / Expediente técnico para el mantenimiento periódico de los caminos vecinales de los tramos Rural Road Infrastructure Individual Consultant Pending IBRD / 85620 Post Open 64,410.80 0.00 2018-05-11 2018-05-18 2018-05-18 2018-06-01 2018-07-31 1) Palo Seco - Parobamba Viejo, Maintenance Selection Implementation 2) Puente Tambillo - Runtujirca y 3) Emp. R548 (Huayllan) - Huanchacbamba PE-PROVIAS-62414-CS-INDV / Expediente técnico para el mantenimiento periódico de los Rural Road Infrastructure Individual Consultant Pending caminos vecinales de los tramos IBRD / 85620 Post Open 32,562.05 0.00 2018-05-11 2018-05-18 2018-05-18 2018-06-01 2018-07-31 Maintenance Selection Implementation 1) Dv. Saywite - Cachora y 2) Cementerio - San isidro de Chicón PE-PROVIAS-62415-CS-INDV / Expediente tecnico para el Rural Road Infrastructure Individual Consultant Pending mantenimiento periodico del IBRD / 85620 Post Open 49,428.95 0.00 2018-05-11 2018-05-18 2018-05-18 2018-06-01 2018-07-31 Maintenance Selection Implementation camino vecinal Puente Mirador - Boca Satipo Page 5 PE-PROVIAS-62416-CS-INDV / Expediente Técnico para el mantenimiento periodico de los caminos vecinales de los tramos Rural Road Infrastructure Individual Consultant Pending IBRD / 85620 Post Open 70,928.31 0.00 2018-05-11 2018-05-18 2018-05-18 2018-06-01 2018-07-31 1) Emp R510 (Cerro Rico) - Mina Maintenance Selection Implementation San Juan de Chorunga y 2) Huanca - Pte. Pichiricma - Sector Suchocc PE-PROVIAS-62417-CS-INDV / Expediente tecnico para el mantenimiento periodico del Rural Road Infrastructure Individual Consultant Pending camino vecinal Circuito de IBRD / 85620 Post Open 70,841.00 0.00 2018-05-11 2018-05-18 2018-05-18 2018-06-01 2018-07-31 Maintenance Selection Implementation Produccion Km 15.5 Carretera Mazamari - Puerto Ocopa - A Dos de Mayo PE-PROVIAS-62418-CS-INDV / Expediente técnico para el mantenimiento periódico de los Rural Road Infrastructure Individual Consultant Pending caminos vecinales de los tramos IBRD / 85620 Post Open 48,166.65 0.00 2018-05-11 2018-05-18 2018-05-18 2018-06-01 2018-07-31 Maintenance Selection Implementation 1) DV. Chapapampa - Jonsani y 2) DV. Pampa Blanca - Huanuara- Cairani PE-PROVIAS-62419-CS-INDV / Expediente tecnico para el Rural Road Infrastructure Individual Consultant Pending mantenimiento periodico del IBRD / 85620 Post Open 18,276.43 0.00 2018-06-04 2018-06-11 2018-06-11 2018-06-25 2018-08-24 Maintenance Selection Implementation camino vecinal Paijan - El Milagro PE-PROVIAS-62420-CS-INDV / Expediente tecnico para el Rural Road Infrastructure Individual Consultant Pending mantenimiento periodico del IBRD / 85620 Post Open 28,713.88 0.00 2018-06-04 2018-06-11 2018-06-11 2018-06-25 2018-08-24 Maintenance Selection Implementation camino vecinal Locuto - Callejones PE-PROVIAS-62421-CS-INDV / Expediente tecnico para el Rural Road Infrastructure Individual Consultant Pending mantenimiento periodico del IBRD / 85620 Post Open 8,361.57 0.00 2018-06-04 2018-06-11 2018-06-11 2018-06-25 2018-08-24 Maintenance Selection Implementation camino vecinal Santa Rosa de Masisea - Laguna Santa María PE-PROVIAS-63005-CS-INDV / Elaboración de Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 20,738.00 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Provincial Participativo de Management Selection Implementation Asunción PE-PROVIAS-63490-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 23,177.80 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Management Selection Implementation Provincial Participativo - Casma PE-PROVIAS-63496-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 25,312.60 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Provincial Participativo - Management Selection Implementation Antabamba PE-PROVIAS-63497-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 31,107.04 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Provincial Participativo - Management Selection Implementation Aymaraes PE-PROVIAS-63502-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 22,872.83 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Management Selection Implementation Provincial Participativo - Camaná PE-PROVIAS-63503-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 25,312.60 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Provincial Participativo - Management Selection Implementation Condesuyos PE-PROVIAS-63507-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 31,107.04 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Management Selection Implementation Provincial Participativo - Arequipa PE-PROVIAS-63508-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 32,021.96 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Management Selection Implementation Provincial Participativo -Caylloma PE-PROVIAS-63510-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 22,872.83 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Provincial Participativo - Management Selection Implementation Parinacochas PE-PROVIAS-63512-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 26,532.48 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Management Selection Implementation Provincial Participativo - Sucre PE-PROVIAS-63513-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 24,092.71 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Provincial Participativo -Santa Management Selection Implementation Cruz PE-PROVIAS-63515-CS-INDV / Elaboración del Plan Vial Decentralized Road Individual Consultant Pending IBRD / 85620 Post Open 26,532.48 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Provincial Participativo -San Management Selection Implementation Miguel PE-PROVIAS-63517-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 28,972.25 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Management Selection Implementation Provincial Participativo - Celendin PE-PROVIAS-63519-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 29,887.16 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Management Selection Implementation Provincial Participativo - Jaén PE-PROVIAS-63521-CS-INDV / Decentralized Road Individual Consultant Pending Elaboración del Plan Vial IBRD / 85620 Post Open 20,738.03 0.00 2018-05-21 2018-05-28 2018-05-28 2018-06-15 2018-09-13 Management Selection Implementation Provincial Participativo - Palpa Page 6