Procurement Plan Mozambique: P125120 - Greater Maputo Water Supply Expansion Project I. General 1. Bank’s approval Date of the procurement Plan 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: The procurement period of project covered from year January 2017 to June 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Above US$ 1,500,000 All 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 10 million All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Available 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 0.50 4 No Post of the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 All 2. Single Source (Firms) Above US$ 500,000 All 3. Individual Above US$ 200,000 All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 0.60 2 Post of number of contracts that will be let under QCBS Summary 1.40 9 Post CQS/IC of number of contracts that will be let under other methods PROCUREMENT Mozambique : Greater Maputo Water Supply Expansion Project PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2017-04-25 2021-06-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P125120 GPN Date: Project Name: Greater Maputo Water Supply Expansion Project Loan / Credit No: IDA / 52900 Water Regulatory Council Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CRA/GMWSP/G-03/15 / Component D: Capacity Video Conference Equipment Request for Single Stage - One IDA / 52900 Building and Operational Post Open - National 70,000.00 53,899.21 Signed 2017-04-03 2017-05-29 2017-08-07 2017-11-25 for CRA's Head Office and Quotations Envelope Support to CRA Regional Offices CRA/GMWSP/G-02/16 / Supply of ICT Equipment for Component D: Capacity RECO Service Provider ( Single Stage - One IDA / 52900 Building and Operational Post Request for Bids Open - National 150,000.00 0.00 Canceled 2017-07-03 2017-07-08 2017-08-19 2017-09-18 2017-10-23 2018-04-21 "Respond the Consumer Envelope Support to CRA Expectations" (RECO) in Urban and Small/Medium Towns) CRA/GMWSP/G-01/16 / Component D: Capacity Single Stage - Two Supply of IT Equipment for IDA / 52900 Building and Operational Post Request for Bids Open - International 200,000.00 0.00 Canceled 2017-07-31 2017-08-05 2017-09-16 2017-11-29 2018-01-03 2018-07-02 Envelope IBNET Monitoring System Support to CRA CRA/GMWSP/G-01/17 / Component D: Capacity Supply of ICT Equipment for Single Stage - One IDA / 52900 Building and Operational Post Request for Bids Open - National 150,000.00 0.00 Canceled 2019-03-27 2019-04-01 2019-05-13 2019-06-12 2019-07-17 2020-01-13 the Reporting & Monitoring Envelope Support to CRA Platform (RECO & IBNET) CRA/GMWSP/GOODS 01/18 / Component D: Capacity Single Stage - One PROMOTION OF THE CRA IDA / 52900 Building and Operational Post Request for Bids Limited 70,000.00 0.00 Canceled 2018-11-13 2018-11-18 2018-12-30 2019-01-29 2019-03-05 2019-09-01 Envelope INSTITUTIONAL IMAGE Support to CRA CRA/GMWSP/G-01/18 / Monitoring Tolls for Surveys & Component D: Capacity Request for Single Stage - One Water Quality Control (Private IDA / 52900 Building and Operational Post Limited 35,000.00 26,009.44 Signed 2018-11-21 2019-01-28 2019-01-16 2019-04-30 2019-07-15 Quotations Envelope Water Supply Providers - Support to CRA Periurban areas) CRA/GMWSP/G/19 / Component D: Capacity Single Stage - One Purchase of vehicles for IDA / 52900 Building and Operational Post Request for Bids Open - National 125,000.00 129,584.36 Signed 2019-02-11 2019-01-30 2019-02-16 2019-03-30 2019-02-20 2019-04-29 2019-04-02 2019-06-03 2019-04-30 2019-11-30 Envelope service monitoring. Support to CRA MZ-CRA-143131-GO-RFQ / Acquisition of Field Tools for Component D: Capacity Request for Single Stage - One CORAL & ALC STAFF (AURA, IDA / 52900 Building and Operational Post Limited 55,000.00 0.00 Canceled 2020-02-02 2020-03-29 2020-09-25 Quotations Envelope IP, e as CORAL's, Regional Support to CRA Offices) MZ-CRA-143127-GO-RFQ / Component D: Capacity Acquisition of Furniture Single Stage - One IDA / 52900 Building and Operational Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-06-01 2020-06-06 2020-07-18 2020-08-17 2020-09-21 2021-03-20 (AURA, IP, e as CORAL's, Envelope Support to CRA Regional Offices) MZ-CRA-175401-GO-RFQ / Component D: Capacity Request for Single Stage - One IT and Communication IDA / 52900 Building and Operational Post Limited 15,000.00 0.00 Canceled 2020-07-03 2020-08-28 2021-02-24 Quotations Envelope Equipment Support to CRA MZ-CRA-143128-GO-RFQ / Component D: Capacity Aquisition of Computers (desk Single Stage - One IDA / 52900 Building and Operational Post Request for Bids Open - National 100,000.00 0.00 Canceled 2019-12-15 2019-12-20 2020-01-31 2020-03-01 2020-04-05 2020-10-02 and laptops for AURA, IP, e as Envelope Support to CRA CORAL's, Regional Offices) MZ-CRA-241078-GO-RFQ / Component D: Capacity Pending Request for Single Stage - One Aquisition of vehicle for field IDA / 52900 Building and Operational Post Limited 55,000.00 0.00 Implementati 2021-07-02 2021-08-27 2022-02-23 Quotations Envelope and office Support to CRA on MZ-CRA-241088-GO-RFQ / Component D: Capacity Pending Request for Single Stage - One Aquisition and assembly of IDA / 52900 Building and Operational Post Limited 70,000.00 0.00 Implementati 2021-07-02 2021-08-27 2022-02-23 Quotations Envelope furniture for regional offices Support to CRA on MZ-CRA-241080-GO-RFQ / Component D: Capacity Pending Aquisition and assembly of Request for Single Stage - One IDA / 52900 Building and Operational Post Limited 100,000.00 0.00 Implementati 2021-07-06 2021-08-31 2022-02-27 computer equipment for Quotations Envelope Support to CRA on AURA, IP and regional offices NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CRA/GNWSP/CON- Component D: Capacity 01/FCS/18 / Edition and Request for Single Stage - One IDA / 52900 Building and Operational Post Limited 40,000.00 0.00 Canceled 2019-11-16 2019-08-13 2020-01-11 2020-07-09 Printing of CRA´s Report on Quotations Envelope Support to CRA Regulated Entities - 2018 Component D: Capacity MZ-CRA-175406-NC-RFQ / Request for Single Stage - One IDA / 52900 Building and Operational Post Limited 15,000.00 0.00 Canceled 2020-07-03 2020-08-28 2021-02-24 Communication Campaign Quotations Envelope Support to CRA Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CRA/GMWSP/CONS18/FCS/17 / Development and Component D: Capacity Consultant Implementation of a Strategic IDA / 52900 Building and Operational Post Qualification Open - National 90,000.00 107,128.18 Signed 2017-03-30 2017-04-20 2017-04-20 2017-06-03 2018-02-05 2017-07-03 2018-05-22 2017-08-07 2018-05-31 2018-02-03 Evaluation System (scored Support to CRA Selection approach) for Human Resources Performance CRA/GMWSP/CONS- Component D: Capacity Consultant 16/FCS/16 / Technical IDA / 52900 Building and Operational Post Qualification Open - National 100,000.00 0.00 Canceled 2017-04-24 2017-05-11 2017-05-15 2017-06-28 2017-07-28 2017-09-01 2018-02-28 Assistance for Review of CRA Support to CRA Selection Internal Regulations CRA/GMWSP/CONS Component D: Capacity Consultant 21/FCS/17 / Improve IDA / 52900 Building and Operational Post Qualification Open - National 70,000.00 45,014.62 Signed 2017-04-24 2018-02-27 2017-05-15 2017-06-28 2018-07-05 2017-07-28 2018-11-29 2017-09-01 2018-12-19 2018-02-28 Computer and Software use Support to CRA Selection skills for CRA's Staff CRA/GMWSP/CONS- Component D: Capacity Consultant 24/ICS/17 / Accountant IDA / 52900 Building and Operational Post Qualification Open - National 30,000.00 0.00 Canceled 2017-06-19 2017-06-09 2017-07-10 2017-08-23 2017-09-22 2017-10-27 2018-10-26 Manager Support to CRA Selection CRA/GMWSP/CONS- 08/FCS/15 / Impact Component D: Capacity Consultant Evaluation - Completion of IDA / 52900 Building and Operational Post Qualification Open - International 200,000.00 0.00 Canceled 2017-09-18 2017-10-09 2017-11-22 2017-12-22 2018-01-26 2018-07-25 Baseline and End Project Support to CRA Selection Survey of Water Service in the Greater Maputo Area CRA/GMWSP/CONS- 02/FCS/17 / DESIGN AND Component D: Capacity Consultant IMPLEMENTATION OF SERVICE IDA / 52900 Building and Operational Post Qualification Open - National 140,000.00 0.00 Canceled 2017-04-17 2017-05-08 2017-06-21 2017-07-21 2017-08-25 2018-02-21 QUALITY REPORTING SYSTEM Support to CRA Selection (RECO - Project) CRA/GMWSP/CONS- 05/FCS/15 / Design and Component D: Capacity Consultant Scaling Up of RECO (Respond IDA / 52900 Building and Operational Post Qualification Open - National 110,000.00 0.00 Canceled 2017-11-27 2017-12-18 2018-01-31 2018-03-02 2018-04-06 2018-10-03 to Water and Sanitation Support to CRA Selection Consummers Expectations) CRA/GMWSP/CONS- 02/FCS/15 / Design and Component D: Capacity Establishment of CRA Quality And Cost- IDA / 52900 Building and Operational Prior Open - International 300,000.00 0.00 Canceled 2017-04-14 2017-05-05 2017-06-18 2017-07-16 2017-08-15 2017-09-19 2017-10-24 2018-10-24 Monitoring Information Based Selection Support to CRA System and IBNET Data Collection Platform CRA/GMWSP/CON- 28/FCS/17 / Avaliaçao nda Component D: Capacity Consultant Eficacia do Contracto de IDA / 52900 Building and Operational Post Qualification Open - National 150,000.00 0.00 Canceled 2018-03-20 2018-04-10 2018-05-24 2018-06-23 2018-07-28 2018-10-26 Adesao (Serviço do Support to CRA Selection Abastecimento de Agua) CRA/GMWSP/CONS 09/FCS/17 / Model Study for Component D: Capacity Consultant Performance Improvement of IDA / 52900 Building and Operational Post Qualification Open - National 90,000.00 101,207.74 Signed 2018-04-17 2018-07-27 2018-05-08 2018-06-21 2019-02-07 2018-07-21 2019-09-11 2018-08-25 2019-11-11 2019-02-21 Local Regulatory Agents (ALC Support to CRA Selection & CORAL) CRA/GMWSP/CONS- Component D: Capacity 01/FCS/16 / Beneficiary Quality And Cost- IDA / 52900 Building and Operational Post Open - International 300,000.00 0.00 Canceled 2019-06-20 2019-07-11 2019-08-24 2019-09-21 2019-10-21 2019-11-25 2019-12-30 2020-12-29 Assessment - 3 Regions Based Selection Support to CRA (South, Center and North) CRA/GMWSP/CON- Component D: Capacity Quality And Cost- 29/FCS/17 / Institutional IDA / 52900 Building and Operational Post Open - International 300,000.00 0.00 Canceled 2018-11-20 2018-12-11 2019-01-24 2019-02-21 2019-03-23 2019-04-27 2019-06-01 2020-05-31 Based Selection Regulatory Study Support to CRA CRA/GMWSP/CONS- 11/FCS/17 / Designing Tools Component D: Capacity Consultant for Improving Regulatory IDA / 52900 Building and Operational Post Qualification Open - International 250,000.00 0.00 Canceled 2018-07-26 2018-10-25 2018-08-16 2018-10-26 2018-09-29 2018-10-29 2018-12-03 2019-06-01 Governance in Water and Support to CRA Selection Sanitation Services CRA/GMWSP/CONS13/FCS/15 / Study for Defining Appropriate Regulatory Component D: Capacity Consultant Framework Sanitation IDA / 52900 Building and Operational Post Qualification Open - International 190,000.00 0.00 Canceled 2019-08-20 2019-09-10 2019-10-24 2019-11-23 2019-12-28 2020-06-25 Services, including Drainage Support to CRA Selection Systems and Fecal Sludge Management CRA/GMWSP/CON- 02/FCS/15 / Design and Component D: Capacity Quality And Cost- Establishment of CRA ICT IDA / 52900 Building and Operational Post Open - International 450,000.00 0.00 Canceled 2018-03-28 2018-04-23 2018-04-18 2018-06-06 2018-06-01 2018-08-30 2018-06-29 2018-07-29 2018-09-02 2018-10-07 2020-04-07 Based Selection Monitoring Platform (IBNET & Support to CRA RECO) CRA/GNWSP/CON- 19/FCS/17 / Development Component D: Capacity Consultant and Implementation of CRA IDA / 52900 Building and Operational Post Qualification Open - National 200,000.00 0.00 Canceled 2018-09-28 2018-10-19 2018-12-02 2019-01-01 2019-02-05 2027-04-24 Communication & Image Support to CRA Selection Strategy INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CRA/GMWASP/CON- Component D: Capacity Individual 24/ICS/17 / Accountant IDA / 52900 Building and Operational Post Consultant Direct 30,000.00 24,470.10 Signed 2017-07-07 2017-07-12 2017-07-17 2017-10-10 2017-08-07 2017-10-19 2017-09-11 2017-09-15 2019-09-11 Manager Support to CRA Selection Page 2 CRA/GMWSP/CONS- Component D: Capacity Individual 22/ICS/17 / CRA South IDA / 52900 Building and Operational Post Consultant Open 30,000.00 0.00 Canceled 2017-03-13 2017-05-03 2017-05-01 2017-05-22 2017-06-26 2018-06-26 Regional CTR (Inhambane) Support to CRA Selection CRA/GMWSP/CONS23/ICS/17 Component D: Capacity Individual / CRA South Regional IDA / 52900 Building and Operational Post Consultant Limited 30,000.00 12,355.34 Canceled 2017-03-20 2016-03-01 2017-03-25 2017-07-11 2017-04-15 2017-07-17 2017-05-20 2017-03-01 2018-05-21 Assistant - Inhambane Support to CRA Selection CRA/GMWSP/CON-22/ICS/17 Component D: Capacity Individual / TECHNICAL ASSISTANT OF IDA / 52900 Building and Operational Post Consultant Direct 30,000.00 0.00 Canceled 2017-07-07 2017-07-17 2017-08-07 2017-09-11 2019-09-11 CRA SOUTH REGION Support to CRA Selection (Inhambane) CRA/GMWSP/CONS Component D: Capacity Individual 06/ICS/17 / Procurement IDA / 52900 Building and Operational Post Consultant Open 50,000.00 0.00 Canceled 2017-05-08 2017-06-05 2017-06-26 2017-07-17 2017-08-21 2018-02-17 Specialist Support to CRA Selection Component D: Capacity Individual CRA/GMWSP/CON-26/ICS/17 IDA / 52900 Building and Operational Post Consultant Direct 95,000.00 45,000.00 Signed 2017-09-26 2017-10-16 2017-10-06 2017-10-27 2017-10-24 2017-12-01 2017-11-06 2018-12-01 / Project Manager Support to CRA Selection CRA/GMWSP/CONS- 15/ICS/16 / Establishment of Component D: Capacity Individual a Center of Excellence for the IDA / 52900 Building and Operational Post Consultant Limited 70,000.00 0.00 Canceled 2017-09-18 2017-09-23 2017-10-14 2017-11-18 2018-05-17 Development of Water and Support to CRA Selection Sanitation Services Regulation CRA/GMWSP/CON-22/17 / Component D: Capacity Individual TECHNICAL REGIONAL IDA / 52900 Building and Operational Post Consultant Direct 30,000.00 0.00 Canceled 2017-07-07 2017-08-24 2017-07-17 2017-08-07 2017-09-11 2019-09-11 COORDINATOR - CTR - CRA Support to CRA Selection SOUTH REGION (Inhambane) Component D: Capacity Individual CRA/GMWSP/CONS- IDA / 52900 Building and Operational Post Consultant Limited 50,000.00 0.00 Canceled 2017-07-17 2017-07-22 2017-08-12 2017-09-16 2018-03-15 20/ICS/17 / Financial Analyst Support to CRA Selection CRA/GMWSP/CONS19/ICS/17 / Development and Component D: Capacity Individual Implementation of CRA's IDA / 52900 Building and Operational Post Consultant Limited 30,000.00 0.00 Canceled 2017-04-24 2017-03-16 2017-04-29 2017-05-20 2017-06-24 2017-12-21 Communication Strategy to Support to CRA Selection reach the Water Consumers CRA/GMWSP/CON - Component D: Capacity Individual 22/ICS/17 / Regional IDA / 52900 Building and Operational Post Consultant Limited 30,000.00 10,410.15 Signed 2018-02-14 2017-09-29 2018-02-19 2017-09-26 2018-03-12 2017-12-08 2018-04-16 2018-02-01 2018-10-13 Technical Coordinator - CTR Support to CRA Selection (South Region - Inhambane) CRA/GMWSP/CONS- Component D: Capacity Individual 25/ICS/17 / Translation IDA / 52900 Building and Operational Post Consultant Open 55,000.00 17,909.44 Signed 2018-03-28 2018-01-23 2018-05-16 2018-06-06 2018-04-26 2018-07-11 2018-05-23 2019-07-11 Specialist for Procurement Support to CRA Selection Documents CRA/GMWSP/CONS Component D: Capacity Individual 01/ICS/18 / Technical IDA / 52900 Building and Operational Post Consultant Limited 70,000.00 25,040.71 Signed 2018-06-20 2018-05-14 2018-06-25 2019-01-21 2018-07-16 2019-02-15 2018-08-20 2019-02-26 2019-08-20 Assistance for Review of CRA Support to CRA Selection Internal Regulations CRA/GMWSP/CONS03/ICS/18 Component D: Capacity Individual / Economical Regulation IDA / 52900 Building and Operational Post Consultant Limited 150,000.00 0.00 Canceled 2018-11-22 2018-11-27 2018-12-18 2019-01-22 2019-09-19 Expert of Water & Sanitation Support to CRA Selection Services CRA/GMWSP/CONS 02/ICS/18 / Technical Component D: Capacity Individual Monitoring & Evaluation IDA / 52900 Building and Operational Post Consultant Limited 150,000.00 0.00 Canceled 2018-11-21 2018-11-26 2018-12-17 2019-01-21 2019-09-18 Expert of Water & Sanitation Support to CRA Selection Services Component D: Capacity Individual CRA/GMWSP/CONS IDA / 52900 Building and Operational Post Consultant Limited 30,000.00 0.00 Canceled 2018-07-26 2018-04-23 2018-07-31 2018-08-21 2018-09-25 2019-09-25 07/ICS/17 / IT Technician Support to CRA Selection MZ-CRA-143133-CS-INDV / Component D: Capacity Individual Water Quality Assessment IDA / 52900 Building and Operational Post Consultant Limited 80,000.00 0.00 Canceled 2019-11-28 2020-04-17 2019-12-08 2020-01-07 2020-02-27 2020-08-25 Specialist Support to CRA Selection Component D: Capacity Individual MZ-CRA-143135-CS-INDV / IDA / 52900 Building and Operational Post Consultant Limited 70,000.00 0.00 Canceled 2020-01-14 2019-12-09 2020-01-19 2020-02-09 2020-03-15 2020-09-11 Human Resource Specialist Support to CRA Selection Component D: Capacity Individual MZ-CRA-143137-CS-INDV / IDA / 52900 Building and Operational Post Consultant Limited 100,000.00 39,200.00 Signed 2019-11-28 2019-12-26 2019-12-08 2020-03-05 2020-01-07 2020-04-27 2020-02-20 2020-04-30 2020-08-18 Regulations Expert Advisor Support to CRA Selection MZ-CRA-175388-CS-CDS / Design and Development of Component D: Capacity the Monitoring Platform for IDA / 52900 Building and Operational Post Direct Selection Direct 120,000.00 0.00 Canceled 2020-06-01 2020-06-03 2020-06-11 2020-08-15 2021-02-11 Water and Sanitation (Within Support to CRA scope of COVID 19) Component D: Capacity Individual CRA/GMWSP/CON-06/ICS/17 IDA / 52900 Building and Operational Prior Consultant Direct 50,000.00 0.00 Canceled 2017-09-29 2017-10-09 2017-10-30 2017-12-04 2018-12-04 / PROCUREMENT SPECIALIST Support to CRA Selection Page 3